Executive Summary of Draft EIA Report Tagoor Laboratories ...
Draft EIA Report - Gujarat Pollution Control...
Transcript of Draft EIA Report - Gujarat Pollution Control...
Draft EIA Reportof
M/s. Asahi Songwon Colors Ltd. Survey No. 429 to 432,
Village: Dudhwada, Taluka: Padra, Dist.: Vadodara, Gujarat.
Prepared by
San Envirotech Pvt. Ltd.424, Medicine MarketOpp. Shefali CentrePaldi, Ahmedabad
Email: [email protected]
REIA report of Asahi Songwon Colors Ltd. 1
Contents
Particulars Page no. Contents 1-6 List of Tables 7-8 List of Figures 9 List of Annexure 10
INDEX
Executive Summary
E.1 Background E-1
E.2 Project Description E-1
E.3 Size of Project E-2
E.4 Description of Environment E-3
E.5 Air Environment E-3
E.6 Water Environment E-4
E.7 Noise Environment E-5
E.8 Environmental Impacts and Mitigation Measures E-6
E.9 Environment Monitoring E-7
E.10 Environment Management Plan E-8
E.11 Qualitative Risk analysis E-8
E.12 Conclusion E-8
Chapter 1 Introduction
1.1 Background of the company 1-1
1.2 Purpose & Need of EIA 1-1
1.3 Statutory Requirements 1-3
1.4 Regulatory Framework 1-4
1.5 Terms of Reference accepted/issued by MoEF on 26/11/10
1-4
1.6 Industrial activities within 10 km radius 1-12
1.7 Statement of Principles 1-13
1.8 Study area 1-13
1.9 Site selection criteria 1-15
1.10 Objective of EIA 1-15
1.11 Scope of EIA 1-16
REIA report of Asahi Songwon Colors Ltd. 2
1.12 Methodology of EIA 1-17
Chapter-2 Project Description
2.1 Introduction 2-1
2.2 Location 2-1
Justification of the Project 2-1 2.3
Land Requirement 2-2
2.4 Capital Investment 2-3
2.5 Product and Size of the Unit 2-3
2.6 Manufacturing Process 2-4
2.6.1 CPC Blue Crude 2-4
2.6.2 CPC Beta Blue 2-6
2.6.3 Pigment Alpha Blue- 15/15.1 2-9
2.6.4 CPC Green-7/36 2-11
2.6.5 Pigment Violet-23 2-14
2.7 Input Requirement 2-17
2.7.1 Raw material requirement 2-17
2.7.2 Water 2-17
2.7.3 Fuel 2-17
2.7.4 Power 2-17
2.7.5 Dematerialized water system 2-18
2.7.6 Reverse Osmosis System 2-18
2.8 Generation of Pollutants 2-19
2.8.1 Existing Manufacturing activities 2-19
2.8.2 Proposed Expanded Capacity 2-21
2.8.3 Pollution Control Strategy 2-22
2.8.4 Resource Recovery 2-26
2.9 Resource Conservation 2-27
2.9.1 Ground Water Recharging System 2-27
2.9.2 Green Belt Development 2-27
2.10 Fire Frightening System 2-27
2.11 Rain Water Harvesting 2-27
Chapter 3 Description of the Environment
3.1 Introduction 3-1
3.2 Air Environment 3-2
3.2.1 Design of Network for Ambient Air Quality Monitoring Stations
3-2
REIA report of Asahi Songwon Colors Ltd. 3
3.2.2 Reconnaissance 3-2
3.2.3 Micrometeorology of the area 3-3
3.2.4 Ambient Air Quality Survey 3-5
3.2.5 Baseline Status 3-5
3.3 Water Environment 3-6
3.3.1 Water Quality 3-6
3.4 Noise Environment 3-7
3.4.1 Introduction 3-7
3.4.2 Methodology 3-8
3.4.3 Ambient Air Quality Standards in Respect of Noise
3-8
3.4.4 Day time & night time noise levels 3-8
3.4.5 Ambient Noise Levels in the Study Area 3-8
3.4.6 Conclusions 3-8
3.5 Soils 3-9
3.5.1 Introduction 3-9
3.5.2 Soil Characteristics 3-9
3.5.3 Findings 3-9
3.6 Socio Economic & Land use 3-11
3.6.1 Land use pattern and infrastructure 3-11
3.6.2 Demographic and Socio-Economic Environment: Rural
3-11
3.6.3 Demographic and Socio-Economic 3-13
3.7 Ecology 3-13
3.7.1 Terrestrial Ecology (Flora) 3-13
3.7.2 Terrestrial Ecology (Fauna) 3-13
3.7.3 Common Crop Plants 3-14
Chapter 4 Anticipated Environmental Impacts & Mitigation Measures
4.1 General 4-1
4.2 Air Environment 4-2
4.2.1 Prediction of impact at Construction phase 4-2
4.2.2 Operational Phase 4-2
4.2.3 Sources of Air Pollution 4-3
4.2.4 Air Emission 4-4
4.2.5 Micrometeorology 4-4
REIA report of Asahi Songwon Colors Ltd. 4
4.2.6 Air Quality Modeling and Predictions using the Gaussian Model
4-5
4.2.7 Predicted GLCs of proposed Chemicals plant 4-6
4.3 Water Environment 4-7
4.4 Noise Level Impact 4-8
4.4.1 Construction Phase 4-8
4.4.2 Operational Phase 4-8
4.5 Land / Soil Environment 4-9
4.6 Socio-Economic Environment 4-10
4.7 Ecological Environment 4-11
Chapter 5 Environmental Management Plan
5.1 Introduction 5-1
5.2 Objective of EMP 5-1
5.3 Component of EMP 5-2
5.3.1 Environmental Management systems 5-2
5.3.2 Environmental, Health and Safety Management System
5-2
5.4 Environmental Management during Construction Phase
5-3
5.5 Environmental Management during the Operational Phase
5-3
5.5.1 Air Environment 5-3
5.5.2 Action plan to control ambient air quality 5-5
5.5.3 Green Belt 5-5
5.5.4 Measures to control fugitive emissions 5-6
5.5.5 Water Environment 5-6
5.5.6 Artificial water recharge 5-7
5.5.7 Hazardous/Solid Waste Management 5-7
5.5.8 Noise Control Technique 5-8
5.5.9 Green Belt Development 5-9
5.6 Resource Conservation/ Waste Minimization 5-10
5.7 Health & Safety 5-10
5.7.1 Possibility of occupational health hazard & its control
5-12
5.7.2 Preventive measures 5-13
5.7.3 Occupational Health Programme 5-13
5.7.4 Hazard Communication and Chemical Safety 5-14
REIA report of Asahi Songwon Colors Ltd. 5
5.8 Post-Project Environmental Monitoring 5-15
Chapter 6 Quantitative Risk Assessment
6.1 Introduction 6-1
6.1.1 Scope of Study 6-1
6.1.2 Study Objective 6-1
6.1.3 The Study Approach 6-1
6.1.4 System Description 6-2
6.1.5 Identification of Hazards 6-2
6.1.6 Risk Reduction Measures 6-2
6.2 Probable Hazards & Risk 6-2
6.3 Hazardous Identification 6-2
6.3.1 Hazardous Substances to be handled at Asahi Songwon Colors Ltd.
6-3
6.4 Quantity of Hazardous Materials 6-6
6.4.1 Probable Hazards and Risk 6-6
6.4.2 Hazards due to loss of Containment 6-7
6.4.3 Release of Chlorine 6-8
6.4.4 Release of Flammable Materials 6-8
6.4.5 Effect and Consequence Analysis 6-8
6.4.6 Maximum Credible Accident Scenario 6-8
6.4.7 Methodology for selection of Accident Scenario 6-9
6.5 Maximum Credible Accident Scenario 6-10
6.5.1 Consequence Analysis 6-10
6.5.2 Release of Chlorine 6-10
6.5.3 Effect and Consequence Analysis 6-10
6.5.4 Maximum Credible Accident Scenario 6-10
6.5.5 Consequence Analysis for Chlorine Release Scenarios
6-11
6.5.6 Catastrophic Rupture of IBA Tank 6-13
6.5.7 Catastrophic Rupture of Xylene Tank 6-13
6.6 General Safety Precaution & Occupational Health 6-14
6.6.1 Occupational Health & First aid Measures 6-15
6.6.2 Risk reduction Measures 6-15
6.6.3 Safe Guards for Storage and Handling of Hazardous Chemicals
6-17
6.6.4 Handling of Hazards 6-18
REIA report of Asahi Songwon Colors Ltd. 6
6.6.5 General Working Condition 6-18
6.6.6 Safe Operating Procedures 6-19
6.6.7 Work Permit System 6-19
6.6.8 Personnel Protective Equipment (PPEs) 6-19
6.6.9 Fire Protection 6-20
6.6.10 Emergency Preparedness 6-20
6.6.11 Static Electricity 6-20
6.6.12 Access 6-20
6.6.13 Material Handling 6-20
6.6.14 Communication System 6-21
6.6.15 First Aid Facilities 6-21
6.6.16 Management of Change 6-21
6.6.17 Accident Reporting, Investigation and Analysis 6-21
6.8.18 Safety Inspections 6-22
6.8.19 Safe Operating Procedures 6-22
Chapter 7 Onsite Disaster Management Plan
7.1 Introduction 7-1
7.2 Probable Hazards & Risk 7-1
7.3 Objectives of the Plan 7-2
7.4 Identification of Major Hazards 7-3
7.5 Scope of Plan 7-3
7.6 The availability, organization and utilization of resources and facilities for emergencies
7-3
7.7 Response Organization Structure 7-5
7.8 Emergency Response Centre 7-8
7.8.1 Emergency Telephone Number 7-9
7.9 Post Emergency - Recovery 7-10
Chapter 8 Disclosure of Consultant 8-1
REIA report of Asahi Songwon Colors Ltd. 7
List of Tables Table No.
Name Page No.
1.1 Major Industries within 10 km radius 1-12
2.1 (A) Details of Products 2-29
2.1 (B) Raw Materials 2-30
2.2 Hazardous Chemical Storage Facilities 2-31
2.3 Typical Fuel Analysis 2-32
2.4 Details of Water Consumption and Wastewater Generation
2-33
2.5 Details Of Effluent Treatment Plant 2-34
2.6 Performance of Existing ETP 2-35
2.7 Details of Fuel Consumption 2-36
2.8 Details of Stacks 2-36
2.9 (a) Performance of Stack Emission 2-38
2.9 (b) Estimated Emission from new Stacks/Vents 2-38
2.10 Result of Work place Monitoring 2-39
2.11 Details of Solid / Hazardous waste 2-40
2.12 Result of Solid/Hazardous Waste analysis 2-41
2.13 Noise Survey 2-42
3.1 Ambient Air Quality Monitoring Locations 3-15
3.2 Ambient Air Quality Status 3-16
3.3 Ambient Air Quality Status (PM10) 3-17
3.4 Ambient Air Quality Status (SO2) 3-18
3.5 Ambient Air Quality Status (NOx) 3-19
3.6 Hydrocarbon and VOCs 3-20
3.7 National Ambient Air Quality Standard 3-21
3.8 Results of Groundwater Quality in the Study Area 3-23
3.9 Indian Standard Specification for Drinking Water 3-24
3.10 Ambient Noise Levels in the Study Area 3-25
3.11 Ambient Air Quality Standards with respect to Noise 3-25
3.12 Soil Analysis of Study area 3-26
3.13 Land Use Pattern 3-27
3.14 Present land use based on satellite imagery 3-28
3.15 Summary of Socio-Economic Status (Demography) 3-29
REIA report of Asahi Songwon Colors Ltd. 8
3.16 Summary of Socio-economic status of Study area (Amenities)
3-30
3.17 List of Tree Species found in the study area 3-33
3.18 List of Amphibians, Reptilia and Birds in the study area 3-35
4.1 Estimated emission from new stacks/vents 4-12
4.2 GPCB Stack and Process Emission Standards Details for
Industry
4-12
4.3 The 24-hourly average GLC Concentration Values for SPM 4-13
4.4 The 24-hourly average GLC Concentration Values for SO2 4-14
4.5 The 24-hourly average GLC Concentration Values for NOx 4-15
4.6 The 24-hourly average GLC Concentration Values for Cl2 4-16
4.7 The 24-hourly average GLC Concentration Values for HCl 4-17
4.8 The 24-hourly average GLC Concentration Values for NH3 4-18
5.1 Design features for minimization of fugitive emissions 5-17
5.2 Environment Monitoring 5-18
6.1 Effects Due To Incident Radiation Intensity 6-23
6.2 Damages to Human Life to Thermal Radiation 6-23
REIA report of Asahi Songwon Colors Ltd. 9
List of Figures
Figure No.
Name Page No.
1.1 Location Map 1-19
1.2 Industrial location on map 1-20
1.3 Land use/ land cover map 1-21
2.1(a) Water Balance Diagram (Existing) 2-43
2.1(b) Water Balance Diagram (After expansion) 2-44
2.1(c ) Water Balance Diagram (Recycling) 2-45
2.2 Line Diagram of ETP 2-46
2.3 Site Plan and Factory Layout 2-47
3.1 Graphical representation of Ambient Air quality 3-16
3.2 Graphical Representations for PM10 3-17
3.3 Graphical Representations for SO2 3-18
3.4 Graphical Representations for NOx 3-19
3.5 Graphical Representations for HC & VOCs 3-20
3.6 Ambient Air Quality Monitoring Stations 3-38
3.7 Wind rose Diagram 3-39
3.8 Water sampling Location 3-40
3.9 Locations of Noise Survey 3-41
3.10 Soil Sampling Location 3-42
3.11 Land Use/ Land Cover map by Satellite image 3-43
4.1 Isopleths for Ground Level Concentrations for SPM 4-19
4.2 Isopleths for Ground Level Concentrations for SO2 4-20
4.3 Isopleths for Ground Level Concentrations for NOx 4-21
4.4 Isopleths for Ground Level Concentrations for Cl2 4-22
4.5 Isopleths for Ground Level Concentrations for HCl 4-23
4.6 Isopleths for Ground Level Concentrations for NH3 4-24
5.1 EHS Management 5-19
6.1 Procedure for hazard identification and risk assessment
6-24
7.1 On Site Disaster Management Plan 7-12
REIA report of Asahi Songwon Colors Ltd. 10
List of Annexure
SR.NO. PARTICULAR ANNEXURE
NO.
1.0 Compliance of CC&A 01
2.0 Membership certificate 02
3.0 CREP guidlines 03
4.0 TOR Letter 04
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Sonwon Colors Ltd. E-1
EXECUTIVE SUMMARY E-1 BACKGROUND
Since India is a developing country and chemicals industries have
always played major role in the economic development of the
country. Gujarat is a one of the well developed industrialized State,
has a significant contribution in industrial as well as economic
development of the country.
M/s. Asahi Songwon Colors Ltd. is an existing unit located at survey
no. 429 to 432, Village: Dudhwada, Taluka: Padra, Dist.: Vadodara,
State: Gujarat. Since the establishment the unit has been involved in
manufacturing of CPC Blue Crude & Pigment Beta Blue-A/B with 850
MT/month & 100 MT/month production capacities. Now, looking to
the market demand, the unit envisage to increase the production
capacity of CPC Blue from 850 MT/month to 1000 MT/month,
Pigment Beta Blue-A/B from 100 MT/month to 500 MT/month with
introduce of three new products – Pigment Alpha Blue: 15/15.1 with
60 MT/month, Pigment Violet-23 with 25 MT/month and Pigment
Green-7/36 with 200 MT/Month production capacities.
The total area of the premises is @ 85259 sq. mt, and the proposed
expansion will be in the same premises. There will not be any
additional land requirement for the proposed expansion.
E-2 PROJECT DESCRIPTION
Location of Project
The proposed expansion activities will be carried out in the existing
premises of M/s. Asahi Songwon Colors Ltd., located at Plot: 429 to
432, Village: Dudhwada, Vadodara, Gujarat.
The location of the project site is given hereunder in terms of
longitude and latitude.
Longitude: 20011’35.47” N
Latitude: 72053’55.47” E
Elevation from sea level is 25 meter.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Sonwon Colors Ltd. E-2
Site Selection
Since the unit has been already in existence since long and the unit
is good familiar with the surrounding environment, therefore, it
becomes easy for the unit to expand the project in the same
premises. However, besides this the selected project site has all basic
facilities like availability of water and natural gas, electricity, easy
availability of raw material, communication and transportation
facilities etc. as well as Treated effluent disposal facilities managed
by ECP Limited.
The nearest town Baroda is only 30 km away from the project site
which is very well connected with other parts of the country by road,
rail and air. No R & R will be required. No national park or wildlife
Habitats falls within 10 km radial distance from proposed project site.
As the easy availability of all necessary thing, the alternative for the
project site location is not thought of.
E-3 Size of the Project
The unit has been already involved in the manufacturing of CPC blue
crude and now, intends to expand it production capacity as under,
Sr. No.
Product Existing capacity in MT/ month
New Capacity Addition
in MT/month
Total Capacity in MT/ month
Product Expansion in existing Plants 01 Phthalocyanine Blue Crude 850 150 1000 02 Pigment Beta Blue-A/B 100 400 500
New Products Additions 01 Pigment Alpha Blue: 15 / 15.1 -- 60 60 02 Pigment Violet – 23 -- 25 25 03 Pigment Green – 7 -- 200 200
Grand Total of Capacities : 950 835 1785 Bye Products 1 Blue Crude Plant Ammonium Sulphate/Carbonate 0 1200 1200 2 Pigment Green Plant HCl - 20% 0 150 150 Sodium Hypochlorite solution - 12% 0 200 200 3 Alpha Blue Plant: Dilute Sulphuric Acid - 30% 0 1370 1370
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Sonwon Colors Ltd. E-3
CAPITAL INVESTMENT
Total additional cost of projects will be 41.00 crores, out of which,
around 07 crores will be utilized for Environment Management
Systems.
E-4 DESCRIPTION OF ENVIRONMENT
To predict the impact of the proposed activities on the surrounding
environment the current base line environmental status was studied
by collecting the data and carrying out monitoring for the period of
December-10 to February-11. The environmental quality has been
analyzed with respect to ambient air quality, water quality, noise
levels, soil characteristics, flora & fauna and parameters concerning
human interest. Based on the data, the relevant impacts on various
environmental components were also predicted by using appropriate
mathematical models as well as impact assessment techniques. An
appropriate environmental management plan was also delineated to
minimize the adverse impacts.
E-5 Air Environment
The ambient air quality monitoring was carried out at 6 AAQM
locations including project site, with a frequency of twice a week, to
assess the existing sub-regional air quality status for Winter Season
i.e. December-10 to February-11. The Respirable Dust Sampler along
with the analytical methods prescribed by CPCB was used for
carrying out air quality monitoring. At all these sampling locations;
PM10, SO2 and NOx were monitored on 24-hourly basis and grab
sample were collected and analyzed for the HC and VOC to enable
the comparison with ambient air quality standards prescribed by
CPCB.
The data on concentrations of various pollutants were processed for
different statistical parameters like arithmetic mean, standard
deviation, minimum and maximum concentration and various
percentile values.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Sonwon Colors Ltd. E-4
Respirable Suspended Particulate Matter (PM10)
The arithmetic mean and 98th percentile value of 24-hourly PM10
values at all the locations ranged between and 60-73 μg/m3 and 64-
79 μg/m3 respectively, meeting the CPCB standards of 100 μg/m3.
The 24-hourly concentration values show that the values are well
within the prescribed limit.
Sulphur Dioxide (SO2)
The arithmetic mean and 98th percentile value of 24-hourly SO2 at
all the locations ranged between 15-20 μg/m3 and 17-22 μg/m3
respectively, which are well within the stipulated standards of 80
μg/m3 for residential areas.
Oxides of Nitrogen (NOx)
The arithmetic mean and 98th percentile value of 24-hourly NOx at
all the locations ranged between 14-21 μg/m3 and 17-25 μg/m3
respectively, which are much lower than the standards of 80 μg/m3,
stipulated by CPCB for residential areas.
E-6 Water Environment
Ground water quality
Color: All the Six samples were found colorless and meeting
desirable norms.
pH: All the samples meet the desirable standards (pH ranges from
7.1 to 7.6).
Total Dissolved Solids (TDS): TDS in samples ranges from
857mg/l (Gametha) to 1164 mg/l (Kahanva). All the samples meet
the permissible limit of 2000 mg/l (If alternate sources of potable
water are not available).
Calcium: Calcium contents in the water ranges from 38 mg/l
(Gametha) to 54 mg/l (project site), all the samples meet the
desirable limit of 75 mg/l.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Sonwon Colors Ltd. E-5
Magnesium: Magnesium content in the water ranges from 24 mg/l
(Karkhadi) to 47 mg/l (Tithor). All samples meet the permissible limit
of 100 mg/l. (If alternate sources of potable water are not available).
Sulfate: Sulfate content in the water ranges from 41 mg/l
(Karkhadi) to 63 mg/l (Kahanva). All samples meet the desirable
limit of 200 mg/l.
Total Alkalinity: Total alkalinity in the water samples ranges from
219 mg/l (Karkhadi) to 314 mg/l (project site). All the samples are
within the permissible limit of drinking water 600 mg/l for drinking
water (if alternate source of potable water is not available).
Heavy metals like copper, cadmium, lead, chromium, nickel and
zinc are well below to prescribe limit in all samples.
Other Parameters: Potassium (ranges from 31 mg/l to 44 mg/l),
Sodium (ranges from 180 mg/l to 265 mg/l), Chloride (ranges from
267 mg/l to 408 mg/l), and Iron (ranges from 0.16 mg/l to 0.29
mg/l). Samples were also analyzed for Phenolic compound (less than
0.001 mg/l in all samples).
Conclusions: Ground water samples from villages meets the
permissible limit set by the authority (BIS). Indian standard
specification for drinking water.
E-7 Noise Environment
The Leq values of noise levels during day-time varied between 53.5
to 61.5 dB(A) Highest Leq daytime value was recorded Project Site,
however it is less than the prescribed limit for the residential (75
dB(A)). The Leq values of noise levels during night time varied
between 39.5 to 57.4 dB (A). Highest Leq night time value was
recorded Nr. Project Site which is less than prescribed limit (70 dB
(A)).
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Sonwon Colors Ltd. E-6
E-8 Environmental Impacts and Mitigation Measures
Air Environment
Since M/s. Asahi Songwon Colors Ltd. is the main source of air
pollution is from flue gas stacks and process gas stack. However, the
unit has already provided adequate air pollution control measure.
After proposed expansion there will one boiler and Six thermic fluid heaters
& Five Spin Flash Dryer will be added.
Unit has proposed to install Bag Filter to flue gas stack and two stage
water scrubber to the process gas stack, which will also be adequate
to meet stipulated norms. Adequate stack height will also be
provided for proper dispersion of gaseous emission.
The unit has provided all the precautionary measures to control the
fugitive emission.
Air Quality Modelling and Predictions
It is predicted that the maximum contribution in GLCs, with units
operating at full capacity, is 3.205 μg/m3, 1.472 μg/m3 and 0.485
μg/m3 for SPM, SO2 and NOx respectively 2km away from Project
Site in N direction Where as NH3, HCl , Cl2 were 2.397, 0.291, and
0.125 respectively 1 km away from centre of industry in N direction.
With this marginal contribution due to the expansion of the project,
the levels of SPM, SO2 and NOX will be below residential area limit
prescribed by CPCB.
Water Environment
The additional water requirement for the proposed expansion will be
2105 KL/day, which will be satisfied through own bore well. Source of
water is existing bore well. The main industrial water requirement
will be for the process & washing, utilities, Domestic and gardening.
At present the industrial wastewater generation is 1482 KL/day which
will be reduce up to 1174 KL/day after proposed expansion.
The Company has already installed a full-fledged ETP plant which
comprises of neutralization, equalization, settling, aeration, filtration
through Carbon and sand filters to remove suspended particles. With
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Sonwon Colors Ltd. E-7
minor modifications in existing ETP plant to reduce the water
consumption. After treatment and meeting GPCB norms entire
quantity of treated industrial effluent will be discharged into Mahi
Creek through ECP channel.
The unit proposed ground water recharging sump at low lying area
which will be connected to the storm water drainage system. To
recharging the ground water during the rain, unit will be balanced
ground water.
Hazardous/Solid Waste Management
The main source of hazardous waste generation will be ETP sludge,
which will be sent to TSDF site operated by M/s. Naroda Enviro
Projects Ltd. (NEPL), Naroda-Ahmedabad for final disposal. The other
sources will be generation of discarded drums/barrels/liners/bags
and waste/spent oil respectively from the material handling and
storage and plant & machinery. The discarded
drums/barrels/liners/bags will be decontaminated and reused/sold to
approved scrap vendors whereas spent/waste oil will be reused
within premises as lubricant or sold to MoEF approved scrap vendors.
The unit has also provided isolated area within premises for the
storage and handling of hazardous waste with impervious floor and
roof cover.
Green Belt Development
The unit has already developed green belt on the area of 5475 sq mt.
which will be increased up to 29850 sq. mt. Thus, total area allotted
for the green belt development after proposed expansion will be @
35% of the total industrial area.
E-9 ENVIRONMENT MONITORING
The unit proposes to carry out post monitoring for the verification of
compliance of the GPCB norms and arrange the schedule for the
same. The details of the post monitoring facilities are given
hereunder,
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Sonwon Colors Ltd. E-8
Nature of Analysis Frequency of Analysis Number of Sample
Stack Monitoring of each stack
Monthly At all stack
Ambient Air Quality Monitoring
Monthly for 24 hours or as per the statutory
conditions
3 Location
Industrial Effluent for applicable parameters as per the Consents Conditions
Ones in a Month One Sample
E-10 Environment Management Plan
The overall objective of EMP is given hereunder,
Prevention: Measures aimed at impeding the occurrence of negative
environmental impacts and/or preventing such an occurrence having
harmful environmental impacts.
Preservation: Preventing any future actions that might adversely
affect an environmental resource or attribute.
Minimization: Limiting or reducing the degree, extent, magnitude,
or duration of adverse impacts.
EMP for M/s. Asahi Songwon Colors Ltd. for proposed expansion
project covers following aspects:
- Description of mitigation measures
- Description of monitoring program
- Institutional arrangements
- Implementation schedule and reporting procedures
E-11 Qualitative Risk Analysis
Risk analysis and study have been carried out for identification of
hazards, selection of credible scenarios, Risk Mitigation measures etc.
All the hazardous chemicals will be stored and handled as per MSDS
guidelines.
E-12 Conclusion:
Base on the study
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Sonwon Colors Ltd. E-9
• The air pollution potential of the project will be mitigated by recovery
of process gas like NH3 and CO2 gas with provision of adequate
scrubbing system.
• The unit has also provided adequate air pollution control system for
the control of flue gas emission. Bag Filter will be a main pollution
control facilities for flue gas emission.
• Water pollution potential of the project will be mitigated by providing
proper treatment of effluent at proposed Effluent Treatment Plant
(ETP) and after meeting GPCB norms entire quantity of finally treated
effluent will be discharged into ECP channel.
• Cleaner production technology will be adopted for resources
conservation.
• Rainwater harvesting systems will be provided to replenish the
ground water resources.
• Adequate arrangement for Handling and disposal of Hazardous / solid
waste will be made.
• Fire protection and safely measures will be provided to take care of
fire and explosion hazard.
• Follow the suggestion of qualitative risk analysis study to minimize
the accident and safe operations.
• Follow the recommendation suggested in Environmental Management
Plan to minimize the impact of proposed expansion.
Considering the above points, it can be concluded from overall
assessment in terms of positive, negative effect on various environment
components that will be improved by M/s. Asahi Songwon Colors Ltd.
Overall direct and indirect employment opportunities, improvement in
basic infrastructures by development of industries etc. with negligible
impact on environments.
It can be concluded that on positive implementation of mitigation
measures and environmental management plan during the construction
and operational phase would have negligible impact on the environment.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-1
CHAPTER-1
Introduction
1.1 BACKGROUND OF THE COMPANY
M/s. Asahi Songwon Colors Ltd. is the existing unit located at Survey
No. 429 to 432, Village: Dudhwada, Taluka: Padra, Dist.: Vadodara,
State: Gujarat. The unit has been established in the year April, 2005.
Unit has been involved in manufacturing of CPC Blue Crude & Pigment
Beta Blue-A/B with 850 MT/month & 100 MT/month production
capacities.
Now, Unit envisage to increase the production capacity of CPC Blue
from 850 MT/month to 1000 MT/month, Pigment Beta Blue-A/B from
100 MT/month to 500 MT/month with introduce of three new products
– Pigment Alpha Blue: 15/15.1 with 60 MT/month, Pigment Violet-23
with 25 MT/month and Pigment Green-7/36 with 200 MT/month
production capacities.
The promoter Mr. Munjal M. Jaykrishna, Managing Director of the
company, A young and dynamic MBA has very good business
experience in the same field since last 15 years. The company is also
supported by other senior personal including Mr. S. R. Dhoble, a
Chemical Engineer and Vice President have more than 25 year
experience in the chemical industries and overall controlled by the
Executive Directors. The quality of the product has been dramatically
improved and the product has been accepted in the domestic and
international market. Since the unit also believes in the sustainable
development with production and product quality, the unit is equally
concern with the environment preservation and pollution control.
1.2 PURPOSE & NEED OF E.I.A
Environmental Impact Assessment (E.I.A) is a formal document
prepared by independent Environmental consultant, based on the
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-2
details/documents provided by the project. The EIA report summarizes
the process and results of the environmental analysis of a project
having the potential for significant and diverse impacts.
Environmental analysis is the process of evaluating the environmental
impact of a project and identifying ways to improve the project
environmentally by preventing, minimizing, mitigating and/ or
compensating for adverse impacts.
M/s. Asahi Songwon Colors Ltd. falls under the category of 5(f) of
schedule of EIA Notification, 2006 “Synthetic Organic Chemical
Industries (Dyes & Dye intermediates; bulk drugs and intermediates
excluding drug formulations; synthetic rubbers; basic organic
chemicals, other synthetic organic chemicals and chemical
intermediates)” and categorized under “A” because unit is located
outside the notified industrial area and appraised at centre level.
Therefore, units require EC for proposed activities.
In view of the above, monitoring work has been carried out for all the
environmental attributers by M/s. San Envirotech Pvt. Ltd. -
Ahmedabad.
The Environmental (Protection) Act-1986 (Environmental Impact
Assessment Notification, 2006) established the requirements for
preparing Environmental Impact Assessment (EIA) in India. The EIAs
subsequently have been prepared, on an individual basis for
new/expansion of project. While the project specific EIAs have been
successful to varying extent in the incorporation of environmental
objectives in the project design, several experiments have been done
to address the issue of cumulative environmental impacts by carrying
out Regional Environmental Impact studies. This has given a basis for
evaluating total environmental impacts of the region and hence helped
in planning at the regional level. Other uses of EIA tool have been in
the Strategic Environmental Assessment (SEA), now mandatory in
many industrialized countries, to evaluate environmental impacts of
policies and programs. Hence, EIA tool has been improvised and used
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-3
innovatively for assisting decision-makers in assessment of
environmental impacts and considering alternative mitigation
measures in a variety of situations.
Environmental Impact Assessment (EIA) is required to be carried out
only for certain categories of projects and the criteria for screening
have been provided in the Act. Thus, EIA is essentially made applicable
to industrial and developmental projects, which are more likely to have
significant environmental impacts. Different criteria have been used for
screening. Indian regulation utilizes project category based on the
Scale of Impact, Sensitivity of Impact and Nature of locations as the
primary criteria for deciding on the requirement of EIA for approval.
1.3 STATUTORY REQUIREMENTS
As per the Environment Impact Assessment (EIA) notification issued
by Ministry of Environment and Forests (MoEF), New Delhi dated 14th
September 2006, setting up a new projects or activities, or on the
expansion or modernization of existing projects or activities based on
their potential environmental impacts as indicated in the Schedule to
the notification, being undertaken in any part of India, unless prior
environmental clearance has been accorded.
The proposed expansion of M/s. Asahi Songwon Colors Ltd. is for CPC
crude and CPC Beta Blue with addition of three new products i.e.
Pigment Alpha Blue: 15/15.1, Pigment Violet-23, Pigment Green-7,
which are covered under the said EIA notification and require to carry
out Environmental Impact assessment for its proposed project and
also, require to prepare the report on the same for the perusal of MoEF
for judging the environmental compatibility of the project as discussed
during the presentation of Terms of Reference to Expert committee of
MoEF on dated 22nd October, 2010.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-4
In view of the same, the monitoring/analysis as well EIA-Report
preparation work for the proposed expansion project of M/s. Asahi
Songwon Colors Ltd. has been carried out by M/s. San Envirotech Pvt.
Ltd., Ahmedabad- a reputed Environmental Consultant.
1.4 Regulatory Framework
The MoEF, CPCB and SPCBs together form the regulatory and
administrative core of the sector. Legislation for environmental
protection in India for chemical industry is mainly EIA Notification-
2006, water (Prevention & control of pollution) act-1974, Air
(Prevention & control of pollution) act-1981, Water (Prevention and
Control of Pollution) Cess Act, 1977; Hazardous Wastes (Management
and Handling) Rules, amended time to time etc are major
Act/rules/notification applicable to industry.
1.5 Terms of reference accepted/issued by MoEF on 26/11/10.
As per the discussion during 15th meeting of the Expert Appraisal
Committee (Industry) held on 22nd and 23rd October, 2010 for the
preparation of EIA/EMP, the TOR has been finalized for the proposed
expansion of M/s. Asahi Songwon Colors Ltd. as given hereunder,
Sr. No.
TORs Compliance
1 The proposal will be considered for
environmental clearance only when
permission from GPCB for disposal of
treated effluent into Creak of Mahi
through ECP Channel is included or
other a commitment for adopting
Zero Discharge is being included.
We are planning to reduce effluent discharge to ECP less than current level of discharged which was consented by MoEF in EC letter and GPCB in our CC & A letter. Granted quantity discharge to ECP is 1482 m3/day and; Proposed quantity to be discharged to ECP 1174 m3/day. Pl. refer figure 2.1 (a, b & c) on page no-2-43, 2-44 & 2.45 of chapter-2.
2 Executive summary of the project Incorporated in the report as
separate chapter.
3 Justification of the project Justification of the project is given
in Section: 2.3 of Chapter-2 on
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-5
Sr. No.
TORs Compliance
Page no: 2-1.
4 Promoters and their back ground. Pls. refer Point: 1.1 of Chapter-1.
5 Regulatory framework Pls. refer Section: 1.4, page no-
1-4 of Chapter-1.
6 A map indicating location of the
project and distance from severely
polluted area
Pls. refer Figure: 1.2, page no-
1-20 of Chapter-1.
7 Project location and plant layout. Project location described in Point:
2.2 on page: 2-1 of Chapter-2 &
Fig.: 1.2, page no-1-20 of
Chapter: 1. Layout is given in: Fig.
2.3 on page no. 2-47.
8 Infrastructure facilities including
power sources.
Pls. refer Point: 2.7 of Chapter-2
on page: 2-17.
9 Total cost of the project along with
total capital cost and recurring
cost/annum for environmental
pollution control measures.
Cost of Proposed project will be 41
crores including 7.0 crores for
environment protection measures.
10 Project site location along with site
map of 10 km area and site details
providing various industries, surface
water bodies, forests etc.
Surface water bodies, forests etc.
cover map by satellite images is
given in Fig.: 1.3, page no-1-21 of
Chapter: 1. Details of major
Industries within 10 km radius is
given in table no-1.1 of chapter-1
on page no- 1-12.
11 Present land use based on satellite
imagery for the study area of 10 km
radius. Location of National Park/Wild
life sanctuary/Reserve Forest within
10 km radius of the project.
Land use/Land Cover Map by
satellite images is given in Figure:
3.11 on Page: 3-43 and table no-
3-14 on page no-3-28 of Cha: 3.
12 Forest Clearance in case the forest
land is involved.
No protected Forest area covered
within 10 km radius hence not
applicable.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-6
Sr. No.
TORs Compliance
13 Details of the total land and break-up
of the land use for green belt and
other uses.
Table with total land area and
break-up of the land use is given
in Point: 2.3 of Chapter-2 on page
2-2.
14 Data on existing ambient air, stack
emission, fugitive emissions data;
water requirement and water balance
cycle; generation, re-utilization and
disposal of solid/hazardous waste for
the existing plant and predicted
increase in pollution load (GLCs) due
to proposed expansion should be
incorporated.
Data on existing ambient air are
prescribed in Table: 3.2 to 3.6 of
Chapter-3, page: 3-16 to 3-20 and
Stack emission data in Table: 4.1
of Chapter-4, page no: 4-12
whereas fugitive emissions data
are given in Table: 2.10 of
Chapter: 2 on page: 2-39.
Water requirement and water
balance diagram are given Table
2.4 of page no: 2-33 & Figure: 2.1
(a), 2.2 (b), on 2-44 & 2-45
respectively. Details of disposal of
solid/hazardous waste for the
existing plant are given in Table:
2.11 on page: 2-40 of Chapter-2.
Predicted increases in pollution
load (GLCs) due to proposed
expansion are mentioned in
tabulated form in Table 4.3 to 4.8 of
Chapter-4 on page no: 4-13 to 4-18.
15 All the environment clearances
accorded by the Ministry, Consent to
Establish and Operate and point-wise
compliance to the specific and
general conditions stipulated in the
environmental clearance and consent
to establish and operate for all the
existing plants.
Compliance of CC&A, EC & NOC
and amended CC&A enclose as
Annexure-I.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-7
Sr. No.
TORs Compliance
16 List of products along with the
production capacities and list of
solvents and its recovery plan.
Provision of connecting reactor to
chilled brine condenser system.
List of Products are described in
Section: 2.5 & Table No.: 2.1 (A &
B) of Chapter-2 on page No: 2-3 &
2-29. Inbuilt solvent recovery
system on RVD with connection of
cooling plant and brine chillers is
not require because high boiling
point of solvent i.e. 1880C.
17 Detailed list of raw material required
and source, mode of storage and
transportation.
Detailed of raw material required
and source, mode of storage and
transportation are listed in Table
2.1(b) of Chapter-2 on Page No:
2-30. All raw materials are locally
available and transported by road
trucks.
18 Manufacturing process details along
with the chemical reactions.
Details of all Manufacturing
Process with Chemical Reaction are
described in Section: 2.6 of
Chapter-2 on 2-4 to 2-16.
19 Site-specific micro-meteorological
data using temperature, relative
humidity, hourly wind speed and
direction and rainfall is necessary.
Micro-meteorological data
summarised in Section: 3.2.3 of
Chapter-3 on Page No: 3-3 and
same is used for wind rose
diagram.
20 Ambient air quality monitoring at 6
locations within the study area of 5
km., aerial coverage from project
site. Location of one AAQMS in
downwind direction.
Ambient air quality monitoring is
Discussed in Section: 3.2.4 on 3-5
& tabulated in Table 3.1 on page:
3-15.
Figure: 3.6 shown all six locations
of AAQMS along with down wind
direction on page no: 3-38 of
Chapter-3.
21 One season site-specific micro- Meteorological data are
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-8
Sr. No.
TORs Compliance
meteorological data using
temperature, relative humidity,
hourly wind speed and direction and
rainfall and AAQ data (except
monsoon) for PM10, SO2, NOx
including HC and VOCs should be
collected. The monitoring stations
should take into account the pre-
dominant wind direction, population
zone and sensitive receptors including
reserved forests. Data for water and
noise monitoring should also be
included.
summarized in Section: 3.2.3 on
page: 3-3 and tabulated in Table
3-1 to 3-6 of Chapter-3 on page
no: 3-15 to 3-20.
Wind Rose diagram is given in Fig:
3.7 on page: 3-39
Water monitoring in Table: 3.8 &
Fig: 3.8 on 3-23 & 3-40
respectively.
Noise monitoring in Table: 3.10 &
Fig: 3.9 on page no: 3-25 & 3-41
of Chapter-3.
22 Air pollution control measures
proposed for the effective control of
gaseous emissions within permissible
limits.
Air pollution control measures
discussed in Section: 5.5.1 on 5-3
& Section 2.8.3 B on 2-24 of
Chapter-5 & Chapter-2
respectively.
APC measure with Stack details
tabulated in Table 2.8 of Chapter-2
on 2-36.
23 Design details of ETP, incinerator, if
any, along with control of Dioxin &
Furan, boiler, scrubbers/bag filters
etc.
ETP details summarised in Table
2.5 on page: 2-34 and ETP
Diagram given in Figure 2.3 on
Page: 2-46 of Chapter-2,
incinerator is not required in our
case and Dioxin & Furan not
generated from process.
24 Details of water and air pollution and
its mitigation plan.
Discussed in point no-2.8.3 of
chapter-2 on page no-2-22.
25 Action plan to control ambient air
quality as per NAAQES Standards
notified by the Ministry on 16th
Pls. refer Section: 5.5.2 & 5.5.3 of
Chapter-5 on page no: 5-5.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-9
Sr. No.
TORs Compliance
September, 2009.
26 An action plan to control and monitor
secondary fugitive emissions from all
the sources as per the latest
permissible limits issued by the
Ministry vide G.S.R. 414(E) dated
30th May, 2008.
Pls. refer Section: 5.5.2 & 5.5.3 of
Chapter-5 on page no: 5-5.
Pls. refer Table: 5.2 on Page no:
5.18 of Chapter-5.
27 Determination of atmospheric
inversion level at the project site and
assessment of ground level
concentration of pollutants from the
stack emission based on site-specific
meteorological features. Air quality
modelling for proposed plant.
Please go through Section: 4.2.6 &
4.2.7 of Chapter-4 on page: 4-5 &
4-6.
28 Permission for the drawl of 3,515
m3/day ground water and Narmada
water from the CGWA/ SGWB/
concerned authority. Water balance
chart including quantity of effluent
generated recycled and reused and
discharged. Action plan for Zero
Discharge of effluent as proposed
should be included.
Due to recycling mechanism, raw
water requirement will be reduce
from 2188 to 2105 m3/day and no
additional water require for
proposed expansion hence not
applicable.
Pl. Refer fig-2.1 (a, b & c) on page
no: 2-43 for water recycling/reuse
and not increase wastewater after
expansion at current rate.
29 Ground water monitoring minimum at
6 locations should be carried out.
Geological features and Geo-
hydrological status of the study area
and ecological status (Terrestrial and
Aquatic).
Ground Water Sampling Locations
is mapped in Fig:3.8 on page:
3-40 and
Ground Water analysis report
given in Table 3.8 on page: 3-23
of Chapter-3 where as Ecological
status discussed in Section: 3.7 on
3-13 and tabulated in Table: 3.17
& 3.18 on 3-33 & 3-35.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-10
Sr. No.
TORs Compliance
30 The details of solid and hazardous
wastes generation, storage,
utilization and disposal particularly
related to the hazardous waste
calorific value of hazardous waste and
detailed characteristic of the
hazardous waste. Action plan for the
disposal of fly ash generated from
boiler should be included.
Pls. refer Chapter-6 for hazardous
waste characteristic and other
details.
Ash disposal point in Section:
2.8.3 D and Table 2.11 on page:
2-25 & 2-40 of Chapter-2.
31 Precautions to be taken during
storage and transportation of
hazardous chemicals should be
clearly mentioned and incorporated.
We follow the guideline MSDS of
respective chemicals for storage
and transportation of hazardous
chemicals.
32 Details of land fill along with design
details as per CPCB guidelines.
Location of secured land fill/TSDF.
We will not going to create our
landfill site hence not applicable.
Unit has obtained membership of
M/s. Naroda Enviro Project Ltd.
(NEPL), Naroda.
33 Authorization/Membership for the
disposal of liquid effluent in CETP and
solid/ hazardous waste in TSDF.
Unit has taken membership of M/s.
Naroda Enviro Project Ltd. (NEPL),
Naroda for disposal of solid/
hazardous waste. & Treated
effluent will be disposed through
ECP channel to Mahi Creek.
Membership letter from NEPL &
ECP authorities is enclosed as
Annexure-II.
34 Ground water monitoring around the
project site as well as around land fill
site
We will not going to create our
landfill site hence not applicable.
35 Risk assessment for storage for
chemicals/solvents and phosgenes.
Action plan for handling & safety
Pls. refer chapter-6.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-11
Sr. No.
TORs Compliance
system, whenever any cyanide is
involved in process.
36 An action plan to develop green belt
in 33% area.
Proponent has already planned to
develop 35% green belt area
(GBA).
Pl. refer point no 2.9.2 of chapter-
2 on page no-2-27.
37 Action plan for rainwater harvesting
measures at plant site should be
included to harvest rainwater from
the roof tops and storm water drains
to recharge the ground water.
Pls. refer Point: 2.11 of Chapter-2
on Page no: 2-27.
38 Occupational health of the workers
and periodical monitoring should be
included.
Please go through Section: 5.7 of
Chapter-5 on Page: 5-10.
39 Socio-economic development
activities should be in place.
Socio-economic development
activities are described in Section:
4.6 of Chapter-4 on Page No:
4-10.
40 Note on compliance to the
recommendations mentioned in the
CREP guidelines.
As per Annexure-III.
41 Detailed Environment management
Plan (EMP) with specific reference to
details of air pollution control system,
water & wastewater management,
monitoring frequency, responsibility
and time bound implementation plan
for mitigation measure should be
provided.
Pls. refer chapter-5.
42 EMP should include the concept of
waste-minimization, recycle/ reuse/
recover techniques, Energy
Please refer Section: 5.5.5 of
Chapter-5 on page no: 5-6 and
figure 2.1 (a, b & c) for recycle/
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-12
Sr. No.
TORs Compliance
conservation, and natural resource
conservation.
reuse/ recover techniques of water
on page: 2-43 and Sec: 2.9 for
resource conservation on page no-
2-27 of chapter-2.
43 Total capital cost and recurring
cost/annum for environmental
pollution control measures.
Please go through Section: 2.4 of
Chapter-2 on page: 2-3.
44 Any litigation pending against the
project and/or any direction/order
passed by any Court of Law against
the project, if so, details thereof.
No
45 Public hearing issues raised and
commitments made by the project
proponent on the same should be
included separately in EIA/EMP
Report in the form of tabular chart
with financial budget for complying
with the commitments made.
Incorporate after public hearing
46 A tabular chart with index for point
wise compliance of above TORs.
Done
1.6 INDUSTRIAL ACTIVITIES WITHIN 10 KM RADIUS
Major industries working in study area are summarized in Table 1.1:
Sr. No.
Name of Industries Type of activities Distance from the project site
1. Mayur Dyechem H-Acid & V.S. 0.5 2. Sunpharma Pvt Ltd. Pharma Product 0.6 3. Alembic Ltd. API / Bulk Drugs 0.7 4. Sterling Gelatin Gelatin Powder 1 5. Solaris Pvt Ltd. (Solaris
Biotech) Bromine Related
Products 1.1
6. Bestvalue Chemical Pvt Ltd. Detergent Product 1.5 7. S.D. Intermidates Pvt Ltd. Dyes 1.6 8. Ami Lifescience Pvt Ltd. API / Bulk Drugs 1.7 9. Quebec Pvt Ltd. Petroleum Product 1.8 10. Saraswati Pigment Pigment 1.8 11. Shivam Engineering Engineering Works 1.9 12. Transmetal Chemicals Chlorinated products 2
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-13
13. Cadillac Chemicals Fine chemicals 2.1 14. Vishal Engineering Engineering Works 2.2 15. Philodin Chemicals Chemical 2.2 16. Kiri Dyes & Chemicals H-Acid & V.S. 0.3 17. Losen Kiri chemicals Dyes 0.9 18. Synergy Pvt Ltd. PAC 1 19. Kiri Dyes & Chemicals Sulphuric Acid 1.2 20. I.S. Dyes Stuff V.S. 1.4 21. Aden Pharmaceuticals Pharma Product 1.4 22. Prathana Chemicals Chemical 1.5 23. Satandar Ice Factory Ice 1.8 24. Bodal Chemicals Dyes Intermediates 2 25. Shanti Chemicals Chemical 2.2
1.7 STATEMENT OF PRINCIPLES
The EIA is intended to provide for the protection, conservation and
wise management of environment through planning and informed
decision making.
Following are the guiding principles:
To help decision-makers to protect, conserve and manage
environment according to the principles of sustainable
development, thereby achieving or monitoring human well being, a
healthy environment and a sound economy.
To ensure that the industries consider the effect on the health,
economy and culture of the surrounding communities as well as its
impacts on the air, land and water.
To ensure communication of information to Public.
1.8 THE STUDY AREA
Project Site
The existing unit of Asahi Songwon Colors Ltd. is located at Survey
No.: 429 to 432, Village: Dudhwada, Taluka: Padra, Dist.: Vadodara,
Gujarat. Since the unit has adequate land for the expansion and site
location is preferable, the proposed project will be carried out in the
same premises.
The location map is shown at Figure 1.1.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-14
Study Area Features
Longitude: 22011’35.47” N
Latitude: 72053’55.47” E
Elevation from sea level is 25 meter.
Project Components
The proposed expansion will be in the existing premises located at
Survey No. 429 to 432, Village: Dudhwada, Taluka: Padra, Dist.:
Vadodara, State: Gujarat, having all basic necessary facilities like
infrastructure, communication, medical facilities, power, natural gas,
communication system, well design effluent management facilities
(Water+ Hazardous /solid), raw material availability as well market for
the finished products etc.
The project location is mentioned in the location map attached as
Figure: 1.1.A useful way of identifying many of the potential impacts
of a project is to consider all the aspects of the projects and its
receiving environment and systematically identify the potential for
interactions between them. The first step is to draw up a list of all
project components and activities during each phase of its
implementation. The possible components of proposed project could
lead to environmental impacts are described in this section based on
the understanding of Chemical industry.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-15
Environmental Components
Defining all the possible aspects of the environment is essential for
identification of potential impacts. This may cover features of the
environment (e.g. habitats, settlements, and historic sites); aspects of
environmental quality (e.g. air quality, water quality, noise, physical
conditions, soil stability and hydrology) and uses of the environment
(e.g. agriculture, recreation and fishing). This will be done with
generation of base line data.
1.9 SITE SELECTION CRITERIA
The unit is an existing unit, located at Survey No. 429 to 432, Village:
Dudhwada, Taluka: Padra, Dist.: Vadodara, State: Gujarat. The unit
has been already in existence and the unit is good familiar with the
surrounding environment, therefore, it becomes easy for the unit to
expand the project in the same premises. However, the base of
selection of site was primarily based on the availability of the following
amenities:
Availability of all basic facilities like fuel, water, power,
manpower, raw materials, etc.
The nearest town Baroda is only 30 km away from the project
site which is very well connected with other parts of the country
by road, rail and air.
Good communication and transportation facilities
A treated Effluent disposal facility is also very near to project site
i.e. Effluent Channel Projects.
No R & R will be required
No national park or wildlife Habitats falls within 10 km radial
distance from proposed project site.
1.10 OBJECTIVES OF EIA
EIA is a policy and management tool for both planning and decision
making. EIA assists in identification, prediction and evaluation of the
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-16
foreseeable environmental consequences of proposed developmental
and industrial projects.
The objectives of the present EIA Study is to assess the impacts on
various environmental components due to the proposed project and to
recommend appropriate environmental management plant for the unit
to ensure that the adverse impacts if any will be minimized. Moreover
to prepare an Environmental Statement to indicate conclusively if the
overall impacts are positive or negative.
1.11 SCOPE OF EIA
The scope of present Environment Impact Assessment includes
following studies,
Collection and evaluation of project details and related documents
Analysis of the quality of gaseous emission, wastewater analysis,
hazardous waste generation based on the monitoring results for
the last one year
Assessment of pollution potential due to proposed project
Collection and evaluation of present environmental baseline status
within an impact zone of 5-km radial distance from the project
site on environmental parameters/attributes considering the
proposed activities like,
Ambient Air quality
Water quality and surrounding environmental water bodies.
Soil quality
Noise levels
Meteorology and climates.
Land use pattern and socio-economic status
Identification, assessment and evaluation of the beneficial and
adverse impacts on surrounding environment due to proposed
project activities considering the existing baseline status along
with compilation of other information
Identify the sources and impact of hazards, if any
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-17
Base on the same suggest and design risk assessment plant and
disaster management plant to prevent any hazard
Preparation of final Environmental Impact Statement & EMP
1.12 METHODOLOGY FOR EIA
Environmental Assessment (EA), another term used in the
environmental studies, refers to an understanding of the present
status of environment and a study of how to manage them.
Keeping in view the nature and size of the proposed project and
industrial area and various guidelines available, it was decided to
cover an area of 5-km radius from the center of proposed plant
site for the purpose of environmental impact assessment study.
The methodology is briefly reported below and has been described
in this section.
Baseline data Collection
The baseline data for the impact zone have been generated for the
following environmental parameters:
Ambient Air Quality
Micrometeorology
Noise Levels
Surface and ground water quality
Soil Quality
Flora and fauna
Land use pattern
Occupational structure and socio-economics
The baseline status of the above environmental parameters has
been worked out based on the rapid monitoring/analysis carried out
during the study period of December-10 to February-11 supplemented
by data collected from various government departments, census
publications etc.
Evaluation of Impact from Project Activities The environmental
Impact resulting from the various project activities, have been
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-18
identified, predicted and evaluated based on the study of
manufacturing process and other project related activities as well as
correlating the same with existing base line status.
Preparation of Environmental Management Plan
Environmental Management plan has been prepared covering pollution
prevention measures at source in terms of air and water pollution
control measures, solid waste/hazardous waste management, safety
management, green belt development, environmental surveillance and
environmental management team.
Finally, the detailed assessment of the resultant environmental
impacts have been made based on the impacts identification and
evaluated from the activities over the baseline status of various
environmental components.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-19
Figure 1.1
Location Map
Asahi Songwon
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-20
Figure 1.2
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 1-21
Figure 1.3
Asahi
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-1
Chapter 2
Project Description
2.1 INTRODUCTION
M/s. Asahi Songwon Colors Ltd. is the existing unit located at survey
no. 429 to 432, village: Dhudhwada, Taluka: Padra, Dist.: Vadodara,
State: Gujarat. Now, the unit proposes to expand its production
capacity of CPC Blue and Pigment Beta Blue-A/B in existing product
with capacity of 850 MT/month & 100 Mt/Month respectively. Now
Unit envisage to increase the production capacity of CPC Blue from
850 MT/Month to 1000 MT/month, Pigment Beta Blue from 100
MT/Month to 500 MT/Month with introduce of three new product –
Pigment Alpha Blue with 60 MT/month, Pigment Violet – 23 with 25
MT/Month and Pigment Green – 7/36 with 200 MT/Month.
2.2 LOCATION
The unit is existing unit, located at Survey No. 429 to 432, Village:
Dhudhwada, Taluka: Padra, Dist.: Vadodara, State: Gujarat.
The location of the project site is given hereunder in terms of
longitude and latitude.
Longitude : 22011’35.47” N
Latitude : 72053’55.47” E
Elevation from sea level is 25 meter.
2.3 JUSTIFICATION OF THE PROJECT:
Since last few years’ company has esteemed growth in this field due
to talented science qualified staff. From this Company has achieved
excellent improvement in its product quality with sustainable
environmental development. Moreover due to good quality product,
demand of product has been also increased from last few years in
both National & International market. In view of the availability of
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-2
scientific staff that able to develop sustainable process at relatively
low cost, and high demand of product in market company has
decided to expand its production capacity of CPC Blue and Pigment
Beta Blue-A/B in existing product with capacity of 850 MT/month &
100 Mt/Month respectively in the existing unit located at survey no.
429 to 432, village: Dhudhwada, Taluka: Padra, Dist.: Vadodara,
State: Gujarat.
LAND REQUIREMENT
Since the proposed expansion is in the existing premises
admeasuring total area of the premises of 85259 sq. mt. Out of
which @ 16306 sq. mt. area has been already utilized for existing
production. The detail break of the area is given hereunder,
Area, sq. mt. Sr
No.
Particular
Existing Proposed required
After expansion
1 Plant Facilities 1470 4295 5765
2 Storage (Fuel) 360 1653 2013
3 Storage (Water) 300 500 800
4 Storage (Hazardous Waste) 273 2860 3133
5 Storage (Hazardous Chem.) 300 648 948
6 Storage (Others) 720 2120 2840
7 Utilities 398 1675 2073
8 Approach Road(s) 2000 5600 7600
9 Green Belt 5475 24375 29850
10 ETP 2160 1742 3902
11 Office 150 607 757
12 Parking 2700 1215 3915
13 Open to Sky 68953 37969 21663
Total 85259 85259 85259
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-3
The project in house main factory building, go down, effluent
treatment facility, storage tank yard, various utilities required for the
product etc. Existing constructed area includes plant area, storage
area and Effluent Treatment Plant along with office building. The site
plan and factory lay out is also attached herewith as Drawing-2.3.
2.4 CAPITAL INVESTMENT
Total additional cost of projects will be 41.00 crores, out of which,
around 07 crores will be utilized for Environment Management
Systems.
2.5 PRODUCT AND SIZE OF THE UNIT
The unit has been already involved in the manufacturing of CPC blue
crude and now, intends to expand it production capacity as under,
Sr. No.
Product Existing capacity in (MT) / month
New Capacity Addition in (MT) / month
Total Capacity in (MT) / month
Product Expansion in existing Plants 01 Phthalocyanine Blue Crude 850 150 1000
02 Pigment Beta Blue-A/B 100 400 500
New Products Additions
01 Pigment Alpha Blue : 15 / 15.1 -- 60 60
02 Pigment Violet – 23 -- 25 25
03 Pigment Green – 7/36 -- 200 200
Grand Total of Capacities : 950 835 1785
Bye Products
1 Blue Crude Plant Ammonium Carbonate /Ammonium
Sulphate 0 600/1200 600/1200
2 Pigment Green Plant HCl - 20% 0 150 150 Sodium Hypochlorite solution - 12% 0 200 200 3 Alpha Blue Plant: Dilute Sulphuric Acid - 30% 0 1370 1370
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-4
2.6 MANUFACTURING PROCESS
The manufacturing process for existing and proposed products is
given hereunder,
2.6.1 CPC Blue Crude
BASIC CHEMICAL REACTIONS 4C8H4O3+2CO (NH2)2. 130°C ~ 140°C 4C8 NO2H5 + 2CO2 + 2H2O Phthalamide Eq.-I 140°C~170°C 4C8 NO2H5+8CO(NH2)2. 4C8 H7NO2+2CO2+2H2O Di-Amino Phthalamide 180°C~190°C Eq.–II 4C8H7N3+CuCl . C32H16N8Cu+NH4Cl+1/6N2+2/3 NH3 Ammonium Molybdate CPC Blue Equ - III
Manufacturing Process:
(1) Charge required quantity of Phthalic Anhydride, Urea in a Glass
Vessel, which is already having a solvent at desire temperature.
(2) Heating the content to higher temperature and then, addition of
catalyst and Cuprous Chloride to it.
(3) Raise the temperature of the reaction mass at desire temperature
and maintain this temperature for 6/8 hours.
(4) After reaction is over, draw the sample and check for complete
conversion of Phthalic Anhydride to CPC Blue Crude.
(5) Discharge the batch into Horizontal Rotary Vacuum Dryer (HRVD)
and remove the solvent under vacuum. After complete removal of
solvent add water to the Horizontal Rotary Vacuum Dryer (HRVD)
and transfer the material to treatment tank.
(6) Give the requisite treatment to CPC Blue Crude and filter it
through PP Filter Press.
(7) Dry the material using Spin Flash Dryer (SFD) and collect the
dried powder in bags and send it to Godown.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-5
Glass vessel
Rotary Vacuum Dryer
Acidic Treatment
Filtration & Washing
Alkali Treatment
Filtration & Washing
Spin Flash Dryer
Bagging
Storage
Solvent
NH3, CO2
Output Kgs
Scrubber
Weak Ammonium Sulphate sol &
solvent
11000
Recovered Solvent 5120
Steam Condensate 942
ML + Wash Water 25500
Alkali ML + Wash Water
38350
Evaporation loss 2500
Products 2000
Input Kgs
Cuprous Chloride Phthalic
Anhydrous Urea
Recovered solvent
Ammo. Molybdate
Water
355
2100
2800 5200
7.0
8000
Steam Water
1950 3980
Steam Water
1750 24250
Steam Water
Caustic lye
1950 3980 300
Steam Acidic ML
from Alpha Blue
30% H2SO4 Water
1750 3750
695 6595
Steam Water
1750 14250
Process Flow Diagram for CPC Blue Crude:
85412 85412
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-6
2.6.2 CPC Beta Blue
Chemical Reaction
No chemical reaction is involved in the manufacturing of CPC Beta
Blue, only unit operations/ processes will be involved.
Manufacturing Process
(1) Charge RVD dried Blue Crude to Blender and homogenize the
mass for 2 hours.
(2) Add required quantities of Sulphuric acid to the blender.
(3) Blend the mass for 2-3 hours and remove the powder
(4) Now. Mill the powder in swing Mill or in Ball mill.
(5) The milling permeation should be carried out for at least 2
hours.
(6) After milling the material, charge the powder to acid leaching
tank (MS/BL). Add required quantity of Sulphuric acid to the
tank and make concentration of Sulphuric acid equal to 21% by
adding fresh water.
(7) Heat the contents at require temperature and maintain for 2
hours.
(8) Filter the material and wash it to neutral pH and remove the
cake.
(9) Now, charge the wet cake into water and disperse the wet cake
by agitation.
(10) Rotate the slurry through Gyrator for 2 hours to break
agglomerate formed during the process. Now, add solvent,
Caustic Lye (48%) and emulsifier.
(11) Mix the material thoroughly and heat the contents till the reflux
stars. Continue the reflux of solvent for 5 hours and then, start
recovery of the same.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-7
(12) Starts collecting recovered solvent in a separate tank and at
the end of the recovery inject live steam into the vessel to
recover max. Quantity of solvent.
(13) Filter the mass under hot condition and wash the material to
neutral pH.
(14) Dump the wet cake in re-slurry vessel and adjust the pH in
between 6.5 to 7.5 by 98% Sulphuric acid.
(15) Filter the material and bring the pH of wet cake to neutral. Give
Final wash of RO/DM water to the wet cake till the conductivity
of filtrate is found to be less than 100 micro ohms/Cm.
(16) Route the wet cake to SFD for drying purpose and collect the
material in the HDPE/ Jumbo bags.
(17) If necessary, blend the material in the blender and pack the
material in PP bags or Jumbo bags depending upon the
requirement of the plant.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-8
Material Balance Diagram:
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-9
2.6.3 Pigment Alpha Blue: 15 / 15.1
o Blue Crude is grinded in a Ball Mill or a Swing Mill. o The grinded material is dissolved in Sulphuric Acid in a glass
vessel under cooling. o The dissolved material is dumped into cold water in FRP drowning
vessel where the pigment particle gets separated. o The material is filtered, washed and the cake is transferred to
another vessel for treatment. o In treatment vessel distilled / RO water is taken and the wet cake
is added. Additives are added according to the product quality desired. Caustic is also added to bring pH more than 9. The material is heated to a certain temperature and filtered through PP Filter press. The filter press is washed with plenty of water till the pH of filtrate is neutral.
o The wet cake is dried in Spin Flash Dryer and the material is
collected in jumbo bags and dispatched to godown for sale.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-10
Vibration/Ball milling
Acid Swelling
Drawing & Leaching
Filtration
Treatment
Filtration
Output KGS
Sulphuric Acid
Input KGS
CPC Blue
1000
Sulphuric acid Wash Water
6000 3000
Alpha Wash Water
11000
Steam Wash Water
250 13000
Steam Additive I & II
Alpha Wash Water
500 22
6500
Steam loss-70
16500 250
Process Flow Diagram for Pigment Alpha Blue: 15/15.1
Drying in SFD
Blending
Packing
Dispatch
Whole ML+Wash water is reuse in process so no load on ETP
Reuse in Alpha + CPC Blue
31250
ML+Wash Water to BC plant Reuse in Alpha
Blue
Evaporation
23750
2022
Product 1000
Total 58022
Total 58022
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-11
2.6.4 CPC GREEN – 7/36:
• Chlorine/Bromine gas is reacted with CPC Blue in a eutetic mixture of Aluminium Chloride and Sodium Chloride in presence of Cupric Chloride.
• The reaction is carried out at high temperature and it is continuously
monitored for completion of reaction.
• After the reaction is over the material is dumped in water and filtered. The Mother Liquor is collected in ETP plant and sold to textile mills.
• In the filter, wash the cake to neutral pH, then, it is removed from the filter
press.
• The wet cake further purified in the pigmentation vessel in presence of solvent and other ingredients.
• After the solvent finishing is over the material is filtered again and washed
with water to bring the pH neutral.
• Wet cake is removed from the filter press and dried in Spin Flash Dryer to recover the CPC Green powder.
• The powder is packed in 20 kgs. Bags or in jumbo bags and dispatched to
go down.
Reaction: AlCl3 + NaCl/NaBr CPC Blue + Cl2 /Br2
CuCl2 CPC Green + HCl /HBr
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-12
N
N N+
N
N+
N N
N Cu2-
Cl Cl Cl Al
Cl
Cl
+ + NaCl+
N
N N+
N
N+
N N
N Cu2-
Cl
Cl
Cl
Cl
Cl
Cl
Cl
Cl
Cl
Cl
ClCl
Cl
Cl
Cl
Cl
+ ClH
Note: For PG-36 Raw material is change PG-7 PG-36
Chlorine Bromine NaCl NaBr HCl HBr
Chemical reaction and structure for Pigment Green-7
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-13
Chlorination
Dumping
Filtration
Pigmentation/ Treatment
Filter
Dryer
Blender
Bagging & storage
Output
HCl Hypo
KGS
750 1000
ML for sale
3200
Wash Water
24800
Solvent Loss
5700 300
ML to ETP 36760
Evaporation 2200
1000
Input KGS
Chlorine Aluminum Chloride
CPC Blue Sodium
Chloride/Bromine Cupric Chloride
Water
1500 2800 800
600 90
1200
Water 300
Steam Water
1440 23560
Water Xylene Caustic
Emulsifier Steam
5000 6000 350 50
4320
Steam Hot water
1440 23560
Process Flow Diagram for CPC Green (Pigment Green-7/36)
Total 75710
Total 75710
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-14
2.6.5 Pigment Violet – 23:
• Carbazole is an ethoxylated with Ethyl Sulphate. The product is centrifuged and washed with methanol to remove the impurities.
• Wet cake removed from the Centrifuge is mixed with Chloronil in
presence of solvent and the mixture is taken to Nitrator.
• In Nitration reaction, concentrated Nitric Acid is added to this mixture at controlled rate and under cooling and the fumes are continuously removed from the vessel. After the nitration is over the material is dumped to reduction vessel.
• In reduction vessel the nitrated mass is reduced with iron powder /
hydrogen and the reduced mass is filtered in a neutch filtrate and the wet cake is further treated with a solvent to remove the impurities.
• The solvent treated material is centrifuged and dried in a tray dryer
and grinded in Ball Mill. The material so obtained is known as Crude Violet.
Solvent finishing
• The Crude Violet is treated with Hydrochloric Acid under certain temperature and the material is filtered and washed with water to neutral pH.
• The wet cake is further treated with Solvent and additives in
pigmentation vessel and the pigmentation is carried out in presence of solvent.
• After the pigmentation the material is filtered, washed, dried and
packed, and packed material sent to the godown for sale.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-15
NH
S
O
O
OHCH3+N
CH3
N
CH3
+ OH N+
O-
O N
CH3
N+
O-
O
N
CH3
N+
O-
O
Fe2+
O
OH CH3+H2
N
CH3
NH
H
N
CH3
NH
H
+ +O
Cl
Cl
OCl
Cl
NNH
H CH3
N
CH3
N
H
NN
H CH3
O
OCl
Cl
Chemical reaction and structure for Pigment Violet-23
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-16
Flow Chart for Pigment Violet-23
Ethylation
Centrifuging
Nitration
Reduction
Neutch Filter
Cyclisatim
Neutch Filter
Tray Dryer
Milling
Pigmentation
Filtration/Washing
Drying/Pulverization
Packing
Output KGS
MCB recover 850
Effluent 1500
Effluent 1658
650
Recovery Reuse
MeOH
MeOH Distillation
Sludge
Solvent-MCB
1700
1200
5500
2800
1000
ODCB 2300
Input KGS
Carbazole MCB
Caustic Soda Diethyl Sulphate
Additive
1100 880 1400 880 50
Water 1000
Nitric Acid Water
1214 600
Iron powder/ Hydrogen Acidic Acid Soda Ash
ODCB
260 346 85 75
2450
Catalyst Chloronil
Benzene Sulphonly Chloride
94 147 102
MeOH 1700
Additives MCB
25 1250
Water 5500
ODCB Steam loss-70
Total 19158 Total 19158
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-17
2.7 INPUT REQUIREMENTS
2.7.1 Raw Material Requirement
The details of the raw material requirement are given in
Table-2.1.B
2.7.2 Water The unit has their own bore wells within premises to satisfy its fresh
water requirement. At present the total fresh water requirement is
2188 KL/day which will be reduced up to 2105 KL/day even after
proposed expansion through Implementations of water recycle
mechanism.
The details breakup of the water consumption is given in Table:-2.4.
The water Balance diagrams for existing, and after proposed
expansion are given in Figure-2.1(a) to Figure-2.1(b).
2.7.3 Fuel
At present there are two steam boiler having steam generation
capacity of 2.5 TPH & 10 TPH FBC Boiler and Six Thermic fluid
heaters of 800u & 500ux2 TPH, 1500x2 TPH & 1000 TPH capacity
respectively, where coal / lignite is used as fuel.
After proposed expansion there will one boiler and Six thermic fluid
heaters & Five Spin Flash Dryer will be added. The details of stack
and process emission are tabulated in table no-2.8. Details of fuel
consumption are summarized in table no-2.7.
2.7.4 Power
M/s. Asahi Songwon Colors Ltd. fulfills power requirement through
Madhya Gujarat Vij Utpadan Company Limited (MGVUC). At present
the connected load is 750 KWH and after proposed expansion it will
be increased up to 96+750 KWH. Source of power remain same i.e.
Madhya Gujarat Vij Utpadan Company Limited (MGVUC).
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-18
2.7.5 DEMATERIALIZED WATER SYSTEM
The DM plant will meet the requirement of process water, make-up
requirement of steam generators, cooling tower etc. and the input to
the DM plant will be drawn from the own bore well.
2.7.6 REVERSE OSMOSIS (RO) SYSTEM
The RO plant shall consist of following in 2 X 70 % configuration:
High pressure feed pumps and PX booster pump (as applicable)
Membrane element assembly unit
Energy recovery Turbine / Pressure exchanger
Auto dumping system
Suck back tank
Permeate water booster pump
Clean in place system
Flushing water system
Water from the bore well is fed to the RO plant, at the suction of the
High-pressure feed pump. The high-pressure pump pressurizes and
feeds it to the membrane assembly unit. A set of High pressure
pump / recovery turbine or Pressure exchanger and the Membrane
element assembly unit forms a train in the RO plant.
In case of pressure exchanger being used for energy recovery, a PX
booster pump shall be installed in a parallel with main HP pump.
To avoid excess back pressure on the permeates, permeate booster
shall be provided.
Brine leaving the permeator outlet connection at a pressure close to
the feed pressure shall be by a flow control valve.
The permeate water is discharged to product water system where the
permeate water will be treated to correct pH. Stored product water
will be then transported to the consumption destination by product
water system.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-19
2.8 GENERATION OF POLLUTANTS
2.8.1 EXISTING MANUFACTURING ACTIVITIES
A) Process Effluents from Existing Products
The main source of the industrial wastewater generation is process,
washing and utilities. The entire quantity of the industrial wastewater
is segregated in to three parts as per the concentration,
(i) concentrated stream (i.e. ML of acidic treatment of CPC Blue)
(ii) general/weak stream from manufacturing activities of other
product from Manufacturing stream
(iii) Effluent from the utility section i.e. RO reject, DM plant
regeneration, cooling bleed off, boiler blow down etc.
The unit has also provided its own Effluent Treatment Plant
comprising of primary and secondary treatment units to treat the
industrial effluent being generated from the existing production
activities and, then after finally treated industrial effluent is
discharged into ECP channel.
The details of the wastewater generation and Effluent Treatment
plant are depicted in Table-2.4.
B) Gaseous Emissions
The main sources of the air pollution from the existing industrial
activities are flue gas emission and process gas emission. The flue
gas emission is from the common stack attached to steam boiler and
Six nos. of thermic fluid heaters due to combustion of fuel which are
attached to three stack.
Whereas the process gas emission is from the one process gas stack
attached to process vessels (1 to 4), second process stack attached
to Process Vessel (5 to 6) and three process stack attached to spin
flash dryers. Details of pollutant with stack height and APCM
measures are summarized in Table No. 2.8.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-20
C) Fugitive Emission
There are also chances of the fugitive emission due to handling of
process gas emission and hazardous chemicals as well as due to
liberation of the excess solvents from the reactors.
However, to prevent the same the unit takes all the precautionary
measures like adequate scrubbing system to absorb the process gas
and to carry out entire process in the closed reactors, etc. Work
place environment for existing activities are given in Table No.
2.10.
D) Hazardous/Solid waste
The main source of hazardous waste generation is ETP sludge from
the Effluent Treatment facilities. The other sources are discarded
barrels/bags/liners/drums and spent/waste oil from the material
handling and storage and plant & machinery.
The details of the hazardous waste are given Table-2.11 & 2.12.
E) Noise
Noise can be defined as an unwanted sound. It interferes with speech
and hearing and is intense enough to damage hearing or is otherwise
annoying. The definition of noise as unwanted sound implies that it
has an adverse effect on human beings and their environment. Noise
can also disturb natural wildlife and ecological system. Sound is
mechanical energy from a vibrating surface, transmitted by cyclic
series of compression and rarefaction of molecules of the materials
through which it passes.
Sound can be transmitted through gases, liquids and solids. The
number of compressions and rarefactions of the air molecules in the
unit of time is described as its frequency. Frequency is expressed in
hertz (Hz), which is the same as the number of cycles per second.
Noise monitoring for existing plant activities ate given in Table No.
2.13.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-21
2.8.2 PROPOSED EXPANDED CAPACITY
Since the unit proposes to enhance the production capacity of its
existing product with introduction of three new products, there will
be increased in the pollution load due to proposed expansion. The
details are given hereunder,
Liquid Effluents-After proposed capacity
Since most of the industrial activities will be remained same after
proposed expansion, except increased in wastewater generation from
process & utilities. However, after proposed expansion the industrial
wastewater generation will be reduce due to recycling of treated
wastewater.
The unit is also going to continue its current practice of the
wastewater management and entire quantity of the industrial
wastewater will be segregated into three parts depending upon the
concentration. Entire quantity of industrial waste water will be
treated at its own ETP after and finally discharged into ECP channel
which convey the treated effluent into river Mahi Creek.
At present our wastewater discharge is tune around 1482 KL/day
which will be reduced up to 1174 after proposed expansion.
Justification of wastewater reduction after expansion is given in
Figure-2.1(c). (Recycling of water).
The details of the wastewater generation after proposed expansion
and Effluent Treatment plant are depicted in Table-2.4 and Table-
2.5.
To maintain or reduce the wastewater discharge into ECP channel
which convey the treated effluent into river Mahi Creek, unit
proposed to install a RO & Multi effect evaporation systems. The
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-22
details of recycling systems are summarized in point no-2.8 and
water balance diagram is work out as per figure-2.1 (b).
B) Gaseous Emissions
In addition to existing sources of air pollutions, there will be one
stack of flue gases (steam boiler and six nos. of thermic fluid
heaters), two process gases and four vents for Spin flash dryers will be
added. Details of pollutant with stack height and APCM measures are
summarized in table no-2.8.
C) Hazardous/ Solid waste
The sources of hazardous waste generation will also be remained
unchanged after proposed expansion however, there will be
increased in the quantity of the hazardous waste generation. Details
of existing source and quantity and addition after proposed
expansion are summarized in Table-2.11.
D) Noise
Power plant will be the major source of noise pollution generation in
addition to existing noise level.
2.8.3 POLLUTION CONTROL STRATEGY
A) Effluent Management
After proposed expansion, industrial effluent treat/handle in our
existing ETP, this is adequate after reduction of industrial
wastewater. The detail of effluent treatment scheme is given
hereunder.
There will be mainly three streams generated during the
manufacturing process (i) concentrated stream (i.e ML of acidic
treatment of CPC Blue) (ii) general/weak stream from manufacturing
activities of other product from Manufacturing stream and (iii)
effluent from the utility section i.e. RO reject, DM, plant
regeneration, cooling bleed off, boiler blow down etc. The effluent
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-23
treatment plant is based on segregation system of difference
streams.
ETP Description: The Company has planned to reuse 1837 KL
water per day therefore the amount of Fresh water need will be
around 2105 KL. for processing, steam generation, cooling owers
evaporation, drinking, sanitation, gardening, etc. Details are shown
in Figure No- 2.1 (b) & (c). It is estimated that almost 3100 KL/d
of waste water shall be generated from various processes. Part of the
waste water shall be highly acidic in nature and it will be consumed
in the unit itself and/or sold to end user. This load may further
dropped down if RO rejected is further refined in RO plant to get
good quality of water and further followed with reuse membrane
technology to reduce the load on discharged to ECP Channel. Thus
total load on ETP will be 1174 KL/d. The Company has already
installed a full-fledged ETP plant which comprises of neutralization,
equalization, settling, aeration, filtration through Carbon and sand
filters to remove suspended particles. With minor modifications in
existing ETP plant and taking more efforts to reduce the water
consumption, unit can treat its waste water in existing facility with
some additions of the other equipments.
Copper Removal:
Since the unit is using Cuprous Chloride in the process and hence
Copper is coming in the effluent. Copper is removed by adding
chemical `x’ to the effluent and removed by filtration. The Copper
free effluent is taken to ETP plant for further treatment. The
recovered copper sludge will be sold in the market for recovery of
Copper by manifest mechanism and taking care to sell only
CPCB/GPCB registered recycler which has registration Certificate-
cum-Pass Book for Re-refining/Recycling of Hazardous Wastes.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-24
R.O Regeneration of effluent water & Multi effect evaporator
B) Air Pollution Control
The unit has already provided separate dust collector as air pollution
control measures to the flue gas stack. The unit has also provided
adequate scrubbing system comprising of three stages of water
scrubbers to absorb the process gas generating from the process
reactors for recovery of by-products and controlling the emission
levels as per GPCB norms.
After proposed expansion, as mentioned in above section there will
also be increased in the flue gas stacks due to installation of one new
CPC blue guide Acidic ML
216 m3 /day
CPC blue guide Acidic wash 450 m3 /day
Alkaline Treatment
630 m3 /day
Beta Blue WW 630 m3/day
Copper Treatment & Stripping
Collection & Equalization
1296 m3 /day
PSF-ASF-UF 630 m3 /day
Back Wash 50 m3/day
Primary Treatment
Bioreactor
Reverse Osmosis
1296 m3/day
Permeate 910 m3 /day
Solid waste 10 m3 /day
RO 580 m3/day
RO Reject 140 m3 /day
Disposal to MEE 140 m3 /day
Reject Water 386 m3 /day
Reuse Water 440 m3 /day
Water Balance Diagram
580
MEE 526 m3 /day
Loss 29 m3 /day
Recovered 487 m3 /day
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-25
steam boiler where the unit proposes to install Dust collector-Bag
filter as air pollution control measures.
There will also addition of process gas stack where the unit proposes
to continue its current practice of scrubbing system and will install
the three stage of water scrubbing system, which will be adequate to
meet gaseous emission norms recognized by GPCB.
The unit has already provided adequate stack height of 32.0 m for
flue gas stacks and 15.0 m to process gas emission for the proper
dispersion of the gaseous emission and minimizing the impact of air
pollution at ground level. Now, the unit also proposes to provide
stack height of @ 32.0 m to the proposed steam boiler and 15.0 to
process gas stack, which will also be adequate considering the worse
scenario of Sulphur contents at the rate of 2.4 % in the fuel
proposed to used after proposed expansion.
C) Hazardous/Solid Waste Management
Entire quantity of hazardous waste will be handled and disposed as
per Hazardous Waste (Management, Handling & Trans Boundary
Movement) Rules -2008.
The ETP sludge will be disposed to secured landfill site operated by
M/s. NEPL, Naroda-Ahmedabad. Whereas discarded/ barrels/bags/
drums /liners will be decontaminated and reused/sold to approved
vendors. The spent/waste oil will be sold to CPCB approved recyclers.
D) Ash Disposal
Around 30 % ash of total ash generation will be utilized for bricks
manufacturing and balance ash will be sold off to cement
manufacturer for use in PPC cement, to hollow concrete brick
manufacturer etc., and also will be supplied to the company for land
leveling, conditioning and road construction, etc.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-26
2.8.4 RESOURCE RECOVERY
Liq. Ammonia/Ammonium Carbonate Recovery system
Main source of Ammonical Nitrogen is reaction of Phthalic Anhydride,
Urea, CuCl and acid treatment for purification of products. Second
source is air pollutant-Ammonia scrub by water.
The process emission containing Ammonia and Carbon dioxide
mainly. The Ammonia gas gets absorbed in the water and results in
Liq. Ammonia solution (12–15%). This Ammonia solution is
recovered as By- Product and sold to actual users or converted it to
(NH4)2SO4. Proposed process to generate (NH4)2SO4 and control of
Ammonia and Amonical Nitrogen is summarized below.
Generated acidic water contains (NH4)2SO4 and some part of urea
which is responsible for Ammonical nitrogen in the effluent.
We will isolate acidic effluent stream which contains ammonical
nitrogen, and use to scrub the gases (which contain ammonia and
carbon dioxide). This acidic filtrate will absorb ammonia as
ammonium sulfate. As the pH of this filtrate goes from 2 towards 7
we will go on adding more sulfuric acid for faster reaction.
This will resulted in about 20% ammonium sulfate solution which we
will recover as by product by concentrating through multiple effect
evaporators. There by the effluent stream containing ammonical
nitrogen will be dealt separately and will not go to our effluent
treatment plant.
Generated Ammonium Sulphate will be sold to actual users.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-27
2.9 RESOURCE CONSERVATION
2.9.1 GROUND WATER RECHARGING SYSTEM
The unit proposed ground water recharging sump at low lying area
which will be connected to the storm water drainage system. To
recharging the ground water during the rain, unit will be balanced
ground water.
2.9.2 GREEN BELT DEVELOPMENT
The unit has done extensive plantation in 24375sqm and will be
added some more area for greenbelt development and it will be
around 5475 sqm. After expansion greenbelt will be in 29850 sq. mt.
areas and it will be around 35% of total land area.
2.10 FIRE FIGHTING SYSTEMS
The fire fighting system will be designed by incorporating the
recommendations of the Tariff Advisory Committee of Insurance
Association of India. During the design of such system, codes and
standards of National Fire Protection Association (NFPA), USA will be
taken in to consideration and the same would be applied. Fire
fighting system will consist of hydrant system, water spray system,
foam system, emulsifier system, portable fire extinguishers and fire
alarm system.
The water will be taken from the product water storage tank for fire
water pumps of hydrant network and water spray. Fire water pumps
and fire water storage tanks shall be provided as per regulations.
2.11 RAIN WATER HARVESTING
Rain Water Harvesting is a method of utilizing rain water for
domestic and agricultural use is already widely used throughout the
world. It is a method which has been used since ancient times and is
increasingly being accepted as a practical method of providing
potable water in development projects throughout the world.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-28
Improve the ground water in Industrial area is one of the main
problems which is being faced by developed countries of the world.
In Industrial area the charging of underground water in natural way
like rural areas is not taking place due to large sprawl of Industrial
activities. But it is feasible by inject the water by percolating wells.
To considering the Industrial area and various types of activities may
contaminate the rain water, recharging the rain water by inject the
rain water to underground aquifers is not advisable. Asahi Songwon
Colors Ltd. will reuse the rain water collect from rooftop during the
rainy season.
The average long-term rainfall, out of which 20% of the rainfall is
considered to go to the ground as a natural recharge and remaining
rainfall runoff and this, is available for the artificial recharge after
accounting for soil moisture storage and evaporation.
We proposed two artificial water recharge well in our premises in low
lying are with due considering to avoid any contamination.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-29
Table 2.1 (A)
Detail of the Products
Sr. No.
Product Existing capacity in (MT) /
month
New Capacity Addition in (MT)/ month
Total Capacity in (MT) /
month Product Expansion in existing Plants 01 Phthalocyanine Blue Crude 850 150 1000 02 Pigment Beta Blue-A/B 100 400 500
New Products Additions 01 Pigment Alpha Blue : 15 / 15.1 -- 60 60 02 Pigment Violet – 23 -- 25 25 03 Pigment Green – 7 -- 200 200
Grand Total of Capacities : 950 835 1785
Bye Products
1 Blue Crude Plant Ammonium Sulphate 0 1200 1200 2 Pigment Green Plant HCl - 20% 0 150 150 Sodium Hypochlorite solution - 12% 0 200 200 3 Alpha Blue Plant: Dilute Sulphuric Acid - 30% 0 1370 1370
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-30
Table 2.1 (B)
Raw Materials
Sr. No.
Raw Materials Existing Cons. in
MT/ month
Proposed req. in
MT/ month
Total Req. in
MT/ month Phthalocyanine Blue Crude 01 Phthalic Anhydride 943.5 166.5 1110 02 Urea 1258 222 1480 03 Cuprous Chloride 161.5 28.5 190 04 Solvent – Loss 25.5 4.5 30 05 Sulphuric Acid 255 45 300 06 Caustic Lye 68 12 80 07 Catalyst 3.4 0.6 4
Pigment Beta Blue-A/B 01 Blue Crude 95 380 475 02 Solvent Loss 0.5 2.0 2.5 03 Gum Rosin 8 32 40 04 Sulphuric Acid / HCl – 30% 9 36 45 05 Caustic Lye 5 20 25
Pigment Alpha Blue : 15 / 15.1 01 Blue Crude 0 58.2 58.2 02 Sulphuric Acid (98%) 0 390 390 03 Emulsifier – Additives – I 0 1.65 1.65 04 Additive – II 0 9.21 9.21 05 Caustic Lye (48%) 0 1.53 1.53
Pigment Violet – 23 01 Carbazole 0 22.75 22.75 02 Chloronil 0 21.25 21.25 03 Solvent – ODCB 0 4.125 4.125 04 Solvent – Methanol 0 1.025 1.025 05 Solvent – MCB 0 0.55 0.55 06 Nitric Acid 0 25.075 25.075 07 Iron powder 0 50.05 50.05 08 Di Ethyl Sulphate 0 0.5 0.5 09 Catalyst 0 3.075 3.075
Pigment Green – 7/36 01 CPC Blue Crude 0 110.0 110.0 02 Aluminium Chloride 0 386.0 386.0 03 Sodium Chloride/ Sodium Bromide 0 90.0 90.0 04 Cupric Chloride 0 14.0 14.0 05 Emulsifier 0 4.0 4.0 06 Oleic Acid 0 8.0 8.0 07 HCl/HBr 0 14.0 14.0 08 Caustic Lye 0 28.0 28.0 09 Solvent – Make up 0 14.0 14.0 10 Liq Chlorine/Bromine 0 207.0 207.0
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-31
Table No 2.2 Hazardous Chemicals storage facilities
Name of Chemical Quantity,
MT/month
MOC Storage
Facility
Sulphuric Acid (98%) 75 MS Above GL
Spent Acid (20-22%) 100 MSRL/FRV Above GL
LAB (Solvent) 120 SS Claded Above GL
Iso butyl Alcohol 30 SS Claded Above GL
Chlorine or Bromine 207 MS/Glass Cylinder/bottles
Xylene 30 SS Claded Above GL Nitric Acid 25 MS Drum
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-32
Table No. 2.3 Typical Fuel Analysis
Lignite Analysis
Ultimate analysis by % weight (Dry basis) Component Lignite Carbon 40.00 Hydrogen 2.20 Nitrogen 0.60 Sulphur 1.8 – 2.4 Oxygen 7.00 Ash 10 – 12 Moisture 30 - 33 G.C.V (Kcal/kg) 3300
Coal Analysis Ultimate analysis by % weight (Dry basis)
Component Imported coal Carbon 40.00 Hydrogen 2.20 Nitrogen 0.60 Sulphur 0.5 Oxygen 7.00 Ash 6-7 Moisture 35 - 36 G.C.V (Kcal/kg) 5600 (+/-100)
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-33
Table 2.4
Details of water consumption and wastewater generation
Water Consumption
KL/day Sr. No.
Category
Existing Proposed 1. Domestic 25 50 2. Gardening 15 180
Industrial 1 Process 1127 2497 2 Washing 80 100 3 Boiler 191 462 4 Cooling Tower 525 123 5 Reject Water 225 530*
Total water consumption 2188 3942 Less Recycled 0 1837 Actual fresh water requirements 2188 2105
Wastewater Generation KL/day
Sr. No.
Category
Existing Proposed 1. Domestic 22 45 2. Gardening 0 0
Industrial 1 Process 1000 2427 2 Washing 80 100 3 Boiler 20 23 4 Cooling Tower 157 20* 5 Reject Water 225 530
Total wastewater generation 1482 3100 Less Recycled 0 1926 Actual wastewater generation 1482 1174 * Water consumption and wastewater generation will be reduced after proposed expansion because operation period of cooling tower will be reduced because use of chilling plant.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-34
Table 2.5
Details of Effluent Treatment Plant
Sr. No.
Name of the Equipment Nos. of units
Size of the unit with SWD in m
1 Acid–proof brick lined Mother liquor collection
2 7.25 φ x 2.0 (each)
2 Collection/Neutralization Tank 4 10 x 10 x 2.5 3 Plate and Frame type Filter Press 6 @40 plates each of
size1.2x1.2 4 Filtrate collation sum 2 50 m3 5 Primary settling Tank 3 4.8 x 4.3 (2.25+2.5) 6 Air Stripper 2 50 m3 7 Flash mixer 2 1 m3 & 20 m3 8 Flocculation Chamber 2 1 m3 & 20 m3 9 Chemical Dosing tanks 4 - 10 Aeration Tank for secondary
Treatment 3 11 x 9 x 4 (each)
11 Secondary settling tank 2 3.8 x 3.5 x (2.75+2.0) (each)
12 Treated water Sump 2 5 x 5 x 2.5 13 Activated Charcoal Column 2 2.2 dia x 1.5 m 14 Sand filter 2 2.2diax2 m 15 Guard Pond 1 100 m3 16 Sludge drying bed 3 -
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-35
Table 2.6
Performance of Existing ETP
(Date of sampling: 14/02/11)
Sr. No.
Parameters Unit Raw Effluent
After Primary
After Secondary
GPCB Norms
1. pH pH Unit
4.5 7.6 7.7 6.5-7.5
2. Color Co-Pt Unit
1650 243 92 <100
3. SS mg/L 892 142 94 <100
4. TDS mg/L 4572 4856 4753 <5000
5. COD mg/L 2292 1563 220 <250
6. BOD mg/L 1062 542 92 <100
7. Oil & Grease mg/L 16.5 7.5 7.5 <10
8. Copper mg/L 12.7 1.78 1.78 <2
9. Ammonical Nitrogen
mg/L 6115 242 65 <50
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-36
Table 2.7 Details of fuel consumption
Sr. No.
Type of Fuel Existing TPD
Proposed addition
TPD
Total TPD
1 Coal/Lignite 95 85 180
2 LDO NA NA NA
Table 2.8
Details Stacks
Sr. No.
Stack attached to
Fuel Type Stack Height,
in m
APC measures
Probable emission
Existing
Flue Gas Stacks
1. Steam boiler-1 -- 32
Cyclone Separator
followed by Bag Filter
SPM=<150 mg/Nm3
SO2=<100 PPM
NOX=<50 PPM
2.
FBC IBR Boiler (10TPH) & IBR Boiler (2.5 TPH)
-- 32
Cyclone Separator
followed by Bag Filter
SPM=<150 mg/Nm3
SO2=<100 PPM
NOX=<50 PPM
3. Thermic Fluid heater 1, 2 & 3
-- 32
Cyclone Separator
followed by Bag Filter
SPM=<150 mg/Nm3
SO2=<100 PPM
NOX=<50 PPM
4. Thermic Fluid Heater 4 & 5
-- 32
Cyclone Separator
followed by bag filter
SPM=<150 mg/Nm3
SO2=<100 PPM
NOX=<50 PPM
5. Thermic Fluid heater – 6
-- 32
Cyclone Separator
followed by Bag Filter
SPM=<150 mg/Nm3
SO2=<100 PPM
NOX=<50 PPM
Process Gas Stacks
1. Process Vessel 1 to 6
-- 15 Three stage water Scrubber
NH3<175 mg/NM3
2 Spin Flash Dryer – 1
-- 6 Bag Filter SPM=<150 mg/Nm3
3 Spin Flash -- 6 Bag Filter SPM=<150 mg/Nm3
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-37
Dryer – 2
4 Spin Flash Dryer – 3
-- 6 Bag Filter SPM=<150 mg/Nm3
Proposed Flue Gas Stacks
1 Boiler – 3 Lignite 32
Cyclone Separator
followed by Bag Filter
SPM,
SO2,
NOX
2 Thermic Fluid Heater 7 – 8
-- 32
Cyclone Separator
followed by Bag Filter
SPM,
SO2,
NOX
3 Thermic Fluid Heater 9 – 10 -- 32
Cyclone Separator
followed by Bag Filter
SPM,
SO2,
NOX
4 Thermic Fluid Heater 11 – 12 -- 32
Cyclone Separator
followed by Bag Filter
SPM,
SO2,
NOX
Process Gas Stacks
1 Chlorination &
Dumping Vessel
-- 18
Two Stage Water Scrubber
Followed by alkali scrubber
HCl :- <20 mg/Nm3
Cl2 :- <10 mg/Nm3
2 Spin Flash Dryers 1
-- 11 Bag Filter SPM
3 Spin Flash Dryers 2
-- 11 Bag Filter SPM
4 Spin Flash Dryers 3
-- 11 Bag Filter SPM
5 Spin Flash Dryers 4
-- 11 Bag Filter SPM
6 Spin Flash Dryers 5
-- 11 Bag Filter SPM
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-38
Table 2.9(a)
Performance of Stack emission
Date of Sampling:-14/02/2011
Sr. No.
Stack attached to
Stack Temp. In 0K
Velocity m/s
Stack Height in m
Fuel Used
SPM mg/Nm3
SO2
PPM NOX
PPM
01 Boiler 452 9.4 32 Coal 139 72.4 25.7
02 Process Stack-1
329 6.5 15 - NH3 = 127.4 mg/Nm3
03 Process Stack-2
329 6.9 15 - NH3 =116.0 mg/Nm3
Table 2.9(b)
Estimated emission from new stacks/vents
Sr. No.
Stack attached to
Stack Temp. In 0K
Velocity m/s
Stack Height in m
Fuel Used
SPM mg/Nm3
SO2
PPM NOX
PPM
01 Boiler-2 450 10 32 Lignite /Coal
125 75 25
02 Thermic Fluid Heater
440 10 32 Lignite /Coal
125 75 25
03 Process Stack-3
325 6.5 15 - NH3 = 125 mg/Nm3
04 Chlorination & Dumping Vessel
350 5.5 18
- HCl = 25 mg/Nm3
Cl2 = 10 mg/Nm3
05 Spin Flash Dryers 1
410 6.0 11 - PM =40 mg/Nm3
06 Spin Flash Dryers 2
410 6.0 11 - PM =40 mg/Nm3
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-39
Table 2.10
Result of Work place monitoring
Sr. No.
Pollutant Location Results μg/m3
14/02/11
Results μg/m3
16/02/11
Results μg/m3
18/02/11 1 RPM Packing area 229
208 211
2 RPM Raw Material Storage Yard
163
179 190
3 RPM Coal handling area
218
216 229
4
SO2 Nr. Boiler House 23 32 31
5
HC Nr. Rotary Vacuum Dryer
32 29 34
6
HC Nr. Solvent Storage tanks
18 32 27
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-40
Table 2.11
Details of Solid / Hazardous waste
Quantity
Sr. No.
Name of Waste
Existing Proposed Total
Disposal facility
1. Chemical Sludge
335
MT/Month
50
MT/Month
385
MT/Month
TSDF Site-Naroda,
Ahmedabad
2. Spent Oil 0.2 MT/ Annum
0.3 MT/ Annum
0.5 MT/ Annum
Collection, Storage,
Transportation, Disposal by selling to
Registered recycler
3. Discarded containers of Hazardous
Raw material
Liner
360000
Nos/ Annum
5.0 Mt/Month
360000
Nos/ Annum
5.0
Mt/Month
360000
Nos/Annum
10.0
Mt/Month
Collection, Storage,
Decontamination, Transportation,
Disposal by selling to
authorized recycler
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-41
Table 2.12
Result of Solid/Hazardous Waste Analysis
Sr. No. Parameters Unit Result
AS IS BASIS
1. Moisture (%) - 25.2
2. Ether Soluble gm/Kg 0.1
3. TIS at 5500 C gm/Kg 766.1
WATER LEACHATE (10% SOLUTION IN DISTILLED WATER)
1. pH pH Unit 7.8
2. Total Alkalinity gm/Kg 14.0
3. COD gm/Kg 4.4
4. Sulphate gm/Kg 46.4
5. Chloride gm/Kg 22.9
ACID LEACHATE
1. Iron gm/Kg 31.9
2. Total Chromium gm/Kg BDL
3. Copper gm/Kg 14.3
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-42
Table 2.13
Noise survey
Sr. No.
Location Noise Level In dBA
Date:14/02/11
Noise Level In dBA
Date:16/02/11
Noise Level In dBA
Date: 18/02/11 1. Inside Plant Building 77.5 76.7 75.9 2. Nr. Drier 69.7 77.5 68.2 3. Nr. Process Vessel 73.6 82.0 72.1 4. Nr. Elect. Panel Room. 69.3 77.2 68.0 5. Nr. Boiler Room 77.4 76.6 75.8
6. Nr. Rotary vacuum Dryer
78.0 72.4 73.8
7. Nr. Spin Flash Dryer 76.2 75.2 72.9
8. Nr. Scrubbering area 73.6 82.0 72.1
9. Inside Lab 68.2 75.9 66.7
10. Nr. Main Gate 61.1 60.6 59.4
11. ETP 68.7 76.5 67.3
12. RM Storage yard 62.7 59.4 66.4
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-43
Figure: -2.1(a)
Water Balance Diagram (Existing)
3.0Loss
SteamEv. Loss 6 67
1000
Raw water 2188 kl/d
Domestic25
Process1127
Utilities941
Greenbelt15
Process 982
Scrubber 145
Boiler191
Cooling Tower
525
Reject225
Blow Down 20
Blid off 157
ETP Collection Tank1482 kl/d
Liq. Ammonia(12-15%)
145
Sock pit 22
Washing80
Steam Addition
1043
SFDEv. Loss
43
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-44
Figure-2.1(b) after expansion
Water Balance Diagram
*(G + V) means effluent generates from Green-7 and Pigment Violet, which directly taken in to ETP.
Raw water 2105 kl/day
Greenbelt 180 kl/day
Process 1837 kl/day
Utilities 1775 kl/day
Process 2497 kl/day
Product water 1245 kl/day
Boiler 462 kl/day
Cooling 123 kl/day
Scrubber 225 kl/day
Process 1996 kl/day
Water treatment with RO
1926 kl/day
Ammonium Sulphate & Ammonia carbonate/ HCl-3 / NoCl-4 / AlCl3
ETP 501+100 + 23+20+530=1174
kl/day
Reject 530
EV Loss 70
(G + V) 501 kl/day
Blow down 23
Blow off 20
1350
660
Steam 240 m3/day
1771 Steam loss-15
MEE 526m3/day
Solid-10 m3/day
E.V loss-29 m3/day Recover
487 m3/day
(G + V)* -501 kl/day
Soak pit
Washing 100
kl/day
Domestic 50 kl/day
45
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-45
Figure-2.1(c) Water Balance Diagram (Recycling)
CPC blue guide Acidic ML
216 m3 /day
CPC blue guide Acidic wash 450 m3 /day
Alkaline Treatment
630 m3 /day
Beta Blue WW 630 m3/day
Copper Treatment & Stripping
Collection & Equalization
1296 m3 /day
PSF-ASF-UF 630 m3 /day
Back Wash 50 m3/day
Primary Treatment
Bioreactor
Reverse Osmosis
1296 m3/day
Permeate 910 m3 /day
Solid waste 10 m3 /day
RO 580 m3/day
RO Reject 140 m3 /day
Disposal to MEE 140 m3 /day
Reject Water 386 m3 /day
Reuse Water 440 m3 /day
Water Balance Diagram (Recycling)
580
MEE 526 m3 /day
Loss 29 m3 /day
Recovered 487 m3 /day
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-46
Acidic stream
1A
1B
2
2
2
FCS 3
5 A
General Stream 5 B
5 C
FLC 6
7A
8A
8B
9
9B
10 A
12 11
Final disposal
13
10 B
Fig.2.2 Line Diagram of ETP for Asahi Songwon Colors Ltd.
Ammonia Stripping Tower 4
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 2-47
Figure 2.3
Site plan/plan layout
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-1
CHAPTER-3
Description of the Environment 3.1 Introduction
Any development activities related to industrial sector are expected
to cause impacts on environmental quality in surrounding area of the
respective project locations.
However, the assessment of environmental impacts from proposed
project at a specific location needs a datum on which the evaluation
can be done. It is necessary to collect data about different
environmental attributes that are being affected by the operation of
project activity, which in turn defines an existing environmental
quality to serve as the datum.
Baseline data requirement is also necessary to identify
environmentally significant issues as well as to enumerate the critical
environmental changes that are likely to occur due to proposed
project activity.
Here, in this chapter the baseline status for the surrounding
environment has been determined considering the following
environmental attributes and as per MoEF guidance in approved
Terms of Reference (TORs).
(i) Air Environment
(II) Water Environment
(III) Noise Environment
(IV) Soil Environment
(V) Socio Economic and Land use
(VI) Ecology
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-2
3.2 Air Environment
The impact on air environment would depend on identification of
sources of air pollution from various process operations; the nature
of pollutants and their quantities likely to be discharged to the
atmosphere; and the baseline data on air quality.
The baseline data on air quality and micrometeorological conditions
of the area surrounding the project site have been generated through
an appropriately designed network for and monitoring of ambient air
quality (AAQ) within the zone of likely impacts.
3.2.1 Design of Network for Ambient Air Quality Monitoring Stations
The following criteria were taken into account while designing the
ambient air quality-monitoring network:
Topography/Terrain of the study area
Populated areas within the region
Prediction of maximum concentrations and distances of their likely
Occurrence under prevailing meteorological conditions
Representation of regional background
Representation of valid cross sectional distribution in downwind
Direction
Availability of infrastructure facilities like electricity, approach,
safety of equipments etc.
3.2.2 Reconnaissance
Reconnaissance survey was undertaken to establish the baseline
status of air environment in the study region. The prime objective of
the AAQ survey, within 5 km radial study area around the industry at
Survey No. 429 to 432, Village: Dudhwada, Taluka: Padra, Dist:
Vadodara, Gujarat. The terrain of the study area surrounding the
industries is plain. Six Ambient Air Quality Monitoring (AAQM)
stations (One is fixed at Industrial location and five stations were
located in villages in the study area and were change based on the
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-3
wind direction. The locations (relative directions and distances) of
these stations with respect to project site are given in Figure 3.6.
The Respirable Particulate Matter (PM10), Sulphur Dioxide (SO2), and
Oxides of Nitrogen (NOx), were identified as significant parameters
for ambient air quality monitoring, particularly because these are
likely to be emitted from the industry and for which ambient air
quality standards are prescribed. Hydrocarbon (HC) and VOC were
sampled and analyze as grab near by industry.
The micrometeorological data on wind speed; wind direction,
temperature and relative humidity were collected through a weather
monitoring station for the study period. The baseline status of air
quality is monitored within the study area i.e. 5 Km radial distance
from project site.
3.2.3 Micrometeorology of the Area
The micrometeorological conditions at the project site will regulate
the transport and diffusion of air pollutants released into the
atmosphere. The principle meteorological variables are horizontal
convective transport (average wind speed and direction), vertical
convective transport (atmospheric stability, mixing height) and
topography of the area. The data on surface meteorological
parameters (wind speed and direction) in the study area were
collected from December-2010 to February-2011 using weather
monitoring station placed at location of Industry. The sensors of this
equipment were kept at about 10 m above ground level with free
exposure to the atmosphere all through the study period in winter
season.
Wind rose
The 24 hour wind rose was prepared using the data on wind direction
and speed collected for December-2010 to February-2011 in the
study area. The same, as depicted in Figure 3.7, shows the
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-4
predominant wind directions are N, NNW, NNE, NW & ESE implying
that winds come from these directions for most of the time during
the period. The wind speed class 1-5 kmph occurred for 32.06 % and
6-10 kmph is 18.47 %, 11-15 kmph is 13.88 %, 16-20 is 6.22 % and
more than 20 kmph is observed around 3.19 % of the time during
study period. The calm condition (below 1 kmph) observed is 26.18
% of the time. The local prevailing wind pattern during the study
period is in conformity with the climatologically normal of the region.
The average wind speed recorded is 5.7 kmph during the study
period (December-2010 to February-2011).
Temperature
During the study period the maximum and minimum temperatures
recorded at project site were recorded as 33.8OC and 12.7OC
respectively.
Relative Humidity
At project site during study period, the maximum relative humidity
was recorded as 73.1% and minimum as 15.3%.
For the study area, the year can be broadly divided into following seasons:
Winter Season (November to February)
Summer Season (March to May)
Monsoon Season (June to September)
Transition Month (October)
Winter is mostly cool and pleasant season. Sky is clear with stray
high clouds, winds blowing mainly towards South – West direction.
December and January are the coolest months. April and May are the
hottest months.
The monsoon sets in by about the second week of June. South-west
winds blow from May and last till the end of September. About 95%
of the annual rainfall in the area occurs during the months of June to
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-5
September. The normal annual rainfall in this region is 850 mm to
900 mm.
3.2.4 Ambient Air Quality Survey
The ambient air quality monitoring was carried out at 6 AAQM
locations, with a frequency of twice a week continuously for three
months i.e. December-2010 to February-2011, to assess the existing
sub-regional air quality status. The Respirable Dust Sampler along
with the analytical methods prescribed by CPCB was used for
carrying out air quality monitoring. At all these sampling locations;
PM10, SO2, and NOx were monitored on 24-hourly basis and grab
sample were collected and analyzed for the HC and VOC to enable
the comparison with ambient air quality standards prescribed by
CPCB. The data on concentrations of various pollutants were
processed for different statistical parameters like arithmetic mean,
standard deviation, minimum and maximum concentration and 98
percentile values.
3.2.5 Baseline Status
The existing baseline levels with respect to PM10, SO2, and NOx are
presented in Tables 3.3 to 3.5 along with statistical analysis;
represent the cross sectional distribution of baseline air quality status
of the study region and graphical representations for PM10, SO2 and
NOX are given in Figure 3.2 to 3.4.
Respirable Suspended Particulate Matter (PM10)
The average and 98th percentile value of 24-hourly PM10 values at all
the locations ranged between and 60-73 μg/m3 and 64-79 μg/m3
respectively, meeting the CPCB standards of 100 μg/m3. The 24-
hourly concentration values show that the values are well within the
prescribed limit.
Sulphur Dioxide (SO2)
The average and 98th percentile value of 24-hourly SO2 at all the
locations ranged between 15-20 μg/m3 and 17-22 μg/m3 respectively,
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-6
which are well within the stipulated standards of 80 μg/m3 for
residential areas.
Oxides of Nitrogen (NOx)
The average and 98th percentile value of 24-hourly NOx at all the
locations ranged between 14-21 μg/m3 and 17-25 μg/m3
respectively, which are much lower than the standards of 80 μg/m3,
stipulated by CPCB for industrial areas.
3.3 WATER ENVIRONMENT
Water Environment of an area is broadly classified into following categories
1. Surface waters: Rivers, drains, canal, ponds etc.
2. Ground water: Accumulation in deeper strata of ground
The only source of recharging for both surface and groundwater
source is from precipitation (rainfall).
3.3.1 Water Quality
Collected water samples were analyzed for various desirable
characteristics of drinking water. Results of Ground Water Quality in
the Study Area are shown in Table No. 3.8. Sampling locations are
shown in Figure 3.8.
Ground water quality
Color: All the six samples were found colorless and meeting desirable norms.
pH: All the samples were meet the desirable standards (pH ranges from 7.1 to 7.6).
Total Dissolved Solids (TDS): TDS in samples ranges from 857
mg/l (Gametha) to 1164 mg/l (Kahanva). All the samples meet the
permissible limit of 2000 mg/l (If alternate sources of potable water
are not available).
Calcium: Calcium contents in the water ranges from 38 mg/l
(Gametha) to 54 mg/l (Project Site), all the samples meet the
desirable limit of 75 mg/l.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-7
Magnesium: Magnesium content in the water ranges from 24 mg/l
(Karkhadi) to 47 mg/l (Tithor). All samples meet the permissible limit
of 100 mg/l. (If alternate sources of potable water are not available).
Sulfate: Sulfate content in the water ranges from 41 mg/l
(Karkhadi) to 63 mg/l (Kahanva). All samples meet the desirable
limit of 200 mg/l.
Total Alkalinity: Total alkalinity in the water samples ranges from
219 mg/l (Karkhadi) to 314 mg/l (Project Site). All the samples are
within the permissible limit of drinking water 600 mg/l for drinking
water (if alternate source of potable water is not available).
Heavy metals like copper, cadmium, lead, chromium, nickel and
zinc are well below to prescribe limit in all samples.
Other Parameters: Potassium (ranges from 31 mg/l to 44 mg/l),
Sodium (ranges from 180 mg/l to 265 mg/l), Chloride (ranges from
267 mg/l to 408 mg/l), and Iron (ranges from 0.16 mg/l to 0.29
mg/l). Samples were also analyzed for Phenolic compound (less than
0.001 mg/l in all samples).
Conclusions: Ground water samples from villages meets the
permissible limit set by the authority (BIS). Indian standard
specification for drinking water is given in Table 3.9.
3.4 NOISE ENVIRONMENT
3.4.1 Introduction
Noise can be defined as an unwanted sound. It interferes with speech
and hearing and is intense enough to damage hearing or is otherwise
annoying. The definition of noise as unwanted sound implies that it
has an adverse effect on human beings and their environment. Noise
can also disturb natural wildlife and ecological system.
Sound is mechanical energy from a vibrating surface, transmitted by
cyclic series of compression and rarefaction of molecules of the
materials through which it passes. Sound can be transmitted through
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-8
gases, liquids and solids. The number of compressions and
rarefaction’s of the air molecules in the unit of time is described as its
frequency. Frequency is expressed in hertz (Hz), which is the same
as the number of cycles per second.
3.4.2 Methodology
To understand the noise environment in the study area, a survey was
conducted using Sound Level Meter at each of the locations (Figure
3.9).
3.4.3 Ambient Air Quality Standards in Respect of Noise
Ministry of Environment and Forest has notified the ambient
standards in respect of noise in Gazette of India on February 14,
2000. Table 3.11 gives these standards in respect of noise.
3.4.4 Day-Time and Night-Time Noise Levels
Considering the site specificity with respect to settlements, silent
zones (like hospitals, schools) Heavy traffic movements (like state
highways) and the source. Seven locations are selected for Noise
Survey in the day-and night time during the study period. Table
3.10 gives Lday, Lnight noise levels for all locations.
3.4.5 Ambient Noise Levels in Study Area
The Leq values of noise levels during day-time varied between 53.5
to 61.5 dB(A). Highest Leq daytime value was recorded Nr. project
site, However it is less than the prescribed limit for the residential
(75 dB(A)). The Leq values of noise levels during night time varied
between 39.5 to 57.4 dB(A). Highest Leq night time value was
recorded Nr. Project Site which is less than prescribed limit (70 dB
(A)).
3.4.6 Conclusions
The hourly Leq noise levels recorded at various locations in the study
area show considerable fluctuations because of changes in traffic
movement, commercial and industrial activities in the study area.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-9
Though the noise levels found within the prescribed limit both during
day time as well as night time, however the noise level (Leq daytime
as well as Leq night time) found at all locations within limit.
3.5 SOILS
3.5.1 Introduction
Soils may be defined as a thin layer of earth’s crust that serves as a
natural medium for the growth of plants. It is the unconsolidated
mineral matter that has been subjected to and influenced by natural
as well as anthropogenic factors. Soil serves as a reservoir of
nutrients for plants and crops and also provides mechanical
anchorage and favorable tilth.
The study area has primarily Black type of soil. The soils of this type
basically originate from alluvium rocks. According to texture
classification, this belongs to Clay & Clay slit category. This type of
soil has moderate permeability and water retention capacity.
3.5.2 Soil Characteristics
Samples of soils were collected from five locations viz. Project Site,
Village Dudhvada, Village Gametha, Village Karkhadi & Village
Kahanva during the study period and these locations are shown in
Figure 3.10.
The values of important physical and chemical parameters of these
soil samples are given in Table 3.12. From the tabulated values, the
following conclusions can be drawn about the physical and chemical
characteristics of these soil samples.
3.5.3 Findings
Physical Parameters
Particle Size: Particle sizes of the different constituents (clay, silt,
and sand) control the porosity and water holding characteristic of the
soil. Clay (size <0.002 mm) amount in the soil samples ranges from
21% to 29%; Silt (size 0.002 to 0.075 mm) in the soil samples is
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-10
30% to 35%; Sand (size 0.075 to 0.475 mm) in the soil samples is
21% to 28% and Gravel (size >4.75 mm) in the soil samples ranges
from 14% to 18%. Analysis shows it is clay loamy soil with moderate
water holding capacity.
Porosity: Porosity is a measure of space in between soil particles
caused by structural conditions and determined under identical
conditions. Porosity of soil samples of the study area ranges from
40.1 to 42.5%.
Water Holding Capacity (WHC): Water holding capacity (WHC) of
soil samples of the study area ranges between 39 to 46% and these
being clay loamy soils are capable of retaining sufficient water during
irrigation for facilitating the plant growth.
Bulk Density: Bulk Density of soils in the study area is found to be
in the range from 1.42 to 1.48 g/cm3. Bulk density is of greater
importance for characterizing the physical behavior of soils. Generally
soils with low bulk density have favorable physical conditions
(porosity and permeability) whereas those with high bulk density
exhibit poor physical conditions.
Chemical Parameters
pH: pH was determined by taking 1:5 ratio of soil and distilled water.
pH of soils in the study area is found to be in the range of 7.4 to 7.9.
The soils of the study area are neutral in nature.
Chloride: Chloride content in soils of the study area is found to be in
the range of 76 to 110 mg/kg.
Calcium: The soluble calcium as CaCO3 in soil samples is found to be
in the range 79 to 109 mg/kg.
Magnesium: Magnesium content in soil samples of the study area
ranges from 43 to 47 mg/kg.
Available Phosphorus: Available Phosphorus content in soil
samples of the study area ranges from 110 to 127 mg/kg.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-11
Available Nitrogen content in soil samples of the study area is
found to be in the range from 149 to 179 mg/mg.
Potassium: Potassium content in soil samples of the study area is
found to be in the range from 50 to 90 mg/kg.
Sodium: Sodium content in soil samples of the study area is found
to be in the range from 72 to 104 mg/kg.
This type of soil is good for agricultural uses.
3.6 SOCIO ECONOMIC AND LAND USE
3.6.1 Land use pattern and infrastructure
The land use pattern indicates the manner in which different parts of
land in an area is being utilized or non - utilized. It is an important
indicator of environmental health; human activity and degree of inter
play between them. Even though the soil quality, water availability
and climate have strong influence on agriculture and vegetation, the
human activity may alter the natural environment to a large extent
to suit human needs. Unnatural land use often triggers rapid
environmental deterioration and disturbs ecological balance.
In census records, major land use classifications are; cultivable area,
cultivable wasteland and area not available for cultivation. Cultivable
land is further classified as: irrigated and unirrigated. Area not
available for cultivation includes lands put to non-agriculture uses as
well as barren and uncultivable lands.
The main land use in urban area is for dwellings, infrastructure and
related activities. These are primarily based on 2001 Census are
presented in Table 3.13.
3.6.2 Demographic and Socio-Economic Environment: Rural
The demographic and socio-economic details of the study area are
discussed below. Data on number of households, population as well
as literacy and employment pattern in the study area have been
presented in Table-3.15. The employment pattern in the area is an
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-12
indicator of number of persons employed in various sectors. It also
indicates the various categories of employment flourishing in the
area. Moreover, data on amenities (educational, medical,
communication, etc. facilities) available within the zone of influence
has also been provided.
Living Standard and Infrastructure
In India it is not possible to setup a common standard of living
because of wide variations in terms of income, economic conditions,
social custom, employment opportunity, pattern of spending, etc.
However, availability of amenities like education, medical, water
supply, communication, road network, electricity, etc. significantly
reflects the level of development of the area. Information on
available amenities in the study area has been extracted from census
record of 2001.
Educational Facilities
As per 2001 census, in the study area of 16 villages, the total
numbers of educational institutions in various categories are 79. Out
of which 44 are primary schools, 9 are high schools, 4 are Pre
University/ higher secondary school and 22 are Adult Literacy Class.
Medical Facilities
In the study area, consisting of 16 villages as per 2001 census, out
of which 13 have Registered Private practitioners, 19 community
health workers, 5 primary health sub center, 6 family planning
centers, 6 dispensaries and 4 maternity homes.
Drinking Water Supply
All the villages in the study area have two or more sources of
drinking water. 16 villages of study zone have tap water supply in
addition to well (almost all), tanks are other source of drinking water.
Communication and Transport
The main mode of public transport available in the study area is by
bus service. All the villages are connected with state transport bus
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-13
services. 2 villages have approach to railway station as western
railway meter gauge line is passing nearby and also has stations.
Majority of villages in the study area is connected with pucca road.
Post and Telegraph
As per 2001 census record out of 16 villages in study area, all
villages have post office facility at doorstep and have telephone
facility in the village.
Power Supply
As per 2001 census record out of 16 villages in study area, all the
villages are getting power supply for all purposes.
3.6.3 Demographic and Socio-Economic:
Since existing Asahi plant at Survey Nos. 429 to 432, Village:
Dudhwada, Taluka: Padra, Dist.: Vadodara, Gujarat. The main land
use in urban area is for dwelling, infrastructure and related activities.
To assess the demogragraphic and socio-economic profile of this
area, parameters like population, literacy, employment pattern, etc.
have been studied. Data pertaining to above parameters are
presented in Table No. 3.15.
3.7 ECOLOGY
3.7.1 Terrestrial Ecology (Flora)
Some plantation of Limdo, Baval, Banana etc are found in the study
area. Forest occurring in the area is not under the category of
reserved forest, but is under control of revenue department. The
structure and type of vegetation depends on climatic conditions and
physiography of an area. Climate of the study area is arid to semi
arid and suited for the growth of selected variety of vegetation. The
tree spices found in the study area as well as in the forest area are
presented in Table No. 3.17.
3.7.2 Terrestrial Ecology (Fauna)
The area is devoid of thick vegetation; no significant wild life habited
is reported. There is no National Park in the study area. The common
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-14
species of fauna in the study area is tabulated in the Table No.
3.18.
3.7.3 Common Crop Plants
Common cultivated crop plants in the study area include: Rabi
season- wheat, bajri, Sugarcane, vegetables and Kharif- Vegetables,
cotton etc are some of the crop plants grown in the fields.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-15
Table 3.1: Ambient Air Quality Monitoring Locations
(Period of Monitoring: December-10 to February-11)
Sr. No.
Sampling Location
Direction w.r.t. center of Industry
Distance
1 Project Site - 0.0
2 Dudhvada W 1.8
3 Karakhadi NNW (Down wind direction)
2.1
4 Chokari NNE (Down wind direction)
4.6
5 Tithor NW (Down wind direction)
4.3
6 Gametha S (Upwind direction) 2.8
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-16
Table 3.2: Ambient Air Quality Status
(Period: December-10 to February-11)
PM10 SO2 NOx Sr. No.
Sampling Location
Average (Min-Max)
1 Project Site 73 (61-79)
20 (17-22)
21 (19-26)
2 Dudhvada 65 (56-72)
16 (13-17)
15 (13-17)
3 Karakhadi 69 (66-75)
17 (15-18)
17 (15-18)
4 Chokari 63 (61-69)
16 (13-18)
14 (12-17)
5 Tithor 67 (64-73)
15 (14-17)
16 (15-17)
6 Gametha 60 (55-64)
15 (12-18)
15 (13-19)
Figure 3.1 Graphical representation of Ambient Air quality
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-17
Table 3.3: Ambient Air Quality Status (PM10)
(Period: December-10 to February-11)
Average –24 Hours Unit - μg/m3
Station Name
Max Min 98 Percentile
75 Percentile
50 Percentile
25 percentile
Avg. SD
Project Site 79 61 79 77 72 71 73 5
Dudhvada 72 56 71 67 66 66 65 5
Karakhadi 75 66 74 69 68 67 69 3
Chokari 69 61 68 63 63 62 63 2
Tithor 73 64 72 67 66 65 67 3
Gametha 64 55 64 63 60 58 60 3
Figure 3.2 Graphical Representations for PM10
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-18
Table 3.4: Ambient Air Quality Status (SO2)
(Period: December-10 to February-11)
Average –24 Hours Unit - μg/m3
Station Name
Max Min 98 Percentile
75 Percentile
50 Percentile
25 percentile
Avg. SD
Project Site 22 17 22 21 20 19 20 1
Dudhvada 17 13 17 17 16 15 16 1
Karakhadi 18 15 18 17 17 17 17 1
Chokari 18 13 18 16 16 15 16 1
Tithor 17 14 17 16 15 15 15 1
Gametha 18 12 18 16 15 14 15 2
Figure 3.3 Graphical Representation for SO2
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-19
Table 3.5: Ambient Air Quality Status (NOx)
(Period: December-10 to February-11)
Average –24 Hours Unit - μg/m3
Station Name
Max Min 98 Percentile
75 Percentile
50 Percentile
25 percentile
Avg. SD
Project Site 26 19 25 23 21 20 21 2
Dudhvada 17 13 17 16 15 15 15 1
Karakhadi 18 15 18 17 17 16 17 1
Chokari 17 12 17 15 14 14 14 1
Tithor 17 15 17 17 16 16 16 1
Gametha 19 13 18 16 15 15 15 2
Figure 3.4 Graphical Representation for NOx
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-20
Table 3.6: Hydrocarbon & VOCs in mg/m3
(Period: December-10 to February-11)
(Grab Sample)
Sr. No.
Station Name Hydro
Carbon
VOCs
(Non Methane)
1 Project Site 52 32
2 Dudhvada 46 29
3 Karakhadi 38 24
4 Chokari 32 20
5 Tithor 35 25
6 Gametha 29 21
Figure 3.5 Graphical Representations for HC & VOCs
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-21
Table 3.7: National Ambient Air Quality Standards
(EP, 7th amendment rules-2009)
Concentration in ambient air Pollutants Time-weighted average Industrial,
Residential, Rural and
others area
Ecologically Sensitive area (Notified by
Central Government)
Method of Measurement
Annual Average* 50 20 Sulphur Dioxide (SO2) µg/m3 24 hours** 80 80
Improved west and Gaeke
Ultraviolet fluorescence
Annual Average* 40 30 Oxides of Nitrogen as (NO2) µg/m3
24 hours** 80 80 Modified Jacob &Hochheiser
(Na-Arsenate) Chemiluminescence
Annual Average* 60 60 Particulate Matter(Size less than 10 µm or PM10, µg/m3
24 hours** 100 100 Gravimetric TOEM Beta attenuation
Annual Average* 40 40 Particulate Matter(Size less than 2.5 µm or PM2.5, µg/m3
24 hours** 60 60 Gravimetric TOEM Beta attenuation
8 hours ** 100 100 Ozone (O3) µg/m3 1hours** 180 180
UV photometric Chemiluminescence
Chemical Method
Annual Average* 0.50 0.50 Lead (Pb) µg/m3 24 hours** 1.0 1.0
AAS/ICP method after sampling on EPM 2000 or equivalent filter paper
ED-XRF using Teflon filter
8 hours** 02 02 Carbon Monoxide (CO) mg/m3
1 hour** 04 04 Non Dispersive Infra Red (NDIR) spectroscopy
Annual Average* 100 100 Ammonia(NH3)
µg/m3
24 hours** 400 400 Chemiluminescence
Indophenol Blue Method
Benzene (C6H6) µg/m3
Annual* 05 05 Gas chromatography based continuous analyzer
Adsorption and desorption followed by GC analysis
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-22
Benzo(a)Pyrine (BaP)-particulate phase only, µg/m3
Annual* 01 01 Solvent extraction followed by HPLC/GC analysis
Arsenic (As), µg/m3
Annual* 06 06 AAS/ICP method after sampling on EPM 2000 or equivalent filter paper
Nickel (Ni) µg/m3
Annual* 20 20 AAS/ICP method after sampling on EPM 2000 or equivalent filter paper
*
Annual Arithmetic mean of minimum 104 measurements in a year taken twice a week 24 hourly at uniform interval.
**
24 hourly/8 hourly or 01 hourly values, as applicable, shall be complied with 98% of the time in a year. 2% of the time the time, they may exceed the limits but not two consecutive days of monitoring.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-23
Table 3.8: Results of Ground Water Quality in the Study Area
(Date of Sampling: 12/01/2011 to 14/01/2011)
CONCENTRATION Parameters Unit
Project Site
Dudhvada Gametha Karkhadi Kahanva Tithor
pH pH Unit 7.6 7.1 7.4 7.3 7.2 7.4 Color Co-Pt
Unit Color Less
Color Less
Color Less
Color Less
Color Less
Color Less
Temperature 0C 29 28 25 27 25 26 Conductivity Micro
mhos/cm 1502 1263 1210 1345 1672 1605
Turbidity NTU 6.2 6.1 5.5 5.6 7.1 7.4 TDS mg/L 1054 891 857 924 1164 1125 Total Hardness as CaCO3
mg/L 311 240 207 208 281 302
Total Alkalinity mg/L 314 264 247 219 297 281 Sodium as Na+ mg/L 226 180 197 215 265 246 Potassium K+ mg/L 44 35 31 35 44 41 Calcium Ca+2
mg/L 54 50 38 44 41 44 Magnesium Mg+2 mg/L 43 28 27 24 44 47 Chlorides as Cl- mg/L 322 267 292 322 408 400 Sulfates as SO4
-2 mg/L 58 55 44 41 63 59 Fluoride F- mg/L 0.66 0.52 0.49 0.46 0.42 0.43 Nitrates as NO3
-3 mg/L 29 30 26 31 27 25 Phenol as C6H5OH mg/L <0.001 <0.001 <0.001 <0.001 <0.001 <0.00
1 Cyanide as CN- mg/L <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 Arsenic as As mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Cadmium as Cd mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Copper as Cu mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Lead as Pb mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Manganese as Mn mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Iron as Fe mg/L 0.29 0.17 0.19 0.16 0.27 0.27 Total Chromium mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Zinc as Zn mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 % Sodium -- 57 57.4 63.1 64.8 62.9 60.1
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-24
Table 3.9: Indian Standard Specification for Drinking Water S.
No. Parameters Desirable Limit Permissible Limit
in the Absence of Alternate Source
I Essential Characteristics 1. Colour, Hazen Units, Max. 5 25 2. Odour Unobjectionable - 3. Taste Agreeable - 4. Turbidity, NTU, Max. 5 10 5. pH value 6.5-8.5 No Relaxation 6. Total Hardness (as CaCO3) mg/l, Max. 300 600 7. Iron (as Fe) mg/ l, Max. 0.3 1.0 8. Chlorides (as Cl) mg/l, Max. 250 1000 9. Residual Free Chlorine, mg/l, Min. 0.2* - II Desirable Characteristics 10. Dissolved Solids, mg/l, Max. 500 2000 11. Alkalinity (as CaCO3), mg/l, Max. 200 600 12. Sulphate (as SO4) mg/l, Max. 200 400** 13. Nitrate (as NO3) 45 100 14. Fluoride (as F) mg/l, Max. 1.0 1.5 15. Calcium (as Ca) mg/l, Max. 75 200 16. Magnesium (as Mg) mg/l, Max. 30 100 17. Copper (as Cu) mg/l, Max. 0.05 1.5 18. Manganese (as Mn) mg/l, Max. 0.1 0.3 19. Mercury (as Hg) mg/l, Max. 0.001 No Relaxation 20. Cadmium (as Cd) mg/l, Max. 0.01 No Relaxation 21. Selenium (as Se) mg/l, Max. 0.01 No Relaxation 22. Arsenic (As As) mg/l, Max. 0.05 No Relaxation 23. Lead (as Pb) mg/l, Max. 0.05 No Relaxation 24. Zinc (as Zn) mg/l, Max. 5 15 25. Aluminium (as Al) mg/l, Max. 0.03 0.2 26. Boron (as B) mg/l, Max. 1 5 27. Chromium (as Cr) mg/l, Max. 0.05 No Relaxation 28. Cyanide (as CN) mg/l, Max. 0.05 No Relaxation 29. Phenolic Compounds (as C6H5OH) mg/l,
Max. 0.001 0.002
30. Anionic Detergents (as MBAS) mg/l, Max. mg/l, Max.
0.2 1.0
31. Mineral Oil mg/l, Max. 0.01 0.03 32. Pesticides Absent 0.001 33. Polynuclear Aromatic Hydrocarbons (as
PAH) g/l, Max. - -
34. Radioactive Materials a. Alpha Emitters, Bq/I, Max. b. Beta Emitters, Bq/I, Max
- -
0.1 1
Note: * Applicable only when water is chlorinated ** Provided magnesium (as Mg) does not exceed 30 mg/l Source: IS 10500: 1991, Fourth Reprint, July 1999
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-25
Table 3.10: Ambient Noise Levels in the Study Area
Date of Monitoring: 12/01/2011 to 14/01/2011
Sr. No. Location Ld/Ln Noise Level
Ld 61.5 1 Project Site
Ln 57.4
Ld 53.5 2 Primary School Dudhvada
Ln 40.4
Ld 57.1 3 Temple Gametha
Ln 41.1
Ld 60.6 4 Bus stop Karkhadi
Ln 41.4
Ld 56.5 5 Post office, Kahanva
Ln 39.5
Ld 60.2 6 Nr. ECP Canal
Ln 49.8
Ld 56.3 7 Temple Dudhvada
Ln 51.1
Table 3.11: Ambient Air Quality Standards with respect to Noise
Limits Leq, dB(A) Category of Area
Day Time Night Time
Industrial 75 70
Commercial 65 55
Residential 55 45
Silence 50 40
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-26
Table 3.12: Soil Analysis of Study area
Date of Sampling: 12/01/2011 to 14/01/2011
S. No.
Parameters Unit Project Site
Dudhvada Gametha Karkhadi Kahanva
1. pH (5%)Solution 7.9 7.5 7.4 7.6 7.8 2. Loss of Ignition % 7.5 6.1 6.2 5.8 5.6
Particle Size Clay (< 0.002 mm)
% 26 29 21 28 29
Silt (0.002 to 0.075mm)
% 32 32 35 30 30
Sand (0.075-0.475mm
% 28 21 28 26 24
3.
gravel (size > 4.75mm)
% 14 18 16 16 17
4. Water Holding Capacity
% 46 42 44 39 43
5. Permeability cm/hr 3.21 3.27 3.29 3.22 3.25 6. Bulk Density g/cm3 1.42 1.48 1.43 1.42 1.45 7. Porosity % 42.5 40.1 42.1 42.5 41.3 8. Sodium
Absorption Ratio Meq/
100gm 1.75 2.11 1.58 1.84 2.13
9. Sodium mg/kg 81 104 72 83 97 10. Potassium mg/kg 50 52 65 54 90 11. Calcium mg/kg 85 109 86 82 79 12. Magnesium mg/kg 46 45 43 43 47 13. Chlorides mg/kg 110 76 84 94 82 14. Sulphates mg/kg 68 52 70 59 74 15. Organic Matter mg/kg 1.72 1.46 1.39 1.46 1.35 16. Available
Nitrogen mg/kg 179 162 149 163 159
17. Available Phosphorus
mg/kg 110 115 112 120 127
18. Iron mg/kg 1.49 1.32 1.27 1.32 1.39
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-27
Table 3.13: Land Use Pattern
Sr. No.
Name of Village
Total Area of the Village
(ha)
Irrigated by source
(ha)
Unirrigated (ha)
Culturable waste (ha)
Area not available for
cultivation (ha) 1 Karkhadi 1659.50 144.47 833.23 105.53 576.27
2 Kareli 2151.72 275.00 962.52 15.97 1098.23
3 Dudhwada 614.48 892.44 111.55 15.86 40.585
4 Gametha 343.14 255.14 52.01 1.48 34.51
5 Kahanva 972.97 390.00 490.06 8.36 84.55
6 Chokari 1380.11 175.00 346.09 144.58 714.44
7 Tihor 2462.04 25.29 549.29 9.72 1877.74
8 Majatan 456.65 25.00 380.19 16.21 35.25
9 Chitral 371.70 190.05 136.64 5.19 39.82
10 Vishrampura 234.91 153.81 56.67 8.78 15.65
11 Muval 781.07 278.28 405.21 34.89 62.69
12 Piludara 720.62 40.00 596.75 8.04 75.83
13 Masar 1361.55 620.11 593.18 26.06 122.09
14 Kural 561.66 92.14 404.68 5.49 59.35
15 Gavasad 946.86 150.00 686.38 12.17 98.31
16 Pindapa 689.92 -- 587.40 32.30 70.22
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-28
Table 3.14: Present land use based on satellite imagery
Sr. no. Description % Area Area (Ha.)
1 Fallow land 8.75 2732.25 2 Crop land 58.58 18292.05 3 Open scrub 1.32 412.18 4 Mudflat 13.81 4312.28 5 Saline area 1.12 349.73 6 Ravenous 2.36 736.93 7 River 4.22 1317.73 8 Sand 0.16 49.96 9 Built up residential 0.97 302.89 10 Mudflat with vegetation 0.16 49.96 11 Dense scrub 0.61 190.48 12 Marsh land 4.39 1370.81 13 Saltpan 0.71 221.70 14 Marsh vegetation 2.01 627.64 15 Built up industrial 0.63 196.72 16 Water body 0.2 62.45
Total 100 31225.76
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-29
Table: 3.15: Summary of Socio-economic status of Study area (Demography)
Total Population (Including
institutional and houseless
population)
Literates Total main Workers
Cultivators Agricultural Laborer
Marginal Workers
Non-Worker Name of the
Village/ Town/ Ward
No. of Occupie
d Residen
tial House P M F M F M F M F M F M F M F
Karkhadi 983 4484 2436 2048 1726 1169 1385 68 255 03 671 47 04 03 1047 1977
Kareli 1144 5431 2832 2599 1972 1083 1648 577 658 84 683 282 68 270 1196 1752
Kahanva 1636 7810 4202 3608 2815 1395 2475 494 941 100 1196 383 121 950 1606 2164
Dudhwada 400 1804 941 863 747 556 538 135 158 2 193 35 41 154 362 574
Gametha 483 2399 1269 1130 964 578 629 19 322 10 360 697 155 695 487 416
Chokari 1561 7880 4217 3663 2836 1346 2079 549 673 48 921 742 444 1183 1694 1931
Tihor 960 4495 2428 2067 1614 693 1345 406 232 33 637 209 119 91 964 1570
Majatan 571 2741 1440 1301 1050 587 823 43 340 166 279 517 65 669 552 589
Chitral 342 1733 882 851 598 374 461 103 149 10 263 134 50 153 371 595
Vishrampura 510 2623 1358 1265 1008 631 588 190 197 25 457 447 205 491 565 584
Muval 818 3946 2070 1876 1464 1028 1148 279 322 49 369 442 60 520 862 1077
Piludara 902 4269 2255 2014 1740 1134 1319 527 499 40 309 81 5 12 931 1475
Masar 716 3429 1772 1657 1236 774 1019 407 256 200 497 343 66 373 687 877
Kural 567 2620 1393 1227 995 624 640 74 185 8 363 266 199 244 554 909
Gavasad 713 3448 1849 1599 1368 907 1118 467 215 12 293 247 0 111 731 1021
Pindapa 282 1473 782 691 603 313 447 66 195 89 148 128 16 156 319 469
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-30
Table 3.16: Summary of Socio-economic status of Study area (Amenities)
Name of Village
Educational Facility
Medical Facility
Drinking Water Facility
Communication (Post
or Telegraph)
Transportation Facility
(bus etc.)
Approach to
Village
Nearest town and Distance
(Kms.)
Power Supply
Karkhadi P(2), H, PUC, Ac
MH,PHC,FPC,RP
T,W,TK,R PO, Phone BS PR Padra-24 EA
Kahanva P(15),H, Ac(3)
PHS,D, FPC,RP, CHW(2)
T,W,TW PO, Phone BS,RS PR,KR Jambusar-26 EA
Dudhwada P CHW T,W,TK PO, Phone BS PR Padra-18 EA
Gametha P,H CHW T,W,TK,TW PO BS PR Jambusar-18 EA
Kareli P(7),H, Ac(6) CWC,PHS, FPC,RP(2) CHW(4)
T,W PO, Phone BS PR Jambusar-21 EA
Chokari P, Ac(9) D,RP,CHW T,W,TK,R PO, Phone BS PR Padra-18 EA
Tihor P(2) RP,CHW T,W,TK,TW,
HP
PO, Phone BS PR Padra-18 EA
Majatan P RP,CHW T,W,TK PO, Phone BS PR Padra-17 EA
Chitral P,H CHW T,W,TK,TW PO BS PR,KR Padra-19 EA
Vishrampura P,Ac CHW T,W,TK PO BS PR Padra-14 EA
Muval P,H D,RP,CHW T,W,TK,TW PO, Phone BS PR Padra-16 EA
Piludara P(6),H, PUC, Ac
PHS,FPC, RP(2), CHW
T,W,HP PO, Phone BS PR Jambusar-18 EA
Masar P(2),H, PUC, Ac
MH,PHS,D, FPC,RP,
CHW
T,W,TK,TW PO, Phone BS PR,KR Jambusar-12 EA
Kural P,H,PUC MH,D,RP(2),
CHW
T,W,TK,N PO, Phone BS,RS PR Padra-20 EA
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-31
Name of Village
Educational Facility
Medical Facility
Drinking Water Facility
Communication (Post
or Telegraph)
Transportation Facility
(bus etc.)
Approach to
Village
Nearest town and Distance
(Kms.)
Power Supply
Gavasad P MH,PHS,D,
FPC,CHW
T,W,TK,TW PO, Phone BS PR Padra-18 EA
Pindapa P CHW T,W,TK PO BS PR,KR Padra-19 EA
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-32
Abbreviations:
Educational P - Primary School H - Matriculation/High School PUC - Higher Secondary/Pre P University/Junior College/ Inter. AC - Adult Literacy Class/ Centre
Medical Facility
PHC - Primary Health Centre PHS - Primary Health Sub-Centre RP - Registered Private Practitioner D - Dispensary MH - Maternity Home FPC - Family Planning Centre CHW - Common Health Worker
Drinking Water
T - Tap Water W - Well Water TW - Tube well Water TK - Tank water HP - Hand Pump N - Nallah
Post and Telegraph
PO - Post Office P - Phone
Transportation
BS - Bus RS - Railway Station
Approach to Village
PR - Pucca Road KR - Kachcha Road
Power Supply
EA - Electricity for all purpose Land Use
R - River TWE - Tube well T - Total
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-33
Table No 3.17: List of Tree Species found in the study area
SR. NO. BOTANICAL NAME FAMILY VARNACULAR NAME
1 Azadirachta indica Meliaceae Limdo 2 Acacia nilotica sub sp.
Indica Mimosaceae Baval
3 Achras sapota Sapotaceae Chiku 4 Ailanthus excelsa Simaroubacceae Rukhdo 5 Alangium salvifolium Alangiaceae Ankol 6 Albizia lebbeck Mimosaceae Kalo saras 7 Annona squamosa Annonaceae Sitaphal 8 Anogeissus seicea Combretaceae Dhao 9 Balanites aegyptiaca Balanitaceae Ingorio 10 Bauhinia racemosa Caesalpiniaceae Astori 11 Bombax ceiba Bombacaceae Shimlo 12 Borassus flabellifer Arecaceae Tad 13 Butea monosperma Fabeceae Kesudo 14 Cassia siamea Caesalpiniaceae --- 15 Ceiba pentandra Bombacaceae Dholo shimlo 16 Citrus limon Rutaceae Limbu 17 Dendrocalamus strictus Poaceae Vans 18 Eucalyptus globulus Myrtaceae Nilgiri 19 Feronia elephantum Rutaceae Kotha 20 Ficus benghalensis Moraceae Vad 21 Ficus religiosa Moraceae Papal 22 Ficus virens Moraceae Pipli 23 Fzizyphus mauritiana Rhamnaceae Bor 24 Holarrhena
antidysenterica Apocynaceae Indrajav
25 Holoptelea integrifolia Ulmaceae Kanjo 26 Leucena latisiliqua Mimosaceae Pardesi baval 27 Madhuca indica Sapotaceae Mahudo 28 Mangifera indica Anacardiaceae Ambo 29 Manilkara hexandra Saptaceae Rayan 30 Morinda tomentosa Rubiaceae Aal 31 Moringa concan Moringaceae Jangli saragavo 32 Parkinsonia aculeata Caesalpiniaceae Ram baval 33 Phoenix sylvestris Arecaceae Khajuri 34 Pithecellobium dulce Mimosaceae Goras ambli 35 Pongamia pinnata Fabeceae Karanj 36 Prosopis juliflora Mimosaceae Gando baval 37 Prosopis spicigera Mimosaceae Khijado 38 Psidium guajava Myrtaceae Jamphal 39 Streblus asper Moraceae Harero 40 Tamarindus indica Caesalpiniaceae Amli 41 Teminalia catappa Combretaceae Deshi bardam
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-34
List of Shrubs in the study area
SR. NO. BOTANICAL NAME FAMILY VARNACULAR NAME
1 Euphorbia Nerifolia Euphorbiaceae Thor 2 Calotropis procera Asclepiafaceae Akado 3 Capparis decidua Capparidaceae Kerdo 4 Capparis sepiaria Capparidaceae Kanthar 5 Cassia auriculata Caesalpiniaceae Aval 6 Cobretum ovalifolium Combretaceae Mad velo 7 Cocculus cillosus meinspermaceae Vevdi 8 Euphorbia tirucalli Euphorbiaceae Thor 9 Impomoea fistulosa convolvulaceae Naphatio 10 Jatroha cureas Euphorbiaceae --- 11 Kriganelia reticulata Euphorbiaceae Kamboi 12 Lassonia inernis Lythraceae Mendhi 13 Mucuna pruriens Fabaceae Kavach 14 Opuntia elatori Cactaceae Phafda thor 15 Ricinus communis Euphorbiaceae Divel 16 Zizyphus mummularia Rhmnaceae Chani bor
List of Herbs in the study area
SR. NO. BOTANICAL NAME FAMILY VARNACULAR
NAME 1 Cynodon dactylon Poaceae Darbh 2 Apluda mutica Poaceae Pofli 3 Argemone mexicana Pepavraceae Darudi 4 Blumea membranacea Asteraceae - 5 Chloris barbata Poaceae Mindadin 6 Echinops echimatus Asteraceae Shulio 7 Eragrostic tinella Poaceae - 8 Hygrophila auriculata Acanthaceae Kantashulio 9 Sphaeranthus indicus Asteraceae Gorakh mundi 10 Tephrosia purpurea Fabaceae Sarphankho 11 Tridax procumbens Asteraceae Pardeshi bhangro 12 Typha angustata Typhaceae Ramban
List of Agriculture Crops in the study area
SR. NO. BOTANICAL NAME FAMILY VARNACULAR NAME
1 Zea maize Poaceae Makai 2 Sorghum vulgare Poaceae Bajri 3 Triticum aestivum Poaceae Gehu 6 Gossypium herbaceum Malvaceae Kapas 7 Cajamus cajan Fabaceae Tuver 8 Oryaza sativa Poaceae Danger
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-35
Table 3.18 List of Amphibia, Reptilia and Birds in the study area
AMPHIBIA
SR. NO.
COMMON NAME SCIENTIFIC NAME
1 Skipper frog Euphlyctic cyanophlytis 2 Common Indian Toad Bufo melanostictus
REPTILIA
SR. NO.
COMMON NAME SCIENTIFIC NAME
1 Wall Lizard Hemidactylus flaviviridis 2 Garden lizard Calotes versicolor 3 Skink Mabuya carinata 4 Fan throated lizard Sitana ponticeriana 5 Cobra Naja naja 6 Rat Snake Ptyas mucous
BIRDS
SR. NO.
COMMON NAME SCIENTIFIC NAME
1 Black drongo Dicrurus adsimilis 2 Ashy crowned finch lark Eremopterix grisea 3 Bank myna Acredotheres ginginianus 4 Black winged kite Elanus caerulus 5 Blue rock pigeon Columba livia 6 Cattle egret Bulbucus ibis 7 Common babbler Turdoides caudatus 8 Common crow Corvus splendens 9 Common myna Acredotheres tristis 10 Common sandpiper Tringa hypoleucos 11 Coppersmith Megalaima haemacephala 12 Crow- pheaasent Centropus sinensis 13 Fantail flycatcher Rhipidura aureola 14 Franklins wren warbler Prinia hodgsonii 15 Grey shrike Lanius excubitor 16 Grey tit Parus major 17 House sparrows Passer domesticus 18 House swift Apus affinus 19 Indian koel Eudynamysscolopaceae 20 Indian robin Saxicoloides fulicata 21 Indian roller Coracias benghalensis 22 Indian tree pie Dendrocitta vagabunda 23 Indian white backed vulture Gyps benghalensis 24 Jungle babbler Turdoides striatus 25 Jungle crow Corvus macrorhynchos 26 Lesser goldenbacked woodpeaker Dinopium benghalens
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-36
27 Lotens sunbird Nectarinia lotenia 28 Magpie robin Copsychus saularis 29 Pariah kite Milvus migrans 30 Pond heron Ardeola grayii 31 Purple sunbird Nectarinia asiatica 32 Red vented bulbul Pycnonotus cafer 33 Red wattled lapwing Vanellus indicus 34 Rofous backed shrike Lanius schach 35 Rofous tailed finch lark Aammomanes deserti 36 Rose ringed parakeet Paittacula krameri 37 Shikra Accipter badius 38 Small green bee- eater Merops orientalis 39 Spotted owlet Ethane brama 40 Swallow Hirundo rustica 41 Tailor bird Orthotomus sutorius 42 White breasted kingfisher Halcyon smyrensis 43 White wagtail Motavilla alba 44 Yellow throated sparrows Patronia xanthocollis
List of Insects and others in the study area
SR. NO.
COMMON NAME SCIENTIFIC NAME
1 Ant lion Myrmeleo sp. 2 Beetle Mylabris sp. 3 Black ant Camponotous compressus 4 Blue pancy Précis orithya 5 Common castor Ariadne merione merione 6 Common crow Euploea core core 7 Common evening brown Maelanitus leda leda 8 Common grass yellow Eurema hecabe simulate 9 Common mormon Papilio polyets romulus 10 Danaid eggfly Hypolimans misippus 11 Earthworm Megascolex sp 12 Field cricket Gryllus bimaculatus 13 German cockroach Blatta germanica 14 Grasshopper Orthetrum sp. 15 Grasshopper Conocephalus sp. 16 Honey bee Apis dorsata 17 Honey bee Apis indica 18 House cricket Gryllus domecticus 19 House fly Musca domestica (Linn.) 20 Indian cupid Everes lcturnus syntala 21 Lime butterfly Papilio demoles 22 Mole cricket Grylltaipa Africana 23 Mosquito Anopheles sp. 24 Mosquito Culex sp. 25 Pigmy locust Acridium sp. 26 Plain tiger Danus crysippus crysippus 27 Potter wasp Eumenes sp.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-37
28 Red ant Oecophylla smargdina 29 Red cotton bug Ddysdercus sp. 30 Striped tiger Danus genutia genutia 31 Termite Microtermes 32 Tree cricket Oecanthus indicus (Sauss) 33 wasp Icaria sp. 34 Water strider Geris spinole (Leth) 35 Yellow pancy Précis hierta hierta
SPIDERS
SR. NO.
COMMON NAME SCIENTIFIC NAME
1 Banded four legged spider Argiope aemula (Walckenaer)
2 Banded four legged spider Argiope sp. 3 House spider Crossopriza sp. 4 Jumping spider Plexippus sp. 5 Lynx spider Oxyopes sp. 6 Lynx spider Peucetia sp. 7 Orb web spider Cyclosa sp. 8 Orb web spider Larinia sp. 9 Orb web spider Neoscona sp. 10 See spider Clubiona sp. 11 Social spider Stegodyphus sp. 12 Two tailed spider Hersilia sp. 13 Wolf spider Hippasa sp. 14 Wolf spider Lycosa sp. 15 Wolf spider Pardosa sp.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-38
Figure 3.6 Ambient Air Quality Monitoring Stations
Indicating Ambient Air Quality Monitoring Station
Project site
5 KM Radius
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-39
Figure 3.7
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-40
Figure 3.8 Water Sampling Locations
Indicating Location of Ground Water Sample
Project site 5 KM Radius
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-41
Figure 3.9 Location of Noise survey
Indicating Noise Monitoring Station
Project site 5 KM Radius
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-42
Figure 3.10 Soil Sampling Locations
Indicating Location of Soil Sample
Project site 5 KM Radius
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of M/s. Asahi Songwon Colors Ltd. 3-43
Figure 3.11: Land use/Land Cover Map by satellite images
Asahi
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-1
CHAPTER-4 ANTICIPATED ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES 4.1 GENERAL
Environmental Impact can be defined as any change in
environmental conditions which may be adverse or beneficial
occurred due to action or set of actions under consideration.
Environmental impact can be assessed by identifying the sources of
the impact and predicting the same. The identification of
environmental impacts has been made by co relating the relationship
between project activity and environmental parameters. The project
activities of the proposed project are usually divided into two phases:
Construction Phase and Operation Phase. The activities like mining,
excavation, erosion, building construction, transportation of
construction material, etc. are usually consider in the construction
phase. While in the operation phase the activities like transportation
and storage of raw materials and finished products, manufacturing
process, resource consumption, emergency disaster and green belt
development has been considered.
The next step is prediction of impacts, which is an important
component in environmental impact assessment process. Several
techniques and methodologies are in vogue for predicting the
impacts due to existing and proposed industrial development on
physical, chemical, biological and socio-economic components of
environment. Such predictions delineate contribution in existing
baseline condition for the proposed project. The additional impacts
due to proposed activities are analyzed keeping in mind the baseline
status. This helps assess the assimilative capacity of the environment
and in turn the gravity of the impacts.
The third important component of the environmental assessment is
the evaluation. Based on the identification and prediction of the
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-2
nature of impact the environment, the impact can be evaluated
qualitatively and quantitatively.
The environment impact due to proposed activities will be evaluated
considering the following parameters,
• Air Environment
• Water Environment
• Noise Environment
• Land Environment
• Ecology
• Socio-Economic Environment
4.2 AIR ENVIRONMENT
Sources of Impact
There are chances of impact on the air environment due to
installation of new machinery during construction phase and due to
gaseous emission from the flue and process gas stacks during
operational phase.
4.2.1 Prediction of impact
Construction Phase
Since the proposed expansion will be carried out in the existing
premises, no major construction activities will be carried out.
However, there will be chances of dust emission from site cleaning
and construction activity and minor excavation activities. This will be
limited only up to working area. Dust and other emissions are not
likely to spread in wider area, which would affect homes and other
properties. Dust will generate within working areas and measures will
need to taken to protect workers.
However, to mitigate the impact due to Suspended Particulate Matter
(SPM), regular sprinkling of the water will be done along with the
construction activities.
4.2.2 Operational Phase
The impacts on air quality from any project depend on various
factors like design capacity, configuration, process technology, raw
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-3
material, fuel to be used, air pollution control measures, operation
and maintenance.
4.2.3 Source of Air Pollution
The main point sources of air pollution due to proposed expansion
project will be of additional flue gas stacks & process gas stacks.
Flue gas stack will be attached to boiler and Thermic fluid heater
where as three process stacks attached to process vessel and third
process stack attached to spin flash dryers.
Flue gas will be mainly due to the combustion of coal/lignite.
However, the unit has provided cyclone separator followed by bag
filter as air pollution control system which will be adequate to meet
the recognized gaseous emission norms. The unit also proposes to
provide proper stack height to all the stacks. Chimney heights have
been chosen such that the generated pollutants disperse effectively
and ensure that the ground level concentrations of pollutants in the
surrounding environment remain well within the permissible limits.
There are also chances of process gas emission- mainly HCl/Cl2 from
the manufacturing of pigment Green-7, where the unit will provide
multistage scrubbing system to reduce emissions of HCl/Cl2.
In Blue Crude plant, NH3 gas will be generated. The unit is already
having scrubbing system in place which is working efficiently and
effectively. The unit proposes to install scrubbing system as per
existing system.
The unit will provide adequate stacks heights of 32 m for the flue gas
stacks (Boiler & Thermic Fluid Heater) and 15-18 m for process gas
stacks, which is adequate for the proper dispersion of the gaseous
emission.
To minimize fugitive emission the unit has adopted the practice of
carrying out entire manufacturing process into closed vessel as well
as provided adequate scrubbing system for efficient absorption of
process gas. Unit also takes special care while solvent recovery.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-4
Special care is also taken while material handling and storage. To
reduce the pollutant emission during transportation, the unit has
adopted the practice of regular check up and maintenance of
vehicular engines for complete combustion of the fuel.
In the present study, the mathematical model that has been used for
predictions on air quality includes steady state Gaussian Plume
Dispersion model designed for multiple point sources.
4.2.4 Air Emissions
The results for gaseous emission for existing flue gas stack as well as
for the process gas stacks are summarized in Table: 4.1.
Gas Stack and process Emission Standard Details for Industry give in
Table: 4.2
The results show that all parameters are well within the stipulated
standards.
4.2.5 Micrometeorology
The hourly wind speed, solar insolation and total cloudiness during
day time and wind speed and total cloudiness during night time were
used to determine the hourly atmospheric stability classes (defined
by Pasquill and Gifford as A to F, A being most unstable and F being
most stable).The hourly stability classes were determined based on
the technique suggested by Turner.
Turner’s system used for determining the stability classes is as
follows:
- For day or night: If total cloud cover (TC) = 10/10 and
ceiling <7000 ft (2134 m), NR=0
- For night-time (defined as period from one hour before
sunset to one hour after sunrise):
a) If TC<4/10, use NR = -2
b) If TC>4/10, use NR = -1
- For daytime: determine isolation class number (IN)
a) If TC<5/10, use NR=IN
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-5
b) If TC>5/10, modify IN by the sum of the following
applicable criteria
If ceiling<7000 ft (2134m), modification = -2
If ceiling>7000 ft but <16000 ft (4877 m), modification
= -1
If TC=10/10 and ceiling>7000 ft, modification = -1, and let modified
value of IN=NR, except for day-time NR cannot be <+1.
During the study period stability calculated based on above-
mentioned Turner method gives average stability as A-B class during
Day time and E class during Night time. The mean mixing height
considered for prediction is 100 m as mean minimum and 1000 m as
mean maximum. Average micro meteorological data of December-10
to February-11 is used.
4.2.6 Air Quality Modeling and Predictions using the Gaussian Model
The impact on air quality due to emissions from single source or
group of sources is evaluated by use of mathematical models. When
air pollutants are emitted into the atmosphere, they are immediately
diffused into surrounding atmosphere, transported and diluted due to
winds. The air quality models are designed to simulate these
processes mathematically and to relate emissions of primary
pollutants to the resulting downwind air quality. The inputs include
emissions, meteorology and surrounding topographic details to
predict the impacts of conservative pollutants.
The impacts of air pollutants were predicted using Gaussian air
dispersion model, which is selected on the basis of existence of
multiple point sources within the industrial complex and the plain
terrain at the project site.
The Gaussian air dispersion model has been developed to simulate
the effect of emissions from point sources on air quality. Gaussian
model extensively used for predicting the Ground Level
Concentrations (GLCs) of conservative pollutants from point, area
and volume sources. The impacts of primary air pollutants are
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-6
predicted using this air quality model keeping in view the plain
terrain at the project site. The micrometeorological data monitored at
project site during study period have been used in this model.
The Gaussian model provides estimates of pollutant concentrations at
various receptor locations. It is an hour-by-hour steady state
Gaussian model which takes into account the following:
- Terrain adjustments
- Stack-tip downwash
- Gradual plume rise
- Buoyancy-induced dispersion, and
- Complex terrain treatment and consideration of partial
reflection
- Plume reflection off elevated terrain
- Building down wash
- Partial penetration of elevated inversions is accounted for
Hourly source emission rates, exit velocity and stack gas
temperature
A Gaussian air dispersion models were used to estimate the ambient
air quality levels at the different monitoring stations due to stack
emissions from Asahi Songwon. Only two stability conditions based
on the meteorology aspects were used to calculate the theoretical
maximum ground level concentration is comparing the actual data
and data generated from mathematical modeling, it highlights that
the stability condition E & A-B were predominant in the region. The
maximum ground level concentration of SPM, SO2 and NOx were
2000 m & HCl, Cl2, NH3 were 1000 m away from the source Using
the existing stack emission data and wind speed directions, a
mathematical model was prepared to establish the ground level
concentration in the region.
4.2.7 Predicted GLCs of proposed Chemicals Plant
It is predicted that the maximum contribution in GLCs, with units
operating at full capacity, is 3.205 μg/m3, 1.472 μg/m3 and 0.485
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-7
μg/m3 for SPM, SO2 and NOx respectively 2 km away from Project
Site (Source) in N direction. Whereas NH3, HCl, Cl2 were 2.397,
0.291, and 0.125 respectively 1 km away from centre of industry in
N direction.
With this marginal contribution due to the expansion of the project,
the levels of SPM, SO2 and NOX will be below residential area limit
prescribed by CPCB.
4.3 WATER ENVIRONMENT
Sources of Impacts
The main sources of impact on water environment will be due to
withdrawal of additional fresh water from the ground during
construction and operation phase and treated waste water discharge.
Prediction of Impact
Construction Phase
Since the proposed expansion will be in the existing premises and no
major construction activities will be carried out, there will not be any
adverse impact on the quality of water because very small quantities
of water will be used. No disposal of construction waste outside the
plant and no leaching are anticipated.
Operational Phase
The unit has provided its own bore well to satisfy the water
requirement within premises. At present the total water requirement
is 2188 KL/day for domestic and industrial purpose which will be
reduced up to 2105 KL/day after proposed expansion. This is due to
recycling of treated wastewater.
The main source of industrial wastewater generation will remain
same after proposed expansion, except increase in waste water
generation from process & utilities and it will be control by recycling
of treated water in process.
Impact Assessment
Since fresh water will be required for the proposed expansion, there
will be insignificant impact on the ground water table. However it will
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-8
be balanced by recharge ground water during the monsoon season.
For that, Industry proposed to develop recharging sump at low lying
area which will be connected to the storm water drainage system to
recharging the ground water during the rain.
The entire quantity of industrial wastewater will also be treated at its
modified Effluent Treatment Plant and after meeting effluent
discharge norms recognized by GPCB, entire quantity of the treated
effluent will be finally disposed off into sea through ECP project.
To reduce the wastewater discharge into ECP channel which convey
the treated effluent into river Mahi Creek, unit proposed to install a
RO & Multi effect evaporation systems for recycling of treated
effluent and maintain/minimize the discharge to ECP compare to
current consented capacity.
4.4 NOISE LEVEL IMPACT
During construction phase the impact on noise environment will be
due to installation of new mechanical equipments and machineries
while during the operational phase the impact on noise environment
will be due to manufacturing activities, boilers and transportation
activities.
4.4.1 Construction Phase
The noise produced during construction may have significant impact
on the existing ambient noise levels. However, the proposed
expansion of M/s. Asahi Songwon Colors Ltd. is in the existing
premises and there will not be any major construction activities will
be carried out. Minor quantity of noise will be generated due to
installation of new machineries and equipments. The impact will be
very minor and temporary in nature.
4.4.2 Operational Phase
The main sources of noise within the plants are: boiler, Turbine,
transferring pumps and material handling systems. Suitable noise
control system will be provided to ensure that noise at the ventilation
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-9
openings does not exceed 90 dB(A) at 1 m distance in conformity
with ISO 3746. The noise level shall, however, exceed the above
limits for a short period during start-up of equipments.
The continuous source of noise during plant operation will be boilers,
turbine, transferring pumps and equipment. The other sources of
noise are the movement of vehicles along the road.
However, proper noise preventive measures have been taken to
minimize the noise pollution like ear plugs, dampers to the boilers,
efficient silencers to the vehicles, etc.
The results of monitoring carried out in the region have been
presented in Chapter-3. The permissible levels in the ambient
environment are presented in Chapter 3. The results are below the
standards prescribed for Industrial environment.
Thus, impact on the environment during the operation phase will be
long term but, insignificant quantity.
4.5 LAND/SOIL ENVIRONMENT
The main source of impact on land and soil environment will be due
to construction activities and hazardous waste disposal.
Construction Phase
Since the proposed project activities will be carried out in the existing
premises. All the existing infrastructure facilities will be utilized with
addition of some new machinery. Therefore, no major construction
activities will be carried out for the proposed project. Further, the
area of the plant is flat. Leveling would not be required. Thus,
topography will also be remained unchanged after proposed
expansion.
Thus, the impact on the land/soil during the construction is for short
terms and insignificant.
Operation Phase
Entire quantity of the hazardous waste will be stored in the isolated
hazardous waste storage area within premises having leachate
collection system and roof cover.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-10
Entire quantity of ETP sludge generated from the Effluent Treatment
Facilities will be sent to TSDF site operated by M/s. Naroda Enviro
Projects Ltd. (NEPL), Ahmedabad for final disposal.
Whereas, discarded barrels/bags/drums/liners will be
decontaminated and reuse/sold to approve vendors and waste/spent
oil will be reused as lubricant within premises or sold to MoEF
approved registered recyclers.
4.6 SOCIO-ECONOMIC ENVIRONMENT
The proposed expansion will be in the existing premises and no
additional land will be required. Therefore, no displacement of person
is envisaged.
The plant is most modern and will require educated and trained
manpower. The surrounding area has got good educational facilities
at Vadodara & Padra. So employment will be satisfied from
surrounding area.
However, some persons with requisite experience is come from
outside also, but most of them may stay at Vadodara.
The operation of the existing plant requires a workforce of 225
persons and after expansion it will be increased up to 350. Thus,
increasing industrial activity will boost up the commercial and
economical status of the locality to some extent.
Thus, overall impacts on socio-economic environment due to the
existence of plant are long term and positive in nature.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-11
4.7 ECOLOGICAL IMPACTS
Impacts of the proposed expansion on the ecological environment
like natural vegetation, crops, fisheries and aquatic life, species
diversity, which is summarized hereunder,
Since the proposed expansion will be in the existing premises, there
will not be any cutting of natural vegetation.
On the contrary, the unit proposes to develop green belt on and
around the premises.
The areas around the premises consist of a dense growth of
vegetation. Various trees, shrubs and herbs are found in and around
it, a list of which is given in Chapter 3. None of the plants are in the
list of Endangered Plant Species.
The high Stomatal Index of Azadirachta indica, makes them
susceptible to SO2. However, the SO2 emissions from the industry
will within limits and proper disperse at the stack height of 32
meters. Hence, no major adverse impact is expected on these plants
with the increased emissions.
The high SPM levels may harm leaves by blocking stomata and thus
interfering with exchange of gases during photosynthesis and
respiration and also cause abrasion of plant surfaces when the wind
blows. But the site is not subjected to high-speed winds and the
plants can be expected to be free from any major impacts of SPM on
plants.
Thus, there will not be any significant impact on ecological
environment due to proposed project activities.
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-12
Table 4.1:
Estimated emission from new stacks/vents
Sr. No.
Stack attached to
Stack Temp. In 0K
Velocity m/s
Stack Height in m
Fuel Used
SPM mg/Nm3
SO2
PPM NOX
PPM
01 Boiler-2 450 10 32 Lignite /Coal
125 75 25
02 Thermic Fluid Heater
440 10 32 Lignite /Coal
125 75 25
03 Process Stack-3
325 6.5 15 - NH3 = 125 mg/Nm3
04 Chlorination & Dumping Vessel
350 5.5 18
- HCl = 25 mg/Nm3
Cl2 = 10 mg/Nm3
05 Spin Flash Dryers 1
410 6.0 11 - PM =40 mg/Nm3
06 Spin Flash Dryers 2
410 6.0 11 - PM =40 mg/Nm3
Table 4.2:
GPCB Stack and Process Emission Standards Details for Industry
Sr.
No.
Stack Attached
to
Parameter Permissible Limit
Flue Gas Stack
1 Boilers & Heaters
PM, SO2, NOX
PM< 150 mg/Nm3
SO2<100 ppm NOX< 50 ppm
Process Gas Stack
2 Process Gas NH3 NH3<175 mg/Nm3
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-13
Table 4.3
The 24-hourly average GLC Concentration Values for SPM
RANK CONC RECEPTOR (XR,YR) TYPE RANK CONC RECEPTOR (XR,YR) TYPE
1 3.205 ( .00, 2000.00) GC 26 2.124 ( .00, 3000.00) GC
2 3.101 ( .00, 1000.00) GC 27 2.109 ( .00, 1000.00) GC
3 2.721 ( .00, 3000.00) GC 28 2.096 ( .00, 2000.00) GC
4 2.623 ( .00, 2000.00) GC 29 2.086 ( .00, 2000.00) GC
5 2.553 ( .00, 2000.00) GC 30 2.048 ( .00, 1000.00) GC
6 2.525 ( .00, 2000.00) GC 31 2.047 ( 1000.00, 1000.00) GC
7 2.523 ( .00, 1000.00) GC 32 2.039 ( .00, 1000.00) GC
8 2.500 ( .00, 2000.00) GC 33 2.018 ( .00, 3000.00) GC
9 2.469 ( .00, 2000.00) GC 34 2.009 ( .00, 3000.00) GC
10 2.418 ( .00, 1000.00) GC 35 2.000 ( .00, 2000.00) GC
11 2.417 (-2000.00, 2000.00) GC 36 1.940 ( .00, 1000.00) GC
12 2.405 ( .00, 2000.00) GC 37 1.908 ( -3000.00, 3000.00) GC
13 2.340 -1000.00, 1000.00) GC 38 1.900 ( .00, 1000.00) GC
14 2.277 ( .00, 1000.00) GC 39 1.883 ( .00, 4000.00) GC
15 2.251 ( .00, 3000.00) GC 40 1.875 ( .00, 3000.00) GC
16 2.241 ( .00, 4000.00) GC 41 1.857 ( .00, 5000.00) GC
17 2.240 (-2000.00, 2000.00) GC 42 1.854 ( .00, 4000.00) GC
18 2.233 ( .00, 3000.00) GC 43 1.847 ( .00, 4000.00) GC
19 2.233 ( .00, 1000.00) GC 44 1.841 ( .00, 2000.00) GC
20 2.228 ( .00, 2000.00) GC 45 1.801 ( .00, 4000.00) GC
21 2.219 ( .00, 3000.00) GC 46 1.797 ( -2000.00, 2000.00) GC
22 2.185 ( .00, 3000.00) GC 47 1.776 ( .00, 1000.00) GC
23 2.168 -1000.00, 1000.00) GC 48 1.773 ( .00, 3000.00) GC
24 2.158 ( .00, 1000.00) GC 49 1.772 ( .00, 3000.00) GC
25 2.134 ( .00, 2000.00) GC 50 1.767 ( .00, 4000.00) GC Note: Receptor Types: GC = Grid cart, Concentration in µg/m3
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-14
Table 4.4
The 24-hourly average GLC Concentration Values for SO2
RANK CONC RECEPTOR (XR,YR) TYPE RANK CONC RECEPTOR (XR,YR) TYPE
1 1.472 ( .00, 2000.00) GC 26 0.959 ( .00, 1000.00) GC 2 1.342 ( .00, 3000.00) GC 27 0.957 ( .00, 5000.00) GC
3 1.196 ( .00, 2000.00) GC 28 0.952 ( .00, 2000.00) GC
4 1.196 ( -2000.00, 2000.00) GC 29 0.940 ( .00, 4000.00) GC
5 1.148 ( .00, 2000.00) GC 30 0.939 ( .00, 4000.00) GC
6 1.142 ( .00, 2000.00) GC 31 0.937 ( .00, 3000.00) GC
7 1.139 ( .00, 4000.00) GC 32 0.926 ( .00, 2000.00) GC
8 1.137 ( .00, 2000.00) GC 33 0.904 ( .00, 4000.00) GC
9 1.137 ( .00, 2000.00) GC 34 0.903 (-1000.00, 1000.00) GC
10 1.123 ( .00, 1000.00) GC 35 0.898 ( .00, 4000.00) GC
11 1.107 ( .00, 3000.00) GC 36 0.889 (-2000.00, 2000.00) GC
12 1.102 ( .00, 3000.00) GC 37 0.887 (-3000.00, 3000.00) GC
13 1.100 (-2000.00, 2000.00) GC 38 0.886 ( .00, 1000.00) GC
14 1.098 ( .00, 2000.00) GC 39 0.870 ( .00, 3000.00) GC
15 1.093 ( .00, 3000.00) GC 40 0.870 ( .00, 4000.00) GC
16 1.054 ( .00, 3000.00) GC 41 0.867 ( .00, 3000.00) GC
17 1.054 ( .00, 3000.00) GC 42 0.864 (1000.00, 1000.00) GC
18 1.015 ( .00, 2000.00) GC 43 0.858 (-2000.00, 5000.00) GC
19 0.994 ( .00, 3000.00) GC 44 0.834 ( .00, 4000.00) GC
20 0.992 ( -1000.00, 1000.00) GC 45 0.831 ( .00, 2000.00) GC
21 0.988 ( .00, 3000.00) GC 46 0.829 ( .00, 3000.00) GC
22 0.980 ( -3000.00, 3000.00) GC 47 0.823 ( .00, 4000.00) GC
23 0.979 ( .00, 2000.00) GC 48 0.820 ( 2000.00, 2000.00) GC
24 0.967 ( .00, 2000.00) GC 49 0.816 ( .00, 5000.00) GC
25 0.959 ( .00, 4000.00) GC 50 0.815 ( .00, 6000.00) GC
Note: Receptor Types: GC = Grid cart, Concentration in µg/m3
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-15
Table 4.5
The 24-hourly average GLC Concentration Values for NOx RANK CONC RECEPTOR (XR,YR) TYPE RANK CONC RECEPTOR (XR,YR) TYPE
1 0.485 ( .00, 2000.00) GC 26 0.316 ( .00, 1000.00) GC
2 0.442 ( .00, 3000.00) GC 27 0.316 ( .00, 5000.00) GC
3 0.395 ( .00, 2000.00) GC 28 0.314 ( .00, 2000.00) GC
4 0.394 ( -2000.00, 2000.00) GC 29 0.310 ( .00, 4000.00) GC
5 0.379 ( .00, 2000.00) GC 30 0.310 ( .00, 4000.00) GC
6 0.377 ( .00, 2000.00) GC 31 0.309 ( .00, 3000.00) GC
7 0.376 ( .00, 4000.00) GC 32 0.306 ( .00, 2000.00) GC
8 0.375 ( .00, 2000.00) GC 33 0.298 ( .00, 4000.00) GC
9 0.375 ( .00, 2000.00) GC 34 0.298 ( -1000.00, 1000.00) GC
10 0.370 ( .00, 1000.00) GC 35 0.296 ( .00, 4000.00) GC
11 0.365 ( .00, 3000.00) GC 36 0.293 ( -2000.00, 2000.00) GC
12 0.363 ( .00, 3000.00) GC 37 0.292 ( -3000.00, 3000.00) GC
13 0.363 ( -2000.00, 2000.00) GC 38 0.292 ( .00, 1000.00) GC
14 0.362 ( .00, 2000.00) GC 39 0.287 ( .00, 3000.00) GC
15 0.361 ( .00, 3000.00) GC 40 0.287 ( .00, 4000.00) GC
16 0.348 ( .00, 3000.00) GC 41 0.286 ( .00, 3000.00) GC
17 0.348 ( .00, 3000.00) GC 42 0.285 ( 1000.00, 1000.00) GC
18 0.335 ( .00, 2000.00) GC 43 0.283 ( -2000.00, 5000.00) GC
19 0.328 ( .00, 3000.00) GC 44 0.275 ( .00, 4000.00) GC
20 0.327 ( -1000.00, 1000.00) GC 45 0.274 ( .00, 2000.00) GC
21 0.326 ( .00, 3000.00) GC 46 0.274 ( .00, 3000.00) GC
22 0.323 ( -3000.00, 3000.00) GC 47 0.271 ( .00, 4000.00) GC
23 0.323 ( .00, 2000.00) GC 48 0.270 ( 2000.00, 2000.00) GC
24 0.319 ( .00, 2000.00) GC 49 0.269 ( .00, 5000.00) GC
25 0.316 ( .00, 4000.00) GC 50 0.269 ( .00, 6000.00) GC
Note: Receptor Types: GC = Grid cart, Concentration in µg/m3
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-16
Table 4.6 The 24-hourly average GLC Concentration Values for Cl2
RANK CONC RECEPTOR (XR,YR) TYPE RANK CONC RECEPTOR (XR,YR) TYPE
1 0.125 ( .00, 1000.00) GC 26 0.062 ( .00, 1000.00) GC
2 0.100 ( .00, 1000.00) GC 27 0.062 ( .00, 2000.00) GC
3 0.100 ( .00, 1000.00) GC 28 0.062 ( .00, 2000.00) GC
4 0.098 ( .00, 1000.00) GC 29 0.061 ( .00, 2000.00) GC
5 0.097 ( .00, 1000.00) GC 30 0.061 ( .00, 1000.00) GC
6 0.097 ( .00, 1000.00) GC 31 0.059 ( .00, 1000.00) GC
7 0.092 ( .00, 1000.00) GC 32 0.058 (1000.00, 1000.00) GC
8 0.089 ( -1000.00, 1000.00) GC 33 0.058 ( .00, 2000.00) GC
9 0.086 ( .00, 1000.00) GC 34 0.057 ( .00, 1000.00) GC
10 0.084 ( -1000.00, 1000.00) GC 35 0.056 ( .00, 1000.00) GC
11 0.083 ( .00, 1000.00) GC 36 0.056 ( .00, 2000.00) GC
12 0.081 ( .00, 1000.00) GC 37 0.055 ( .00, 2000.00) GC
13 0.078 ( .00, 1000.00) GC 38 0.055 ( .00, 1000.00) GC
14 0.076 ( .00, 1000.00) GC 39 0.053 ( -1000.00, 1000.00) GC
15 0.075 ( .00, 2000.00) GC 40 0.053 ( .00, 1000.00) GC
16 0.071 ( .00, 1000.00) GC 41 0.052 ( .00, 1000.00) GC
17 0.068 ( .00, 1000.00) GC 42 0.052 ( -1000.00, 1000.00) GC
18 0.067 ( -1000.00, 1000.00) GC 43 0.050 ( .00, 1000.00) GC
19 0.066 ( .00, 1000.00) GC 44 0.050 ( .00, 1000.00) GC
20 0.065 ( .00, 1000.00) GC 45 0.050 ( .00, 2000.00) GC
21 0.065 ( .00, 1000.00) GC 46 0.049 ( .00, 2000.00) GC
22 0.065 ( .00, 1000.00) GC 47 0.049 ( .00, 2000.00) GC
23 0.064 ( .00, 1000.00) GC 48 0.048 ( .00, 3000.00) GC
24 0.063 ( .00, 1000.00) GC 49 0.047 ( .00, 1000.00) GC
25 0.062 ( .00, 2000.00) GC 50 0.046 ( -2000.00, 2000.00) GC
Note: Receptor Types: GC = Grid cart, Concentration in µg/m3
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-17
Table 4.7
The 24-hourly average GLC Concentration Values for HCl
RANK CONC RECEPTOR (XR,YR) TYPE RANK CONC RECEPTOR (XR,YR) TYPE
1 0.291 ( .00, 1000.00) GC 26 0.144 ( .00, 1000.00) GC
2 0.234 ( .00, 1000.00) GC 27 0.144 ( .00, 2000.00) GC
3 0.233 ( .00, 1000.00) GC 28 0.144 ( .00, 2000.00) GC
4 0.229 ( .00, 1000.00) GC 29 0.143 ( .00, 2000.00) GC
5 0.227 ( .00, 1000.00) GC 30 0.142 ( .00, 1000.00) GC
6 0.226 ( .00, 1000.00) GC 31 0.138 ( .00, 1000.00) GC
7 0.215 ( .00, 1000.00) GC 32 0.136 ( 1000.00, 1000.00) GC
8 0.208 ( -1000.00, 1000.00) GC 33 0.135 ( .00, 2000.00) GC
9 0.200 ( .00, 1000.00) GC 34 0.133 ( .00, 1000.00) GC
10 0.196 ( -1000.00, 1000.00) GC 35 0.130 ( .00, 1000.00) GC
11 0.193 ( .00, 1000.00) GC 36 0.130 ( .00, 2000.00) GC
12 0.189 ( .00, 1000.00) GC 37 0.129 ( .00, 2000.00) GC
13 0.183 ( .00, 1000.00) GC 38 0.128 ( .00, 1000.00) GC
14 0.176 ( .00, 1000.00) GC 39 0.124 ( -1000.00, 1000.00) GC
15 0.175 ( .00, 2000.00) GC 40 0.123 ( .00, 1000.00) GC
16 0.167 ( .00, 1000.00) GC 41 0.122 ( .00, 1000.00) GC
17 0.158 ( .00, 1000.00) GC 42 0.121 ( -1000.00, 1000.00) GC
18 0.156 ( -1000.00, 1000.00) GC 43 0.117 ( .00, 1000.00) GC
19 0.153 ( .00, 1000.00) GC 44 0.117 ( .00, 1000.00) GC
20 0.153 ( .00, 1000.00) GC 45 0.117 ( .00, 2000.00) GC
21 0.152 ( .00, 1000.00) GC 46 0.114 ( .00, 2000.00) GC
22 0.152 ( .00, 1000.00) GC 47 0.114 ( .00, 2000.00) GC
23 0.150 ( .00, 1000.00) GC 48 0.112 ( .00, 3000.00) GC
24 0.146 ( .00, 1000.00) GC 49 0.110 ( .00, 1000.00) GC
25 0.145 ( .00, 2000.00) GC 50 0.108 ( -2000.00, 2000.00) GC
Note: Receptor Types: GC = Grid cart, Concentration in µg/m3
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-18
Table 4.8
The 24-hourly average GLC Concentration Values for NH3
RANK CONC RECEPTOR (XR,YR) TYPE RANK CONC RECEPTOR (XR,YR) TYPE
1 2.397 ( .00, 1000.00) GC 26 1.170 ( .00, 1000.00) GC
2 1.944 ( .00, 1000.00) GC 27 1.134 ( .00, 1000.00) GC
3 1.919 ( .00, 1000.00) GC 28 1.093 ( .00, 1000.00) GC
4 1.893 ( .00, 1000.00) GC 29 1.061 ( .00, 1000.00) GC
5 1.879 ( .00, 1000.00) GC 30 1.046 ( .00, 2000.00) GC
6 1.872 ( .00, 1000.00) GC 31 1.031 ( .00, 1000.00) GC
7 1.749 ( .00, 1000.00) GC 32 1.025 ( .00, 1000.00) GC
8 1.644 ( .00, 1000.00) GC 33 1.013 ( .00, 2000.00) GC
9 1.592 ( .00, 1000.00) GC 34 1.013 ( .00, 2000.00) GC
10 1.567 ( .00, 1000.00) GC 35 1.012 ( .00, 1000.00) GC
11 1.559 ( -1000.00, 1000.00) GC 36 1.007 ( .00, 2000.00) GC
12 1.483 ( -1000.00, 1000.00) GC 37 1.004 ( 1000.00, 1000.00) GC
13 1.467 ( .00, 1000.00) GC 38 0.974 ( .00, 1000.00) GC
14 1.414 ( .00, 1000.00) GC 39 0.956 ( .00, 2000.00) GC
15 1.387 ( .00, 1000.00) GC 40 0.927 ( .00, 1000.00) GC
16 1.304 ( .00, 1000.00) GC 41 0.923 ( -1000.00, 1000.00) GC
17 1.279 ( .00, 1000.00) GC 42 0.919 ( -1000.00, 1000.00) GC
18 1.278 ( .00, 1000.00) GC 43 0.912 ( .00, 2000.00) GC
19 1.275 ( .00, 1000.00) GC 44 0.906 ( .00, 1000.00) GC
20 1.263 ( .00, 1000.00) GC 45 0.903 ( .00, 2000.00) GC
21 1.248 ( .00, 1000.00) GC 46 0.845 ( .00, 1000.00) GC
22 1.235 ( .00, 2000.00) GC 47 0.823 ( .00, 1000.00) GC
23 1.225 ( .00, 1000.00) GC 48 0.814 ( .00, 2000.00) GC
24 1.217 ( .00, 1000.00) GC 49 0.807 ( .00, 2000.00) GC
25 1.176 ( -1000.00, 1000.00) GC 50 0.805 ( .00, 2000.00) GC
Note: Receptor Types: GC = Grid cart, Concentration in µg/m3
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-19
Figure 4.1
Isopleths for Ground Level Concentrations for SPM
-10000 -8000 -6000 -4000 -2000 0 2000 4000 6000 8000 10000-10000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
10000
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-20
Figure 4.2
Isopleths for Ground Level Concentrations for SO2
-10000 -8000 -6000 -4000 -2000 0 2000 4000 6000 8000 10000-10000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
10000
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-21
Figure 4.3
Isopleths for Ground Level Concentrations for NOX
-10000 -8000 -6000 -4000 -2000 0 2000 4000 6000 8000 10000-10000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
10000
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-22
Figure 4.4
Isopleths for Ground Level Concentrations for Cl2
-10000 -8000 -6000 -4000 -2000 0 2000 4000 6000 8000 10000-10000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
10000
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-23
Figure 4.5
Isopleths for Ground Level Concentrations for HCl
-10000 -8000 -6000 -4000 -2000 0 2000 4000 6000 8000 10000-10000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
10000
San Envirotech Pvt. Ltd.-Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 4-24
Figure 4.6
Isopleths for Ground Level Concentrations for NH3
-10000 -8000 -6000 -4000 -2000 0 2000 4000 6000 8000 10000-10000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
10000
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-1
Chapter-5 Environnent Management Plan
5.1 Introduction
Assessment of environmental and social impacts arising due to
implementation of the proposed project activities is at the technical
heart of EIA process. An equally essential element of this process is
to develop measures to eliminate, offset or reduce impacts to
acceptable levels during implementation and operation of projects.
The integration of such measures into project implementation and
operation is supported by clearly defining the environmental
requirements within an Environmental Management Plan (EMP).
From the previous chapter it can be said that the proposed expansion
project of M/s. Asahi Songwon Colors Ltd. has significantly less
pollution potential. For abatement of environmental pollution, the
unit would adopt several measures, which are summarized under in
this chapter.
Since M/s. Asahi Songwon Colors Ltd. is the existing unit and already
have well developed and efficient Environmental Management Plan.
This will be modified/ upgraded as per requirement after the
proposed expansion.
5.2 Objective of Environmental Management Plan
The objective of the Environmental Management Plant is summarized
hereunder,
• To limit/reduce the degree, extent, magnitude or duration of
adverse impacts
• To treat all the pollutants i.e. liquid effluent, air emissions and
hazardous waste with adoption of adequate and efficient
technology
• To comply with all the norms and standards stipulated by
Gujarat Pollution Control Board / Central Pollution Control Board
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-2
• To create good working conditions
• To reduce any risk hazards and design the disaster management
plan
• Continuous development and search for innovative technologies
for a cleaner and better environment
5.3 Components of EMP
EMP for the proposed expansion project of Asahi Songwon Colors Ltd.
covers following aspects:
• Description of mitigation measures which are proposed for
proposed operation phase only
• Description of monitoring program
• Institutional arrangements
• Implementation schedule and reporting procedures
All above aspects and objectives are kept in the view and considering
the same EMP is prepared for two major fields,
5.3.1 Environmental Management systems
M/s. Asahi Songwon Colors Ltd. is well aware of environmental
requirements for planning and implementation of the project and set
up a department with trained personnel headed under the qualified
environmental manager. As indicated in the impact and mitigation
chapter of this report, the environmental impact due to the proposed
expansion is very marginal release of pollutants due to proposed
expansion.
5.3.2 Environmental, Health and Safety Management System
Chemical Industries prefer an integrated approach and make
environmental management a part of overall Environment, Health
and Safety (EHS) Management system.
This model EHS system suggests and addresses EMS issues such as:
- Management system expectation
- Management leadership, responsibilities and accountability
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-3
- Risk assessment and management
- Compliance and other requirements
- Personnel, training and contractor services
- Documentation and communications
- Facilities design and construction
- Operation, maintenance and management
- Community awareness and emergency response
- EHS performance monitoring and measurement
- Incident investigation reporting and analysis
- EHS management system audit
- Management review and audit
With this type of EHS management approach, proposed expansion of
project would be able to integrate the requirements of ISO-14001
into the overall management system.
5.4 Environmental Management during Construction Phase
Since M/s. Asahi Songwon Colors Ltd. is the existing unit and
proposed expansion will be carried out in the same premises. No
major excavation work will be carried out. Minor activities for the
installation of new additional machineries/equipments will be carried
out. Thus, impact will be temporary and negligible.
Minor construction for installation work shall generate noise and dust
will generate within working areas. Therefore, measures will need to
taken to protect workers.
In order to mitigate the adverse environment impact due to the
construction phase, regular sprinkling of the water will be
recommended along with the construction activities.
5.5 Environmental Management during the Operational Phase
5.5.1 Air Environment
The main Sources of the Air Pollution from the existing industrial
activities are flue gas emission and process gas emission. After
proposed expansion there will one boiler and two thermic fluid
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-4
heaters will be added. The flue gas emission is from the common
stack attached to steam boiler and Six nos. of thermic fluid heaters
due to combustion of fuel which are attached to three stack. Whereas
the process gas emission is from the one process gas stack attached
to process vessels (1 to 4), second process stack attached to Process
Vessel (5 to 6) and three process stack attached to spin flash dryers.
The major air pollutants, identified from this industry, will be PM, SO2
and NOx due to flue gas emission & NH3, Cl2 & HCl from process
vent. Generated Ammonium Carbonate and HCl as by products will
be sold to actual users as per the guideline of GPCB.
However, in order to achieve the reduction, it is suggested that
during operational phase regular maintenance and periodic tuning of
the burner system should be done to ensure proper atomization and
subsequent minimization of any unburned combustibles. Besides
reduction in particulate emissions, it would also result in better
operating efficiency of Bag Filter
For this, combustion process may be further improved by adopting
following measures:
I. Optimization of combustion aerodynamics should be done using
a flame retention device.
II. Re-circulation of flue gas may be considered to achieve the
triple goals of low PM emissions, low NOx emissions and high
thermal efficiency.
III. Primary flame zone O2 level should be decreased by decreasing
overall O2 level, controlling (delaying) mixing of fuel and air,
and use of fuel-rich primary flame zone.
Flue gas volume should be checked for amount of air needed for the
complete combustion of the fuel.
The unit during operation phase may also implement energy
conservation measures through installation of heat recovery systems.
This would reduce the fuel consumption and in turn the emissions.
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-5
The unit proposes to install Beg Filter to the steam boiler whereas
three stage water scrubber to the process gas stack as air pollution
control system, which will be adequate to meet the stipulated
gaseous emission norms.
The unit will also provide adequate stack monitoring facilities for the
periodic monitoring of the stack to verify the compliance of the
stipulated norms.
5.5.2 Action plan to control ambient air quality:-
Following measures taken by us to control the air quality as per the
NAAQES standards notified by the Ministry on 16th September, 2009.
• Effective implementation of air pollution control measures and
monitoring.
• Ammonia recovery by cooling systems to reduce fugitive
emission.
• Effective scrubbing systems will be installed to control un-
recovered ammonia.
• Proper air pollution control systems like dust collector-bag filter
are installed.
• Material handling systems will be designed to avoid any
spillage.
• Development of greenbelt.
• Improve internal road condition etc.
5.5.3 Green Belt
In order to minimize the air pollution the unit has already developed
green belt on and around its premises. And, now proposes to expand
its green belt area considering the following guidelines,
i) Green cover should be created at all the available open spaces.
ii) To make green belt dense more trees are to be planted at all
patches where plantations already exists.
iii) Strict surveillance is made to increase the survival rate of the
trees.
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-6
iv) Plants with higher height, medium and low height should be
planted to ensure thick belt for attenuation of fugitive emission.
This activity demands expert advice and guidance.
5.5.4 Measures to control the fugitive emissions
The fugitive emissions of VOCs emitted from leakage through valves,
fittings, pumps, etc. Excess use of solvent may also results in the
fugitive emission from the process vessels.
Since this is the existing unit it can be seen that there is no major
source of fugitive emission from the process plant. However, the unit
has adopted adequate measures for the minimization/prevention of
the fugitive emission.
The unit has adopted following measures, which will be continued
after proposed expansion.
• Regular maintenance of valves, pumps and other equipment to
prevent leakage and thus minimize the fugitive emissions of
VOCs.
• Entire process is carried out in the closed reactors with proper
maintenance of pressure and temperature.
• Regular periodic monitoring of work area to check the fugitive
emission.
In case modernisation is undertaken by Asahi Songwon Colours Ltd.,
design features as suggested in Table 5.1 for new equipment may
be considered.
5.5.5 Water Environment
Since most of the industrial activities will be remained same after
proposed expansion, except increased in wastewater generation from
process & utilities. However, after proposed expansion the industrial
wastewater generation will be reduce due to recycling of treated
wastewater.
The unit is also going to continue its current practice of the
wastewater management and entire quantity of the industrial
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-7
wastewater will be segregated into three parts depending upon the
concentration. Entire quantity of industrial waste water will be
treated at its own ETP after and finally discharged into ECP channel
which convey the treated effluent into river Mahi Creek.
At present our wastewater discharge is tune around 1482 KL/day
which will be reduced up to 1174 after proposed expansion.
Justification of wastewater reduction after expansion is given in
Figure-2.1(c). (Recycling of water).
The details of the wastewater generation after proposed expansion
and Effluent Treatment plant are depicted in Table-2.4 and Table-
2.5.
To maintain or reduce the wastewater discharge into ECP channel
which convey the treated effluent into river Mahi Creek, unit
proposed to install a RO & Multi effect evaporation systems. The
details of recycling systems are summarized in point no-2.8 and
water balance diagram is work out as per figure-2.1 (b).
5.5.6 Artificial water recharge
The average long-term rainfall, out of which 20% of the rainfall is
considered to go to the ground as a natural recharge and remaining
rainfall runoff and this, is available for the artificial recharge after
accounting for soil moisture storage and evaporation.
We proposed two artificial water recharge well in our premises in low
lying are with due considering to avoid any contamination.
5.5.7 Hazardous/Solid Waste Management
Hazardous/Solid Waste management includes following:
- Measures to minimize waste generation
- Operation of waste handling, treatment and disposal facilities
The Waste Management plan includes:
- Waste Inventory
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-8
- Classification of waste
- Packaging, Storing and Transporting Wastes to Disposal site
- Data Management and Reporting
- Personnel Training
- Waste Minimization
Since the unit is the existing unit and there will not any major
change in industrial activities after proposed expansion. The unit has
also provided adequate hazardous waste management system, which
will be continued after proposed expansion. The ETP sludge will be
sent to TSDF site operated by M/s. Naroda Enviro Projects Ltd.
(NEPL), Ahmedabad for final disposal.
Whereas discarded bags/liners/drums/barrels will be decontaminated
and reused/sold to approve vendors and spent/waste oil will be
reused as lubricant/sold to MoEF approved registered recyclers.
The unit has also provided isolated area for the storage of hazardous
waste with roof cover and impervious floor.
The unit also maintains the records for the hazardous waste storage
and disposal.
Entire quantity of hazardous is handled as per Hazardous Waste
(Management, Handling & Transboundary Movement) Rules 2008.
5.5.8 Noise Control Technique
At present the main source of noise pollution is boiler/Thermic fluid
heater, vehicular transportation and plant & machinery.
There will be slight increase in noise level due to proposed
manufacturing activities, due to installation of some new additional
mechanical equipment required for the proposed expansion including
power plant.
However, to minimize the noise pollution the unit proposes the
following noise control measures,
Noise suppression measures such as enclosures, buffers and/or
protective measures should be provided (wherever noise level is
more than 90 dB(A).
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-9
Employees should be provided with ear protection measures like
earplugs or earmuffs. Earplug should be provided to all workers
where exposure is 85 dB (A) or more.
The transportation contractor shall be informed to avoid unnecessary
speeding of the vehicles inside the premises.
Extensive oiling, lubrication and preventive maintenance will be
carried out for the machineries and equipments to reduce noise
generation.
The selection of any new plant equipment will be made with
specification of low noise levels.
Areas with high noise levels will be identified and segregated where
possible and will include prominently displayed caution boards.
The green belt area will be developed within industrial premises and
around the periphery to prevent the noise pollution in surrounding
area.
Monitoring of noise levels is essential to assess the efficacy of
maintenance schedules undertaken to reduce noise levels and noise
protection measures. A good quality digital sound pressure level
meter is essential for this purpose.
5.5.9 Green Belt Development
Tree plantation is one of the effective remedial measures to control
the air pollution and noise pollution. It also causes aesthetics
improvement of the area as well as sustains and supports the
biosphere.
Plantation around the pollution sources control the air pollution by
filtering the air particulate and interacting with gaseous pollutant
before reaches the ground.
Each plant shows different air pollution tolerance level depending
upon number of factors. In green belt area about 1000 trees per acre
of land as prescribed by Gujarat Pollution Control Board shall
planted. The selection of tree species suitable for plantation at the
industry shall be governed by following factors,
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-10
• The trees should be tolerant to air pollutants present in the
area
• The trees should be able to grow and thrive on soil of the area,
be evergreen, inhabitant, having minimum of leaf fall.
• The trees should be tall in peripheral curtain plantation and
with large and spreading canopy in primary and secondary
attenuation zone
• It is also recommended to plant few trees, which are sensitive
to air pollution as air pollution indicator.
The unit has already developed the green belt on 5475 sq mt. area
which will be increased up to 29850 sq. mt. after proposed
expansion.
5.6 RESOURCE CONSERVATION/ WASTE MINIMIZATION
The units shall also implement the concept of waste minimization
circle including:
• By-products recovered and reused.
• Good House Keeping: Proper house keeping practices makes the
system easier and less costly. Some of these are as follows:
• Solid wastes e.g. powders, spills, etc. in process, and packaging
are to be separately collected and disposed off instead of allowing
these to effluent streams. This will reduce load and increase the
efficiency of treatment system.
• Liquid wastes from various sections should be collected and treat
with effluents.
• Rain water harvesting system shall be adopted to reduce the fresh
water requirement.
• Cleaner production technology shall be adopted for the resource
conservation and pollution control.
5.7 HEALTH & SAFETY
M/s. Asahi Songwon Colors Ltd. has followed occupational health
program right from the start of production.
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-11
Health hazards associated with occupation are called occupational
hazard. The following check-ups shall be carried out regularly to
avoid occupational hazard,
• Pre-employment medical check-up at the time of employment
• Provision of periodic medical check up for all the employees
• To provide necessary first aid facilities. The first aid training
shall also be given to the employees
• Monitoring of occupational hazards like noise, ventilation,
chemical exposure shall be carried out at frequent intervals.
• The unit will be appoint the medical officer for the regular
medical examination and treatment of the employee
The following precautions shall be taken to avoid foreseeable
accident like spillage, fire and explosion hazards and to minimize the
effect of any such accident and to combat the emergency at site level
in case of emergency.
• Various emergency spots in plant area will be identified and
kept in sharp and alert watch.
• Protective equipments will be regularly checked and will be
kept easily accessible and easily workable during emergency
• Safety installations like available quantity of running water will
be regularly watched.
• Fire bucket and hose reels will be provided to withstand the fire
or explosion conditions
• Various types of fire extinguishers such as (Foam type, water
CO2 type, CO2 type) will be provide inside the factory premises
• Every pressure vessel will be provided with minimum one or
more pressure relief devices. The design of the valve is made
in such a way that the breakage of any part will not obstruct
force discharge of the liquid under pressure. Moreover, relief
valves are tested and a periodic schedule for their testing shall
be maintained. The defective valves will be removed if found
unsafe for the operation
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-12
5.7.1 Possibility of occupational health hazard & its control
Following are major health hazards involve in our proposed
activities mainly
Chemical agents: There are possibility to generate gases,
vapours, liquids and aerosols (dusts, fumes, mists). We will take
care to reduce it at optimum minimum level and advices to workers
to use PPE who work in such identify area.
Noise & Heat: Noise is considered as any unwanted sound that
may adversely affect the health and well-being of individuals or
populations. Aspects of noise hazards include total energy of the
sound, frequency distribution, duration of exposure and impulsive
noise. Hearing acuity is generally affected first with a loss or dip at
4000 Hz followed by losses in the frequency range from 2000 to
6000 Hz. Noise might result in acute effects like communication
problems, decreased concentration, sleepiness and as a
consequence interference with job performance. Exposure to high
levels of noise (usually above 85 dB(A)) over a significant period of
time may cause both temporary and chronic hearing loss.
Permanent hearing loss is the most common occupational disease
in compensation claims.
In our case there will be no high noise level issue or heat or
radiation. However we will identify such are like D.G. Sets, utilities
area and advice to workers to not enter without PPE.
Occupational surveillance involves active programmes to anticipate,
observe, measure, evaluate and control exposures to potential
health hazards in the workplace. Depending upon the occupational
environment and problem, two surveillance methods can be
employed: medical and environmental. Medical surveillance is used
to detect the presence or absence of adverse health effects for an
individual from occupational exposure to contaminants, by
performing medical examinations and appropriate tests.
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-13
Environmental surveillance is used to document potential exposure
to contaminants for a group of employees, by measuring the
concentration of contaminants in the air, in bulk samples of
materials, and on surfaces.
Medical surveillance is performed because diseases can be caused
or exacerbated by exposure to hazardous substances. We will
appoint part time doctor who are knowledgeable about occupational
diseases, diagnoses and treatment.
5.7.2 Preventive Measures
The methods of protecting the work force from exposure to toxic
agents in the workplace apply to the use of solvents:
• Segregation of processes using solvents;
• Enclosures or special ventilator control of processes;
• Good general ventilation — particularly important if the solvent
is used in a confined space;
• Personal protection — Protective clothing should be worn,
including gloves, where there is a possibility of absorption
through the skin. Suitable respiratory protection is necessary
like Panorama gas mask with cartridge suitable for the
chemicals we will be handling, Breathing Air Apparatus and Air
Hood with instrument air connection.
• Gas detector with emergency alarm systems in confined area.
Emergency preparedness plan
5.7.3 Occupational Health Programme
Some of the philosophies underlining the occupational health
programme are discussed below:
Asahi Songwon Colors Ltd. has employed well qualified and
experienced safety Manager and makes arrangement for part time
doctor for regular checking of health of the employees. Also, plans
to become member of any local hospital for emergency need.
Annual health check for employees will be carried out and record
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-14
will be maintained. Regular training to plant personnel in safety fire
fighting and first aid will be provided.
Unit will maintain a healthy work environment. This will be
accomplished through the identification, evaluation and control of
workplace environmental factors which may cause sickness,
impaired health or significant discomfort and inefficiency among
workers. Environmental factors such as noise, physical hazards
toxicity/ chemical hazard and ergonomic hazards will be monitored
on a periodic basis to assist in maintaining a healthy work
environment. Workers exposed to noise and toxic materials will be
evaluated against applicable recognised exposure levels in the
Factories Act. Hearing protection aid will be provided to workers
who work in the high noise areas, during construction of the
proposed facilities and also to those who will continue through the
life of the facility.
5.7.4 Hazard Communication and Chemical Safety
Asahi Songwon Colors Ltd. proposed expansion project will
communicate to its workers information on hazards of the materials
used to its workers.
A hazardous chemical directory is being developed to maintain
information on the hazards associated with each chemical used.
Copies of Material Safety Data Sheets for all hazardous materials at
the existing/proposed facility will be kept at the unit and will be
available for employee review. Specific programs and procedures
for the control of health hazards associated with potentially harmful
materials such as Acids, Alkali and volatile chemicals etc. Will
follow the guiding principles established for Occupational Health.
The hazard communication program will serve as the basis for
selection of personal protective equipment such as gloves, goggles,
face shields, etc. A select group of employees at the proposed
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-15
facilities will receive first aid training to provide an immediate
response and medical care for injuries.
5.8 POST-PROJECT ENVIRONMENTAL MONITORING
The post – project environmental monitoring suggested herewith
should be as per the following guideline. The highlights of the
integrated environmental monitoring plan are:
• The stack monitoring facilities like ladder, platform and port –
hole of all the stacks maintained in good condition.
• Regular monitoring of all gaseous emissions from stacks/ vents
and all fugitive emissions in the process areas.
• The performance of air pollution control equipment evaluated
based on these monitoring results.
• Water consumption in the complex recorded daily.
• Analysis of untreated and treated effluent, before discharge
into the final disposal pipeline carried out regularly.
• Performance of effluent treatment plant units evaluated based
on these analysis results.
• As far as possible, noise curbed at its source, with the help of
acoustic hoods and other such noise reducing equipment.
Regular noise level monitoring carried out.
• Green belt properly maintained and new plantation
programmes undertaken frequently.
• Continued environmental awareness programmes carried out
within the employees and also in the surrounding villages.
• Rain water harvesting ponds will be developed within the
industrial premises and encouraged in the surrounding villages
too. All possible back–up and support provided to them.
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-16
Ambient Air Quality Monitoring
Schemes for monitoring ambient air quality stack emissions and
fugitive emissions are proposed. The ambient air quality monitoring
systems are recommended for monitoring the ground level
concentrations and fugitive emissions around the plant. Asahi
Sogwon should install three monitoring stations around its battery
limit (at 1200 as per guideline) for monitoring SPM, SO2 and NOx.
The combined data will provide overall characteristic and emission
from the industry. For this, the following equipment is recommended
to be procured or can higher the services from Environmental
consultant by the project proponent for implementing the above
mentioned monitoring schemes:
Respirable Dust sampler
Blower -1.0-1.3 m3/min capacity with adapter for uniform suction
through filter and a properly calibrated manometer assembly for the
determination of flow rate through filter paper
Rota meter- For gaseous sampling, calibrated Rota meter (0-5 LPM)
for maintaining flow rate should be provided
Main housing-The main housing should be rectangular with a stand
of about 1.25 m height.
Besides this, stack emissions monitoring as per GPCB guidelines shall
be carried out.
Noise Environment
Monitoring of noise levels is essential to assess the efficacy of
maintenance schedules undertaken to reduce noise levels and noise
protection measures. A good quality digital sound pressure level
meter is essential for this purpose.
Water Environment
Wastewater is being analyzed at the ETP discharge regularly and
should continue after the expansion also.
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-17
Table 5.1
Design features for minimization of fugitive emissions
S.
No.
Equipment Design Features Control Efficiency
%
Sealless design 100 1 Pumps
Dual Mechanical Seal 100
2 Valves Sealless Design 100
3 Compressor Dual Mechanical Seal 100
4 Connectors Weld together 100
5 Pressure Relief
Devices
Rupture Disc 100
6 Sampling Connection Closed loop sampling 100
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-18
Table 5.2 Environment Monitoring
Nature of Analysis Frequency of
Analysis
Number of Sample
Stack Monitoring of
each stack
Monthly At all stack
Ambient Air Quality
Monitoring
Monthly for 24 hours
or as per the statutory
conditions.
3 Location
Work place area for
Fugitive emission
Monthly 5 to 6 location
Industrial Effluent for
applicable parameters
as per the Consents
Conditions
Ones in a Month One Sample
San Envirotech Pvt. Ltd.- Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 5-19
Figure 5.1
EHS Management
Technical Director
Vice President (Operation)
Supervisors/operator
EHS Manager
ETP Chemist
Environmental Chemist
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-1
Chapter-6
Quantitative Risk Assessment 6.1 Introduction
The risk assessment studies have been conducted for identification of
hazards, to calculate damage distances and to spell out risk
mitigation measures.
Asahi Songwon Colors Ltd. is the existing unit located at survey no.
429 to 432, village: Dhudhwada, Taluka: Padra, Dist.: Vadodara,
State: Gujarat. Now, the unit proposes to expand its production
capacity of CPC Blue and Pigment Beta Blue-A/B in existing product
with capacity of 850 MT/month & 100 Mt/Month respectively. Now
Unit envisage to increase the production capacity of CPC Blue from
850 Mt/Month to 1000 MT/month, Pigment Beta Blue from 100
Mt/Month to 500 Mt/Month with introduce of three new product –
Pigment Alpha Blue with 60 MT/month, Pigment Violet–23 with 25
Mt/Month and Pigment Green–7/36 with 200 Mt/Month.
6.1.1 Scope Of Study
The scope of work is to carry out risk analysis for the proposed
expansion of plant covering all the hazardous chemicals to be
handled and stored at the plant after expansion.
6.1.2 Study Objective
The objective of the risk analysis includes the following:
• Identification of hazards
• Selection of credible scenarios
• Consequences Analysis of selected accidents scenarios
• Risk Mitigation Measures
6.1.3 The Study Approach
The risk assessment study broadly comprised of the following steps:
• System Description
• Identification of Hazards
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-2
• Selection of Credible Accident Scenarios
• Consequence Analysis
• Risk Mitigation Measures
6.1.4 System Description
This step comprised the compilation of the location, design and
operational information needed for the risk analysis.
6.1.5 Identification of Hazards
Hazards associated with the plant after expansion was identified.
Summary of relevant accident cases was reviewed.
6.1.6 Risk Reduction Measures
Based on hazard identification and consequence analysis, risk
reduction measures were suggested to reduce risk and enhance
safety at the plant.
6.2 PROBABLE HAZARDS & RISK
Hazard identification and risk assessment is carried out through
careful study of plant process. Following this various scenarios by
which an accident can occur are then determined. Concurrent study
of both probability and the consequences of an accident are carried
out and the final risk assessment is made. Since chemical & fuel
posses’ different kind of hazard, both have been separately
associated. The chemicals poses more of Occupational Health Hazard,
while fuel posses more of safety / accidental hazards. Hazard & risk
assessment has been carried out for exposure to harmful dust /
vapors, liquid pool evaporation or boiling and leakage’s in confined
space.
6.3 HAZARDOUS IDENTIFICATION
Hazard is defined as a chemical or physical conditions those have the
potential for causing damage to people, property or the environment.
Hazard identification is the first step in the risk analysis and entails
the process of collecting information on:
• The types and quantities of hazardous substances stored and
handled,
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-3
• The location of storage tanks & other facilities,
• Potential hazards associated with the spillage and release of
hazardous chemicals.
6.3.1 Hazardous Substances to be handled at Asahi Songwon
Colors Ltd.
M/s Asahi Songwon Colors Ltd. has been engaged in handling and storage of
various flammable and toxic hazardous materials. Important characteristic of
these hazardous materials are described in details below:
Chlorine gas
Chlorine is a toxic gas (B. P. is -34oC). In liquefied form chlorine is a
clear amber dense liquid. The gas is greenish-yellow, about 2.5 times
as dense as air, and non-flammable. Liquid chlorine causes severe
irritation and blistering of skin. The gas has a pungent suffocating
Odour and is irritant to the nose and throat. It is an extremely
powerful vesicant and respiratory irritant.
Typically, exposure to chlorine concentrations of 3 - 6 ppm results in
a stinging and burning sensation in the eyes. Exposures for 0.5 -1
hour to concentrations of 14-21ppm cause pulmonary oedema,
pneumonitis emphysema and bronchitis. This is usually associated
with marked bronchospasm, muscular soreness and headache. Whilst
there is inevitably a variation in individual susceptibility, typically 4
ppm is the maximum concentration that can be breathed for one
hour without any damage, 40-60 ppm is dangerous for a 30-minute
exposure and a concentration of 1000 ppm is likely to be fatal after a
few breaths. IDLH (immediately Dangerous to Life and Health) value
for chlorine is 10 ppm. Permissible limit in exposure of chlorine in
work environment under Factories Act, 1948 is 1 ppm Time Weighted
Average (TWA) Concentration (8 hours).
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-4
Isobutyl Alcohol:
Isobutyl Alcohol is flammable liquid. Harmful if swallowed, inhaled or
absorbed through skin. Affects central nervous system, causes
irritation to skin, eyes and respiratory tract.
Appearance: Clear, colorless solution.
Odor: Sweet-musty odor.
Solubility: 9.5g/100ml water @ 200C
Specific Gravity: 0.803
% Volatiles by volume @ 210C: 100
Boiling Point: 1080C
Melting Point: -1080C
Vapor Density (Air=1): 2.6
Vapor Pressure (mm Hg): 8.8 @ 20C (68F)
Sulphuric Acid:
Sulphuric acid is a colorless to yellowish highly corrosive liquid.
Poison, danger and corrosive. Mist causes severe burns to all body
tissue. May be fatal if swallowed or contacted with skin harm full if
swallowed. Avoid substance contact. Do not inhale vapors/aerosols.
Ensure supply of fresh air in enclosed rooms. Do not allow
unprotected person to handle material. Main Physical properties of
Sulphuric acid are summarized bellows
Physical state : Liquid
Specific gravity : 1.5
pH value at 49g/l H2O at 25 0C : 0.3
Color : Colorless
Odor : Odorless
Boiling point : ~310 0C
Freezing point : -42 0C
Melting point : ~ -15 0C
Bulk density : 1.5 g/ml
Vapor pressure at 20 0 C (mm) : ~0.0001hPa
Solubility in water at 20 0C : soluble
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-5
Thermal decomposition : ~338 0 C
Caustic Lye:
Caustic is a colorless liquid. Harmful if swallowed or inhaled Causes
burns to any area of contact. It is not considered to be fire hazard.
Do not handle without PPEs. Use safety goggles, Gumboots, PVC
hand gloves and rubber apron if required. Main Physical properties of
Sulphuric acid are summarized bellows
Molecular formula : NaOH
Appearance : Clear Soapy Liquid
Odor : Odorless
Boiling point : 1480C
Vapor pressure at 400C : 3.6 mm Hg
Bulk density : 1.5 g/ml
pH : Highly alkaline
Specific gravity : 2.12
Liq. Ammonia
Ammonia is a colorless gas and adsorb into water to convert
Ammonia solution. It has penetrating, suffocating odor. It is stable
and hydroscopic in nature. Toxic by inhalation or skin contact - may
be fatal if inhaled. Physical properties are summarized bellow.
Appearance : colorless
Odor : Penetrating & suffocating
Melting point : -77.70C
Boiling point : -33.30C
Vapor density : 0.89 g/l
Vapor pressure : 0.597
Specific gravity : 0.77
Flash point : 110C
Explosion limits : 16% - 25%
Water solubility : High
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-6
6.4 QUANTITIES OF HAZARDOUS MATERIALS
As mentioned in Section-6.3, various hazardous chemicals will be
used and stored at the plant in small to large quantities as per
requirement. As per Manufacture, storage and Import of Hazardous
Chemicals rules 1989 and amendment subsequently, there will be
only few hazardous chemicals, which have potential for creating risk
to life and property in an unlikely event of leakage or spillage
followed by fire.
The hazardous chemicals are stored at the plant in tank with
adequate dyke. Other chemicals will be stored in cylindrical tanks,
barrels and carboys. Details of storage of hazardous materials are
given in Table - 6.1.
Table - 6.1: Facilities for Storage of Chemicals
Name of Chemical Quantity, MT/month MOC Storage
Facility
Sulphuric Acid (98%) 75 MS Above GL
Spent Acid (20-22%) 100 MSRL/FRV Above GL
LAB (Solvent) 120 SS Claded Above GL
Iso butyl Alcohol 30 SS Claded Above GL
Chlorine or Bromine
207 MS Cylinder
Xylene 30 SS Claded Above GL
Nitric Acid
25 MS Drum
6.4.1 Probable Hazards & Risk
From the preliminary risk assessment study carried out for Asahi
Songwon unit some of the possible hazards have been identified. The
likely accident scenarios considered are given below:
S. No.
Scenario Vulnerability Zone
Remarks
1. Spill of Solvent
Area close to spill area
Isolate the area immediately and ensure no ignition source
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-7
/Acids comes nearby. Reclaim the material if possible or cover the spill with sand/mud /foam (to be safely disposed off later)
2. Toxic Liquid Leakage/ Spillage in Confined Space
Confined Area Spillage to be mopped up, decontaminated (if required) and disposed of as per norms. Fresh Air inlet / Ventilation System to be fully opened. Ventilation Exhaust will carry harmful vapors. Personnel to avoid contact with exhaust vapors. Exhaust to be released at safe elevation.
3. Flammable liquid tank in tank farm on fire
Area adjoining to tank periphery/ other tanks in tank farm
Deluge all adjoining tanks till fire stops and heat is dissipated. Transfer/neutralize the spillage (if any).
The above mentioned hazards scenarios can further aggravate into
much more serious incidents if not intercepted in time. The fire in
one tank of tank farm can spread to adjoining tanks and may result
in explosions. The vulnerability zone will be considerably enlarged.
The vapors of toxic fluids/dust if carried away by wind above TLV
concentrations may further enlarge the vulnerability zone. Similarly,
toxic fluid spillage and all wastes leaving the live processing zone if
not decontaminated properly can cause serious health hazard to
plant personnel and persons in nearby area.
6.4.2 Hazards Due to Loss of Containment
In the event of leakage or accidental release of above mentioned
hazardous chemicals, it will create localized effects within the short
distances in side the plant. Adequate safety measures including fire
fighting facilities will be provided to attend any emergency for these
hazardous chemicals. Among the hazardous inventories, Ammonia
gas from process is toxic gas and in unlikely event of release, toxic
vapour cloud may form and move on site or even off site of the plant.
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-8
6.4.3 Release of Chlorine
In the event of release of chlorine from 900 kg cylinders, cloud of
toxic gas will be formed and moved towards wind direction. The IDLH
(Immediately Dangerous to Life and Health) concentration value for
10 minutes exposure has been taken as the criteria for the ‘wounded’
category.
6.4.4 Release of Flammable Materials
Solvents and flammable materials will be stored in tanks of various
sizes at the plant to meet the process requirements. Suitable dyke
have been provided for loss of containment. At the time of leakage,
pool will be form in dyke and in an unlikely event of fire thermal
radiation may cause damage to life and property.
6.4.5 Effect & Consequence Analysis
As a part of risk assessment study maximum credible accident
analysis (MCA) is carried out to determine the maximum loss
scenario from this analysis. It is an eventuality which is possible and
will have maximum consequential distances for the particular
hazardous chemicals under evaluation.
The selection of the accident scenarios is based on the engineering
and professional judgment, accident descriptions of the past in
similar type of plants & the expertise in risk analysis studies.
6.4.6 Maximum Credible Accident Scenarios
M/s. Asahi Songwon Colors Limited is dealing with many hazardous
substances. Most of hazardous chemicals are solvents and will not
create major threat to life and property in the event of spillage as
dykes have been provided for full containment. Subsequently their
consequence will be confined within short distances.
Chlorine is major toxic hazardous. Chlorine is stored in 900 kg
cylinders. In an unlikely event of accidental release of chlorine, toxic
cloud will be formed and moved to towards wind directions.
For the selection of maximum credible accident scenarios following
methodology have been adopted:
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-9
6.4.7 Methodology for Selection of Accident Scenarios
In this study the following steps were followed for scenario selection
for risk analysis study:
• The hazardous materials handled at Asahi Songwon Colors Limited
and the associated hazards were identified and assessed.
• Operating and storage conditions of handling and storage of
hazardous materials were studied.
An assessment was made of what inventories can get released
accidentally.
Sl. Type of
Release
Outcome Cases
Considered
1. Spill of Solvent /Acids
Area close to spill area
Isolate the area immediately and ensure no ignition source comes nearby. Reclaim the material if possible or cover the spill with sand/mud /foam (to be safely disposed off later)
2. Toxic Liquid Leakage/ Spillage in Confined Space
Confined Area Spillage to be mopped up, decontaminated (if required) and disposed of as per norms. Fresh Air inlet / Ventilation System to be fully opened. Ventilation Exhaust will carry harmful vapors. Personnel to avoid contact with exhaust vapors. Exhaust to be released at safe elevation.
3. Flammable liquid tank in tank farm on fire
Area adjoining to tank periphery/ other tanks in tank farm
Deluge all adjoining tanks till fire stops and heat is dissipated. Transfer/neutralize the spillage (if any).
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-10
6.5 MAXIMUM CREDIBLE ACCIDENT SCENARIOS
Following maximum credible scenarios have been selected for
consequence analysis as a result of accidental releases:
6.5.1 Consequence Analysis
Consequence analysis for the selected accident scenarios has been
carried to estimate the vulnerable zones. When the vulnerable zone
is identified for failure cases, measures can be taken for risk
mitigation measures and to eliminate damage to the plant and injury
to personal.
6.5.2 Release of Chlorine
In the event of release of chlorine from 900 kg cylinders, cloud of
toxic gas will be formed and moved towards wind direction. The IDLH
(Immediately Dangerous to Life and Health) concentration value for
10 minutes exposure has been taken as the criteria for the ‘wounded’
category.
6.5.3 Effect & Consequence Analysis
As a part of risk assessment study maximum credible accident
analysis (MCA) is carried out to determine the maximum loss
scenario from this analysis. It is an eventuality which is possible and
will have maximum consequential distances for the particular
hazardous chemicals under evaluation.
The selection of the accident scenarios is based on the engineering
and professional judgment, accident descriptions of the past in
similar type of plants & the expertise in risk analysis studies.
6.5.4 Maximum Credible Accident Scenarios
M/s. Asahi Songwon Colours Limited is dealing with many hazardous
substances. Most of hazardous chemicals are solvents and will not
create major threat to life and property in the event of spillage as
dykes have been provided for full containment. Subsequently their
consequence will be confined within short distances.
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-11
Chlorine is major toxic hazardous. Chlorine is stored in 900 kg
cylinders. In an unlikely event of accidental release of chlorine, toxic
cloud will be formed and moved to towards wind directions.
For the selection of maximum credible accident scenarios following
methodology have been adopted:
6.5.5 Consequence Analysis for Chlorine Release Scenarios
Scenario Description
Catastrophic failure of the chlorine cylinder from valve will result in a
release of chlorine gas. The released chlorine gas will flash
vigorously. Toxic vapour cloud of chlorine gas will be formed which
will be dispersed in the prevailing wind direction. For atmospheric
dispersion of chlorine “heavy gas dispersion model” has been used.
Outcome: Toxic Vapour Cloud of Chlorine
Results of dispersion modelling of chlorine gas and atmospheric
conditions using Heavy Gas Instantaneous Gas Release Model for 10
ppm (IDLH) concentration at cloud boundary are given below, for day
time atmospheric stability conditions B & D and for night time
stability condition E.
I. Chlorine Gas Cloud Size and Location for 10 PPM (IDLH)
Concentration in Unstable Atmospheric Conditions
Catastrophic failure of the chlorine cylinder will result in a release of
Cl2 and toxic vapour cloud will be formed which will be dispersed
towards prevailing wind direction. For atmospheric dispersion of
chlorine “heavy gas dispersion-Instantaneous gas release” has been
used.
Atmospheric Conditions
Temperature : 35oC
Average Wind speed : 2 m/s
Stability Conditions : B
Model Output Information
Size of chlorine gas cloud and its location with Cl2 concentration of 10
PPM (IDLH) at cloud boundary.
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-12
Time t after Start of Cl2 Release (s) : 120
Maximum Width of Vapour Cloud (m) : 92
Maximum Length of Vapour Cloud (m) : 239
Minimum Distance to Threshold Concentration (m) : 116
Maximum Distance to Threshold Concentration (m) : 355
II. Chlorine Cloud Size and Location for 10-PPM (IDLH)
Concentration in Neutral Atmospheric Conditions
Catastrophic failure of the chlorine cylinder results in a release of Cl2
and toxic vapour cloud will be formed which will be dispersed in the
prevailing wind direction. For atmospheric dispersion of chlorine
“heavy gas dispersion-Instantaneous gas release” has been used.
Atmospheric Conditions
Temperature : 35oC
Average Wind speed : 1 m/s
Stability Conditions : D
Model Output Information
Size of Chlorine cloud and its location with Cl2 concentration of 10
PPM (IDLH) at cloud boundary.
Time t after Start of Cl2 Release (s) : 480
Maximum Width of Vapour Cloud (m) : 148
Maximum Length of Vapour Cloud (m) : 434
Minimum Distance to Threshold Concentration (m) : 150
Maximum Distance to Threshold Concentration (m) : 584
III. Chlorine Cloud Size and Location for 10-PPM (IDLH)
Concentration in Stable Atmospheric Conditions
Catastrophic failure of the chlorine cylinder results in a release of Cl2
and toxic vapour cloud will be formed which will be dispersed in the
prevailing wind direction. For atmospheric dispersion of chlorine
“heavy gas dispersion-Instantaneous gas release” has been used.
Atmospheric Conditions
Temperature : 20oC
Average Wind speed : 1 m/s
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-13
Stability Conditions : E
Model Output Information
Size of chlorine cloud and its location with Cl2 concentration of 10
PPM (IDLH) at cloud boundary.
Time t after Start of Cl2 Release (s) : 480
Maximum Width of Vapour Cloud (m) : 139
Maximum Length of Vapour Cloud (m) : 564
Minimum Distance to Threshold Concentration (m) : 233
Maximum Distance to Threshold Concentration (m) : 797 6.5.6 Catastrophic Rupture of IBA Tank
In the event of catastrophic rupture of IBA tank, fixed pool will be
formed in dyke and in the event of fire, thermal radiation will be
occurred. Outcome of model are summarized below:
Combustion Rate : 0.23 kg/s
Heat Radiation Distance from Fixed Pool Boundary
15 kW/m2 : 2.7 m
12.7 kW/m2 : 3.2 m
10 kW/m2 : 4.0m
3 kW/m2 : 7.4 m
1 kW/m2 (Safe Distance) : 11.0 m
6.5.7 Catastrophic Rupture of Xylene Tank
In the event of catastrophic rupture of Xylene tank, pool will be
formed in dyke and in the event of fire, thermal radiation will be
occurred. Outcome of model are summarized below:
Combustion Rate : 1.12 kg/s
Heat Radiation Distance from Pool Boundary
15 kW/m2 : 4.3 m
12.7 kW/m2 : 5.0 m
10 kW/m2 : 6.2 m
3 kW/m2 : 13.5 m
1 kW/m2 (Safe Distance) : 21.9 m
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-14
6.6 GENERAL SAFETY PRECAUTIONS & OCCUPATIONAL HEALTH:
Safety of plant personnel and equipment’s is of utmost importance
irrespective of plant size. Units should bring its environment, health
and safety policy and follow it. Proper safety procedures are being
followed as far as possible including the use of personal protective
gadgets (hand gloves, dust masks, face shield, goggles, apron etc. as
required) by the workers while charging material manually (if
required) in reaction/purification/washing/storage vessel, operating
filter; flushing the equipment or pipe line; and drawing samples for
analysis to prevent hazardous exposure to worker and to avoid spill
of inflammable chemicals. Avoid contact with the raw materials
(touch, inhale or oral route) with the use of Personal protective
equipment. Prevention is better than cure. Safety of plant personnel
and equipment’s is of utmost importance irrespective of plant size.
Units should bring its environment, health and safety policy and
follow it. Proper safety procedures are being followed as far as
possible including the use of personal protective gadgets (hand
gloves, dust masks, face shield, goggles, apron etc. as required) by
the workers while charging material manually (if required) in
reaction/purification/washing/storage vessel, operating filter;
flushing the equipment or pipe line; and drawing samples for analysis
to prevent hazardous exposure to worker and to avoid spill of
inflammable chemicals. Avoid contact with the raw materials (touch,
inhale or oral route) with the use of Personal protective equipment.
Prevention is better than cure. A schedule has been drawn up for
regular preventive maintenance of each unit and the same needs to
be faithfully followed as far as possible. All the valves, which are
prone to open and spill inflammable / toxic material due to accident
impact, must be placed with suitable guard. The unit's management
should ensure that all rotating machines and moving parts are
provided with appropriate guards and the guards are put back in the
position after check up and maintenance.
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-15
All the control systems are being periodically checked for their
reliability and accuracy.
Ventilation has been provided in process area where chances of build
up of concentration of hazardous chemicals are high to prevent
fire/toxic hazard.
Electrical grounding of all equipment is ensured.
Units' management has identified all hazardous chemicals in use in
the plant and prepared Safety Data Sheets for most of them. Safety
Data Sheets are quite comprehensive and provide important
data/information on physical and chemical properties, fire and
explosive hazards, toxic limits, emergency and first aid measures etc.
6.6.1 Occupational Health and First aid Measures
Units are using a number of chemicals, which if handled in safe ways
with all precautions (as detailed in respective MSDS) will not cause
harm to employees. However in rare case of exposures, immediate
action is to be taken to save life and reduce the extent of damage.
Unit has first aid facilities and calling base ambulance facilities as and
when required. Industry has appointed part time doctor for
periodically health check.
Instructions for immediate actions to exposures to some of the
chemicals will be given to employees.
6.6.2 Risk Reduction Measures
For risk mitigation / reduction, attempts should be made to either
reduce inventories that could get released in the event of loss of
containment or failure likelihood’s or both as feasible. Risk analysis
identifies the major risk contributors, which enables prioritization of
the plant that deserve special attention in terms of inspection and
maintenance in particular and over all safety management as a
whole.
For the risk reduction at Asahi, the following salient suggestions and
recommendations are made:
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-16
• On site and off site emergency response plan should be prepared
and circulated to concern persons.
• Personnel at the proposed plant and public in surrounding area
should be made aware about the hazardous substance stored at
the plant and risk associated with them.
• A written process safety information document should be compiled
for general use.
• The document compilation should include an assessment of the
hazards presented including (i) toxicity information (ii) permissible
exposure limits. (iii) Physical data (iv) thermal and chemical
stability data (v) reactivity data (vi) corrosivity data (vii)
information on process and mechanical design.
• The process design information in the process safety information
compilation must include P&IDs/PFDs; process chemistry;
maximum intended inventory; acceptable upper and lower limits,
pressures, flows and compositions and process design and energy
balances.
• The adequate numbers of chlorine and SO2 gas detectors/sensors
should be provided at strategic locations in the plant and
indication of detectors/sensors should be provided in main control
room.
• A system of checking testing/sealing of relief valves during major
plant overhauls should be instituted for plant equipment,
wherever it is applicable.
• Predictive and preventive maintenance schedule should be
prepared for equipment, piping, etc. and thickness survey should
be done periodically as per standard practices.
• A written procedure (Management of Change) must be developed
to manage changes to process chemicals, technology, equipment
and procedures that affect a covered process.
• Safe work practices should be developed to provide for the control
of hazards during operation and maintenance such as: i. lockout
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-17
/tag out ii. Confined space entry iii. Opening process equipment or
piping iv. Control over entrance into a facility by maintenance,
contractor, laboratory, or other support personnel.
• Personnel engaged in handling of hazardous chemicals should be
trained to respond in an unlikely event of emergencies.
• The plant should check and ensure that all instruments provided in
the plant are in good condition and documented.
• Close loop type fire hydrant system pressurised at 7 kg/cm2 with
jockey pumps should be provided in flammable chemical storage.
• Safety measures in the form of DO and Don’t Do should be
displayed at strategic locations especially in local language and
English.
• Regular mock drills should be carried out once in every 3 months
and shortcomings should be recorded and rectified. Records
should be maintained for the response of Mock Drills and
corrective actions should listed and taken accordingly.
6.6.3 Safe Guards for Storage and Handling of Hazardous
Chemicals
Personal Protective Equipment
Personal protective equipment is devices that are fitted and issued to
each worker personally for his or her exclusive use. They are
intended for temporary use and emergency response action only. If a
worker must enter a contaminated area, he must wear adequate
protective equipment suitable for chlorine service. Employees should
be taught when and how to use respiratory apparatus provided, and
how to recognize defects in the equipment. Full dress escape drills
should be conducted at least once a year. If such safety equipment is
not available, entry into the contaminated area should not be
attempted.
• Keep personal protective equipment where it can be accessed
quickly, outside the chlorine storage area and away from areas of
likely contamination.
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-18
• Employees who work near chlorine must be issued a properly
fitting cartridge type or canister type escape respirator.
• Facial hair should not be permitted for those who are issued
escape-type or self-contained respirators because it prevents a
proper seal.
• Workers should always carry escape type respirators while
working around chlorine.
• Each employee should maintain his/her personal protective
equipment in clean, working condition at all times.
• All equipment should be used and maintained in accordance with
the manufacturer’s instructions.
6.6.4 Handing of Hazards
• Personal protective equipment used by the person during handling
of hazardous chemicals, should be replaced after certain time.
• If any spillage of hazardous chemicals, it should be cleaned and
disposed as per standard practiced.
• Empty drums of hazardous chemicals should neutralize
immediate.
• Personnel engaged in handling of hazardous chemicals should be
made aware of properties of hazardous chemicals.
6.6.5 General Working Conditions
(a) House Keeping
• All the passages, floors and stairways should be maintained in
good condition. The system should be available to deal with any
spillage of dry or liquid chemical at the plant.
• Sufficient disposable bins should be clearly marked and these
should be suitably located in the plant.
• Walkways should be clearly marked and free from obstructions.
• In the plant, precaution and instructions should be displayed at
strategic locations.
• All pits, sumps should be properly covered or securely fenced.
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-19
• Roads/walkway within the plant should be maintained neat and
clean.
(b) Ventilation
• Adequate ventilation should be provided in the work floor
environment.
• The work environment should be assessed and monitored
regularly.
• Local ventilation is most effective method for controlling dust and
gaseous emissions at work floor.
6.6.6 Safe Operating Procedures
• Safe operating procedures should be available for mostly all
operations and equipment.
• The workers should be informed of the consequences of failure to
observe the safe operating procedures.
6.6.7 Work Permit System
Work permit system should be followed at the plant. Hazardous work
permit should be used for hot work, electrical works, etc.
6.6.8 Personal Protective Equipment
Personal protective equipment (PPEs) is devices that are fitted and
issued to each worker personally for his or her exclusive use. They
are intended for temporary use and emergency response action only.
If a worker must enter a contaminated area, he must wear adequate
protective equipment. Employees should be taught when and how to
use respiratory apparatus (SCBA) provided, and how to recognize
defects in the equipment. Without SCBA entry into the contaminated
area should not be attempted.
• Keep personal protective equipment where it can be accessed
quickly, outside the hazardous material storage area and away
from areas of likely contamination.
• Each employee should maintain his personal protective equipment
in clean, working condition at all times.
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-20
• All equipment should be used and maintained in accordance with
the manufacturer’s instructions.
• Equipment installed for body and eye wash should be checked
properly for round the clock operation.
6.6.9 Fire Protection
• Adequate fire fighting facilities should be available at the plant,
including, dry chemical powder type, water CO2 type, mechanical
foam type, CO2 type and sand buckets.
• The fire fighting system and equipment should be tested and
maintained as per relevant standards.
• The fire drills should be conducted once in six months.
6.6.10 Emergency Preparedness
• On-site emergency plan should be prepared and readily available
for an unlikely event of emergency.
• Emergency telephone numbers should be available and display
properly strategic locations.
6.6.11 Static Electricity
• All equipment and storage tanks/containers of flammable
chemicals should be bounded and earthed.
• Electrical resistance for earthing circuits should be maintained.
Periodic inspections should be done for earth pit and record should
be maintained.
6.6.12 Access
• Adequate safe access should be provided to all places where
workers need to work and all such access should be in good
condition.
6.6.13 Material Handling
• Material handling areas should be clearly defined.
• The workers should be made aware about the hazards associated
with manual material handling.
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-21
6.6.14 Communication System
• Adequate communication facilities should be available at the plant
and supported with uninterrupted power supply.
• Communication facilities should be checked periodically for its proper
functioning.
6.6.15 First Aid Facilities
• First box should be provided at strategic locations within the plant.
• At least one stature should be available in first aid room.
• List of important telephone numbers should be displayed in first
aid room.
6.6.16 Management of Change
The system for Management of Change (MOC) should be practiced at
the plant. It is suggested that written procedures should be
developed to manage the changes in process/equipment
/piping/technology. The procedures should assure following
consideration, are addressed prior to any change:
• The Technical basis of the existing change
• Impact of change on safety and health
• Modification to operating procedures
• Necessary time period for change
• Duration of change incase of temporary change
• Authorization requirements for the existing change
Occupational Safety and Health Administration (USA), Regulatory
Check List, 29 CFR 1910.119 may be referred for developing the
system for Management of Change.
6.6.17 Accident Reporting, Investigation And Analysis
A system should be initiated for accident and near miss reporting,
investigation and analysis. To motivate and awareness among the
personnel at the plant about safety, total accident (lost time injury)
free days can be displayed on the board prominently at strategic
location.
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-22
6.6.18 Safety Inspections
The system should be initiated for checklist based routine safety
inspection and internal audit of the plant periodically. Safety
inspection team should be formed from various disciplines and
departments.
6.6.19 Safe Operating Procedures
Safe operating procedures should be formulated and updated,
specific to process & equipment and distributed to concerned plant
personnel.
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-23
Table-6.1: Effects Due To Incident Radiation Intensity
INCIDENT
RADIATION -Kw/M2
TYPE OF DAMAGE
0.7 Equivalent to Solar Radiation 1.6 No discomfort on long duration 4.0 Sufficient to cause pain within 20 sec.
Blistering of skin (first degree burns are likely)
9.5 Pain threshold reached after 8 sec. Second degree burns after 20 sec.
12.5 Minimum energy required for piloted ignition of wood, melting of plastic tubing etc.
Table-6.2 Damages to Human Life to Thermal Radiation
Exposure Duration
Radiation Energy (1%Lethality,
kW/m2)
Radiation Energy for 2nd
degree burns, kW/m2
Radiation Energy for 1st degree burns,
kW/m2 10 sec 21.2 16 12.5 30 sec 9.3 7.0 4.0
San Envirotech Pvt. Ltd. – Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 6-24
Figure-6.1
Procedure for Hazard Identification and Risk Assessment
Process Information
Study
Met. Data
Population Data
Inventory Analysis
FEI and Toxicity Index
Identification of Hazard Prone Areas
Effects Evaluation
Hazardous Units
Checklist Approach
Risk Evaluation
Hazard Survey
Risk Mitigation Measures
EPP
DMP
Report
Process Engg. Details (P&I)
Plot Plan Layout
Data Collection Physical
Properties of Chemicals
Past Accident Data
Env. Opinion Data
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-1
CHAPTER-7
Onsite Disaster Management Plan
7.1 INTRODUCTION
An emergency is said to have arisen when operators in the plant are
not able to cope with a potential hazardous situation i.e. loss of
control of an incident causes the plant to go beyond its normal
operating conditions, thus creating danger. When such an emergency
evolves, chain of events which affect the normal working within the
factory area and/or which, may cause injuries, loss of life, substantial
damage to property and environment both inside and around the
factory take place and a DISASTER is said to have occurred.
M/s. Asahi Songwon Colors Ltd. is the existing unit, involved in
manufacturing of CPC blue crude & Pigment Beta Blue. Now, unit
proposed to expand its production capacity of existing products with
introduce of three new products i.e. Pigment Alpha Blue: 15/15.1,
Pigment Violet – 23 and Pigment Green – 7/36.
As described in previous chapter-6, the risk assessment studies have
been conducted for identification of hazards, to calculate damage
distances and to spell out risk mitigation measures.
Despite of our best efforts in the way of managing an emergency
situation lies in the prevention of the any risk hazards from the
manufacturing process or material handling, things can go wrong.
Therefore, it is essential to plan and develop the support system,
which will be required in case an emergency arises.
7.2 PROBABLE HAZARDS & RISK
From the preliminary risk assessment study presented in Chapter 6
of this report, some of the possible hazards have been identified.
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-2
7.3 OBJECTIVES OF THE PLAN
Following are the Objectives of the disaster management plan:
• To define and assess emergencies, including risk and environment
impact assessment.
• To reduce possibilities of accident
• To safeguard employees, visitors and other people in the vicinity.
• To minimize damage to property and / or the environment.
• To inform employees, general public and the authorities about the
hazards/risk assessed, safeguard provided, residual risk if any and
the role to be played by them in the event of emergency.
• To be ready for the mutual aid if need rises to help the
neighboring unit. Normal jurisdiction of an On-site Emergency
Plan is the own premises only, but looking to the time factor in the
arriving the external help of off-site plan agency, the jurisdiction
must be extended outside to the extent possible incase of
emergency occurring outside.
• To inform authorities and mutual aid centers to come for help.
• To affect rescue and treatment of casualties to count injured.
• To identify and list any dead.
• To inform and help relatives.
• To secure the safe rehabilitation of affected area and to restore
normalcy.
• To provide authoritative information to the news media.
• To preserve records, equipment, etc., and to organize
investigation into the cause of the emergency and preventive
measure to stop its recurrence.
• To insure safety of the works before personal re-enter and resume
work.
• To work out a plan with all provisions to handle emergencies and
to provide for emergency preparedness and the periodical
rehearsal of the plan.
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-3
The structure of the plan may vary depending on number of
employees, materials and processes, availability of resources,
location of site, size and complexity of work.
The plan should not be complicated. Instructions should not overlap
or create any confusion. Responsibilities should be clearly assigned
and should be workable smoothly. For clear understanding and quick
action, the action (Role) by each individual (his emergency duty)
should be prepared in a booklet or card size and given to him.
7.4 IDENTIFICATION OF MAJOR HAZARDS
The major hazardous field where disaster management plant is
required are as under,
• Bursting of high-pressure steam pipe, vessels, etc. due to
abnormal pressure rise
• Fire hazard due to ignition of fuel
• Inhalation of any hazardous chemical
7.5 SCOPE OF PLAN
• The plan will set into action immediately after a fire or other
hazard occurs in and around the plant
• Fuel storage facility is situated away from the manufacturing plant
and fulfilling all rules and regulations
• All the electrical fittings are of explosion proof fitting
• All necessary fire-fighting arrangements have been provided near
the storage area
7.6 THE AVAILIBILITY, ORGANIZATION AND UTILIZATION OF
RESOURCES AND FACILITIES FOR EMERGENCIES
In order to maintain an emergency response capability, certain
facilities must be kept in a state of readiness and sufficient supplies
and equipment must be available. In some cases, it may be
impossible to maintain all of the equipment necessary for all possible
emergencies. In these cases, agreements have to be made with
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-4
neighboring facilities to provide additional support as and when
necessary.
Where the local police or private agencies may be called upon, such
as volunteer fire companies and ambulance associations, agreements
have to be developed ahead of time. Emergency hardware can be
classified according to its use during the response operations.
Typical examples are:
• Emergency operation centers
• Communication equipment
• Alarm system
• Personal protection equipment
• Fire fighting facilities, equipment and supplies
• Spill and vapor release control equipment and supplies
• Medical facilities, equipment and supplies
• Monitoring systems
• A media Center
• Transportation system
• Security and access control equipment
Some of these resources will also be available in the local
municipalities. It is the responsibility of the plant management to
ensure that the appropriate equipments and materials are available
to respond to their very hazard-specific emergencies at the facilities,
independently from external resources. These resources can be
extremely valuable, but should be used mainly in support of the main
response actions that the facility personnel will have to implement in
case of a serious emergency.
In any case, the availability of resources within the community must
be determined beforehand, so that these resources can be mobilized,
if the time comes to do so.
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-5
7.7 RESPONSE ORGANIZATION STRUCTURE
To set up a response organization structure necessary for chain of
commands during emergency situation, which may arise in the
premises is one of the most important objectives of emergency plan,
which is briefly described hereunder,
Functions and Responsibilities
The main key person of the emergency plan is Chief Emergency
Co-coordinator (Factory Manager / Plant Head). He shall be assisted
by,
• Emergency Plant Coordinator, Chief (Production)
• Material Management Coordinator, Chief (Commercial)
• Special Job Coordinator, Chief (Administration Finance)
Chief Emergency Coordinator
He shall be responsible for
• Essential communications
• Public relation
• Transportation
• Investigation and reports
• Alert the hospital authorities
Emergency Plant Coordinator (Chief – Production)
• Rush to the site of emergency on receipt of information.
• Direct plant operation/shut-down operations as needed to
control situation.
• Guide the Shift Production Officer and members of the
Emergency Squad in fire fighting/rescue operations.
• Arrange for any additional fire fighting/safety equipment, which
may be required at the site.
• Keep in constant touch with the Chief Emergency Coordinator
and pass on all relevant and necessary information to him so
as to enable him keep in touch with concerned authorities.
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-6
• Keep in touch with the other coordinators for requirement of
any services like external help, communication, transportation,
etc.
• Arrange for replacement/refilling of used up fire fighting
equipment’s or gas masks/canisters so as to make these
available at the site at the earliest.
• Carry out investigation of the accident and assist in filling of
statutory reports as required.
• Carry out preliminary investigation into the accident with the
help of concerned personnel.
• Preserve records/evidence that may be required for
investigation.
• Material Management Coordinator (Chief-Commercial)
• Rush to the site of emergency.
• Keep the stores open for emergency issue of any items that
may be required for control of emergency.
• In case some material is not available, arrange for its
emergency purchase.
• Keep contact with other coordinators to assess any
requirements in terms of material.
• Arrange for any trucks/trolleys, which may be required for
transportation of materials.
• Keep in constant touch with the Chief Emergency Coordinator.
• Assess the situation in consultation with the Chief Emergency
Coordinator and other coordinators.
• Arrange to get maintenance mechanics along with their
toolboxes to provide help in any isolation/repair work as may
be required.
• Arrange for requisite number of contractor workmen in case
any additional help is required.
• Arrange for the Shift Electrician and get power supply to the
affected area isolated, if required.
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-7
• Make arrangements for temporary lighting/emergency lighting
at the affected area, as required.
• In case of a power failure, ensure the running of the DG sets
and uninterrupted power supply to emergency facilities.
Special Job Coordinator (Chief – Administration/Finance)
• Rush to the site of emergency
• Assess the situation in consultation with Emergency Plant
Coordinator to provide help as may be required.
• Keep in constant touch with the Chief Emergency Coordinator.
• Assess the situation in consultation with Chief Emergency
Coordinator.
• Attend to all emergencies related communications at the
Security Gate.
• Arrange for all Security Guards at their respective post and in
case of the availability of some spare Security Guards, they
may be sent to site of emergency to assist emergency Squad in
fire fighting/rescue operations.
• Monitor closely all movements at the gate keeping passage
clear for movement of emergency vehicles.
• No visitors should be allowed to come inside the premises
during the period of emergency.
• Assess the law and order situation inside/outside the premises
and take necessary action accordingly. Proper vigilance to be
maintained to avoid any attempts from inside/outside
saboteurs.
• Arrange to keep the emergency vehicles and ambulance ready
with their drivers for any movement of personnel/material.
• Arrange for canteen services for the personnel on duty and in
the affected area.
• In case of any injuries, provide necessary first aid and arrange
for shifting of the injured personnel to the ESI or other
hospitals as the case may be.
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-8
• Attend to any external calls/telephones relating to information
about emergency.
• In case of need from other emergency coordinators at site,
arrange to inform external agencies like Fire Brigade, Police
Station, Ambulance and other Medical Services.
• Arrange for filling of statutory report that may be required.
7.8 EMERGENCY RESPONSE CENTER
The place identified as Emergency Response Center will be
considered as the Security Gate Office.
The location of Emergency Response Center may change in future as
per convenience. The facilities available at the Emergency Response
Center shall include:
• Internal Telephone
• External Telephone
• Manual Fire/Emergency Siren
• Siren Actuation Switch
• Important Address and Telephone Numbers
• Emergency Vehicles
• Confined Space Entry Procedure
• List of antidote/actions to be taken in case of exposure to
hazardous Chemicals/ materials.
• Material Safety Data Sheets of chemicals
• A copy of On-Site Disaster Management Plan
All communications after General Shift working hours and on
Sundays/Holidays are to be routed through the Security Gate Office.
7.8.1 Emergency Telephone Number
Emergency Contact Numbers
Disruption Concern person Cell No. Landline No. Factory Manager Mr. A.K. Nayak 9925246356 2680809
Vice President (Technical)
Mr. Sunil Mahajan 9925246351 6595806
Production Manager Mr. K.K. Magar 9925246358 9879863433 Safety Officer Mr. Dipak Patil 9924726457 - Jt. Director Mr. P.M. Shah 9879093888 2335550/
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-9
(Ind. Health & Safety) 2432543 Dy. Director
(Ind. Health & Safety) Mr. G.D. Solanki 9998477096
2335550/ 2432543
Fire Station (Control Room)
- - 101
Fire Station (Dandiya Bazar)
- - 2426413
Fire Station (Makarpura GIDC)
- - 2642444
Fire Station (Panigate) - - 2513014 Fire Station (Wadi) - - 2343545
Hospital (SSG Baroda)
- - 2423112/ 222314
GEB (Muval) - - 242242 GEB (Jambua) - - 2637953
Police Station (Padra) - - 222333/ 257233
Security Mr. N.Patel 9824014871 2358589 Company Doctor Dr. Kailas Agrawal 9824263700 2338718
Ambulance - - 102 Ambulance (Karkhadi) - - 273501
Head Office (Chhatral) - - 02764-
233007/10
General Rules
• Follow sense of discipline and do not panic.
• Do not rush and endanger your personal safety.
• Use personnel protective equipment according to the situation.
• Do not block any passages which may hinder the movement of
emergency
• Vehicles.
• In case you have to shut down your plant operations, do it in
an orderly
• Manner as per standard operating procedures.
• In situation when you have to leave your work and evacuate to
identify places out of operating areas, do it in an orderly
manner.
• Follow instruction of the Emergency Coordinators.
• Understand the disaster management plan well and take
interest in practice drills
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-10
Emergency Squad
There is a group of personnel (5-10 in number) who will be identified
to handle any emergency situation. These personnel including
officers shall be taken from various operating areas and will be
imparted extensive training in fire fighting, material safety data for
hazardous chemicals, rescue operations, decontamination
procedures, confined space entry procedures, first aid and other
related functions. The members will be so chosen that at any given
time, at least 2–3 members of Emergency Squad will be available
in the premises.
Communication System
Intercom telephone points shall be provided at all critical areas of
operations. An Emergency Telephone shall be available at the
Emergency Response Center. In addition, telephone connections shall
be provided at the residence of all critical personnel to ensure
immediate contact.
7.9 POST EMERGENCY – RECOVERY
When an emergency is over, it is desirable to carry out a detailed
analysis of the causes of accidents to evaluate the influence of
various factors involved and to propose methods to eliminate or
minimize them in future. Simultaneously, the adequacy of the
disaster preparedness plan will be evaluated and any shortcomings
will be rectified.
Accident Investigation
a. As soon as possible after the emergency is over and
plant operation has become normal, the investigation
will be carried out to determine the cause of the event.
b. Representatives from various disciplines will be
members of the investigating team.
c. The area of the event will be sealed off so that
tampering or alteration of the physical evidence will not
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-11
occur.
d. Key components will be photographed and logged with
time, place, direction, etc.
e. Statements will be taken from those who were involved
with the operation or who witnessed the event.
Damage Assessment
This phase of recovery establishes the quantum of replacement
machinery considered necessary for bringing back the plant to
normal operation, property and personnel losses, and culminates in a
list of necessary repair, replacement and reconstruction work.
Insurance companies will be informed of the damage and requested
to pay the compensation as per claim.
Cleanup and Restoration
This phase will only begin after the investigation is complete.
Reporting documentation will be prepared and forwarded to
appropriate authorities.
Repairs, restoration and cleanup will begin.
Insurance claims will be prepared and submitted.
San Envirotech Pvt. Ltd. - Ahmedabad
REIA report of Asahi Songwon Colors Ltd. 7-12
Figure 7.1
On Site Disaster Management Plan
Chief Emergency Coordinator Factory manager /
Plant head
Material management Coordinator
(Chief Commercial)
Special Job Coordinator
(Chief Administration
Finance)
Emergency Plant Coordinator (Chief Production)
San Envirotech Pvt. Ltd. - Ahmedabad
CHAPTER-8
Disclosure of consultant
The profile of the consultant is given below:
About San Envirotech Private Limited
San Envirotech Pvt. Ltd. is a leading multi-disciplinary testing laboratory in
Gujarat. SEPL provides testing services in the areas of environmental
assessment and analytical testing.
SAN ENVIROTECH PVT. LTD. started work in 1990 to serve the environment
as a trustee of a next generation with a small infrastructure.
During last two decade, San has been taking care of client’s unique problems
and concerns in order to develop cost effective strategies to meet their
regulatory obligations. We focus on strategic planning and comprehensive
solutions to address both the short and long term needs of the clients.
Consequently we have developed long – term relationship with our clients to
provide them with the services necessary to meet their changing needs.
To protect and preserve the natural resources on earth for future generation,
it offers extensive consultancy services in the field of environment. With its
rich experience, multidisciplinary expertise and with the support of its state-
of the-art analytical equipment, the services offered by the division are vide
ranging and encompasses entire scope of environment management and
monitoring services. With its emphasis on quality services over the years, it
has evolved itself into a single reference point in India for comprehensive
environmental services.
The quality Policy
SAN Envirotech Pvt. Ltd is functioning as leading environmental
consultant to fulfill the aim as to serve environment as a trustee of next
generation with small infrastructure.
REIA report of Asahi Songwon Colors Ltd. 8-1
San Envirotech Pvt. Ltd. - Ahmedabad
We conduct analytical works pertaining to various Environmental
Parameters. We perform Effluent treatability studies also. To conduct the
analysis work, we follow National & International Quality Standard and
update our process regularly.
“Quality Assurance Team” always welcomes any suggestion and
feedback, to improve the Quality, Performance and Standards of the
services. These suggestion and feedback are considered for reviewing of the
services and complied immediately.
Major Milestones and Accreditation
1997-Auditors for schedule-II Industries approved by the committee of Hon.
High Court of Gujarat.
2007- Recognized laboratory under Environment Protection (EP) Act by
Government of India (GOI).
2011-Accredited by QCI/NABET, Govt. of India for EIA report preparation.
The list of persons involved in the preparation of present EIA/EMP report is
presented below:
Sr.
No.
Name Qualification Position Contribution Experience
1. Dr. Mahendra Sadaria
Ph.D. Director Coordinator & In-house
expert for AQ, AP & HW
22 years
2. Mr. Satish Borad B. E. Civil Empanel
expert
Land Use (LU)
expert
22 years
5. Mr. Mehul Panchal B. E. Chemical In-house
expert
Expert (WP) 5 years
6. Mr. Sameer V. Deshpande
M.Sc. (Botany) Empanel
expert
Expert (EB) 6 years
7. Mr. Sankalp Anand
Ph.D. Empanel
expert
Expert (NV) 8 years
8. Mr. Tarkeshwar Ekande
M.A., Masters diploma in
development planning
Empanel expert
Expert (SE) 26 years
9. Mr. Nirzar Lakhia M.Sc., PGD Empanel expert
Expert (HG) 11 years
11. Mr. P.K. Shrivastava
B.Tech (Chemical) Empanel
expert
Expert (RH) 40 years
REIA report of Asahi Songwon Colors Ltd. 8-2
National Accreditation Board for Education and Training
The Director March 08, 2011 San Envirotech Pvt. Ltd. 424- Medicine Market, Opp. Shefali Center, Paldi Cross Road, Ahmedabad - 380006 (Kind Attention: Dr. Mahendra R. Sadaria)
Dear Sir,
OCI- NABEr $cherne for Accreditation of EIA Consultant Organization
This is with reference to your application for QCI- NABEl Accreditation as EIA Consultant Organization.
We are pleased to inform you that based on Document & Office Assessment, the Accreditation Committee has recommended the accreditation of San Envirotech Pvt. Ltd. as per the scope given in Annexure I (A & B).
Please confirm the correctness of spellings of the names of the experts mentioned in Annexure I B. The detailed terms and conditions are mentioned in Annexure II. You are also advised to check the QCI website for the Minutes of the Accreditation Committee Meeting held on February 17, 2011, for observations related to your application or any decisions with respect to Schemel assessment process and take necessary action for compliance,
The accreditation of your organization will be for three year period starting January 25, 2011. The annual renewal of the accreditation will be confirmed after surveillance assessment every year. Surveillance assessments will be conducted to ensure compliance with NABET Scheme and the details mentioned in your Quality Manual.
May we request you for an early payment of the annual fees and your confirmation of acceptance of the terms and conditions attached. This will enable us to issue you the requisite accreditation letter & certificate which will be valid for one year duration,
We thank you for your esteemed support in making this scheme successful and for your participation in
this national cause.
Thanks and best regards,
Yours sincerely,
~~ Director NABEr
Page 1 of6
Institution of Engineers Building. 2nd Floor. Bahadur Shah lafar Marg, New Delhi - 110 002, India Tel: +91-11-2337 9321, 2337 8057 Fax: +91-11-2337 9621 email: [email protected] Website: www,qcin,org
!
9CI - NABET Scheme for Accreditation of EIA Consultant Organizations Annexure I-A
Name of the Consultant: San Envirotech Pvt. Ltd.
424· Medicine Market, Opp. Shefali Center, Paldi Cross Road, Ahmedabad· 380006
Sectors Approved - S Nos.
SI. Sector Name of Sector Category No. No. AlB 1 4 Thermal Power Plants B 2 9 Cement Plants B
Pesticide industry and pesticide specific intermediates (excluding3 17 A
formulations) Synthetic organic chemicals industry (dyes & dye intermediates; bulk drugs and intermediates excluding drug formulations; synthetic rubbers;
4 21 Abasic organic chemicals, other synthetic organic chemicals and chemical intermediates) !I Building and large construction projects including shopping malls,
5 38 mUltiplexes, commercial complexes, housing estates, hospitals, B institutions
Total" 5 Sectors· '! ·Sectors allocated ta lndividuat ElA Coordinators are mentioned iIJ AnneMure I~B
~~)-V;~ahni
Director NABET
Page 20f6