Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O....

87
Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigation s Copy right reserved to Dr O. Hamza

Transcript of Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O....

Page 1: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

Dr O

mar

Ham

za

Foundation EngineeringCE 483

2. Site Investigations

Copy

righ

t res

erve

d to

Dr O

. Ham

za

Page 2: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

Contents– Introduction– Program of site investigation– Planning– Implementation– Reporting

CE 483 - Foundation Engineering - 2. Site Investigation

Dr O

mar

Ham

za

Page 3: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

3

Introduction

CE 483 - Foundation Engineering - 2. Site Investigation

What is Site Investigation (SI)? Why Site Investigation? Objectives of Site Investigation

Copy

righ

t res

erve

d to

Dr O

. Ham

za

Page 4: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

4

Introduction

What is site investigation (SI)?

The design of foundations of structures (such as buildings, bridges, and dams) generally requires information about:

Structure

Ground

• Structure• Ground

CE 483 - Foundation Engineering - 2. Site Investigation

Page 5: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

5

Introduction

• Site investigation (SI) or soil exploration is the process of gathering information, within practical limits, about the stratification (layers) and engineering properties of the soils underlying the proposed construction site.

Structure

GroundSite Investigation

Bore

hole

What is site investigation (SI)?

Layers

• The principal engineering properties of interest are the strength, deformation, and permeability characteristics.

Drilling rig

Page 6: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

6

Introduction

Why site investigation (SI)?

CE 483 - Foundation Engineering - 2. Site Investigation

• Many engineering failures could have been avoided if a proper site investigation had been carried out.

Sinkhole

The site has a sinkhole risk which might have

been discovered in a proper site investigation

Page 7: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

7

Introduction

Why site investigation (SI)?

CE 483 - Foundation Engineering - 2. Site Investigation

Sophisticated theories alone will not give a safe and sound design.

• The success or failure of a foundation depends essentially on the reliability of the knowledge obtained from the site investigation.

Page 8: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

8

Introduction

Objectives of site investigationThe knowledge about the ground of the proposed construction site is obtained by Site Investigation, and used to determine:

Suitability: of site for the proposed

construction? Type of design solution: e.g.

type of foundation:

shallow or deep.Design parameters:

such as strength,

compressibility, permeability &

other parameters

used for geotechnical

design

Ground or Ground-water

conditions: that would affect the

design and construction? e.g. expansive soil, collapsible

soil, high ground water…

Geo-materials: available on site which can be re-

used?

Effect of changes: How will the design affect adjacent properties and

the ground water?

Site

Inve

stiga

tion

Page 9: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

9

Introduction

Objectives of site investigation

Suitability: of site for the proposed

construction? Type of design solution: e.g.

type of foundation:

shallow or deep.Design parameters:

such as strength,

compressibility, permeability &

other parameters

used for geotechnical

design

Ground or Ground-water

conditions: that would affect the

design and construction? e.g. expansive soil, collapsible

soil, high ground water…

Geo-materials: available on site which can be re-

used?

Effect of changes: How will the design affect adjacent properties and

the ground water?

Site

Inve

stiga

tion

Manage the geotechnical risk

CE 483 - Foundation Engineering - 2. Site Investigation

Page 10: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

10

Program of site investigation

CE 483 - Foundation Engineering - 2. Site Investigation

Before Site Investigation The sequence of Site Investigation

Dr O

mar

Ham

za

Page 11: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

11

Program

Before Site Investigation• Site Investigation is usually carried out as part of Subsurface Exploratory

program. • Before conducting the Site Investigation, the program usually include: Desk

Study and Site Reconnaissance.

Desk Study Collect and review preliminary information about the site, and the structure to be built.

Site ReconnaissanceVisual inspection of the site.

CE 483 - Foundation Engineering - 2. Site Investigation

Page 12: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

12

Collecting general information about the structure, from the architectural and structural design:

Structure

Ground

Information about the Structure– Type, dimensions, and use of the structure,

and any special architectural considerations. – the load that will be transmitted by the

superstructure to the foundation system– the requirements of the local building code

(e.g. allowable settlement)

Program

Desk Study Before Site Investigation

CE 483 - Foundation Engineering - 2. Site Investigation

Page 13: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

13

Collecting general information about the ground, from already existing data such as: geological maps, seismic maps, Ariel Photography, Services records (Gas, Water, Electricity), Previous geo-environmental or geotechnical reports, … etc. at or near site.

Structure

Ground

Program

Desk Study Before Site Investigation

Information about the ground:– the geological conditions of the ground (e.g.

layers, Geological features, Ground water, Flood & Earthquake risk in the area, ..).

– the historical use of the site – if previously used as quarry, agricultural land, industrial unit with contamination issue, man-made fill/slope, etc.

CE 483 - Foundation Engineering - 2. Site Investigation

Page 14: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

14CE 483 - Foundation Engineering - 2. Site Investigation

Ariel Photograph taken for a site – shows a possible sinkhole

Page 15: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

15

Program

Site Reconnaissance

The Site Reconnaissance is normally in the form of a walk-over survey of the site.

Before Site Investigation

CE 483 - Foundation Engineering - 2. Site Investigation

What things do I need to

look for?

Engineer during Site Visit

Dr O

mar

Ham

za

Page 16: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

16

Program

Site ReconnaissanceImportant evidence to look for is:

Before Site Investigation

1. Stratification of soil: from deep cut, such as those made for the construction of nearby highway or other projects – if any.

2. Slope: signs of slope instability include bent trees, shrinkage cracks on the ground and displaced fences or drains.

Stratification of soil Signs of slope instability

Page 17: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

17

Program

Site ReconnaissanceImportant evidence to look for is:

Before Site Investigation

3. Structures: type of buildings in the area and the existence of any cracks in walls or other problems. You may need to ask local people.

Tipping settlement (often without cracks)

Differential settlement (with cracks)

Indication of possible ground-related problem

CE 483 - Foundation Engineering - 2. Site Investigation

Page 18: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

18

Program

Site ReconnaissanceOther important evidence to look for is:

Before Site Investigation

4. Mining: The presence of previous mining is often signs of subsidence and possibly disused mine shafts. Open cast mining is indicated by diverted streams replaced or removed fence/hedge lines.

5. Hydrogeology: Wet marshy ground, springs or seepage, ponds or streams and Wells.

6. Topography: possible existence of drainage ditches or abandoned debris or other man-made features.

7. Vegetation: may indicate the type of soil.8. Access: It is essential that access to the site can be easily obtained.

Possible problems include low overhead cables and watercourses.

CE 483 - Foundation Engineering - 2. Site Investigation

Page 19: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

19

Program

The sequence of Site Investigation

• Whether investigation is preliminary or detailed, there are three important phases:

planning, implementation and reporting.

Planning

Implementation

Reporting

• In large construction projects, 2 site investigations (SI) are carried out: – Preliminary SI, followed by – Detailed SI.

• Soil exploration is a requirement for the design of foundations of any project.

CE 483 - Foundation Engineering - 2. Site Investigation

Sequ

ence

of S

ite In

vesti

gatio

n

Page 20: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

20

Sequ

ence

of S

ite In

vesti

gatio

n

Planning

Implementation

Reporting

CE 483 - Foundation Engineering - 2. Site Investigation

Planning

Why planning Depth of investigation Spacing of boreholes

Page 21: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

21

Bore

hole

CE 483 - Foundation Engineering - 2. Site Investigation

Planning

Why planning?

• How many borings do we need?• How deep the borings should be?

The more the better, but what about the cost?

Page 22: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

22

• Minimize cost of explorations and yet give reliable data.• Decide on quantity and quality depending on type, size and

importance of project and whether investigation is preliminary or detailed.

Planning for site investigation is required to:

• Decide on minimum depth and spacing of exploration.

Dep

th o

f Bor

ehol

eBorehole Spacing

CE 483 - Foundation Engineering - 2. Site Investigation

Planning

Why planning?

Page 23: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

23

Dep

th o

f Bor

ehol

e

• In general, depth of investigation should be such that any/all strata that are likely to experience settlement or failure due to loading.

• The estimated depths can be changed during the drilling operation, depending on the subsoil encoun tered.

• To determine the approximate minimum depth of boring, engineers may use the following rules:

CE 483 - Foundation Engineering - 2. Site Investigation

Planning

Depth of investigation

Page 24: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

24

1. Determine the net increase of stress, under a foundation with depth as shown in the Figure.

2. Estimate the variation of the vertical effective stress, ‘0 , with depth.

3. Determine the depth, D = D1, at which the stress increase ’ is equal to (1/10) q (q = estimated net stress on the foundation).

Determination of the minimum depth of boring

4. Determine the depth, D = D2, at which /'0 = 0.05.

5. Unless bedrock is encountered, the smaller of the two depths, D1 and D2, is the approximate minimum depth of boring required.

’0’

q

D

CE 483 - Foundation Engineering - 2. Site Investigation

Planning

Depth of investigation

Page 25: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

25

Table shows the minimum depths of borings for buildings based on the preceding rule.

Depth of Boring

Number of StoriesBuilding width

(m)

What do you notice about this table?

CE 483 - Foundation Engineering - 2. Site Investigation

Planning

Depth of investigation

Page 26: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

26

• There are no strict rules for the spacing of the boreholes. • The following table gives some general guidelines for borehole spacing. • These spacing can be increased or decreased, depending on the subsoil

condition. • If various soil strata are more or less uniform and predictable, the number of

boreholes can be reduced.

What do you notice about this table?

Type of project Spacing (m)

Planning

Spacing of boreholes

Page 27: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

27

Planning

Implementation

Reporting

CE 483 - Foundation Engineering - 2. Site Investigation

Overview Boring Sampling Testing

Implementation

Sequ

ence

of S

ite In

vesti

gatio

n

Page 28: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

28

Overview

Boring

Trial pits

Boreholes

Sampling

Soil Sampling

Rock Sampling

Testing

In-situ tests

Laboratory tests

The implementation phase of site investigation usually includes three important aspects:

CE 483 - Foundation Engineering - 2. Site Investigation

21 3

Implementation

Page 29: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

29

Boring

Trial pits

Boreholes

Sampling

Soil Sampling

Rock Sampling

Testing

In-situ tests

Laboratory tests

CE 483 - Foundation Engineering - 2. Site Investigation

21 3

BoringImplementation

Page 30: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

30

Trial pits

CE 483 - Foundation Engineering - 2. Site Investigation

• Trial pits are shallow excavations - less than 6m deep.

• The trial pit is used extensively at the surface for block sampling and detection of services prior to borehole excavation.

• For safety ALL pits below a depth of 1.2m must be supported.

BackhoePick and shovel

Depth Excavation Method

0-2m By Hand

2-4m Wheeled Back Hoe

4-6m Hydraulic Excavator

Trial Pit6m > depth

BoringImplementation

Page 31: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

31

Boreholes

CE 483 - Foundation Engineering - 2. Site Investigation

1. Auger Boring2. Wash Boring 3. Rotary Drilling4. Percussion Drilling

Borehole• The right choice of method depends on:

– Ground condition: presence of hard clay, gravel, rock.

– Ground-water condition: presence of high ground-water table (GWT).

– Depth of investigation– Site access

• Boreholes may be excavated by one of these methods:

BoringImplementation

Page 32: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

32

• This is the simplest of the methods. Hand operated or power driven augers may be used.• Suitable in all soils above GWT but only in

cohesive soil below GWT.

Hand operated augers

Power driven augers

Post hole auger Helical auger

1. Auger Boring

Boreholes BoringImplementation

Page 33: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

33

• A casing is driven with a drop hammer. A hollow drill rod with chopping bit is inserted inside the casing.• Soil is loosened and removed from the

borehole using water or a drilling mud jetted under pressure.• Wash boring is a very convenient

method for soil exploration below the ground water table provided the soil is either sand, silt or clay. The method is not suitable if the soil is mixed with gravel or boulders.

2. Wash Boring

CE 483 - Foundation Engineering - 2. Site Investigation

Boreholes BoringImplementation

Page 34: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

34

• In this method a heavy drilling bit is alternatively raised and dropped in such a manner that it powders the underlying materials which form a slurry with water and are removed as the boring advances.

• Possibly this is the only method for drilling in river deposits mixed with hard boulders of the quartzitic type.

3. Percussion Drilling

CE 483 - Foundation Engineering - 2. Site Investigation

Boreholes BoringImplementation

Page 35: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

35

• In this method a rapidly retaining drilling bit (attached to a drilling rod) cut the soil and advance the borehole.

4. Rotary Drilling

• When soil sample is needed the drilling rod is raised and the drilling bit is replaced by a sampler.

• This method is suitable for soil and rock.

Drilling bit

Drilling rod

Rotary Head

Movement transmitter

CE 483 - Foundation Engineering - 2. Site Investigation

Boreholes BoringImplementation

Page 36: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

36

Boring

Trial pits

Boreholes

Sampling

Soil Sampling

Rock Sampling

Testing

In-situ tests

Laboratory tests

CE 483 - Foundation Engineering - 2. Site Investigation

21 3

SamplingImplementation

Page 37: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

37

Soil sampling

Soil samples are recovered carefully, stored properly to prevent any change in physical properties, and transferred to laboratory for testing.

CE 483 - Foundation Engineering - 2. Site Investigation

SamplingImplementation

Samples from each type of soils are required for laboratory testing to determine the engineering properties of these soils.

• Soil Sampling equipment?• Disturbed vs Undisturbed?

Page 38: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

38

Soil Sampling equipment

There is a wide range of sampling methods such as Split-spoon, Thin-walled Tube. The choice of method depends on:

• the requirement of disturbed or undisturbed samples• Type of soil discovered at site (Gravel, Sand, Silt, Clay)

Split-spoon Sampler

Soil sampling SamplingImplementation

Soil Sample

advancement

Page 39: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

39

Soil sampling SamplingImplementation

Soil Sampling equipment

Page 40: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

40

• Two types of soil samples can be obtained during sampling: disturbed and undisturbed.

• The most important engineering properties required for foundation design are strength, compressibility, and permeability. These tests require undisturbed samples.

• Disturbed samples can be used for determining other properties such as Moisture content, Classification & Grain size analysis, Specific Gravity, and Plasticity Limits.

CE 483 - Foundation Engineering - 2. Site Investigation

Soil sampling SamplingImplementation

Disturbed vs Undisturbed

Page 41: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

41

• It is nearly impossible to obtain a truly undisturbed sample of soil.

• The quality of an "undisturbed" sample varies widely between soil laboratories. So how is disturbance evaluated?

• Quality of samples is evaluated by calculating Area Ration AR:

Sampling tube

soil

The thicker the wall of the sampling tube, the greater the disturbance.

Outer Diameter

Inner Dia.

Good quality samples AR<10% .

CE 483 - Foundation Engineering - 2. Site Investigation

Soil sampling SamplingImplementation

Disturbed vs Undisturbed

Page 42: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

42

Area Ration AR = ----------------- =

• Samples collected in Split-spoon Sampler is usually classified as “disturbed”.

What is the Area Ration?

CE 483 - Foundation Engineering - 2. Site Investigation

Soil sampling SamplingImplementation

Disturbed vs Undisturbed

Page 43: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

43

• Core drilling equipment?• Core recovery parameters?

Rock samples are called “rock cores”, and they are necessary if the soundness of the rock is to be established.

CE 483 - Foundation Engineering - 2. Site Investigation

SamplingImplementation

Rock Sampling (Coring)

Page 44: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

44

• Coring is done with either tungsten carbide or diamond core bits.• Rock sampler is called “core

barrel” which usually has a single tube.• Double or triple tube core

barrel is used when sampling of weathered or fractured rock.

Core barrel: (a) Single-tube; (b) double-tube

(a) (b)

Inner barrelOuter barrel

Core barrel

Rock

Rock

Rock

Corin

g bi

t

Drill rod

Diamond Drill Bit

Rock core

Rock

Rock Sampling (Coring) SamplingImplementation

Core drilling equipment

Page 45: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

45

• Cores tend to break up inside the drill barrel, especially if the rock is soft or fissured. • Core recovery parameters are used to describe

the quality of core.• Length of pieces of core are used to determine:

– Core Recovery Ratio (Rr)– Rock Quality Designation (RQD)

Rock cores

CE 483 - Foundation Engineering - 2. Site Investigation

SamplingImplementation

Rock Sampling (Coring)

Core drilling equipment

Page 46: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

46

10

• Assuming the following pieces for a given core run:

S L i=L

100%

(Core run)

Rr

( L i ≥ 10 cm )(Core run)

Recovery Ratio, Rr

Rock Quality Designation, RQD

Rock Sampling (Coring) SamplingImplementation

Core drilling equipment

Core recovery (lengths of intact pieces of core)

Page 47: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

47

• So Rock Quality Designation (RQD) is the percentage of rock cores that have length ≥ 10 cm over the total drill length (core run).

• RQD may indicate the degree of jointing or fracture in a rock mass. e.g. High-quality rock has an RQD of more than 75%.

• RQD is used in rock mass classification systems and usually used in estimating support of rock tunnels.

Core recovery parameters

CE 483 - Foundation Engineering - 2. Site Investigation

Rock Sampling (Coring) SamplingImplementation

Page 48: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

48

Class Example

Work out Rr and RQD for the following core recovery (intact pieces), assuming the core run (advance) is 150 cm.

What is the rock mass quality based on RQD?

CE 483 - Foundation Engineering - 2. Site Investigation

Rock Sampling (Coring) SamplingImplementation

Core recovery parameters

Page 49: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

49

• Total core recovery L = 125 cm• Core recovery ratio:

Rr = 125/150 = 83%• On modified basis (for pieces ≥ 10cm),

95 cm are counted, thus: RQD = 95/150 = 63 %

• RQD = 50% - 75% Rock mass quality is “Fair”

Solution:

CE 483 - Foundation Engineering - 2. Site Investigation

Rock Sampling (Coring) SamplingImplementation

Core recovery parameters

?

? = ? S L i

L100% = S L i

L

Page 50: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

50

Boring

Trial pits

Boreholes

Sampling

Soil Sampling

Rock Sampling

Testing

In-situ tests

Laboratory tests

CE 483 - Foundation Engineering - 2. Site Investigation

21 3

TestingImplementation

Page 51: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

51

In-situ tests• Introduction• Groundwater measurements• Standard Penetration Test (SPT)• Cone Penetration Test (CPT)

TestingImplementation

• Plate Load Test (PLT)• Pressure-meter Test (PMT)• Flat Dilatometer Test (DMT)• Vane shear test (VST)

PLT

In Borehole

Piez

omet

er

Page 52: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

52

Introduction

Definition: • In-situ tests are carried out in the field with intrusive testing equipment. • If non-intrusive method is required, then it is better to use geophysical

methods which use geophysical waves – i.e. without excavating the ground.

Advantage of in-situ testing (against lab testing)• It avoids the problems of sample recovery and disturbance • some in-situ tests are easier to conduct than lab tests • In-situ tests can offer more detailed site coverage than lab testing.

Testing standards• American Society for Testing and Materials (ASTM)• British Standard (BS)

CE 483 - Foundation Engineering - 2. Site Investigation

: In-situ tests TestingImplementation

Page 53: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

53

Groundwater measurements

Why Groundwater:• Groundwater conditions are fundamental

factors in almost all geotechnical analyses and design studies.

Types of Groundwater measurements:• Determination of groundwater levels (GWT) and

pressures. Borehole instrumented with Piezometer is used for this purpose.• Measurement of the permeability of the

subsurface materials, particularly if seepage analysis is required. The test called Pumping test.

Piezometer

CE 483 - Foundation Engineering - 2. Site Investigation

: In-situ tests TestingImplementation

Ground water level

Standpipe

Page 54: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

54

Standard Penetration Test (SPT)

• This empirical test consists of driving a split-spoon sampler, with an outside diameter of 50 mm, into the soil at the base of a borehole.

• Drivage is accomplished by a trip hammer, weighing 65 kg, falling freely through a distance of 760 mm onto the drive head, which is fitted at the top of the rods.

• The split-spoon is driven three times for a distance of 152.4 mm (6 in) into the soil at the bottom of the borehole. The number of blows required to drive (only) the last two 152.4 mm are recorded. The blow count is referred to as the SPT-N.

760 mm

152.4 mm (6 in) x 3 timesThe first one does not count

Falling Hammer

Definition

Drive head

Slit spoon

CE 483 - Foundation Engineering - 2. Site Investigation

: In-situ tests TestingImplementation

Page 55: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

55

• Relatively quick, simple, reasonably cheap, and suitable for most soils.• good correlation between SPT-N and soil properties.• provides a representative soil sample for further

testing.

Disadvantage• SPT does not typically provide continuous data• Limited applicability to soil containing cobbles and

boulders.• Samples obtained from the SPT are disturbed.• SPT N blow require correction

Advantage

CE 483 - Foundation Engineering - 2. Site Investigation

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

Page 56: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

56

• Corrections are normally applied to the SPT blow count (N) to account for:– Energy loss: during the test (about only 60% of energy remains)– Equipment differences: hammer, sampler, borehole diameter, rod

Corrections for energy and equipment

• The following equation is used to compensate for these factors:

(0.75-1.0)

(1.0-1.15)

(usually 0.50-0.80)

(0.8-1.0)

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

Usually this correction is made by the Site Investigation operator.

60%

Page 57: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

57

Corrections for overburden pressure

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

CN = overburden pressure correction factor

• In granular soil (sand, gravel) the SPT blows are influenced by the effective overburden pressure at the test depth:

Many equations have been suggested for CN – see Page 86, (Das’s text book). For example:

Page 58: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

58

Standard Penetration Test (SPT)

Correlation between N and friction angle

• There are many equations suggested. The figure shows the correlation with the angle of shearing resistance of sand (according to Pecks, 1974).

TestingImplementation : In-situ tests

Angle of shearing resistance f’ (degree)

Cor

rect

ed S

PT N

blo

w

Page 59: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

59

The following are the recorded numbers of SPT blows required for spoon penetration of three 152.4cm (6 in) in a sand deposit:

Class example

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

Depth from ground surface (m) 1.5 3 4.5 6 7.5

SPT blows (blow/ 6 in) 3, 4, 5 7, 9, 10 7, 12, 11 8, 13, 14 10, 14, 15

The ground water table (GWT) is located at a depth of 4.5m. The wet unit weight of sand above GWT is 18 kN/m3, and the saturated unit weight of sand below GWT is 19.81 kN/m3.

• Draw a sketch of the foundation showing the given details of the soil.• Determine the standard penetration number (SPT-N) at each depth.• What is the corrected (SPT-N) value? (use Seed’s equation).• Determine the friction angle at depth 4m below the footing. (Use Peck’s

Equation or Chart).

Note. Assume the above SPT blows are corrected for energy and equipment.

Page 60: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

Z, m SPT blow N60 s0’ (kPa) CN N f’

1.5 3, 4, 5 4+5=9 1.5x18 =27 0.27 1.7 15.3 35o

3 7, 9, 10 9+10=19 54 0.54

4.5 7, 12, 11 23

6 8, 13, 14 ?

7.5 10, 14, 15

60

Only the last 2 sets of blows count

Solution

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

g =18 kN/m3

gsat=19.8 kN/m3

2

4

Z

Corrected

Page 61: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

61

• The corrected SPT N blow can be approximately correlated to many important engineering properties of soil such as shear strength & compressibility. • This equation shows the correlation with untrained shear strength Su (or Cu)

of clay. (also with OCR = Over Consolidation Ratio).

CE 483 - Foundation Engineering - 2. Site Investigation

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

Correlation between N and untrained shear strength

In C

lay

Page 62: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

62

• The table shows the correlation corrected SPT-N with untrained shear strength Su (or Cu) of clay (according to Terzaghi et al. 1996)

CE 483 - Foundation Engineering - 2. Site Investigation

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

Correlation between N and untrained shear strength

Page 63: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

63CE 483 - Foundation Engineering - 2. Site Investigation

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

Class Example

shown belowthe Figure

Page 64: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

64

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

Solution

Z, m N60 s0’ (kPa) Cu (kPa) s0’ (MPa) OCR

3 51.5x16.5+

1.5x(19-9.81) = 38.5100x0.29

x50.72 =92.338.5/1000=

0.03850.193x(5/

0.038)0.689 = 5.5

4.5 838.5+1.5x(16.5-

9.81) = 48.5 129.6 0.0485

6 8

7.5 9

9 10

OCRav = Cu -av =

Page 65: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

65

Standard Penetration Test (SPT)

Correlation between N and Relative Density Dr

• correlation between N60 and Relative Density of Granular Soil

TestingImplementation : In-situ tests

CE 483 - Foundation Engineering - 2. Site Investigation

Copy

righ

t res

erve

d to

Dr O

. Ham

za

For Clean sand onlyGeneral

Page 66: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

66

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

CE 483 - Foundation Engineering - 2. Site Investigation

Very loose

Loose

Medium

Dense

Correlation between N and Relative Density Dr

Page 67: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

67

Standard Penetration Test (SPT) TestingImplementation : In-situ tests

Correlation between Modulus of Elasticity and Standard Penetration Number

• The modulus of elasticity of granular soils (Es) is important parameter in estimation the elastic settlement of foundation.

• An approximate estimation for Es was given by Kulhawy and Mayne (1990) as:

Page 68: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

68

Cone Penetration Test (CPT)

• called also "Dutch cone test“ or “Static Penetration test”.• The test method consists of pushing an

instrumented cone, with the tip facing down, into the ground at a slow controlled rate.• Cone: 60 degree apex cone, Dia = 36 mm.

Definition

Cone

CE 483 - Foundation Engineering - 2. Site Investigation

TestingImplementation : In-situ tests

Measures

• Cone or Tip resistance (qc) or (qt)

• Sleeve friction (fs)

• Water Pore pressure (ub)

Friction Ratio, Fr = qc

fs

qc or qt

fs

Hydraulic push at rate 20 mm/s

Cone Rod (36 mm dia.)

• Other variables e.g. Shear wave velocity (vs)

Page 69: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

69

Cone Penetration Test (CPT)

CE 483 - Foundation Engineering - 2. Site Investigation

TestingImplementation : In-situ tests

• Soil profile (stratigraphy): soil type identification• Estimation of geotechnical

parameters (strength, compressibility, permeability)• Evaluation of groundwater

conditions (pore pressure)• Geo-environmental:

distribution and composition of contaminants

Applications:

Sample data

Sleev

e fric

tion, f s

Tip re

sista

nce, q

c

Pore

Pressu

re, u

Clay

Clay

& S

iltSi

lty C

lay

Clay & Sand

Fricti

on Ratio , F

r

Page 70: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

70

Cone Penetration Test (CPT)

TestingImplementation : In-situ tests

– High in granular soil– Low in cohesive soil

– Low in granular soil– High in cohesive soil

• Friction Ratio Fr

• Point resistance qc

Soil Identification:

• However, the cone/tip (qc) and sleeve (fs) resistance increase with increasing overburden stress s0

• for accurate identification, normalization of qc & fs by overburden stress is required. Classification Chart (Robertson et al., 1983)

Page 71: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

71

Cone Penetration Test (CPT)

CE 483 - Foundation Engineering - 2. Site Investigation

TestingImplementation : In-situ tests

• Inability to penetrate through gravels and cobbles• Newer technology = less populated database

than SPT• Lack of sampling

Disadvantages:

• Borehole is not necessary• Almost continuous data (reading every 10mm)• Elimination of operator error (automated)• Reliable, repeatable test results

Advantages:

Page 72: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

72

Cone Penetration Test (CPT)

CE 483 - Foundation Engineering - 2. Site Investigation

TestingImplementation : In-situ tests

• In Sand: the drained friction angle

Correlation with shear strength

where: qc = the cone (tip) (point) resistance

s’0 & s0 = effective and total overburden pressure, respectively

NK = Bearing factor depends on type of cone (varies from 11-20)OCR = Over Consolidation Ratio

• In Clay: undrained shear strength cu

(Ricceri et all’s. 2002)

Page 73: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

73

Cone Penetration Test (CPT)

TestingImplementation : In-situ tests

Class example: Correlation with shear strength

Use equation proposed by Ricceri et all’s. 2002.

Page 74: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

74

Cone Penetration Test (CPT)

TestingImplementation : In-situ tests

Solution:

Depth, m qc (MPa) s0’ (kPa) qc /s0’ f’ (Rad) f’ (deg)

1.5 2.06 1.5 x 16 =24 2060 / 24 = 85.8 0.690.69x180/

p=40o

3 4.23 48 88.1

4.5 6.01

6 8.18

7.5 9.97

9.0 12.42f’av =

f’av = Sf’ / 6Note. tan -1 is inverse tangent, the angle returned is in Radian.

Page 75: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

75

Plate Load Test (PLT) TestingImplementation : In-situ tests

• The test essentially consists in loading a rigid steel plate at the foundation level and determining the settlement corresponding to each load increments.

• The ultimate bearing capacity is then taken as the load at which the plate starts sinking at a rapid rate.

• Plate load test is a field test to determine the ultimate bearing capacity of soil.

Page 76: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

76

Laboratory tests

CE 483 - Foundation Engineering - 2. Site Investigation

TestingImplementation

Page 77: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

77

• Basic physical properties tests (Moisture content, Specific gravity, Soil Indexes, ..)

• Particle size test (sieving, Sedimentation)• Direct shear box test• Unconfined compression test• Triaxial test• Consolidation test• Permeability test• Other lab tests: Chemical test (pH,

contamination,..)

CE 483 - Foundation Engineering - 2. Site Investigation

Laboratory tests

TestingImplementation

Page 78: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

78

Planning

Implementation

Reporting

CE 483 - Foundation Engineering - 2. Site Investigation

Preparation of Borehole Site Investigation Report

Reporting

Sequ

ence

of S

ite In

vesti

gatio

n

Page 79: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

79CE 483 - Foundation Engineering - 2. Site Investigation

Reporting

Preparation of Boring Logs

Initial information: Name and address of the drilling company, Driller’s name, Job description and reference number, boring information (number, type, and location of, and date of boring).

Example of a typical boring log

Page 80: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

80CE 483 - Foundation Engineering - 2. Site Investigation

Subsurface stratification: which can be obtained by visual observation of the soil brought out by auger, split-spoon sampler, and thin-walled Shelby tube sampler.

Groundwater: Elevation of water table and date observed, use of casing and mud losses, and so on

Reporting

Preparation of Boring Logs

Page 81: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

81CE 483 - Foundation Engineering - 2. Site Investigation

In-situ tests: Standard penetration resistance and the depth of SPT

Samples: Number, type, and depth of soil sample collected; in case of rock coring, type of core barrel used and, for each run, the actual length of coring, length of core recovery, and RQD.

Reporting

Preparation of Boring Logs

Page 82: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

82

The following borehole is part of a site investigation (SI) carried out over a proposed location of a bridge.

Assess the subsoil conditions and ground-water conditions based on the borehole data. In particular write about:

• Soil layers: types, description, depth…• Soil properties: shear strength properties -based on SPT.• Ground water depth

Reporting

Preparation of Boring Logs

Class example

Copy

righ

t res

erve

d to

Dr O

. Ham

za

Page 83: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

83CE 483 - Foundation Engineering - 2. Site Investigation

Page 84: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

84CE 483 - Foundation Engineering - 2. Site Investigation

• When: After the completion of all of the field and laboratory work, a site investigation report is prepared.

• Why: for the use of the design office and for reference during future construction work.

• The report is also called soil exploration report or Geotechnical Factual report.

SITE

INVESTIGATION

Reporting

Site Investigation Report

What should be included in the site investigation report?

Page 85: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

85CE 483 - Foundation Engineering - 2. Site Investigation

The report should contain descriptions of the followings:

• Purpose & Scope of the investigation• Site & Structure: site location, existing structures, drainage conditions,

vegetation,… and information about the structure.• Factual Details of field exploration: boreholes, samples, and testing.

For each type, quantities, method, tools should be presented.• Geological setting of the site (variation of depth and thickness of layers

as interpreted from the borings)• Subsoil and water-table conditions, (soil parameters as interpreted

from the testing results).• Design analysis & recommendations: type of foundation, allowable

bearing pressure, settlement estimation, and any special construction procedure; alternatives design solution. • Conclusions and limitations of the investigations

Reporting

Site Investigation Report

Usu

ally

giv

en in

ano

ther

repo

rt(G

eote

chni

cal D

esig

n Re

port

)

Page 86: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

86CE 483 - Foundation Engineering - 2. Site Investigation

The following graphical presentations must be attached to the report:

1. General map showing site location 2. A plan view of the location of the borings with

respect to the proposed structures and those nearby

3. Boring logs (including in-situ tests results and samples)

4. Laboratory test results

5. Other graphical presentations (geotechnical cross section based on the boring logs, photos of the field work and soil samples,…)

Reporting

Site Investigation Report

Page 87: Dr Omar Hamza Foundation Engineering CE 483 2. Site Investigations Copy right reserved to Dr O. Hamza.

87

Geotechnical cross section based on the boring logs

Reporting

Site Investigation Report