TOPIC – CONTINUOUS FLOW INTERSECTION (CFI)
SR400 @ SR53
July 10th 2014
Presenter: Robert P. Murphy Program Manager D-4
DAWSON COUNTY CHAMBER OF
COMMERCE MEETING PRESENTATION
![Page 2: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/2.jpg)
To Provide a Safe Connected and Environmentally Sensitive Transportation System That Enhances Georgia’s Economic Competitiveness by Working Efficiently and Communicating Effectively to Create Strong Partnerships.
GDOT MISSION
![Page 3: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/3.jpg)
• Introduction to Continuous Flow Intersection CFI
– Background
– Concepts
– Analysis Tools.
• View Concept Layout
• View CFI Animations & Videos
• Question/Answer Session
PRESENTATION OUTLINE
![Page 4: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/4.jpg)
• Continous Flow Intersection (CFI) concept developed about 20 years ago
• Also referred to as Displaced Left Turn (DLT)
• Locations for CFIs in Planning, Design, Construction or Operation
– United States
• 1st CFI in the U.S. was built in Long Island, New York
• Arkansas, Georgia, New York, Louisiana, Maryland, Mississippi, Missouri, Ohio, Texas, Utah, Virginia
– International
• Over 40 Locations in Mexico
INTRODUCTION
![Page 5: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/5.jpg)
INTRODUCTION
A CFI/DLT is an at-grade intersectionthat is intended to support large volume of left turns movements and high volume through movements.
![Page 6: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/6.jpg)
• There is a need to adequately accommodate
future capacity @ SR 400 and SR53
• Reduce Delay Times at this Intersection
• Cost Effectiveness compared to Original
Fly-Over Project.
Reason for Project
![Page 7: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/7.jpg)
Conventional Intersection
INTRODUCTION
![Page 8: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/8.jpg)
8
Unconventional Intersection (CFI)
INTRODUCTION
![Page 9: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/9.jpg)
CFI Typical Turning Movements
INTRODUCTION
![Page 10: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/10.jpg)
ADVANTAGES
• Handles significantly more capacity than conventional at-grade intersection designs.
• Substantial savings over grade-separated alternatives while providing equal or better performance.
• Can be deployed in one-, two-, three-, and four-legged versions.
• Reduces the number of conflict points
• Provides clear lines of sight, avoiding the visual barriers created by overpasses.
• Helps reduce pollution by reducing congestion.
• Requires shorter construction time and less utility relocation
![Page 11: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/11.jpg)
PROJECT LOCATION
![Page 12: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/12.jpg)
Outlet
Kroger
Home Depot
Wal-Mart
Theatres
Ingles
PROJECT LOCATION- EXISTING CONDITIONS
![Page 13: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/13.jpg)
TRAFFIC COUNTS
BASE YEAR (2016) ADT DESIGN YEAR (2036) ADT
SR400 38,350 62,800
SR53 20,000 32, 650
![Page 14: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/14.jpg)
Level of Service (LOS)
No Build Conditions 2036 Build Conditions 2036
SR400/SR53 AM = F L.O.S.PM = F L.O.S.
AM = C L.O.S.PM = D L.O.S
SR53/Lumpkin Campground Rd.
AM = F L.O.SPM = F L.O.S.
AM = F L.O.S.PM = F L.O.S.
![Page 15: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/15.jpg)
Microscopic Simulation Model - VISSIM•Used to analyze SR400 @ SR53 (CFI intersection) due to its geometric complexities
ANALYSIS TOOLS
Traffic Optimization Tool - SYNCHRO•Used to analyze surrounding traditional intersection geometries •Used to develop optimal signal timing and phasing
![Page 16: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/16.jpg)
P.I.# 132790APD00-0056-01(063)
SR400 @ SR53 CFI
VIEW GDOT CONCEPT LAYOUT
![Page 17: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/17.jpg)
VISSIM Animations & Project Videos
![Page 18: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/18.jpg)
SR400 @SR53 CFI DRIVER’S VIEW ANIMATION
Dawson County, GA
![Page 19: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/19.jpg)
SR400 @ SR53 PROJECT ANIMATION
Dawson County, GA
![Page 20: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/20.jpg)
AIRLINE HIGHWAY @ SIEGEN LANE CFI DRIVER’S VIEW VIDEO
Baton Rouge, LA
![Page 21: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/21.jpg)
BATON ROUGE CFI PUBLIC COMMENTS
Baton Rouge, LA
![Page 22: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/22.jpg)
BATON ROUGE CFI PUBLIC COMMENTS
![Page 23: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/23.jpg)
P.I. #132790 SR 400 @ SR 53 CFIProject Manager Mr. Robert P. Murphy
MGMT ROW Date Authorized
FFPR Date May 2014
Letting Date November 2014
AnticipatedMobilization Date
January 2015
Construction Duration
12-18 Months
![Page 24: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/24.jpg)
QUESTIONS????
![Page 25: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/25.jpg)
P.I. #0007169 SR 136 @ Etowah RiverBridge Replacement
Project Manager Mrs. Davida White
MGMT ROW Date December 2014
FFPR Date April 2015
Letting Date September 2015
Anticipated Mobilization Date
December 2015
Approved Detour for duration of project.
9 Months
![Page 26: Dot presentation](https://reader030.fdocuments.in/reader030/viewer/2022020505/568c54c01a28ab4916c010af/html5/thumbnails/26.jpg)
P.I. #0007030 SR 9 @ Etowah RiverBridge Replacement
Project Manger Mr. Otis Clark
MGMT ROW Date February 2014
FFPR Date July 2014
Letting Date December 2014
Anticipated Mobilization Date
March 2015
No Detour during Construction Phase
Project Duration 18- 24 Months