ITS/Operational Improvement Plan
Why is this Plan Needed?
1. Develop consistent process for continuous effectiveness
– Investment strategy and portfolio instead of a list
– Produce complementary and collective projects
– Understand and convey value of the projects for prioritization
– More systematic/transparent and less random process
– Whole team knowing the game plan and end game
2. Achieve measurable desired outcomes for mutual benefits
– Achieve benefits every year progressively and accumulatively
2
System Optimization (Game Plan)
• Develop Concept of Operations ConOps will provide a unified direction
for TMS development and operational
improvement program based on
Department’s goals and addressing
regional transportation needs.
Project Overview
3
Project Overview
ITS and Operational Improvement Plan
1. Maintain inventory of ITS/operational improvement projects
2. Concept of Operations congruency
3. Prioritization of the projects
4. Selection recommendation for funding
4
Project Overview
Coordination & CollaborationPlanning
Public Works/
Engineering
PlanningEngineering/
Operations
5
Benefits of ITS & Operational Improvements
Key Classes of Benefits (End Game)
� Increased Safety (preventing accidents)
� Improved Operational Performance (maximizing capacity by improving throughput)
� Enhanced Mobility and Convenience (reducing congestion)
� Improved Environmental Outcomes (reducing fuel consumption and emissions)
� Boosted Productivity and Economic Growth (reducing travel times and fuel costs)
6
Benefits of ITS & Operational Improvements
Make California’s Transportation System More Intelligent (End Game)
� Travelers and Goods Get Where They Need To Go Safely, On Time
� Provide Choice and Control to Travelers
� Provide Necessary Integrated Systems & Tools for System Managers
� Make Best Use of Limited Funds
7
Benefits of ITS & Operational Improvements
Caltrans Vision
(Game Plan)
MTC Director:
“Rather than asphalt lanes that are left
to function on their own, a modern
freeway is one in which performance is
monitored continuously, operation is
adjusted minute by minute, incidents
are cleared quickly, and motorists are
provided up-to-date information before
and during their trips.”
8
Local Jurisdiction 1 – Traffic Signal System
AVL system–Transit Agency
Regional Rail Agency Train Management System–
– Freeway Management SystemCaltrans –
Benefits of ITS & Operational Improvements
Optimization (Game Plan)
• Build Project Inventory (in layers)
PParking Management
–Local Jurisdiction 2 Traffic Signal System– Fu
ture
Fu
lly I
nte
gra
ted
Sys
tem
9
Benefits of ITS & Operational Improvements
Optimization (Game Plan)
• Build Project Inventory (in layers – future focus)
MTC Director:
“Operating the entire transportation
network as a whole, rather than each
system in isolation as is done now, is
the next leap forward in achieving
efficient use and management of our
constrained infrastructure.”
Here now Near future
10
Corridor Example
Optimization (US50 Example)
• Build Inventory from Concept of Operations
• Build Inventory Addressing Issues
Mobility – Safety – Incidents – Traveler Information – Goods Movement
AM Peak Congestion PM Peak Congestion
11
Corridor Example
AM Peak (8AM) Congestion PM Peak (5PM) Congestion
May 2, 2013
May 9, 2013
May 16, 2013
May 2, 2013
May 9, 2013
May 16, 2013
12
Total Cost County Type Project Description
$1,400,000 SAC ITS / IM Fiber Optic - 50 In Sacramento County on Route 50 from PM 0 to PM 5.1
$1,000,000 SAC ITS / IM Upgrade Video Wall at RTMC
$2,500,000 SAC Ops - Auxiliary LaneExtend aux lane on WB Rt-50 from Stockton Blvd off-ramp to the Rt-51 connector on-
ramp. Realign Stockton Blvd on-ramp to WB Rt-50 and add accel taper.
$5,000,000 SAC Ops - Auxiliary Lane Auxiliary Lane: EB and WB, from Sunrise Blvd. to Zinfandel Dr.
$3,000,000 SAC Ops - Transition Lane Transition Lane: NB, Howe Ave. on-ramp to SB Howe Ave. on-ramp.
$3,000,000 SAC Ops - Transition Lane Transition Lane: WB, from Sunrise Blvd. slip off-ramp to Sunrise Blvd. slip on-ramp.
$8,000,000 SAC Ramp Metering Ramp meter improvements on both directions on US 50 from Folsom to Stockton Blvd.
$8,000,000 SAC Ramp MeteringFolsom Blvd bridge widening to two lanes. Loop onramp improvements including ramp
metering.
$1,000,000 ED Arterial ManagementTraffic signal modification - dual left turn from Pioneer Trail and two WB lanes on the
highway, through intersection, then merging prior to Santa Fe Trail/ Apache intersection
$1,000,000 ED Arterial Management Controlled intersection at SR89
$1,000,000 ED Arterial ManagementInstall Adaptive Traffic Signal Control at 19 locations in El Dorado County along US 50
from Pioneer Trail to Stateline Avenue.
$2,784,600 EDTraveler Information (TI)
Incident Management (IM)
El Dorado ITS - Install IM System and TI System including CCTV, BTR, TMS, HAR, TTS, and
RWIS at various locations, and one RMS at Cambridge Rd.
$2,488,200 EDTraveler Information (TI)
Incident Management (IM)
Sierra 50 ITS - Install Incident Management System including TMS, BTR, RWIS, HAR, CMS,
and CCTV at various locations.
Corridor Example
Optimization (US50 Example)
• Build Project InventoryCapital Improvements
ITS/Operational Improvements
Total Cost County Type Project Description
$75,000,000 SAC Widening and HOV Construct HOV lanes and widen freeway - various segments.
$100,000,000+ SACFreeway to Freeway
Interchange Modification
Multiple phase project to reconstruct 1) the Oak Park IC, 2) the W-X portion of Rt-50 and
3) the River Front IC in City of Sacramento. This project would reconstruct freeway-to-
freeway direct connectors and add HOV direct connectors to the Oak Park Interchange.
13
Corridor Example
Optimization (US50 Example)
• Determine Prioritization (and Sequencing)
– Qualitative Assessment
� Congruent with Concept of Operations
� Address issues (high-medium-low)
� Expected desired outcome (high-medium-low)
– Quantitative Assessment
� Valuation (benefit-cost analysis)
– Sequencing
� Address downstream bottlenecks/congestion first
� High benefit versus low cost
14
Selection Priority Benefit-Cost Total Cost County Type Project Description
1 3.5 $8,000,000 SAC Ramp Metering Ramp meter improvements on both directions on US 50 from Folsom to Stockton Blvd.
2 3.4 $2,500,000 SAC Ops - Auxiliary LaneExtend aux lane on WB Rt-50 from Stockton Blvd off-ramp to the Rt-51 connector on-
ramp. Realign Stockton Blvd on-ramp to WB Rt-50 and add accel taper.
3 < 2.0 $8,000,000 SAC Ramp MeteringFolsom Blvd bridge widening to two lanes. Loop onramp improvements including ramp
metering.
4 1.0 $3,000,000 SAC Ops - Transition Lane Transition Lane: NB, Howe Ave. on-ramp to SB Howe Ave. on-ramp.
5 2.0 typical $1,000,000 ED Arterial ManagementTraffic signal modification - dual left turn from Pioneer Trail and two WB lanes on the
highway, through intersection, then merging prior to Santa Fe Trail/ Apache intersection
6 2.0 typical $1,000,000 ED Arterial Management Controlled intersection at SR89
75.0 (TI)
3.0 typ (IM)$2,784,600 ED
Traveler Information (TI)
Incident Management (IM)
El Dorado ITS - Install IM System and TI System including CCTV, BTR, TMS, HAR, TTS, and
RWIS at various locations, and one RMS at Cambridge Rd.
8 1.7 $5,000,000 SAC Ops - Auxiliary Lane Auxiliary Lane: EB and WB, from Sunrise Blvd. to Zinfandel Dr.
9 1.5 $3,000,000 SAC Ops - Transition Lane Transition Lane: WB, from Sunrise Blvd. slip off-ramp to Sunrise Blvd. slip on-ramp.
104.4 (TI)
3.0 typ (IM)$2,488,200 ED
Traveler Information (TI)
Incident Management (IM)
Sierra 50 ITS - Install Incident Management System including TMS, BTR, RWIS, HAR, CMS,
and CCTV at various locations.
11 4.5 typical $1,000,000 ED Arterial ManagementInstall Adaptive Traffic Signal Control at 19 locations in El Dorado County along US 50
from Pioneer Trail to Stateline Avenue.
12 < 1.0 $1,400,000 SAC ITS / IM Fiber Optic - 50 In Sacramento County on Route 50 from PM 0 to PM 5.1
13 < 1.0 $1,000,000 SAC ITS / IM Upgrade Video Wall at RTMC
Corridor Example
Optimization (US50 Example)
• Determine Prioritization (and Sequencing)
Capital Improvements
ITS/Operational Improvements
Selection Priority Benefit-Cost Total Cost County Type Project Description
- < 2.0 $75,000,000 SAC Widening and HOV Construct HOV lanes and widen freeway - various segments.
- < 1.0 $100,000,000+ SACFreeway to Freeway
Interchange Modification
Multiple phase project to reconstruct 1) the Oak Park IC, 2) the W-X portion of Rt-50 and
3) the River Front IC in City of Sacramento. This project would reconstruct freeway-to-
freeway direct connectors and add HOV direct connectors to the Oak Park Interchange.
15
Corridor Example
AM Peak Congestion PM Peak Congestion
5
3
2
5
3
2
Optimization (US50 Example)� Capital Improvements - HOV & ML widening at various segments; Oak Park IC
� ITS/Operational Improvements
1. SAC – Ramp metering from Folsom Blvd to Stockton Blvd
2. SAC – Auxiliary lane from Stockton Blvd to SR51
3. SAC – WB transition lane at Howe Ave IC
4. ED – Controlled SR89 I/S and Pioneer Trail I/S modification
5. SAC – EB/WB auxiliary lane and transition lane between Zinfandel Dr to Sunrise Blvd
6. SAC/ED – traveler information and incident management
16
Project Overview
Why is Project Needed
1. Develop consistent process for continuous effectiveness
– Investment strategy and portfolio instead of a list
– Produce complementary and collective projects
– Understand and convey value of the projects for prioritization
– More systematic/transparent and less random process (cradle to grave)
– Whole team knowing the game plan and end game
2. Achieve measurable desired outcomes for mutual benefits
– Achieve benefits every year progressively and accumulatively
17