Design, production and installation of modular housing for the … · 2020-02-19 · finished...

24
Design, production and installation of modular housing for the social and affordable residential market

Transcript of Design, production and installation of modular housing for the … · 2020-02-19 · finished...

Page 1: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

Design, production and installation of modular housing for the social and affordable residential market

Page 2: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

FACTS AND FIGURES OF ROLLALONG Capacity Manufacture 1,000 modules per year and can deliver a 32 unit housing development in just 75 weeks.

Newship Group Rollalong is part of a privately owned group of companies. Its owners provide continuous investment and support to the business. Established The largest offsite design and build contractor in the South, operating from our 11 acre manufacturing facility in Dorset. Revenue Average turnover circa £40m. Relationship Long term relationships with our clients within the Defence, Education and Residential sectors with a proven track record on delivering quality projects. Team 170 skilled employees working together from the initial design development to the final project handover. We have a continuous improvement philosophy in both our design and manufacturing processes. Experience & Commitment Operating since 1932, Rollalong has over 80 years of experience within the offsite construction industry.

WHO WE ARE Rollalong specialise in the manufacture of modular buildings from our state-of-the-art-factory in Dorset.

The business journey began in 1932 from manufacturing caravans, and even having the privilege of supplying the Royal Family.

With continuous investment, Rollalong has transformed into being an integral part of a successful £200m turnover group.

Our factory and site based teams have every required aspect of the construction process covered in order to supply all clients with a quality building in impressive lead times.

We are a housing supplier, delivering community benefits and positive social impacts. Homes are either supplied on a turnkey or specialist sub-contractor basis with our innovative designs and manufacturing processes producing high quality, low energy, low maintenance, permanent homes in a rapid timeframe.

We produce a unique standard ’chassis’ that enables continuous and repetitive production to reduce cost, time and defects.

Further, our standard production system allows for various internal finishes and external cladding treatments, so each building can look entirely different to meet local planning constraints.

We deliver high quality homes faster and at affordable prices.

Page 3: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

ROLLALONG SOLUTION TO HOUSING SHORTAGE OBJECTIVES: Build Affordable Homes The housing crisis is viewed as being critical. We have a solution to build better quality homes at a faster and more efficient timescale using modern offsite methods of construction. We take cost out by driving efficiencies in the manufacturing processes. Reduce Price Inflation The shortage of homes has increased house prices, making them unaffordable to many. Rollalong aims to take cost out by supplying ‘homes’ as products on publicly owned land. The speed at which offsite constructed homes can be manufactured could increase the supply and therefore reduce pressure on prices. Our solution will meet Government demands of providing a fast track housing solution to support the ambition of building 300,000 homes per year. Build High Quality Homes Offsite construction methods within the residential sector ensure products are suitably designed to be built in a controlled factory environment at speed with a total focus on quality. We manufacture low maintenance and energy efficient houses each year.

Page 4: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

1. BUILD 40% FASTER VS

TRADITIONAL BUILD

5. QUICK

RENTAL GENERATION

8. MAINTAIN FOR LIFE

BENEFITS OF OFFSITE CONSTRUCTION

RETURN ON INVESTMENT

Build 40% quicker than traditional build

Earlier return of revenue for clients

Generate greater return on capital outlay

Cost efficiencies through repetition and volume

Fixed costs without variable factors

FACTORY MANUFACTURED SOLUTION

Not weather dependent

Not subject to national skills and labour shortage

Quality controlled in factory environment

Precision construction methods reduce defects and increase time efficiency

Improved health and safety governance

Simplified process of producing interchangeable standard products in volume on a repetitious basis

ENVIRONMENT

Reduced impact on carbon footprint

Improved waste management

Less vehicle movements

Page 5: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

THE ROLLALONG OFFSITE MANUFACTURING PROCESS: How it works

SITE ASSESSMENT

GROUNDWORKS

BUILT OFFSITE

INSTALL & CERTIFY

SUPPORT

SITE ASSESSED FOR SUITABILITY, ALLOWING DESIGNS TO BE FINALISED WITH THE CLIENT. COSTS, TIMEFRAME & REQUIREMENTS WILL BE CONFIRMED.

GROUNDWORKS UNDERTAKEN SIMULTANEOUSLY TO THE OFFSITE MODULES INCLUDES FOUNDATIONS, PAVING & SOFT LANDSCAPING.

MODULES MANUFACTURED AT ROLLALONG’S FACTORY BASED IN DORSET. PRE FINISHED MODULES INCLUDE FITTING OF ELECTRICS, PLUMBING, WINDOWS, DOORS, PLASTERING, FLOORING, BATHROOM & KITCHEN FITTINGS & OTHER EXTRAS. 100% FIRE COMPLIANCE & HEALTH & SAFETY CONSIDERED.

COMPLETED MODULES ARE TRANSPORTED BY LORRY TO SITE AND CONNECTED TOGETHER FOR INSTALLATION. MODULES CAN BE UP TO 6 STOREYS HIGH. FINAL FIX PLUMBING & ELECTRICS ARE CARRIED OUT ON SITE. ALL WORK IS CERTIFIED.

ROLLALONG RESIDENTIAL TEAM OFFER CUSTOMER SUPPORT PACKAGES FOR THE LIFETIME OF THE BUILDING BOTH INTERNALLY & EXTERNALLY.

BUILT IN FACTORY— ROOF BUILT IN FACTORY—FITTINGS & FIXTURES APPLIED IN FACTORY—TRANSPORTED TO SITE—INSTALLED ON SITE

Page 6: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

Modular housing has come a long way in terms of design.

Rollalong focuses on providing a desirable exterior with a beautiful and often bespoke interior design, with kitchens and bathrooms already installed.

We can build:

Apartments (1, 2, 3 bedroom)

Houses (2, 3, 4 bedroom)

Bungalows (2, 3 bedroom)

Town Houses (2, 3, 4 bedroom)

RAPID

Rapid delivery and scalable production

AFFORDABLE

Cost effective alternative housing

INNOVATIVE

Sustainable with zero compromise on quality and design

VERSTAILE ATTRACTIVE DESIGNS

Page 7: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

TYPICAL ROLLALONG HOUSING PLANS

2 BED

4 PERSON

60 METRES2

Double bedroom

Shared bathroom

Open plan kitchen, dining and living space

Ensuite bathroom

Double bedroom

Amenity space balcony

Page 8: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

ROLLALONG HOMES FOR ALL: Timing Plan

SIZE MANUFACTURING TIME

1 BED

2 PERSON 10 PER WEEK

50M2

2 BED

4 PERSON 8 PER WEEK

60M2

3 BED

5 PERSON 8 PER WEEK

78M2

Page 9: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

A LARGER SCALE: ROLLALONG RESIDENTIAL PLANS

SIZE INDICATIVE PROGRAMME

18 Unit Development

8 X 2 BED 22 WEEKS

4 X 3 BED from manufacture to handover

4 X 1 BED

32 Unit Development

16 X 2 BED 45 WEEKS

8 X 3 BED from manufacture to handover

8 X 1 BED

Page 10: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

ROLLALONG MANUFACTURING PROCESS: How long will it take?

13 Weeks

8 Weeks

Pre-App Design

Planning Application

18 UNIT DEVELOPMENT INDICATIVE PROGRAMME—52 weeks

6 Weeks

3 Weeks

Install

Handover

Pre Construction Services Agreement Period—

21 weeks

9 Weeks

Design & Procurement

Groundworks

Manufacture

2 Weeks

Construction Period– 22 Weeks

Page 11: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

32 UNIT DEVELOPMENT INDICATIVE PROGRAMME—75 weeks

13 Weeks

8 Weeks

Pre-App Design

Planning Application

Design & Procurement

9 Weeks

8 Weeks

6 Weeks

Install

Handover

Pre Construction Services Agreement Period—21 weeks

Groundworks

Manufacture

4 Weeks

Construction Period– 45 Weeks

Page 12: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,
Page 13: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,
Page 14: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,
Page 15: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

ZINC DANISH METRIC BRICK

LONDON STOCK BRICK

A FINISHING TOUCH FOR ALL REQUIREMENTS: Materials

TIMBER COPPER /CORTEN

ALUMINIUM

OXIDISED COPPER

Page 16: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

ROLLALONG ECO LIVING

Rollalong have a purpose built Passivhaus Eco Show Home at our Dorset based factory. Please contact our team for a viewing and factory tour: 01202 824541

ROLLALONG PASSIVHAUS ECO HOUSE

Our homes can be built to excellent regulated energy ratings, and save up to 70% on utility bills compared to a traditional build with central heating.

Page 17: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

ROLLALONG PASSIVHAUS ECO HOUSE: 2 Bed Layout

Page 18: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

ROLLALONG HOUSING PORTFOLIO

Apartment Blocks in Weymouth Housing Estate in Kent

Housing in Aldershot

Page 19: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

Housing Estate in Folkestone

Page 20: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

Housing Estate in Folkestone

Page 21: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

ROLLALONG 2 BED DESIGN

Page 22: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

ROLLALONG 3 STOREY 3 BED DESIGN

Page 23: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

FINANCE AND SECURITY FOR YOUR ROLLALONG HOME: Supply with confidence

ROLLALONG HOMES GUARANTEED WITH: NHBC Warranty

BLP Approved

BOPAS Accredited

Council of Mortgage Lenders Approved

Building Control Certified

LHC Appointed Company

Low Energy Guarantee

ISO 9001:2015 Quality

Page 24: Design, production and installation of modular housing for the … · 2020-02-19 · finished modules include fitting of electrics, plumbing, windows, doors, plastering, flooring,

Rollalong Permanent Offsite Construction For building desirable living accommodation offsite t:01202 824541 e: [email protected] w: www.rollalong.co.uk Rollalong Ltd Woolsbridge Industrial Park, Three Legged Cross, Wimborne, Dorset, BH21 6SF