CONCRETE PLACEMENT AND FINISHING
ANDREW MERRICK
![Page 2: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/2.jpg)
Purpose of Meeting
Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects on neighbours
Review schedule of concrete placements
![Page 3: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/3.jpg)
Attempt for an early morning start time within the by-law requirements
Goal is to get concrete in early so that it sets up early to allow finishing to start and be completed earlier.
If necessary, could be started later in the day to accommodate weather forecasts, inspections, etc.
Early Morning Start
![Page 4: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/4.jpg)
Pour Sequence
Sequence slab placements in a south to north direction to provide a buffer between work and South Street after initial placement.
![Page 5: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/5.jpg)
Placement of Slabs
Place slab in thirds to cut down on the volume of concrete to be placed and finished
![Page 6: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/6.jpg)
Erection of Wind/Sound Screens
Plywood barrier approximately 4 feet high erected to cut down on wind and sound transmission.
![Page 7: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/7.jpg)
Light Direction
Lights when required to be directed away from South and LeMarchant Streets.
![Page 8: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/8.jpg)
Faster Concrete Set Time
Money to be spent on admixture additives placed in the concrete to shorten set time
![Page 9: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/9.jpg)
Concrete Placement Method
Traditional method with tower crane on site is to use concrete bucket for slab placements which is time consuming.
![Page 10: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/10.jpg)
Concrete Placement Method
Slabs to be placed using a concrete pump which will increase the rate that the concrete is placed.
![Page 11: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/11.jpg)
Concrete Placement Method
Supplement concrete pump with deck placer from level 3 to roof.
Articulating arm eliminates need to drag hoses over slab increasing placement rate.
![Page 12: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/12.jpg)
Schedule
When concrete placements occur, Aecon site office will be open and personnel can be contacted at 407-7730.
Estimated 26 slab placements to occur First placement scheduled is basement
slab on grade in mid-May 3 placements every 2 weeks once level 3
slab is completed and typical floors start Completion of concrete work scheduled
for early November
![Page 13: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a410b5503463e778b4f47/html5/thumbnails/13.jpg)
Questions