J O H N S O N C R E E K P U M P S TAT I O N I N F O R M AT I O N A L C O M M U N I T Y M E E T I N G
DEKALB COUNTY DEPARTMENT OF WATERSHED MANAGEMENT
1 10/11/2016
A G E N D A
2
Introduction & Remarks
Consent Decree Project Definition & Purpose
Project Overview—Johnson Creek Pump Station
Community Outreach
Questions?
10/11/2016 Johnson Creek Informational Community Meeting
C O N S E N T D E C R E E P R O G R A M Def in i t ion
3
DeKalb County entered into agreement with U.S. Environmental Protection Agency (EPA) and the Georgia Environmental Protection Division (EPD) on December 20, 2011
Provides a road map for working cooperatively with
the EPA and EPD
Formalizes implementation of certain sanitary sewer system programs and improvements
10/11/2016 Johnson Creek Informational Community Meeting
C O N S E N T D E C R E E P R O G R A M Purpose
4
Reduce SSOs and meet level of service goals through:
Defined CIP rehabilitation projects
Capacity upsizing
Sewer system condition assessment
Design and construction of needed infrastructure rehabilitation
Cleaning of sewer lines
10/11/2016 Johnson Creek Informational Community Meeting
P R O J E C T O V E R V I E W Des ign -Bui ld Pro ject
5 10/11/2016 Johnson Creek Informational Community Meeting
P R O J E C T O V E R V I E W Fa l l 2016 -Spr ing 2018
6
Replacement existing Johnson Creek PS
Demolition of existing Johnson Creek PS
Pump house improvements
New odor control system
Improved station access and aesthetics:
• Driveways and parking facilities
• Drainage structures
• Landscaping and hardscaping
10/11/2016 Johnson Creek Informational Community Meeting
P R O J E C T O V E R V I E W Construct ion Phases
7
Excavation for new pump station
Construction of new pump station
Connection of the station to existing sewer collection system
Demolition of existing pump station
10/11/2016 Johnson Creek Informational Community Meeting
P R O T O C O L S A N D P R O C E D U R E S
10/11/2016 Johnson Creek Informational Community Meeting 8
Work hours – 7:00 a.m. – 7:00 p.m., Monday-Friday (excluding major holidays)
Authorized contractors will • Have the proper identification • Drive marked vehicles
48-hour notifications prior to schedule changes, major construction milestones or traffic impacts
C O M M U N I T Y O U T R E A C H
How we will keep you informed:
Community Informational Meetings
Project Bulletins and Flyers
Distribution of Door Hangers
Websites and Social Media
Contact Us
• Email: [email protected]
• Phone: 1-800-986-1108
10/11/2016 Johnson Creek Informational Community Meeting 9
C O N TA C T U S
NEED HELP? We’re here for you at:
Email: [email protected]
Phone: 1-800-986-1108
• Monday-Friday, 8:30 a.m. – 5:00 p.m.
STAY INFORMED – More info available at:
Website – www.dekalbwatershed.com
10/11/2016 Johnson Creek Informational Community Meeting 10
Q U E S T I O N S
10/11/2016 Johnson Creek Informational Community Meeting 11