ERCOT Finance & Audit Committee Meeting · 20.06.2011 · ERCOT Finance & Audit Committee Meeting
December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.
-
Upload
theodore-fields -
Category
Documents
-
view
212 -
download
0
Transcript of December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.
![Page 1: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/1.jpg)
December 7, 2012
ERCOT Planning Horizon SOL Methodology Update
Jeff Billo
RPG
![Page 2: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/2.jpg)
2
Background
• Per FAC-010-2.1 the Planning Authority (ERCOT) is to establish a documented SOL methodology for its area
– ERCOT has issued a change to the methodology and communicated that change per Requirement 4
• Why are we making these changes?
– Better align planning horizon SOL/ IROL methodology with TPL-003 and PRC-023
– Learn from Southwest Event
• What changes are we making?
– General rewrite
– Add SOL/ IROL identification for steady-state cascade conditions
– Better define IROL identification
– Effective January 1, 2013
December 7, 2012 RPG
![Page 3: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/3.jpg)
3
How does PRC-023 fit in?
• Defines transmission circuit relay loadability requirements for Transmission Owners
• Provides 13 different methods for TOs to set their phase protective relay settings– Based on this we have used the conservative assumption that
transmission circuits loaded above 150% of their normal rating or 115% of their emergency (2-hour) rating will trip
– Assumption used for screening purposes only
• Limitation– Applies only to facilities 200 kV or higher or 100-200 kV facilities
that the Planning Coordinator identifies as ‘critical to the reliability of the BES’
December 7, 2012 RPG
![Page 4: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/4.jpg)
4
PRC-023 Side Note
• Assume all 345 kV facilities set per PRC-023
• Run separate analysis to identify 138 kV circuits that will lead to Cascade event if relays are set between 100% loading and PRC-023 loadability requirements– Report 138 kV circuits as ‘critical to reliability’ if meet this
criterion
December 7, 2012 RPG
![Page 5: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/5.jpg)
5
How is ERCOT applying this?
• In ERCOT’s TPL standard analysis, no facilities should be loaded above 100% for Category A or B contingencies
• If the analysis shows that for a Category C (multi-element) contingency facilities will be loaded above 150% of the normal rating or 115% of the emergency rating then we will assume that the facility will trip– If this causes a Cascade condition then ERCOT Planning will
investigate and take one or more of the following actions if the Cascade condition is confirmed (per Category C Planning process):
• Plan an upgrade
• Plan a Mitigation Plan (including RAPs and/or load shed)
December 7, 2012 RPG
![Page 6: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/6.jpg)
6
How is ERCOT applying this?
• An SOL will be created when …
1. Manual system adjustment (switching, load shed, etc.) is required in order to prevent cascading or voltage collapse;
2. A stability limit is identified;
3. Voltage stability margin is less than 5% for NERC Category B contingencies or 2.5% for Category C contingencies; or
4. Post disturbance frequency is not within 59.4 Hz to 60.4 Hz
• The SOL will be classified as an IROL if the load loss (either via manual load shed or as a consequence of the event) is greater than four times 1% of the load in the case
• The IROL Tv will be defined as the lower of the relay trip setting time delay or 30 minutes
December 7, 2012 RPG
![Page 7: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/7.jpg)
7December 7, 2012 March 12, 2010
Comments or Questions?
Send formal comments to:
RPG
![Page 8: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/8.jpg)
8December 7, 2012 March 12, 2010
Appendix
RPG
![Page 9: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/9.jpg)
9
Quick Example on Facility Ratings (courtesy of WECC)
December 7, 2012
Load Shed (15 min)
Emergency (2 hour)
Normal (continuous)
0 MVA
Limit Exceedance = Go beyond limit
Limit Violation = Exceed limit for a time duration longer than required mitigation time
RPG
![Page 10: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/10.jpg)
10
Quick Example on Facility Ratings
December 7, 2012
Load Shed (15 min)
Emergency (2 hour)
Normal (continuous)
0 MVA
Operate in this range all you want. Nothing is being exceeded, nothing is being violated.
RPG
![Page 11: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/11.jpg)
11
Quick Example on Facility Ratings
December 7, 2012
Load Shed (15 min)
Emergency (2 hour)
Normal (continuous)
0 MVA
Operate in this range for no more than 2 hours:
1.You are exceeding the normal rating.2.You are violating the limit if you operate in this range for longer than 2 hours.
RPG
![Page 12: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/12.jpg)
12
Quick Example on Facility Ratings
December 7, 2012
Load Shed (15 min)
Emergency (2 hour)
Normal (continuous)
0 MVA
Operate in this range for no more than 15 minutes:
1.You are exceeding the emergency rating.2.You are violating the limit if you operate in this range for longer than 15 minutes.
RPG
![Page 13: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/13.jpg)
13
Quick Example on Facility Ratings
December 7, 2012
Load Shed (15 min)
Emergency (2 hour)
Normal (continuous)
0 MVA
You can’t operate over this limit. If you do you may damage equipment, cause safety problems and/or trip the facility
1.You are exceeding the load shed rating.2.To exceed the highest time-limit rating established is to violate the limit.
RPG
![Page 14: December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649e585503460f94b50a08/html5/thumbnails/14.jpg)
14
Quick Example on Facility Ratings
December 7, 2012
Normal (continuous) = Emergency (2 hour) = Load Shed (15 min)
0 MVA
If all ratings are the same, you can never operate over the normal limit. If you do you may damage equipment, cause safety problems and/or trip the facility
1.You are exceeding the load shed rating.2.To exceed the highest time-limit rating established is to violate the limit.
RPG