December 2012 Update - I-95 New Haven Harbor …i95newhaven.com/pdfs/contracts/cog progress summary...

10
December 2012 Update Prepared by: Connecticut Department of Transportation District 3A 424 Chapel Street New Haven, CT 06511 Prepared for: South Central Regional Council of Governments 127 Washington Avenue, 4 th Floor West North Haven, CT 06473 I-95 New Haven Harbor Crossing Corridor Improvement Program

Transcript of December 2012 Update - I-95 New Haven Harbor …i95newhaven.com/pdfs/contracts/cog progress summary...

December 2012 Update

Prepared by:

Connecticut Department of Transportation

District 3A

424 Chapel Street

New Haven, CT 06511

Prepared for:

South Central Regional Council of

Governments

127 Washington Avenue, 4th Floor West

North Haven, CT 06473

I-95 New Haven Harbor Crossing Corridor Improvement Program

I-95 NEW HAVEN HARBOR CROSSING CORRIDOR IMPROVEMENT PROGRAM

New Haven – East Haven – Branford Quarterly Progress Report – December 2012

- 1 -

PROGRAM DESCRIPTION The I-95 New Haven Harbor Crossing (NHHC) Corridor Improvement Program is a multi-modal improvement program that includes operational and safety improvements to 7.2 miles of I-95 between Exit 46 in New Haven and Exit 54 in Branford. These improvements include construction of a new signature, 10-lane Pearl Harbor Memorial (Q) Bridge, the Reconstruction of the I-95/I-91/Route 34 Interchange, and additional lanes along northbound and southbound I-95 from the Q Bridge in New Haven to Cedar Street in Branford.

Also included in the Program are expanded transit service & transit management (TSM) measures including a new commuter rail station at State Street in New Haven and Shore Line East station improvements in Branford, Clinton, Guilford, Madison, and Westbrook.

PROGRAM STATUS Construction began in October 2000. Construction is currently scheduled for completion in November 2016. Program construction is approximately 60% complete with 15 projects completed as of August 31, 2012. Two major projects, the Pearl Harbor Memorial Bridge (Contract B), and the reconstruction of the I-95/I-91/Route 34 Interchange (Contract E) are currently ongoing. Refer to the attached “Key Plan” for details.

* Cost includes Contract Items, Incidentals, Utility Relocations, Force Accounts, Incentive Payments and Contingencies

Completed Projects Ongoing Progress Progress to Date Planned Projects

In year of expenditure dollars, the target cost of the Program is $2.0 billion. This is a decrease of $0.9 million from the previously recorded cost in the June 2012 Progress Report.

PROGRAM MILESTONES

On Friday, June 22, 2012, the Program held a Ribbon Cutting Ceremony marking the opening of the I-95 NB bridge portion of the Pearl Harbor Memorial (Q) Bridge.

The completed construction of the new NB Q-Bridge occurred on the following day, June 23, 2012, and allowed for the first Corridor-Wide Traffic Shift, moving I-95 NB off of the existing Q-Bridge and onto the new Q-Bridge.

In the summer of 2013, the second Corridor-Wide Traffic Shift will move I-95 SB off the existing Q-Bridge and onto the completed NB Q-Bridge portion of the new Q-Bridge. This will allow for the continued demolition of the existing Q-Bridge.

CONTRACT Cost (MM)*State Street Station (92-529) A 7.5$ I-95 Branford (14-173) D 44.7$ I-95 East Haven (43-122) C1 64.7$ Preloading & Drainage (92-581) E1 32.8$ I-95 New Haven (92-533/569) C2 98.8$ WPCA Force Main (92-613) 21.9$ NB West Approach (92-618) B1 156.5$ Rte. 34 Flyover (92-619) E2 114.8$ Q-Bridge (92-532) B 556.5$ I-95/I-91/Rte 34 (92-531/622/627) E 512.8$ I-95 Long Wharf (92-649) 27.2$

2004 2005 2006 20072000 2001 2002 2003 20162008 2009 2010 2011 20132012 20152014

58%30%

I-95 NEW HAVEN HARBOR CROSSING CORRIDOR IMPROVEMENT PROGRAM

New Haven – East Haven – Branford Quarterly Progress Report – December 2012

- 2 -

PROGRESS

PEARL HARBOR MEMORIAL (Q) BRIDGE - CONTRACT B

Contract B (SPN 92-532) includes construction of the new Pearl Harbor Memorial Bridge (Q-Bridge) carrying Interstate I-95 over the Quinnipiac River. The new Pearl Harbor Memorial Bridge is an “extradosed” cable-stayed bridge that will accommodate five travel lanes in each direction, as well as full inside and outside shoulders.

Construction activities this quarter included:

• Completed construction of the new NB Q-Bridge, which allowed for the first Corridor-Wide Traffic Shift, shifting I-95 NB off of the existing Q-Bridge and onto the new Q-Bridge, on June 23, 2012.

• Completion of pile driving and foundation work for the Temporary Bridge on the West Approach of the Q-Bridge.

• Completion of the stage 2 pier columns and pier caps on East Approach of the Q-Bridge.

• Continued steel erection between Piers 17 and 21 on East Approach of the Q-Bridge.

• Completion of stage 2 foundations at Tower Pier 3 to Anchor Pier 4 on the I95 SB portion of the new Q-Bridge.

• Stage 2 drilled shaft installation of Tower Pier 3 of the I95 SB portion of the new Q-Bridge.

• Installation of the trestle fingers needed to construct Anchor Pier 1 foundations and stage 2 bridge demolitions.

Planned activities next quarter include:

• Finish the substructure work for the Temporary Bridge on the West Approach of the new Q-Bridge.

• Complete steel erection for the Temporary Bridge on the West Approach of the new Q-Bridge.

• Place deck pans and install rebar for stage 2 bridge deck from Span 17 through Span 22 on East Approach of the I95 NB portion of the Q-Bridge.

• Finish foundation work at Tower Pier 3 of the I95 SB portion of the new Q-Bridge.

• Build cofferdam for shaft installation at Anchor Pier 1 for the I95 SB portion of the new Q-Bridge.

• Start construction of towers and columns of Tower Pier’s 2 and 3, and Anchor Pier 4 of the I-95 SB portion of the new Q-Bridge.

• Continue with construction of the construction access for marine work.

I-95 NEW HAVEN HARBOR CROSSING CORRIDOR IMPROVEMENT PROGRAM

New Haven – East Haven – Branford Quarterly Progress Report – December 2012

- 3 -

View of new Pearl Harbor Memorial (Q) Bridge cable stays

Beginning demolition of original Pearl Harbor Memorial (Q) Bridge

View of the completed I-95 NB side of the new Pearl Harbor Memorial (Q) Bridge

I-95 NEW HAVEN HARBOR CROSSING CORRIDOR IMPROVEMENT PROGRAM

New Haven – East Haven – Branford Quarterly Progress Report – December 2012

- 4 -

Completed I-95 NB portion of the new Pearl Harbor Memorial (Q) Bridge

Preparations for latex modified concrete for driving surface of West Approach and I-95 NB Pearl Harbor Memorial (Q) Bridge

Traffic on the new I-95 NB portion of the Pearl Harbor Memorial (Q) Bridge

Partial demolition of original bridge in preparation for the construction of a temporary bridge to allow SB traffic onto the new Pearl Harbor Memorial (Q) Bridge

I-95 NEW HAVEN HARBOR CROSSING CORRIDOR IMPROVEMENT PROGRAM

New Haven – East Haven – Branford Quarterly Progress Report – December 2012

- 5 -

RECONSTRUCTION OF THE I-95 / I-91 / ROUTE 34 INTERCHANGE – CONTRACT E Contract E (SPN 92-531/622/627) includes reconstruction of the I-95/I-91/Route 34 Interchange. The project includes the reconfiguration of the Interchange to eliminate left lane exit and entrance ramps and provides for 2 lane interstate to interstate connections. The reconstruction will provide three travel lanes on I-95 through the Interchange, and includes fourteen new or modified bridges, twenty-one retaining walls, new drainage systems, signing and lighting.

Construction this quarter included:

• Continued staged demolition of existing structures throughout the interchange.

• Continued widening of existing I-91 NB bridges including construction of footings and abutments as well as structural steel erection.

• Completed interchange reconstruction elements that are required for the first Corridor-Wide Traffic Shift, shifting I-95 NB off of the existing Q-Bridge and onto the new Q-Bridge.

• Continued installation of foundation piles for new bridge abutments and piers as well as installation of formwork, steel reinforcing bars and concrete.

o Bridge 172 - Drove production piles at Abutment 2, placed concrete for Pier Cap 5N and column for Pier 4S and completed installation of bridge steel between Pier 3S and Abutment 2.

o Bridge 3035 - Completed concrete for footings at Pier 1, placed concrete for pier column and began placing concrete for wingwalls at Abutment 2.

o Placed deck parapets at Bridge 6609 (Part of connector from I-91 SB to I-95 SB).

o Formed bridge deck at Bridge 3039 (Connector from I-91 SB to RT 34 EB).

o Completed backfilling behind Abutments 1 and 2 at Bridge 167 and began installation of structural steel.

• Continued installation of sanitary sewer line at the 424 Chapel Street parking lot.

• Completed installation of drainage in the median of I-95 SB at Canal Dock Road.

Planned activities next quarter include:

• Continue bridge and retaining wall construction activities throughout the interchange.

• Continued staged demolition of existing structures throughout the interchange.

• Continued installation of foundation piles for new bridge abutments and piers as well as installation of formwork, steel reinforcing bars and concrete.

I-95 NEW HAVEN HARBOR CROSSING CORRIDOR IMPROVEMENT PROGRAM

New Haven – East Haven – Branford Quarterly Progress Report – December 2012

- 6 -

Steel erection for the elevated section of the western-most portion of I-95 SB

Began installation of concrete abutment footing on I-95 NB/SB (Bridge 172)

Iron workers installing reinforcement steel onto the I-95 SB bridge connector on the west approach of the new Q-Bridge

Demolition of the old Q-Bridge on I-95 NB going over East Street

I-95 NEW HAVEN HARBOR CROSSING CORRIDOR IMPROVEMENT PROGRAM

New Haven – East Haven – Branford Quarterly Progress Report – December 2012

- 7 -

PUBLIC INFORMATION PROGRAM WEBSITE - www.i95newhaven.com

Between June and December of this year there have been 20,995 visits to the program website. Website traffic peaked in conjunction with a program milestone – the opening of the I-95 northbound bridge of the new Pearl Harbor Memorial (Q) Bridge. The day prior to the opening, the website had 880 views. The highest amount of daily traffic so far this year took place on the day of the Ribbon Cutting Ceremony, held on June 22, 2012, with a record 2,170 visits. The website also saw a spike in traffic surrounding the Chicane Traffic Shift, which occurred during the weekend of October 19th-21st. On October 17th, the Wednesday before the traffic shift, the website had 440 views.

I-95 NEW HAVEN HARBOR CROSSING CORRIDOR IMPROVEMENT PROGRAM

New Haven – East Haven – Branford Quarterly Progress Report – December 2012

- 8 -

EVENTS The following events were held between June and December of this year:

Pearl Harbor Memorial Bridge I-95 Northbound - Ribbon Cutting Ceremony On Friday, June 22nd the I-95 New Haven Harbor Crossing Corridor (NHHC) Corridor Improvement Program held a Ribbon Cutting Ceremony marking the opening of the I-95 NB Bridge of the new Pearl Harbor Memorial (Q) Bridge. Commissioner James P. Redeker welcomed over 300 guests, including five Pearl Harbor survivors, Navy veterans, and government and state officials. Speeches were delivered by Governor Dannel P. Malloy, U.S. Representative Rosa DeLauro, Senator Richard Blumenthal and New Haven Mayor John DeStefano. Navy Master Chief Richard Iannucci read the names of the seventeen men that lost their lives during the attack on Pearl Harbor and accompanied each with the ringing of a bell. After the names were read, the surviving Connecticut Pearl Harbor veterans were invited to participate in a wreath-laying ceremony.

I-95 NEW HAVEN HARBOR CROSSING CORRIDOR IMPROVEMENT PROGRAM

New Haven – East Haven – Branford Quarterly Progress Report – December 2012

- 9 -

PUBLIC INFORMATION PRESENTATIONS The following presentations and tours were held between June and December of this year:

• The Structural Engineers of Connecticut participated in a tour on Tuesday, June 5th. Following the tour, Department of Transportation staff provided a presentation on the I-95 NHHC Corridor Improvement Program.

• On Tuesday, September 25th, Deputy Commissioner Anna Barry visited the program office for a presentation and tour.

• The Central Connecticut State University Construction Management Club participated in a presentation on Tuesday, October 2, 2012.

• The Coast Guard Academy visited the program office for a presentation and tour of the construction site on Thursday, October 22, 2012.

• Additional presentations and tours were given on Friday, June 15th, Friday, July 20th, Friday, August 17th, Friday, September 1st and Friday October 19th.

Upcoming Events for the First Quarter of 2013 will include:

• Grass Roots Neighborhood Outreach – Continued

• Noise Wall Public Information Meeting – January 24, 2013 at Conte-West Hills School in New Haven

• Engineering Week at The University of New Haven- February 2013

• 2nd Annual Career Fair - March 2013

• 4th Annual Open House - April 2, 2013