DC Water Embraced Alternative Delivery And Now There Are ...
Transcript of DC Water Embraced Alternative Delivery And Now There Are ...
DC Water Embraced
Alternative
Delivery…
And Now There Are
Lessons Learned
Diala Dandach, Supervisor, Program Management, DC Water Department of Engineering Services and Technical Services,
April 2015
Agenda
Background on DC Water’s Biosolids Program
Why DC Water Embraced Alternative Delivery
Lessons Learned to Date with More to Come
2
Background
370 MGD (ADWF Capacity) >1B hydraulic capacity
550 MG primary treatment
Total Nitrogen Old 7.5 mg/l
New 4.2 mg/l
Phosphorus to .18 mg/l
3
Background
Solids Processing of Three Different Sludges
Gravity Thickeners(Primary Sludge)
DAFT Bldg.(Biological Sludge)
Centrifuge Dewatering
Class B Cake Loadout
Lime
Biosolids Program Site
4
Background
Until recently, DC Water:
Collected and blended
primary, secondary, and
nite/denite sludges
Added lime
Thoroughly mixed
Dewatered with centrifuges
Hauled away to farmland
5
Background
Residual disposal a major
DC Water operation:
Lime stabilized class B
sludge
1200 wet tons/day
65, 20 yd3 trucks per day
6
Four Components and Three Delivery Methods
Dewatering
Lime
Store &
Loadout
Class B
DAFTs
Mix
R
R
Screening and
Pre-DewateringBelt Filter
Presses
Recycle
Processing
R
LoadoutCambi™ THP
Steam Biogas
Biogas Treatment and
CHP
Emissions
Mesophilic
Anaerobic
Digestion
Class A
Power
R
R
Gravity
Thickeners
Blend
Tank
Site
Preparation
Main Process
TrainDesign-Build
Combined Heat &
PowerDesign-Build-Operate
Site PrepDesign-Build-Build
Final
DewateringDesign-Build-
Build
Background
7
Background
The 2008 Biosolids Management Plan update identified Thermal
Hydrolysis Process(THP) with digestion as the most effective
solution for biosolids management at DC Water. Its benefits were:
Hedge against Class B biosolids land application restrictions
Hedge against electricity cost uncertainty using a combined heat
and power system
Benefit from a 50% reduction in quantity of biosolids production and
disposal costs
Generate Class A biosolids (increases diversity of product use)
Avoid costly upgrades to the existing lime stabilization process
8
Background
Five projects were developed
Project Name Procurement
Method
Construction
Bid Cost
Percent
Complete
Site Preparation DBB $5.4 million 100
MPT DB $206 million 99
CHP DBO $82 million 97
FDF 1 C DBB $7 million 100
FDF 2 C DBB $78 million 98
9
Main Process Train
Project Highlights
Blended Sludge mixing
Pre-dewatering to 15%-18%
4-train thermal hydrolysis
system
4, 3.8 mg mesophilic
digesters
10
Combined Heat and Power (CHP)
Project Highlights
Gas pressurization
Gas treatment including
siloxane removal
3 gas turbines
Auxiliary boiler
11
Final Dewatering
Project Highlights
16, 2-meter belt filter
presses
Polymer addition
Dedicated cake bins (solids
approximately 30+%)
12
Why Did DC
Water Embrace
Alternative
Delivery
13
Why Did DC Water Embrace AD?
Best value selection of contractors
Price certainty at an early phase for budget
management
Process performance guarantees
14
Why Did DC Water Embrace AD?
Best Value selection of contractor:
DB allows for a qualification step to select the
best team: designer and contractor
2-step process that still allows for competitive
pricing amongst the best shortlisted teams in
addition to a technical evaluation based on
points at the RFP stage
15
Why Did DC Water Embrace AD?
Price certainty at early stage:
In DBB, price is only known after Design is
100% complete
In DB, price is known after selection at early
stage of design.
16
Why Did DC Water Embrace AD?
Process performance guarantees:
In DBB, although designers are responsible,
performance liability is a grey area due to a
third part contractor. Usually a dispute topic.
In DB, one team means one responsible party
for the performance of the process.
17
Why DC Water embraced AD?
Why DBO:
Operating a power generation plant is not an
are of experience
Power production and savings guarantees
18
Lessons Learned
Divided by Project Stage:
Overall
Planning
Procurement
Design Phase
Construction
Startup and Commissioning
19
Lessons Learned – Overall
1. Educate all stakeholders at all levels on Alternative Delivery and how it
differs from DBB.
2. Develop a roles and responsibility matrix early for the Owner, the
consultants (PM, CM) and the Design-Builder
3. Develop a clear communication protocol for all phases of the work and
assign Points of Contacts between the Owner’s representatives and the
Design-Builder
4. The Design-Builder team structure is important when selecting and
qualifying teams
5. Customize your procurement process and documents to the internal
needs: level of prescriptivism was and remains an internal debate
6. It will take time and effort to successfully plan, prepare and implement a
new delivery method
20
Lessons Learned – Planning
1. Be realistic about the procurement schedule and be
mindful of not cutting into the contractor’s schedule
2. Where possible mitigate risks that may adversely
impact schedule and budget (i.e.. perform geotechnical
study early, site survey, hazardous waste)
3. Define project objectives and performance guarantees
and get concurrence from the team
4. Define desired level of prescriptiveness early and level
of control owner wants over the project
21
Lessons Learned – Procurement Phase
1. DC Water found the Technical Alternate/Preliminary
Technical Proposal process better than requesting variations
through RFIs
2. Proprietary meetings allow for clarification for both sides.
Documentation of meetings, questions, answers is important
and when appropriate, include an amendment to RFP.
3. Avoid catch all statements in contract - be clear in the
requirements
4. Mandatory requirements must be clear and be consistent
with the desired level of prescriptiveness
22
Lessons Learned – Negotiation Phase
1. Develop conformed bridging documents that
incorporate contract negotiations, amendments, and
accepted alternatives. Plan for time and resources to
complete.
2. Owner must be notified in writing by DB for any
changes to the bridging documents.
23
Lessons Learned During DB
Design Phase
1. Schedule needs to allow adequate time for review
2. Require and implement a strong QA/QC plan
3. Allow time for addressing issues and closing them. Do it in a
timely manner.
4. Implement a issues resolution process in order to solve the
issues at the appropriate level with a clear escalation process
24
Lessons Learned During DB
Construction Phase
1. Transition of roles from design phase to construction phase
for reviews needs to be addressed.
2. Design submittals in the construction phase proved to be an
issue and should be expected on a DB type contract
3. Changes after Final Design Drawings are approved must be
identified to the owner
4. Named manufacturers might take exception to certain
specifications: ensure in the RFP that named manufacturers
(if any) can meet the specifications required• This goes back to the level of prescriptivism
25
Conclusions
Establish your goals and success criteria
Educate the team and include all stake
holders including consultants
Pick the best team
Partnering at executive levels and project
level at all phases
Try and get ahead of issues
26
QuestionsQuestions?
27