0 November, 2014 Commission of Fine Arts DC CLEAN RIVERS PROJECT Division J – Northeast Boundary Tunnel Briefing for: District of Columbia Water and Sewer Authority George S. Hawkins, General Manager

Transcript of DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine...

Page 1: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

0

November, 2014

Commission of Fine Arts

DC CLEAN RIVERS PROJECTDivision J – Northeast Boundary Tunnel

Briefing for:

District of Columbia Water and Sewer AuthorityGeorge S. Hawkins, General Manager

Page 2: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

1

Northeast Boundary TunnelOverview

Northern Section of DC Water’s Combined Sewer Overflow (CSO) Tunnel System

Store and convey captured CSOs to DC Water’s Blue Plains AWWTP

5.1 miles long with an Inside Diameter = 23 feet

Eight drop shafts Diversion Chambers Odor Control and Ventilation Facilities Schedule:

• Award for Design-Build: December 2016• Construction: December 2016 – March

2022

NEBT

NEBT

Page 3: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

2

Northeast Boundary TunnelSites With Above Ground Construction

Site Location Property Owner Above Ground Construction

W Street Junction Shaft Site

Located South of W Street NE Between Downing Street NE and 14th

Street NE.

DPW • Ventilation Control Facility Building• Ventilation Vault Structure• Exposed Retaining Wall

R Street Diversions Site

Located at Intersection of 6th

Street NW, R Street NW and Rhode Island Avenue NW.

U. S. Under

District Jurisdiction

• Relocate Existing Traffic Signal Boxes• Reconstructed Cooper Park

Mount Olivet Road Diversions Site

Located Adjacentto the Mount Olivet Cemetery along Mount Olivet Road NE.

DPW • Installation of New Electrical Equipment in Cabinets Screened Behind Existing Fence

Page 4: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

3

W Street Junction Shaft Site Existing Site Photo Key

Photo Location

Image from Google Maps.

Photo 1

Image from Google Maps.

NORTH

Photo 3

Photo 2

Photo 4

Existing DPW Salt Dome

Existing Hill to Be Removed

W Street NE

Page 5: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

4

W Street Junction Shaft Site Existing Site Photos

Existing Hill to Be Removed

Photo 1Photo 2

Photo 4

Photo 3

Existing DPW Salt Dome

View of Amtrak Facilities

Natural Visual Barrier• The Ground Rises

along portions of W Street NE

• 35 Feet from curb line to remain undisturbed.

Page 6: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

5

W Street Junction Shaft SiteKey Design Elements

1. Ventilation Control Facility Building and Ventilation Control Vault will channel air from the Northeast Boundary Tunnel

2. Air will pass through carbon treatment during low flow conditions3. Retaining Wall will allow removal of existing hill to provide usable area for the

Department of Public Works4. Install 42-Inch high aluminum rail fence at retaining wall for fall protection5. Install 8-Foot high Screening Fence located 15 feet inside property line to

meet Zoning requirements 6. Green infrastructure includes:

a) Bioretention Area for entire impervious areab) Green roofc) Building design to LEED Silver equivalent

Page 7: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

6

W Street Junction Shaft Site Proposed Final Site Plan

BIORETENTION AREA

EXISTING SALT DOME

BELOW GRADE SHAFT

Page 8: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

7

W Street Junction Shaft SiteRendering 1: Aerial View

W Street Residences

Existing Salt Dome

DPW UsableSpace Created by Removal of Hill

Ventilation Control Vault Amtrak

Property

Ventilation Control Facility

BioretentionArea

35 Feet of Natural Vegetation and 8 Foot High Screening Fence

Green Roof

Page 9: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

8

W Street Junction Shaft SiteRendering 2: Ventilation Control Facility – East Elevation

Existing Salt Dome

35 Feet of Natural Vegetation and 8 Foot High Screening Fence

Page 10: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

9

W Street Junction Shaft SiteRendering 3: Ventilation Control Facility – South and West Elevations

35 Feet of Natural Vegetation and 8 Foot High Screening Fence

BioretentionArea

Proposed Materials

Aluminum Sun Screens

Precast Concrete Panels

Vision Roll Up Doors

Textured Precast ConcreteCorrugated Metal Panel(on East Elevation)

Page 11: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

10

W Street Junction Shaft SiteExample Retaining Wall and Screen Fence Materials

Limestone Texture Blocks as Manufactured By Redi-Rock or Similar

Louvered Screening Fence as Manufactured By Ametco or Similar

Page 12: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

11

W Street Junction Shaft SiteAs Viewed From Amtrak Rails

Vantage PointFrom Amtrak Rails

Ivy City Yard Tracks

Metal Shed

Salt DomeProposed Ventilation Control Facility Building

Key:Limits of field of vision in Rendering 4.

Field of vision of Ventilation Control Facility for Amtrak passenger.

Note: View from New York Avenue is completely obstructed by existing vegetation

Page 13: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

12

W Street Junction Shaft SiteRendering 4: View from Amtrak Rails

Proposed Ventilation Control Facility Building

Ivy City Yard Tracks

Metal Shed

Salt Dome

Conclusion: Proposed construction will not impact the view from Amtrak trains.

Page 14: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

13

R Street Diversions Site Existing Site Photo Key

Photo Location

Photo 4

DC Clean Rivers Construction at this Site is Below Grade(Relocation of Existing Above Ground Features Only)

NORTH

Image from Google Maps.

Photo 1

Photo 2

Photo 3

Cooper-Gordon ParkProject has been reviewed and approved by District DPR, DGS, HPO & ANC

Page 15: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

14

R Street Diversions SiteExisting Site PhotoPhoto 1

Photo 2

Photo 3

Park to Be Restored• Character of park

preserved• Amenities improved per

DPR & ANC request• All New Construction is At

or Below Grade• Existing Above Ground

Traffic Signal Cabinets Relocated Outside of Park

Photo 4

Existing Electrical Cabinets

Page 16: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

15

R Street Diversions SiteDesign Concept

1. All New Construction Located Underground2. Two Existing Traffic Signal Boxes to be Relocated Out of Park3. Cooper-Gordon Park to Be Restored Based on Extensive

Coordination Between:a) DC Department of General Services (DGS)b) DC Department of Parks and Recreation (DPR)c) DC Historic Preservation Office (HPO)d) Advisory Neighborhood Commission 6E (ANC)e) Community Groups

Page 17: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

16

R Street Diversions Site Proposed Final Site Plan

Cooper-Gordon Park

Park to Be Restored• Character of park

preserved• Amenities improved per

DPR & ANC request• All New Construction is At

or Below Grade• Existing Above Ground

Traffic Signal Cabinets Relocated Outside of Park

Page 18: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

17

R Street Diversions SiteCooper-Gordon Park Restoration Plan

Page 19: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

18

R Street Diversions SiteLooking North on R Street

**Conceptual Rendering: details may differ from appearance depicted**

Relocated Traffic Signal Boxes

Page 20: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

19

Mount Olivet Road Diversions SiteExisting Site Photo Key

.

NORTH

Images from Google Maps.

Mount Olivet Road NELooking West

DPW WV Avenue Facility Restored to Existing Conditions

• Restore Fence Consistent with Commercial-Light Industrial Zoning

• Above Ground Electrical Cabinets are Inside the Fence

Page 21: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

20

Mount Olivet Road Diversions SiteDesign Concept

1. Major New Construction is Located Underground2. New Above Ground Equipment Consists of:

• Electrical Cabinet• Electrical Transformer

3. Above Ground Equipment Located Behind Existing Chain Link Fence With Privacy Slats

4. Coordination in Progress with Department of Public Works (DPW)

Page 22: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

21

Mount Olivet Road Diversions Site Proposed Site Plan and Renderings

Electrical Cabinet

Transformer

Site Plan

Restore Existing Fence

Page 23: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

22

Request For Conceptual Design ApprovalNortheast Boundary Tunnel

Northeast Boundary Tunnel• Ventilation Control Facility Building and Appurtenances• Miscellaneous Above Ground Electrical Cabinets

Page 24: DC CLEAN RIVERS PROJECT Division J – Northeast Boundary …...0 November, 2014. Commission of Fine Arts DC CLEAN RIVERS PROJECT. Division J – Northeast Boundary Tunnel. Briefing

23

Questions