Dated::18.06.2012 Consequent upon the resignation of … · 2016. 11. 7. · Dated::18.06.2012 N O...
Transcript of Dated::18.06.2012 Consequent upon the resignation of … · 2016. 11. 7. · Dated::18.06.2012 N O...
-
N O T I C E Dated::18.06.2012
Consequent upon the resignation
of Sh.Buddhadev Gangopadhyay
from the post of Secretary of the
Society on account of personal
reasons, BOD has since selected
and appointed Md.Mustakim as
Secretary Of the Co-Operative
Society with immediate effect and
until further notice.
ChairPerson
Note:- To be displayed at Web site(http://niravra.angelfire.com)
-
Dated::18.06.2012
N O T I C E
As per the decision taken at the AGM held on 10.06.2012, following are
the different charges payable by the members for the year 2012-13. All dues
have to be cleared latest by 31st of July 2012 failing with which interest @2%
per month will be levied.
Sl. No.
Item of Charge AGM Approved
Amount(Rs.)
Already Paid by
April’12(Rs.)
Balance payable by 31.07.12 (Rs.)
1. Maintenance Charge 3600/- 3000/- 600/-
2. Car Parking Charge 1200/- 1000/- 200/-
3. 2-wheeler parking Charge 500/- 400/- 100/-
4. Tenancy Charge 8000/- 5000/- 3000/-
7200/- 800/-
2. It is Found that some members have not paid their past dues even
after long expiry of due date(s). They are requested once again to please pay
their dues along with accrued interest at the earliest.
Secretary
-
27.06.2012
Niravra Co-Operative Housing Society Ltd.
Sub.:- Data On 4-wheeler/2-wheeler under ownership of members and Air Conditioners installed at the
Residential Flats of the Society.
All members/residents are requested to kindly furnish requisite information as per the format below.
Secretary
Flat No.
4 –Wheeler with Regn.
No.
2 – Wheeler with Regn. No.
Air - Conditioners
Signature Tel.No. Split Window
Nos. Capacity Nos. Capacity
-
27.06.2012
N O T I C E
As approved at the AGM held on 10.06.2012, the following charges are
intimated for information and necessary action of all concerned.
Sl. No.
Item Of Charge Amount Effective from
1. Overnight car parking fee for guests/visitors
4-wheeler: Rs. 200/Day
2-wheeler: Rs.100/Day
1st July 2012
2. Penalty for Offence under section 93(2) (b) Of WBCS Act’2006 in letting out of flats.
Rs.10,000/-
With Immediate Effect
3. For continuance of the offence mentioned at Sl.No.2 above for period exceeding two months.
Rs.1000/- Per Month
-Do-
Secretary
-
Dated::25.06.2012
NIRAVRA Co-Operative Housing Society Ltd.
There will be an inspection from CESC Officials of the Electrical Installations
including the main switch/meter box area in each building. To facilitate the same the
meter box/main switch area at the ground floor of each building need be kept clean as
well as be kept easily accessible. All the bi-cycles parked in that area are, therefore, to
be shifted immediately. For parking the bi-cycles, a part of the Security Rest Room has
been cleared and specially earmarked.
All the members/residents are therefore requested to shift their bi-cycles
immediately to the earmarked place.
Secretary
-
17.07.2012
Niravra Co-operative Housing Society Limited
Notice
Sub.:- Non–Payment of Maintenance and Other Charges.
It is found that many members (both resident & non-resident) are not paying the Co-operative dues for quite a long time. Some members have not paid their dues for years together. Repeated requests/reminders in this regard have been/are being ignored. It may be noted that there have been all round increase in all the recurring expense heads and in absence adequate fund it has become difficult to meet both ends. Besides, the developmental work undertaken cannot be sustained unless all members co-operate and pay their dues in time. There are stringent provisions in the WBCS Act’2006 to deal cases of continuous default which we do not want to invoke and neither do we want to embarrass the members by notifying publicly their names and flat nos. We earnestly, once again, request all the members to clear their dues at the earliest.
Secretary
-
17.07.2012
Niravra Co-operative Housing Society Limited
Notice
Sub.:-Relatives staying at member’s flat
As per the provisions of the WBCS Act’2006 all relatives staying at member’s flat have to enter into tripartite agreement to be signed by the relative, member and the Co-operative. All concerned are therefore requested to please do the needful at the earliest.
Secretary
1.Flat No.1/15.
2.Flat No.6/7
3.Flat No.3/10
-
5.08.12
Niravra Co-operative Housing Society Limited
Notice
This is to inform that the enclosures for the Meter Boxes and the Electric Main switches, recently installed in all the Buildings of the Society, have been put under lock and key. The keys have been handed over to the security personnel. The residents in need of access to the meter box/main switch may obtain the same from the security duly recording details in the register kept for the purpose. However, once done with they may return the key on the same day positively. All are requested to kindly co-operate.
Secretary
-
01.09.2012
Niravra Co-Operative Housing Society Ltd.
NOTICE
It is noticed that some members are not displaying the logo of the Society on their cars. The
appeals made in this regard have so far been ignored.
The concerned members are once again requested to
please display the logo of the society on their cars
without any further delay. They may collect the logo-
stickers from the Security Post.
All are requested to co-operate.
Chairperson
-
01.09.2012
Niravra Co-Operative Housing Society Ltd.
NOTICE
This is to inform that with effect from 1st September 2012, one of our security peronnel will be
on round-the-clock duty at the Northern Main Gate
i.e Manjulika – ‘A’ Gate. This will facilitate
unrestricted 24x7 entry of members/residents of our
Society to the Campus.
Chairperson
-
Niravra Co-operative Housing Society Limited
Urgent Notice Sub.:- Celebrating a Pollution free Dewali
This Year the City Police in no uncertain terms has directed all concerned to refrain from bursting the banned firecrackers during the festival of Kalipuja/Dewali. The Police administration specifically has asked the residential complexes to remain vigilant in this regard and enforce strictly that the acoustic pollution is within the prescribed limit. In view of the above the residents of the Co-operative are herewith requested not to light/burst such crackers for our own safety and to ensure that the directives from the City Police are complied with both in letter and spirit. All are requested to cooperate.
ChairPerson
-
27.11.2012
Niravra Co-Operative Housing
Society Ltd.
N O T I C E
It is informed that
Md.Mustakim has since
resumed as Secretary w.e.f
18.11.2012.
ChairPerson
Copy to: Web site(http://niravra.angelfire.com)
http://niravra.angelfire.com/
-
28.11.2012
Niravra Co-operative Housing Society Ltd.
N O T I C E
As per the decision taken at the AGM, the Deep Tubewell Resinking
Charge (Last Installment) is to be collected from all the members. The
amount may be paid latest by 31st December,2012 failing with which
interest @2% per month will be levied.
Sl. No.
Item of Charge Amount (Rs.)
Payable by
31.12.12 1. Deep Tubewell Resinking Charge(Last
Installment)
1000/-
2. It is found that some members have not paid their past
installments even long after the expiry of due date. Repeated reminders in
this regard have been ignored. These members are requested once again
to please pay their installments and other dues along with accrued
interest at the earliest.
Secretary
-
Niravra Co-operative Housing Society Ltd.
Notice
Sub.:-Disposing off the Junk Bi/Tri-cycles
Attention of all concerned is invited to the notice issued earlier for disposing off the bi/tri-cycles which are
in dilapidated condition. The owner residents are once
again requested to please take suitable action at the
earliest and latest by 31st Dec.’2012. In the event of non-
compliance BOD will take necessary action as may be
deemed fit to clear off the occupied space.
3.12.12
Secretary
-
Niravra Co-operative Housing Society Limited
Notice
The roof-doors of all the buildings will
henceforth be kept under lock and key. The keys
will be available with the security. Anyone
desirous of access of the terrace may obtain the
key from the security. Once done with, the key
may be returned on the same day and latest by
the evening.
It is also informed that duplicate key can be
provided to any willing member, on requisition.
The measure has been taken to ensure security and safety of the residents.
3.12.2012
Secretary
-
19.12.2012
NIRAVRA Co-Operative Housing Society Ltd.
N O T I C E
Reproduced below is the extract of a letter received from Satellite
Communication, 344 RR plot Kol-700107 for information and necessary action by the
concerned residents.
“
Ref.No…. Dated 17.12.2012
To, The Secretary Niravra Co-oprative Housing Ltd. Kol-107
Sub.:- Price of Set Top Box Dear Sir, We are to inform you that few members of our cable subscribers of your complex have so far not taken their set top box till date. On the other hand, the price of set top box has increased and hence we are constrained to supply the said box to rest of our subscribers at the price of Rs.800/- from …..14th Nov.2012. We, therefore request those subscribers to collect their set top box at the above mentioned price. ………………………………………………… Thanking You,
Yours faithfully, Sd/-
Satellite Communication”
Secretary
-
No.hGM_13/Niravra Dated. 9.01.2013
Niravra Co-operative Housing Society Ltd.
Half – Yearly General Meeting
N O T I C E
In terms of Section 30 of the West Bengal Co-operative Societies Act’2006,
notice is herewith given to all members informing that the half-yearly General Meeting
will be held on 03.02.2013 (Sunday) at 10:30 AM in the premises of the Society to
transact the following business.
Agenda for the meeting:
To review the activities of Society on the basis of the report placed.
To consider the latest audit report.
To review the financial position on the basis of provisional accounts and consider proposal for raising fund for the proposed relaying of inner campus
road and to meet extra expenditure incurred for developmental work.
To consider any other matter as may be brought in the meeting in accordance with the provisions of the Act as well as bye-laws of the Society.
(Md.Mustakim) Secretary
To, All Members.
-
Niravra Co-operative Housing Society Limited
Notice
No. Dated. 5.02.2013
As decided in the Half-yearly General meeting held on 03.02.2013, an amount of Rs.3500/- is to be paid by each member towards relaying of inner campus road, various developmental activities and replenishment of maintenance fund as per the following schedule.
Sl. No. Amount (Rs.) Payment Due Date
1. 2000/- Latest By 28.02.2013
2. 1500/- Latest By 30.04.2013
All are requested to kindly co-operate and pay the amount within the due date. Kindly be informed that failure to make payment within the due date will attract penal interest of 2% per month.
Secretary
-
Niravra Co-Operative Housing Society Ltd.
N O T I C E 17.02.2013
It is informed that Smt. Rajalakshmi Ray,
the Chairperson of the Society will be away
from the campus for a period of about a
month and a half. During this period Sh. Sunil
Mitra, Vice-Chairman will look after the office
of the Chairperson.
Secretary
Copy to: Web site(http://niravra.angelfire.com)
-
20.03.2013
Niravra Co-operative Housing Society Limited
Notice
The following items of work have been undertaken and
are underway.
1. Repair/replacement of soil/rainwater pipes, pipe-bends,
joints etc.
2. Repair of damaged/cracked sunshades, railing-
bases at balcony, worn out plaster at outer walls etc.
While the plumbers/masons have been asked to be careful
so that no damaged portions are left out,
members/residents are also requested to remain alert in
order to ensure that all damages/cracks in and around their
flats are adequately attended.
All are requested to cooperate.
Secretary
-
28.03.2013
N O T I C E
All members are requested to pay the following charges latest by 30th April 2013.
Members are also reminded that the due date for payment of amount of Rs.1500/- as decided
at Half - Yearly General Meeting and notified on 05.02.2013 also falls on 3oth April 2013.
Delay in the payment of dues will attract penal interest @2% per month.
2. The above charges are for the year 2013-14 and are subject to ratification at AGM. In
case it is decided to enhance the charges, the balance has to be paid by the due date to be
fixed at AGM.
3. It is found that some members have not paid their past dues even long after the expiry
of due date(s). These members are requested once again to please pay their dues along with
accrued interest at the earliest.
Secretary
Sl. No.
Item of Charge Amount(Rs.)
1. Maintenance Charge 3600/-
2. Car Parking Charge 1200/-
3. 2-wheeler parking Charge 500/-
-
02.05.2013
Niravra Co-Operative Housing
Society Ltd.
N O T I C E
It is informed that Smt.
Rajalakshmi Ray has since
resumed as Chairperson
w.e.f 01.05.2013.
Secretary
Copy to: Web site(http://niravra.angelfire.com)
-
8.05.2013
Niravra Co-Operative Housing Society Ltd.
Members are herewith informed that the
Annual General Meeting of the Society has been
decided to be held on 30.06.2013. The election of
the new BOD will also take place in the meeting.
JRCS has already appointed an ARO for the
purpose. Further action as per the requirement of
statute will follow.
Secretary
Copy to: Web site(http://niravra.angelfire.com)
-
8.05.2013
Niravra Co-Operative Housing Society Ltd.
NOTICE
The draft Voters’ list has been published and put up at the Office Notice Board as well as at the
Notice Board at Security Post. As has been
mentioned in the last page of the list, the members
are free to submit their objections, if any, on
18.05.2013 between 7 PM to 9 PM.
Secretary
-
Niravra Co-operative Housing Society Ltd.
Notice
Sub.:- Postponement of Election of new BOD.
Joint Registrar of Co-Operative Socities, K.M.A.H Cell have communicated that Co-Operative Election Commission,
WB have passed an order vide no. 429-CEC/IV-01/2012-13
dated 24.05.13 that election of Co-Operative Societies at all
stages in the State to be held under their supervision and
control will remain postponed until further orders.
Accordingly, the election of the new BOD of the Society
scheduled to be held on the day of the AGM on 30.06.2013
will also stand postponed. The AGM, however, will be held
as scheduled on 30.06.2013. Notice for the same will be issued
separately.
27.05.2013
Secretary
-
Niravra Co-operative Housing Society Ltd.
Notice
An Aluminum extensible wall ladder Of 24ft x 40ft
(24 ft – nominal length to be extended up to 40 ft) has
been purchased by the Society and is kept at the Security
rest room. Members/residents can put the ladder into use
at a charge of Rs.50/- per day. Requisition for the same
can be given to Security outpost.
Secretary
-
Niravra Co-operative Housing Society Ltd.
Annual General Meeting
N O T I C E
In exercise of the authority conferred on the undersigned under sub-section (2)
of section 29 of the West Bengal Co-operative Societies Act, 2006, notice is hereby given to
all members of the society that the Annual General Meeting for the Co-operative year 2013-
2014 will be held on 30/06/2013(Sunday) at 2:30 P.M. in the premises of the society where
the following business will be transacted.
Agenda of the Annual General Meeting (2013-2014)
Confirmation of the proceedings of the last Half-Yearly and Annual General Meeting
(2012-2013);
Consideration of the latest audit report (2012-2013) and audited statement of accounts
referred to in section 98, if received before the date fixed for the annual general meeting.
Consideration of the Annual Report prepared by the Board;
Approval of the Annual Budget (2013-2014);
Consideration of any other matter which will be brought at the meeting as miscellaneous
items in accordance with the provisions of the Act and the Bye-Laws of the Society.
6.06.2013
(Md.Mustakim)
Secretary
-
Niravra Co-operative Housing Society Ltd.
Schedule of Charges
NOTICE
As per the decision taken at the AGM held on 30.06.2013, the SCHEDULE OF
CHARGES for 2013-14 are herewith notified for information and necessary action of
the members. Failure to make payment on or before the due date will be charged with
interest @2% per month.
Sl. No.
Item of Charge Amount (Rs.)
Already Paid(Rs.)
Balance (Rs.)
Payable By Remarks
1. Maintenance 5000/- 3600/- 1400/- 31stJuly’13
2. Tenancy 10000/- 8000/- 2000/- -do-
3. 4-wheeler Parking 1300/- 1200/- 100/- -do-
4. 2-wheeler Parking 550/- 500/- 50/- -do-
5. Building Restoration Fund
2000/- - a. 1000/- b. 1000/-
a. 30th Sept’2013 b. 28th Feb’2014
Will continue in 2014-15
6. Penalty for defaulters
1.Maintenance: 2.Tenancy: 3.Parking Fee(4-wheeler): 4.Parking Fee(2-wheeler):
a. 250/- b. 500/- c. 150/- d. 75/-
-
-
Yearly
This is in addition to the interest usually charged and have to be paid on failure to make payment during the year in which the amount is due. This comes into force with retrospective effect.
2. It is found that some members have not paid their past dues even
long after the expiry of due date. Repeated reminders in this regard have
been ignored. These members are requested once again to please pay
their installments and other dues along with accrued interest and
penalty at the earliest.
2.07.2013
Secretary
-
Niravra Co-operative Housing Society Limited
Notice The tenure of the present BOD will come to an end on 3rd Oct’2013. The BOD however decided to relinquish office in June’2013 so that the Election of the new
BOD and the AGM could be held on the same date. The idea was to avoid extra
expenditure. Accordingly, we took up the matter with JRCS vide our letters dated
11.12.2012 and dated 16.01.2013. Subsequently, we personally met JRCS and as
per suggestion,BOD on 16.04.2013 proposed 23rdJune’13 for AGM/election. As an
alternative, 30th June was also suggested. JRCS however accepted the later date
i.e. 30th June’2013 and appointed an ARO(Asst. Returning Officer) for the election.
Accordingly, the process of election was initiated and draft and final Voters’ list
was published. However, the ARO on 24.05.2013 forwarded an WB Govt. Order
wherein all elections under Co-operative Election Commission were put in
suspension in view of State Panchayat Polls until further orders. From our side,
however, on 16.07.2013 we proposed two dates e.g. 8th Sept. and as an alternative
- 15th Sept’13 for election. We kept in touch with ARO and ultimately the ARO on
8.08.2013 informed that the above mentioned Govt. order is yet to be revoked
and as such an uncertainty has cropped up in the holding of the Co-operative
elections. However, there is a chance of review of the order at the end of the
current month.
In view of the above the election cannot be held on any of the two dates
(i.e.8th /15th Sept’13) proposed by us. On the other hand the end of tenure date of
the present BOD is fast approaching. Under this circumstance and considering that
a minimum of 21 days’ period is to be provided between notice and actual election
– appropriate action
need to be taken else Special Officer will be appointed in place of the present
BOD once its tenure gets over. Thus, for no fault of ours we’ll end up at the
receiving end.
-
One way out, perhaps can be to seek legal redress. We also plan to meet
JRCS on the matter.
This notice is given to keep members abreast of the development and they
are also requested to inform the BOD of any alternate suggestion to tide over the
jinx.
Secretary Dated.11.08.2013
-
Niravra Co-operative Housing Society Ltd.
Building Restoration Fund(2013-14)
NOTICE
Members are reminded that in the AGM held on
30.06.2013 collection of Rs.2000/- payable in two
installments respectively in months of sept’2013 and
Feb’2014 @Rs.1000/- under Building Restoration Fund
was decided and approved.
Accordingly, the first installment of Building
Restoration Fund amounting Rs.1000/- is due to
be paid latest by 30th Sept 2013. All are requested
to please pay the amount within due date.
27.08.13
Secretary
-
6.10.2013
Notice for Special General Meeting
In exercise of the authority conferred on the undersigned as per provision of the WBCS Act
2006, Rules 2011, notice is hereby given to all members of the society that a special
General Meeting has been convened on 14/11/2013 at 3 P.M.in the
premises of the society with a single point agenda to hold election for
electing Board Of Directors of the Society.
Copy of the election schedule is enclosed.
Secretary
-
6.10.2013
Election Schedule Of
Niravra Co-operative Housing Society Ltd.
1. No. of Vacancies to be filled up by election: 13.
2. Qualification for eligibility for membership of the Board: As per relevant provisions of WBCS Act
2006, Rules 2011 and Registered Bye-Laws Of the Society.
3. Date, Time and Place for issue of Nomination Papers:
Date:- 30.10.2013 to 04.11.2013
Time:- 8 PM to 9 PM.
Place:-Office Of the Society.
4. Date, Time and Place for filing of Nomination Papers:
Date:- 30.10.2013 to 04.11.2013
Time:- 8 PM to 9 PM
Place:- Office Of the Society.
5. Date, Time and Place for Scrutiny of Nomination Papers:
Date:- 06.11.2013
Time:- 2 to 3 PM
Place:- Office Of the Society.
6. Date of publication of valid nomination after Scrutiny:
Date:- 06.11.2013
Time:- After 3 PM.
Place:- Office Of the Society.
7. Date, Time and Place for withdrawal of Nomination Papers:
Date:- 07.11.2013
Time:- 2 to 3 PM
Place:- Office Of the Society.
8. Date, Time and Place for publication of list of contesting Candidates:
Date:- 07.11.2013
Time:- After 3 PM
Place:- Office Of the Society.
9. Date, Time and Place for Election:
Date:- 14.11.2013
Time:- 4 to 6 PM.
Place:- Office of the Society
(Biswajit Pramanik) Asstt. Returning Officer.
-
14.11.13
Niravra Co-operative Housing Society Limited
O R D E R
In terms of regulation 3(17) of West Bengal Co-Operative Election regulations 2012, I do
hereby declare that following candidates are elected as directors from the Niravra Co-
Operative Housing Society Ltd..
Sl.No. Name Flat No. 1. Abdul Samad D-6/3 2. Sh. Bikash Roy Chaudhury D-11/5 3. Sh. Devadatta Sinha D-13/3 4. Sh. Gautam Das D-7/14 5. Sh. Mahadeb Kumar Basu D-13/9 6. Sh. Mrinal Kanti Bhadra D-13/15 7. Sh. Piyal Nandi D-10/9 8. Sh. Prabir Kumar Chattaraj D-9/10 9. Sh. Sujoy Kumar Basu D-5/3
10. Sh. Sunil Kumar Mitra D-4/4 11. Sk.Md.Mustakim D-1/16 12. Smt. Namita Das D-6/11 13. Smt. Rajlakshmi Ray D-1/9
(Sh.Biswajit Pramanik)
ARO
-
7.12.2013
Niravra Co-operative Housing Society Limited
N O T I C E
In the meeting of Board Of Directors held on 7.12.2013 at
4 PM wherein Sh.Biswajit Pramanik , ARO was also present, Office
bearers of the Society were unanimously elected. Accordingly, the
constitution of the BOD stands as hereunder.
1. Smt. Rajlakshmi Ray D-01/09 Chairperson 2. Sh. Devadatta Sinha D-13/03 Vice-Chairperman 3. Sh. Sunil Mitra D-4/04 Panel Chairman 4. Sk.Md.Mustakim D-1/16 Secretary 5. Sh. Bikash Roychoudhury D-11/5 Treasurer 6. Sh. Prabir Kumar Chattaraj D-9/10 Director 7. Sh. Sujoy Kumar Basu D-5/3 Director 8. Smt. Namita Das D-6/11 Director 9. Sh. Mrinal Kanti Bhadra D-13/15 Director
10. Sh. Mahadeb Kumar Basu D-13/9 Director 11. Sh.Piyal Nandi D-10/9 Director 12. Abdul Samad D-06/03 Director 13. Sh. Gautam Das D-07/14 Director
Sd/- Secretary
-
17.01.2014
NIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD.
Half-yearly General Meeting
Notice
In exercise of the authority conferred on the undersigned as per provision of the WBCS Act 2006, notice is
hereby given to all members of the society that the half-yearly General Meeting will be held
on 16/02/2014 at 4 P.M.at the premises of the society to transact business as per
the agenda points mentioned hereunder. Members are requested to please
attend the meeting.
Agenda for the meeting:
To review the activities of the Society on the basis of report placed. To review the financial position on the basis of the provisional accounts and
to consider proposal for raising of fund for the implementation of sanitation project.
To consider any other matter as may be raised in the meeting in accordance with the provisions of Bye-Laws and the Co-operative Act.
(Md.Mustakim)
Secretary
To, All Members
-
Niravra Co-operative Housing Society Ltd.
Notice
Dated.17.02.2014
In the Half-Yearly General Meeting held on 16.02.2014,
the proposed Sanitary Project (i.e. work relating to taking
out of the U-pipes of kitchen and toilets from inside the
flats) and the charges payable thereof, was discussed and
decided.
As approved each member has to pay an amount of
Rs.9500/- for the implementation of the project. The
amount will be collected in instalments and as per the
mode mentioned hereunder.
1st Instalment: Rs.5000/- to be paid by 31st
March’2014.
2nd Instalment: Rs.4500/- to be paid by 30th
June’2014.
Members are requested to kindly make payment
accordingly.
Secretary
-
Niravra Co-operative Housing Society Ltd.
Notice
Dated.05.03.2014
All members are informed that before installation of Air-Conditioner(s), the connected load at the respective
Flat may be increased suitably to avoid any disbalance in
the distribution of power inside the campus. It is also
reminded that intimating CESC about installation of AC is a
statutory requirement.
Members are requested to take necessary action
accordingly.
Secretary
-
NIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD.
Dated.02.04.2014
N O T I C E
All members are requested to pay the following charges latest by 30th April 2014.
Members may kindly note that delay in the payment of dues will attract penal interest @2%
per month.
2. The above charges are for the year 2014-15 and are subject to ratification at AGM. In
case it is decided to enhance the charges, the balance has to be paid by the due date to be
fixed at AGM.
Secretary
Sl. No.
Item of Charge Amount(Rs.)
1. Maintenance Charge 5000/-
2. Car Parking Charge 1300/-
3. 2-wheeler parking Charge 550/-
-
NIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD.
Dated.12.04.2014
N O T I C E
Recently there have been two instances wherein the toilet taps/wash-basin taps were found to be left open in closed flats. Apparently, the residents ‘forgot’ to close the taps
before going out – in one occasion, for work and in other for long excursion. The end result of
the carelessness – the overhead tank drained out in no time and in this summer, the family
members in different flats had to suffer. Temper ran high. Several complaints were lodged and
the BOD, obviously, was at the receiving end. To cope with the situation, the pump was run
several times to lift adequate water. But for the carelessness and callousness of few
individuals the situation would not have arisen. Residents are requested to be more careful
that all water outlets are tightly and firmly closed after use and that there are no leakages at
the taps or cisterns.
2. Empty liquor/beer bottles have been found to be strewn about, in the terrace and at the top of the staircase. This is objectionable as well as dangerous. While we have no
comment about the drinking habits of the residents but littering of terrace, stairs or campus
with empty bottles is certainly a matter of concern. Attention of all concerned is drawn to this
matter.
3. Complaints have been received that there had been attempts to deliberately damage the outdoor unit of AC located at the rooftops. This is rather serious and was thus far unheard
of. Members are requested to remain vigilant and such incident must not recur in future.
All are requested to kindly co-operate on the matters mentioned above.
Secretary
-
Niravra Co-Operative Housing Society Ltd.
Dated.:18.04.2014
N O T I C E
In spite of extensive discussion at AGM and half-yearly GM, certain
points and FAQs need to be clarified for information of the members. The
same are mentioned here under .
Scope Of Sanitary Project: The aim is to take out of the boundary
wall of the buildings, the waste lines of kitchen and toilets which
appear as U-shaped pipe-bends at the ceilings of the flats at 2nd,1st
and ground floor of each building. In this way the menace of
occasional dripping of dirty water the residents at these flats face,
will be gotten rid of.
The Work:
1. Partial chipping away of the kitchen, main toilet and WC
floors.
2. Dismantling the main – toilet embedded in the platform at
the main bathroom. Dismantling the platform.
3. Removing the U-bends.
4. Installing a new WC at the dismantled site.
5. Fixing new waste lines and taking the same outside the flats.
6. Sealing the gaping holes on the floor.
Faqs:
a. All costs for the above will be borne by the society out of the
fund being collected.
-
b. The new WC will be of standard type and will be selected out
of the best available but according to the available fund. In
case any member desires to install something different then
the extra cost has to be borne by him/her.
c. The making good of the floor for damaged tiles/marble is
outside the scope of the project. The floor will be finished
with cement plaster. As such,cost of preparation of the
damaged floor with marble/tile has to be borne by the flat-
owner.
d. In flats where WC (S-trap type) has already been installed,
still it needs to be dismantled.
e. A project committee has already been formed and notified.
f. Tender for the job has already been published in leading
newspaper.
g. Project will take off once all essentialities are completed by
the committee.
h. For any further querry, members are free to contact at the
office with the convenor of the Project Committee.
Secretary
-
Niravra Co-operative Housing Society Limited
An Appeal
The green grass at the Children’s Park in our campus is under destruction, thanks to the game of football being played regularly by the few of the boys of the Society. The green stretch that was built with considerable effort and money are being ravaged. Our efforts to desist them went in vain as these boys ignored requests from all of us. It pains to see that boys from an HIG-campus have urchin like attitude and body language of defiance. Because of them the rightful users of the park (i.e. the children) do not find entry inside. The matter was also brought to the notice of the guardians of these boys but to no avail. The park belongs to all of us. As such the responsibility to protect also lies with all the residents. Therefore, all the residents including the Ladies may please come forward and make a concerted effort so as not to allow playing of such games that may damage the green grass or destroy it. This appeal is a last ditch effort to protect the park as otherwise we do not find any other way to protect it. Dated:-08.07.2014 Secretary. To, Personal attention of all residents.
-
Niravra Co-Operative Housing Society Ltd.
Sub.:- Sanitary Project - Progress reg.
Though the work of the project took off at the intended time i.e immediately after the press tender and selection of vendor on the basis of submitted rates but
abruptly the work stopped as the selected vendor refused to continue work at the
quoted rate of Rs.3000/-(excluding Material Cost) per flat. Instead,for the
continuation of work he asked for a rate of Rs.4400/- per flat. In the meeting with
Project Committee, he submitted his inability to continue with the work and
accordingly the work order placed on him was cancelled. The second lowest rate
was Rs.3500/- per flat. We tried to contact the particular vendor but he could not
be traced/contacted. The project committee then decided to offload the work to
two other vendors who approached us for the work. Unfortunately, they also
backed out. Next Project Committee/BOD members through personnel contacts
and through known sources approached plumbers of known acumen. Several
turned up but backed out. Finally, after several rounds of discussion, two
plumbers viz. M/s Entazul Khan and M/s Pradip Naskar were selected. The Project
Committee approved these plumbers for the work at the rate of the second lowest
quote of Rs.3500/- (excluding Material) per flat. The work has since started and is
being carried out independently by these two teams. Since then there has been
steady progress. Already work has been completed in 25 nos. Of flats. We have
hired a person to supervise the work, issuance of materials and to keep record of
day to day jobs. Convenor of Project Committee and BOD members also keep track
of day to day activities as far as possible. But needless to say that best Supervision
has to come from the residents themselves in whose flats the work is underway.
Cont’d...2/-
-
2. For the successful implementation of the work, it is imperative that the
work takes Off simultaneously at flats in all the floors and located in a vertical line
i.e at the four flats one top of another. Refusal to let do the work or closed flat
jeopardise the project work in all the flats in that line. Members are therefore
requested to co-operate for the completion of the project. Residents are informed,
in advance, prior to the commencement of the job.
3. It may kindly be noted that work involves the following jobs:
Dismantling the existing system.
Taking out the U-bends.
Digging holes across the wall.
Jamming the gaping holes on the wall.
Sealing the gaping hole on the floor and allowing setting time.
Chipping the floor for a positive slope.
Installing new WC, cistern etc.
Fitting Pipes, bends etc. And connecting the outlines as well as
the WC with the outside pipes.
Sundry plumbing work.
It takes usually 4 to 5 days to complete successfully all the above. This period
might extend if flat owners go, additionally, for tile-fitting of the floor.
All are requested to bear the discomfort / inconvenience for the period of
work. Once the work is completed the menace the residents faced will be taken
care of permanently. If everything goes as planned, ALMIGHTY willing, the project
will be completed by August or 1st week of September’2014.
Dated.20.07.2014.
Secretary
-
Niravra Co-operative Housing Society Ltd. N O T I C E
The installment of Building Restoration
Fund amounting Rs.1000/- is due to be
paid latest by 30th Sept 2014. All are
requested to please pay the amount within
due date else interest @2% P.M will be
levied.
The members who have not yet paid dues
under different Heads e.g. Maintenance(’13-
14,’14-15), Sanitary Project(Mar’&June’14) etc.
are once again requested to pay their dues
without any further delay. It may be noted
that outstanding dues now stands at
Rs.6,00,000/-(approx.).
01.09.14
Secretary
-
Dated.02.09.2014
Niravra Co-operative Housing Society Ltd.
Annual General Meeting
N O T I C E
In exercise of the authority conferred on the undersigned under sub-section (2) of Section 29 of the West Bengal Co-operative Societies Act,2006, notice is hereby given to all
members of the Society that the Annual General Meeting for the Co-operative year 2014-15
will be held on 28.09.2014 at 3:00 PM in the premises of the Society.
Agenda for the meeting is as mentioned hereunder,
Confirmation of the proceedings of the last Half-Yearly and Annual General Meeting
(2013-14).
Consideration of the Audit Report (2013-14) and audited statements of accounts.
Consideration of the Annual Report prepared by the Board.
Approval of the Annual Budget (2014-15).
Consideration of any other matter as may be raised in the meeting as miscellaneous
item in accordance with the provisions of the Act and Bye-Laws of the Society.
(Md.Mustakim) Secretary.
To, All Members.
-
Niravra Co-operative Housing Society Ltd.
Building Restoration Fund
NOTICE
As per the decision taken at the AGM held on 28.09.2014, the CHARGES for
Building Restoration Fund have been revised. The rate now stands at Rs.1500/- in
place of Rs.1000/- and is to be paid by 30th September and 28th February every
year. The details are as indicated below.
Sl. No.
Item of Charge Amount (Rs.)
Payable By
1. Building Restoration Fund
1500/- 30th Sept.
2. -do- 1500/- 28th Feb.
2. For the current year, the amount due at Sept’2014 can be paid
by 31st December’2014. Those who have already paid the amount at the
old rate of Rs.1000/- can pay the balance amount of Rs.500/- latest by
31st Dec’2014.
Dated 29.09.2014
Secretary
-
Niravra Co-Operative Housing Society Ltd.
NOTICE
Sub.:- Dengue outbreak
Four cases of dengue have been reported in our campus. KMC volunteers/personnel have already visited the campus and have spread insecticide
for killing mosquito larvae. As a precautionary measure we’re also applying
bleaching powder at the drains/accumulated water in the campus. Residents are
also requested to remain vigilant so that there is no accumulated water in and
around their flats. The places to be particularly careful about are:
At the outlet container of refrigerator compressor which holds water.
The container must regularly be emptied.
The plastic containers under the flower pots that hold the excess water
from the watering of the plants. The water can be germinating spot for
larvae.
Bottle/container at indoor containing plants like money plant or any
other decorative saplings. Regularly, fresh water need be used.
Plastic Cups, sweat meat cups or other plastic/metal containers thrown
carelessly in and around the buildings. Rain water or accumulation from
other sources at these cups can be safe breeding place for mosquitoes.
All are requested to co-operate.
Dated.10.09.2014.
Secretary
-
Niravra Co-operative Housing Society Ltd.
Parking Charge(2014-15): Clarification
N O T I C E
In the light of the decision taken at the AGM/BOD meeting, following clarifications are issued for information and necessary action of all concerned.
Members: There is no change in the parking fee either for 2-wheeler or 4-wheeler. Full
charge will be levied irrespective of the period of parking i.e. be it full year or part of the
year.
Tenants:
1. 4-Wheeler: Four wheeler parking is not allowed.
2. 2-Wheeler: Annual Parking Charge is Rs.6600/-. Full year’s charge is payable
if the period of parking is more than six months. However, for period of parking of
six months or less, half of the above amount i.e. Rs.3300/- is to be paid by the
concerned tenant.
Dated:-04.11.2014.
Secretary.
-
Niravra Co-operative Housing Society Ltd.
N O T I C E
Fire extinguishers of 4 Kg. capacity MAP powder-based ABC type
have been installed at an accessible height at the first landing of staircase
of each building. Residents are requested not to pull the ring attached to
the cylinder or unhook it except at the hour of need. If so done, the
extinguisher may be rendered useless. Already such an episode has
happened in Building No.11 with the result that Mono Ammonium
Phosphate powder were thrown out of the extinguisher resulting in
lowering of its pressure inside the cylinder thus jeopardizing its
effectiveness. Residents may remain vigilant that such things do not recur
in other Buildings.
All are requested to co-operate.
Dated:-05.11.2014.
Secretary.
-
Niravra Co-operative Housing Society Ltd.
N O T I C E
Sub:- Interest for late payments.
Members have been found to be reluctant in the payment of accrued interest for the delayed payment of Co-operative dues. Rather the predominant tendency is to evade the payment of the interest at one pretext or another. It is informed that the Bye-Laws of the Society provide for payment of 2% interest on all late remittances of Co-operative dues. As such, members who have not yet paid the accrued interest amount on delayed payments are requested to pay the same at the earliest.
All are requested to co-operate.
Dated:-17.12.2014.
Secretary.
-
Niravra Co-Operative Housing Society Ltd.
N O T I C E
Sub.:- Extra Commode-Payment Reg.
During the course of Sanitary Project many of our members opted for Commodes (WCs),which were different
to the standard WCs supplied as part of the project. Similarly,
some members took extra WCs beyond their eligibility.
Extra sums on both these accounts have to be paid by the
concerned members. The details are as indicated at pages
hereunder. Respective members are requested to kindly pay the
due amount forthwith through A/c payee cheque to the Co-
operative.
10.01.2015
Secretary
-
Niravra Co-operative Housing Society Limited.
Co-Operative Dues: Defaulters’ Statement As On 16.01.2015
Notice
Members are herewith informed of the perennial problem being faced by the Society i.e. Non –payment of co-operative dues. Time and again the matter
has been brought to the notice of the defaulting members but to no avail. A
statement is again displayed for attention to all concerned.
2013-14:
Maintenance: 4 nos.
Road (2nd Installment): 9 nos.
Building Restoration Fund (Sept): 9 nos.
Building Restoration Fund (Feb): 16 nos.
2014-15:
Maintenance: 12 nos.
Sanitary Project (Mar.): 6 nos.
Sanitary Project (Jun): 19 nos.
Building Restoration Fund (Sept.): 64 nos.
Building Restoration Fund (Sept –AGM Raised): 102 nos.
16.01.2015
Secretary
-
Niravra Co-operative Housing Society Ltd.
N o t i c e
Sub.:-Building Restoration Fund –
Feb.’15 Instalment
Members are reminded that the 2nd instalment of Building Restoration Fund is due to be paid latest by 28th
Feb’2015. All are requested to kindly pay the amount of
Rs.1500/- within the due date.
Dated.04.02.2015
Secretary
-
Niravra Co-operative Housing Society Ltd.
N o t i c e
Sub.:-Renting out Co-operative Space.
It is herewith informed that the BOD has decided that members can use the space at the Indoor Games’ Room
i.e. the room below the Co-Operative Office for holding of
private family functions. The schedule of charges for such
use is as indicated hereunder.
Rent: Rs.2000/- for single use for a day or less.
Electricity: No charge for use of fans or lights fitted at the room. However, for additional
connections an amount of Rs.100/- per use per day
will be levied.
Dated.16.02.2015
Secretary
-
NIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD.
Half-yearly General Meeting
Notice
In exercise of the authority conferred on the undersigned as per provision of the WBCS Act 2006, notice is
hereby given to all members of the society that the half-yearly General Meeting will be held
on 29/03/2015 at 10:30 A.M. at the premises of the society to transact business
as per the agenda points mentioned hereunder. Members are requested to
please attend the meeting.
Agenda for the meeting:
To review the activities of the Society on the basis of report placed. To review the financial position on the basis of the provisional accounts.
To consider any other matter as may be raised in the meeting in accordance with the provisions of Bye-Laws and the Co-operative Act.
(Md.Mustakim) Secretary
To, All Members.
-
Niravra Co-operative Housing Society Ltd.
N O T I C E
Sub.:- Campaign to link Aadhar Card & Voter
Card.
A Campaign has been launched to link the Aadhar and EPIC Card under the National Electoral Roll Purification
and Authentication programme. Accordingly, the Election
Office, Kasba has supplied us with the requisite form. Each
member/resident is herewith requested to please fill in
the proforma. The filled-in proforma may be submitted to
the Election office representatives on
30.05.2015(Saturday) 10AM onwards at the collection
Office at the Indoor Games’ Centre (the space below
the Co-Operative Office) in the campus. The residents
may also bring alongwith Aadhar cards and Voter cards for
necessary verification, if required.
Dated.27.05.2015 Secretary
To,
All members. A copy of proforma is also send alongwith.
-
Niravra Co-operative Housing Society Ltd.
Reg.Children’s Park.
Notice-cum-Appeal
Attention of all conscientious residents, gents and ladies alike, is drawn to the problem we are facing in the upkeep of the Children’s Park. The grown up
boys of the campus, in defiance to all requests and appeal/notice, regularly play
the games of Football and Cricket. They play these games daily and for prolonged
periods of about 4-5 hours. As a result the green surface that was built with
considerable efforts, care and money has all but destroyed fully. Already the
green surface, in large patches, has given way to the sandy brown surface. Thus
we are back to square one and the huge sum that was spent has gone to waste.
2. Ironically, the rightful owners of the park i.e. the children are not allowed
entry by these boys. As a result they play on the road and over the underground
reservoir. This is dangerous as anytime some untoward accident may happen
and our children, God forbids, may suffer injuries. The cast Iron covers on the
reservoir can also give way and in that event fatality is not ruled out.
On behalf of the BOD, a fervent appeal is therefore made to all residents to
come forward and make a concerted effort not only to save the green top of the
park but also restore the park for play to the children only. Actions are required
to be taken forthwith to prevent any untoward happening.
Dated:-01.06.2015.
Secretary.
-
Niravra Co-operative Housing Society Ltd.
Maintenance & other Charge(2015-16)
N O T I C E
As per decision at the Annual General Meeting held on 26.07.2015, the
charges, those are to be remitted by members/residents, are as mentioned
hereunder. All are requested to please pay the due amount within the last date
mentioned failing with which an interest of 2% will be levied.
Head Approved Amount at AGM(Rs.)
Amount already paid(Rs.)
Balance Payable(Rs.)
Last Date for Payment
Maintenance 6000 5000 1000 31.08.2015 4-wheeler
Parking Fee 1400 1300 100 -do-
2-wheeler Parking
Fee(Members)
600 550 50 -do-
2-wheeler Parking
Fee(Tenant)
7200 6600 600 -do-
2. Members are also reminded that they are welcome to pay the September Installment of
Building Restoration fund along with.
Dated:-03.08.2015.
Secretary.
Niravra Co-operative Housing Society Ltd.
-
N O T I C E
Sub.:- Voluntary Group for Healthcare Needs(VGHN).
As per decision taken at the AGM’2015 and subsequent discussion at the BOD meeting, a Voluntary Group for Healthcare Needs(VGHN) in the Society is
herewith formed. The following residents of the Society will be the members of
this group.
1. Sh. Suresh Chandra Sharma – Flat no.D-07/01.
2. Sh. Sibendu Dey – Flat no.D-03/04.
3. Smt. Anima Mondal – Flat no.D-12/13.
4. Sh.Sujay Basu – Flat no.D-05/03.
5. Sh.Goutam Das – Flat no.D-07/14.
6. Abdul Samad – Flat No.D-06/03.
7. Sh. Ranjan Roy – resident – Flat no.D-06/02.
8. Sh. Piyal Nandi – Flat no. D-10/09. --------Convenor.
Broad Terms of Reference for the group:
i. To keep in regular touch with the senior residents, especially the
single lady members.
ii. To maintain database of hospitals, doctors, healthcare
amenities/facilities etc. as available in the neighbourhood.
iii. To upkeep the equipments e.g wheelchair, stretcher etc. as available
with the Society.
iv. To provide assistance at the hour of medical emergency of any
resident of the Society.
v. To undertake any other activity commensurate with the objective of
the Group.
Dated.16.11.2015 Secretary
NIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD.
-
N O T I C E
Draft Bye – Laws Of The Society
The Committee for the amendment of the Bye-Laws has submitted the draft
to the BOD on 29th Dec’2015. Members are requested to kindly study the draft
and suggest their valued opinion. It is proposed to discuss the draft Bye-Laws in
the next General meeting before finally placing the Bye-Laws in the AGM/special
GM for approval.
2. To facilitate the study, a copy of the draft Bye-Laws as submitted by the
Committee has been uploaded at the Society Web-site
(http://niravra.angelfire.com). The uploaded draft is in pdf format and is
password protected. Desirous members may obtain the password from the
office of the Society.
30.11.2015 (Md.Mustakim)
Secretary
NIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD.
http://niravra.angelfire.com/
-
Half-yearly General Meeting
Notice
In exercise of the authority conferred on the undersigned as per provision of the WBCS Act 2006, notice is
hereby given to all members of the society that the half-yearly General Meeting will be held
on 07/02/2016 at 10:30 A.M. at the premises of the society to transact business
as per the agenda points mentioned hereunder. Members are requested to
please attend the meeting.
Agenda for the meeting:
To review the activities of the Society on the basis of report placed. To review the financial position on the basis of the provisional accounts.
To discuss the draft Bye-Laws of the Society.
To consider any other matter as may be raised in the meeting in accordance with the provisions of Bye-Laws and the Co-operative Act.
Sd/- 22.12.2015 (Md.Mustakim)
Secretary To, All Members. Copy to: JRCS for information.
-
NIRAVRA CO-OPERATIVE HOUSING
SOCIETY LTD.
Dated.02.02.2016
N O T I C E
All members are requested to pay the following charge latest by 29th February’ 2016. Members may kindly note that delay in the payment
of dues will attract penal interest @2% per month.
2. The above charge is for the year 2015-16 and creditable to the
Head ‘Long Term Development Fund’.
Secretary
Sl. No.
Item of Charge Amount(Rs.)
1. Building Restoration Fund 1500/-
-
NIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD. Dated.02.04.2016
N O T I C E Sub.:-Schedule of Charges 2016-17
The following table depicts the charges payable by members for the year 2016-17. All Charges except that mentioned at Sl.no.4 are to be
paid latest by 30th April 2016. Any delay in the payment of dues will
attract penal interest @2% per month.
2. The charges mentioned at Sl.no.1,2&3 are subject to
ratification/revision at AGM. In case it is decided to enhance the charges,
the balance has to be paid by the due date to be fixed at AGM.
3. Members, are welcome to pay the full year’s charge at one go.
Secretary
Sl. No.
Item of Charge Amount(Rs.) Remarks
1. Maintenance 6000/- Payable by 30th April’2016.
2. Car Parking 1400/- -do- 3. 2-wheeler parking 600/- -do-
4. Building Restoration Fund
@1500/- Payable in Sept’16 & Feb’17
-
Dated.29.06.2016
Niravra Co-operative Housing Society Ltd.
Annual General Meeting
N O T I C E
In exercise of the authority conferred on the undersigned under sub-section (2) of Section 29 of the West Bengal Co-operative Societies Act,2006, notice is hereby given to all
members of the Society that the Annual General Meeting for the Co-operative year 2016-17
will be held on 24.07.2016 at 3:00 PM in the premises of the Society.
Agenda for the meeting is as mentioned hereunder,
Confirmation of the proceedings of the last Half-Yearly and Annual General Meeting
(2015-16).
Consideration of statements of accounts.
Consideration of the Annual Report prepared by the Board.
Approval of the Financial Proposals and Annual Budget (2016-17).
Consideration of any other matter as may be raised in the meeting as miscellaneous
item in accordance with the provisions of the Act and Bye-Laws of the Society.
(Md.Mustakim) Secretary.
To, All Members Copy to: The Jt. Registrar of Co-Operative Society, Kolkata Metropolitan Area Housing Cell, 245, B B Ganguly Street, Kolkata – 12.
-
Niravra Co-operative Housing Society Limited Notice
Sub.:-Organising of Pujas at the Children’s Park.
On 14.08.2015 during the BOD meeting some of the senior members of the
Society including members of the Puja Committee came to the Office and
requested for the accordance of the permission for holding of the Pujas as well
as other festivities at the Children’s Park Of the Society. The matter was
discussed at length at the BOD meeting. However, while the members were
unanimous that the Pujas must be celebrated at the Society Premises but there
was difference of opinion as to whether the festivities be allowed to be held at
the Park.
2. In view of above, opinion of members is herewith sought as to whether
the Pujas will be allowed to be held at the Children’s Park. The BOD will abide by
the opinion of the majority of members. We again emphasize that all are
unanimous about the holding of the Pujas at the Society premises. Only bone of
contention as to whether the festivities be allowed to be held at the Park.
Members may kindly opine at the enclosed sheet.
Secretary
-
Niravra Co-operative Housing Society Limited Notice
Sub.:-Organising of Pujas at the Children’s Park.
We have since received the opinion expressed by the member-residents on the matter mentioned in the subject
above. All concerned are informed that the response is
overwhelmingly in favour of holding of the pujas and allied
festivities at the Children’s Park of the Society. In line with
the decision taken at the meeting on 14.08.2016, the BOD
therefore unequivocally accepts the response expressed
by the member-residents.
It is desired that all members and residents amicably and
joyfully will participate at the festivities in the Campus.
17.08.2016
Secretary
-
Niravra Co-operative Housing Society Limited
Notice
Members are informed that the following amounts are to be paid by each. The last date for payment of these dues has been fixed at 30th September 2016.
Maintenance ----------------------------Rs.500/- (as was raised at AGM)
Building Restoration Fund----------------Rs.1500/- (September Installment) Dated.27.08.2016
Secretary
-
Niravra Co-Operative Housing Society Ltd.
N O T I C E
Consequent upon the resignation of
Smt.Rajlakshmi Roy from the post of
Chairperson of the Society, BOD has since
Co-Opted Sh. Sunil Mitra as the Chairman
Secretary Of the Co-Operative with
immediate effect and until further notice.
Dated.26.09.2016.
Secretary
-
Niravra Co-Operative Housing Society Ltd.
N O T I C E
Sub.:-Formation of Committee on court case
Matter.
As per approval accorded at the Annual General Meeting, a Committee has been constituted to deal with the
court case on matter of M/s Aashiana Vs. Our Society in the
light of the recent proposal received from the Vendor for an
out-of-court amicable settlement. The Committee after
necessary deliberations/negotiation will recommend further
action that need be taken by the BOD. It is expected the
committee will safeguard the interest of the Society and
extricate it from the litigation. The Constitution of the
Committee is as mentioned hereunder.
1. Sh.Buddhadeb Gangopadhayay (1/8): Chairman.
2. Sh.Manoranjan Roy(8/15):Member.
3. Sh. B K Chakroborty(1/15):Member
Dated.26.09.2016.
Secretary
Copy to : Committee Members.
-
Greetings From BOD for the ensuing Festivities.
Dated.:-6.10.2016
Niravra Co-operative Housing Society Ltd.
A U T U M N
NOTICE:
THE OFFICE WILL REMAIN CLOSED FROM 7TH OCTOBER TO 16TH OCTOBER.
-
N O T I C E
Once the functions (family or otherwise)
organized in the campus get over, the place
has more often than not been found to be
littered with waste-food, left-over food,
plates etc. together with materials like
wire-nails, pins, wooden pieces etc. arising
out of the dismantled pandals. The garbage
of waste food material etc. are unhygienic
and presents an ugly untidy sight. The
strewn materials like wire-nails, pins may
cause injury or may result in flat tyres in
cars/bikes.
The hosts/organisers of such functions are therefore requested to ensure that the
caterers/decorators clean the site properly before
departing the campus with their amenities.
Dated.:02.11.2016 Secretary
-
Niravra Co-operative Housing Society Limited
Urgent Notice Sub.:- Celebrating a Pollution free Dewali
The Govt. Administration in no uncertain terms has directed all concerned to refrain from bursting the banned as well as high decibel firecrackers during the festival of Kalipuja/Dewali. The residential complexes have been specifically asked to remain vigilant in this regard so as to keep the acoustic pollution within the prescribed limit. In view of the above the residents of the Co-operative are herewith requested not to light/burst such crackers for our own safety and to ensure that the directives are complied with both in letter and spirit. All are requested to cooperate.
Secretary
N O T I C EN O T I C E
27.06.2012N O T I C ENiravra Co-Operative Housing Society Ltd.N O T I C ENiravra Co-operative Housing Society Ltd.N O T I C E
19.12.2012NIRAVRA Co-Operative Housing Society Ltd.No.hGM_13/Niravra Dated. 9.01.2013Niravra Co-operative Housing Society Ltd.Half – Yearly General MeetingNiravra Co-Operative Housing Society Ltd.N O T I C EN O T I C E
Niravra Co-Operative Housing Society Ltd.N O T I C ENiravra Co-Operative Housing Society Ltd.Niravra Co-operative Housing Society Ltd.Annual General MeetingNiravra Co-operative Housing Society Ltd.Schedule of ChargesNiravra Co-operative Housing Society Ltd.Building Restoration Fund(2013-14)NIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD.Dated.02.04.2014N O T I C ENIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD.Dated.12.04.2014Niravra Co-operative Housing Society Ltd.Niravra Co-operative Housing Society Ltd.Building Restoration Fund
Niravra Co-operative Housing Society Limited.Co-Operative Dues: Defaulters’ StatementNIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD.Dated.02.02.2016N O T I C ENIRAVRA CO-OPERATIVE HOUSING SOCIETY LTD.Dated.02.04.2016N O T I C E
Niravra Co-Operative Housing Society Ltd.Niravra Co-Operative Housing Society Ltd.