D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology...

68
D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology Version 1.1 Status Final Work package WP 4 Deliverable type Report Contractual date of delivery 31/01/2016 Actual date of delivery 15/03/2016 Author JJ de las Heras (ADV), Manuel Ramiro (ADV) Contributors Alba Fuertes (UOP), Rory Jones (UOP), Denys (DCH), Miguel Pinho (ISEP), Miquel Casals (UPC), Marta Gangolells (UPC) Keyword list Implementation plan, building & socio-economic analysis , data collection infarstructure, communication methods Dissemination level PU

Transcript of D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology...

Page 1: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 – Pilot implemetation methodology

(preliminary)

Document number D4.1

Document title Pilot implementation methodology

Version 1.1

Status Final

Work package WP 4

Deliverable type Report

Contractual date of delivery 31/01/2016

Actual date of delivery 15/03/2016

Author JJ de las Heras (ADV), Manuel Ramiro (ADV)

Contributors Alba Fuertes (UOP), Rory Jones (UOP), Denys (DCH), Miguel Pinho (ISEP), Miquel Casals (UPC), Marta Gangolells (UPC)

Keyword list Implementation plan, building & socio-economic analysis , data collection infarstructure, communication methods

Dissemination level PU

Page 2: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 2 of 68

Amendment history

Version Date Author (unit) Description

1.0 25.11.15 Manuel Ramiro (ADV) ToC definition

1.01 09.12.15 Alberto Cantalejo (ADV)

J.J. De las Heras (ADV)

ToC rev.

1.02 15.01.16 Alba Fuertes (UOP)

Rory Jones (UOP)

Content update

1.03 22.01.16 J.J. De las Heras (ADV)

Manuel Ramiro (ADV)

Content update

1.04 06.03.16 Miguel Pinho (ISEP)

A. Barros (ISEP)

Content update

1.05 07.03.16 Miquel Casals (UPC)

Marta Gangolells (UPC)

Content update

1.06 11.03.16 Manuel Ramiro (ADV)

J.J. De las Heras (ADV)

Content update

1.07 11.03.16 Miguel Pinho (ISEP)

A. Barros (ISEP)

Content update

1.08 14.03.16 Manuel Ramiro (ADV) Content update

1.09 15.03.16 Miquel Casals (UPC)

Marta Gangolells (UPC)

Internal review #1

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 649673. Disclaimer: The sole responsibility for the content of this material lies with the authors. It does not necessarily represent the views of the European Union, and neither EASME nor the European Commission are responsible for any use of this material.

Page 3: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 3 of 68

Executive summary This report represents Deliverable 4.1- Pilot implementation methodology (preliminary) developed in the course of WP4 activities, focused on the pilot implementation activities.

This report is a preliminary version of pilot implementation methodology and it is intended to cover the implementation plan, introduce the technical solution designed to provide the energy data collection and communication infrastructure of the pilot homes, and the communication methods used with the tenants participating in the pilot. A final version is planned to be delivered by M24, this version will cover the pilot implementation in its full extent.

The report includes the actions carried out during the pilot implementation for the first reporting period. These activities involve the identification of the suitable houses from the pool of preselected pilot homes (137) and the installation of the monitoring and communication infrastructure developed ad-hoc for the project as a generic solution to ensure the maximum compatibility with the different electricity and gas meters type identified during the analysis of the information collected in WP2 (D2.3). The pilot installation is being carried out following an incremental approach, a total of 43 households have been provisioned with the ICT solution at the time of writing this report.

The report presents the main building and socio-demographic characteristics of the 43 households where the monitoring kit has been already installed. The data presented in this report come from the EnerGAware Social Housing Survey, the DCH’s Building Stock Condition and Energy Database and the information collected by the DCH personnel when installing the monitoring kits.

Page 4: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 4 of 68

Table of contents 1. INTRODUCTION ................................................................................................................................... 10 2. DATA COLLECTION AND COMMUNICATION INFRASTRUCTURE DESIGN ......................................... 10

2.1 MONITORING ARCHITECTURE....................................................................................................................... 10 2.2 MONITORING INFRASTRUCTURE .................................................................................................................... 12

2.2.1 Electricity meters ...................................................................................................................... 12 2.2.2 Gas meters ............................................................................................................................... 13 2.2.3 Data concentrator .................................................................................................................. 14

2.3 DATA COLLECTION ..................................................................................................................................... 16 3. IMPLEMENTATION PLAN ...................................................................................................................... 17

3.1 PHASE 1 .................................................................................................................................................... 18 3.2 PHASE 2 .................................................................................................................................................... 19 3.3 PHASE 3 .................................................................................................................................................... 22 3.4 RISK ASSESMENT – CONTINGENCY PLAN ........................................................................................................ 22

4. RESIDENT COMMUNICATION PROCEDURE ........................................................................................ 22 5. DESCRIPTION OF THE POOL OF PILOT HOMES ................................................................................... 23

5.1 BUILDING ANALYSIS .................................................................................................................................... 23 5.1.1 Characteristics ......................................................................................................................... 23 5.1.2 Envelop ..................................................................................................................................... 27 5.1.3 Services and controls .............................................................................................................. 31 5.1.4 Renewable energy sources ................................................................................................... 38 5.1.5 Access to internet .................................................................................................................... 41

5.2 SOCIO ECONOMIC ANLYSIS ........................................................................................................................ 42 5.2.1 Age of the Household Representative Person (HRP) .......................................................... 42 5.2.2 Gender of the Household Representative Person (HRP) .................................................... 43 5.2.3 Family structure ........................................................................................................................ 43 5.2.4 Employment status of Household Representative Person (HRP) and other family members ................................................................................................................................................ 46 5.2.5 Qualifications of the Household Representative Person (HRP) .......................................... 47 5.2.6 Welfare benefits ....................................................................................................................... 48 5.2.7 Health of the Household Representative Person (HRP) ...................................................... 48

Page 5: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 5 of 68

6. DESCRIPTION OF THE MONITORED PILOT HOMES.............................................................................. 49 6.1 BUILDING CHARACTERISTICS ........................................................................................................................ 50 6.2 SOCIO-DEMOGRAPHIC CHARACTERISTICS .................................................................................................... 55 6.3 ENERGY INFRASTRUCTURE CHARACTERISTICS ................................................................................................. 57

7. CONCLUSIONS .................................................................................................................................... 63 APPENDIX A. ENERGAWARE INFORMATION SHEET................................................................................. 64 APPENDIX B. ENERGAWARE TECHNICAL INFORMATION DATA COLLECTION FORM ........................... 66

Page 6: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 6 of 68

Figures Figure 1. EnerGAware Monitoring architecture. .......................................................................................... 11

Figure 2. EnerGAware monitoring infrastructure. ......................................................................................... 12

Figure 3. Electricity meter monitoring at pilot house. .................................................................................. 13

Figure 4. Gas meter monitoring at pilot house. ............................................................................................ 14

Figure 5. Data concentrator at pilot house. ................................................................................................. 15

Figure 6. Data concentrator components. ................................................................................................... 16

Figure 7. Installation of the monitoring kit in house #44. ............................................................................. 18

Figure 8. Installation of kit in analogue gas meter with curve display. ..................................................... 19

Figure 9. Dwelling type ..................................................................................................................................... 24

Figure 10. Year of construction ....................................................................................................................... 25

Figure 11. Number of storeys ........................................................................................................................... 25

Figure 12. Number of habitable rooms .......................................................................................................... 26

Figure 13. Energy rating of dwellings .............................................................................................................. 26

Figure 14. Wall construction ............................................................................................................................. 28

Figure 15. Wall insulation .................................................................................................................................. 28

Figure 16. Roof construction ............................................................................................................................ 28

Figure 17. Roof insulation thickness ................................................................................................................. 29

Figure 18. Glazing .............................................................................................................................................. 29

Figure 19. Secondary glazing .......................................................................................................................... 30

Figure 20. Proportion of draught-proofing installed ..................................................................................... 30

Figure 21. Electric meter type .......................................................................................................................... 32

Figure 22. Mains gas available ........................................................................................................................ 32

Figure 23. Main space heating system .......................................................................................................... 33

Figure 24. Main space heating fuel type ....................................................................................................... 33

Figure 25. Main space heating controls ........................................................................................................ 34

Figure 26. Secondary space heating system ................................................................................................ 34

Figure 27. Secondary space heating fuel type ............................................................................................ 35

Page 7: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 7 of 68

Figure 28. Water heating system ..................................................................................................................... 36

Figure 29. Water heating fuel type ................................................................................................................. 36

Figure 30. Cylinder size ...................................................................................................................................... 36

Figure 31. Cylinder insulation ........................................................................................................................... 37

Figure 32. Cylinder thermostat ........................................................................................................................ 37

Figure 33. Air conditioning ............................................................................................................................... 38

Figure 34. Proportion of low energy lighting installed .................................................................................. 38

Figure 35. Solar water heating......................................................................................................................... 39

Figure 36. Photovoltaics ................................................................................................................................... 39

Figure 37. Biomass boiler .................................................................................................................................. 40

Figure 38. Air or ground source heat pump .................................................................................................. 40

Figure 39. Micro combined heat and power (CHP) .................................................................................... 41

Figure 40. Access to the Internet at home .................................................................................................... 41

Figure 41. Internet connection type for households with Internet access at home ............................... 42

Figure 42. Percentage of respondents (of the total) in each age category. ......................................... 43

Figure 43. Responses to the question “who is living with you” for 2-person households. ....................... 44

Figure 44. Responses to the question “who is living with you” for 3-person households. ....................... 44

Figure 45. Responses to the question “who is living with you” for 5-person households. ....................... 45

Figure 46. Employment status of the household representative person (percentage of the total). ... 46

Figure 47. Highest qualification level of the household representative person(percentage of the total). ................................................................................................................................................................... 48

Figure 48. Responses to the question ‘how was your health in general in the last 12 months’(percentage of the total). ................................................................................................................. 48

Page 8: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 8 of 68

Tables Table 1. Current status of kit installation. ........................................................................................................ 21

Table 2. Employment status of other members of the household ............................................................. 47

Table 3. Percentage of responses for each written category of General Practice (GP) visits. ............ 49

Table 4. Building characteristics of the already monitored houses. ......................................................... 54

Table 5. Socio-demographic characteristics of the already monitored houses. ................................... 57

Table 6. Energy infrastructure characteristics of the already monitored houses. ................................... 62

Page 9: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 9 of 68

Glossary and abbreviations

ICT Information and Communication Technology

IoT Internet of Things

GPRS General Packet Radio Service

SAP Standard Assessment Procedure. UK government approved system for assessing the energy rating for a new home.

TRV

Thermostatic radiator valve. Self-regulating valve fitted to hot water heating system radiator, to control the temperature of a room by changing the flow of hot water to the radiator.

UK United Kingdom

VPN Virtual Private Network

Page 10: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 10 of 68

1. Introduction This task has been slightly modified during the project execution. Initially, part of the aim of this task was to perform an energy audit over the pilot homes. After the recruitment process and following the recommendations of social experts, the consortium decided to modify the interaction approach with the recruited tenants so as to minimise the demand and time commitments on the participating households. Therefore, the consortium agreed on a generic monitoring solution able to be installed in most of the houses in just one visit per home.

During Task 2.1, households were asked in the EnerGAware Social Housing Survey whether they would be interested in partaking in further follow up studies. From the 537 households completing the survey, 237 stated that they would be interested. These households were asked again if they would be interested in being part of the monitoring stage and 137 answered affirmatively. Section 5 (Description of the pool of pilot homes) describes the main building and socio-economic characteristics of a subset of these households, the ones with the ICT solution installed.

At the time of writing this deliverable, the monitoring system has been already installed in 43 homes. Section 6 (Description of the monitored pilot homes) describes the main building and socio-economic characteristics of these households. As this deliverable is publically available, only limited data are presented at a household level for the households partaking in the field trial in order to maintain their anonymity in accordance with the EU ethical procedure governing the EnerGAware project and the Data Protection Act (1998).

2. Data collection and communication infrastructure design

2.1 Monitoring architecture

A dedicated monitoring architecture has been designed and implemented in order to easily deal with data collection and communication constraints at pilot homes. As shown in Figure 1, four different layers can be identified in the adopted approach:

Sensing: within this layer, all the energy and gas meters to be monitored are included.

Devices: all the needed communication gateways and data loggers used to capture data from meters are covered in this layer. Devices include Energy Cams to read gas meters consumption and pulse readers attached to energy meters. This information is collected and logged in a Modbus TCP-complaint data logger which forwards it to the platform layer

Page 11: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 11 of 68

through a Virtual Private Network (VPN) implemented on a GPRS communication infrastructure.

Platform: running on the data server, it manages all the devices configuration, maintenance and monitoring tasks. It also parses messages and exposes data through web services to the application layer

Aggregation layer: ensures the raw data are pre-processed and exposed to the IoT platform in a predefined format, this layer also supports the communication interfaces between the two parties.

Figure 1. EnerGAware Monitoring architecture.

Thanks to this architecture, we might be able to scale up the data collection and analysis processes for a wider pilot campaign seamlessly.

Page 12: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 12 of 68

2.2 Monitoring infrastructure

In order to comply with DCH houses covered in the EnerGAware pilot campaign, an standard kit to be used in any house with little intervention from installers was defined. Thus, a plug &play approach was followed from the beginning by selecting suitable devices to collect consumption information from gas and electricity meters as well as to group data collected and send to the remote data server for further analysis. Therefore, the monitoring infrastructure used in the project is as follows:

Figure 2. EnerGAware monitoring infrastructure.

2.2.1 Electricity meters

None of the electricity meters installed at pilot homes had any communication port to be used by the monitoring devices to collect consumption data. Thus, the only option was to select those meters that had at least led pulse outputs. The technical challenge was to perform energy monitoring without or with very little intervention reducing tenants’ involvement during installation and operation of pilot campaign. Therefore, the adopted solution consisted in attaching an optical pulse reader jointly with a standard Wireless M-Bus pulse counter. This set would allow to send information wirelessly from the meter (usually located outdoor) to the data concentrator (as shown in ¡Error! No se encuentra el origen de la referencia. 3).

Page 13: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 13 of 68

Figure 3. Electricity meter monitoring at pilot house.

2.2.2 Gas meters

Similarly to electricity meters, gas meters already deployed at Plymouth pilot houses did not bring any communication port we could use to get data. Only visual reading of current gas consumption was possible. In order to keep a standard-based monitoring kit, we selected the EnergyCam product from German company Fast Forward. This device is mainly a visual recognition module that reads data and transforms it into an M-Bus parameter that can be read wirelessly by our data concentrator.

Page 14: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 14 of 68

Figure 4. Gas meter monitoring at pilot house.

2.2.3 Data concentrator

A standard pre-wired and configured cabinet was designed and developed for the purpose of the ENERGAWARE project. As can be seen in the figure on the right, a very compact design was chosen in order to avoid visual impact at homes. This data concentrator (Figure 5) is able to collect data from meters and send them to the remote server through a GPRS connection.

Page 15: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 15 of 68

Figure 5. Data concentrator at pilot house.

As shown in figure 6, the data concentrator cabinet includes the following components:

General protection: following regulations about safety in electrical equipment, a general protection has been included.

Power supply: a 24VDC @ 60W power supply is able to feed the whole set.

Wireless MBusbridge: it is a modified version of ADV DM-108 Wireless Modbus bridge1 developed during the project to be able to collect data from both wireless M-Bus readers attached to gas and electricity meters. Moreover, it converts data to Modbus readable registers that can be polled from the datalogger through the physical RS485 interface.

Datalogger: through its RS485 Modbus RTU port, the ADV UCM-316 Modbus datalogger2 is able to read meters data and store in the internal memory. Periodically (every 15 minutes), this datalogger receives requests from the remote server to send current data through its embedded GPRS modem (with a SIM installed in it).

1Commercial DM-108 Datasheet

http://www.advanticsys.com/shop/documents/1439288069_DM-108%20D006%202014%20ENG.pdf 2Commercial Datalogger Datasheet

http://www.advanticsys.com/shop/documents/1421237559_UCM-316%20ENG%20DS002%2013012015.pdf

Page 16: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 16 of 68

Antennae: two GPRS and Wireless M-Bus antennae are also installed in the mini cabinet to be able to connect easily to each wireless network without coverage problems.

Figure 6. Data concentrator components.

2.3 Data collection

The complete kit installed at each home sends, upon request from a remote server, all the stored information every 15 minutes. This remote server hosts a dedicated ADV Concordia cloud software distribution managing all the connections and devices through a dedicated virtual private network on GPRS. The remote server performs devices management tasks including:

Data collection scheduler tool: every 15 minutes, each datalogger is requested to send data. Several retries are used to ensure proper reception of data.

Devices connection check: periodically, it “pings” each IP address to identify communication losses

Communication notifications: if any communication incident occurs (loss of communication to datalogger or electricity/gas meters readers), the system raises alarms accordingly.

Page 17: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 17 of 68

In order to apply any data analytics techniques and algorithms, the server exposes them through webservices to the IoT Platform. Three methods are implemented, returning a JSON object with relevant info:

getEnerGAwareSignals: returns the list of signals (with the last valid value stored)

getEnerGAwareSignalLastValue: returns a specific signal information

getEnerGAwareTimeSeriesData: returns time series data for a specific signal.

3. Implementation plan Due to the change on the approach on how to handle the interactions with tenants (to minimise the needed technical interventions), the consortium agreed to build and install a generic monitoring solution able to be installed in most of the houses in just one visit per home, instead of tailoring specific kits for each house.

From the 137 houses willing to participate in the monitoring stage of the EnerGAware project, 43 had to be discarded as they did not match with the generic solution (pre-paid meters, non-pulse meters, etc.). So finally, the consortium identified 94 homes suitable to be able to be monitored with the identified monitoring solution.

The consortium also agreed that the installation of the monitoring equipment in the project participant’s homes would be carried out by the DCH in-house repairs team supported ADV, the technology provider partner.

After selecting the houses to be monitored, the developed Pilot Implementation Plan specified a 3-stages installation campaign, starting on November 2015.

The first phase was planned to be performed jointly by DCH and ADV focusing on a small number of homes. This first phase should allow testing the monitoring kit and training DCH personnel in-site. The second phase was planned to include the installation of 60 more kits to monitor both gas and electricity consumption. The third phase was planned to cover the installation of smart meters in those homes where only the electricity is going be monitored.

Page 18: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 18 of 68

3.1 Phase 1

Phase 1 was intended to test the developed generic kit in a random sample of houses. The goal was both to assess the suitability of the kit as well as to verify the in-site conditions for installation. In parallel, DCH teams would be trained to install the second phase kits.

This phase took place 11-12 of November 2015. A total of 8 houses were visited, of which 3 were not suitable for installation:

2 of the houses had a non-compatible gas meter (digital meter which cannot be used for camera reading)

1 of the houses with radio coverage problems

Figure 7 shows the installed kit on the gas meter (left), electricity meter (centre) and data aggregator (right) on house #44, which was the most compatible one.

Figure 7. Installation of the monitoring kit in house #44.

Of the 5 houses installed it was further detected that 4 had analogue gas meters with a curve display, which forced adaptation of the installation of the reading camera. Albeit the difficulties, it was possible to adapt the kit for this type of reader (Figure 8).

Page 19: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 19 of 68

Figure 8. Installation of kit in analogue gas meter with curve display.

3.2 Phase 2

Phase 2 of installation started late January 2016, and is ongoing. During this period, it is planned to install the monitoring kits in 60 houses, out of which 38 kits are already installed in designated homes. One additional kit was installed but later removed on the request of the tenant. Of these 38 houses, 21 have the full kit installed, while the remaining have partial installation either by exclusively electricity or gas consumption monitoring.

The accumulated results after Phase 2 are 26 homes with the full kit installed, 13 homes have electricity consumption monitoring only, and 4 homes have gas consumption monitoring only (Table 1). The remaining 22 monitoring kits are currently being installed.

Page 20: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 20 of 68

Kit ID Pulse Counter Energy Cam Installed Extent

Pha

se 1

EA#001 installed installed yes full

EA#002 installed installed yes full

EA#003 installed installed yes full

EA#004 installed installed yes full

EA#005 installed installed yes full

Pha

se 2

EA#006 installed yes partly

EA#007

EA#008 installed installed yes full

EA#009

EA#010

EA#011 installed yes partly

EA#012 installed installed yes full

EA#013 installed yes partly

EA#014

EA#015 installed yes partly

EA#016

EA#017 installed yes partly

EA#018 installed installed yes full

EA#019 installed installed yes full

EA#020 installed yes partly

EA#021

EA#022 installed yes partly

EA#023 installed installed yes full

EA#024

EA#025

EA#026 installed yes partly

EA#027

EA#028 installed installed yes full

EA#029 installed installed yes full

EA#030

EA#031

EA#032 installed installed yes full

EA#033

EA#034 installed yes partly

EA#035 installed yes partly

Page 21: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 21 of 68

Kit ID Pulse Counter Energy Cam Installed Extent

EA#036 installed installed yes full

EA#037 installed installed yes full

EA#038 installed yes partly

EA#039

EA#040 removed

EA#041 installed yes partly

EA#042

EA#043 installed yes partly

EA#044 installed installed yes full

EA#045 installed yes partly

EA#046

EA#047 installed installed yes full

EA#048 installed installed yes full

EA#049

EA#050 installed installed yes full

EA#051

EA#052

EA#053

EA#054 installed installed yes full

EA#055 installed yes partly

EA#056 installed installed yes full

EA#057 installed installed yes full

EA#058 installed installed yes full

EA#059

EA#060 installed yes partly

EA#061 installed installed yes full

EA#062 installed yes partly

EA#063 installed installed yes full

EA#064 installed installed yes full

EA#065

Table 1. Current status of kit installation.

Page 22: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 22 of 68

3.3 Phase 3

Phase 3, which will include installation of the remaining houses, will be planned when phase 2 finishes, to allow integrating in the planning the full feedback from the installations, as well as the non-used cameras and pulse meters. This is expected to be done until end of March, and installations performed immediately after analysing accurately the overall situation.

3.4 Risk assesment – contingency plan

The total installation of the kits will be finished in time for the next step in the pilot (the deployment of the serious game beta version starting month 20). Therefore, in this aspect there is no need to adapt the plans of the project.

However the project baseline period started November 2015. Knowing that the installation would not be completed in time, the consortium decided that the data needed for the baseline definition will be completed using energy bills from the tenants. Actions to obtain these data have also been started.

4. Resident communication procedure 286 DCH households were sent a recruitment letter and returning form by post to ask them whether they would like to join the energy monitoring study, of these 137 expressed an interest in taking part by sending a completed returning form back to the EnerGAware team using the stamped addressed envelope provided. A specific postal address for the EnerGAware project was set up at DCH’s offices in Plymouth:

EnerGAware Project DCH Health, Safety and Environment 2 Ker Street Devonport Plymouth PL1 4GE

On the returning form, the residents were asked to provide their name, a telephone and/or mobile phone number, an email address, as well as a convenient time to contact them by telephone to arrange installation of the monitoring equipment.

Page 23: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 23 of 68

A member of DCH’s Maintenance and Repairs team then telephoned the residents to arrange a convenient time and date to install the monitoring equipment in the homes. They also answered any questions that the residents had about the energy monitoring study.

At the time and date arranged with the residents on the telephone, an equipment installer from DCH’s Maintenance and Repairs team arrives at the property and makes face-to-face contact with the residents. The installer passes the residents an information sheet which explains all the essential information about the project (See Appendix A). The residents are then given enough time to read the information sheet and ask the installer any questions about the project. The residents are then required to give verbal permission to the installer, to start installing the monitoring equipment in their home.

The information sheet is for the residents to keep and provides a direct telephone number (0300 123 8080) and email address ([email protected]) for them to contact at any time during the energy monitoring if they have any questions, notice any problems with the monitoring equipment or wish to withdraw from the activity.

On completion of the monitoring equipment installation, the installers show the residents the equipment and remind them that they can contact the EnerGAware project at any time using the details at the bottom of the information sheet.

The EnerGAware project partners have setup a password protected database of contact details for the residents which they provided on the returning form in the event that they need to be contacted during the monitoring study.

5. Description of the pool of pilot homes This section describes the main building and socio-demographic characteristics of the 137 households that specifically stated that they would be interested in being part of the monitoring stage of the EnerGAware project. The data presented in this section come from the EnerGAware Social Housing Survey and the DCH’s Building Stock Condition and Energy Database.

5.1 Building analysis

5.1.1 Characteristics

As shown in Figure 9, over half of the pool of pilot homes lives in flats (51.6%), whereas 40.2% live in houses and just over 8% live in other dwelling types, including maisonettes and bungalows.

Page 24: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 24 of 68

Most of the dwellings of the pool of pilot homes were constructed within the 1976-1995 period (18.8% between 1976 and 1982, 22.3% between 1983 and 1990 and 15.2% between 1991 and 1995). Oldest buildings represent 25.9% whereas buildings erected after 1995 only represent 17.9% of the pool of the pilot homes (Figure 10).

According to Figure 11, 70.5% of the tenants live in a single storey. The remaining tenants live in two storeys (28.7%) or three storeys (0.8%).

As shown in Figure 12, most of the dwellings have either two (36.1%) or three (36.9%) habitable rooms3. Some of the dwellings had four (18%), five (8.2%) or six (0.8%) habitable rooms.

Figure 9. Dwelling type

3 Habitable rooms include any living room, sitting room, dining room, bedroom, study, conservatory with internal quality door between it and the dwelling and kitchen having a discrete seating area.

Bungalow3.3%

Flat51.6%

House40.2%

Maisonette4.9%

Page 25: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 25 of 68

Figure 10. Year of construction

Figure 11. Number of storeys

Pre 190011.6% 1930 - 1949

1.8%

1967 - 197512.5%

1976 - 198218.8%

1983 - 199022.3%

1991 -199515.2%

1996 - 20025.4% 2007 +

12.5%

One storey70.5%

Two storeys28.7%

Three storeys0.8%

Page 26: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 26 of 68

Figure 12. Number of habitable rooms

The most common energy rating within the households that specifically stated that they would be interested in being part of the monitoring stage of the EnerGAware project is D (51.0%) followed by C (43.3%). Only 3.8% of the dwellings were rated in the E band and 1.9% in the F band (Figure 13).

Figure 13. Energy rating of dwellings

Two rooms36.1%

Three rooms36.9%

Four rooms18.0%

Five rooms8.2%

Six rooms0.8%

C43.3%

D51.0%

E3.8%

F1.9%

Page 27: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 27 of 68

5.1.2 Envelop

In terms of building envelope4, most of the dwellings interested in being part of the monitoring stage have a cavity wall (65.2%). Some of them have a solid wall construction (27.7%) whereas others have other types of wall constructions including timber frame (5.4%) and granite or other whinstone (1.8%) (Figure 14). According to Figure 15, almost 43% of the properties have no wall insulation (i.e. cavity wall or solid wall insulation) and 57.1% 54.9% of them have some type of wall insulation.

As shown in Figure 16, most householders in pool of pilot homes live in a property with a pitched roof with loft access (63.4%), whereas others have another dwelling above (i.e. a flat or a maisonette) (17.8%) or have a flat roof construction (17.8%). Finally, only 1.0% have a pitched roof with no access. According to Figure 17, roof insulation thicknesses typically are 150 mm (28.8%), 200 mm (21.2%) or 250 mm (26.9%), all above the 270 mm recommended thickness of roof insulation, assuming that the insulating material is mineral wool (the most common insulating material in the UK). In addition, around 1.9% of the social housing tenants in the pool of the pilot homes live in dwellings with 50 mmm roof insulation.

4The building envelope is a term for the parts of the building which surround the heated and cooled parts of the building. This includes external walls, floors or ground deck, roofs or constructions towards unheated ceilings, windows and doors. If a basement is heated then the basement walls and the basement floor are part of the building envelope. If it is unheated, the building envelope includes the floor between the ground floor and the basement. The building envelope may also address heat loss through foundations or other thermal bridges (Laustsen, 2008).

Cavity65.2%

Solid brick27.7%

Timber frame5.4%

Granite or whinstone (igneous)

1.8%

Page 28: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 28 of 68

Figure 14. Wall construction

Figure 15. Wall insulation

Figure 16. Roof construction

Insulated57.1%

Uninsulated42.9%

Pitched, loft access

63.4%

Pitched, no access

1.0%

Flat17.8%

Other Dwelling Above17.8%

Page 29: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 29 of 68

Figure 17. Roof insulation thickness

Data regarding glazing (Figure 18) indicates that 56% of the dwellings are single glazed whereas 44% are multiple glazed. As shown in Figure 19, none of the dwellings have secondary glazing. Most of the dwellings in the pool of pilot homes (97.2%) had no draught-proofing5 (Figure 20). Only 1.8% of the dwellings had all the glazed areas draught-proofed and 0.9% had half.

Figure 18. Glazing

5Draught-proofing is a low cost method of reducing air leakage around glazed areas in a property.

50mm1.9%

100mm11.5%

150mm28.8%

200mm21.2%

250mm26.9%

300mm +7.7%

Unknown1.9%

Single glazed56.0%

Multiple glazed44.0%

Page 30: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 30 of 68

Figure 19. Secondary glazing

Figure 20. Proportion of draught-proofing installed

Yes0%

No100%

None97.2%

Half 0.9%

All1.8%

Page 31: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 31 of 68

5.1.3 Services and controls

According to Figure 21, most of the pool of pilot homes have a standard single tariff electricity meter (47.3%). 37.5% of them have a dual (economy 7) electricity meter, indicating that the residents have two different tariffs for electricity6.

50.9% of the pool of pilot homes had no mains gas available (the space and water heating in the properties is supplied by electricity or bulk LPG) whereas 43.7% of the dwellings have mains gas available (Figure 22).

As shown in Figure 23, homes willing to participate in the monitoring stage of the project have either gas-fuelled combi (30.6%) or condensing combi boiler (36.1%) or electric storage heaters (28.7%). Only 0.9% of the dwellings have community/district heating. Gas is the most commonly used fuel (69.7%), followed by and electricity (29.4%) and bulk LPG (0.9%) (Figure 24).

Figure 25 shows that most of the pool of pilot homes (56.8%) have a programmer for setting on/off times of space and water heating and a room thermostat for setting a single demand temperature for the dwelling overall. 38.9% of the pilot homes have manual charge controls, which are commonly associated with electric heating. Only 1.1% of the dwellings had a full set of heating controls (defined as a programmer, room thermostat and TRVs), 1.1% of the dwelling were found to have a programmer, TRVs and a bypass and an additional 1.1% had appliance thermostats. In addition, 1.1% of the dwellings were found to have a boiler energy manager installed, which is a type of automated/intelligent heating control system that uses Variable Thermal Response (TRV) and Auto Weather Compensation software to achieve energy savings.

Most of the dwellings have no secondary space heating system (86.1%) whereas only 7.4% had panels, convectors or radiant heaters and 4.6% portable heaters. Only 0.9% had an open fire using mineral and wood and another 09% had 2000 or later room heaters (Figure 26). As shown in Figure 27, the electricity is mostly used in secondary space heating systems (13%) whereas mineral and wood are used in a much lower proportion (0.9%)

6The dual rate was designed so that properties that rely on electric storage heaters can run them overnight when it is cheaper and store the heat energy for release during the day. One rate is a standard day rate and the other is a cheaper overnight rate.

Page 32: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 32 of 68

Figure 21. Electric meter type

Figure 22. Mains gas available

Dual (economy 7

and such things)37.5%

Single (normal mains electric)

47.3%

Unknown15.2%

Mains Gas Available

47.4%Mains Gas Not

Available50.9%

Unknown1.7%

Page 33: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 33 of 68

Figure 23. Main space heating system

Figure 24. Main space heating fuel type

Combi30.6%

Community Heating

0.9%Condensing1.9%Condensing

Combi36.1%

Heat Pump -Wet System

0.9%

Standard0.9%

Storage Heaters28.7%

Mains Gas69.7%

Electricity29.4%

Bulk LPG0.9%

Page 34: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 34 of 68

Figure 25. Main space heating controls

Figure 26. Secondary space heating system

Programmer and room thermostat

56.8% Programmer, room

thermostat and TRVs

1.1%

Programmer, TRVs and bypass

1.1%

Programmer, TRVs and

boiler energy manager

1.1%

Manual charge control38.9%

Appliance thermostats

1.1%

None86.1%

2000 or Later -Room Heater

0.9%

Open fire in grate0.9%

Panel, convector or

radiant heaters

7.4%

Portable heaters

4.6%

Page 35: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 35 of 68

Figure 27. Secondary space heating fuel type

According to what is shown in Figure 28, condensing combi boilers (35.8%), gas-fuelled combis (30.3%) and electric immersion heaters (28.4%) are the most common types of water heating systems in the pool of pilot homes. In 0.9% of the dwellings, the hot water is supplied by a community/district heating scheme. Gas (70.6%) is the most widespread water heating fuel (Figure 29). Electricity is used in the remaining 29.4% pool of pilot homes.

Figure 30 shows that 87.5% of the dwellings have a hot water cylinder in their homes. The cylinder size is unknown in 47.3% of the pool of pilot homes. When this information is available, the most common size is the normal one (39.3%) ranging between 90 and 130 litres. Only 0.9% of the pool of pilot homes have a medium cylinder (131-170 litres).

In terms of cylinder insulation and according to Figure 31, 81.3% of the pool of pilot homes having a hot water cylinder are insulated with a spray foam layer on the outside and the remaining 13.6% had a removable insulating jacket.

Only 36.1% of the properties with a hot water cylinder had a thermostat7 installed (Figure 32).

7A cylinder thermostat measures the temperature of the hot water cylinder and switches on and off the water heating. Without a thermostat, residents have no control over the temperature of their hot water and can lead to inefficient energy use.

None86.1%

Dual fuel (mineral

and wood)0.9%

Electricity13.0%

Page 36: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 36 of 68

Figure 28. Water heating system

Figure 29. Water heating fuel type

Figure 30. Cylinder size

Combi30.3%

Community Heating

0.9%Condensing1.8%Condensing

Combi35.8%

Electric immersion (On-peak or Off-

peak)28.4%

Instant0.9%

Standard0.9%

Other0.9%

Mains Gas70.6%

Electricity29.4%

Normal (90-130)

39.3%

Medium (131-170)0.9%

No cylinder12.5%

No access47.3%

Page 37: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 37 of 68

Figure 31. Cylinder insulation

Figure 32. Cylinder thermostat

As can be seen in Figure 33, none of the pilot homes willing to participate in the monitoring stage of the project had air conditioning. In addition, none of the pilot homes have efficient lighting installed (Figure 34).

Jacket13.6%

Spray foam86.4%

Yes36.1%

No63.9%

Page 38: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 38 of 68

Figure 33. Air conditioning

Figure 34. Proportion of low energy lighting installed

5.1.4 Renewable energy sources

In general, the pool of pilot homes does not use local sources of renewable energy. Only 2.8% of the targeted social houses had solar water heating (Figure 35). However, none of the dwellings had photovoltaics (Figure 36), biomass boilers (Figure 37), air or ground source heat pumps (Figure 38) or Micro Combined Heat and Power (Figure 39).

Yes0%

No100%

All0%

Half0%

None100%

Page 39: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 39 of 68

Figure 35. Solar water heating

Figure 36. Photovoltaics

Yes2.8%

No97.2%

Yes0%

No100%

Page 40: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 40 of 68

Figure 37. Biomass boiler

Figure 38. Air or ground source heat pump

Yes0%

No100%

Yes0%

No100%

Page 41: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 41 of 68

Figure 39. Micro combined heat and power (CHP)

5.1.5 Access to internet

As shown in Figure 40, around 78% of the pool of pilot homes have access to the Internet at home. Out of the homes with Internet access and according to Figure 418, 65.6% have wireless broadband, 21.9% Mobile 3G and 21.1% Mobile 4G.

Figure 40. Access to the Internet at home

8The total percentage of Internet connection types is greater than 100% because some of the households have multiple types of Internet connection in the same home.

Yes0%

No100%

Yes78%

0%

No22%

Page 42: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 42 of 68

Figure 41. Internet connection type for households with Internet access at home

5.2 Socio economic anlysis

5.2.1 Age of the Household Representative Person (HRP)

Within the pool of pilot homes, tenants had a mean age of 54 (ranging between 24 and 84). As can be seen from Figure 4242, the majority of tenants (69%) are over 45 years of age. Most householders fall in the 45-54 (23%) or 55-64 (22%) age category.

0

10

20

30

40

50

60

70

Wirelessbroadband

Wiredbroadband

Mobile 3G Mobile 4G Don't know Other

Num

ber o

f hou

seho

lds

Internet connection type

65.6%

12.5%

21.9% 21.1%

3.9% 0.8%

Page 43: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 43 of 68

Figure 42. Percentage of respondents (of the total) in each age category.

5.2.2 Gender of the Household Representative Person (HRP)

Out of the 137 householders in the pool of pilot homes, 56 (41%) are male, 73 (53%) are female, and 8 (6%) did not provide their gender in the Tenants’ Survey.

5.2.3 Family structure

In total, in the pool of pilot homes, 81 respondents (59%) provided age and gender information on the other members of their household, the remaining 56 (41%) respondents either lived on their own or did not report any details on the other members of their household. Forty-two respondents reported living with one other person. As can be seen from Figure 4343, respondents in two-person households mostly reported living with another adult.

missing5% age 18-24

2%

age 25-3410%

age 35-4414%

age 45-5423%

age 55-6422%

age 65-7417%

age 75+7%

Page 44: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 44 of 68

Figure 43. Responses to the question “who is living with you” for 2-person households.

Sixteen respondents reported living with two other persons. As can be seen from ¡Error! No se encuentra el origen de la referencia.44, respondents in three-person households mostly reported living with two adultsor another adult and a child under 16 years of age.

Figure 44. Responses to the question “who is living with you” for 3-person households.

Fifteen respondents reported living with three other persons. As can be seen from ¡Error! No se encuentra el origen de la referencia.5, respondents in four-person households mostly reported living with another adult and two children under 16 years of age.

Missing

Female

Male

Missing

Child (under 16)

Child (16-18)

Adult (18+)

Gen

der

Age

31.3%18.8%

50.0%31.3%

6.3%62.5%

18.8%50.0%

31.3%18.8%

81.3%

Missing

Male

Child (16-18)

Missing

Male

Adult (18+)

Gen

der

Age

Gen

der

Age

Pers

on 2

Pers

on 1

Who is living with you? (3 person household)HRP mean age 43 (SD = 12.34), 44% male

Numbers represent percentage of the total (N = 16)

Page 45: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 45 of 68

Figure 45. Responses to the question “who is living with you” for 5-person households.

Only two respondents reported living with five other persons, due to the small number of respondents in this group further data is not reported on the family structure of these households (i.e. to ensure their data remains anonymous).

50.0%

16.7%

33.3%

66.7%

33.3%

50.0%

33.3%

16.7%

66.7%

33.3%

50.0%

50.0%

50.0%

16.7%

33.3%

66.7%

33.3%

16.7%

83.3%

Missing

Female

Male

Child (under 16)

Child (16-18)

Missing

Female

Male

Child (under 16)

Adult (18+)

Female

Male

Child (under 16)

Child (16-18)

Adult (18+)

Missing

Male

Child (under 16)

Adult (18+)

Gen

der

Age

Gen

der

Age

Gen

der

Age

Gen

der

Age

Pers

on 4

Pers

on 3

Pers

on 2

Pers

on 1

Who is living with you? (5 person household)HRP mean age 38 (SD = 10.33), 0% male

Numbers represent percentage of the total (N = 6)

Page 46: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 46 of 68

5.2.4 Employment status of Household Representative Person (HRP) and other family members

As can be seen in Figure 46, in the pool of pilot homes, the household representative person was most likely to be employed (39%) or retired (32%), with smaller groups of respondents unemployed (4%) or looking for work (3%).

Figure 46. Employment status of the household representative person (percentage of the total).

The household representative person was asked to report the employment status of other household members; the responses are summarised in Table 2. Employment status of other

members of the household

. Similar to Figure 4646, the highest number of responses was given for the ‘employed’ and ‘retired’ category.

How many people in your household are… Number of responses in each category Employed 75 Unemployed 37 Seeking work 34 Student 42

Employed39%

Unemployed4%

Seeking work3%

Student1%

Retired32%

Prefer not to

answer12%

Other (please specify)

5%

Missing4%

Page 47: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 47 of 68

Retired 66 Other 42 Prefer not to answer 30

Table 2. Employment status of other members of the household

5.2.5 Qualifications of the Household Representative Person (HRP)

The household representative person was asked whether they had any educational qualifications for which they received a certificate, 126 householders in the pool of pilot homes provided an answer to this question of which 71% answered yes, and 29% answered no. The HRP was also asked whether they had any professional, vocational or other work-related qualifications for which they received a certificate, 124 householders in the pool of pilot homes provided an answer to this question of which 65% answered yes, and 35% answered no. Finally, the HRP was asked to indicate their highest qualification level. Figure 47 shows that 23% of the householders in the pool of pilot homes held an O’level, GCSE, NVQ level 2 or equivalent9, 17% held an A’Level, NVQ level 3 or equivalent10, and 18% held a higher education degree level or above. Eighteen percent of householders indicated that the question was not applicable to them.

9O’level (Ordinary Level), GCSE (General Certificate of Secondary Education), and NVQ (National Vocational Qualification) Level 2, are academic and work-based qualifications up to the age of 16 years old. 10A’Level (General Certificate of Education Advanced Level) is awarded to students completing secondary or pre-university education. NVQ (National Vocational Qualification) Level 3, is the equivalent work-based qualification.

O’level, GCSE, NVQ level 2 or

equivalent23%

A’Level, NVQ level 3 or

equivalent17%Degree

level (e.g. BA, BSc) or above

18%Another kind of

qualification9%

Not applicable18%

Prefer not to answer

8% Missing7%

Page 48: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 48 of 68

Figure 47. Highest qualification level of the household representative person(percentage of the total).

5.2.6 Welfare benefits

Out of the one hundred and twenty-eight householders in the pool of pilot homes who responded to the question, 50.8 percent selected ‘yes’ to the question whether they or members of their household were in receipt of welfare benefits, such as unemployment allowance or housing benefit.

5.2.7 Health of the Household Representative Person (HRP)

The majority of householders in the pool of pilot homes rated their health, in general, over the last 12 months as good (24%) or fair (28%) – as can be seen in Figure 48.

Figure 48. Responses to the question ‘how was your health in general in the last 12 months’(percentage of the total).

Very good15%

Good24%

Fair28%

Bad20%

Very bad10%

Prefer not to answer

3%

Missing2%

Page 49: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 49 of 68

One hundred and six householders in the pool of pilot homes provided an answer to the question ‘how many times have you visited your General Practice (GP) surgery in the last 12 months’. Ninety-four householders provided a number: on average they visited their GP five times in the last 12 months (SD = 5.01). Numbers ranged from zero to twenty-four. Twelve householders provided a written answer (e.g. ‘rarely’) these were coded into common responses and are displayed in Table 3. Most commonly, householders reported visiting the GP ‘often’ in the last 12 months (33.3%), or being ‘unsure’ about how often they had visited the GP (25%).

How many times have you visited your GP surgery in the last 12 months

Percentage of responses (of the total N = 12)

Rarely/a few times 16.7% Several times 8.3% Often/a lot 33.3% Don’t know/unsure 25% Other 16.7%

Table 3. Percentage of responses for each written category of General Practice (GP) visits.

On average, householders in the pool of pilot homes felt fairly satisfied with life nowadays, with a mean score of 6.03 (SD = 2.54) on a scale ranging from 0 (Not at all satisfied) to 10 (Completely satisfied), based on 134 responses. A one-sample t-test indicated that the mean score was significantly above the neutral midpoint of the scale, t(133) = 4.70, p<.001.

Finally, 38.8% of respondents in the pool of Pilot Homes considered themselves to have a disability, and 20.3% reported that another member of their household considered themselves to have a disability.

6. Description of the monitored pilot homes This section describes the main building and socio-demographic characteristics of the 43households where the monitoring kit has been already installed. The data presented in this sectioncome from the EnerGAware Social Housing Survey, the DCH’s Building Stock Condition and Energy Database and the information collected by the DCH personnel when installing the monitoring kits using the Technical Information Data Collection Form (See Appendix B).

Page 50: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 50 of 68

As Deliverable 4.1 is publically available, only limited data are presented at a household level for the households partaking in the field trial in order to maintain their anonymity in accordance with the EU ethical procedure governing the EnerGAware project and the Data Protection Act (1998). In addition, where possible, data have been aggregated into defined groups. The full range of data for each home is held internally and only accessible to those project partners requiring the data and are signatory to a non-disclosure agreement.

6.1 Building characteristics

Table 4 shows the main building characteristics of the 41 monitored homes including the type of property, the period of construction, the number of storeys and the number of habitable rooms. Table 4 also provides information about the SAP, types of energy, main heating fuel and renewable energy systems in each household.

Page 51: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary)Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 51 of 68

Dwelling Id* Property type Period of

construction Number of

storeys Number of

habitable rooms SAP SAP band Energy Main heating

fuel Renewable

energy system

1 Mid terrace House 1967-1975 1 3 72 C Gas and electric Mains gas No

2 End terrace house 2007+ 2 4 82 B Gas and electric Mains gas No

3 End terrace house 1976-1982 2 3 62 D Gas and electric Mains gas No

4 Mid Terrace House 2007+ 3 6 85 B Gas and electric Mains gas Solar hot water

5 Flat 2007+ 1 3 76 C Gas and electric Mains gas No

6 Mid terrace House 2007+ 2 3 75 C Gas and electric Mains gas No

7 Mid terrace House 2007+ 2 3 69 C Gas and electric Mains gas No

8 Mid terrace House 1900-1949 2 5 55 D Gas and electric Mains gas No

9 Mid terrace House 1900-1949 2 5 27 F Gas and electric Mains gas No

10 Flat 1996-2002 1 3 76 C Gas and electric Mains gas No

11 Semi-detached bungalow 1900-1949 1 3 63 D Gas and electric Mains gas No

Page 52: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary)Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 52 of 68

Dwelling Id* Property type Period of

construction Number of

storeys Number of

habitable rooms SAP SAP band Energy Main heating

fuel Renewable

energy system

12 Semi-detached bungalow 1967-1975 1 3 65 D Gas and electric Mains gas No

13 Flat 1976-1982 1 2 63 D Electric only Electricity No

14 Flat 1983-1990 1 2 71 C Electric only Electricity No

15 Flat 1983-1990 1 2 60 D Electric only Electricity No

16 Flat 1983-1990 1 2 75 C Electric only Electricity Solar hot water

17 Flat 1983-1990 1 2 77 C Electric only Electricity No

18 Mid terrace House 2007+ 3 6 84 B Gas and electric Mains gas No

19 Semidetached house 1967-1975 1 4 71 C Gas and electric Mains gas No

20 End terrace house 1991-1995 1 4 67 D Gas and electric Mains gas No

21 Flat 1983-1990 1 2 63 D Electric only Electricity Solar hot water

22 Semi-detached house 1991-1995 1 4 68 D Gas and electric Mains gas No

23 Mid terrace house 1996-2002 1 4 68 D Gas and electric Mains gas No

Page 53: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary)Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 53 of 68

Dwelling Id* Property type Period of

construction Number of

storeys Number of

habitable rooms SAP SAP band Energy Main heating

fuel Renewable

energy system

24 Mid terrace House 1900-1949 2 5 74 C Gas and electric Mains gas No

25 Mid terrace House 2007+ 2 4 87 B Gas and electric Mains gas No

26 Mid terrace House 1900-1949 2 4 60 D Gas and electric Mains gas No

27 Flat 1976-1982 1 2 61 D Gas and electric Mains gas No

28 Flat 1983-1990 1 2 59 D Gas and electric Mains gas No

29 Maisonette 1983-1990 1 4 69 C Gas and electric Mains gas No

30 Flat 2007+ 1 2 89 B Gas and electric Mains gas No

31 Mid terrace House 2007+ 2 4 83 B Gas and electric Mains gas No

32 End terrace house 1967-1975 2 4 54 E Gas and electric Mains gas No

33 Mid terrace House 2007+ 2 4 83 B Gas and electric Mains gas No

34 Mid terrace House 1967-1975 3 3 55 D Gas and electric Mains gas No

35 Mid terrace House 2007+ 3 6 84 B Gas and electric Mains gas No

Page 54: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary)Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 54 of 68

Dwelling Id* Property type Period of

construction Number of

storeys Number of

habitable rooms SAP SAP band Energy Main heating

fuel Renewable

energy system

36 Flat 1976-1982 1 2 75 C Gas and electric Mains gas Solar hot water

37 Flat 1976-1982 1 2 56 D Gas and electric Mains gas No

38 Semi-detached bungalow 1967-1975 1 3 68 D Gas and electric Mains gas No

39 End terrace house 2007+ 2 4 85 B Gas and electric Mains gas No

40 Mid terrace House 2007+ 1 3 68 D Gas and electric Mains gas No

41 Flat 2007+ 1 2 74 C Gas and electric Mains gas No

42 Mid terrace House 2007+ 2 4 86 B Gas and electric Mains gas No

* Information about dwelling id 43 is pending.

Table 4. Building characteristics of the already monitored houses.

Page 55: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary)Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 55 of 68

6.2 Socio-demographic characteristics

Table 5 provides information about age and the employment status of the Household Representative Person as well as the size of the household in number of people and the corresponding composition.

Dwelling

id* HRP age Household size Household composition HRP employment status

1 70-79 1 One person Employed

2 18-29 5 Couple with dependent child(ren) Employed

3 30-39 3 Lone parent with dependent child(ren) Prefer not to answer

4 40-49 5 Couple with dependent child(ren) Employed

5 30-39 3 Lone parent with dependent child(ren) Other

6 70-79 1 One person Employed

7 40-49 1 One person Employed

8 70-79 1 One person Retired

9 30-39 4 Couple with dependent child(ren) Employed

10 40-49 3 Couple with dependent child(ren) Employed

11 50-59 2 Couple, no dependent children Retired

12 50-59 3 Couple with dependent child(ren) Retired

13 30-39 1 One person Retired

14 60-69 2 Couple, no dependent children Retired

15 70-79 1 One person Retired

16 60-69 2 Couple, no dependent children Retired

Page 56: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 56 of 68

Dwelling id* HRP age Household

size Household composition HRP employment status

17 40-49 5 Couple with dependent child(ren) Retired

18 50-59 1 One person Employed

19 50-59 1 One person Retired

20 18-29 2 Couple, no dependent children Employed

21 60-69 1 One person Retired

22 40-49 3 Couple with dependent child(ren) Retired

23 70-79 1 One person Employed

24 30-39 4 Couple with dependent child(ren) Prefer not to answer

25 30-39 1 One person Employed

26 80+ 2 Couple, no dependent children Retired

27 70-79 1 One person Retired

28 50-59 1 One person Retired

29 80+ 1 One person Employed

30 60-69 1 One person Retired

31 60-69 1 One person Other

32 40-49 3 Lone parent with dependent child(ren) Student

33 50-59 2 Couple, no dependent children Employed

34 80+ 1 One person Retired

35 40-49 3 Couple with dependent child(ren) Employed

Page 57: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 57 of 68

Dwelling id* HRP age Household

size Household composition HRP employment status

36 50-59 1 One person Retired

37 50-59 1 One person Prefer not to answer

38 80+ 1 One person Retired

39 40-49 2 Lone parent with dependent child(ren) Employed

40 80+ 1 One person Employed

41 18-29 5 Couple with dependent child(ren) Other

42 30-39 1 One person Employed

* Information about dwelling id 43 is pending.

Table 5. Socio-demographic characteristics of the already monitored houses.

6.3 Energy infrastructure characteristics

Table 6 provides information about the gas and the electricity meters as well as the distance between data aggregators and meters and the availability of internet connection.

Page 58: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 58 of 68

Dwelling id*

Gas meter Electricity meter Distance data aggregator -

meters

Inter-net Observations

Type Manufacturer Model Location Type Manufacturer Model Conversion factor Location

1 Analogue Schlumberger G4 Indoor Analogue N/K*** N/K 200 rev/kWh Indoor Gas: 1 m Yes -

2 Analogue Krom/Schroder G4 Indoor Digital Landis&Gyr E470 1000 impulses/kWh Indoor Electric: 0.5 m

Gas: 2 m Yes Pulse counter removed

3 Analogue Actaris G4 External cupboard Analogue English

electric C11B/M 200 rev/kWh Outdoor Gas: 5 m Yes

Unable to fit to electric meter due to being

analogue

4 Analogue Actaris N/K Outdoor Digital Landis&Gyr 5235A 1000 impulses/kWh Indoor 1 m Yes

Unable to fit to electric meter

due to low position of meter

in ground

5 Analogue Actaris N/K Outdoor Digital Landis&Gyr 5235A 1000 impulses/kWh Indoor Electric: 6 m

Gas: 14 m Yes -

6 Digital Landis&Gyr G370 Indoor Digital Landis&Gyr E470 1000 impulses/kWh Indoor Electric: 1.5 m

Gas: 1 m Yes Digital gas meter so unable to fit

EC

7 Analogue Schlumberger N/K Outdoor Analogue British electric N/K 200 rev/kWh Outdoor Electric: 1.5 m Gas: 3 m No -

8 Analogue Krom/Schroder G4 Outdoor Digital Landis&Gyr E110 1000 impulses/kWh Indoor 0.5 m Yes

Unable to fix EC to meter due to

front cover

9 Digital Landis&Gyr G370 Indoor Digital Landis&Gyr E470 1000 impulses/kWh Indoor 1 m Yes -

Page 59: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 59 of 68

Dwelling id*

Gas meter Electricity meter Distance data aggregator -

meters

Inter-net Observations

Type Manufacturer Model Location Type Manufacturer Model Conversion factor Location

10 Analogue Actaris G4 Indoor Analogue British electric N/K 1000 impulses/kWh Indoor Gas: 3 m No -

11 Analogue Schlumberger n/a**** Outdoor Analogue n/a n/a 200 rev/kWh Indoor n/a Yes

Unable to fit EC to meter due to proximity of front cover of meter

box

12 Analogue Schlumberger G4 Outdoor Digital Landis&Gyr E110 1000 impulses/kWh Indoor Electric: 0.5 m

Gas: 5 m Yes -

13 - - - - Digital Landis&Gyr E110 1000 impulses/kWh Indoor 2 m Yes No gas installed

at property

14 - - - - Digital Landis&Gyr 5235D 1000 impulses/kWh Indoor 1.5 m No No gas installed

at property

15 - - - - Digital Landis&Gyr 5235D 1000 impulses/kWh Indoor 2 m Yes No gas installed

at property

16 - - - - Digital Landis&Gyr 5235D 1000 impulses/kWh Indoor n/a Yes No gas installed

at property

17 - - - - Digital Landis&Gyr 5235D 1000 impulses/kWh Indoor 4 m Yes No gas installed

at property

18 Analogue Actaris N/K Outdoor Digital Landis&Gyr E470 1000 impulses/kWh Indoor Electric: 1 m

Gas: 3 m Yes -

19 Analogue Actaris G4 Indoor Pre-payment Actaris ACE9000

KBD 1000 impulses/kWh Indoor Electric: 0.5 m

Gas: 4 m Yes -

Page 60: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 60 of 68

Dwelling id*

Gas meter Electricity meter Distance data aggregator -

meters

Inter-net Observations

Type Manufacturer Model Location Type Manufacturer Model Conversion factor Location

20 Analogue Schlumberger N/K Outdoor Digital Landis&Gyr E110 1000 impulses/kWh Outdoor Electric: 2 m

Gas: 2.5 m Yes -

21 - - - - Digital Landis&Gyr 5235D 1000 impulses/kWh Outdoor 3 m No -

22 Analogue Actaris G4 Indoor Digital Landis&Gyr E110 1000 impulses/kWh Indoor Electric: 1 m

Gas: 6 m Yes -

23 Analogue Schroder BK-G4 Outdoor Digital pre-payment Landis&Gyr ZCE527,

1 1000 impulses/kWh Outdoor 4 m Yes -

24 Analogue Krom/Schroder G4 Outdoor Digital pre-payment Landis&Gyr E110 1000

impulses/kWh Indoor Electric: 2 m Gas: 3 m Yes -

25 Analogue Krom/Schroder G4 Indoor Digital Landis&Gyr E470 1000 impulses/kWh Indoor Electric: 0.5 m

Gas: 1 m Yes -

26 Analogue Schlumberger R5 Indoor Digital Landis&Gyr 5235A 1000 impulses/kWh Indoor 0.5 m Yes -

27 Analogue Schlumberger R5 Indoor Digital Actaris Ace1000 800 impulses/kWh Indoor 2 m No -

28 Analogue Actaris N/K Outdoor Digital Landis&Gyr 52350 1000 impulses/kWh Outdoor Electric: 3 m

Gas: 4 m Yes -

29 Analogue Krom/Schroder G4 Indoor Digital Landis&Gyr E110 1000 impulses/kWh Indoor 4 m Yes -

30 - - - - Digital Landis&Gyr E110 1000 impulses/kWh Indoor 6 m No

Heating and hot water fed from

communal boiler

Page 61: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 61 of 68

Dwelling id*

Gas meter Electricity meter Distance data aggregator -

meters

Inter-net Observations

Type Manufacturer Model Location Type Manufacturer Model Conversion factor Location

system via heat exchanger

31 Analogue Actaris G4 Indoor Digital Landis&Gyr E470 1000 impulses/kWh Indoor Electric: 0.5 m

Gas: 1 m Yes -

32 Analogue Actaris G4 Outdoor Digital Landis&Gyr E110 1000 impulses/kWh Outdoor Electric: 1 m

Gas: 6 m Yes -

33 Analogue Actaris G4 Indoor Digital Landis&Gyr E470 1000 impulses/kWh Indoor Electric: 0.5 m

Gas: 1 m Yes -

34 Analogue Krom/Schroder G4 Outdoor Digital Landis&Gyr E110 1000 impulses/kWh Outdoor Electric: 1 m

Gas: 6 m Yes -

35 Analogue Krom/Schroder G4 Indoor Digital Landis&Gyr E470 1000 impulses/kWh Indoor Electric: 1 m

Gas: 1.5 m Yes -

36 Analogue Actaris G4 Outdoor Digital Landis&Gyr E110 1000 impulses/kWh Outdoor Electric: 4 m

Gas: 6 m Yes -

37 Analogue Actaris G4 Outdoor Digital Landis&Gyr E110 1000 impulses/kWh Outdoor Electric: 5 m

Gas: 6 m No -

38** Analogue Sensus Cubix U6 Outdoor Digital Landys E110 1000

impulses/kWh Indoor 15 m N/K -

39** Analogue Sensus Cubix U6 Outdoor Digital Landys E110 1000

impulses/kWh Indoor 5 m N/K -

40** Analogue Sensus Cubix U6 Outdoor Digital Landys E110 1000

impulses/kWh Indoor 5 m N/K -

Page 62: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 62 of 68

Dwelling id*

Gas meter Electricity meter Distance data aggregator -

meters

Inter-net Observations

Type Manufacturer Model Location Type Manufacturer Model Conversion factor Location

41** Analogue Hanson PLC UGI Indoor Digital Landys E110 800 impulses/kWh Outdoor 5 m N/K -

42** Analogue Sensus Cubix U6 Outdoor Digital Landys E110 1000

impulses/kWh Indoor 10 m N/K -

* Information about dwelling id 43 is pending.

** Information about dwelling ids 38, 39, 40, 41 and 42 needs to be confirmed.

*** N/K: Not known

**** n/a: Non applicable

Table 6. Energy infrastructure characteristics of the already monitored houses.

Page 63: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 63 of 68

7. Conclusions This deliverable is the preliminary version of the reporting activities on the pilot implementation methodology, a final version will be delivered a t the end of the second reporting period (M24). The report presents the planning and the results of the two installation phases carried out at the time of writing this report.

The original approach for the field campaign has been slightly modified during the project execution. Initially, the aim of this task was to perform an energy audit over the pre-selected pilot homes to identify the technical requirements and design an ad-hoc ICT solution for the data collection. After the recruitment process and following the recommendations of social experts, the consortium decided not to annoy the pre-selected tenants with preliminary visits and audits. Therefore, the consortium agreed on a different approach, the design of a generic monitoring solution able to be installed in most of the houses in just one visit per home.

Deliverable 4.1 has presented the analysis of the building and energy infrastructure characteristics as well as the socio-economic aspects of 43 households resulting of the initial field campaign undertaken.

Page 64: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 64 of 68

Appendix A. EnerGAware information sheet

Page 65: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 65 of 68

Page 66: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 66 of 68

Appendix B. EnerGAware technical information data collection form

Page 67: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 67 of 68

Page 68: D4.1 – Pilot implemetation methodology (preliminary) · D4.1 – Pilot implemetation methodology (preliminary) Document number D4.1 Document title Pilot implementation methodology

D4.1 - Pilot Implementation methodology (preliminary) Dissemination level: PU

EnerGAware - 649673 Version 1.1 Page 68 of 68

References [1] Department of Energy and Climate Change (DECC). 2012. The Government’s Standard

Assessment Procedure for Energy Rating of Dwellings. SAP 2012 version 9.92. BREGarston.

[2] Laustsen, J., International Energy Agency Energy. 2008. Efficiency requirements in building codes, energy efficiency policies for new buildings.