CSD TWO INTERCONNECTED MIDDLE SCHOOLS REVISIONS TO...

83
Page 1 of 14 Date: January 15, 2021 Re: CSD TWO INTERCONNECTED MIDDLE SCHOOLS Dover, Delaware 2019180.00 ADDENDUM TWO The addendum forms a part of the contract documents and modifies the original bidding documents dated December 18, 2020, and Addendum 0NE date January 8, 2021, as noted below. REVISIONS TO ADDENDUM ONE 1. Under PROJECT MANUAL VOLUME 2, item #6, CHANGE not required to be AWI certified to not required to be AISC certified.2. Under PROJECT MANUAL VOLUME 2, item #4, CHANGE Section 117300to Section 133418.3. Under PROJECT MANUAL VOLUME 2, item #9, CHANGE Section 133418to Section 117300.PROJECT MANUAL VOLUME 1 1. See attached RYJ Addendum No. 2. PROJECT MANUAL VOLUMES 2 1. Section 064023 - Interior Architectural Woodwork. a. Under 1.6C.1., DELETE Bowmar Millwork Corporation, Princess Anne, Marylandand ADD .3- D Fabrication, Inc., Newark, DE;T.J. Lane Construction, Dover, DE;and Group Three Inc., Wilmington, DE.2. Section 096466-Wood Athletic Flooring a. Under 2.1A1., DELETE a. through d. and REPLACE witha. Connor, b. .Robbin’s, c. Superior Floor, d. Action Flooring.3. Section 096566-Resilient Athletic Flooring a. Under 2.1.A.7., DELETE and patterns.b. Under 2.1B..7., DELETE and patterns.4. ADD attached Section 098400-ACOUSTICAL WALL SYSTEMS. 5. REPLACE Section 098433- SOUND-ABSORBING WALL UNITS with attached Section 098433. 6. Section 101463-Electronic Message Signage a. Under 1.2A1, CHANGE Double-sidedto Single-sided.b. CHANGE 2.2 DOUBLE-FACED LED SIGNSto 2.2 SINGLE-FACED LED SIGNS.c. Under 2.2A, ADD 2. Watchfire.d. Under 2.2D, CHANGE Double-sidedto Single-sided.e. Under 2.2D1., CHANGE 16 mmto 10 mm.7. Section 116133-Stage Rigging and Draperies a. Under 3.3B2, ADD c. Wenger/JR Clancy’s standard Varion stage rigging hoist system (15 FPM

Transcript of CSD TWO INTERCONNECTED MIDDLE SCHOOLS REVISIONS TO...

  • Page 1 of 14

    Date: January 15, 2021

    Re: CSD TWO INTERCONNECTED MIDDLE SCHOOLS

    Dover, Delaware

    2019180.00

    ADDENDUM TWO

    The addendum forms a part of the contract documents and modifies the original bidding documents dated December 18,

    2020, and Addendum 0NE date January 8, 2021, as noted below.

    REVISIONS TO ADDENDUM ONE

    1. Under PROJECT MANUAL VOLUME 2, item #6, CHANGE “not required to be AWI certified to “not required to be AISC certified.”

    2. Under PROJECT MANUAL VOLUME 2, item #4, CHANGE “Section 117300” to “Section 133418.”

    3. Under PROJECT MANUAL VOLUME 2, item #9, CHANGE “Section 133418” to “Section 117300.”

    PROJECT MANUAL VOLUME 1

    1. See attached RYJ Addendum No. 2.

    PROJECT MANUAL VOLUMES 2

    1. Section 064023 - Interior Architectural Woodwork.

    a. Under 1.6C.1., DELETE “Bowmar Millwork Corporation, Princess Anne, Maryland” and ADD “.3-D Fabrication, Inc., Newark, DE;” “T.J. Lane Construction, Dover, DE;” and “Group Three Inc.,

    Wilmington, DE.”

    2. Section 096466-Wood Athletic Flooring

    a. Under 2.1A1., DELETE a. through d. and REPLACE with” a. Connor, b. .Robbin’s, c. Superior

    Floor, d. Action Flooring.”

    3. Section 096566-Resilient Athletic Flooring

    a. Under 2.1.A.7., DELETE “and patterns.”

    b. Under 2.1B..7., DELETE “and patterns.”

    4. ADD attached Section 098400-ACOUSTICAL WALL SYSTEMS.

    5. REPLACE Section 098433- SOUND-ABSORBING WALL UNITS with attached Section 098433.

    6. Section 101463-Electronic Message Signage

    a. Under 1.2A1, CHANGE “Double-sided” to “Single-sided.”

    b. CHANGE “2.2 DOUBLE-FACED LED SIGNS” to “2.2 SINGLE-FACED LED SIGNS.”

    c. Under 2.2A, ADD “ 2. Watchfire.” d. Under 2.2D, CHANGE “Double-sided” to “Single-sided.”

    e. Under 2.2D1., CHANGE “16 mm” to “10 mm.”

    7. Section 116133-Stage Rigging and Draperies

    a. Under 3.3B2, ADD “c. Wenger/JR Clancy’s standard Varion stage rigging hoist system (15 FPM

  • Page 2 of 14

    speed) is an acceptable equivalent.

    8. Section 133413.13-Greenhouses.

    a. Under 2.2G3,, DELETE 3a and REPLACE with”3a. Sloped glass units are to be fully insulated 1/8"

    tempered Clear, 5/8" air space, and 1/8" tempered Clear inner layer for an overall thickness of 7/8".

    All units may be gas filled. ( If Required ).”

    b. Under 2.2G3,, DELETE 3b and REPLACE with”3b. Vertical glass units are to be fully insulated 1/8"

    tempered Clear, 5/8" air space, and 1/8" tempered Clear inner layer for an overall thickness of 7/8".

    All units may be gas filled. ( If Required ).”

    9. ADD attached Section 265501- STAGE LIGHING SYSTEMS.

    10. Section 274100 – Audio and Video Systems

    a. REMOVE 2.2, F. Classroom AV Equipment

    11 REPLACE Section 321813-SYNTHETIC GRASS SURFACING with attached Section 321813.

    DRAWING VOLUMES 1

    1. REPLACE C-901 with the attached C-901, which revises Control Joint Detail, Construction/Expansion Joint

    Detail and Combination Sidewalk and PCC Curb Type 1-6 Detail.

    2. REPLACE C-300 with the attached C-300, which adds Utility Construction Note regarding Utility Post-

    Construction Verification (As-Built) Requirements for the project.

    3. REPLACE A001 with the attached A001, which adds wall type JK.

    4. REPLACE A101A with the attached A101A, which moves door B117/1.

    5. REPLACE A101B with the attached A101B, which moves door B127/1.

    6. REPLACE A101C with the attached A101C, which adds auditorium seat sizes.

    7. REPLACE A101F with the attached A101F, which moves doors C127/1, C131/1, C131/2, C136/1, C140/1 and

    C140/2.

    8. REPLACE A101G with the attached A101G, which moves doors C119/1, C119/2, C123/1 and C123/2.

    9. REPLACE A102G with the attached A102G, which moves doors C215 and C215/2.

    10. REPLACE A407 with the attached A407, which revises Details 2, 3, 5 AND 6.

    11. REPLACE A420 with the attached A420, which revises Details 2A and 2C.

    12. REPLACE A421 with the attached A421, which revise greenhouse dimensions and revises lighting.

    13. ADD attached A546.

    14. REPLACE A701 with the attached A701, which adds casework legend.

    15. A704

    a. On elevations 1, 2, 5 and 8, ADD “(AP-2)” before “Acoustical Pyramidal Diffuser, Typ.”

  • Page 3 of 14

    b. On elevations 3 and 7, CHANGE “AP-5” to “AP-1-See specs for size.”

    c. On elevations 4 and 6, CHANGE “AP-2” and “AP-3” to “AP-1-See specs for size.”

    16. T504

    a. REVISE Notes to delete Teachlogic WC-400 wall cabinet.

    BIDDER’S RFI’s

    RFI 15

    1. Should section 126613 be added to go with scope item AAA gym bleachers?

    a. Answer: See revisions to Contract a-5 Summary of Work

    2. Should section 112800 be added to go with scope item DDD for the literature racks?

    a. Answer: Literature racks were deleted from Contract A-5 in Addendum 1.

    3. Section 133418 Post Framed Building Systems (basis of design by Lester Building Systems) reads like a pole

    barn. The spec is listed in the carpentry scope but there is nothing mentioned in the written scope items. Is the

    pole building intended to be included in the carpentry contract?

    a. Answer: See Addendum 1, RFI 03, Answer 1

    .

    RFI 16

    1. Spec section 064023 - Interior Architectural Woodwork. The approved contractor Bowmar Millwork has a

    telephone number no longer in service. Checking the web, the stated number in the spec is correct. The second

    contractor, Cabinetry Unlimited is still active. Is there another approval other than Bowmar?

    a. Answer: Bowmar will be deleted, and 3-D Fabrication, Inc., T.J. Lane Construction and Group Three

    Inc. added by this addendum.

    2. Spec section 114683 – Ice Machine is not located in the specs. An Ice Machine is noted in spec section

    114000 – Food Service Equipment, item # 65, page 59. Is that our ice machine or is there another ice machine

    that is our responsibility?

    a. Answer: Ice machine is to be provided by Contract 14 Kitchen Equipment

    RFI 17

    1. Will a spec for the wood trusses be issued?

    a. Answer: A spec will be added by future addendum.

    2. Would the monumental stairs be included in the General trades contract?

    a. Answer: Any wood products at monumental stairs is to be by Contract A-5 Carpentry & General Work.

    3. I have not found a louver that was not a mechanical louver. Please have architect advise of louvers not

    supplied and installed by mechanical contractor.

    a. Answer: See revisions to Contract A-5 Summary of Work in Addendum 1. .

    4. Detail 2/A313 shows blow up on S17/A616. A616 is not in the drawings. Wall Type 5B Shows DCMU to 7’

    AFF and T.O.M. 3’4” and also 8’6” Min AFF. How high is this wall?

    a. Answer: A616 will be issued by a future addendum Revisions to Wall Type 5B will be issued by future

    addendum.

  • Page 4 of 14

    5. Most of the corridor walls are labeled as 2C which does not have abuse board. The Spec states that abuse

    board is located at Vertical surfaces in corridors less than 10 feet above finished floor, and as indicated on

    Drawings. Should I follow the wall tag and use regular gyp or the spec and use abuse in corridors?

    a. Answer: Follow the spec. The wall tags will be revised by this addendum.

    RFI 18

    1. Please provide a cross section detail of the Library Circulation Desk with materials used

    a. Answer: A cross section will be provided by a future addendum.

    2. Are the stained wood panels for the Circulation desk by Contract 5 or 13 and what wood species is used?

    According to the contract descriptions, all stained/painted wood items are by contract #5.

    a. Answer: Stained wood panels for the Circulation Desk is by Contract A-13 Casework.

    3. Please provide casework schedule for the casework with ID numbers on the elevations

    a. Answer: Each piece of casework is keyed/tagged on the interior elevations on A410, A430, and A701

    through A708. The explanation of the key/tag will be issued by this addendum.

    4. Please provide sheets A613-A616 for the window sill/jamb/head details. These sheets are called out on the

    window elevations yet are not part of the issued drawings

    a. Answer: A613 through A616 are issued by a future addendum.

    5. Will the wood veneered casework only be used in the science areas? There is no differentiation between the

    plam and wood on the elevations. I just want to make sure there isn’t any wood casework in say the Art/FCS

    areas.

    a. Answer: Yes.

    6. Is the stainless steel casework in cafeteria D116 by the food service contract?

    a. Answer : Contract A-13 Casework is to provide.

    7. There are a few items in the casework contract summary that I believe maybe boiler plate because they are not

    shown on the plans and don’t have any specs: Media Shelving and Plam and Wood wall panels.

    a. Answer: P-lam and wood wall panels are to be provided Contract 13 Casework. Media shelving is NIC.

    RFI 19

    1. Drawing C-901: Is caulking of concrete sidewalk expansion and control joints required?

    a. Answer: Per the construction details, caulk is required.

    2. Drawing C-304: Where is storm pipe runs, 27B, and 2E located on the utility plans?

    a. Answer: Pipe 2E is the stub exiting the rear of CB-1E and enters the side of the existing 72” pipe.

    Replace existing pipe and repair connection as necessary. Provide water tight seal.

    Pipe 27B is in the front parking lot, out of CB-27B

    .

    3. Sitework scope of work item R on page 011100-6 says the sitework contractor is responsible for gas lines and

    meters. The Utility Plans C-301 and C-302 state that gas service including meters is by Chesapeake Utilities.

    Which is correct?

    a. Answer: See Addendum 1, RFI 08, Answer 2

    4. Who is responsible for soil compaction testing and concrete cylinder testing?

    a. Answer: All required testing related to your work is to be by each contractor

  • Page 5 of 14

    .

    5. Sitework scope of work item HH on page 011100-7 say to demolish and underground tank. What size is this

    tank and has it been drained?

    a. Answer: The contents and size of the existing tank is unknown. Assume 5,000 gal abandoned fuel

    tank, to be removed in accordance with all local agency permitting and requirements, for the

    purposes of this bid.

    .

    RFI 20

    1. I wanted to clarify that as an AV and Structured cabling vendor bidding on this project that we do not have to

    be on the DE state contracts for these disciplines.

    a. Answer: Bid project as noted in specifications .

    2. On this section of this bid, A-20: Classroom A/V Systems, does this relate to section SECTION 27 41 00 –

    AUDIO-VIDEO SYSTEMS & SECTION 27 41 16 - SMALL AV SYSTEMS?

    a. Answer: See Item A on Sheet 011100-46. .

    3. What divisions are included in A-21: Specialized A/V Systems?

    a. Answer: See Item A on Sheet 011100-47.

    RFI 21

    1. Drawing QT 103 show the rigging beams tilted and pitched along roof line. Structural drawing does not

    provide confirmation of this detail. Can you please confirm rigging beams are tilted and pitched and the the

    bottom flanges of the beams are aligned on the same plane? This is critical for mounting of the rigging hoist

    compression tube.

    a. Answer: Yes, the roof beams are in plane with the roof (tilted and pitched).

    2. Section 116133 does not specify type of cable management for the electrics hoists. Is ETC Helix an

    acceptable solution?

    a. Answer: Yes, the ETC helix stage lighting cable handing system will be noted is acceptable by this

    addendum.

    RFI 22

    1. Clarify – Plan sections reference details on A613 & A616, but A613 & A616 do not exist.

    a. Answer: A613 through A616 are issued by a future addendum .

    2. Clarify – HPC-1 is listed on the wall finish schedule (rooms D118-D118J), however the key makes no

    reference to HPC-1.

    a. Answer: . On Finish Legend-Basis Of Design, REPLACE “EP-1” with “HPC-1.” This was issued by

    Addendum One.

    3. Clarify - Interior metal wall panels are usually an acoustical item. Which contract do these belong to?

    a. Answer: See revisions to Contract A-5 Carpentry & A-10 Acoustical Work in this addendum.

    .

    4. Clarify – Refer to Plan A406, wall finish at Alcove opening under stairs a. What contract owns the wood on

    the walls? b. What contract owns the wood on the bench? c. Are they the same product?

    a. Answer: Contract A-5 Carpentry & General Work provides he wood on the walls and wood on the

    bench.

  • Page 6 of 14

    RFI 23

    1. What contract is responsible for the stainless steel top in Concession F2 on elevation7/A430? I would assume

    the stainless steel counter/shelves/ support legs in the same room, elev 6/A430 would be by the food service

    supplier?

    a. Answer: Elevation 7/A430 to be provided by Contract A-13 Casework; Elevation 6/A430 to be

    provided by Contract A-14 Kitchen Equipment.

    .

    2. Is the details 5 & 6/A513 correct that the solid surface lockertop/sill extends over the low wall and the hallway

    storefront window sits on top of the solid surface? Please reference Michael Weir’s email regarding the

    custom solid surface. If any of these get scratched/dented/broken during the installation of the window,

    replacement of this top could put the completion of the project in jeopardy due to long lead times and be very

    expensive to the party damaging these tops. I would highly suggest changing this detail to have the

    lockertop/sill on both sides of the window butt up against the frame instead of extending underneath it.

    a. Answer: This revision would be acceptable if the two sill pieces are installed under the edge of the

    storefront and the joints cleanly sealed. Approval of a mockup will be required prior to proceeding

    with final installations.

    RFI 24

    1. The drawing (A-421) shows the overall width of the greenhouse being 20’ and the length 36‘ (scaled).

    However, the model spec’d, Sierra Room Model SES-SL16B is only 16’-4 ¾” . And the standard Base

    Lengths don’t seem to match up with an overall 36‘ base.

    a. Answer: The dimensions on A421 will be revised to match the Sierra Model by this addendum.

    2. Also, the specs are showing (3) different kinds of glass that can be used; all having a different price.

    a. Answer: Glass in Section 133413.13- Greenhouses will be revised by this addendum.

    RFI 25

    1. Please confirm all trenched conduit as shown on drawing T001 will be provided and installed by the awarded

    electrical contractor.

    a. Answer: Correct; Contract 17 Electrical to provide.

    2. Please confirm all raceways (conduit and back-boxes) will be provided and installed by the awarded electrical

    contractor to the accessible ceiling for Sections 271000 (Structured Cabling) and Section 28200 (Video

    Surveillance Systems)

    a. Answer: Correct; Contract 17 Electrical to provide.

    3. Please confirm camera #122 is intentionally missing from drawing T102H and from the CCTV camera

    schedule on drawing T512.

    a. Answer: Correct, there is no camera 122.

    4. The CCTV camera schedule lists camera #126 & 132, but these cameras are not shown on any site plan or

    floor plan drawing from T000 through T513. Can you provide the drawing number which shows the location

    of these two cameras?

    a. Answer: Camera 126 is located on Sheet T101A, Alcove B3D. Camera 132 is located on Sheet T001,

    Detail 6 Maintenance Building.

    5. The CCTV camera schedule lists the below interior cameras numbers to be an Axis Q3708-PVE. Can this

    below list camera numbers be changed to an Axis P3807-PVE or an Axis M3057-PLVE?

  • Page 7 of 14

    Camera #6 – Drawing T101A

    Camera #33 – Drawing T101C

    Camera #56 – Drawing T101E

    Camera #57 – Drawing T101E

    Camera #58 – Drawing T101E

    Camera #59 – Drawing T101E

    Camera #60 – Drawing T101E

    Camera #73 – Drawing T101F

    Camera #85 – Drawing T101G

    Camera #96 – Drawing T102A

    Camera #113 – Drawing T102G

    a. Answer: The ceiling mounted cameras listed can be revised to M3057-PLVE. The wall mounted

    cameras listed can be revised to P3807-PVE.

    6. Regarding the encoder/decoder, how many channels or cameras need to be displayed on the main office’s 55”

    LCD monitor as shown on drawing T512 (bottom left corner of the page)?

    a. Answer: 16 Cameras at any given time with the ability to scroll or pick specific cameras from software on demand.

    7. Are the encoders/decoders to be provide and installed by the Section 28200 Video Surveillance Systems

    vendor or Section 274100 Audio-Video Systems vendor

    a. Answer: Since there are no specific, dedicated CCTV monitors, any monitor could provide that

    functionality. We have intended the encoders/decoders be provided/installed through the IP

    Video Distribution System. Coordination between 274200 and 282000 will be required for

    this.

    8. Section 28200-6 paragraph I. states “Provide ceiling or wall mount TV bracket to support flat screen LCD

    TV’s as indicated on drawings. These TV’s shall be fed directly by dedicated cable. Contractor shall provide

    LCD TV’s and coordinate placement with owners representative” Please confirm the equipment schedule

    listed on drawing T513 shall be provided and installed by Section 28200 – Video Surveillance System vendor

    or the Section 27410 Audio-Video Systems vendor.

    a. Answer: Division 282000 does not need to provide the display or display mount. Those items will be provided as part of Division 27.

    9. Are the rack mounted UPS’s being provided and installed by Section 270500 Common Work Results for

    Communications vendor or Section 282000 Video Surveillance System vendor

    a. Answer: 282000 Contractor shall provide/install the UPS for the CCTV headend cabinet. All other UPS equipment in telecom rooms shall be provided/installed by Div 270500 Contractor. CCTV NVRs

    in telecom rooms shall be connected to UPS equipment provided by Div 270500 contractor.

    10. The bid form in CSD Middle School Specifications Volume 1 on page 40 of 480 does not list a “Contract #”

    for section 28200 Video Surveillance System. Could you please update this document or indicate which of the

    21 current contract numbers should be used for the Video Surveillance System?

    a. Answer: To be provided by Contract A-17 Electrical; see revisions to Alternates section.

    11. The bid form in CSD Middle School Specifications Volume 1 on page 40 of 480 does not list a “Contract #”

    for Section 270500 Common Work Results for Communications. Could you please update this document or

    indicate which of the 21 current contract numbers should be used for the Common Work Results for

    Communication.

    a. Answer: See Item A in contracts A-17, A-19, A-20 & A-21.

  • Page 8 of 14

    12. Section 282000-5 and 282000-6 under paragraph D. lists ExacqVision Professional VMS. Please confirm

    Capital School District is using professional or enterprise for their existing ExacqVision VMS solutions.

    a. Answer:Confirmed.

    13. Is the performance bond and payment bond required to be submitted on bid day (Jan. 27th)?

    a. Answer: Performance and payment bonds are not required on bid day; only a bid bond is required by the Prime Contractor for the contract they are bidding.

    .

    14. Section 282000-6 Paragraph F. CCTV Cameras:

    Interior camera shall be an Axis M3044. This camera has been discontinued by Axis. Axis website is

    recommending an Axis M3064-V has the replacement part number. Please confirm the part number which

    will replace the Axis M3044.

    a. Answer: Correct, the Axis M3044 should be replaced with the newer model Axis M3064-V.

    Exterior units shall be an Axis M3026 – This camera is being used both interior and exterior. In addition, the

    M3026 has also been discontinued and suggested replacement camera is an Axis M3206LVE. Please confirm

    the part number which will replace the Axis M3026

    a. Answer. Correct, the Axis M3026 should be replaced with the newer model Axis M320LVE.

    15. Section 282000 CCTV Camera Schedule shows Camera #5 as a P3717-PLE. Please confirm this is incorrect

    and this camera should be a Q3708-PVE

    a. Answer: Correct, Camera #5 should be a Q3708-PVE.

    RFI 26

    1. Currently all the masonry caulking (Masonry control joints, cast stone, etc.) is in the scope of work under

    contract #A-12 Caulking/Painting. Can all the masonry caulking be put in contract #A-3 Masonry work

    making the mason contractor responsible for all caulking of masonry to coincide with the other contracts 1.e.

    A-1 Site work, A-2 Concrete work, A-6 Roofing, A-8 Aluminum Storefront windows/Glass & Glazing, A-15

    Mechanical, etc.?

    a. Answer: See revisions to Contract A-3 Masonry Summary of Work & Contract A-12 Painting/Caulking

    Summary of work in this addendum.

    .

    2. Will caulking be required ate the bottom of the HM frames to hard finish floor surfaces? If yes under what

    contract will this be required?

    a. Answer: Contract 12 Caulking/ Painting if required.

    .

    3. C-901 shows control joints in the sidewalks to be saw cut fill with caulk. Will all control joints in the

    sidewalk/loading area require caulk?

    a. Answer: . Standard sidewalks less than 10’ in width will not require saw cuts to be filled with sealant. Control and Expansion joints in the rear loading area slab and any other large width area slabs will

    require sealant.

    4. C-901

    a. Answer: See sheet C-901 issued by this addendum. Expansion joints at sidewalk to curb connection will not require sealant. Expansion joints at the loading ramp trench drain shall

    require sealant.

    5. Detail 5 on S301 slab/control joint shows fill groove with semi-rigid sealant. Will all slab/control joints

    require sealant or just the joints in areas with exposed concrete?

    a. Answer: All.

  • Page 9 of 14

    6. Detail 5 on S301 slab/control joint show semi-rigid. This sealnt is recommended for use in industrial concrete

    floors that are subject to hard wheel equipment. If theses joints require sealnt can traffic grade urethane listed

    in spec 079200 be used?

    a. Answer: Yes.

    7. Details 6 on S301 lso. Jt @ col., and Details 3, 10, 11, 12, & 13 shows sealant. Will all these joints require

    sealant or just the iso. Joints in areas with exposed concrete?

    a. Answer: All.

    8. Will caulking be required at the vertical joints where the cementitious wall panels meet the masonry? If yes

    under what contract will it be required ? If yes, please provide a detail.

    a. Answer: No.

    9. Will the top of the stair stringers to the wall require caulk? If yes under what contract?

    a. Answer: No.

    10. Will the bottom/underside of the stair stringers to the wall require caulk? If yes under what contract?

    a. Answer: No.

    .

    11. Details 2 & 9 on A507 show control joint typical at masonry wings at steel columns. Will a control joint be

    required at both sides of the masonry wrap? See pictures.

    a. Answer: . Per A004, note 11, “Provide control joints in masonry wall as indicated on plans, elevations and details, and as specified. Where joints are not shown, provide according to B.I.A. and N.C.M.A. Tek

    notes.” Typically, provide control joints between CMU chases and adjoining construction.

    12. Soffit details 11 & 12 on A511 & 12 shows sealant and backer rod on all sides. All sealants at the soffit will

    be the responsibility of the installer, correct?

    a. Answer: Correct

    13. Soffit detail 04 on A529 shows sealant and backer rod at the soffit to the steel beam. All sealants ate the soffit

    will be the responsibility of the installer, correct?

    a. Answer: Correct

    14. Detail 4 on A524 will the steel angle to tube steel and steel angle to masonry in exposed areas require caulk. If

    yes under what contract?

    a. Answer: Yes. In Contract 12 Caulking/ Painting..

    RFI 27

    1. Section 7/S302 calls for #4 x 6'-0" @ 16" over beams AND girders in the SOMD. We are used to seeing these

    bars over girders only. Can we get verification that rebar over beams is actually what the engineer wants? If

    bars ARE required over beams, can we provide the steel in that direction as continuous? The 6'-0" bars would

    actually overlap at each end. Supplying these bars as continuous would be much easier to install (which would

    save some $$$), and would require less rebar to be fabricated and delivered (which would also save some

    $$$).

    a. Answer: Reinforcement is only required at girders unless there is a change of deck direction over a beam (this requires reinforcement above the beam also).

    2. I can’t find any rebar details for Storage Bldg Fdn (dwg A422).

    a. Answer: The foundation design for the storage building is delegated design.

  • Page 10 of 14

    3. I can't find any rebar details for Courtyard Seat Walls (dwg A421). Any help you can provide would be

    appreciated

    a. Answer: Courtyard seat wall reinforcement clarification will be issued by future addendum.

    RFI 28

    1. “52” was added to our Vertex product and the 52 number is also included on other potential product

    offerings. What is the significance of the number 52, if any?

    a. Answer: Referred to 52 oz. face weight. Project specification has been modified by this addendum.

    2. Is there a specific infill weight? Example 6lbs per square ft. etc

    a. Answer: 6 lb/sf minimum specified

    RFI 29

    1. Good afternoon. I have a question on something I found in the specs for this job. Under section 072119.19

    Polyurethane Foam Insulation, it has a section that describes the Air/Vapor barriers, it calls out in that section

    that all air/vapor barriers must be installed by a certified and licensed installer, and all workers installing the

    air/vapor barriers must also be certified. I wanted to see if you could clarify this or get an RFI in asking the

    question of does this include under slab vapor retarder. The section says it includes under slab vapor barriers.

    However in the 033000 section no such requirement is shown. I have never heard of needing to be certified to

    install poly, but nothing surprises me much anymore. Feel free to contact me with any questions or concerns.

    Also what is the last day to ask questions and get an official response.

    a. Answer: Underslab vapor barriers are part of Section 033000 and are not part of Section 072119.19, therefore qualifications shall be per the section associated with the work. Underslab vapor barriers

    are noted in paragraph 1.2.B.1 as a related requirement to help point contractor to other work that

    relates to this section.

    RFI 30

    1. I see that vinyl wall graphics is listed in the Caulking/Painting Contract #12 scope of work. I just want to

    make sure that this is correct and that Caulking/Painting Contract #12 is to supply and install the vinyl

    graphics? Scope of Work Item P states vinyl graphics on walls and glass. I do not see any graphics for glass. Is

    there any vinyl graphics for glass on this project?

    a. Answer: Contract 12 Caulking/ Painting is responsible, see added specification section in Summary of

    work in this addendum.

    RFI 31

    1. SOW calls for provide exterior bleachers and foundations complete. Per sheet C-906 these bleachers set on an

    8” slab. Please confirm this slab is by concrete cont

    a. Answer: Contract 1 Site Work is responsible for concrete pad for bleachers; Contract 5 Carpentry & General Work is responsible for bleachers as shown on Sheet C-906.

    RFI 32

    1. Please review SOW Contract No. 9, item B, P, S, and V along with SOW Contract No. 3, item D. SprayFoam

    insulation should be under 1 contract along with the Liquid Applied Air Barrier for the entire project.. These

    will be performed by an ABAA approved Subcontractor who will want to work with a single Prime

    Contractor. Please review scope of Mason & Drywall

    a. Answer: See revisions to Summary of Work in this addendum for Contract 3 Masonry and Contract 9

  • Page 11 of 14

    Drywall/Metal Stud.

    2 Page A001 Exterior wall types 7D, 7G, and 7J call for different types of insulation behind CWP. I believe it

    should all be the 3” Mineral Wool to meet NFPA 285

    a. Answer: Details are correct as is.

    3. Please have Architect re-issue A206 showing entire elevation inclusive of Area C, D, E there is Metal Wall

    Panels in this area on the roof.

    a. Answer: Elevations for Areas C, D and E are shown on A203, A204, A205 and on building sections.

    4. Contract No.18: Metal Wall Panels should include all MWP, Subgirt framing, 3” Mineral Wool, Flashing,

    Connections Sealants and Accessories. These are usually engineered systems.

    a. Answer: See revisions to Summary of Work in this addendum for Contract 18 Wall Panels.

    Contract No. 18: Cementitious Panels should include all CWP, Subgirt framing, 3” Mineral Wool, Flashing,

    Connections Sealants and Accessories. These are usually engineered systems

    a. Answer: See revisions to Summary of Work in this addendum for Contract 18 Wall Panels.

    Contract No. 18: Is there a spec for the Subgirt Systems??

    a. Answer: See Section 070543-Cladding Support Systems.

    5. Should there be an allowance for Drywall Contract, Acoustical Contract, Wall Panel Contract????

    a. Answer: No additional allowances are being added.

    RFI 33

    1. Spec 098433:: AP-1 is not called out on plans, nor are there any 36 in. x 36 in. panels on the plans. Please

    clarify.

    a. Answer: See revised Section 098433, and revisions to A704, issued by this addendum.

    Spec 098433:AP-2, 3, & 5 Wall Panels in music room are not listed.

    a. Answer: See revised Section 098433, and revisions to A704, issued by this addendum.

    Spec 098433: Pyramidal Wall Panels in music are not listed.

    a. Answer: See revised Section 098433, and revisions to A704, issued by this addendum.

    2 Plans call out Stretch Fabric on walls of Auditorium. Please clarify if this is AP-1 or provide Stretch Fabric

    Specification.

    a. Answer :Section 098400-ACOUSTICAL WALL SYSTEMS is added by this addendum.

    RFI 34

    1. Note 14 Concrete on S100 calls for joint sealant in both formed (construction joints) which is normal and saw cuts which is unusual. Is that the intent?

    a. Answer: Provide joint sealant in all construction joints. Provide joint sealant as required by floor finish in saw cut joints. RFI 35

    1. ERV Units (12):

    Equipment section 2.29 (230000-30): Are the ERV units a Packaged unit with controls?

    a. Answer: ERV units are hydronic with field-installed controls by the ATAC Subcontractor.

  • Page 12 of 14

    Equipment section 2.29 (230000-30): If packaged unit, do the field devices get wired back the package unit

    controller or to a BAS controller? Demand Control Ventilation Section C items 3 a. & b. (230000-32) VFD:

    a. Answer: N/A.

    Demand Control Ventilation Section C items 3 a. & b. (230000-32) VFD:: Spec indicates SF & EX fan VFD

    with units – ok Are the VFD controls BACnet or through BAS?

    a. Answer: VFD’s may be factory furnished or field installed but must meet the specification requirements in Section 230000.

    Demand Control Ventilation Section C items 3 d. (230000-32) Dampers:: Spec indicates all motor operated

    dampers and actuators provided with unit. M203 shows dampers in duct. Which is correct?

    a. Answer: All dampers/actuators shall be furnished by the ATAC Subcontractor and installed by the Sheet Metal Contractor in Ductwork.

    Demand Control Ventilation Dampers Section C items 3 e. (230000-32) Air Flow Monitoring stations: Spec

    indicates outside air flow monitoring station provided with unit. M203 shows OA and Relief flow stations in

    duct. Which is correct?

    a. Answer: The Airflow Monitoring Stations shall be duct mounted as indicated. Mechanical Contractor to determine whose scope they are in.

    Duel Temperature Control Valve Drawing M403: • Valve V1 shown on M403 Who provides valve BAS or

    MC with unit? Controls to unit controller or BAS controller?

    a. Answer: Valves are to be provided by ATC Subcontractor and Controls by BAS controller.

    2. Single Zone VAV Units (SZVAV) (3):

    Equipment Section 2.36 item A. Single Zone VAV Units: Specs call for a packaged unit, does this include

    BACnet? Does the field devices get wired back the package unit controller or to a BAS controller?

    a. Answer: Specs for a packaged unit do include BACnet, and field devices get wired back to a BAS controller

    Equipment Section 2.36 item B 8. Fans • Specs state dampers internal with unit, furnished with unit. • M202

    drawings show dampers in duct work. Which is correct?

    a. Answer: All dampers/actuators shall be furnished by the ATC Subcontractor and installed by the Sheet Metal Contractor in Ductwork.

    Equipment Section 2.36 VFD: • Spec indicates SF & EX fan VFD with units – ok Are the VFD controls

    BACnet or through BAS

    a. Answer: VFD’s may be factory furnished or field installed but must meet the specification requirements in Section 230000.

    Equipment Section 2.36 item G 2 (230000-51) • Specs state Outside Air Flow Station furnished and installed

    by contractor. M202 Drawing shows five (5) air flow stations in duct work. Is the Outside Air Flow Station

    furnished with unit? Are the four other Air Flow Station required?

    a. Answer: The Airflow Monitoring Stations shall be duct mounted as indicated. Mechanical Contractor to determine whose scope they are in.

    Equipment Section 2.36 Head Pressure Control Valve V1: • Valve V1 not listed in Specs Head Pressure

    Control Valve V1 shown on drawing M404 Is the valve provided with unit?

    a. Answer: Pressure Independent Head Pressure Control Valves shall be furnished by the ATC Subcontractor and installed by the Mechanical Contractor.

  • Page 13 of 14

    3. Water to Air Heat Pumps (230000-52) (170):

    Specs do not identify if filed devices shown on drawing M407 are furnished with each unit. Just to verify…

    Who will provide filed devices (DAT, DP, CS, etc.) BAS or MC?

    a. Answer: All field-installed control devices shall be furnished and installed by the ATC Subcontractor.

    2-way Modulating Head Pressure Valve V1 Will the valve V1 (170 units) be provided with equipment?

    Include Trim wiring?

    a. Answer: Pressure Independent Head Pressure Control Valves shall be furnished by the ATC

    Subcontractor and installed in piping by the Mechanical Contractor.

    Modulating Hot Gas Solenoid Valves 2-per unit Will the valves (2 per unit) be provided with equipment?

    Include trim wiring?

    a. Answer: Yes and yes.

    Flow Switch (Thermal Dispersion Type) Will the FS be provided with equipment? Include trim wiring?

    a. Answer: FS will not be provided with equipment. Thermal Dispersion Flow Switch and wiring shall be provided and installed by the ATC Subcontractor.

    4. Vales:

    Can Belimo be added an acceptable manufacture for all types control and Pressure Independent valves?

    a. Answer: Yes.

    5. Flow Meter Fitting (FMF) (20):

    No info on these items – just to clarify provided by MC (?).

    a. Answer: Individual Flow Meters are specified in Section 230524 under Article 2.12-Flow Meters. However, per details, all control valves serving equipment shall also be provided with integral flow

    meters.

    RFI 36

    1. Please provide details of game lines required on RAF flooring a. Answer: Patterns and game lines will be removed from Section 096566 by this addendum.

    RFI 37

    1. Which contract is responsible for the LAP-6 listed in specification. Some of these are light units. a. Answer: LAP -6 is to be provided by Contract A-10 Acoustical Work, final electrical connections are to be by Contract 17 Electrical.

    RFI 38

    1. The specs section 1.2 A. 3. asks to ‘’Provide up to 24’’ chair sizes as designated on the contract drawings’’. Unfortunately, the drawings do not indicated the widths of each individual seats. Please clarify.

    a. Answer: A seating plan showing the sizes will be issued by this addendum.

    END OF ADDENDUM NO. TWO

  • Page 14 of 14

    Attachments: Specification Section 098400-ACOUSTICAL WALL SYSTEMS

    Specification Section 098413-SOUND-ABSORBING WALL UNITS

    Specification Section 265501- STAGE LIGHING SYSTEMS

    Specification Section 274100-AUDIO-VIDEO SYSTEMS

    Specification Section 321813-SYNTHETIC GRASS SURFACING

    Becker Morgan Group, Inc. drawings C300, C901, A001, A101A, A101B, A101C, A101F, A101G,

    A102G, A407, A420, A421, A546 and A701

    ESP drawing T504

    Richard Y. Johnson & Son, Inc Addendum No. 2, dated 01/15/2021.

    201918000_Addendum2.doc

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    ACOUSTICAL WALL SYSTEMS 098400 - 1

    SECTION 098400 - ACOUSTICAL WALL SYSTEMS

    PART 1 GENERAL

    1.01 SUMMARY:

    A. Section Includes:

    Site-fabricated acoustical fabric wall system consisting of fabric stretched over an acoustical or tackable core by

    means of rigid polymer extrusions of varying profiles and sizes, as shown in auditorium.

    1.02 SUBMITTALS:

    A. Product Data:

    Submit manufacturer's product specifications including certified laboratory test reports and other data as

    required to show compliance with the application.

    B. Samples:

    Provide 12" x 12" samples of fabrics, core, and representative samples of rigid polymer mounting devices.

    C. Certified Test Reports:

    Submit test data from an independent testing agency, acceptable to authorities having jurisdiction, evidencing

    that the systems components comply with requirements indicated for fire and toxicity performance

    characteristics.

    1.03 QUALITY ASSURANCE:

    A. Fire hazard Classification: All fabrics, cores and mounting devices shall pass ASTM E84, Class A for flame

    spread and smoke.

    Smoke developed Index: 5

    Flame spread Index: 10 "Class 0-25" (Class A)

    B. Minimum Noise Reduction Coefficient (NRC) of 0.80 with a 1" system and Acoustitherm 600 fiberglass core,

    per ASTM C423.

    C. Installer Qualifications: Installation shall be performed by an authorized entity licensed and trained for

    manufacturer.

    D. Prefabricated panels are not acceptable for this specification.

    1.04 DELIVERY, STORAGE AND HANDLING:

    A. Protect system components from excessive moisture in shipment, storage, and handling. Deliver in unopened

    bundles and store in a dry area with adequate air circulation. Do not deliver material to building until all "wet

    conditions" such as concrete, plaster, paint, and adhesives have been completed and cured to a condition of

    equilibrium.

    1.05 PROJECT CONDITIONS:

    A. Do not install acoustical wall or ceiling system until space has been enclosed and is weathertight, and until

    other finishes and wet-work in the space have been completed and are nominally dry, and until ambient

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    ACOUSTICAL WALL SYSTEMS 098400 - 2

    conditions of temperature and humidity will be continuously maintained at values near those indicated for final

    occupancy.

    1.06 EXTRA MATERIALS:

    A. Deliver extra materials to Owner. Furnish extra materials described below matching products installed,

    packaged with protective covering for storage and identified with appropriate labels. General Contractor is

    responsible to coordinate turn-in with Board of Education Maintenance.

    1. Fabric: Before installation begins, furnish quantity of full-width units equal to 5.0% of amount installed.

    1.07 PRODUCT DRAWINGS:

    A. Installation company shall submit a finish schedule, typical elevations, and details to the Architect and the

    General Contractor, as required.

    PART 2 - PRODUCTS

    2.01 MANUFACTURERS

    A. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work

    include, but are not limited to, those indicated by Whisper Walls, Aurora, CO.

    2.02 SYSTEM DESCRIPTION:

    A. Complete stretched fabric acoustical or tackable fabric system including anchoring and consisting of fabrics

    field applied over core material and mounted securely by continuous one-piece perimeter, midwall, inside

    corner, and outside corner polymer extrusions, while allowing for fabric removal and replacement without the

    removal of the means of attachment or disturbing adjacent panels.

    B. Include required accessories as detailed or specified.

    2.03 MATERIALS:

    A. Fabrics:

    1. Manufacturer’s brand fabrics; colors and patterns as selected by the Architect.

    B. Core Material:

    1. Standard system consisting of 1" Acoustitherm 600 fiberglass core or thickness and density as indicated.

    Other densities and configurations available including dual density cores and airspaces.

    2. Facing fabric is not to be adhesive-applied to acoustical/tackable core. Acceptable systems will stretch

    facing fabric over acoustical/tackable core material, leaving fabric independent from core surface to permit

    tack holes to close when tacks are removed.

    C. Fabric Mounting System: Standard in 1" thickness

    1. One-piece perimeter extrusions with edges selectively covered to create a welting in bevel, square and

    radius conditions.

    2. One-piece midwall extrusions in bevel, square, radius, or integral reveal with conditions installed

    vertically, horizontally, diagonally or using free-form curves.

    3. Corners: 90o one-piece inside

    90o one-piece outside creating a seamed or no seam corner

    4. Anchoring System:

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    ACOUSTICAL WALL SYSTEMS 098400 - 3

    a. Manufacturer’s stapler that has the ability to mechanically diverge staples for securely attaching

    extrusions to drywall with 18 gage wire size.

    b. Standard fasteners recommended by the manufacturer to securely fasten extrusions

    to substrates other than drywall.

    PART 3 - EXECUTION

    3.01 DELIVERY STORAGE AND EXAMINATION:

    A. Examine the condition of the substrate and the conditions under which the work of this Section is to be

    performed. Notify the Contractor in writing of any unsatisfactory conditions. Do not proceed with the work

    until unsatisfactory conditions have been corrected in a manner satisfactory to the Installer.

    B. Field measure each wall area which is to receive the stretched fabric system to establish correct layout.

    3.02 INSTALLATION:

    A. Install materials in accordance with the manufacturer's instructions and complying with governing regulations,

    fire resistance rating requirements indicated and industry standards applicable to the work.

    B. Fasten the rigid polymer extrusions to the surfaces which are to receive the treatment. Secure with

    Manufacturer’s mechanical diverging stapler using 1 inch 18 gage staples spaced on 2 inch centers.

    C. Install rigid polymer extrusions plumb and straight, flush, and in proper alignment.

    D. Install the core material required, continuous and flush, to the shoulder of the track and secure in place with

    recommended fasteners.

    E. Cut the fabric from each roll maintaining sequence of drops and matching direction of weave for sequential and

    uniform installation.

    F. Stretch the fabric and secure into the locking jaws of the extrusions so that it will be smooth, free of wrinkles

    and the weave straight and parallel to perimeter anchors, plumb, and aligned horizontally and vertically.

    Gluing or stapling of fabric will not be acceptable for this work.

    G. Examine fabric as it is installed for damage, imperfections, poor color match, or other deficiencies. Replace

    with acceptable material as directed by the Architect.

    3.03 CLEANING AND PROTECTION:

    A. Clean exposed surfaces of acoustical wall system, comply with manufacturer's instructions for cleaning and

    repair of minor finish damage. Remove and replace work which cannot be successfully cleaned and repaired to

    permanently eliminate evidence of damage.

    B. The Installer shall advise the Contractor of required protection for the System, including temperature, humidity

    limitations, and dust control, so that the work will be without damage and deterioration at the time of

    acceptance by the Owner.

    END OF SECTION 098400

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    SOUND-ABSORBING WALL UNITS 098433-1

    SECTION 098433 – SOUND-ABSORBING WALL UNITS

    PART 1 - GENERAL

    1.1 RELATED DOCUMENTS

    A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

    1.2 SUMMARY

    A. This Section includes the following:

    a. Fabric-wrapped sound-absorbing and sound-diffusing acoustical panels of size and shape indicated.

    1.3 SUBMITTALS

    A. Product Data: For each type of product indicated.

    B. Shop Drawings: Show fabrication and installation details for acoustical wall panels, including plans, elevations, sections, details, and attachments to other Work.

    C. Samples for Initial Selection: Manufacturer's color charts showing the standard range of colors, textures, and patterns available for facing materials for each type of acoustical wall panel indicated. Include

    samples of installation devices and accessories.

    D. Samples for Verification: 8-by-11-inch (200-by-280-mm) units of each type of acoustical wall panel indicated; in sets for each color, texture, and pattern specified for facing materials, showing the full range

    of variations expected in these characteristics. Include samples of installation devices and accessories.

    E. Product Certificates: Signed by manufacturers of acoustical wall panels certifying that products furnished comply with requirements.

    F. Qualification Data: For firms and persons specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names

    and addresses of architects and owners, and other information specified.

    G. Product Test Reports: From a qualified testing agency indicating acoustical wall panels comply with requirements, based on comprehensive testing of current products.

    H. Maintenance Data: For acoustical wall panels and facings to include in maintenance manuals specified in Division 1.

    1.4 QUALITY ASSURANCE

    A. Manufacturer Qualifications: A firm experienced in manufacturing acoustical wall panels similar to those indicated for this Project and with a record of successful in-service performance.

    B. Testing Agency Qualifications: An independent testing agency, acceptable to authorities having jurisdiction, with the experience and capability to conduct the testing indicated, as documented according

    to ASTM E 548.

    C. Source Limitations for Acoustical Wall Panels: Obtain acoustical wall panels from one source with resources to provide products of consistent quality in appearance and physical properties.

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    SOUND-ABSORBING WALL UNITS 098433-2

    D. Fire-Test-Response Characteristics: Provide acoustical wall panels with the following surface-burning characteristics as determined by testing identical products per ASTM E 84 by UL or another testing and

    inspecting agency acceptable to authorities having jurisdiction. Identify acoustical wall panels with

    appropriate markings of applicable testing and inspecting agency.

    a. Flame Spread: 25 or less. b. Smoke Developed: 450 or less.

    1.5 DELIVERY, STORAGE, AND HANDLING

    A. Protect acoustical wall panels from excessive moisture when shipping, storing, and handling. Deliver in unopened bundles and store in a dry place with adequate air circulation. Do not deliver material to

    building until wet-work, such as concrete and plaster, has been completed and cured to a condition of

    equilibrium. Protect panel edges from crushing and impact.

    B. Factory finish and assemble all components before shipment.

    1.6 PROJECT CONDITIONS

    A. Environmental Limitations: Do not install acoustical wall panels until construction in spaces is complete and ambient temperature and humidity conditions are maintained at the levels indicated for Project when

    occupied for its intended use.

    B. Air-Quality Limitations: Protect acoustical wall panels from exposure to airborne odors, such as tobacco smoke, and install panels under conditions free from odor contamination of ambient air.

    C. Field Measurements: Verify wall surface dimensions by field measurements before fabrication and indicate measurements on Shop Drawings. Coordinate fabrication schedule with construction progress to

    avoid delaying the Work.

    a. Established Dimensions: Where field measurements cannot be made without delaying the Work, establish surface dimensions and proceed with fabricating acoustical wall panels without field

    measurements. Coordinate wall construction to ensure that actual surface dimensions correspond

    to established dimensions.

    1.7 WARRANTY

    A. General Warranty: Special warranty specified in this Article shall not deprive Owner of other rights Owner may have under other provisions of the Contract Documents and shall be in addition to, and run

    concurrent with, other warranties made by Contractor under requirements of the Contract Documents.

    B. Special Warranty: Written warranty, signed by manufacturer agreeing to repair or replace components of acoustical wall panel system that fail in performance, materials, or workmanship within specified

    warranty period. Failure in performance includes, but is not limited to, acoustical performance. Failure

    in materials includes, but is not limited to, sagging or distortion of facing or warping of core.

    C. Warranty Period: Three years from date of Substantial Completion.

    PART 2 - PRODUCTS

    2.1 MANUFACTURERS

    A. In other Part 2 articles where titles below introduce lists, the following requirements apply to product selection:

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    SOUND-ABSORBING WALL UNITS 098433-3

    1. Basis-of-Design Product: The design for each commercial appliance is based on the product

    names. Subject to compliance with requirements, provide either the named product or a

    comparable product by one of the other manufacturers specified.

    2.2 FABRIC-WRAPPED ACOUSTICAL PANELS (AP-#)

    A. Fabric-wrapped Sound Absorptive Panels (AP-1) in Music D131 and Music D132.

    1. Basis-of-Design: Subject to compliance with requirements, provide product by CONWED

    Designscape, Div. of Owen’s Corning or comparable product by one of the following:

    a. Wenger Corporation. b. Golterman & Sabo.

    2. Absorber Panels: Manufacturer’s standard high impact resistant construction consisting of 2” thick, 6-7 pcf dimensionally stable glass fiber core with foil backing (no exposed fiberglass) faced

    with 1/8” high impact resistant, 16-20 pcf molded glass fiber board.

    a. Edge: Wood hardened edge detail with half bevel finish. b. Corners: Square. c. Finish: Class A rated fabric according to ASTM E-84, fully covered back. d. NRC: ASTM C423: 1.00-1.10

    3. Sound-Absorption Performance: Provide acoustical wall panels with minimum noise reduction coefficients indicated, as determined by testing per ASTM C 423 for mounting type specified.

    4. Mounting Accessories: Manufacturer's standard or recommended accessories for securely mounting panels to substrates.

    a. Mounting: Z-Clips

    5. Finishes:

    a. Wall-mounted panels: Manufacturer's woven plain weave 100% polyester 2-ply fabric wrap-ping entire core and frame and glued to back of frame. Up to four colors may be selected.

    6. Sizes: As indicated on drawings:

    a. 2’ x 4’

    b. 4’ x 4’

    c. 4’ x full length, including wrapping of columns and chases.

    7. Locations: As indicated on drawings.

    8. Selections not identified on color schedule will be made from manufacturer’s full range of fabrics

    and colors.

    B. Fabric-wrapped Sound Diffuser Panels (AP-2) in Music D131 and Music D132

    1. Basis-of-Design: Subject to compliance with requirements, provide product by Armstrong or

    comparable product by one of the following:

    a. Wenger Corporation. b. Golterman & Sabo.

    5. Diffuser Panels: Manufacturer’s standard high impact resistant construction consisting of dimensionally stable fiber reinforced plastic core faced with fabric.

    a. Shape: Pyramidal. b. Finish: Class A rated fabric according to ASTM E-84.

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    SOUND-ABSORBING WALL UNITS 098433-4

    c. NRC: ASTM C423: .10 - .15

    6. Mounting Accessories: Manufacturer's standard or recommended accessories for securely mounting panels to substrates.

    a. Mounting: Z-Clips

    5. Finishes:

    b. Wall-mounted panels: Manufacturer's woven plain weave 100% polyester 2-ply fabric wrap-ping entire core and frame and glued to back of frame. Up to three colors may be selected.

    6. Sizes: As indicated on drawings:

    a. 2’ x 2’

    b. 2’ x 4’

    c. 4’ x 4’

    7. Locations: As indicated on drawings.

    8. Selections not identified on color schedule will be made from manufacturer’s full range of fabrics

    and colors.

    PART 3 – EXECUTION

    3.1 EXAMINATION

    A. Examine substrates and blocking, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting acoustical wall panel performance. Proceed with installation

    only after unsatisfactory conditions have been corrected.

    3.2 INSTALLATION

    A. Install acoustical wall panels in locations indicated with vertical surfaces and edges plumb, top edges level and in alignment with other panels, and scribed to fit adjoining work accurately at borders and at

    penetrations. Comply with panel manufacturer's written instructions for installation of panels using type

    of mounting accessories indicated or, if not indicated, as recommended by manufacturer. B. Construction Tolerances: As follows:

    1. Variation from Plumb and Level: Plus or minus 1/16 inch (1.6 mm).

    2. Variation of Joints from Hairline: Not more than 1/16 inch (1.6 mm).

    3.3 CLEANING

    A. Clip loose threads; remove pills and extraneous materials.

    B. Clean panels with fabric facing, on completion of installation, to remove dust and other foreign materials

    according to manufacturer’s written instructions.

    C. Remove surplus materials, rubbish, and debris resulting from acoustical wall panel installation, on

    completion of the Work, and leave areas of installation in a neat and clean condition.

    3.4 PROTECTION

    A. Provide final protection and maintain conditions, in a manner acceptable to manufacturer and Installer

    that ensure acoustical wall panels are without damage or deterioration at time of Substantial Completion.

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    SOUND-ABSORBING WALL UNITS 098433-5

    B. Replace panels that cannot be cleaned and repaired, in a manner approved by Architect, before time of

    Substantial Completion.

    END OF SECTION 098433

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    STAGE LIGHTING SYSTEMS 265501 - 1

    SECTION 26 55 01 - STAGE LIGHTING SYSTEMS

    PART 1 - GENERAL

    1.1 RELATED DOCUMENTS

    A. Drawings and general provisions of Contract, including General and Supplementary Conditions, Special Conditions, Division 1 Specification sections, and section 11 61 33 (Stage Rigging and

    Draperies) apply to work specified in this section.

    1.2 RELATED WORK AND REQUIREMENTS

    A. Section 26 00 00

    1.3 SCOPE

    A. This section requires the fabrication, furnishing, delivery, installation and testing of the lighting system as indicated on the drawings and specified herein.

    B. The contractor shall provide all materials, equipment, labor, tools, scaffolds, and incidentals necessary to perform the scope of work.

    C. It is the intention of these specifications that the contractor provides a professional quality, complete and properly operating system in every respect and detail.

    D. The installation contractor shall examine the plans in detail to familiarize themselves with the scope of the work. Special attention shall be paid to reviewing all project electrical drawings, floor plans,

    conduit risers, and the like for locations and quantities of boxes and enclosures.

    E. The contractor shall assume full responsibility for a complete operating installation, in the required location, in accordance with the contract documents.

    F. Coordinate fully with the Division 26 Contractor.

    G. Definitions: For this project, the following entities are referenced:

    1. Owner: Dover Central School District, Dover

    2. Architect: Becker Morgan Group, Dover, DE

    3. Theatre Consultant: Scheu Consulting Services, Inc., Fayetteville, NY

    4. The Contractor: The contractor or sub-contractor performing the work. The contractor shall be qualified per Part 1.6 of these specifications.

    1.4 WORK INCLUDED

    A. Without restricting volume or generality of above “Scope,” work to be performed under this section shall include, but not be limited to, the furnishing and installation of the following:

    1. Auditorium and Stage

    a. A computer controlled dimming system with approximately 48 each ”smart” breaker stage lighting relay circuits. The design shall incorporate a rear of house Tech Gallery position over

    the control booth, two balcony rail positions, four on stage lighting battens, four onstage

    plugging boxes, two apron face plugging boxes, and two concert ceilings. A certified stage

    lighting network with network receptacles that shall be located at each of the previously listed

    lighting positions. There shall be two LED follow spotlights. The stage lighting system

    consists of the relay panels and racks, auxiliary rack, network switch and patch bay, circuit

    distribution raceways, wire, DMX-512 computer-based stage lighting console, video display,

    console plug-in stations, a backstage control panel, a mix of LED, and moving stage lighting

    fixtures, cables, accessories and spares. The system infrastructure shall be network based.

    b. A separate house lighting dimmer rack with up to12 relay circuits shall be included. House Lighting Control shall consist of a backstage control station, a portable touch screen control

    booth control station, a control booth entry station and entry stations located at the auditorium

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    STAGE LIGHTING SYSTEMS 265501 - 2

    exits.

    c. An Emergency Lighting power and control transfer system

    2. Black Box

    a. A computer controlled dimming system with approximately 24 each ”smart” breaker stage lighting relay circuits. The design shall incorporate plugging boxes mounted to the pipe grid

    and lower side walls, The stage lighting system consists of the relay panel, DMX splitter,

    circuit distribution plug boxes, wire, DMX-512, computer-based stage lighting console,

    console plug-in stations, a wall mounted control station, a mix of LED stage lighting fixtures,

    cables, accessories and spares.

    B. The Contractor shall examine the plans in detail to familiarize themselves with the scope of work.

    C. The Contractor shall provide the required manufacturers’ shop drawings.

    D. The Contractor shall provide all the necessary specialty equipment for the complete lighting and dimming system installation as specified herein and as shown on the drawings.

    E. The Contractor shall coordinate the system control wire conduit and device locations with the Division 26 Contractor.

    F. The Contractor shall deliver to the job site, and coordinate the installation of, the specialty equipment with the Division 26 Contractor.

    G. The Contractor shall provide, install, and terminate all system control wires.

    H. The Contractor shall provide and install all system control devices.

    I. The Contractor shall uncrate, assemble, hang and aim all the stage lighting fixtures as shown on the drawings.

    J. The Contractor shall provide for the system activation.

    K. The Contractor shall provide the system manuals.

    L. The Contractor shall provide the system warranty.

    M. It is the Contractor’s responsibility to ensure that the system and all of the system components, fixtures, equipment, devices, wire, terminations, field assemblies (including custom assemblies), etc. pass all

    required inspections by the local authority having jurisdiction.

    N. Procurement of all required permits.

    1.5 WORK NOT INCLUDED

    A. The following work, although in another section, has a significant impact on the scope of this work. The Contractor is responsible for the successful coordination of the following:

    1. System conduit.

    2. Installation and termination of Line supply.

    3. Installation and termination of Load wire.

    4. Dimmer rack installation.

    5. Non-dim panel installation.

    6. Distribution installation.

    1.6 CONTRACTOR’S QUALIFICATIONS:

    A. Only qualified contractors shall be used.

    B. The work of this section shall be contracted to a single firm, referred to as the contractor.

    C. The contractor shall be a lighting system contractor who regularly engages in the furnishing, installation, and servicing of systems of similar nature, size, scope and complexity to that contemplated

    by this specification. The contractor shall have done so for a period of not less than five years preceding

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    STAGE LIGHTING SYSTEMS 265501 - 3

    the bid date.

    D. The contractor shall have maintained for the five years preceding the bid date, a suitably staffed and equipped service organization which has continuously offered maintenance and repair services for

    systems of the nature, size, scope and complexity to that contemplated by this specification.

    E. The contractor shall have on staff a factory trained field service agent, capable of system testing, commissioning, and troubleshooting systems of the nature, size, scope and complexity to that

    contemplated by this specification.

    F. The contractor shall have on staff a qualified and competent lighting designer / engineer capable of designing systems of the nature, size, scope and complexity to that contemplated by this specification.

    G. The contractor shall maintain for the duration of this contract all required business and professional licenses and insurance.

    H. The contractor shall demonstrate to the satisfaction of the owner, through submittals presented in accordance with the project timetable, that the contractor meets all the above qualifications. The

    minimum contractor qualification submittal shall include the following:

    1. Statement of company history. Include a breakdown by percentage of gross sales of all business activities the contractor is involved in for each of the last 5 years (e.g. system installation = 30%,

    expendable sales = 40%, equipment rentals = 20%, design and other professional services = 10%,

    etc).

    2. Previous experience: Furnish a list of four installations of the type and size contemplated by these specifications, currently in use as originally installed, in which a theatre / system consultant was

    involved, completed in the last 5 years and the following information regarding each installations:

    a. Name and address of each installation facility.

    b. Facility owner and telephone number.

    c. Name, address, and phone number of a person regularly employed by the owner, who is familiar with the operation of the systems and who has no connection or business connections

    with the contractor except as the contractor shall fully disclose

    d. Name, address, and phone number of the theatre / system consultant, along with the names of all the consultant’s personal directly involved.

    e. System shop drawing – These shall be returned if the contractor provides a call tag or return postage.

    f. Owner’s manual drawing – These shall be returned if the contractor provides a call tag or return postage.

    g. System as-built drawings drawing – These shall be returned if the contractor provides a call tag or return postage.

    h. List of contractors personal involved with each person’s responsibility on the project.

    i. Name, address and phone number of the general contractor, along with the names of all key GC personal directly involved.

    j. Name address and phone number of the electrical contractor, along with the names of all key EC personal directly involved.

    3. Statement of current company capabilities and ownership.

    4. Key Personal: For each of the key personnel listed in the below; Include individual’s name, title, and number of continuous years of service to contractor. Include a resume detailing industry

    experience, and role within organization (include only full-time/regular staff employees; not

    independent contractor, freelance, or temporary positions). List all industry certifications held,

    training courses attended, and continuing education credits, including dates of attendance.

    a. Project Manager

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    STAGE LIGHTING SYSTEMS 265501 - 4

    b. Senior Technician

    c. Service Manager

    5. Factory Trained Field Service Agent. Include individual’s name and title. List all factory held certifications, training courses attended, and continuing education credits, including dates of

    attendance. Provide a list of recently commissioned systems, scope of project, and commissioning

    dates.

    6. Lighting Designer / Engineer. Include individual’s name and title. List current design credits with scope of project, and design completion dates.

    7. Other Department Staff. Include size of staff and experience of each staff member.

    8. Replacement and Spare Parts Inventory – Provide detailed list of primary replacement parts, components, and spares typically held in inventory.

    9. Test Equipment and Physical Plant – Include an inventory of all test facility equipment owned and used regularly by the Service Department. Provide description of physical plant and space

    utilization.

    10. Copies of all business and professional licenses and insurance certificates.

    PART 2 - PRODUCTS

    2.1 GENERAL

    A. When this document lists several acceptable manufacturers for a particular item of equipment, more than one of which is to be provided, the Contractor shall furnish all of those similar items of equipment

    from one manufacturer.

    B. All ETC and Strand dimmer racks, dimmer modules, lighting controls and lighting consoles shall be from the same manufacturer. Lightolier dimmers many only be used with Grand MA consoles and

    Pathport network distribution.

    C. Any item of equipment or hardware that may not be specifically shown on the drawings or specified herein, but required for proper system operation or installation, shall be furnished and installed and be

    of the highest quality available.

    D. All materials and equipment used in this project shall be new, unused and of the latest models and design. Refurbished materials and equipment are not permitted except where noted.

    E. The performance of all equipment must meet the most recently published manufacture’s data sheet.

    F. UL Labels: All equipment, where applicable standards have been established, shall be listed by Underwriters’ Laboratories, Inc., and shall bear UL label when delivered to the job.

    G. If so required by the local authority having jurisdiction, anything not arriving at the job bearing a UL label shall be field inspected and labeled by a nationally recognized testing laboratory recognized and

    approved by the local authority having jurisdiction.

    2.2 ACCEPTABLE MANUFACTURERS

    A. The stage lighting and control manufacturer shall be one who has been continuously engaged in the manufacture of stage lighting control equipment, wiring devices, and electronic dimmers for ten years

    or more.

    B. Except where otherwise noted in this specification, the following are the approved manufacturers for the listed respective products:

    Altman Lighting Inc.

    57 Alexander Street

    Yonkers, NY 10701

    (914) 476-7987

    Electronic Theatre Controls, Inc.

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    STAGE LIGHTING SYSTEMS 265501 - 5

    3031 Pleasant View Rd

    Middleton, WI 53562-0979

    (800) 688-4116

    LEX Products Corp.

    401 Shippan Avenue

    Stamford, CT 06902

    (800) 643-4460

    LynTec

    8401 Melrose

    Lenexa, KA 66214

    (913) 529-2233

    Lycian Stage Lighting

    PO Box D

    Kings Hwy

    Sugar Loaf, NY 10981-0214

    (845) 469-2285

    Middle Atlantic Products, Inc.

    North Corporate Drive

    Riverdale, NJ 07457

    (973) 839-1011

    Pathway Connectivity

    Acuity Brands Lighting

    #103- 143917th Ave SE

    Calgary AB T2G1J9, Canada

    403-243-8110

    Robert Juliat USA

    48 Capital Dr.

    Wallingford, CT 06492

    (203) 294-0481

    SSRC

    11 Freedom Court

    Greer, South Carolina 29650

    (864) 848-9770

    Strand Lighting, Inc.

    267 5th Ave

    New York, NY 10016

    (212) 532-2593

    Strong Entertainment Lighting

    4350 McKinley Street

    Omaha, NE 68112

    (402) 453-4444

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    STAGE LIGHTING SYSTEMS 265501 - 6

    C. Substitutions: In no case shall equipment or materials of lesser design or workmanship be acceptable. Only those materials and equipment listed in this specification shall be considered unless prior

    approval is sought and received.

    1. When a specific piece of equipment specified has been discontinued and/or replaced by a new model, substitution shall be acceptable when:

    a. Submission of complete data on the new model or substitute has been approved by the owner prior to equipment acquisition.

    b. Substitute equipment or the replacement of rejected equipment shall be at the sole expense of the contractor.

    2. Substitutes shall be considered only when they are submitted fourteen days prior to bid date, and shall be accompanied by sufficient catalog data, specifications, and technical information for

    evaluation.

    a. Summarize proposal with a list of equipment catalog or series numbers. Substitute bids shall include a system riser diagram detailing the components and any deviation of functionality

    from the drawings and specifications herein.

    b. The bidder shall include the name, address, and phone number of at least two- (2) factory authorized Field Warranty centers within a 250-mile radius of the job site as a part of the

    submittal documents.

    c. On the lighting fixtures, the bidder submitting other equipment shall include performance data taken and reported in compliance with the “Recommended Practice for Reporting

    Photometric Performance of Incandescent Filament Lighting Units used in Theatre and

    Television Production,” approved as the official standard by the U.S. Institute for Theatre

    Technology, the Illuminating Engineering Society, the Society of Motion Picture and

    Television Engineers, and the American Theatre Association. For purposes of establishing

    the validity of such submissions, the manufacturer shall furnish this data from an independent

    testing laboratory. Proposals that fail to meet this requirement shall not be considered.

    d. On the dimming system, the bidder submitting other equipment shall include pertinent performance data, charts and drawings showing in what respect the system will function in

    accordance with specification, and in what way it will deviate from the specification. This

    submittal shall include, but not be limited to the following:

    i) Rated ampacity, peak single cycle surge current rating, I^2t rating, and transient voltage rating of the output devices employed in the dimmers.

    ii) Laboratory verification of minimum current rise time at a 90-degree conductive angle, with the dimmer operating at the maximum load.

    iii) Description of the air-cooling and air filtration systems.

    iv) Description of the packaging and ease of replacement for all spare parts required in this specification.

    v) Original Manufacturer’s catalog data sheets for all major components of the dimmer system.

    e. For the control system, the bidder shall submit the name of the manufacturer, and list of ten (10) or more operating systems in the State of Delaware or surrounding area of the type

    specified which meet the performance control functions designed, with contact names and

    telephone numbers for references. This information shall be mandatory as a basis for

    determining the bidder’s intent in meeting the full requirements of this specification and shall

    be submitted at least fourteen days in advance of bidding.

    f. It is understood that any additions or revisions of wiring required by the use of substitute equipment, whether such wiring is part of this contract or of the prime electrical contract,

    shall be the responsibility of the bidder making the substitution.

    g. If required by the Owner, the Consultant, or Architect, the bidder shall provide working

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    STAGE LIGHTING SYSTEMS 265501 - 7

    samples of substitute equipment including lamps for any lighting fixtures, to be delivered to

    the premises designated, for examination by Architects, Consultants, and such representatives

    as the Owner may direct. Handling, shipping and delivery to, or removal from site, of any

    sample required shall be at the cost of the Contractor. The Contractor shall be responsible

    for the arrangement of the cost of the electrical supply required to properly test any lighting

    instruments or item of equipment. Proposals which fail to address specification requirements

    or review comments shall be rejected.

    h. Prior approval submittal review and approval shall not be considered to be shop drawing review. Prior approval in no way relieves the Contractor of responsibility to fully meet the

    requirements and intent of this specification.

    i. Should the contractor propose and receive approval for the use of alternative or substitute equipment which requires additional or modified conduit, the contractor shall be solely

    responsible for the installation of such conduit.

    2.3 AUDITORIUM STAGE AND BLACK BOX LIGHTING RELAY RACKS

    A. General

    1. Intelligent breaker system shall be 120V Sensor IQ systems as manufactured by ETC, Inc., or equal

    2. Breaker Panels shall be UL508, UL67, and UL924 Listed, and shall be so labeled when delivered

    3. Breakers shall be UL489 listed and shall be labeled when delivered

    4. Breaker Panels shall consist of a main enclosure with 48 or 24 pole breaker subpanels, integral control electronics for low voltage terminations and provision for accessory cards

    a) Up to two accessory cards shall be supported per breaker panel

    B. Mechanical

    1. The panel shall be constructed of 16-gauge galvannealed steel. All panel components shall be properly treated or finished in fine-textured, scratch resistant paint

    2. Breaker panels shall be capable of being mounted on the surface of a wall or recessed mounted

    3. The breaker panel for the Auditorium shall be a 48-pole configuration. The breaker panel for the Black Box shall be a 24 pole configuration

    4. Panel cover shall be for surface mount application. This outer panel shall ship complete with a locking door to limit access to electronics and breakers

    5. The unit shall provide interior cover over the control electronics and accessory cards to allow access only to class 2 wiring and prevent direct access to class 1 line voltage components

    6. The panel for the Auditorium system shall support up to 48 single pole branch circuits The panel for the Black Box system shall support up to 24 single pole branch circuits

    a) Branch circuits shall range from 15A to 30A capable of holding full rated load for minimum of three hours continuously

    b) Two and three-pole circuits shall be supported at decreased density where each pole constitutes one of the available single-pole circuits. Mixing of circuits in any combination

    shall be supported

    7. Breakers shall provide manual switching control while power is unavailable to the panel such that

    critical lighting can be set to an on state, without the need for power to the panel

    8. Breaker output lugs shall accept 10-14 AWG dual conductor wire

    9. Breaker output lug shall support solid or stranded 6-14 AWG class B, C, or K copper wire

    10. Control wiring for DMX, station bus, and Emergency input terminations shall land on a removable

    leader for contractor installation

  • CSD TWO INTERCONNECTED MIDDLE SCHOOLS 2019180.00

    STAGE LIGHTING SYSTEMS 265501 - 8

    C. User Interface

    1. The user interface shall contain an LCD display with button pad to include 0-9 number entry, up,

    down back arrow navigation and enter

    2. Test shortcut button s