CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management...
-
Upload
norman-burke -
Category
Documents
-
view
217 -
download
0
Transcript of CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management...
![Page 1: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/1.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
1
CS3100Software Project Management
November 22nd 2012
Week 7: Earned value
![Page 2: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/2.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
2
learning outcome
To be able critically to discuss some qualitative and quantitative measures for assessing project progress – and to select appropriate approaches
![Page 3: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/3.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
3
Questions(Read Cadle & Yeates Ch 11) If you are working on a £100,000 job and you get to a
milestone halfway through it, but discover you have spent £80,000, what is your best estimate of what it will cost to completed?
How much do you think the work you have done is worth? The job was to have taken you 5 months to complete, but
it takes you four months to get to the milestone halfway. How long do you think it will take to finish?
How much did you intend to spend each month? How much have you actually spent each month? What is your main problem here?
![Page 4: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/4.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
4
How do we know how a project is doing?
Pay day!
30, 60 or 90 days
time
Final delivery
Let’s consider a very simple example:
We’re making a great start!
We’re doing well
We’re ahead of schedule
We have some
problems, but we’re on schedule
We have a bit of a
problem…
Best tell the customer it will take another 3
months… and, by the way, we need another
£100,000 to finishWe can measure:How long it is takingHow many people are employed and how much they costOthers costs
BUTWhat progress are we making?
![Page 5: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/5.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
5
Let’s go back to our work breakdown
Example based on Cadle & Yeates, (4th ed) pp 204&ff
weeks0 1 2 3 6 7 8 94 5 10
Task A
Task B
Task C
Task D
Task E
Each task requires 4 software engineers, costing £500/day for 2 weeks
Budget = £100,000
£20,000
£20,000
£20,000
£20,000£20,000
![Page 6: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/6.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
6
Every month, you get something like this… (very simplified example)
Returns for Period X
Labour Grade Rate Days Cost Notes
2 £1,000 3 £3,000
4 £500 20 £10,000
5 £300 15 £4,500
Total Labour £17,500
Services
£7,500 Technical writer (FastDoc)
Total Services £7,500
Bought-in
£2,000 Software licences
Total Bought-in £2,000
Total £27,000
Rate may be hourly
Where do these come from?
![Page 7: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/7.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
7
Each company will do it differently
Your finance department will set rates
Some rates are agreed with some customers
• (e.g. EU has a list of allowed costs for O/H)
PM needs to understand about rates and to know what must be recovered directly
Direct costs associated with•Salary•Tax and NI•Pension
Personal overheads accounting for•Sick pay•Holidays•General overhead activity•Etc,
Other overheads•Accommodation, heating, lighting, etc•General equipment•Shared services•Management costs•etc…
![Page 8: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/8.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
8
Last week… D
irectIndirect
Indirect Building Maintenance 2,500.00
Heating, etc 1,000.00
Communications 500.00
Equipment (central/general) 2,500.00
Central services 10,000.00
School services 25,000.00
training 1,000.00
42,500.00
Direct NI & pension (approx.) 7,273.77
London weighting 2,166.00
Lecturer B (spine No. x) salary 32,471.00
Direct Equipment 10,000.00
51,910.77
Total 94,410.77
We worked out the rates for this data
![Page 9: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/9.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
9
A couple of questions:
Should you cost the MD into your tasks?
If your company has only 3 people, it might be appropriate, but most companies would put
management into the day-rate of project staff through the
overhead
Should you cost a computer into your
tasks?
If you need that particular computer for that particulartask, you might cost it (or a
fraction of it) into the project. General purpose computer costs
normally go into the overhead.
Project managers do not need to know the details,
necessarily, but do have to know how to use the rates and what else needs to be
costed in.
![Page 10: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/10.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
10
Review 1 month into the project – Bad news!
Example based on Cadle & Yeates, (4th ed) pp 204&ff
weeks0 1 2 3 6 7 8 94 5 10
Task A
Task B
Task C
Task D
Task E
Project hit problems – Someone was sick in the middle and work stopped for a week. However, it still took a week of effort more than anticipated and so cost an extra £10,000. Now Task B is only just ready to commence
What are the implications for cost and timescale?
£30,000
Task A
Task A
Task B
A
![Page 11: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/11.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
11
Three easy scenarios:
weeks0 1 2 3 6 8 10 124 5 14
Task A
Task BTask C
Task DTask E£30,000
7 9 11 16 17 18 1913 15 20
£30,000
£30,000
£30,000
£30,000
Scenario A: The project continues in the same way as it has begun (i.e. the way we worked out our simple problem): Costs will rise to £150k – i.e. a 50% cost overrun It will take 20 weeks – i.e. a 100% timescale overrun
This is probably the fairest assumption, based on your performance so far.This is probably the fairest assumption, based on your performance so far.
Task AA
Task BB
Task CC
Task DD
Task EE
![Page 12: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/12.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
12
Three easy scenarios:
weeks0 1 2 3 6 8 10 124 5 14
Task A
Task BTask C
Task DTask E£30,000
7 9 11 16 17 18 1913 15 20
£20,000
Most naïve Project Managers will try to argue that this is the caseMost naïve Project Managers will try to argue that this is the case
Task AA
Task B
Task C
Task D
Task E
£20,000
£20,000£20,000
Costs will rise to £110k – i.e. a 10% cost overrunIt will take 12 weeks – i.e. a 20% timescale overrun
Scenario B: The problems to date are one-off, and it will go as planned from here on:
![Page 13: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/13.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
13
Three easy scenarios:
weeks0 1 2 3 6 8 10 124 5 14
Task A
Task BTask C
Task DTask E£30,000
7 9 11 16 17 18 1913 15 20
This is the aim of a good Project Manager (and by far the most difficult challenge)This is the aim of a good Project Manager (and by far the most difficult challenge)
Task AA
Task B
Task C
Task D
Task E
Each Task (B-E) must now cost £17,500 or lessEach Task (B-E) must now take 1½ weeks or less
£17,500
£17,500£17,500
£17,500
Scenario C: The PM gets the project back on course and finishes within time and budget:
![Page 14: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/14.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
14
Back to our analysis
Problem
1 month into the project, we are:£10k overspent &2 weeks behind
Scenario AScenario A
Fairest estimate(NOT WORST CASE)50% over budget100% over on time
Scenario BScenario B
Easy estimate10% over budget20% over on time
Scenario CScenario C
TargetWithin budgetOn time
Customer-facingquestions:
Can the customer waitanother 10 weeks and
pay another £50k?
Can the customerafford a 2 week delay
and another £10k?
Business-facingquestions:
Will my management waitanother 10 weeks and
cover a £50k overspend?
Can I ensure thatthis is really the end
of the bad news?
How can I boost myTeam’s performance by
25%-50%?
Thinkspot:What is the worst scenario?
![Page 15: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/15.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
15
A Project Manager needs to…
Problem
1 month into the project, we are:£10k overspent &2 weeks behind
Scenario AScenario A
Fairest estimate(NOT WORST CASE)50% over budget100% over on time
Scenario BScenario B
Easy estimate10% over budget20% over on time
Scenario CScenario C
TargetWithin budgetOn time
Quantify this
And work towards this
The schizophrenia of Project Management
![Page 16: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/16.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
16
Let’s put this on a more formal footing:Earned Value Analysis (very simplified)
weeks0 1 2 3 6 7 8 94 5 10
Task A
Task B
Task C
Task D
Task E
£30,000
Task A
Task AA
£20,000£20,000
3 critical parameters & 2 helpful ratios3 Critical questions:1. How much have I spent?2. How much did I plan to spend?3. How much is what I have done actually worth?
Actual Spend, AS = £30,000Actual Spend, AS = £30,000
I planned to have completed Tasks A & B: Planned Spend,PS = £40,000
I’ve completed Task A, which was I’ve completed Task A, which was worth £20,000 in my plan: Earned worth £20,000 in my plan: Earned Value, EV = £20,000Value, EV = £20,000
![Page 17: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/17.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
17
Some trickier names:Variable Name Also known as…
AS Actual spend Actual cost of work performed (ACWP)
PS Planned spend Budgeted cost of work scheduled (BCWS)
EV Earned Value Budgeted cost of work performed (BCWP)
These provide some simple markers on how we are doing
Seminar activity – write a definition in your own words
![Page 18: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/18.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
18
Some trickier names:Variable Name Also known as…
AS Actual spend Actual cost of work performed (ACWP)
PS Planned spend Budgeted cost of work scheduled (BCWS)
EV Earned Value Budgeted cost of work performed (BCWP)
Cost variance, C = (EV-AS) +ve if you are ahead on budget+ve if you are ahead on budget-ve if you are behind on budget-ve if you are behind on budget
Schedule variance, S = (EV-PS) +ve if you are ahead of schedule+ve if you are ahead of schedule-ve if you are behind of schedule-ve if you are behind of schedule
These provide some simple markers on how we are doing
![Page 19: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/19.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
19
For our example…Cost variance, C = (EV-AS) = -10,000
Schedule variance, S = (EV-PS) = -20,000
Try to think of these in words – e.g. In this case the Cost Variance tells me that I have spent more than I have earned – so I am trouble
But how do we But how do we make predictions?make predictions?
![Page 20: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/20.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
20
Predictions:
Q: What is the underlying assumption, here?
Cost performance index, CPI = (EV/AS) >1 if you are ahead on budget>1 if you are ahead on budget<1 if you are behind on budget<1 if you are behind on budget
Schedule performance index, SPI = (EV/PS) >1 if you are ahead of schedule>1 if you are ahead of schedule<1 if you are behind of schedule<1 if you are behind of schedule
Assume the same rate of success in turning your plans into Earned Value, will continue to the end of the project
![Page 21: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/21.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
21
For our example…Cost variance, C = (EV-AS) = -10,000
Cost performance index, CPI = (EV/AS) = 2/3
Schedule variance, S = (EV-PS) = -20,000
Schedule performance index, SPI = (EV/PS) = 0.5
Try to think of these in words – e.g. In this case the Schedule Performance index tells me that I am going half as fast as I had planned
![Page 22: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/22.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
22
Looking forwardPredictions:
This is going to cost (final budget outturn) = Original budget/CPI= 100,000/(2/3)= 150,000
i.e. I have only made two-thirds the progress I had expected for every pound I have spent, so it is going to take me one and a half times as much as I had planned, in order to finish
This gives us scenario A!!
This is going to take (timescale) = Original timescale/SPI= 10/0.5= 20 weeks
i.e. I have only made half the progress I had expected for every week I have spent, so it is going to take me twice as long as I had planned, in order to finish
![Page 23: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/23.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
23
This is not magic…
It assumes• Time and money will stay roughly linked in the
same way as you originally planned• That you will carry on in the same way, on the
whole, as you have behaved in getting to the point of assessment
It will not work so well• When time and money run out of synch (i.e. you
get different predictions from the two calculations)• When the cost and effort levels vary widely with
time.
![Page 24: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/24.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
24
Let’s go back…
Example based on Cadle & Yeates, (4th ed) pp 204&ff
weeks0 1 2 3 6 7 8 94 5 10
Task A
Task B
Task C
Task D
Task E
Original predictions: £100,000 and 10 weeksEV-predictions: £150,000 and 20 weeks.
Task A Can both of these be true at once – i.e. it will take twice as long, but you will only overspend by 50%?
![Page 25: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/25.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
25
Let’s go back to the start…
weeks0 1 2 3 6 7 8 94 5 10
Task A
Task B 75%
Task C
Task D
Task E
Another scenario – Assume that you test after 3 weeks and get the following feedback.
Task A
What are the key choices here?
![Page 26: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/26.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
26
Worse still…
weeks0 1 2 3 6 7 8 94 5 10
Task B
Task D
Task E
This situation is virtually out of control and you have no way of estimating real progress
Task A
Task C
You want to keep the emphasis on finishing!
![Page 27: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/27.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
27
Options for assessing incomplete tasks
Task B 75%1. Take a guess and use the fraction completed in your calculation
Problem: This guessing is difficult and people tend to be optimistic
![Page 28: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/28.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
28
Task B 75%1. Take a guess and use the fraction completed in your calculation
Problem: This guessing is difficult and people tend to be optimistic
Task B 50%2. Use 50% as your estimate while Task B is underway, 100% after completion
Problem: This still gives an optimistic view at critical times
Task B 0%3. Use 0% as your estimate while Task B is underway, 100% after completion
This provides a pessimistic estimate and gives you a nice boost when it its complete
Options for assessing incomplete tasks
![Page 29: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/29.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
29
The story so far
The concept of ‘earned value’ enables us to:• compare what we have done with what we
expected to have done by that stage• Make predictions about final spend and timescales
Earned value works best for completed tasks• We can make some estimates for incomplete
tasks
We can probably do a little better…We can probably do a little better…
![Page 30: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/30.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
30
Milestones
Task B
weeks0 1 2 3 6 7 8 94 5 10
Task D
Task E
Task A
Task C
Agree a milestone with the customer – plus a part payment to be made once you hit it
0 1 2 3 6 7 8 94 5 10
Deb
t (£)
Payment delay – usually Payment delay – usually much longer than a weekmuch longer than a week
![Page 31: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/31.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
31
Some guidelines for milestones
They formalise ‘earned value’ inside the project• May be used for part-payments internally• Staff bonuses• Staff performance assessment
They can be used to obtain part payments from the customer
So why not have a milestone at the end of every task?
![Page 32: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/32.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
32
Task B
Milestones
weeks0 1 2 3 6 7 8 94 5 10
Task D
Task E
Task A
Task C
Milestones may cost quite a lot to prepare (i.e. checking, sign-off, special formats, extra tests, etc)
We spent ages agreeing the formats and writing a special set of reports instead of getting on with papers
![Page 33: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/33.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
33
Key messages
You need a reliable means of measuring real progress• Earned value is one such approach
Earned value analysis helps to:• Assess where you are• Make predictions for planning options• Support internal team processes• Obtain part-payments from customers
It’s only a rough guide
![Page 34: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/34.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
34
For homework:
weeks0 1 2 3 6 7 8 94 5 10
Task A
Task B
Task C
Task D
Task E
£30,000
Task A
Task AA
£20,000£20,000
Task B
Difficult negotiations with team – they improve work-rate and deliver
to original time estimates
Task C
Replace 2 low-cost coders with a top class coder who doubles productivity
AS = £60,000Tasks A-C completeWhat is the latest forecast on cost & timescale?
Actual
Planned
Summary: Following a poor First Review, the Project Manager brought Task B to completing in a further 2 weeks at a cost of £20,000 and then changed the staff mix for Task C. This resulted in Task C being completed within a week for a cost of £10,000. At the end of week 7, a Second Review is conducted and the result is that Tasks A-C have been completed, while the Actual Spend is £60,000. What is the new estimate for the final cost and the delivery date?
![Page 35: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/35.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
35
Homework
Part 2: Suppose you are the Project Manager's boss. You look at how well the project has improved between the First Review and the Second Review. You decide that the Project Manager is doing quite well and might continue to recover the situation. How might you try to estimate the impact of continued improvement (any ideas are worth working on)? What is your best estimate of the final cost and finishing date?
![Page 36: CS3100 S/w Project ManagementWeek 9: Earned value Sept ‘12 1 CS3100 Software Project Management November 22 nd 2012 Week 7: Earned value.](https://reader030.fdocuments.in/reader030/viewer/2022032612/56649ed15503460f94bdfd61/html5/thumbnails/36.jpg)
CS3100 S/w Project Management Week 9: Earned valueSept ‘12
36
Next week: Monitoring & control
Cadle, J. and Yeates, D. (2008). Project Management for Information Systems (5th edition) London, UK: Pearson Education Ltd, Chapters 11 &12