CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation...

25
CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI- DataLink (NO Programming and LOW maintenance!)

Transcript of CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation...

Page 1: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

CRITICAL VARIABLES PROGRAM

Get plant operating results with aninexpensive and simple

implementation using onlyPI-ProcessBook and PI-DataLink

(NO Programming and LOW maintenance!)

Page 2: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

AGENDA

• Introduction• Problem: Unit Operating

Settings• Proposed Solution & Game Plan• Details of Critical Variables

Program– Displays for current plant status– Reports for deviation tracking

• Results: Successes & Failures

Page 3: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

GENERAL INFO

• Carolyn Przybylski (sha–BILL–skee)– B.S. Chemical Engineering (1987)– Started with Cytec as Process Engineer ->

Production Engineer -> Process Control Engineer– Currently Sr. Manufacturing Systems Engineer– PI System Manager (4 years)

• Cytec Industries – Fortier Plant– New Orleans, LA– Chemical Manufacturing plant– Continuous Processes (24/7/365)– 440+ Cytec employees & 150+ contractors

onsite

Page 4: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

PI SYSTEM LAYOUT

• Separate Networks (Process & Office)• Two 50K tag servers with PI-to-PI

interface• Interfaces:

– 6 DCS (GSE D/3 & Yokogawa)– 20+ PLC (Square D, Allen Bradley)– 2 APC Systems– Laboratory Mgmt System (LIMS)– Environmental Mgmt System (EMIS)

PROCESS NETWORK

OFFICE NETWORK

Routers/Firewall

DCS & PLC

Process PI Server

(50k)APC

Office PI

Server (50k)

PI-to-PI Server

EMIS

LIMS

Clients

Page 5: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.
Page 6: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

PROBLEM

• Spent a lot of time & money improving control loops to enable finer control closer to constraints

• Plant was still being run at “easy” settings rather than economical

• Some settings could be detrimental to process (plugging) or equipment (corrosion) over the long term

• Advanced Control option too expensive

Page 7: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

“CHEAP & EASY” SOLUTION

Needed a system to maintain the plant attarget operating points and

to track excursions from target• CHEAP – used existing PI Clients of

ProcessBook and DataLink• EASY – no special programming required, just

standard ProcessBook, DataLink, and Excel functions

• Focused effort on developing list of key parameters and their targets/limits and then following up to ensure that unit was run within those limits

Page 8: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

WHY USE PI INSTEAD OF DCS?

• Lab sample results do not reside in DCS, but do reside in PI

• Some key parameters are calculations that are done in PI, not on DCS

• Future parameters from other units that were in PI

• Limited DCS screens used for control; can use PC screen for PI

• Easy to make changes (more people trained on PI-ProcessBook and Excel than on DCS)

Page 9: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

GAME PLAN

• Step 1: Establish list of critical variables as key indices for the plant and include ranges for TARGET, HI/LO, and HIHI/LOLO

• Step 2: Develop ProcessBook display to show where plant is currently operating in relation to established targets (snapshot view)

• Step 3: Develop daily DataLink report to show how much time was spent in each range (% of time) for monitoring off-shift periods

Page 10: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

HOW ARE WE DOING RIGHT NOW?

Page 11: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

NO VBA PROGRAMMING:MULTISTATE SYMBOLS, ONLY

Page 12: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

HOW HAVE WE DONE IN THE PAST?

Page 13: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.
Page 14: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

PI TIME FILTER FUNCTION

Page 15: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

TIME INTERVAL FORMATTING

=($B$4-$B$3)*24&"h"

Page 16: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

CRITICAL LIMITSENTRY FOR REPORT

Cell “$L10” used in Time

Filter Formula

Page 17: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

TIME FILTER FUNCTION EXPRESSION (LO/HI)

Page 18: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

TIME FILTER FUNCTION EXPRESSION (LOLO/HIHI)

Page 19: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

• % Time in Target Ranges:– Unit 1 = 95%– Unit 2 = 80%

• Steam Savings of M$1.6• Long term savings: TBD

– Extend equipment life?– Reduce outages due to plugging?

• Communication key to success (supervisors, operators, engineers)

RESULTS

Page 20: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

• Originally one display and one report applied to operating parameters for one unit

• Now three units using displays and reports for operating parameters

• As successes are realized, more units should begin similar implementations

• Have added displays and reports for Cooling Tower Operation and Quality Control

ADDITIONAL STEPS

Page 21: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

COOLING TOWER DISPLAY

Page 22: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

USED DATASETS TODISPLAY LIMITS ON TRENDS

Page 23: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

QUALITY CONTROL DISPLAY

Page 24: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.

SUMMARY OFCRITICAL VARIABLES PROGRAM

• Simple method to maintain key variables on target using basic functionality of PI & Excel

• Can be applied to multiple areas such as production, cooling towers, & quality control

• KEY COMPONENT: COMMUNICATION!– Tool just helps to provide FOCUS on key issues &

problem areas– Once target deviations are identified, operators,

engineers, and supervisors MUST work together to apply solutions (specific communications/training)

Page 25: CRITICAL VARIABLES PROGRAM Get plant operating results with an inexpensive and simple implementation using only PI-ProcessBook and PI-DataLink (NO Programming.