Critical Chain Project Management Final

download Critical Chain Project Management Final

of 16

Transcript of Critical Chain Project Management Final

  • 8/2/2019 Critical Chain Project Management Final

    1/16

    1

    CRITICAL CHAIN PROJECTMANAGEMENT (CCPM)

    Presented by Adnan DastgirSp-10-137

  • 8/2/2019 Critical Chain Project Management Final

    2/16

    SEQUENCE

    Main problems in project management

    Contradictions in project management

    Critical chain project management Steps of CCPM

    Benefits

    Conclusion

    2

  • 8/2/2019 Critical Chain Project Management Final

    3/16

    MAIN PROBLEMS IN PROJECT MANAGEMENT

    The main problem is variation things happenin unpredictable way

    Basic negative factors during execution ofproject can be grouped as:

    Multitasking Accumulation of numerous pending tasks at the same time

    Students Syndrome Everything is done at the last moment and then something goes

    wrong

    Mutual dependencebetween tasks Delays are accumulated and work is not finished in advance

    3

  • 8/2/2019 Critical Chain Project Management Final

    4/16

    CONTRADICTIONS IN PROJECTMANAGEMENT

    What we want... ...and what we actually doTo finish projects on time We try to finish separate tasks on

    time

    To take more projects; We try to make our people moreefficient

    To decrease the time for projectaccomplishment;

    We try to decrease the time for taskaccomplishment;

    To keep projects within their budget; We take risks related tocomparatively small costs;

    To make customer happy; We fight with each other on resourceconflicts;

    In this column we have only

    global, company-

    level factors;

    In this column we have

    only local

    factors! 4

  • 8/2/2019 Critical Chain Project Management Final

    5/16

    SOLUTION CRITICAL CHAINPROJECT MANAGEMENT

    Application of method known as Critical Chain ProjectManagement (CCPM).

    A method of planning and managing projects that puts the main

    emphasis on the resources required to execute project tasks

    This method stresses protection of the whole project byapplication of Project Buffer and working with challengingnettimes for each separate task.

    Critical Chain is the longest chain of dependent tasks andresource usage steps in a project.

    5

  • 8/2/2019 Critical Chain Project Management Final

    6/16

    THE FIVE FOCUSED STEPS IN CCPM

    1. Identify the constraint;

    2. Exploit the constraint;

    3. Subordinate everything else in the System toArt. 2;

    4. Eliminate the root cause of the constraint;

    5. Go back to Art. 1 and do not allow inertia tobecome the real constraint!

    ( E. Goldratt )

    6

  • 8/2/2019 Critical Chain Project Management Final

    7/16

    HOW TO MANAGE PROJECT THIS WAY?

    1. Identify the Constraint!

    It is the Critical Chain that acts as projectconstraint;

    It defines its success or failure!

    7

  • 8/2/2019 Critical Chain Project Management Final

    8/16

    2. EXPLOIT THE CONSTRAINT!

    Squeeze the Critical Chain! Press timely implementation(net times!) of all tasks lying on it!

    Resources work without fixed deadline their orders looklike Start at , work with full priority and maximal intensity,and when you are ready pass the task to the nextresource!

    Protect the whole project length by Project Buffer; Main indicatoris consumption of the project buffer!

    8

  • 8/2/2019 Critical Chain Project Management Final

    9/16

    3. SUBORDINATE EVERYTHING ELSE

    IN THE SYSTEM TO ART. 2!

    9

    1. The non-critical parts of project plan are completely

    subordinated to the Critical Chain.2. These part are known as Feedingchains;Subordination

    means that these chains must be completed beforeplanned start of next task in the Critical Chain;

    3. Resulting protection time gap is called Feeding Buffer.

  • 8/2/2019 Critical Chain Project Management Final

    10/16

    BUFFERS Project Buffer protects the whole project from variation

    along the Critical Chain

    Project Buffer serves as main indicator for projectprogress

    Feeding Buffer protect the project from variation alongfeeding chains

    10

  • 8/2/2019 Critical Chain Project Management Final

    11/16

    CHALLANGES We must create attitude in people which does not

    allow the StudentSyndrome!

    Apply relay race method (When I get a task, I

    will start it immediately, I will do it in the fastestpossible way, I will do nothing else and I willtransfer it immediately to next link of projectchain!)

    No multitasking is allowed!

    Make this basic part of organizational culture!

    11

  • 8/2/2019 Critical Chain Project Management Final

    12/16

    4. ELIMINATE THE ROOT CAUSE OF THE CONSTRAINT

    Increase the resources along

    the Critical Chain;Other possibilities include

    doubling of feeding chains

    and/or their acceleration.

    12

  • 8/2/2019 Critical Chain Project Management Final

    13/16

    PROJECT BUFFER AS INDICATOR

    13

    The project leader sees a chart like that below; this mayhappen in real time;Delay in accomplishment of certain task look like crawlingupwards of corresponding task point upwards to the redarea;

    Rule is simple: if points are in green area do not do anything;if in yellow area check what is going on; if in the red area(only then!) take action!

    ProjectBuffer

    Consumptio

    n

    0 25 50 75 100

    Critical Chain Accomplishment (%)

    0

  • 8/2/2019 Critical Chain Project Management Final

    14/16

    BENEFITS OF CCPM

    An aggressive target duration schedule, along withelimination of task due-dates, minimizes impact ofStudentssyndrome.

    Buffers allow resources to focus on work without task due-

    date distraction and efficiently protect against "Murphy'sLaw" with shorter project lead-times.

    Resource alerts and effective prioritization of resourceattention allow projects to take advantage of good luck and

    early task finishes while buffers protect against bad luck andlater than scheduled finishes.

    Buffer Management provides focus for schedulemanagement, avoids unnecessary distraction, and allows

    recovery planning to take place when needed, but wellbefore the project is in trouble. 14

  • 8/2/2019 Critical Chain Project Management Final

    15/16

    CONCLUSION

    Putting Critical Chain Scheduling and BufferManagement in place is not quite as easy asflipping a switch or turning on a new piece of

    software It requires real change in how projects, resources,

    and priorities are managed

    But if project speed and reliability are important to

    an organization, it may well be worth the effort toassess the potential benefits of implementingCCPM

    15

  • 8/2/2019 Critical Chain Project Management Final

    16/16

    THANK YOU

    16