Cradle Coast Regional Planning Initiative · 2020-01-30 · Cradle Coast Region to commence from...

506
Cradle Coast Regional Planning Initiative c/- PO Box 338 Burnie Tasmanian 7320 The Executive Commissioner Tasmanian Planning Commission GPO Box 1691 Hobart TAS 7001 9 th July 2014 Dear Sir Joint Report in accordance with section 30J land Use Planning and Approvals Act 1993 in relation to the Interim Planning Schemes of the Cradle Coast Region. The Minister for Planning declared an interim planning scheme for each municipal district within the Cradle Coast Region to commence from 19 th October 2013. Each of the declared interim planning schemes was concurrently notified in accordance with section 30H Land Use Planning and Approvals Act 1993 from 19 th October 1993 and a period of two months allowed for community consideration and written comment. A total of 260 individual representations were received during the notification period. I am pleased to advise the planning authorities of the Cradle Council Region have each determined to provide to the Tasmanian Planning Commission a report containing the views and opinions of the planning authority in relation to the merits and impacts of the representations made on the notified interim planning scheme for their municipal district. The views and opinions of each planning authority are combined into a joint report in accordance with LUPAA s30J for planning schemes that were concurrently notified. The decision of each Council has instructed that the Cradle Coast Regional Planning Initiative Steering Committee compile the s30J Joint Report, and provide it to the Tasmanian Planning Commission. The s30J Joint Report will be provided in digital format under separate cover to the Tasmanian Planning Commission. Provision of the s30J Joint Report is a significant milestone in the planning scheme reform program for the Cradle Coast Region. The Report marks the conclusion of the independent actions required of the planning authorities within the Region under the Memorandum of Understanding. The final task was to prepare and implement replacement planning schemes that are consistent to the mandatory format and structure provided in Planning Directive No1 and harmonised in relation to the purpose and content of local provisions on matters that do not have to be different between the planning schemes of adjacent municipal districts.

Transcript of Cradle Coast Regional Planning Initiative · 2020-01-30 · Cradle Coast Region to commence from...

  • Cradle Coast Regional Planning Initiative

    c/- PO Box 338

    Burnie

    Tasmanian 7320

    The Executive Commissioner Tasmanian Planning Commission GPO Box 1691 Hobart TAS 7001 9th July 2014 Dear Sir Joint Report in accordance with section 30J land Use Planning and Approvals Act 1993 in relation to the Interim Planning Schemes of the Cradle Coast Region.

    The Minister for Planning declared an interim planning scheme for each municipal district within the Cradle Coast Region to commence from 19th October 2013.

    Each of the declared interim planning schemes was concurrently notified in accordance with section 30H Land Use Planning and Approvals Act 1993 from 19th October 1993 and a period of two months allowed for community consideration and written comment.

    A total of 260 individual representations were received during the notification period.

    I am pleased to advise the planning authorities of the Cradle Council Region have each determined to provide to the Tasmanian Planning Commission a report containing the views and opinions of the planning authority in relation to the merits and impacts of the representations made on the notified interim planning scheme for their municipal district.

    The views and opinions of each planning authority are combined into a joint report in accordance with LUPAA s30J for planning schemes that were concurrently notified.

    The decision of each Council has instructed that the Cradle Coast Regional Planning Initiative Steering Committee compile the s30J Joint Report, and provide it to the Tasmanian Planning Commission.

    The s30J Joint Report will be provided in digital format under separate cover to the Tasmanian Planning Commission.

    Provision of the s30J Joint Report is a significant milestone in the planning scheme reform program for the Cradle Coast Region.

    The Report marks the conclusion of the independent actions required of the planning authorities within the Region under the Memorandum of Understanding.

    The final task was to prepare and implement replacement planning schemes that are consistent to the mandatory format and structure provided in Planning Directive No1 and harmonised in relation to the purpose and content of local provisions on matters that do not have to be different between the planning schemes of adjacent municipal districts.

  • The actions and commitment by all of the planning authorities to attain this outcome in a constructive and cooperated manner remains a hallmark of the approach taken within the Region on planning reform.

    The views and opinions expressed within the 30J Joint Report continue to evidence a high level of consistency and agreement between planning authorities of the Region.

    The Joint Report provides constructive observation and advice to assist the Tasmanian Planning Commission in determining representations and in approving a final form of planning scheme that is strategically and operationally robust.

    The Region is aware of the current considerations at State level for further reforms within the land use planning system, including for transition to a single state wide planning scheme.

    However, the Region urges that the interim planning scheme process for the Cradle Coast Region not be terminated or unduly delayed in anticipation of a possible replacement model.

    The Region and the State have both invested considerable financial, political, and technical capital in preparing and providing the interim planning schemes.

    The Region has initiated a statutory process to invite the community to consider and comment on the declared interim planning schemes; and the statutory requirements in LUPAA allow that those who have made representations can anticipate that the subsequent processes will be now be finalised.

    It is requested that the Tasmanian Planning Commission receive the Joint Report and advise its requirements for continuing the process for final determination as planning schemes in accordance with LUPAA s30N.

    Yours faithfully

    Charles Arnold Chair – Cradle Coast Regional Planning Initiative Steering Committee

  • Cradle Coast Region Interim Planning Schemes

    Joint Report under s30J Land Use Planning and Approvals Act 1993 on Representations made in relation

    to Common Provisions and Local Provisions in the –

    Burnie Interim Planning Scheme 2013

    Central Coast Interim Planning Scheme 2013

    Circular Head Interim Planning Scheme 2013

    Devonport Interim Planning Scheme 2013

    Kentish Interim Planning Scheme 2013

    King Island Interim Planning Scheme 2013

    Latrobe Interim Planning Scheme 2013

    Waratah Wynyard Interim Planning Scheme 2013

    West Coast Interim Planning Scheme 2013

    Prepared by –

    Burnie City Council

    Central Coast Council

    Circular Head Council

    Devonport City Council

    Kentish Council

    King Island Council

    Latrobe Council

    Waratah Wynyard Council

    West Coast Council

    June 2014

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 1

    Cradle Coast Region Interim Planning Schemes

    Joint Report under s30J Land Use Planning and Approvals Act 1993 on Representations made in relation

    to Common Provisions and Local Provisions in the –

    Burnie Interim Planning Scheme 2013

    Central Coast Interim Planning Scheme 2013

    Circular Head Interim Planning Scheme 2013

    Devonport Interim Planning Scheme 2013

    Kentish Interim Planning Scheme 2013

    King Island Interim Planning Scheme 2013

    Latrobe Interim Planning Scheme 2013

    Waratah Wynyard Interim Planning Scheme 2013

    West Coast Interim Planning Scheme 2013

    Prepared by –

    Burnie City Council

    Central Coast Council

    Circular Head Council

    Devonport City Council

    Kentish Council

    King Island Council

    Latrobe Council

    Waratah Wynyard Council

    West Coast Council

    June 2014

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 2

    Table of Contents

    Page

    Introduction 3

    Table 1 – Principles for response on representations 9

    Table 2 – Persons making Representations 15

    Table 3 – Persons making representations (by municipal district and issues) 16

    Representations and response in relation to interim planning schemes

    Table 4 –Format and Operation 34

    Table 5 - Purpose and Objectives 53

    Table 6 - Administration 55

    Table 7 - Exemptions 60

    Table 8 - Permit Pathways 74

    Table 9 Special Provisions 95

    Table 10 - General Residential Zone 106

    Table 11 - Inner Residential Zone 147

    Table 12 - Low Density Residential Zone 148

    Table 13 - Rural Living Zone 156

    Table 14 - Environmental Living Zone 189

    Table 15 - Urban Mixed Use Zone 200

    Table 16 - Village Zone 203

    Table 17 - Community Purpose Zone 206

    Table 18 - Recreation Zone 214

    Table 19 - Open Space Zone 217

    Table 20 - Local Business Zone 225

    Table 21 - General Business Zone 234

    Table 22 - Central Business Zone 238

    Table 23 – Commercial Zone 242

    Table 24 – Light Industrial Zone 251

    Table 25 – General industrial Zone 261

    Table 26 – Rural Resource Zone 269

    Table 27 – Significant Agricultural Zone 370

    Table 28 - Utilities Zone 371

    Table 29 – Environmental Management Zone 383

    Table 30 – Major Tourism Zone 401

    Table 31 – Port and Marine Zone 402

    Table 32 – Particular Purpose Zone 406

    Table 33 – Codes 407

    Table 34 – Code E1 Bushfire-prone Areas 408

    Table 35 – Code E2 Airport Management 417

    Table 36 – Code E4 Change in Ground Level 430

    Table 37 – Code E5 Local Heritage Code 434

    Table 38 – Code E6 Hazard Management 446

    Table 39 – Code E7 Signs 451

    Table 40 – Code E8 Telecommunication Infrastructure 454

    Table 41 – Code E9 Traffic Generating Use and Parking Code 456

    Table 42 – Water and Waterways Code 464

    Table 43 – Code E11 (Devonport IPS 2013) 471

    Table 44 – Specific Area Plans 473

    F4 Turners Beach SAP (central Coast IPS) 473

    F3 Stony Rise SAP (Devonport IPS) 475

    F1 Cradle Gateway SAP (Kentish IPS) 475

    F2 Port Sorell SAP (Latrobe IPS) 475

    Boat Harbour and Sisters Beach SAP (Waratah Wynyard IPS) 476

    Table 45 - Appendices 478

    Table 46 – Additional Matters 479

    Proposed Electricity Transmission Infrastructure Protection Code 479

    Appendix 1 – Council Motions to provide 30J Joint Report 483

    Appendix 2 – Substantive Modifications suggested for the interim planning

    scheme Ordinances.

    487

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 3

    Introduction

    In October 2013 the Tasmanian Minister for Planning declared an Interim Planning

    Scheme in accordance with s30F Land Use Planning and Approvals Act 1993 for each

    of the nine municipal districts of the Cradle Coast Region of northwest Tasmania.

    The Minister’s declaration effectively repealed all former planning schemes applying

    for the municipal districts and replaced them with an Interim Planning Scheme.

    Each Interim Planning Scheme became the operational and enforceable planning

    instrument for the applicable municipal district.

    A period for community consideration and comment concurrently commenced with

    declaration of the schemes.

    The purpose of this report is to identify each of the representations received, and to

    set out a joint response by the planning authorities of the Cradle Coast Region on

    each issue in each representation, including whether a change to the interim planning

    scheme may be justified.

    Interim planning schemes

    A planning scheme is enforceable regulation prepared and approved under the Land

    Use Planning and Approvals Act 1993 for the purpose of prescribing how land in a

    municipal district is to be used, developed, protected and conserved.

    Toward Consistency – A Guide to the Cradle Coast Interim Planning Schemes October

    2013 provides explanation for the statutory requirements and for the strategy and

    policy considerations underpinning provisions in the interim planning schemes.

    An interim planning scheme is a particular form of planning scheme in accordance

    with LUPAA s30E.

    The primary purpose of an IPS is to translate a former planning scheme into a

    common format and structure, and to align the purpose of regulatory provisions to a

    regional land use strategy.

    The objective for an IPS is to provide greater consistency and coordination between

    the purpose and provisions of the planning schemes applying for adjacent municipal

    districts within the Cradle Coast Region.

    Each interim planning scheme is required to –

    a) Be consistent with and likely to further the objectives and outcomes of the

    Cradle Coast Regional Land Use Strategy 2010 - 2030 (CCR LUS)

    The purpose and provisions of a planning scheme must be based on sound

    strategic planning and must further the objectives and be coordinated with

    the strategies and policies applying for land and resource management in

    Tasmania.

    Each interim planning scheme must be aligned to the regional strategic

    perspective for land use planning.

    It is not the function of an interim planning scheme to render significant

    strategic change, including in the purpose for which land was assigned under

    a zone in the former planning scheme.

    The IPS for each of the CCR municipal districts generally retain the purpose

    for which land was zoned under the applicable former planning scheme.

    Change is only made if reasonably required for compliance to the CCR LUS.

    The IPS process does not allow a wholesale review of local land use strategy

    and a corresponding change in the purpose or nature of the manner in which

    land may be utilised.

    The IPS process does not allow opportunity for rationalisation and correction

    of zone assignment and boundary location under the former planning

    scheme.

    b) Contain all of the common provisions for issues relating to the use,

    development, protection or conservation of land, or for procedural matters

    arising from operation of a planning process, as detailed by a Planning

    Directive as necessary for consistency between all municipal areas.

    Common mandatory provisions are requirements a planning scheme must

    contain.

    The common mandatory provisions for the interim planning scheme are –

    (i) The format and structure of the planning scheme ordinance as

    required by Planning Directive No 1.

    The common mandatory provisions establish the sequence and

    general expression of the provisions in an IPS, and including –

    a. Part A – Clauses 1.0, 2.0 and 3.0 for citation and for

    identifying purpose of the interim planning scheme;

    b. Part B – clauses 4.0, 5.0, 6.0, 7.0 and 8.0 which provide for

    definitions, exemptions, operation, and permit

    requirements;

    c. Part C – clause 9.0 which provide compliance requirements

    for change of existing non-conforming use, boundary

    adjustments, demolition, and subdivision; and

    d. Part D – which the zone purpose statement for each of the

    zones described in clauses 10 – 32 inclusive

    (ii) The provisions in clause 10.4.3 for development standards for single

    dwellings in the General Residential zone of the interim planning

    scheme as notified in accordance with Planning Directive No 4; and

    from 28th

    February 2014, the provisions in 10.4.1 to 10.4.8 inclusive

    relating to development standards for single and multiple dwellings

    as required by Planning Directive No 4.1;

    (iii) The provisions in Code E1 for Bushfire-prone Areas as required by

    Planning Directive No 5;

    (iv) The provisions in Table E9A to Code E9 – Traffic Generating Use and Parking Code relating to provision of parking for single dwelling and

    multiple dwelling development in the General Residential zone as

    required by Planning Directive No 4.1

    (v) Optional common provisions as requirements a planning scheme is

    to contain if the matters addressed by the provision are relevant to

    the circumstances and conditions of the municipal district.

    There are no optional common provisions applicable for the IPS of

    the Cradle Coast Region.

    c) Contain local provisions that are overriding local provisions.

    Local provisions are requirements that are particular to an interim planning

    scheme.

    Overriding local provisions are requirements that prevail in the interim

    planning scheme against a common mandatory provision if there is a conflict

    with a common mandatory provision.

    The overriding local provisions in each interim planning scheme are

    identified by a Planning Purpose Notice; and are –

    (i) with respect to any provision in Code E1 – Bushfire-prone Areas

    a. Code E3.0 – Clearing and Conversion of Vegetation;

    b. Code E5.0 – Local Heritage; and

    c. Code E10.0 Water and Waterways ; and

    (ii) with respect to any provision in Clause 10.0 General Residential

    zone

    a. Clause 10.4.12 Setback of sensitive use development

    b. Code E3.0 – Clearing and Conversion of Vegetation;

    c. Code E4.0 – Change in Ground Level;

    d. Code E5.0 – Local Heritage;

    e. Code E6.0 – Hazard Management;

    f. Code E10.0 Water and Waterways; and

    d) Contain provisions that are conflicting local provisions

    A conflicting local provision is a requirement that is not inconsistent with an

    overriding local provision unless specified in a Planning Purpose Notice.

    There are no conflicting local provisions in any interim planning scheme of

    the Cradle Coast Region.

    e) Contain local provisions that are not inconsistent with common provisions

    and overriding local provisions.

    Local provisions form the larger part of the provisions in the interim planning

    schemes.

    Local provisions may be in two forms –

    (i) Ordinance provisions

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 4

    Ordinance provisions are the written instructions for how the

    interim planning scheme is to operate; and for the matters for

    assessment and decision if the interim planning scheme applies for

    a use or development

    The local provisions in the IPS of the Cradle Coast Region may be

    categorised as –

    a. Regional provision

    A Cradle Coast Region local provision template has ensured

    the form, expression, purpose, and requirements in local

    provisions are the same between all of the declared IPS

    unless there is a very compelling reason to be different.

    Local provisions derived from the Cradle Coast template

    planning scheme are identified as common regional

    provisions (RP) for the purpose of this Report.

    The majority of local provisions in each interim planning

    scheme are common with those in each of the other

    planning schemes.

    b. Local provisions

    Several interim planning schemes contain local provisions

    that are unique to that planning scheme.

    Such provisions are found as Codes (DIPS 2013) and as

    Specific Area Plans in the CCIPS 2013, DIPS 2013, and LIPS

    2013

    Representations relating to provisions that are unique to

    an individual interim planning scheme are identified as

    local provision (LP) matters for the purpose of this report.

    (ii) Planning Scheme maps

    Planning scheme maps indicate the land area to which provisions

    apply.

    There are two main categories of maps –

    a. Zone maps

    The statutory process for preparation of interim planning

    schemes required conversion from the zone applying

    under the former planning scheme into the zone with the

    most corresponding purpose within the range of zones

    provided in the template in Planning Directive No1.

    IPS zone maps must match in purpose the zone maps

    included with the former planning scheme. There is very

    limited opportunity within an IPS to change the purpose

    for which land may be used.

    b. Particular provision maps

    These maps depict factors called in to account by a

    particular provision, such as in Code E3.0 for areas of

    landscape or scenic value, and by Code E6 for areas of

    landslide risk.

    Particular purpose maps are introduced into IPS as a

    requirement of the CCR LUS to more adequately address

    natural hazards.

    Notification of Interim Planning Schemes

    A statutory opportunity in accordance with LUPAA s30H commenced on 19th

    October

    2013 for the community to consider and make comment on any aspect of the interim

    planning schemes.

    The notification commenced on the same date on which each of the IPS became an

    operational planning scheme in accordance with the Ministerial declaration under

    LUPAA s30F.

    The process for notification, including publication notices, was combined in

    accordance with LUPAA s30H (7) into a single process because each of the nine

    interim planning scheme was declared and notified on the same day.

    Written representations on in relation to all or any of the interim planning schemes

    were to be received by 20th

    December 2013.

    A representation is a written statement of facts or reasons in support of or in

    opposition to the interim planning scheme.

    The particular requirements of LUPAA s30I allow that a representation is to be in

    relation to the statutory function and content of an IPS. These are the matters of

    common and local provisions, and changes required for consistency to the CCR LUS.

    Representations should not extend to matters that more generally discuss the

    purpose and practice of the Tasmanian land use planning system; or the adequacy or

    otherwise, and the need for change, in the strategic intent and operational provisions

    of a former planning scheme, including in the purpose for which land is zoned.

    Representations received

    The statutory notification period attracted a total of 260 individual representations.

    Some representations made the same submissions separately to each planning

    authority, and have been identified as individual submissions. The net effect is that in

    the total of 260, some 79 contain replica matters.

    Each representation has been assigned a unique reference number1.

    Table 2 identifies each of the persons making a representation.

    Many representations deal with two or more separate matters.

    There are 797 separate issues raised within the representations.

    Each issue has been assigned a unique reference number.

    The majority of representations may be classified as an objection in that there is an

    expressed dissatisfaction with the purpose or outcome intended, or a desire that the

    IPS be modified.

    1 Some references are numeric and some are alpha-numeric. The difference reflects the

    sequence of registration and does not imply any distinction in the status or treatment of a

    representation

    Several the representations may be described as raising matters that are concerned

    with the content or outcome of an IPS as a replacement planning scheme; but which

    cannot accurately be said to be matters in relation to an IPS as intended by LUPAA

    s30I.

    The distribution of representations by municipal district is –

    Municipal District Representations Received

    Burnie City 33

    Central Coast 52

    Circular Head 37

    Devonport City 34

    Kentish 31

    King Island 13

    Latrobe 14

    Waratah Wynyard 27

    West Coast 17

    Total 260

    Process for Consideration of Representations

    The matters raised in each representation must be considered and taken into account

    before a decision to finalise an interim planning scheme is made.

    The consideration of representations is made initially by the planning authorities of

    the Cradle Coast Region who are to provide the Tasmanian Planning Commission with

    advice on the merits of each matter and the impact of that matter on operation of

    the IPS; and whether it is appropriate to consider modifying the interim planning

    scheme.

    The TPC is subsequently required to review the advice from the planning authorities

    and to consider each representation before making a decision on whether to

    approve, modify or reject the IPS as a final planning scheme.

    Views and opinion of planning authorities

    LUPAA 30I requires that a planning authority to which a representation has been

    made in relation to a provision that is common to all other interim planning schemes

    must provide a copy of that representation to each of the other planning authorities

    which notified an interim planning scheme on the same day.

    LUPAA s 30J requires a planning authority that has notified an interim planning

    scheme must provide a report to the Tasmanian Planning Commission within four

    months from the date on which the notification period concluded.

    The report on each Cradle Coast interim planning scheme is to be provided to the

    Commission by 20Th

    April 2014 unless a further period is agreed.

    The Tasmanian Planning Commission has agreed a further period for provision of the

    Report until 30th

    June 2014.

    LUPAA 30J(9) allows that if two or more interim planning schemes for a region are

    declared and publicly notified on the same date, the planning authorities must

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 5

    provide one Joint Report on common provisions and operation of the IPS instead of

    each providing a separate report.

    A Joint Report must include the views of all of the planning authorities, whether they

    are in agreement or not.

    The planning authorities of the Cradle Cost Region are to provide a Joint Report.

    The Joint Report is to provide –

    a) a copy of each representation received by each planning authority, and if no

    representations are received, a statement to that effect;

    b) a statement indicating the applicable planning authority’s views as to the

    merits of each matter contained in each representation made in relation to a

    local provision of each interim planning scheme as to –

    (i) the need for modification of the interim planning scheme in the

    light of that representation; and

    (ii) the impact of that representation on the interim planning scheme

    as a whole

    Each IPS of the CCR contains provisions that are common for all of the IPS.

    Such provisions are local provisions in the sense that they are not common

    provisions in terms of LUPAA s30B.

    The major proportion of each IPS is comprised of the provisions that are

    common for the Region. These provisions have been identified for the

    purpose of the Joint Report as regional provisions.

    It is appropriate the Joint Report provide the views of all the planning

    authorities on local provisions that are regional provisions. The approach

    allows that such provisions are assessed from a regional perspective, and

    that any modification can be considered from the perspective of retaining

    regional consistency. That is, if a change is made to a local provision that is a

    regional provision in one IPS, the same change is made for all of the other

    IPS.

    This document is the joint Report and contains the collective views of the

    planning authorities of the Cradle Coast Region on the local provisions that

    are regional provisions and incorporated into each IPS; and on those aspects

    of local provisions that have implication beyond the boundaries of the

    applicable municipal district.

    Primary content of the Joint Report in respect of local provisions that are

    particular to a single municipal district, including for the zoning assigned to

    land or for controls on use or development contained in a Specific Area Plan,

    is provided by the applicable planning authority for that municipal district.

    It is relevant to also include a regional perspective on some local issues to

    ensure consistency between IPS on matters of principle and process.

    c) a joint statement by all of the planning authorities indicating theirs views as

    to the merits of each matter contained in each representation made in

    relation to a provision that is a common provision for all interim planning

    schemes as to –

    (i) the impact of that representation on operation of the interim

    planning scheme as a whole if –

    a. the relevant planning directive creating a common

    mandatory provision or a common optional provision were

    to be modified in accordance with the outcome intended

    by the representation; or

    b. the common provision is an optional provision, and in

    accordance with the representation, the provision were to

    be –

    i. taken out of the interim planning scheme; or

    ii. taken out of the interim planning scheme and

    replaced by another optional provision

    This document is the Joint Report and contains the collective views of the

    planning authorities of the Cradle Coast Region on the common provisions

    d) a statement of the planning authority’s views and recommendations in

    respect of the operation of the interim planning scheme.

    This document is the joint Report and contains the collective views and

    recommendations of the planning authorities of the Cradle Coast Region in

    relation to the impact of representations and modifications on operation of

    the IPS.

    It is not necessary to identify a single common response on each matter – the Joint

    Report may indicate there are two or more options for how to deal with a matter.

    It is not necessary the Joint Report provide a single, unanimous or majority view or

    opinion on each matter – the Report may indicate more than one option or opinion

    on how to address a matter in a representation.

    A planning authority is not excluded from holding an independent view. However,

    dissenting or alternate views must be expressed in the Report

    Cradle Coast Region Section 30J Joint Report

    It is the purpose of this document to be the LUPAA s30J Joint Report by the planning

    authorities of the Cradle Coast Region on the representations received during the

    concurrent notification period for each of the Burnie, Central Coast, Circular Head,

    Devonport, Kentish, King Island, Latrobe, Waratah Wynyard, and West Coast interim

    planning scheme.

    Table 1 categorises the matters in representations and provides an indication for how

    the Joint Report views and provides advice in relation to issues in each a category.

    The categorises described may be aggregated in terms of three basic process

    outcomes –

    a) Representations in relation to –

    i. planning scheme reform outcomes; and

    ii. procedural fairness

    (Category 1 and 2)

    These matters are not specific to the purpose or content of an IPS; and can

    be determined without need for a hearing.

    b) Matters in relation to –

    i. an error in drafting of the planning scheme ordinance;

    ii. an error in translation of a zone from a former planning scheme;

    and

    iii. opportunity for improvement in the construction or expression of

    provisions in the planning scheme ordinance to clarify or improve

    operation and compliance without significant change to intended

    outcome

    (Category 3, 4, and 5)

    There is no apparent benefit in conducting a hearing or in delaying

    consequential correction or modification of the IPS if these matters are

    agreed between the planning authorities and the party making a

    representation.

    These modifications could be made as consequential amendments under

    LUPAA s30IA.

    c) Matters requiring modification of the IPS to –

    i. change the purpose or outcome of an objective or compliance test in

    the planning scheme ordinance;

    ii. introduce or delete a provision in the planning scheme ordinance;

    iii. adjust the purpose for which land is assigned by zone to reflect a

    strategic objective, existing use, or land capability; or

    iv. convert the purpose for which land is assigned by zone to provide an

    alternate opportunity for use

    (Category 6, 7, 8 and 9)

    These matters address the substance of IPS provisions and intend significant

    change to purpose or operation.

    Representations require independent review to ensure consistency to

    statutory purpose.

    A hearing could be dispensed with if there is agreement between the

    planning authority and the party making the representation that the IPS

    should be modified.

    The TPC may desire to seek future information or to question the parties.

    A hearing may be necessary if there is difference between the planning

    authorities in relation to regional consistency or disagreement with the party

    making a representation.

    The TPC should have discretion to dispense with a hearing and determine a

    representation if it –

    i. is not in relation to an IPS; or

    ii. does not contain sufficient information to establish a prima facie

    case for consideration in terms of the applicable LUPAA

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 6

    prescriptions for change or departure from the purpose or

    provisions of a planning scheme

    Table 2 identifies each person making a representation by municipal district; and

    describes for each representation the quantum of issues raised in relation to

    common, common regional and local provisions.

    Table 3 of this Report sets out the nature of each matter in each representation, and

    provides a corresponding response in relation to merits of the matter, whether it is

    considered there is a need to modify in accordance with the outcome intended by the

    representation, and the likely impact of such change on operation of the IPS as a

    whole.

    The 30J Report does not represent a decision by the planning authorities to finalise

    how each matter is to be determined.

    The Report is advice to the Tasmanian Planning Commission, and the Commission is

    required to take the advice into consideration when determining how to resolve each

    representation.

    The TPC may not agree with a position in response to a representation as articulated

    in the Joint Report.

    Hearing

    After receiving a Joint Report, the Commission –

    a) Is to hold a hearing in relation to each of the representations provided in the

    Joint Report.

    The Commission is to appoint an independent Panel to conduct hearings.

    Hearings are open to the public.

    The Panel may determine whether a representation is in relation to an

    interim planning scheme or whether it is concerned with a matter that deals

    with other aspects of the land use planning system or could be more

    correctly dealt with through a process other than as required for reviewing

    and finalising an IPS.

    It follows that not all persons making a representation will be invited to

    appear at a hearing.

    Each party making a representation in relation to an interim planning

    scheme is to be invited to attend and speak to the matters identified, and

    may be questioned by the Panel and by other parties, including a planning

    authority, in order to clarify the matters in the representation.

    The Panel may seek further information, including from the person making

    the representation or from the planning authority, to assist its

    understanding and to inform its decision; and may call witnesses if required.

    However, the hearing process should not allow a person opportunity to

    expand the scope of an issue or to substantially embellish the standard of

    material provided in a representation so as to provide further and better

    particulars in support of the outcome advocated.

    b) If there are several representations on the same issue, the Commission may

    consolidate such representations, and hold a hearing in relation to

    consolidated representations; and

    c) May hold hearings in relation to other matters that it thinks fit

    However, LUPAA does not anticipate a hearing to be a forum in which to advance an

    alternate philosophy for purpose of the land use planning system, or to make

    commentary and suggestion on the adequacy or fairness of any prescribed process.

    A hearing is particular to an interim planning scheme, and to the matters that are

    relevant to the function, construction, purpose, and content of each IPS.

    A hearing should not entertain submissions nor engage in deliberation on any matter

    that is extraneous to the statutory purpose of an IPS.

    Determination of an interim planning scheme

    The hearing and review process conducted by the Commission is intended to provide

    a foundation on which to make a decision on whether the interim planning scheme

    can be approved; or for whether the interim planning scheme, in whole or party,

    should be redone.

    After receiving a Joint Report under s30J, and having completed any hearings, the

    Commission is to consider the following matters in relation to the IPS –

    a) the interim planning scheme itself;

    b) any document in relation to the interim planning scheme provided to the

    Commission in the Joint Report;

    c) matters raised at hearings in relation to the interim planning scheme;

    d) the Cradle Coast Regional Land Use Strategy; and

    e) any applicable State Policy

    As a result of such a consideration the Commission is to –

    In relation to common provisions

    Prepare a report to the Minister for Planning in relation to common provisions of the

    interim planning scheme to include –

    a) a copy of each interim planning scheme;

    b) a copy of the Joint Report;

    c) having regard to the Joint Report, provided to it by the planning authorities,

    a statement by the Commission in relation to each common provision to

    specify whether the Commission is of the opinion that –

    (i) a planning directive containing the provision ought be modified to

    take account of the representation made in respect of the

    provision; and

    (ii) the interim planning schemes ought be modified accordingly

    On receipt of the Commission’s report the Minister may direct the Commission to

    prepare a draft planning directive to modify a planning directive containing a

    common provision for which a change is require.

    The Cradle Coast Region expects that the TPC will independently consider and report

    on representations and LUPAA s30J advice on common provisions regardless of any

    submission or decision that may have been made in relation to the same common

    provision under a LUPAA 30K process applying for an IPS in a municipal district

    outside the Region.

    In relation to local provisions

    At the completion of its hearings and after considering all applicable matters, the

    Commission may in relation to a local provision (including for how land is assigned to

    a zone) –

    a) direct the planning authority for a specific interim planning scheme to

    prepare a modification –

    (i) to correct an error in a local provision of that interim planning

    scheme;

    (ii) in relation to a local provision; or

    (iii) in relation to a common provision if -

    a. to modify a common provision in that interim planning

    scheme to comply with a planning directive;

    b. to modify a common provision for the purpose of consistency

    to an urgent amendment made to that interim planning

    scheme in accordance with LUPAA s 30IA(3);

    c. to take an optional common provision out of that interim

    planning scheme; or

    d. to take an optional common provision out of that interim

    planning scheme and replace it with another optional

    common provision; or

    b) prepare such a modification itself

    The planning authority must prepare and submit the required modifications to the

    Commission within the timeframe specified in the direction. If the Commission

    instructs an interim planning scheme must be modified, the Commission may also

    instruct that the modified interim planning scheme must be notified again.

    If the Commission instructs a modified interim planning scheme must be notified, all

    of the requirements of LUPAA with respect to the process and period for notification,

    the responsibilities on a planning authority to prepare a report to the Commission,

    and for the Commission to conduct a hearing and either report to the Minister or

    again require modification, must be fully observed.

    The Cradle Coast Region expects that any decision to require a modification to a local

    provision that is a regional provision must apply for each of the IPS. The approach is

    critical for ensuring consistency is retained between the provisions of each IPS.

    Finalising the Cradle Coast planning schemes

    If the Commission is satisfied that an interim planning scheme, including any

    modification required to an interim planning scheme, is in order having regard to all

    statutory requirements, it must obtain the approval of the Minister to make the

    interim planning scheme into a planning scheme if such planning scheme –

    a) complies with LUPAA s20 in terms of its purpose and provisions;

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 7

    b) complies with LUPAA s21 in terms of consistency and co-ordination to the

    planning schemes applying for adjacent municipal areas and with regard to

    the use and development of the Cradle Coast Region as a whole in social,

    economic and environmental terms

    c) complies with LUPAA s30E in that –

    (i) it contains common mandatory provisions;

    (ii) it contains applicable common optional provisions;

    (iii) it contains local provisions that are not directly or indirectly

    inconsistent with common provisions or an over-riding local

    provision or a conflicting local provision; and

    (iv) it is consistent with and likely to further the objectives and

    outcomes of the Cradle Coast Regional Land Use Strategy

    The Commission’s decision to make a planning scheme must be published in the

    Government Gazette.

    The decision to make a planning scheme revokes the interim planning scheme, and

    the final scheme becomes the enforceable planning scheme for the municipal district

    from the date notified in the Government Gazette.

    The Commission is required to take all reasonable steps to ensure that all of the final

    planning schemes for the Cradle Coast Region are to come into operation on the

    same day.

    Joint Report on Views and Opinions on Representations

    This Joint Report sets out the views and options of the planning authorities of the

    Cradle Coast Region in response to each of the matters raised in each representation.

    The Joint Report addresses the matters required in the Report to be provided to the

    Commission in accordance with LUPAA s30J.

    The interim planning schemes to which this report refers are –

    Burnie Interim Planning Scheme 2013

    Central Coast Interim Planning Scheme 2013

    Circular Head Interim Planning Scheme 2013

    Devonport Interim Planning Scheme 2013

    Kentish Interim Planning Scheme 2013

    King Island Interim Planning Scheme 2013

    Latrobe Interim Planning Scheme 2013

    Waratah Wynyard Interim Planning Scheme 2013

    West Coast Interim Planning Scheme 2013

    It is assumed that the version of each interim planning scheme to which

    representations relate is as contained in the Content Management System module of

    Planning Schemes Online as administered by the Tasmanian Planning Commission at

    the date on which each interim planning scheme was declared and notified.

    The planning scheme maps referenced in the Joint Report are those as declared and

    notified, and were then held in hard copy or as PDF files on the respective planning

    authority website.

    Hard copies of each IPS, including maps, are not included with the Joint Report.

    It is noted that each interim planning scheme has been subsequently modified to

    correct or introduce additional common mandatory provisions, specifically in relation

    to –

    a) clause 8.1 on information requirements from January 2014;

    b) Clause 9.1.1 and 9.2; and

    c) the standards on single and multiple dwelling development on land in the

    General Residential zone as directed by PD 4.1 from 28th

    February 2014

    Representations were not made on the modified mandatory provisions. However,

    the Joint Report makes observation on the modified common mandatory provision in

    association with a response on a representation in relation to the form of provision at

    the date of notification.

    It is noted the planning scheme maps for each of the IPS are now held on the

    Tasmanian Land Information System and linked to the IPS ordinance through the

    Content Management System.

    The format of the Report is -

    Volume 1

    a) An introductory statement

    b) A schedule indicating by municipal district the persons making

    representation and the nature of the provisions addressed in the

    representation.

    c) Tables 4 – 46 inclusive to identify the matters in representations and the

    planning authorities’ response for each issue.

    (i) Each Tableaddresses a particular set of provisions within the interim

    planning scheme ordinance.

    The Tables are set out in the sequence of the provisions within the

    interim planning scheme in accordance with the format and structure

    required by Planning Directive No 1.

    The approach requires that each of the matters in all of the

    representations that relate to a particular provision are identified and

    discussed within the same part of the Joint Report.

    Each matter is addressed in context of its position within the interim

    planning scheme so as to present the full scope of issues and allow

    consistency in the content of the advice provided to the TPC.

    The approach is consistent with the coordinated approach to local

    provisions and the objective for the best possible level of consistency

    between planning schemes.

    The format of the Joint Report means that the entirety of the matters

    in each representation on an interim planning scheme is not treated

    individually.

    The approach may be criticised in that it creates an apparently

    disjointed arrangement in the response provided for each

    representation; and does not allow a person to readily establish what

    has been said by the planning authorities on each matter in a

    representation or on the representation as a whole.

    However, the Joint Report format is in accordance with the

    instruction in LUPAA s30K for consolidation of representations. LUPAA

    s30K instructs that the TPC may disaggregate individual

    representations into component matters, and consolidate all like

    representations into a combined hearing and review process.

    The Joint Report anticipates such an approach and consolidates

    representations in accordance with the relative provisions of the IPS.

    a. Each issue is allocated an Issue Reference Number (1st column).

    Issue Reference Numbers do not relate to the reference number

    allocated to the entirety of a representation.

    The Representation Reference Number is included in the 4th

    column

    identifying for each matter the Person making the Representation to

    enable cross-reference to the original statement.

    (ii) The 2nd

    column indicates the matter addressed in the representation

    by reference to the applicable citation for the provision of the interim

    planning scheme or to the land assigned to a zone.

    (iii) The 3rd

    column identifies whether the issue relates to a common

    provision, a regional provision or a local provision.

    Local provisions relating to the zone to which land is assigned are

    included at the conclusion of issues for each zone provision under the

    heading of Land Assigned to Zone in Column 2.

    A colour code is included for ready reference –

    The distribution of matters raised in representation is –

    Nature of Provision

    Common Mandatory Provisions

    13%

    Regional provisions

    58%

    Provisions

    28%

    Other Matters 1%

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 8

    (iv) Column 4 identifies the person making the representation by reference

    to the Representation Reference Number and the name and contact

    details for the person.

    (v) A copy or summary of that part of the representation addressing each

    individual interim planning scheme provision is provided in the 5th

    Column.

    Copy in full of the representation text is included if the statement is

    relatively succinct.

    Summaries are intended to provide an overview, and may include

    direct quotes from part of the representation document.

    The original statement should be read in full in order to better grasp

    context and expression of the representation.

    (vi) The planning authorities’ response on each issue is provided in Column 6.

    The response contains a view and opinion on the merits of each issue and

    on operation of the interim planning scheme; whether modification is

    required; and the impact of the representation or modification on

    operation of the interim planning scheme as a whole.

    The response is the joint view and opinion of all of the planning authorities

    unless otherwise identified.

    If one or more planning authority hold an alternate or dissenting view on

    the merits or consequence of an issue in a representation, such planning

    authority is identified and the view is stated.

    If several representations address the same matter, the table is set out to

    provide a single statement of response.

    Appendix 1 contains the resolutions made by each planning authority to provide its views

    and opinions in relation to representations received on the municipal interim planning

    scheme; and to include such views and opinions in the Joint Report.

    Appendix 2 contains a summary of the substantive modifications proposed by the Joint

    Report to the common mandatory provisions and the regionally consistent local provisions

    as contained in the interim planning schemes

    Volume 2

    Contains a full copy of each representation received.

    The document is arrangement by representations received for each municipal district; and

    each representation is assigned its own reference number.

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 9

    Table 1 – Principles for response on matters raised in Representation

    Category

    Matters raised

    Principle to guide response

    1.

    Planning scheme reform outcomes

    (5 x representations)

    Adequacy of the IPS process to deliver on reform objectives for the Tasmanian

    planning system

    Express concern for whether the IPS simplify and improve the level of certainty in

    planning regulation; and for capacity to remove constraint on development and

    investment

    The IPS of the Cradle Coast Region have each been prepared in accordance with the mandatory common provisions on format and structure, and include the

    common provisions for residential development and bushfire prone areas.

    The IPS process cannot be responsible for resolving a failing in the expectation of a person that may be based on interpretation of information that did not come

    from the regional planning project. Nor does the IPS process invite opportunity for evaluating opinions on how the planning system could be better structured

    and operated.

    These are not matters in relation to an interim planning scheme.

    It is not appropriate that the Joint Report deliberate and provide advice on matters of general policy for how the planning system should operate; or provide a

    view on whether the IPS should be modified.

    For clarity, the Joint Report provides an explanation for why the issue is not a matter in relation to an IPS.

    2.

    Procedural Fairness

    (9 x representations)

    Question adequacy of the process for notification, including prior consultation,

    personalised invitations to comment, and denial of natural justice

    Notification on the IPS was conducted in accordance with the statutory process prescribed in LUPAA.

    Whether or not the notification process was compliant with statutory requirements is a matter of fact ascertainable by examining the actions and documents of

    the planning authorities.

    For clarity, the Joint Report provides an explanation for why the issue is not a matter in relation to an IPS.

    It is not appropriate that the Joint Report deliberate and provide advice on matters regarding the adequacy of the process prescribed by legislation.

    A person with a grievance on process may initiate a judicial review through avenues outside the TPC hearing.

    3.

    Drafting errors in the planning scheme

    ordinance

    (141 x representations)

    Identify errors in the planning scheme ordinance in relation to spelling, punctuation,

    formatting, numbering, and omissions.

    This category of representation addresses common mandatory provisions, regionally

    common provisions and local provisions.

    There are matters in relation to drafting errors that do not go to substance of an IPS.

    These matters can be treated as consequential amendments arising from a proof reading of the instrument, and do not impact on intent or meaning of provisions.

    The Joint Report indicates whether it is agreed a matter is an error or omission in drafting, and includes advice on the nature of any correction required.

    The TPC may direct in accordance with LUPAA s30M that modifications be made to correct errors in an IPS.

    LUPAA 301A and 37(1) both allow the TPC may dispense with notification of a change to a planning scheme if required to correct an error, remove an anomaly,

    clarify or simplify operation, remove any inconsistency against other regulation, make procedural changes, achieve consistency to common mandatory provisions,

    or for any other prescribed reason – subject only to a requirement that public interest will not be prejudiced.

    The principle to dispense with notification implies it is also not necessary to conduct a hearing.

    The principle should apply in relation to representations received on an IPS that identify errors in need of correction.

    There is no likelihood of compromising a public interest if spelling, punctuation and citation errors are corrected.

    There is little to be gained from hearing a party on such matters. Either the error exists or it does not.

    It can be said these are matters agreed between the parties. A decision panel in other jurisdictions is generally not required to hear further submissions on

    agreed facts.

    The TPC should be able to determine a representation relating to an error or omission in drafting without resort to a hearing.

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 10

    4.

    Errors in relation to the translation from

    the former planning scheme

    (88 x representations)

    Express concern for the correctness of translation from a zone under the former

    planning scheme into the most corresponding zone provided in the PD1 template.

    These matters are really questions of fact for whether there is an error in translating the purpose of a zone under a former planning scheme into the zone with the

    most corresponding purpose as provided in the PD1 template.

    The Joint Report provides advice on whether –

    i. the zone assigned under the former planning scheme has been correctly translated into the zone with the most corresponding purpose as provided under

    the PD1 template; or

    ii. a change in the purpose of the zone assigned to the land is reasonably required by a State Policy, mandatory directive, or for consistency to the CCR LUS

    Modification of an IPS to correct an error in the zone to which land is assigned may be dealt with in the same manner as suggested with respect to correction or

    errors and omissions of drafting.

    The Joint Report indicates whether an issue in a representation is agreed as a matter requiring modification to correct a mistake in translation of zone purpose or

    to deliver greater consistency to the objectives for the CCR LUS.

    It can be said these are matters on which there is agreement between the parties. A decision panel in other jurisdictions is generally not required to hear further

    submissions on agreed facts.

    LUPAA s30IA and 37(1) both allow the TPC may dispense with notification of changes to a planning scheme if required to remove an anomaly or clarify or simplify

    operation – subject only to a requirement that public interest will not be prejudiced.

    The principle to dispense with notification implies it is also not necessary to conduct a hearing.

    The principle should apply in relation to representations received on an IPS that identify opportunity or provide suggestion to improve the construction and

    expression of an IPS provision.

    There is little to be gained from hearing a party on such matters if the Joint Report supports modification.

    5.

    Construction of provisions in the planning

    scheme ordinance

    (208 x representations)

    Suggestion for improvement in construction or expression of individual provisions to

    improve clarity or certainty in operation and compliance without modification to the

    purpose or outcome.

    This category of representation addresses common mandatory provisions, regionally

    common provisions and local provisions.

    These matters are in relation to format and expression or the control content of a provision.

    Such matters address opportunity to improve clarity and certainty for operation and compliance, and are not concerned with changing the purpose of a provision.

    The Joint Report indicates the majority can be agreed as consequential modifications in the nature of LUPAA s37(1) for which there is no express or unintended

    change in purpose, meaning or outcome for each provision.

    These matters can be treated as consequential amendments.

    There is no likelihood of compromising a public interest if changes are made to expression or construction to improve clarity of individual provisions.

    There is little to be gained from hearing a party on such matters if the Joint Report agrees with the representation.

    It can be said these are matters agreed between the parties if the Joint Report agrees with the need for change. A decision panel in other jurisdictions is generally

    not required to hear further submissions on agreed facts.

    The Joint Report indicates whether an issue in a representation is agreed as a matter requiring modification to improve clarity in expression or construction of

    individual provisions.

    The Joint Report provides explanation for why some suggested changes are not agreed.

    LUPAA 301A and 37(1) both allow the TPC may dispense with notification of a change to a planning scheme if required to correct an error, remove an anomaly,

    clarify or simplify operation, remove any inconsistency against other regulation, make procedural changes, achieve consistency to common mandatory provisions,

    or for any other prescribed reason – subject only to a requirement that public interest will not be prejudiced.

    The principle to dispense with notification implies it is also not necessary to conduct a hearing.

    The principle should apply in relation to representations received on an IPS that identify improvement in expression or of individual provisions.

    There is little to be gained from hearing a party on such matters if the Joint Report supports modification.

    The TPC should be able to determine whether a representation offers constructive suggestion or identifies valid reason to make changes that will remove an

    anomaly or clarify or simplify operation of an IPS without need for a hearing.

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 11

    6.

    Protect or preserve the benefit of

    provisions contained in a former planning

    scheme ordinance

    (14 x representations)

    Seek to retain benefit of an unrealised opportunity provided under a former planning

    scheme, including for the types of permitted use, applicable standards, and the

    quantum in compliance tests.

    This category of representation addresses common mandatory provisions, regionally

    common provisions and local provisions.

    This is a separate category of representation seeking to retain elements of a former planning scheme in a manner with potential to impact on consistency

    between planning schemes in terms of how like maters are regulated.

    A loss in the individualism of provisions for like use or development as contained in former planning schemes is an unavoidable consequence in harmonising

    provisions in order to deliver consistency in the purpose and content of provisions for planning schemes applying between adjacent municipal districts.

    The Cradle Coast interim planning scheme process acknowledged it is inevitable that the finer grain of criteria for permitted activity, and for use and development

    standards, will change as provisions are harmonised. The outcome may be an increase or reduction in the level of intervention experienced and in the

    requirements for compliance relative to the provisions of a former planning scheme.

    The Joint Report indicates as a matter of principle that any shift in the nature of an opportunity or compliance test available under a former planning scheme and

    the opportunity or compliance test applying under the IPS for the corresponding zone or Code should be accepted if the general intent and outcome remain

    consistent.

    There is no imperative within the statutory intent for an IPS to protect the exact form of an opportunity that may have been available under a former planning

    scheme provided there is a comparable translation in purpose and outcome.

    The Joint Report suggests the provisions in an IPS should only be modified to protect or preserve provisions applying under a former planning scheme after having

    regard for whether –

    i. the common provisions or the regional provisions include opportunity to insert locality specific criteria that are different to the default acceptable solution

    for the applicable standard; or

    ii. the IPS standard effectively sterilises or unreasonably restrains opportunity to achieve complying use or development of a kind or form previously

    available; and

    iii. there is no alternate permit pathway provided in the IPS

    If modification is required, preference is that the change be effected by modification of the generic provision rather than by a provision that seeks to exclude

    operation of the standard and revert to the provision that pre-dates implementation of the IPS.

    These matters require exercise of judgement for whether –

    a) the IPS effectively sterilises or unreasonably restrains opportunity to achieve complying use or development of a like kind or form regardless of the permit

    pathway or criteria in applicable compliance test;

    b) the desirable to retain standards that applied under a former planning scheme in order only to avoid what may be perceived as a less certain or more

    onerous permit pathway under the IPS which could realise the opportunity provided by the former planning scheme but unsecured through a permit

    process prior to declaration of the IPS;

    c) it is fair and reasonable to create inequity between use or development on the basis of standards that differ only because of the temporal origin for the

    legal identity of a site;

    d) it is necessary for effective operation of an IPS to create an inconsistency between planning schemes in relation to standards on the same planning matter

    for reason only that the former planning instrument was different if there was and remains no need to be different;

    e) it is necessary for effective operation of an IPS to evidence a lack of commitment and consistency to the common standard prescribed in the CCR model IPS;

    and

    f) it is necessary for effective operation of an IPS to include provisions that by-pass an opportunity to demonstrate compliance to the objective through a

    permit pathway relying on performance criteria

    The Joint Report indicates for each matter whether protection of a former opportunity may be achieved where appropriate without inclusion of “saving

    provisions”.

    The Joint Report does not provide a consensus position on whether exception provisions should be introduced to retain former standards for particular use or

    development sites or localities.

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 12

    7.

    Change to the purpose for which land is

    zoned under the IPS

    (71 x representations)

    Seek to change the purpose for which land may be used by converting the zone

    assigned by translation from a former planning scheme zone into an IPS zone that

    does not have a corresponding strategic purpose.

    Representations typically reflect a desire to enhance opportunity for use or

    development.

    Representations in relation to zoning may express dissatisfaction that the zone has

    not been changed to establish an alternate land use purpose.

    In some instances a representation indicates the former and current IPS zone does

    not correlate to the established purpose for which the land is utilised.

    Representations relating to how land is assigned to a zone are described as local

    provision (LP) matters for the purpose of this Report.

    These representations seek to change local provisions in an IPS in relation to the zone to which land is assigned.

    The majority of representations refer to individual sites or discrete small localities.

    These matters are comparable in intended outcome to a scheme amendment or dispensation to change the zoning of land.

    The majority may be described as speculative or opportunistic in order to include individual sites as an increment on an adjacent zone; or changes that may

    involve a significant land area or facilitate a major departure from the purpose for which land is currently assigned.

    There are no representations comparable to LUPAA 40A matters which evidence a commitment to subsequently proceed with a particular kind of use or form of

    development in the event a change is made.

    There are a small few which describe a speculative use or development outcome if the impediment perceived in the applicable IPS for a specific site were to be

    removed.

    While representations for a change in zone may be described as being in relation to a local provision, there is a regional interest with regard to consistency in how

    land is assigned to a zone from both a strategic and operational perspective.

    a) It is debatable whether such representations should be entertained given the statutory purpose for an IPS process to translate and not convert.

    An IPS is not a general reform or review instrument.

    LUPAA 30I requires a representation must be in relation to an interim planning scheme. A representation may be invalid if it pursues an outcome that is

    beyond competence of an IPS.

    There is strong desire among government, industry and the community for the planning system to only activate the processes that are necessary to further

    a statutory outcome. There is no purpose in continuing and exhausting all stages in a land use planning process if it is clear a submission will fail.

    The Joint Report provides advice on whether a representation that seeks to modify the purpose or outcome of an IPS provision, including for the zoning of

    land, is valid against the statutory function for an IPS.

    Such change could follow a dispensation pathway if there is an urgent need to facilitate an outcome consistent with the CCR LUS but which was not

    reasonably contemplated at the time the IPS was declared.

    Alternatively, the change could be more appropriately addressed by a subsequent scheme amendment.

    The Joint Report suggests a representation for a change in the zone assigned to land in order to facilitate a purpose that was not intended by the former

    planning scheme is not a matter within the statutory function of an IPS unless –

    i. reasonably required for consistency to the CCR LUS and in accordance with the published municipal land use strategy; or

    ii. required to rectify an anomaly in the former planning scheme under which –

    a. translation to a corresponding IPS zone perpetuates a purpose that is inconsistent with the reality of the established land use and for which

    there is little likelihood of redeeming the land for the assigned purpose; or

    b. factors such as land capability, infrastructure provision or availability, natural hazards, or economic or cultural values clearly exclude use or

    development for the purpose intended by the zone assigned by direct translation into the IPS format

    b) In the event modifying an IPS to change the zone to which land is assigned is appropriate to the IPS process, the representation should not be further

    considered unless it adequately addresses the corresponding matters for consideration of any change in zone as provided for in LUPAA s30R and s32.

    Both LUPAA s30R and LUPAA s32 prescribe the considerations against which a departure from the current provisions of a planning scheme is to be assessed.

    For consistency to the planning processes required under LUPAA, the adequacy of a representation seeking to modify an IPS should be assessed against the

    same considerations.

    The matters in s30R or s32 should be the default considerations for any significant change in purpose or outcome of the IPS.

    A representation should contain sufficient information to demonstrate compliance to the applicable requirements in 30R or 32.

    The advice in the Joint Report should turn on the information provided with each representation.

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 13

    There is nothing expressly within the IPS representation process to allow a planning authority to request further information.

    There is considerable variation among representations in the scope and standard of supporting information.

    The majority of representations either fail to directly address the considerations in s30R or s32; or are very superficial in the nature and veracity of

    information provided to demonstrate compliance.

    If a representation does not adequately identify and address each of the matters in s30R or s32, it should fail.

    No opportunity should be allowed during the hearing process to substantially expand upon and embellish the scope or standard of information and analysis

    provided with the representation as made during the notification period.

    The Joint Report indicates for each representation whether the information provided is sufficient to establish the change is reasonably required and otherwise

    adequate to address each of the considerations that would apply under LUPAA s30R or s32.

    c) The Joint Report advises inadequate representations should not be allowed, and should be determined without need for a hearing.

    The planning process for an IPS implies expectation of a right to be heard if a representation is made.

    However, the right does not appear absolute, and can appropriately be restricted to only exist if a representation is in relation to an interim planning scheme.

    The nexus between the right to make a representation and the right to be considered or heard must be clearly understood and observed.

    PD1 clause 8.10 illustrates the position with respect to representations on a permit application. A representation is valid only in respect of the provision

    invoking discretion. It is not a general invitation to provide comment on any aspect of the permit application.

    A similar principle should be applied for representations on a planning scheme. If a representation is not particular to the purpose of an IPS it should be

    considered invalid.

    8.

    Appropriateness or adequacy of planning

    scheme ordinance provisions

    (199 x representations)

    Indicate the objectives and compliance tests may not be appropriate or adequate to

    the outcomes intended for the IPS, and that the IPS should be modified to insert or

    delete provisions.

    The suggested modifications intend a change to the purpose or outcome of a

    provision.

    This category of representation addresses common mandatory provisions, regionally

    common provisions and local provisions.

    These matters seek to diminish, embellish, or extend the purpose or outcome of an objective or compliance test.

    Such matters are more than corrections or improvement in expression. They address the substance of a provision.

    Representations variously argue the adequacy or relevance in purpose or objective, the effectiveness or relevance of an IPS compliance test against its objective;

    and a concern for how the IPS may unreasonably or unnecessarily restrict use or develop on a particular site.

    Suggested modification cannot be accommodated without risk of departure from purpose or intended outcome.

    Each must be reviewed for consistency to underpinning State and regional strategy and policy (including the CCR LUS), any mandatory direction, and for

    consistency to other provisions of the IPS; and to determine whether the suggested change has implication for what the provision intends or delivers.

    Resolution involves more than a judgement for compliance to standards for drafting.

    The Joint Report provides advice on whether a modification should be made for the reason that –

    i. The matter is in relation to an IPS;

    ii. The suggested change would improve operation of the IPS without significant variation to strategic purpose or for intended outcome of a provision;

    and

    iii. There is sufficient information provided in the representation to demonstrate compliance to the mandatory matters in LUPAA s30R or s32 for

    modification to the provisions of a planning scheme

    The Joint Report suggests the principles discussed against Category 7 in relation to acceptance of a representation, adequacy of information, and need for a

    hearing, are to apply if a representation requires significant change in the purpose or operation of an ordinance provision.

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 14

    9.

    Relevant agency provisions

    (18 x representations)

    Seek –

    a) expansion of exemptions for infrastructure use and development; and

    b) inclusion of additional provisions to –

    i. protect the operation and security of infrastructure assets; and

    ii. minimise likely impact on safety and amenity of use and

    development on land in proximity of existing and potential

    infrastructure assets

    These matters seek to elevate and expand the role of an IPS to facilitate and protect a

    particular form of utility use and development.

    These matters primarily concern interests of the electricity generating and

    transmission entities Hydro and Transend; and the road entity Department of

    Infrastructure, Energy and Resources.

    This category of representation addresses common mandatory provisions and

    regionally common provisions.

    This category deals specifically with representations by State agencies or business enterprises seeking to change the purpose or operation of provisions in order to

    create an advantage or benefit for the role or responsibilities of the agency or service provider.

    The merit or otherwise of the representations turns on –

    a) whether it is within the jurisdiction of a planning scheme to facilitate an exemption that provides for operational convenience of the infrastructure entity

    and allows use or development of a kind for which there is likely to be more than a low risk to purpose of the IPS; and

    b) whether it is within the competence of a planning scheme to assume a statutory responsibility vested in another statutory agency through legislation

    other than LUPAA

    There is no point in a hearing considering the merits of a representation if the matters are ultra vires the powers for which any planning scheme may make

    provisions or are matters for which a planning authority has no jurisdiction to enforce compliance.

    The Joint Report indicates it is not within the statutory competence of an IPS –

    i. to exempt use or development with potential to have more than a low risk for the statutory purpose of a planning scheme;

    ii. to make decisions with respect to the protection of infrastructure assets and to minimise likely risk to the community in circumstances where there is

    already a statutory responsibility conferred on an infrastructure entity; and

    iii. to extend or embellish exemption or protection provisions already available to an infrastructure entity under its enabling legislation

    The Joint Report indicates the representations made by infrastructure agencies to embellish exemptions and to include infrastructure asset protection provisions

    should not be allowed as matters consistent with the purpose and powers of an IPS.

    There is no need to conduct a hearing into the merit or otherwise of the substantive outcomes intended by the representations.

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 15

    Table 2 – Persons making a representation in relation to a notified Interim Planning Scheme for a municipal district of the Cradle Coast Region

    Allen, Geoff

    Appleby Hotel Pty Ltd (Dobson, Mitchell Allport)

    Atkins, Frank

    Atkinson, Justin

    Badcock Craig (Oldaker Street)

    Badcock, Craig

    Bell, Natalie

    Bennett, Alysia

    Bissett, Kim

    Blenkhorn, Rodney

    Boat Harbour Progress Association Inc (Wilson, Neville)

    Borlini, Pettina (Olivini Pty Ltd)

    Boxhall, Patricia

    Braid, Greg

    Briggs, John (Ecologically Sustainable Design Pty Ltd)

    Britton, Hazel & Ellison, Patricia

    Brumby, RC & LJ

    Burbury, Lonis

    Burnie Airport Corporation

    Burnie City Council

    Campbell, Barry

    Cannell, Elisabeth (1)

    Cannell, Elisabeth (2)

    Carson, Robert and Wendy

    Carson, Robert and Wendy (Irishtown Road)

    Cash, Greg and McMullen, Tija

    Cement Concrete & Aggregates Australia

    Central Coast Council

    Circular Head Council

    Clarke, William

    Colledge, Michele & Garth

    Collins, Sally

    Connelly, Gail (Lester Franks)

    Connolly, R

    Cooke, Robert

    Crawshaw, Christine

    Crawshaw, Ray

    Critchlow, Phillip & Audrey

    Cure, IJ

    Curtis, Glynis and Derek

    Dalby, Mary

    Dart, John

    Davis, Geoff and Patricia

    De Bomford, W

    Denwar Pty Ltd

    Department of Communication (Heazlett, Mark)

    Department of Infrastructure, Energy & Resources

    Devonport Bodyworks (Kerrison, Maurice)

    Devonport Central Pty Ltd (Bullock Consulting)

    Devonport City Council

    Dudley, Simon and Elizabeth

    Eberhardt, Adrian

    Enright, Mark

    EnviroPlan Australia (Wells, Micheal)

    Fisher, Glenn & Janet

    Fishman, FC & KR and Lambert, L

    Flanagan, Rebecca, and O’Rouke, Greg, and Bakker, Jan

    Forsyth, Janet

    Foster, D & J (Lester Franks)

    Freeman, Ron

    Fromberg, Bill

    Gamble, Richard

    Gibson, Jedda

    Goodstone Group (Planning Development Services)

    Gowan Motors (4 Planning Pty Ltd )

    Green Point Tas Pty Ltd (Nicholls, Richard)

    Guthrie, Rod

    Hall, Lesley

    Hamilton, Mary

    Hardy, RT & JM

    Harrisson, Patricia

    Heikkinen, M & A

    Heritage Tasmania (Fitzgerald, Liz)

    Hiscutt, Benjamin

    Hobbs, Rhonda (4 Planning Pty Ltd)

    Horne, Peter and Natalie

    Hoyle, Ian and Virginia

    Hudson, Alan

    Hydro Tasmania

    IASM Investments Pty Ltd (GHD Pty Ltd)

    James Ashworth

    Janney, Douglas

    Jensen-Schnapper, Lynn

    Johns, Jason & Sarah Johnson, Allan

    Johnston, David

    Jones, Annie & Joseph

    Jones, Cliff & Rhonda

    Jones, Faye

    Kay, KR

    Kentish Council

    Kentish Council (rural land)

    Kernan, J and W (Lester Franks)

    Kerr, William

    King Island Council

    Kossler, Margaret & Peter

    Kurrle, Peter & Dianne (Carport Central)

    Lange, Aaron

    Latrobe Council

    Lead Light Investments (Boardman, Evan)

    Leary, Mike

    Lester Franks

    Long, Adam

    Long, Shaun

    Lynd, Philip & Ann

    Martin Gill

    McNab, John

    Meander Valley Council

    Mersey Community Care (Lester Franks)

    Michell Hodgetts & Associate - Plunkett, Paul (Myalla)

    Michell Hodgetts & Associates - Plunkett, Paul (Elliott)

    Michell Hodgetts & Associates - Plunkett, Paul (Preolenna

    Road)

    Michell Hodgetts & Associates - Plunkett, Paul (Tollymore

    Road)

    Michell Hodgetts & Associates (Turgah Road)

    Milne, RA & JE

    Morgan, Kevin

    Nettleton, David

    New Bounty Pty Ltd (Lester Franks)

    Overton, Andrew

    Owens, M

    Parker, Beverly (Environmental Services & Design Pty Ltd)

    Parker, KJ & RA

    Parsons, David

    Peisker, Joe

    Penguin Caravan Park (IreneInc)

    Pitt & Sherry (Dion Lester)

    Poke, Jonathon & Desmond

    Porteus, Timi

    Priestley, R

    Private Forests (Ravenwood, Ian)

    Railpine P/L (Environmental Service and Design Pty Ltd)

    Redruth Trading Co (Lester Franks)

    Roberts-Thomson, Andrew

    Rogers, T & OM

    Rynmarc Pty Ltd (Bullock Consulting)

    Sadler, Duncan

    Sands, Richard

    Shields, GM

    Simplot (Dazeley, G)

    Simplot (West, David)

    Southern Cross Care (Tas) Inc (Fabrzio, Nic)

    Southern Cross Care (Tas) Inc (Sadek, Richard)

    Squeaking Point Properties Pty Ltd (Planning Development

    Services)

    Stammers, Mrs M

    Stewart, Leonie, and Brewster, Kevin

    Storay, M and K (Lester and Franks)

    Stuart, K

    Stuart, R

    Stubbs, Brian and Lorraine

    Sushames, Renee

    Swain, Dale & Dorothy

    Sweeney, Michael

    Sweetman, Vivienne

    Talbot, Mike

    Tall Timbers Tasmania Pty Ltd

    Tarver, C & K

    Tascott Carpet et al (Neil Shephard & Associates)

    Tasports (Planning Development Services)

    Thomson, Debbie

    Thorn, Jennifer

    Thorne, Lyndal

    Timms, RC & HM

    Transend (Goodman, Gina)

    Turners Beach Coastcare Inc

    University of Tasmania (ireneinc)

    Van Der Weide, Robert and Toni

    Walker, Geoff

    Waratah-Wynyard Council

    Ware, Barry

    Waterfront Wynyard Motel (Hilliger, Cyndia and McErlain,

    Justin)

    Webb, Rose

    Weitjens, Jed (FJA Solutions)

    West Coast Council

    West Coast Recreation Association (Giles, Max and

    Croswell, Anthony)

    White, Jeffery

    Whitney, Brian

    Wigg, GV and Sons

    Williams, Geoff

    Wilson, Darren

    Woodhouse, Colin (IreneInc)

    Worthen, Phillip

  • 30J Joint Report on Representations in relation to the notified Interim Planning Schemes of the Cradle Coast Region – 30th June 2014 Page | 16

    Table 3 – Persons making a Representation in relation to a notified Interim Planning Scheme for a municipal district of the Cradle Coast Region by municipal district and issue addressed in the Representation

    BURNIE CITY COUNCIL

    REP

    NO. Person making Representation

    Mandatory

    Provisions

    Regional

    Provisions

    Local

    Provisions

    Other

    Matters

    1

    Bennett, Alysia

    1

    Issue 691

    1

    Issue 703

    2

    Boxhall, Patricia

    1

    Issue 705

    3

    Burbury, Lonis

    1

    Issue 419

    4

    Burnie City Council

    Earle, Patrick

    24

    Issue 24, 26, 27, 28, 32, 34, 35, 39, 41, 42, 52, 55, 58, 60,

    62, 68, 71, 75, 78, 79, 82, 86, 89, 91, 642, 647, 650, and

    657,

    124

    Issue 20, 21, 100, 102, 106, 112, 118, 119, 130, 131, 144,

    168, 169, 171, 173, 174, 188, 191, 211, 217, 219, 220,

    230, 232, 235, 236, 254, 259, 260, 264, 268, 277, 280,

    285, 293, 295, 296, 297, 299, 305, 306, 307, 310, 314,

    315, 316, 318, 324, 325, 326, 335, 340, 342, 343, 344,

    346, 348, 357, 358, 360, 362, 363, 364, 365, 367, 368,

    369, 372, 373, 384, 390, 397, 398, 401, 413, 414, 415,

    416, 433, 437, 438, 441, 448, 455, 465, 470, 482, 573,

    578, 582, 588, 593, 594, 601, 602, 605, 608, 611, 630,

    633, 635, 658, 659, 669, 677, 683, 684, 694, 715, 718,

    720, 724, 725, 729, 731, 740, 747, 748, 749, 765, and

    767,

    4

    Issue 151, 181, 238, and 265

    -

    5

    Campbell, Barry

    1

    Issue 380

    6

    Cement Concrete & Aggregates Australia

    3

    Issue 481, 670, and 761

    7

    Clarke, William

    1

    Issue 618

    8

    Cooke, Robert

    BCC & CCC

    2

    Issue 424, and 446

    9

    Crawshaw, Christine

    1

    Issue 707

    10

    Crawshaw