    PROJECT DELIVERY METHODS

    ARE 413

    CONSTRUCTION MANAGEMENT

    CLASS- 5

    ByBy

    ZulfikarZulfikarAliyuAliyuAdamuAdamu

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    2/43

    Presentation OutlinePresentation Outline

    Project Delivery Methods

    Definition

    Types of Project Delivery Methods

    Traditional

    Design- Build

    Professional Construction Management (PCM)

    BOT ( Build Operate Transfer)

    Advantages & Disadvantages of various PDM

    Summary

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    3/43

    Objectives of Class :Objectives of Class :

    To introduce various types of project delivery methods.

    To distinguish between the common project delivery methods.

    To introduce different types of contract and to differentiate

    between the different contracting methods.

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    4/43

    Project Delivery Methods : What is it ?

    The term delivery method means the approachThe term delivery method means the approachused to organize the project team so as toused to organize the project team so as to

    manage the entire designing and buildingmanage the entire designing and building

    (design(design--build) process.build) process.

    The owner needs to decide whichThe owner needs to decide whichdesigners to hire, when to hire them,designers to hire, when to hire them,

    and under what type of contract ?and under what type of contract ?

    The owner also needs to decide whenThe owner also needs to decide when

    to hire the construction professionalto hire the construction professional

    and under what type of contract ?and under what type of contract ?

    Which organization gets hired first?Which organization gets hired first?

    Do both organizations report to theDo both organizations report to the

    owner, or does one report to the other?owner, or does one report to the other?

    Project Delivery method is anProject Delivery method is anorganizational concept which assigns specificorganizational concept which assigns specific

    responsibilities and authorities to people and organizationsresponsibilities and authorities to people and organizations and which definesand which defines

    relationship of the various elements in construction of a projecrelationship of the various elements in construction of a project.t.

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    5/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    6/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    7/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    8/43

    Definitions: Project Delivery systems

    A project delivery system is the method by which a constructionA project delivery system is the method by which a construction project isproject is

    executed.executed.

    It is the first allocation of base responsibilities between theIt is the first allocation of base responsibilities between the owner, designowner, design

    professional and contractor. Thus, the project delivery system iprofessional and contractor. Thus, the project delivery system is the foundations the foundation

    on which all subsequent negotiations will be based.on which all subsequent negotiations will be based.

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    9/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    10/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    11/43

    Types of PDM

    Types of Project Delivery Methods:

    Traditional

    Design- Build (Turnkey)Professional Construction Management

    (PCM)BOT ( Build Operate Transfer)

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    12/43

    The Four Phases(every project goes through)

    DesignPlanning Bid Construction Occupancy

    NEED

    TraditionalLinear Process

    Design

    Planning

    Occupancy

    Construction

    Fast-Tracking

    Process

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    13/43

    Traditional

    The owner hires a design professional who prepares a complete seThe owner hires a design professional who prepares a complete set oft ofcontract documents for the owner for a design fee.contract documents for the owner for a design fee.

    The owner either negotiates a price with a general contractor orThe owner either negotiates a price with a general contractor or bids out thebids out thework.work.

    The general contractor is totally responsible for delivering theThe general contractor is totally responsible for delivering the completedcompletedproject as spelled out in the contract documents.project as spelled out in the contract documents.

    The general contractor may subcontract out parts of the projectThe general contractor may subcontract out parts of the project, with each, with eachsubcontractor reporting directly to the general contractor.subcontractor reporting directly to the general contractor.

    The designer may be involved in overseeing the construction workThe designer may be involved in overseeing the construction workin thein thefield.field.

    In this delivery method no direct, formal relationship exists beIn this delivery method no direct, formal relationship exists between thetween the

    designer and the builder. They communicate only through the ownedesigner and the builder. They communicate only through the ownerr

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    14/43

    Traditional

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    15/43

    Typical Design-Bid-Build

    Process(The Four Phases)

    DesignPlanning Bid Construction Occupancy

    NEED

    Typical

    Design-Bid-Build

    Process

    Design Team Contractor

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    16/43

    Advantages- Traditional PDM

    Familiarity:Familiarity: Most owners, designers, and builders have workedMost owners, designers, and builders have workedunder this framework on many projects and therefore are familiarunder this framework on many projects and therefore are familiar

    with the system.with the system.

    Overall Job coordination:Overall Job coordination:Their control systems, documentation,Their control systems, documentation,and organizations are all set up to manage this process. Theand organizations are all set up to manage this process. The

    workers, subcontractors, and vendors also understand the system,workers, subcontractors, and vendors also understand the system,

    improving overall job coordination.improving overall job coordination.

    Owner can get aOwner can get a firm fixed pricefirm fixed price for the project before any workfor the project before any workbegins. The owner knows before construction begins what the costbegins. The owner knows before construction begins what the costof the project will be.of the project will be.

    Opportunity to get goodOpportunity to get goodprice competitionprice competition from the open market.from the open market.

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    17/43

    Pros and Cons of the Traditional Approach

    AdvantagesAdvantages DisadvantagesDisadvantages

    Price competitionPrice competition The approach takes a long time .The approach takes a long time .

    Total cost is known beforeTotal cost is known before

    construction startsconstruction startsDesign does not benefit fromDesign does not benefit from

    construction experienceconstruction experience

    WellWell--documented approach useddocumented approach used

    in most government projects donein most government projects done

    for public worksfor public works

    Conflicts between owner & G.C.Conflicts between owner & G.C.

    and betweenand betweenAlEAlE & G.C.& G.C.

    Changes may lead to disputes andChanges may lead to disputes and

    claimsclaims

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    18/43

    Design-Build

    In this approach, a single organization is responsible for perfoIn this approach, a single organization is responsible for performingrmingboth design and construction .both design and construction .

    Within the designWithin the design--build organization, parts of the design may bebuild organization, parts of the design may besubcontracted to specialist consultants.subcontracted to specialist consultants.

    Being responsible for both design and construction, the designBeing responsible for both design and construction, the design--buildbuild

    contractor carries most of the project risks, and this can meancontractor carries most of the project risks, and this can meanadditional cost to owner.additional cost to owner.

    The owner's role in this approach is minimal and is only to exprThe owner's role in this approach is minimal and is only to express hisess hisor her objectives and specifications precisely before detailed dor her objectives and specifications precisely before detailed design isesign isstarted.started.

    Historically, the designHistorically, the design--build approach has been used on large,build approach has been used on large,privately funded, industrialprivately funded, industrial--sector projects. Recently, however, thissector projects. Recently, however, this

    approach has begun to be used on commercial building projects, sapproach has begun to be used on commercial building projects, someomepublicly funded.publicly funded.

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    19/43

    Design-Build

    Design-Build

    Firm

    Owner

    Subcontractors and SuppliersDesigners and Consultants

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    20/43

    Design-Build

    OWNEROWNER

    DESIGNDESIGN--BUILDBUILD

    FIRMFIRM

    design

    subcontractors

    suppliers

    construction

    subcontractorsdesign

    subconsultants

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    21/43

    Typical Design/Build Process

    (The Four Phases)

    NEED

    Design

    Planning

    Occupancy

    Construction

    Typical

    Design/Build

    Process

    Design/Build

    Team

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    22/43

    Design-Build Advantages Good communication occurs between the design team and theGood communication occurs between the design team and the

    construction team. Allows for constructability analyses and valuconstruction team. Allows for constructability analyses and valueeengineering.engineering.

    This collaboration allows the project to be easily fastThis collaboration allows the project to be easily fast--tracked,tracked,

    cutting down on the designcutting down on the design--build time for the project.build time for the project.

    Good cost estimating and scheduling should occur throughout theGood cost estimating and scheduling should occur throughout theentire project.entire project.

    LongLong--lead item identification and ordering should also be able tolead item identification and ordering should also be able to

    proceed smoothly.proceed smoothly.

    In general, this arrangement allows easier incorporation of chanIn general, this arrangement allows easier incorporation of changesges

    due to changed scope or unforeseen conditions than in the otherdue to changed scope or unforeseen conditions than in the other

    arrangements, since the coordination is to occur within the samearrangements, since the coordination is to occur within the same

    company.company.

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    23/43

    Pros and Cons of the Design-Build ApproachAdvantagesAdvantages DisadvantagesDisadvantages

    Single point of responsibility forSingle point of responsibility for

    ownerowner

    New learning curve for ownersNew learning curve for owners

    Reduced conflict. Less adversaryReduced conflict. Less adversary

    relationshipsrelationshipsA/E doesnA/E doesnt work directly fort work directly for

    OwnerOwner

    Time can be reduced if the designTime can be reduced if the design--

    build company overlaps design andbuild company overlaps design and

    constructionconstruction

    Cost may not be known until the endCost may not be known until the end

    of designof design

    Coordination between design andCoordination between design andconstructionconstruction

    New learning curve for ownersNew learning curve for owners

    Easier implementation of changesEasier implementation of changes DesignDesign--build company may reducebuild company may reducequality to save cost Constraints with publicquality to save cost Constraints with public

    lawslaws

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    24/43

    How Are Design-Builders

    Organized?

    Integrated DesignIntegrated Design--Build FirmBuild Firm

    Contractor as leadContractor as lead

    A/E as leadA/E as lead

    Joint VentureJoint Venture

    Developer as leadDeveloper as lead

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    25/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    26/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    27/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    28/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    29/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    30/43

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    31/43

    BOT (Build Operate Transfer)

    The term BuildThe term Build--OperateOperate--Transfer (BOT) was first coined by ExTransfer (BOT) was first coined by Ex--

    Prime Minister of Turkey,Prime Minister of Turkey,TurgutTurgut OzalOzal in 1984in 1984

    Essentially in a BOT project delivery method, a private entity,Essentially in a BOT project delivery method, a private entity,

    usually a consortium is responsible for financing, construction,usually a consortium is responsible for financing, construction,

    operation and maintenance of the facility for agreed durationoperation and maintenance of the facility for agreed duration

    known as Concession period and at the end of the period, transfeknown as Concession period and at the end of the period, transfersrsthe ownership of the facility to the government.the ownership of the facility to the government.

    A BOT mechanism is a complex structure comprising multiple,A BOT mechanism is a complex structure comprising multiple,

    interinter--dependent agreements among various participants.dependent agreements among various participants.

    The concession agreement is between the government and theThe concession agreement is between the government and the

    concessionaire. The concession agreement is regarded as theconcessionaire. The concession agreement is regarded as the

    heartheart of a BOT projectof a BOT project

    Examples of BOT ProjectsExamples of BOT Projects

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    32/43

    Examples of BOT ProjectsExamples of BOT Projects

    BOT Contractual StructureBOT Contractual Structure

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    33/43

    BOT Contractual Structure

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    34/43

    BOT (Build Operate Transfer)

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    35/43

    BOT Advantages The private sector invests directly in the development of infrasThe private sector invests directly in the development of infrastructure,tructure,

    thereby reducing public debt, balancing the budget deficit, anthereby reducing public debt, balancing the budget deficit, andd

    reduced role of public sector. Financing mechanism for infrastrreduced role of public sector. Financing mechanism for infrastructureucture

    The private firms are more efficient, hence project or service cThe private firms are more efficient, hence project or service can bean be

    delivered at lower costdelivered at lower cost

    BOT projects create business opportunities for the local privatBOT projects create business opportunities for the local privatee

    sector, create employment avenues as well as attract substantiasector, create employment avenues as well as attract substantiall

    foreign direct investmentforeign direct investment

    BOT projects help in facilitating transfer of technology by intBOT projects help in facilitating transfer of technology by introducingroducing

    international contractors in the host countriesinternational contractors in the host countries

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    36/43

    BOT Disadvantages

    BOT is not a easy method and requires high capability ofBOT is not a easy method and requires high capability of

    promoters.promoters.

    Not suitable for smaller projects. Victorian Government ofNot suitable for smaller projects. Victorian Government of

    Australia has suggested that projects with a value of less thanAustralia has suggested that projects with a value of less than

    Australian dollar $15m are unlikely to gain benefits from BOTAustralian dollar $15m are unlikely to gain benefits from BOTdelivery method.delivery method.

    The success of BOT project depends upon successful raising ofThe success of BOT project depends upon successful raising of

    necessary finance.necessary finance.

    Transaction costs are high, they amount to 5Transaction costs are high, they amount to 5--10% of total project10% of total project

    costcost

    BOT projects are successful only when substantial revenues areBOT projects are successful only when substantial revenues aregenerated during the operation phase.generated during the operation phase.

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    37/43

    Professional Construction Management

    In this approach, the owner appoints a PCM organization (also knIn this approach, the owner appoints a PCM organization (also known asown as

    construction management organization) to manage and coordinate tconstruction management organization) to manage and coordinate thehe

    design and construction phases of a project using a teamwork appdesign and construction phases of a project using a teamwork approach.roach.

    The design may be provided by specialist design firms and in soThe design may be provided by specialist design firms and in some casesme cases

    by the PCM organization.by the PCM organization.

    With a high level of coordination between the participants, innoWith a high level of coordination between the participants, innovativevativeapproaches of overlapping design and construction (i.e., fastapproaches of overlapping design and construction (i.e., fast-- tracking)tracking)

    can be adopted.can be adopted.

    The PCM organization aims at holding a friendly position similarThe PCM organization aims at holding a friendly position similar to thatto thatof the consultants in the traditional approach.of the consultants in the traditional approach.

    The services offered by the PCM organization overlap those tradiThe services offered by the PCM organization overlap those traditionallytionally

    performed by the architect, the engineer, and the contractor.performed by the architect, the engineer, and the contractor.

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    38/43

    Professional Construction Management

    This may include:This may include:

    management and programming of design;management and programming of design;

    cost forecasting and financial arrangements;cost forecasting and financial arrangements;

    preparation of tender documents; tender analysispreparation of tender documents; tender analysis

    and selection of contractors;and selection of contractors;

    selection of methods of construction;selection of methods of construction;

    planning and scheduling construction works;planning and scheduling construction works;

    materials procurement and deliverymaterials procurement and delivery expeitionexpeition

    Although this approach is likely to prove marginally more expensAlthough this approach is likely to prove marginally more expensive thanive than

    the traditional approach, it offers greater guarantee of performthe traditional approach, it offers greater guarantee of performance andance andthe potential to avoid time overruns and to reduce the cost of cthe potential to avoid time overruns and to reduce the cost of claims.laims.

    The payment to the PCM organization is usually a fixed fee or aThe payment to the PCM organization is usually a fixed fee or a

    percentage of the total project cost.percentage of the total project cost.

    Use of PCM approach, should be considered when there is a need fUse of PCM approach, should be considered when there is a need for timeor timesaving and flexibility for design changes, and the owner has inssaving and flexibility for design changes, and the owner has insufficientufficient

    management resourcesmanagement resources

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    39/43

    Professional Construction ManagementPCM Agency with GC

    Owner

    A/E

    AgencyCM

    Designers and Consultants

    GC

    Subcontractors and Suppliers

    OWNEROWNER

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    40/43

    Construction Management: Agency Form

    ARCHITECTARCHITECT

    OWNEROWNER

    Architects

    design

    consultants

    subcontractors

    LIMITED

    CONSTRUCTION

    ADMINISTRATION

    CMaCMa

    DETAILED

    CONSTRUCTION

    COORDINATION

    FEASIBILITY

    +COST DATA

    materials suppliers

    GENERALGENERAL

    CONTRACTORCONTRACTOR

    DESIGN

    DATA

    Source: Modified AL( 1998)

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    41/43

    4141PCM Advantages & Disadvantages

    Advantages over traditional A/E construction administration:Advantages over traditional A/E construction administration:

    CM with a construction background may be BETTERCM with a construction background may be BETTER

    QUALIFIEDQUALIFIED

    CM provides greater QUANTITY of construction phaseCM provides greater QUANTITY of construction phaseservicesservices

    CM often assumes greater DEGREE of control overCM often assumes greater DEGREE of control over

    contractorscontractors

    limitations: thelimitations: the professionalprofessional oror agentagent CM:CM:

    DOES NOT guarantee construction cost or timeDOES NOT guarantee construction cost or time

    DOES NOT perform any work or contract with the tradeDOES NOT perform any work or contract with the trade

    contractorscontractors

    IS NOT RESPONSIBLE for their performanceIS NOT RESPONSIBLE for their performance usually DOES NOT assume responsibility for safetyusually DOES NOT assume responsibility for safety

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    42/43

    Pros and Cons of the PCM ApproachAdvantagesAdvantages DisadvantagesDisadvantages

    Utilization of construction skills at allUtilization of construction skills at all

    stages with no conflict among participantsstages with no conflict among participants

    Higher owner involvement andHigher owner involvement and

    responsibilitiesresponsibilities

    Independent evaluation of cost andIndependent evaluation of cost and

    schedule to the best owner interestschedule to the best owner interest

    Need skilled construction managersNeed skilled construction managers

    Time could be much lessTime could be much less PCM fees (up to 4%)PCM fees (up to 4%)

    Principals such as "value engineeringPrincipals such as "value engineering

    could be applied in all phasescould be applied in all phases

  • 8/12/2019 Course Presentations 5 Project Delivery Methods

    43/43

    CONCLUSION

    Types of Project Delivery Methods

    Traditional

    Design- Build

    Professional Construction Management (PCM)

    BOT ( Build Operate Transfer)

    Advantages & Disadvantages of various PDM