Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS...
Transcript of Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS...
![Page 1: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/1.jpg)
0
Cotton Belt Corridor
Open House Meetings
September 2017
![Page 2: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/2.jpg)
1
• Open House format with break for brief presentation and Question/Answer
• Allows for one-on-one discussions with staff
• Brief presentation to outline:
– Where we are in the process
– Where we go next
– How you can stay involved and informed
Welcome
![Page 3: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/3.jpg)
2
Open House Information
![Page 4: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/4.jpg)
3
Open House Information
• Alignment Plan and Profile maps
• Specific Alignment Coordination areas– DFW Airport, Cypress Waters, Downtown Carrollton, CityLine, Facilities
• Stations – Platform Concepts and Site Layouts
• Noise and Vibration – Methodology, Measurement Sites and Existing Conditions
• Environmental Topics – Historic, Water Resources, etc.
• Project Topics – Vehicle, Schedule, Ridership, etc.
• Funding/Financing
![Page 5: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/5.jpg)
4
• 12 Potential Stations• Initial 30/60-minute peak and off-peak
service• Future 20 minute peak service
![Page 6: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/6.jpg)
5
aA1
TEXRail Grade SeparationExisting Grade SeparationProposed Grade Separation
cA
B C D EF
G
ba
1
2 3
45
KJ
6
H I
Key Existing Grade Separation
A SH 121
B IH 635
C PGBT
D IH35E/Frontage
E Green Line LRT
F NDT
G Preston Road
H Synergy Park
I Renner Road
J PGBT
K Red/Orange Line LRT
Key TEXRail Grade Separation
a S.B. Frontage International/Ramps
b North Airfield Drive
c SH 114
Key Proposed Grade Separation
1 S. Belt Line Road
2 BNSF/Madill Sub
3 Midway Road
4 Coit Road
5 US 75
6 Plano Parkway
Preliminary Grade Separation Analysis
a
b
c
A
C
D
F
G
K
J
H
B
E
I
1
2
3
4
5
6
![Page 7: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/7.jpg)
6
Community Integration
• Community Integration features such fences, walls, trails, landscaping, etc. will be incorporated into the project subsequent to identification of impacts and required mitigation
• DART will work in cooperation with local jurisdictions for implementation of community integration features, where appropriate
![Page 8: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/8.jpg)
7
• Cities along corridor have requested trails be incorporated into plan
• DART Board Policy indicates that DART will provide opportunities within our right-of-way for trails where feasible
• DART will work in cooperation with NCTCOG and local jurisdictions toward implementation of trails along corridor
Trails
![Page 9: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/9.jpg)
8
Trails Example
![Page 10: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/10.jpg)
9
Where We are in the Process
![Page 11: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/11.jpg)
10
Process Overview
• DART is in the Preliminary Engineering/ Environmental Impact Statement (PE/EIS) Process
• Developing engineering plans to a 10% level of design to support EIS analysis and provide basis for final design and future Design-Build contract
• The EIS is a public disclosure document and will: ‒ Clear the full double-track project
o Initial implementation may have single-track segments or deferred stations
‒ Document the project design and identified impacts
‒ Outline mitigation commitments to address impacts
![Page 12: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/12.jpg)
11
Schedule Overview
PE/EIS phase is anticipated to be complete in Spring 2018
![Page 13: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/13.jpg)
12
Process OverviewKey Milestones in PE/EIS process
Aug 2016 Project Kick-Off
May 2017 Sept 2017 Nov/Dec 2017
5% PE/Draft EIS Existing Conditions
• Basis for impact analysis
• Identification of impacts is initiated
• Obtain community feedback on design progress and existing conditions
5-10% PE/ Preliminary Draft
EIS Findings
• Impact analysis complete
• Mitigation solutions or range of options developed
• Community review of potential impacts and proposed mitigation
Concept Design/ Key Issues for
Draft EIS
• Obtain community input on key issues
• Data collection initiated for engineering and environmental issues
WE ARE HERE
![Page 14: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/14.jpg)
13
Process OverviewDraft and Final EIS
Feb 2018 Spring 2018
Final EIS
• Documents and addresses substantive comments received during DEIS comment period
• Outlines mitigation commitments
• Notice of Availability for 30 days prior to Federal Record of Decision (ROD)
• ROD requires Mitigation Monitoring Program (MMP)
10% PE and Draft EIS Public Hearings
• Draft EIS will be published for a 45-day public and agency comment period
• Written and verbal comments documented and assessed for Final EIS consideration
![Page 15: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/15.jpg)
14
Where We Go Next
![Page 16: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/16.jpg)
15
What Happens after PE/EIS?
• DART will engage a Final Design team to advance design plans
• Final Design plans will incorporate mitigation commitments as outlined in the Mitigation Monitoring Program (MMP)
• The MMP is updated quarterly and reported to Federal agencies to track mitigation
• Community and agency involvement will continue through design and construction
![Page 17: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/17.jpg)
16
How you can stay involved and informed
![Page 18: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/18.jpg)
17
Stay Involved and Informed
• Attend meetings
• Provide feedback on potential impacts and mitigation options
• Stay involved as design progresses
• Email: [email protected]
• Website: www.DART.org/cottonbelt
• Sign up for project alerts
![Page 19: Cotton Belt Corridor - DART.org · •Brief presentation to outline: ... Key Milestones in PE/EIS process Aug 2016 Project Kick-Off May 2017 Sept 2017 Nov/Dec 2017 5% PE/Draft EIS](https://reader033.fdocuments.in/reader033/viewer/2022050114/5f4b6eca4461ed51ee70d2f1/html5/thumbnails/19.jpg)
18
Questions?