Cost Estimation. Problem. Our ability to realistically plan and schedule projects depends on our ability to estimate project costs and development efforts In order to come up with a reliable cost estimate, we need to have a firm grasp on the requirements, as well as our approach to meeting them - PowerPoint PPT Presentation

Transcript of Cost Estimation

Page 1: Cost Estimation

Cost Estimation

Page 2: Cost Estimation

Problem• Our ability to realistically plan and

schedule projects depends on our ability to estimate project costs and development efforts

• In order to come up with a reliable cost estimate, we need to have a firm grasp on the requirements, as well as our approach to meeting them

• Typically costs need to be estimated before these are fully understood

Page 3: Cost Estimation

Estimating uncertainty

Boehm 1981

Page 4: Cost Estimation

What are project costs?

• For most software projects, costs are:

• Hardware Costs

• Travel & Training costs

• Effort costs

Page 5: Cost Estimation

What are effort costs?

• Effort costs typically largest of the 3 types of costs, and the most difficult to estimate.

• Effort costs include:– Developer hours– Heating, power, space– Support staff; accountants, administrators, cleaners,

management– Networking and communication infrastructure– Central facilities such as rec room & library– Social security and employee benefits

Page 6: Cost Estimation

Effort cost estimation - Overhead

• Everything other than salaries

• OSU example: – 45% for benefits– 46% for “indirect” costs (space, infrastructure etc)

calculated on top of everything else

$1,000 +benefits ($450) + infrastructure ($667)

= $2,117

Page 7: Cost Estimation

Software cost estimation – Boehm (1981)

• Algorithmic cost modeling– Base estimate on project size (lines of code)

• Expert judgment– Ask others

• Estimation by analogy– Cost based on experience with similar projects

• Parkinson’s Law– Project time will expand to fill time available

• Pricing to win– Cost will be whatever customer is willing to pay

• Top-down estimation– Estimation based on function/object points

• Bottom-up estimation– Estimation based on components

Page 8: Cost Estimation

Aggravating & mitigating factors

• Market opportunity• Uncertainty/risks• Contractual terms• Requirements volatility• Financial health• Opportunity costs

Page 9: Cost Estimation

Cost drivers

• Software reliability • Size of application

database • Complexity • Analyst capability • Software engineering

capability • Applications experience • Virtual machine

experience • Programming language

expertise

• Performance requirements • Memory constraints • Volatility of virtual machine • Environment • Turnaround time • Use of software tools • Application of software

engineering methods • Required development

schedule

Page 10: Cost Estimation

Productivity metrics

• Lines of code– Simple, but not very meaningful metric– Easy to pad, affected by prog language– How to count revisions/debugging etc?

• Function points– Amount of useful code produced

(goals/requirements met)– Less volatile, more meaningful, not perfect

Page 11: Cost Estimation

Function points

Function points are computed by first calculating an unadjusted function point count (UFC). Counts are made for the following categories (Fenton, 1997):– External inputs – those items provided by the user that

describe distinct application-oriented data (such as file names and menu selections)

– External outputs – those items provided to the user that generate distinct application-oriented data (such as reports and messages, rather than the individual components of these)

– External inquiries – interactive inputs requiring a response – External files – machine-readable interfaces to other systems – Internal files – logical master files in the system

Each of these is then assessed for complexity and given a weighting from 3 (for simple external inputs) to 15 (for complex internal files).

Page 12: Cost Estimation

Unadjusted Function Point Count (UFC)

  Weighting Factor

Item Simple Average Complex

External inputs 3 4 6

External outputs 4 5 7

External inquiries 3 4 6

External files 7 10 15

Internal files 5 7 10

Each count is multiplied by its corresponding complexity weight and the results are summed to provide the UFC

Page 13: Cost Estimation

Object points

Similar to function points (used to estimate projects based heavily on reuse, scripting and adaptation of existing tools)

• Number of screens (simple x1, complex x2, difficult x3)

• Number of reports (simple x2, complex x5, difficult x8)• Number of custom modules written in languages like

Java/C x10

Page 14: Cost Estimation

Function points -> Lines of code

200-300 LOC/Function point in assembly

Multiplication factor by language

Programmer productivity?30-900 LOC/month!

Page 15: Cost Estimation

COCOMO II Model

• Supports spiral model of development• Supports component composition, reuse, customization• 4 sub-models:

– Application composition model – assumes system written with components, used for prototypes, development using scripts, db’s etc (object points)

– Early design model – After requirements, used during early stages of design (function points)

– Reuse model – Integrating and adapting reusable components (LOC)

– Post architecture model – More accurate method, once architecture has been designed (LOC)

Page 16: Cost Estimation

Application composition model

Used primarily to estimate cost of prototyping efforts

PM = (Application points x(1-%reuse/100)/ productivity

Productivity estimates from 4-50 object points/month, depending on experience and the availability/maturity of tools

Page 17: Cost Estimation

Early Design Model

Used once requirements are agreed to get going on an architectural design

PM=2.94 x Size^B x M

B=1.05-1.20

M=Proj characteristics

Page 18: Cost Estimation

Reuse model

• PM = (LOC needing to be adjusted X

% auto-generated)/productivity

Productivity ~ 2,400 LOC/Month

Page 19: Cost Estimation

Post-Architectural Model

• Organic projects - relatively small, simple projects with small teams and good application experience to less than rigid requirements. (A=2.4, B=1.05)

• Semi-detached projects - intermediate (in size and complexity) projects with mixed experience teams and a mix of requirements. (A=3.0, B=1.12)

• Embedded projects - software projects that must be developed within a set of tight hardware, software, and operational constraints. (A=3.6, B=1.20)

PM=A x Size^B x M