Project Cost estimation

download Project Cost estimation

of 48

Transcript of Project Cost estimation

  • 7/29/2019 Project Cost estimation

    1/48

    DETAILED SHEET OF ESTIMATE OF PROPOSED CONSTRUCTION OF AGRICLUTURAL PRODUCE

    WARE-HOUSES, AT VARIOUS LOCATIONS IN MADHYA PRADESH

    B/TO:- Mr. ANOOP GOEL (AGRAWAL)

    S/O:- Shree DINESH AGRAWAL

    Ku. NEHA GOEL (AGRAWAL)

    D/O :- Shree DINESH AGRAWAL

    FOR : G.G.REALESTATE Pvt. Ltd.

    S.No. Particular of Item. No. Length Width Depth Unit Quantity

    1 PLOT CLEANING AND LEVELLING

    Surface dressing of the ground i/c

    removing vegetation and inequalities not

    exceeding 15 cm. deep and disposal of

    a. In ordinary soil. 1.0 176.00 211.42 M2 6201.65

    2 EXCAVATION WORK:

    UNDER GROUND WATER TANK, D.G. ROOM, WEIGH BRIDGE, COMPOUND WALL

    WAREHOUSE BUILDING, MAIN GATE, SECURITY ROOM, TOILET BLOCK, SEPTIC TANK,

    AND INTERNAL ROAD

  • 7/29/2019 Project Cost estimation

    2/48

    Earthwork in excavation in foundation

    trench (not exceeding 1.50m. in width or

    10.0 sqm. in Plan) including dressing of

    side and ramming of bottoms, lift upto

    1.50m. including getting out the excavated

    soil and disposal of surplus excavated soil

    as directed within a lead of 50.0m.

    A. In ordinary soil.a. Warehouse Footings

    F-1 4.0 2.40 3.00 2.60 M3 74.88

    F-2 12.0 1.80 3.00 2.60 M3 168.48

    F-3 12.0 2.00 3.00 2.60 M3 187.20

    F-4 16.0 1.80 2.60 2.60 M3 194.69

    b. Septic Tank 1.0 2.10 3.00 2.60 M3 16.38

    c. Under Ground Water Tank 1.0 2.00 2.80 2.60 M3 14.56

    d. Pile Work

    C-5, 300mm. dia piles. 54.0 2.60 0.09 0.79 M3 9.93

    Pile Bulbs 54.0 0.70 0.20 0.79 M3 5.94

    e. Drainage work

    I/C Chambers

    I/C-1 3.0 1.00 1.00 0.40 M3 1.20

    I/C-2 2.0 1.00 1.20 0.60 M3 1.44

    Drainage Line

    DL-1 1.0 4.23 0.80 0.60 M3 2.03

    DL-2 1.0 13.68 0.80 0.80 M3 8.76

    DL-3 1.0 2.40 0.80 0.50 M3 0.96

    DL-4 1.0 2.90 0.80 0.50 M3 1.16

    M3 687.60

    B. In hard soil.

    a. Warehouse Footings

    F-1 4.0 2.40 3.00 0.60 M3 17.28

    F-2 12.0 1.80 3.00 0.60 M3 38.88

    F-3 12.0 2.00 3.00 0.60 M3 43.20F-4 16.0 1.80 2.60 0.60 M

    3 44.93

    b. Septic Tank 1.0 2.10 3.00 0.60 M3 3.78

    c. Under Ground Water Tank 1.0 2.00 2.80 0.60 M3 3.36

    d. Pile Work

    C-5, 300mm. dia piles. 54.0 0.60 0.09 0.79 M3 2.29

    M3 153.72

    C. DISPOSAL OF EXCAVATED BLACK

    COTTON SOIL UPTI 1K.M. LEAD AND M3 687.60

    3 FILLING WITH SAME HARD SOIL:

    Filling available excavated earth

    (excluding rock) in trenches, plinth, sides

    of foundation etc. in layers not exceeding

    20 cms. in depth consolidating Nos.

    deposited layer by ramming and watering

    lead upto 50.0m. and lift upto 1.50m.

    Total excavation as per Item No 2-B M3 153.72

    4 PLINTH FILLING :

  • 7/29/2019 Project Cost estimation

    3/48

    Filling in plinth and Foundation Pits with

    sand / Crusher stone dust/ Murrum under

    floor including watering , ramming,

    consolidating & dressing complete.

    A. FILLING UPTO N.G.L.

    Total excavation as per Item No 2 M3 841.32

    Deduction of Item no. 2-B M3 -153.72

    Deduction of P.C.C. M3 -22.78

    Deduction of R.C.C. Footings M3 -61.28

    Deduction of R.C.C. Columns M3 -29.38

    Deduction of R.C.C. of Under Ground

    M

    3 -5.70

    Deduction of R.C.C. of Under Ground

    M

    3 -3.99

    Deduction of R.C.C. Chambers and

    Deduction of R.C.C. Drainage Line M3 -2.34

    NET FILLING UPTO N.G.L. M3 562.12

    B. FILLING ABOVE N.G.L. UPTO

    1.0 73.00 53.50 0.80 M3

    3124.40Total murrum filling M

    3 3686.52

    5 PILE EXCAVATION WORK:

    Boring holes with Auger for under reamed

    piles to a depth of 3.0m. below GL and

    below sub soil water level and soil,

    including ramming 21/2

    times the dia of

    pile. (One bulb only).

    C-5, 300mm. dia piles. 54.0 3.20 RM 172.80

    Pile Bulbs 54.0 No 54.00

    6 P.C.C. WORK: In foundation and

    Plinth.Providing and laying mechanical mix

    cement concrete with crushed stone

    aggregates excluding cost of centering

    and shuttering with 40mm nominal size

    graded aggregates.

    A. P.C.C. Work grade M-7.5

    a. Warehouse Footings

    F-1 4.0 2.20 2.80 0.10 M3 2.46

    F-2 12.0 1.60 2.80 0.10 M3 5.38

    F-3 12.0 1.80 2.80 0.10 M3 6.05

    F-4 16.0 1.60 2.40 0.10 M3 6.14

    b. Septic Tank 1.0 1.90 2.80 0.10 M3 0.53

    c. Under Ground Water Tank 1.0 1.80 2.60 0.10 M3 0.47

    M3 21.03

    B. P.C.C. Work grade M-10

    I/C Chambers

    I/C-1 3.0 0.80 0.80 0.10 M3 0.19

    I/C-2 2.0 0.80 1.00 0.10 M3 0.16

    Drainage Line

    DL-1 1.0 4.23 0.60 0.10 M3 0.25

    DL-2 1.0 13.68 0.60 0.10 M3 0.82

  • 7/29/2019 Project Cost estimation

    4/48

    DL-3 1.0 2.40 0.60 0.10 M3 0.14

    DL-4 1.0 2.90 0.60 0.10 M3 0.17

    M3 1.74

    7 R.C.C. WORK- M:15 UPTO PLINTH

    Reinforced cement concrete work with CC

    M--15 Grade, crushed stone aggregate 12mm to 20mm nominal size graded,

    excluding cost of Centering, Shuttering

    and Reinforcement upto Plinth level for

    Plinth string courses and their supports,

    Plinth Slab, Parking, Main Gate Ramp

    and projected bands.

    PLINTH SLABS:

    a. Plinth Slab 1.0 73.00 53.50 0.12 M3 468.66

    b. Main Gate Ramp 4.0 3.00 4.00 0.12 M3 5.76

    PILE WORK:

    C-5, 300mm. dia piles. 54.0 0.79 3.20 0.09 M3 12.22

    Pile Bulbs 54.0 0.70 0.20 0.79 M3

    5.94M3 492.58

    DRAINAGE WORK:I/C Chambers

    I/C-1 3.0 0.70 0.70 0.12 M3 0.18

    6.0 0.70 0.40 0.10 M3 0.17

    6.0 0.50 0.40 0.10 M3 0.12

    I/C-2 2.0 0.70 0.90 0.12 M3 0.15

    4.0 0.70 0.60 0.10 M3 0.17

    4.0 0.70 0.60 0.10 M3 0.17

    Drainage Line

    DL-1 1.0 4.23 0.50 0.12 M3 0.25

    DL-2 1.0 13.68 0.50 0.12 M3

    0.82DL-3 1.0 2.40 0.50 0.12 M

    3 0.14

    DL-4 1.0 2.90 0.50 0.12 M3 0.17

    M3 2.34

    M3 494.92

    8 R.C.C. WORK M-20: UPTO PLINTH

    Reinforced cement concrete work with

    C.C. M--20 grade, crushed stone

    aggregate 20mm nominal size graded,

    excluding cost of Centering, Shuttering

    and Reinforcement upto Plinth level for

    foundation, footings, bases of column /walls ,i/c ,attached pilasters, buttresses,

    Plinth string courses, Plinth

    beams,Cantilevers, columns, pillar posts &

    struts, vertical and horizontal fins

    individually forming box, Septic Tank,

    Under Ground Water Tank, louvers and

    projected bands.

    a. Footings

    F-1 4.0 2.00 2.60 0.35 M3 7.28

    F-2 12.0 1.40 2.60 0.40 M3 17.47

  • 7/29/2019 Project Cost estimation

    5/48

    F-3 12.0 1.60 2.60 0.40 M3 19.97

    F-4 16.0 1.50 2.30 0.30 M3 16.56

    M3 61.28

    b. Columns upto Ground beam bottom

    C-1 4.0 0.40 0.70 2.75 M3 3.08

    C-2 12.0 0.40 0.60 2.70 M3 7.78

    C-3 12.0 0.40 0.60 2.70 M3 7.78

    C-4 16.0 0.40 0.60 2.80 M3 10.75

    M3 29.38

    c. Plinth beams

    GB-I 2.0 0.30 0.40 73.00 M3 17.52

    GB-2 2.0 0.30 0.40 53.50 M3 12.84

    GB-3 2.0 0.20 0.40 53.50 M3 8.56

    GB-4 4.0 0.20 0.40 4.00 M3 1.28

    GB-5 8.0 0.20 0.30 3.00 M3

    1.44M3 41.64

    d. Columns above Ground beam and

    upto plinth level

    C-1 4.0 0.30 0.60 0.40 M3 0.29

    C-2 12.0 0.30 0.50 0.40 M3 0.72

    C-3 12.0 0.30 0.50 0.40 M3 0.72

    C-4 16.0 0.30 0.50 0.40 M3 0.96

    C-5 54.0 0.20 0.30 0.40 M3 1.30

    M3 3.98

    e. Septic tank

    Base Slab1.0 1.90 2.60 0.30 M

    3

    1.48Short walls 2.0 1.60 0.15 2.88 M

    3 1.38

    Long walls 2.0 2.60 0.15 2.88 M3 2.25

    Cover Slab 1.0 1.90 2.60 0.12 M3 0.59

    M3 5.70

    f. Under Ground Water tank

    Base Slab 1.0 1.60 2.40 0.25 M3 0.96

    Short walls 2.0 1.36 0.12 2.85 M3 0.93

    Long walls 2.0 2.40 0.12 2.85 M3 1.64

    Cover Slab 1.0 1.60 2.40 0.12 M3 0.46

    M3 3.99

    TOTAL M3 145.98

    9 SHUTTERING AND SCAFOLDING

    UPTO PLINTH LEVEL

    Centering and Shuttering including

    shuttering propping etc. and removal of

    formwork.

    A. P.C.C. WORK:

    a. Footing P.C.C.

    F-1 4.0 10.00 0.10 M2 4.00

    F-2 12.0 8.80 0.10 M2 10.56

    F-3 12.0 6.00 0.10 M2 7.20

  • 7/29/2019 Project Cost estimation

    6/48

    F-4 16.0 8.00 0.10 M2 12.80

    b. Septic Tank 1.0 9.40 0.10 M2 0.94

    c. Under Ground Water Tank 1.0 8.80 0.10 M2 0.88

    d. I/C Chambers

    I/C-1 3.0 3.20 0.10 M2 0.96

    I/C-2 2.0 3.60 0.10 M2 0.72

    e. Drainage LineDL-1 2.0 4.23 0.10 M

    2 0.85

    DL-2 2.0 13.68 0.10 M2 2.74

    DL-3 2.0 2.40 0.10 M2 0.48

    DL-4 2.0 2.90 0.10 M2 0.58

    B. R.C.C. Work:

    a. Footings

    F-1 4.0 9.20 0.35 M2 12.88

    F-2 12.0 8.00 0.40 M2 38.40

    F-3 12.0 8.40 0.40 M2 40.32

    F-4 16.0 7.60 0.30 M2 36.48

    b. Columns upto Ground beam bottom

    C-1 4.0 2.20 2.75 M2

    24.20C-2 12.0 2.00 2.70 M

    2 64.80

    C-3 12.0 2.00 2.70 M2 64.80

    C-4 16.0 2.00 2.80 M2 89.60

    c. Plinth beams

    GB-I 4.0 73.00 0.40 M2 116.80

    GB-2 4.0 53.50 0.40 M2 85.60

    GB-3 4.0 53.50 0.40 M2 85.60

    GB-4 8.0 4.00 0.40 M2 12.80

    GB-5 16.0 3.00 0.30 M2 14.40

    d. Columns above Ground beam and

    upto plinth level

    C-1 4.0 1.80 0.40 M2 2.88

    C-2 12.0 1.60 0.40 M2 7.68

    C-3 12.0 1.60 0.40 M2 7.68

    C-4 16.0 1.60 0.40 M2 10.24

    C-5 54.0 1.00 0.40 M2 21.60

    e. Septic tank

    Base Slab 1.0 9.00 0.30 M2 2.70

    Short walls 2.0 1.90 2.88 M2 10.94

    2.0 1.60 2.88 M2 9.22

    Long walls 2.0 2.60 2.88 M2 14.98

    2.0 2.30 2.88 M2 13.25

    Cover Slab 1.0 1.60 2.30 M2 3.68

    Cover Slab sides 1.0 9.00 0.12 M2 1.08

    f. Under Ground Water tankBase Slab 1.0 8.00 0.25 M

    2 2.00

    Short walls 2.0 1.60 2.85 M2 9.12

    2.0 1.36 2.85 M2 7.75

    Long walls 2.0 2.40 2.85 M2 13.68

    2.0 2.16 2.85 M2 12.31

    Cover Slab 1.0 1.36 2.16 M2 2.94

    Cover Slab sides 1.0 1.36 0.12 M2 0.16

    g. I/C Chambers

    I/C-1 3.0 2.80 0.12 M2 1.01

  • 7/29/2019 Project Cost estimation

    7/48

    6.0 0.70 0.40 M2 1.68

    6.0 0.50 0.40 M2 1.20

    I/C-2 2.0 3.20 0.12 M2 0.77

    4.0 0.70 0.60 M2 1.68

    4.0 0.70 0.60 M2 1.68

    h. Drainage Line

    DL-1 2.0 4.23 0.12 M2 1.02DL-2 2.0 13.68 0.12 M

    2 3.28

    DL-3 2.0 2.40 0.12 M2 0.58

    DL-4 2.0 2.90 0.12 M2 0.70

    j. Plinth Slab sides 1.0 253.00 0.12 M2 30.36

    k. Main Gate Ramp sides 4.0 10.00 0.12 M2 4.80

    M2 932.02

  • 7/29/2019 Project Cost estimation

    8/48

    10 D.P.C. WORK:

    Providing and laying Damp proof Course

    50mm thick with concrete designation M-

    15 with 20mm nominal size graded stone

    aggregates (crushed) mechanically mixed.

    1.0 253.00 0.20 M2

    50.60

    11 R.C.C. M: 20, WORK IN SUPER

    STRUCTURE:

    Reinforced cement concrete work with CC

    M--20 grade, crushed stone aggregate

    20mm nominal size graded, excluding cost

    of Centering, Shuttering and

    Reinforcement above Plinth level for

    bases of column, Roof Beams / walls i/c

    attached pilasters, buttresses, suspended

    floors, roofs, landings, shelves and their

    supports, balconies, lintels, chhajjas of any

    thickness, Stair case beams, girders,

    bressumers, cantilevers, pillar posts &

    struts, staircase including landings but

    including repairing of top surface and

    finishing, nosing, spiral staircase i/c

    landing, arches, domes, vaults and shell

    roof, chimney shafts, well steining, vertical

    and horizontal f ins individually forming

    box, louvers and projected bands.

    GROUND FLOOR:a. Columns above plinth and upto 0.40

    M ht.

    C-1 4.0 0.30 0.60 0.40 M3 0.29

    C-2 12.0 0.30 0.50 0.40 M3 0.72

    C-3 12.0 0.30 0.50 0.40 M3 0.72

    C-4 16.0 0.30 0.50 0.40 M3

    0.96C-5 46.0 0.20 0.30 0.40 M

    3 1.10

    b. Windows sealWindows, W-1 28.0 1.40 0.20 0.10 M

    3 0.78

    W-2 32.0 1.20 0.20 0.10 M3 0.77

    Vantilators, V-1 28.0 1.40 0.20 0.10 M3 0.78

    V-2 28.0 1.20 0.20 0.10 M3 0.67

    c. LintelGFL-1 2.0 44.50 0.20 0.10 M

    3 1.78

    GFL-2 2.0 61.60 0.20 0.10 M3 2.46

    GFL-3 2.0 44.50 0.20 0.10 M3 1.78

    d. Wheather shedWindows, W-1 28.0 1.40 0.40 0.10 M

    3 1.57

    W-2 32.0 1.20 0.40 0.10 M3 1.54

    Vantilators, V-1 28.0 1.40 0.20 0.10 M3 0.78

    V-2 28.0 1.20 0.20 0.10 M3 0.67

    e. Columns above Plinth level and upto3.20 M ht.

    C-1 4.0 0.30 0.60 2.90 M3 2.09

    C-2 12.0 0.30 0.50 2.90 M3 5.22

    C-3 12.0 0.30 0.40 2.90 M3 4.18

    C-4 16.0 0.30 0.50 2.90 M3 6.96

    C-5 46.0 0.20 0.30 2.90 M3 8.00

    TOTAL G.F., R.C.C. M:20 M3 43.83

    12 SHUTTERING AND SCAFOLDING

    ABOVE PLINTH LEVEL

  • 7/29/2019 Project Cost estimation

    9/48

    Centering and Shuttering i/c Shutering,

    propping etc. & removal of formwork for:

    GROUND FLOOR:

    a. Columns above plinth and upto 0.40

    C-1 4.0 1.80 0.40 M2 2.88

    C-2 12.0 1.60 0.40 M2 7.68

    C-3 12.0 1.60 0.40 M2

    7.68C-4 16.0 1.60 0.40 M

    2 10.24

    b. Windows seal

    Windows, W-1 56.0 1.40 0.10 M2 7.84

    W-2 64.0 1.20 0.10 M2 7.68

    Vantilators, V-1 56.0 1.40 0.10 M2 7.84

    V-2 56.0 1.20 0.10 M2 6.72

    c. Lintel

    GFL-1 4.0 44.50 0.10 M2 17.80

    GFL-2 4.0 61.60 0.10 M2 24.64

    GFL-3 4.0 44.50 0.10 M2 17.80

    d. Wheather shed

    Windows, W-1 28.0 1.40 0.40 M2 15.68

    Sides 28.0 0.80 0.10 M2 2.24

    W-2 32.0 1.20 0.40 M2 15.36

    Sides 32.0 0.80 0.10 M2 2.56

    Vantilators, V-1 28.0 1.40 0.20 M2 7.84

    Sides 28.0 0.40 0.10 M2 1.12

    V-2 28.0 1.20 0.20 M2 6.72

    Sides 28.0 0.40 0.10 M2 1.12

    e. Columns above Plinth level and upto

    3.20 M ht.

    C-1 4.0 1.80 2.90 M2 20.88

    C-2 12.0 1.60 2.90 M2 55.68

    C-3 12.0 1.40 2.90 M2 48.72

    C-4 16.0 1.60 2.90 M2 74.24

    C-5 46.0 1.00 2.90 M2 133.40

    TOTAL G.F. FALSE WORK. M2 504.36

    13 REINFORCEMENT: TOR STEEL, UPTO

    PLINTH LEVEL

    Cold twisted steel and hot rolled deformed

    steel reinforcement for RCC work i/c

    cutting, bending, binding & placing in

    position complete i/c cost of binding wires.

    (i). REINFORCEMENT AS PER;

    R.C.C. WORK- M:15 UPTO PLINTH

    PLINTH SLABS:

    a. Plinth Slab

    8MM Dia bars @ 200MM C/C Both

    Parallel to Short span 1.0 73.40 215.00 0.39 Kg 6154.59

    Parallel to Long span 1.0 53.90 293.00 0.39 Kg 6159.15

    b. Main Gate Ramp

    8MM Dia bars @ 200MM C/C Both

    Parallel to Short span 4.0 4.40 16.00 0.39 Kg 109.82

    Parallel to Long span 4.0 3.40 21.00 0.39 Kg 111.38

  • 7/29/2019 Project Cost estimation

    10/48

    PILE WORK:

    C-5, 300mm. dia piles.

    10MM dia. 5 Nos main bars 54.0 3.75 5.00 0.60 Kg 607.50

    Stirrups, 8MM dia. @150MM C/C 54.0 1.04 22.00 0.39 Kg 483.25

    DRAINAGE WORK:

    I/C Chambers

    I/C-1 3.0 1.50 7.00 0.39 Kg 12.29

    3.0 1.50 7.00 0.39 Kg 12.29

    Side Walls horizintal reinforceent 3.0 3.00 5.00 0.39 Kg 17.55

    I/C-2 2.0 1.90 7.00 0.39 Kg 10.38

    2.0 2.10 9.00 0.39 Kg 14.74

    Side Walls horizintal reinforceent 2.0 3.40 7.00 0.39 Kg 18.56

    Drainage Line

    DL-1 1.0 0.70 36.00 0.39 Kg 9.83

    DL-2 1.0 0.70 115.00 0.39 Kg 31.40

    DL-3 1.0 0.70 21.00 0.39 Kg 5.73

    DL-4 1.0 0.70 25.00 0.39 Kg 6.82

    (ii). REINFORCEMENT AS PER;

    R.C.C. WORK M-20: UPTO PLINTH

    a. FootingsF-1 4.0 2.30 18.00 0.60 Kg 99.38

    4.0 2.90 14.00 0.60 Kg 97.46

    F-2 12.0 1.70 18.00 0.60 Kg 220.36

    12.0 2.90 10.00 0.60 Kg 208.87

    F-3 12.0 1.90 18.00 0.60 Kg 246.29

    12.0 2.90 12.00 0.60 Kg 250.49

    F-4 16.0 1.80 16.00 0.60 Kg 276.54

    16.0 2.60 11.00 0.60 Kg 274.56

    b. Columns upto Ground beam bottom

    C-1 4.0 3.69 12.00 0.90 Kg 159.41Stirrups 4.0 2.10 15.00 0.39 Kg 49.14

    C-2 12.0 3.64 14.00 0.90 Kg 550.37

    Stirrups 12.0 1.90 15.00 0.39 Kg 133.38

    C-3 12.0 3.64 10.00 0.90 Kg 393.12

    Stirrups 12.0 1.90 15.00 0.39 Kg 133.38

    C-4 16.0 3.74 10.00 0.90 Kg 538.56

    Stirrups 16.0 1.90 20.00 0.39 Kg 237.08

    c. Plinth beamsGB-I 2.0 76.08 6.00 0.90 Kg 821.66

    Stirrups 2.0 488.00 1.30 0.39 Kg 494.83

    GB-2 2.0 54.58 5.00 0.90 Kg 491.22

    Stirrups 2.0 358.00 1.30 0.39 Kg 363.01

    GB-3 2.0 54.58 4.00 0.90 Kg 392.98

    Stirrups 2.0 357.00 1.10 0.39 Kg 306.30GB-4 4.0 5.08 4.00 0.90 Kg 73.15

    Stirrups 4.0 27.00 1.10 0.39 Kg 46.33

    GB-5 8.0 3.09 5.00 0.60 Kg 74.16

    Stirrups 8.0 21.00 0.90 0.39 Kg 58.97

    d. Columns above Ground beam and

    upto plinth level

    C-1 4.0 1.48 12.00 0.90 Kg 63.94

    Stirrups 4.0 1.70 4.00 0.39 Kg 10.60

    C-2 12.0 1.48 14.00 0.90 Kg 223.78

    Stirrups 12.0 1.50 4.00 0.39 Kg 28.06

    C-3 12.0 1.48 10.00 0.90 Kg 159.84

  • 7/29/2019 Project Cost estimation

    11/48

    Stirrups 12.0 1.50 4.00 0.39 Kg 28.06

    C-4 16.0 1.48 10.00 0.90 Kg 213.12

    Stirrups 16.0 1.50 4.00 0.39 Kg 37.41

    C-5 54.0 1.48 6.00 0.90 Kg 431.57

    Stirrups 54.0 0.90 4.00 0.39 Kg 75.75

    e. Septic tankBase Slab 2.0 2.80 18.00 0.60 Kg 60.49

    Top and Bottom reinforcement 2.0 3.50 14.00 0.60 Kg 58.79Short walls 2.0 2.50 25.50 0.60 Kg 76.50

    2.0 3.60 9.00 0.39 Kg 25.27

    Long walls 2.0 3.32 15.50 0.39 Kg 40.14

    2.0 3.78 23.00 0.60 Kg 104.31

    Cover Slab 1.0 2.62 16.00 0.39 Kg 16.35

    1.0 3.32 12.00 0.39 Kg 15.53

    Top extra reinforcement, alternate 1.0 0.68 9.00 0.39 Kg 2.37

    1.0 0.85 7.00 0.39 Kg 2.32

    f. Under Ground Water tankBase Slab 2.0 2.50 17.00 0.60 Kg 51.00

    Top and Bottom reinforcement 2.0 3.30 12.00 0.60 Kg 47.51

    Short walls 2.0 2.26 20.00 0.60 Kg 54.24

    2.0 3.57 10.00 0.39 Kg 27.84

    Long walls 2.0 3.12 20.00 0.39 Kg 48.672.0 3.75 17.00 0.60 Kg 76.50

    Cover Slab 1.0 2.32 15.00 0.39 Kg 13.57

    1.0 3.12 11.00 0.39 Kg 13.39

    Kg 22763.19

    (iii). REINFORCEMENT AS PER;

    GROUND FLOOR:

    a. Columns above plinth and upto 0.40

    C-1 4.0 1.48 12.00 0.90 Kg 63.94

    Stirrups 4.0 1.70 4.00 0.39 Kg 10.60

    C-2 12.0 1.48 14.00 0.90 Kg 223.78

    Stirrups 12.0 1.50 4.00 0.39 Kg 28.06

    C-3 12.0 1.48 10.00 0.90 Kg 159.84

    Stirrups 12.0 1.50 4.00 0.39 Kg 28.06C-4 16.0 1.48 10.00 0.90 Kg 213.12

    Stirrups 16.0 1.50 4.00 0.39 Kg 37.41

    b. Windows seal

    Windows, W-1 28.0 1.30 2.00 0.60 Kg 43.68

    Stirrups 28.0 0.25 8.00 0.39 Kg 21.84

    W-2 32.0 1.10 2.00 0.60 Kg 42.24

    Stirrups 32.0 0.25 7.00 0.39 Kg 21.84

    Vantilators, V-1 28.0 1.30 2.00 0.60 Kg 43.68

    Stirrups 28.0 0.25 8.00 0.39 Kg 21.84

    V-2 28.0 1.10 2.00 0.60 Kg 36.96

    Stirrups 28.0 0.25 7.00 0.39 Kg 19.11

    c. Lintel

    GFL-1 2.0 47.40 2.00 0.60 Kg 113.76

    Stirrups 2.0 0.25 224.00 0.39 Kg 43.68GFL-2 2.0 62.50 2.00 0.60 Kg 150.00

    Stirrups 2.0 0.25 309.00 0.39 Kg 60.26

    GFL-3 2.0 45.40 2.00 0.60 Kg 108.96

    Stirrups 2.0 0.25 224.00 0.39 Kg 43.68

    d. Wheather shed

    Windows, W-1 28.0 1.30 4.00 0.39 Kg 56.74

    Main bars 28.0 0.57 12.00 0.60 Kg 114.88

    W-2 32.0 1.10 4.00 0.39 Kg 54.87

    Main bars 32.0 0.57 11.00 0.60 Kg 120.38

    Vantilators, V-1 28.0 1.30 2.00 0.39 Kg 28.44

    Main bars 28.0 0.37 13.00 0.60 Kg 80.79

  • 7/29/2019 Project Cost estimation

    12/48

    V-2 28.0 1.10 2.00 0.39 Kg 24.06

    Main bars 28.0 0.37 11.00 0.60 Kg 68.38

    e. Columns above Plinth level and upto

    3.20 M ht.

    C-5 46.0 4.28 6.00 0.90 Kg 1063.15

    Stirrups 46.0 0.90 2.00 0.39 Kg 32.29

    REINFORCEMENT WORK ABOVE

    PLINTH LEVEL Kg 3180.30

    TOTAL REINFORCEMENT WORK Kg 25943.48

    14 BRICK WORK 300 MM THICK:

    BRICK WORK UPTO PLINTH LEVEL:

    Brickwork with well burnt chimney bricks in

    bulls patent trench kiln manufactured by

    ghol process, crushing strength not less

    than 25 kg/Sq.cm. & Water absorption not

    more than 15% in foundation and

    plinth,20cm thk.

    a. CM 1:8, Laying for beam bottom

    GB-I2.0 70.60 0.30 0.10 M

    3

    4.24GB-2 2.0 50.50 0.30 0.10 M

    3 3.03

    GB-3 2.0 50.50 0.30 0.10 M3 3.03

    GB-4 4.0 4.00 0.30 0.10 M3 0.48

    GB-5 8.0 3.00 0.30 0.10 M3 0.72

    b. CM 1:6, Above Plinth beam and upto

    Plinth LevelM3 11.50

    GB-I 2.0 70.60 0.30 0.40 M3 16.94

    GB-2 2.0 50.50 0.30 0.40 M3 12.12

    GB-3 2.0 50.50 0.30 0.40 M3 12.12

    GB-4 4.0 4.00 0.30 0.40 M3 1.92

    GB-5 8.0 3.00 0.30 0.40 M3 2.88

    M3 45.98

    TOTAL BRICK WORK UPTO PLINTH

    LEVELM

    3 57.48

    15 BRICK WORK ABOVE PLINTH LEVEL:

    200 MM THICK BRICK WORK

    Brickwork with well burnt chimney bricks in

    bulls patent trench kiln manufactured by

    ghol process, crushing strength not less

    than 25 kg/Sq.cm. & Water absorption not

    more than 15% in Ground Floor and First

    Floor main front and back walls,20cm thk.

    CM 1:6Ground Floor Ware house upto 3.2 M

    height

    2.0 70.60 0.20 2.90 M3 81.90

    2.0 50.50 0.20 2.90 M3 58.58

    2.0 50.50 0.20 2.90 M3 58.58

    M3 199.06

    Deduction for opening G.F. AND F.F.

    Windows, W-1 28.0 1.20 0.90 0.20 M3 6.05

    W-2 32.0 1.00 0.90 0.20 M3 5.76

    Vantilators, V-1 28.0 1.20 0.60 0.20 M3 4.03

  • 7/29/2019 Project Cost estimation

    13/48

    V-2 28.0 1.00 0.60 0.20 M3 3.36

    Shutters, D-1 4.0 3.00 3.00 0.20 M3 7.20

    M.S. Doors, D-2 1.0 1.20 3.00 0.20 M3 0.72

    M3 27.12

    NET BRICK IN G.F. SUPER

    STRUCTUREWORKM

    3 171.94

    16 DOORS, WINDOWS AND

    M.S. Z-SECTION FRAMES:

    a. SHUTTERS : Providing and fixing of Z-

    Section Door frames and Shutters

    including making in all respect

    Shutters, D-1 4.0 3.00 3.00 M2 36.00

    M.S. Doors, D-2 1.0 1.20 3.00 M2 3.60

    M2 39.60

    b. WINDOWS: Providing and fixing of Z-

    Section Window frames and Shutters

    including making in all respectWindows, W-1 28.0 1.20 0.90 2.45 Kg 74.09

    W-2 32.0 1.00 0.90 2.45 Kg 70.56

    Kg 144.65

    c. VANTILATORS: Providing and fixing of

    M.S. section Vantilator frames including

    making in all respect

    Vantilators, V-1 28.0 1.20 0.60 2.75 Kg 55.44

    V-2 28.0 1.00 0.60 2.75 Kg 46.20

    Kg 101.64

    17 GLASS WORK:

    Providing and fixing of 5MM thick Branded

    glass to Windows and Vantilators in all

    respect.

    Windows, W-1 28.0 1.15 0.85 M2 27.37

    W-2 32.0 0.95 0.85 M2 25.84

    Vantilators, V-1 28.0 1.15 0.55 M2 17.71

    V-2 28.0 0.95 0.55 M2 14.63

    M2 85.55

    18 FLOORING WORK:

    (i) IPC FLOORING:

    25mm Cement concrete flooring 1:2:4 (1Cement, 2 Sand, 4 Graded stone

    aggregates 12.5mm nominal size) finished

    with floating coat of neat cement at Floor

    level with proper slope..

    Floor Level 1.0 72.40 52.90 M2 3829.96

    M2 3829.96

    19 PLASTER WORK:

    a. 20mm thick cement plaster to uneven

    surface:

  • 7/29/2019 Project Cost estimation

    14/48

    In 1:6 CM Ground floor Double coat

    plaster

    Front Wall outer side 1.0 73.00 3.20 M2 233.60

    Back Wall outer side 1.0 73.00 3.20 M2 233.60

    Right side outer Wall 1.0 53.50 3.20 M2 171.20

    Left side outer Wall 1.0 53.50 3.20 M2

    171.20First intermediate rough surface 1.0 53.50 3.20 M

    2 171.20

    Second intermediate rough surface 1.0 53.50 3.20 M2 171.20

    M2 1152.00

    b. 12mm thick single coat cement

    plaster to even surface:

    In 1:5 CM Ground floor single coat

    plaster

    Front Wall inner side 1.0 73.00 3.20 M2 233.60

    Back Wall inner side 1.0 73.00 3.20 M2 233.60

    Right side inner Wall 1.0 53.50 3.20 M2 171.20

    Left side inner Wall 1.0 53.50 3.20 M2 171.20First intermediate even surface 1.0 53.50 3.20 M

    2 171.20

    Second intermediate even surface 1.0 53.50 3.20 M2 171.20

    M2 1152.00

    c. Neeru plaster

    Under ground water tank

    Short walls 2.0 1.60 2.85 M2 9.12

    Long walls 2.0 2.40 2.85 M2 13.68

    Base Slab 1.0 1.60 2.40 M2 3.84

    Cover Slab 1.0 1.60 2.40 M2 3.84

    Septic tank

    Base Slab 1.0 1.90 2.60 M2 4.94

    Short walls 2.0 1.90 2.88 M2 10.94

    Long walls 2.0 2.60 2.88 M2 14.98

    Cover Slab 1.0 1.90 2.60 M2 4.94

    I/C Chambers

    I/C-1 3.0 2.80 0.40 M2 3.36

    3.0 0.70 0.70 M2 1.47

    I/C-2 2.0 3.20 0.60 M2 3.84

    2.0 0.70 0.90 M2 1.26

    M2 76.21

    20 PAINTING WORK:

    a. White washing on new work (three ormore coats) to give an even shade with

    white Cement.

    M2 2380.21

    b. Distempering (two or more coats) with

    oil bound washable distemper of required

    shade on new work over over and i/c. a

    priming coat with cement primer to give an

    even shade including three coat of Putty

    with rubbing and touching etc. complete in

    all respect.

    M2 2304.00

  • 7/29/2019 Project Cost estimation

    15/48

    c. Painting (two or more coats) with

    synthetic enamel paint on Windows and

    Vantilators gril l, Main gate Shutter work

    over and i/c. an under coat of suitable

    shade with priming coat to give an even

    shade. M2

    39.60

    21 PEB -SUPER STRUCTURE:Pre-engineered building having edge

    height 6.0 Mt. and Ridge height 8.0Mt.

    Including side sheeting and roof covering

    also providing proper drainage system in

    all respect.

    1.0 73.00 53.50 M2 3905.50

  • 7/29/2019 Project Cost estimation

    16/48

    22 MAIN GATE:

    Providing and fixing 9.0M main gate with

    siliding system to both side of height 2.1M.

    1.0 9 2.10 M2

    18.90

    23 COMPOUND WALL:

    200MM thick compound wall of height2.5M on pile foundations framed structure,

    and above this height upto 3.5M berbed

    fencing provided.

    1.0 377.62 RM 377.62

    24 SECURITY ROOM AND TOILET BLOCK:

    R.C.C. framed structure having 200MM

    thick brick wall, Alliminium door and

    window section, vitrified floor tiles. 1.0 10.2 3.40 M2

    34.68

    25 WEIGH BRIDGE:

    R.C.C. Foundaion for 100 M.T. capacity

    weigh bridge in C.M. M:20.

    1.0 3.2 16.00 M2

    51.20

    26 D.G. ROOM:

    Partially covered shed for D.G. 1.0 3 4.00 M2 12.00

    27 INTERNAL ROADS:

    WBM Internal road having PWD

    specifications including storm water open

    drains.

    1.0 176.00 6.00 M2 1056.00

    2.0 187.42 6.00 M2 2249.04

    1.0 176.00 18.00 M2 3168.00

    1.0 187.42 18.00 M2 3373.56

    2.0 146.00 12.00 M2

    3504.00M

    2 13350.60

  • 7/29/2019 Project Cost estimation

    17/48

  • 7/29/2019 Project Cost estimation

    18/48

  • 7/29/2019 Project Cost estimation

    19/48

  • 7/29/2019 Project Cost estimation

    20/48

  • 7/29/2019 Project Cost estimation

    21/48

  • 7/29/2019 Project Cost estimation

    22/48

  • 7/29/2019 Project Cost estimation

    23/48

  • 7/29/2019 Project Cost estimation

    24/48

  • 7/29/2019 Project Cost estimation

    25/48

  • 7/29/2019 Project Cost estimation

    26/48

  • 7/29/2019 Project Cost estimation

    27/48

  • 7/29/2019 Project Cost estimation

    28/48

  • 7/29/2019 Project Cost estimation

    29/48

  • 7/29/2019 Project Cost estimation

    30/48

  • 7/29/2019 Project Cost estimation

    31/48

  • 7/29/2019 Project Cost estimation

    32/48

  • 7/29/2019 Project Cost estimation

    33/48

    ABSTRACT SHEET OF ESTIMATE OF PROPOSED CONSTRUCTION OF AGRICLU

    WARE-HOUSES, AT VARIOUS LOCATIONS IN MADHYA PRADESH

    B/TO:- Mr. ANOOP GOEL (AGRAWAL)

    S/O:- Shree DINESH AGRAWAL

    Ku. NEHA GOEL (AGRAWAL)

    D/O :- Shree DINESH AGRAWAL

    FOR : G.G.REALESTATE Pvt. Ltd.

    .No Particular of Item. Quantity Unit Rate

    1 PLOT CLEANING AND LEVELLING

    WORK:

    Surface dressing of the ground i/cremoving vegetation and inequalities not

    exceeding 15 cm. deep and disposal of

    rubbish.

    a. In ordinary soil. 6201.65 M2

    Rs.10.00

    2 EXCAVATION WORK:

    WAREHOUSE BUILDING, MAIN GATE, SECURITY ROOM, TOILET BLOCK, S

    UNDER GROUND WATER TANK, D.G. ROOM, WEIGH BRIDGE, COMPOUND

    AND INTERNAL ROAD

  • 7/29/2019 Project Cost estimation

    34/48

    Earthwork in excavation in foundation

    trench (not exceeding 1.50m. in width or

    10.0 sqm. in Plan) including dressing of

    side and ramming of bottoms, lift upto

    1.50m. including getting out the excavated

    soil and disposal of surplus excavated soil

    as directed within a lead of 50.0m.

    A. In ordinary soil. 687.60 M2

    Rs.100.00

    B. In hard soil. 153.72 M2

    Rs.140.00

    C. DISPOSAL OF EXCAVATED BLACK

    COTTON SOIL UPTI 1K.M. LEAD AND 687.60 M2

    Rs.50.00

    3 FILLING WITH SAME HARD SOIL:

    Filling available excavated earth

    (excluding rock) in trenches, plinth, sidesof foundation etc. in layers not exceeding

    20 cms. in depth consolidating Nos.

    deposited layer by ramming and watering

    lead upto 50.0m. and lift upto 1.50m.

    153.72 M3

    Rs.60.00

    4 PLINTH FILLING :

    Filling in plinth and Foundation Pits with

    sand / Crusher stone dust/ Murrum under

    floor including watering , ramming,

    consolidating & dressing complete.

    3686.52 M3

    Rs.325.00

    5 PILE EXCAVATION WORK:

    Boring holes with Auger for under reamed

    piles to a depth of 3.0m. below GL and

    below sub soil water level and soil,

    including ramming 21/2 times the dia of

    pile. (One bulb only).

    C-5, 300mm. dia piles. 172.80 RM Rs.80.00

    Pile Bulbs 54.00 No Rs.150.00

    6 P.C.C. WORK: In foundation and

  • 7/29/2019 Project Cost estimation

    35/48

    Providing and laying mechanical mix

    cement concrete with crushed stone

    aggregates excluding cost of centering

    and shuttering with 40mm nominal size

    graded aggregates.

    A. P.C.C. Work grade M-7.521.03 M

    3

    Rs.3,150.00B. P.C.C. Work grade M-10 1.74 M3

    Rs.3,450.00

    7 R.C.C. WORK- M:15 UPTO PLINTH

    Reinforced cement concrete work with CC

    M--15 Grade, crushed stone aggregate 12

    mm to 20mm nominal size graded,

    excluding cost of Centering, Shuttering

    and Reinforcement upto Plinth level for

    Plinth string courses and their supports,

    Plinth Slab, Parking, Main Gate Rampand projected bands.

    494.92 M3

    Rs.4,270.00

    8 R.C.C. WORK M-20: UPTO PLINTH

    LEVEL

    Reinforced cement concrete work with

    C.C. M--20 grade, crushed stone

    aggregate 20mm nominal size graded,

    excluding cost of Centering, Shuttering

    and Reinforcement upto Plinth level for

    foundation, footings, bases of column /

    walls ,i/c ,attached pilasters, buttresses,

    Plinth string courses, Plinth

    beams,Cantilevers, columns, pillar posts &

    struts, vertical and horizontal fins

    individually forming box, Septic Tank,

    Under Ground Water Tank, louvers and

    projected bands.

    145.98 M3

    Rs.4,680.00

    9 SHUTTERING AND SCAFOLDING

    UPTO PLINTH LEVEL

    Centering and Shuttering including

    shuttering propping etc. and removal of

    formwork.

    932.02 M2

    Rs.250.00

  • 7/29/2019 Project Cost estimation

    36/48

    10 D.P.C. WORK:

    Providing and laying Damp proof Course

    50mm thick with concrete designation M-

    15 with 20mm nominal size graded stone

    aggregates (crushed) mechanically mixed.

    50.60 M2

    Rs.180.00

    11 R.C.C. M: 20, WORK IN SUPER

    STRUCTURE:

    Reinforced cement concrete work with CC

    M--20 grade, crushed stone aggregate

    20mm nominal size graded, excluding cost

    of Centering, Shuttering and

    Reinforcement above Plinth level for

    bases of column, Roof Beams / walls i/cattached pilasters, buttresses, suspended

    floors, roofs, landings, shelves and their

    supports, balconies, lintels, chhajjas of

    any thickness, Stair case beams, girders,

    bressumers, cantilevers, pillar posts &

    struts, staircase including landings but

    including repairing of top surface and

    finishing, nosing, spiral staircase i/c

    landing, arches, domes, vaults and shell

    roof, chimney shafts, well steining, verticaland horizontal fins individually forming

    box, louvers and projected bands.

    TOTAL G.F., R.C.C. M:20 43.83 M3

    Rs.4,680.00

    12 SHUTTERING AND SCAFOLDING

    ABOVE PLINTH LEVEL

    Centering and Shuttering i/c Shutering,

    propping etc. & removal of formwork for:

    TOTAL G.F. FALSE WORK. 504.36 M2

    Rs.250.00

    13 REINFORCEMENT: TOR STEEL, UPTO

    PLINTH LEVEL

  • 7/29/2019 Project Cost estimation

    37/48

    Cold twisted steel and hot rolled deformed

    steel reinforcement for RCC work i/c

    cutting, bending, binding & placing in

    position complete i/c cost of binding wires.

    TOTAL REINFORCEMENT WORK 25943.48 Kg Rs.52.00

    14 BRICK WORK 300 MM THICK:

    BRICK WORK UPTO PLINTH LEVEL:

    Brickwork with well burnt chimney bricks in

    bulls patent trench kiln manufactured by

    ghol process, crushing strength not less

    than 25 kg/Sq.cm. & Water absorption not

    more than 15% in foundation and

    plinth,20cm thk.

    TOTAL BRICK WORK UPTO PLINTH

    LEVEL57.48 M

    3Rs.4,200.00

    15 BRICK WORK ABOVE PLINTH LEVEL:

    200 MM THICK BRICK WORK

    Brickwork with well burnt chimney bricks in

    bulls patent trench kiln manufactured by

    ghol process, crushing strength not less

    than 25 kg/Sq.cm. & Water absorption not

    more than 15% in Ground Floor and First

    Floor main front and back walls,20cm thk.

    NET BRICK IN G.F. SUPER

    STRUCTUREWORK 171.94 M3

    Rs.4,300.00

    16 DOORS, WINDOWS AND

    M.S. Z-SECTION FRAMES:

    a. SHUTTERS : Providing and fixing of Z-

    Section Door frames and Shutters

    including making in all respect39.60 M

    2Rs.2,150.00

    b. WINDOWS: Providing and fixing of Z-

    Section Window frames and Shutters

    including making in all respect 144.65 Kg Rs.78.00

  • 7/29/2019 Project Cost estimation

    38/48

    c. VANTILATORS: Providing and fixing of

    M.S. section Vantilator frames including

    making in all respect

    101.64 Kg Rs.90.00

    17 GLASS WORK:

    Providing and fixing of 5MM thick Brandedglass to Windows and Vantilators in all

    respect.

    85.55 M2

    Rs.650.00

    18 FLOORING WORK:

    (i) IPC FLOORING: 3829.96 M2

    Rs.170.00

    19 PLASTER WORK:

    a. 20mm thick cement plaster to uneven

    surface:

    In 1:6 CM Ground floor Double coat plaster

    1152.00 M2

    Rs.235.00

    b. 12mm thick single coat cement

    plaster to even surface:

    In 1:5 CM Ground floor single coat plaster

    1152.00 M2

    Rs.175.00

    c. Neeru plaster

    76.21 M2

    Rs.125.00

    20 PAINTING WORK:

    a. White washing on new work (three or

    more coats) to give an even shade with

    white Cement.

    2380.21 M2

    Rs.25.00

    b. Distempering (two or more coats) with

    oil bound washable distemper of required

    shade on new work over over and i/c. apriming coat with cement primer to give an

    even shade including three coat of Putty

    2304.00 M

    2Rs.115.00

  • 7/29/2019 Project Cost estimation

    39/48

    c. Painting (two or more coats) with

    synthetic enamel paint on Windows and

    Vantilators grill, Main gate Shutter work

    over and i/c. an under coat of suitable

    shade with priming coat to give an even

    39.60 M2

    Rs.85.00

    21 PEB -SUPER STRUCTURE:

    Pre-engineered building having edge

    height 6.0 Mt. and Ridge height 8.0Mt.

    Including side sheeting and roof covering

    also providing proper drainage system in

    all respect.

    3905.50 M2

    Rs.2,300.00

    TOTAL COST OF SINGLE UNIT

    TOTAL COST OF SIX UNITS6.00

    22 MAIN GATE:

    Providing and fixing 9.0M main gate with

    siliding system to both side of height 2.1M.

    18.90 M2

    Rs.3,345.00

    23 COMPOUND WALL:

    200MM thick compound wall of height

    2.5M on pile foundations framed structure,and above this height upto 3.5M berbed

    fencing provided.

    377.62 RM Rs.4,145.00

    24 SECURITY ROOM AND TOILET BLOCK:

    R.C.C. framed structure having 200MM

    thick brick wall, Alliminium door and

    window section, vitrified floor tiles.

    34.68 M2

    Rs.8,700.00

    25 WEIGH BRIDGE:

    R.C.C. Foundaion for 100 M.T. capacity

    weigh bridge in C.M. M:20. 51.20 M2

    Rs.6,500.00

    26 D.G. ROOM:

  • 7/29/2019 Project Cost estimation

    40/48

    Partially covered shed for D.G. 12.00 M2

    Rs.4,300.00

    27 INTERNAL ROADS:

    WBM Internal road having PWD

    specifications including storm water open

    drains. 13350.60 M2

    Rs.300.00

    28 Electrical work: lump sum

    TOTAL

    29 CONSULTANCY FEE

    2%

    GRAND TOTAL

  • 7/29/2019 Project Cost estimation

    41/48

    URAL PRODUCE

    Amount

    62,016.53

    PTIC TANK,

    ALL

  • 7/29/2019 Project Cost estimation

    42/48

    68,760.1921,520.68

    34,380.09

    9,223.15

    1,198,119.27

    13,824.008,100.00

  • 7/29/2019 Project Cost estimation

    43/48

    66,250.80

    6,018.87

    2,113,323.89

    683,206.24

    233,004.30

  • 7/29/2019 Project Cost estimation

    44/48

    9,108.00

    205,133.76

    126,090.00

  • 7/29/2019 Project Cost estimation

    45/48

    1,349,061.22

    241,416.00

    739,324.80

    85,140.00

    11,282.54

  • 7/29/2019 Project Cost estimation

    46/48

    9,147.60

    55,607.50

    651,093.20

    270,720.00

    201,600.009,526.25

    59,505.25

    264,960.00

  • 7/29/2019 Project Cost estimation

    47/48

    3,366.00

    8,982,650.0017,792,480.15

    ##############

    63,220.50

    1,565,234.90

    301,716.00

    332,800.00

  • 7/29/2019 Project Cost estimation

    48/48

    51,600.00

    4,005,180.00365,000.00

    ##############

    2,268,792.65#############