Corrected Dankuni Eia and Empreport

download Corrected Dankuni Eia and Empreport

of 35

Transcript of Corrected Dankuni Eia and Empreport

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    1/35

    Environment Impact Assessment&

    Environment Management Plan Report

    Dankuni is a fast-growing industrial township near Kolkata, India. The town is part of the

    Hooghly District, in the State of West Bengal. It is a part of the area covered by Kolkata

    Metropolitan Development Authority. It is well-reachable by road or trains from both Howrah

    Station and Sealdah Station. Dankuni Junction rail station is 15 km from Howrah Station.

    Nearest Airport is Dum Dum, situated 20 Km from Dankuni.

    Both NH 2 and NH 6 terminate at Dankuni. The PalsitDankuni section of NH 2 is also

    referred to as Durgapur Expressway. Other major arteries meeting at Dankuni are Belghoria

    Expressway connecting to NH 34 and the DankuniMemari Delhi Road. Dankuni railway

    station is located on the Howrah-Bardhaman chord, which was constructed in 1917. The

    Calcutta Chord from Dum Dum to Dankuni over the Willingdon Bridge (renamed Vivekananda

    Bridge) was opened in 1932.It is part of the Kolkata Suburban Railway system. Already, there

    is a growing presence of freight and wagon movements around Dankuni Railway Station,

    which is important as it connects Eastern Railway with South Eastern Railway with a link line.

    Dankuni has a fast growing freight yard, where goods traffic is moved, sorted, and packed to

    deliver at other destinations. In the future, Dankuni will play a significant role because it will

    be the endpoint of the Ludhiana-Dankuni leg of the Dedicated Freight Corridor that is beingbuilt by Indian Railways. Traffic, especially that of freight will continue to grow and will

    positively impact the railways.

    About Project

    A Locomotive Factory for Railways is proposed to be set up at Dankuni. RAIL VIKASNIGAM

    LIMITED (RVNL ), a Special Purpose Vehicle Company under the Companies Act, 1956,

    established by the Ministry of Railways, Govt. of India. Rail Vikas Nigam Limited proposed

    construction of sheds, structures, water supply, arrangement, sewerage, drainage, roads,

    track, S&T, power supply arrangement, general electrical and OHE works and supply,

    erection & commissioning of machinery & plant in connection with setting up of electric

    locomotives factory at Dankuni, West Bengal, India.

    The concept / design of the proposed factory was undertaken by Railways way back and this

    project was sanctioned in 2009-10. Rail Vikas Nigam Ltd (RVNL) awarded the contract for

    construction of the factory to M/s Simplex Infrastructures Ltd. Simplex House 27, Shakespear

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    2/35

    Sarani, Kolkata 700017 for Rs 146.44 Crores vide Notification of Award No.

    RVNL/KOL/CLW/DKAE/1/1876 Dated 02.10.2012. The factory will manufacture components

    for diesel locomotives built at Diesel Locomotive Works, Varanasi.

    The scope of work given in the construction agreement is as under,

    Section 5(28 of 99)4.18 Protection of

    the

    Environment

    The Contractor shall take all reasonable steps to protect the environment

    (both on and off the Site) and to limit damage and nuisance to people and

    property resulting from pollution, noise and other results of his

    operations.

    The Contractor shall ensure that emissions, surface discharges and

    effluent from the Contractor's activities shall not exceed the values stated

    in the Specification or prescribed by applicable Laws.

    The work of the Project Management Consultancy for this Construction work was awarded to

    M/s DATA TECHNOSYS (Engineers) Pvt ltd vide Notification of Award

    No.RVNL/KOLKATA/CLW/950 Dated 02.08.2013and it is under the scope of work of the PMC

    Contract this report is being prepared and submitted.

    The scope of work given in the consultancy agreement is as under,

    Para 3.2 (vii) , Section 4 ( 5 of 48) - Implementation of environmental mitigation measures;

    Para 3.2 (xx1) , Section 4 ( 7 of 48) - All mandatory testing as per the codal provision and

    instructions for P. way, signalling& electrical work and Environmental monitoring Plan are being

    conducted and records of such test be preserved for future."

    Section 4 ( 10 of 48) - clause 4.2.5 Environmental Issues :

    Monitoring of environmental mitigation measures as per Chapter 6 of Section 6 Employers

    requirement of the execution contract bid document. The brief descriptions of the Environmental

    issues / requirements are as under

    1. Provide technical guidance to the contractor for implementation of the EMP and

    preparation of checklists / formats / reports etc.

    2. Conduct regular monitoring of the implementation of the EMP by the contractor.

    3. Conduct regular monitoring of environmental quality (air, water, noise, soil) in and

    around the construction site as given in the EMOP (Environmental Monitoring Program

    in the IEE report, and maintain records for the same.

    Section 4 ( 14 of 48) - clause 5.3 Project Control: - The consultant shall monitor the project

    covering all aspects of the project - Environmental matters

    Section 4 ( 22 of 48) - clause 7.3.1 (ii)

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    3/35

    Environmental Expert : He shall:

    Provide technical guidance to the contractor for implementation of the EMP and preparation

    of checklists / formats / reports etc.

    (a) Conduct regular monitoring of the implementation of the EMP by the contractor.

    (b) Conduct regular monitoring of environmental quality (air, water, noise, soil) in andaround the construction site as given in the EMoP (Environmental Monitoring Plan) in

    the IEE report.

    The breakdown structure of this project i.e.Setting up of electric locomotives factory at

    Dankunias a whole is as under,

    We are at the execution stage where the main role is to monitor and control the Environmental

    aspects, beside other engineering input, based on previous reports / established documents and

    Government Policies / rules for the said project.

    Construction process is invariably involving disturbance of the existing physical environment

    in the vicinity it is undergoing. During this process, residues in the form of wastes will be

    formed. If the residues are not properly disposed off / recycled/ re-utilized they become waste

    and have to be discharged into environment as pollutants. The degree to which the pollutants

    affect the physical environment depends upon their quantitative and qualitative characteristics

    as well as that of the receiving media. However, as a general rule any Construction/

    development process is accompanied by some environmental problems. Proper planning at the

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    4/35

    conceptual stages can minimize many of these problems. Once the physical environment is

    affected badly it becomes difficult and expensive to retrofit pollution control equipment, as

    such incorporation of the same at conceptual stage itself is the best alternative. We presume that

    at the conceptual stage this has been properly addressed and covered so that later on when this

    production unit will come into force no eventuality so far as environmental issues areconcerned is faced. However as it is beyond our scope of the work so we are not required to

    study / comment on the same.

    So far as construction phase of the project is concerned a number of acts, rules and ambient

    standards exist under the Government of India (GOI) which will help to ensure that the program

    will be implemented in an environmentally safe and friendly manner. Key policies that this

    project is subjected to comply with are:

    The Environment (Protection) Act, 1986; The Environmental Impact Assessment Notification, 2006 and its amendment in 2009; Environmental Impact Assessment Guidelines for Rail, Road and Highways Projects,

    1989;

    Forest Conservation Act 1980 (Amended 1988) and Rules (1981 Amended 2003); Wildlife Protection) Act, 1972 (Amended 1993); Water Prevention and Control of Pollution Act 1972 (Amended 1988) and its Rules 1974; Air Prevention and Control of Pollution Act, 1981, (Amended 1987) and its Rules 1982; Noise Pollution (Regulation and Control) Rules, 2000 (Amended 2002); Hazardous Waste Management, Handling and Trans boundary Movement Rules 2008

    (Amended 2009), and Batteries Management and Handling Rules 2001.

    These Acts and Regulations envisage that:

    i. No environmental clearance is required for railway projects. However, periodic review

    will be made of amendments if any in this notification, for the applicability and need of

    environmental clearance for railways project.

    ii. Forest clearance from Department of Forests is required for diversion of forest land for

    non-forest purpose. Prior permission is required from forests department to carry out anywork within the forest areas and felling of rail side trees. Cutting of trees need to be

    compensated by compensatory afforestation as per the requirement of forest department.

    Not applicable in the present case.

    iii. Placement of hot-mix plants, quarrying and crushers, batch mixing plants, discharge of

    sewage from construction camps requires No Objection Certificate (Consent to Establish

    & Consent to Operate) from State Pollution Control Board prior to establishment.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    5/35

    iv. Permission from Central Ground Water Authority is required for extracting ground water

    for construction purposes, from areas declared as critical or semi critical from ground

    water potential prospective by them.

    The Executing Agency (EA) for the program is the Ministry of Railways (MOR) and the

    Implementing Agency (IA) is the Railway Vikas Nigam Limited (RVNL) under theGovernment of India.

    DEFINITION OF EIA / EMP & EMS

    Environmental Impact Assessment (EIA) is a study to identify, predict, evaluate and

    communicate information about the impacts on the environment of a proposed project and to

    detail the mitigating measures prior to project approval and implementation

    Environmental Impact Assessment (EIA) is a planning tool generally accepted as an

    integral component of sound decision-making. EIA is to give the environment its due place in

    the decision-making process by clearly evaluating the environmental consequences of the

    proposed activity before action is taken. Early identification and characterization of critical

    environmental impacts allow the public and the government to form a view about the

    environmental acceptability of a proposed developmental project and what conditions should

    apply to mitigate or reduce those risks and impacts.

    EIA is analysis of issues and recommendations EIA is documented in an Environmental

    Assessment Report (EA Report)

    ENVIRONMENTAL ASSESSMENT (EA)

    Objective

    To identify or obtain information on any relevant environmental impact that the

    construction project may cause.

    Suggested measures

    Identify sensitive environmental areas or uses that may be affected by construction

    activities.

    Identify whether residents adjacent to the site could be affected by pollution from

    construction activities or suffer reduced amenity.

    Monitor baseline air and water quality and ambient noise levels adjacent to the

    construction site.

    Conduct an assessment of expected noise levels from construction activities which

    may affect the surrounding community.

    Conduct a desk study to identify potentially contaminated sites in the construction

    area, and sample and analyse soils that are suspected of being contaminated before

    construction commences.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    6/35

    The EIA mechanism shall be applied to the project in the following order of priority:

    Avoid adverse environmental impact Minimize and control adverse environmental impact Mitigate adverse environmental impact

    The implementation of measures designed to reduce the undesirable effects of a proposed

    action on the environment is called Mitigation.

    Different types of Mitigation measures act in different ways to reduce adverse impacts:

    Type of measure How it works Examples

    Prevention &

    Control measures

    Fully or partially prevent an

    impact/reduce a risk by:

    Changing means or technique Changing the site Specifying operating practices

    PREVENT contamination of wells,

    by SITING wells a minimum

    distance from latrines.OPERATE wastewater treatment

    system for a coffee-washing station.

    Compensatory

    measures

    Offset adverse impacts in one area

    with improvements elsewhere

    Plant trees in a new location to

    COMPENSATE for clearing a

    construction site.

    Remediation

    measures

    Repair or restore the environment

    after damage is done.

    Re-grade and replant a borrow pit

    after construction is finished

    Environmental Management Plan (EMP) is a site-specific plan developed to ensure that all

    necessary measures are identified and implemented in order to protect the environment and

    comply with environmental legislation. EMP is an action plan based on results of EIA

    ENVIRONMENTAL MANAGEMENT PLAN

    Objective

    To develop an environmental management plan to reduce the adverse impact of

    construction activities on the environment.Suggested measures

    A environmental management system should be in place, as a pre-requisite to

    preparing an environmental management plan.

    Prepare an environmental control plan for defined segments of the site for large sites,

    or a whole-of-site plan for smaller sites.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    7/35

    The plan should implement the risk management action plan, include detailed

    specifications on site-specific controls and include a rehabilitation program in the

    plan.

    Base the measures in the plan on best practice. Update the plan to meet new risks or where inspections, monitoring or audit reveal

    that measures are ineffective.

    Update the plan to achieve ongoing improvement

    Environmental monitoring is a necessary complement to mitigation. It should be a normal

    part of monitoring project results.

    Environmental monitoring is,

    Systematic measurement of key environmental indicators over time, within a

    particular geographic area

    Systematic evaluation of the implementation of mitigation measures

    Mitigation & Monitoring are a critical part of environmentally sound design:

    Mitigation minimizes adverse environmental impacts & Monitoring confirms that mitigation

    measures are sufficient & effective.

    Mitigation and monitoring for an activity is defined by the Mitigation and Monitoring (or

    M&M) Plan (also called an Environmental Management Plan, or EMP)

    The EIA reports which must have been prepared along with Project Conception to

    Sanctioning stage were not available nor do any comments on the same comes under the

    preview of this Consultancy so they are not commented at this stage.

    However in general in my view no significant or adverse environmental impacts are

    anticipated during construction stage and what so ever minimum effect will arise will be

    temporary in nature.

    The environmental impacts related with the project are manageable, however monitoring the

    EMP implementation and environmental conditions needs to be done systematically to ensure

    mitigation of any unexpected environmental impacts.

    No significant impacts are anticipated on biodiversity or physical cultural resources becausethe land used was already in railway use. Impacts are primarily from construction activities

    and transportation of construction material. It has been made mandatory for the contractor to

    adopt safe construction practices and ensure use of requisite personnel protective equipment

    to protect occupational health of labour and communities around the construction sites.

    The costs for environment related issues are included under the contractors construction

    costs & Cost for monitoring the EMP is included in the PMC contract.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    8/35

    The implementation agency (IA) i.e. RVNL is to help Construction agency who is fully

    responsible to ensure to obtain necessary consents or permissions (e.g. environmental

    clearance, forest clearance, and water board clearance) from relevant Government Agencies.

    RVNL is also to ensure that all necessary regulatory clearances are obtained prior to

    commencing any civil work of the project. It will also to be ensured that the EMP whichinclude required mitigation measures and monitoring requirements are properly followed by

    the contract-ting agency. This is also to be ensured that construction workers work under safe

    and healthy working environment.

    For the effective and consistent functioning of the project, an Environmental Management

    System (EMS) is to be established at the site. The EMS should include the following:

    i. An Environmental management cell

    ii. Environmental Monitoring

    iii. Personnel Trainingiv. Regular Environmental Audits and Corrective Action

    v. Documentation Standard operating procedures Environmental Management Plans

    and other records

    Apart from having an Environmental Management Plan (EMP), it is also necessary to have a

    permanent organizational set up charged with the task of ensuring its effective implementation of

    mitigation measures and to conduct environmental monitoring. The major duties and

    responsibilities of Environmental Management Cell shall be as given below:

    i. To implement the environmental management plan,

    ii. To assure regulatory compliance with all relevant rules and regulations,

    iii. To ensure regular operation and maintenance of pollution control devices,

    iv. To minimize environmental impacts of operations as by strict adherence to the EMP,

    v. To initiate environmental monitoring as per approved schedule.

    vi. Review and interpretation of monitored results and corrective measures in case monitored

    results are above the specified limit.

    vii. Maintain documentation of good environmental practices and applicable environmental

    laws as ready reference.

    viii. Maintain environmental related records.

    ix. Coordination with regulatory agencies, external consultants, monitoring laboratories.

    x. Maintain of log of public complaints and the action taken

    The purpose of environmental monitoring is to evaluate the effectiveness of implementation of

    Environmental Management Plan (EMP) by periodically monitoring the important environmental

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    9/35

    parameters within the impact area, so that any adverse affects are detected and timely action can

    be taken.

    Description of the Site :

    The land identified for the proposed project is 42 acres. The major portion of land acquired for

    the proposed site is unpopulated, partially cultivated, with some thorny bushes and has no forest

    land. General soil characteristics are suitable for installation of the plant. There are no national

    parks, wildlife sanctuaries, archaeological sites, military areas/establishments, airports, in the

    study area.

    Under this it is required to monitor ambient air quality, noise levels, groundwater quality, and

    solid wastes in accordance with an approved monitoring schedule. The monitoring protocol and

    location selection will have to done carefully. A suggested monitoring protocol, based on the

    expected impacts is as under,

    At start of the project a basic base line survey of the main factors i.e Ambient Air

    Quality, Ambient Noise, Surface Water Quality and Ground Water Quality and depth of Water Table

    should have been conducted by Construction agency. It appears that the same is missing. The project is at

    quite initial stage so this is the first responsibility of the construction agency to arrange this tests / survey

    for generation of base line data with respect to present air quality, water quality, noise level, soil

    quality, ecology, socio-economic and meteorology etc by some competent agency and submit report

    for record and future comparison to study / establish the effect of construction activities on environment.

    Afterwards for the effective monitoring the following tests should be conducted periodically and report be

    submitted for critical analysis and recommendations suggestion so that environmental impact is withincontrollable / permissible limits.

    Suggested Monitoring Program

    Sl.

    NoType Location Parameters Period & Frequency

    1 Ambient Air

    Quality

    Project Site in y

    axis

    Criteria Pollutants:

    SO2, NOx,

    CO,

    24-hr average samples

    twice in a week during

    Construction

    2 Ambient Noise Project Site andaround the project

    site at 5 locations

    dB(A) levels during

    Construction

    3 Surface Water Quality 3 stations around

    project Site

    Physical and chemical

    Parameters.

    Once a month.

    Bacteriological

    parameters.

    Once in a year

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    10/35

    Heavy metals and toxic

    constituents.

    Once in 3 months

    4 Ground Water Quality and

    depth of Water Table

    3 stations in and

    aroun project Site

    Physical and chemical

    Parameters

    Total Organic matter

    concentration

    Once a month.

    Bacteriological

    parameters.

    Once in a month

    Heavy metals and toxic

    constituents.

    Once in 3 months

    OBJECTIVE OF EIA AND EMP REPORT

    The aim of this EIA study report is to take stock of the prevailing quality of environment, to

    assess the impacts of construction activities on environment and to build appropriate

    environmental control measures to minimize adverse impacts and to maximize beneficial

    impacts. The following major objectives have been considered:

    Assess the existing status of environment. Assess the impacts due to the proposed activity. Suggest pollution control and ameliorative measures. Prepare an action plan for implementation of suggested ameliorative measures.

    Suggest a monitoring programme to assess the efficacy of the various adoptedenvironmental control measures.

    The first step in environmental impact assessment is to list all the potentially significant

    environmental impacts. These are then examined critically and the major impacts (both negative

    and positive) are analyzed in detail for the EIA.

    Scope of the Study

    The scope of the study broadly includes:

    a) Collection of base-line data on Physico-chemical, ecological and socio-economic

    aspects of environment considering the following attributes: Meteorology Air Pollution Noise Pollution Water Pollution (both Surface and Ground Water) Soil Characteristics Ecology (Flora and Fauna) Socio-economics

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    11/35

    b)Evaluation of incremental levels of pollutants in the study area due to the proposed

    project.

    a) Prediction of impacts on the various environmental attributes by using scientifically

    developed and widely accepted environmental impact assessment methodologies.

    b) Preparation of Environment Management Plan (EMP) to mitigate the predictedImpacts.

    c) Identification of critical environmental attributes required to be monitored during the

    project execution and to suggest post project monitoring.

    d) Identification and assessment of risk and hazard associated with the activities of the

    proposed plant.

    Methodology for EIA

    The study comprises collection of relevant data. The study should covers at least an area of 10

    km. radius around the proposed project site. The study covers the aspects of air, water, noise,

    biological environment, and meteorology, demographic and socio-economic features of the study

    area.

    Meteorology

    The meteorological parameters such as wind speed, wind direction, temperature, humidity and

    rainfall were collected which were from the nearest IMD observatory of Alipore. As per

    collected data the Maximum temperature in the area is 35C in April / May and minimum

    temperature 14C in December January. As per local IMD station at Alipore, the average annual

    rainfall is 1821.8mm, and most of it is during the monsoon season, which lasts from June ends to

    September. The relative humidity varies from 21 to 87%. The prevailing wind direction is SW

    and, N, NE while mean wind speed is around 5.3 and 5.6 m/s in December and January

    respectively.

    CLIMATOLOGICAL TABLE

    PERIOD: 1971-2000

    Month

    Mean

    Temperature( oC)

    Mean

    Total Rainfall

    (mm)

    Mean

    Numberof Rainy

    Days

    Mean Number of days with

    Daily

    Minimum

    Daily

    Maximum HAIL Thunder FOG SQUALL

    Jan 14.0 26.1 11.7 1.0 0.0 1.0 7.4 0.0

    Feb 17.3 29.1 30.7 2.0 0.1 2.5 4.0 0.5

    Mar 21.9 33.5 38.2 2.2 0.0 3.8 1.3 1.1

    Apr 25.1 35.4 58.8 3.5 0.2 7.1 0.1 2.7

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    12/35

    May 26.2 35.3 136.6 7.2 0.0 9.9 0.1 3.4

    Jun 26.6 33.9 283.5 12.7 0.0 11.7 0.0 1.4

    Jul 26.3 32.4 399.9 17.7 0.0 12.5 0.0 0.5

    Aug 26.2 32.1 352.4 17.0 0.0 12.2 0.0 0.3

    Sep 25.9 32.3 312.6 13.6 0.0 14.8 0.1 0.3

    Oct 24.1 32.3 157.8 6.8 0.0 7.0 0.6 0.1

    Nov 19.7 30.2 30.7 1.3 0.0 0.4 1.3 0.0

    Dec 14.7 27.0 8.8 0.6 0.0 0.2 4.8 0.0

    Annual 22.3 31.6 1821.8 85.6 0.2 82.9 19.5 10.2

    IMPACT ASSESSMENT AND MITIGATION MEASURES

    The construction and operational phase of the proposed project comprises various activities eachof which may have an impact on environmental parameters. Various impacts during the

    construction on the environment have been studied to estimate the impact on the environmental

    attributes and are discussed in the subsequent sections. The probable impacts of each of these

    activities on various sectors of environment have been mentioned here.

    The impact during construction will be localized and short term with permanent changes in the

    land use of project site as compared to the current conditions. Impact will be primarily related to

    the civil works and less intensive impact is expected during erection of the equipment and trial

    operation. The details of the activities and probable impact are discussed blow.Impact on Land-use

    The land identified for the proposed plant is 42 Acres. Land-use and land-cover of the proposed

    plant area will be changed into industrial land use and the changes will be permanent in nature.

    Thus construction activity will bring in certain immediate changes in the land use pattern of the

    proposed project area. The major portion of land acquired for proposed site is unpopulated, with

    some thorny bushes and has no forest land, so the impact on land use pattern will be minor.

    Impact on Land

    Soil disturbances and impacts on local geology will occur mainly because of site preparation

    activities and disposal of excavated or scrapped materials. Secondary effects may occur due to

    erosion and windblown fugitive soil. The soil layer will also be disturbed because of the

    proposed activity.

    Temporary labor colonies, with adequate potable water and sanitary facilities shall

    be provided in the areas already acquired for the project.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    13/35

    This will be only a temporary change (restricted to construction period). After

    construction phase is over, the area acquired by labor colonies shall be reverted

    back as per the requirement for other purposes.

    The Potential Sources of impact and Mitigation Measures on land environment are

    highlighted in the following Table .Potential Environmental Impacts on Land Environment

    Activity Evaluation Potential Environmental Impacts

    Construc

    tion

    Phase

    Potential Source of

    Impact

    a. Disposal of construction debris.

    b. Waste handling

    Controls through

    EMP & Design

    Construction debris will be collected and

    suitably used on-site as per construction waste

    management plan.

    Impact Evaluation Impact will be local as any waste generated

    will be reused for construction activities.

    Impact is insignificant.

    Impact on Soil

    All major construction activities tend to create certain changes in the soil of the core area.

    Excavation denudes the topsoil and makes it loose. Destruction of topsoil leads to

    reduction of fertility and removal of vegetation cover with associated hazards of the soil

    erosion. During storms, some of the excavated soil and construction material such as

    sand etc. would be blown up in the air and dispersed around the project site, some would

    also tend to be driven into the soil and clog inter-granular spaces. However, in order to

    minimize such impacts, appropriate soil conservation measures would be undertaken.

    Top-soil shall be preserved and reused in green areas. Vegetation cover would also be

    replaced by planting and surfing wherever feasible. Short term, localized impacts are

    anticipated on the soil quality of the core area during the construction stage and no impact

    is envisaged on the surrounding area.Preservation of top soil: During construction, soil becomes unconsolidated due to

    removal of stabilizing material such as vegetation and disturbance of stabilized existing

    grade resulting in loss of top soil and also deposition in the undesirable places. A soil

    erosion and sedimentation control plan to be prepared prior to construction and should be

    applied effectively. Measures for preservation of topsoil are mentioned in the Soil

    resource section above.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    14/35

    Topsoil removal and preservation shall be mandatory for development projects larger

    than 1, 00 hectare (Source: National Building Code 2005). Topsoil shall be stripped to a

    depth of 200 mm from areas proposed to be occupied by buildings, roads, paved areas

    and external services. Top soil shall be stockpiled to a height of 400 mm in pre

    designated areas for preservation and shall be reapplied to site during plantation of theproposed vegetation. Measures should be applied to control erosion of preserved top soil.

    Top soil shall be separated from sub-soil debris and stones larger than 50 mm diameter.

    Human activities during construction can accelerate erosion by removing vegetation,

    compacting or disturbing the soil, changing natural drainage patterns, and by covering the

    ground with impermeable surfaces (pavement, concrete, buildings). When the land

    surface is developed or hardened in this manner, storm water and snowmelt cannot seep

    into or infiltrate the ground. This results in larger amounts of water moving more

    quickly across a site which can carry more sediment and other pollutants to streams and

    rivers. (Source: Chapter 3, EPA) Disruption to the natural hydrology of the site could be

    minimised by reducing impervious cover, increasing on site infiltration and managing

    storm water runoff.

    Mitigation options When opening the site, care should be taken to keep vegetation clearing at a

    minimum.

    To keep the damage to topsoil minimum, excavators must be used for

    construction. The excavated material such as topsoil and stones should be

    stacked at safe places for reuse at a later stage of construction.

    Prevent soil erosion for large sites during construction by providing

    sedimentation basin, contour trenching, mulching, as required. Some generic

    soil erosion control measures are described below:

    Soil erosion and sedimentation control measures On the proposed site the net imperviousness of the site should not exceed the

    imperviousness factor as prescribed by the National Building Code 2005; Part9 (Plumbing services) Section 5.5.11.2.1.

    Preserving existing vegetation or revegetating disturbed soils is one of the

    most effective ways to control soil erosion.

    There are two types of soil erosion control:

    Temporary controls provide cover to the soil for a short period of time, till

    the permanent measures are adopted. These are usually applicable during

    construction.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    15/35

    Permanent controls These measures are incorporated on soil, when

    activities that disturb the soil are over. These measures could be applicable

    post construction in the proposed landscape plan.

    Impact and Mitigation Measures on Air Quality

    Dust will be the main pollutant affecting the ambient air quality of the area during the

    construction phase. It will be generated during excavation, back filling, hauling and

    vehicular movement of trucks, dumpers and construction machinery. Special care, as

    mentioned below shall be taken to control dust emission from vehicular movement,

    stockpiles and other construction activities:

    In order to minimize the atmospheric generation of dust and gaseous emissions

    through vehicular traffic and exhaust emissions, only properly maintained

    certified vehicles shall be deployed at site.

    The building material shall be adequately covered while transporting through

    trucks .

    Suitable surface treatment to roads shall be provided to ease the traffic flow. Sprinkling of water on roads shall be regularized to reduce uncontrolled dust

    generation.

    Extensive tree plantation shall be carried out along the plant boundary and at some

    identified area within the proposed site to control spread of fugitive dust emission

    that will occur due to construction activity, like handling of material and

    transportation within the plant premises.

    Aggregates and sand will be stockpiled at suitable places (after stabilizing the

    surface), near the boundary wall so that the wall acts as windshield.

    In case the height of stockpiles exceeds that of the boundary wall then additional

    windshields of adequate height (preferably with tin sheets) will be provided.

    To prevent dust nuisance from the stockpiles it will be covered with plastic sheet,

    wherever required.

    Fugitive dust emission during dry weather conditions, arising out of the

    excavation, leveling, transportations and stockpiling activities shall be controlled

    by water sprinkling.

    Cement will be stocked inside covered sheds only.

    With these provisions, only short term, localized impacts are anticipated due to dust

    emissions during the construction stage.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    16/35

    Impact on Ambient Noise Level

    Noise is typically defined as "unwanted sound", sound being the human sensation of pressure

    fluctuations in the air. Sound levels are expressed in decibels (dB) on a logarithmic scale, where

    0dB is nominally the "threshold of hearing" and 120dB is nominally the "threshold of pain".

    Noise can seriously harm human health and interfere with peoples daily activities. The main

    health risks of noise identified by WHO are:

    Pain and hearing fatigue; Hearing impairment including tinnitus;

    Annoyance; Interferences with social behaviour (aggressiveness, protest and helplessness); Interference with speech communication; Sleep disturbance and all its consequences on a long and short term basis;

    Cardiovascular effects; Hormonal responses (stress hormones) and their possible consequences on human

    metabolism (nutrition) and immune system; Performance at work and school.

    Noise generally radiates in all directions, but can bend around and over walls and buildings

    and can reflect back from solid surfaces. Significantly careful positioning of noisy plant and

    equipment can be very effective in reducing noise levels.

    Noise generated by construction activities particularly in urban areas can impact on any adjacent

    residential and indeed commercial areas, such impacts can be even more severe at

    night. Construction site noise can also be a health hazard for those who are working on site.

    Construction Activity Sound pressure in dB(A)

    Rock drill 110

    7hp road roller on concrete at 10m 100

    Scaffold dismantling at 10m 80

    5hp power float at 7m 70

    Typical office 60It is significantly less expensive (unit cost per decibel reduction) to make noise-generating

    processes quieter than to make a barrier to screen the noise.

    Noise levels can be lowered by eliminating or reducing the noise at source with the use of noise-

    control enclosures, absorbers, silencers and baffles and by the use of personal protective

    equipment, such as earmuffs. Where technical methods are insufficient, noise exposure may be

    reduced by use of hearing protection and by administrative controls -- such as limiting the time

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    17/35

    spent in noisy environment and scheduling noisy operations outside normal shifts or at distant

    locations.

    Essential elements of environmental noise control programmes are education and training of the

    workers to minimise noise generation on a site.

    Abstract of THE NOISE POLLUTION !REGULATION AND CONTROL) RULES. 2000issued by Central Pollution Control Board (CPCB) is as under,

    SCHEDULE

    (seerule3(1)and 4(1))

    Ambient Air Quality Standards in respect of Noise

    Area Code Category of Area I Zone Limits in dB(A) Leq*

    Day Time Night Time

    (A) Industrial area 75 70

    (B) Commercial area 65 55

    (C ) Residential area 55 45

    (D) Silence Zone 50 40

    Note:-

    Day time shall mean from 6.00 a.m. to 10.00 p.m. Night time shall mean from

    10.00 p.m. to 6.00 a.m

    Silence zone is an area comprising not less than 100 metres around hospitals,

    educational institutions, courts, religious places or any other area which is declared as

    such by the competent authority

    Mixed categories of areas may be declared as one of the four above mentione d

    categories by the competent authority.

    *dB(A) Leq denotes the time weighted average of the level of sound ing decibels

    on scale. A which is relatable to human hearing.

    A " decibel" is a unit in which noise is measured.

    "A", indB(A)Leq, denotes the frequency weighting in the measurement of noiseand corresponds to frequency response characteristics of the human ear.

    Leq: It is an energy mean of the noise level over a specified period.

    Heavy traffic for loading and unloading, and handling of construction equipments and

    material are likely to cause an increase in the ambient noise levels. The typical noise

    levels of sources used in construction work including D.G. set and vehicular traffic are

    shown in the following Table . ( Source: Environmental Data Book; page-508 ).

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    18/35

    Composite Background L dn Noise and Plants Construction Noise at a Receptor Point

    S.

    No.

    Equipments Noise,

    dB(A)

    Back-

    ground

    L dn Noi

    se

    Composite Background Day-Night Noise (L dn ) and

    Construction Noise, in dB (A), at Receptor Point

    (distance in meter)

    Equipment Noise50

    mt

    100

    mt

    200

    mt

    300

    mt

    400

    mt

    500

    mt

    650

    mt

    1000

    mt

    2000

    mt

    1. Dredging 89 51.8 52.5 52.0 51.8 51.8 51.8 51.8 51.8 51.8 51.8

    2. Pickup Trucks 92 dB(A) 53.0 52.1 51.9 51.8 51.8 51.8 51.8 51.8 51.8

    3. Scraper 93 53.3 52.2 51.9 51.9 51.8 51.8 51.8 51.8 51.8

    4. Heavy Trucks 95 54.0 52.5 52.0 51.9 51.8 51.8 51.8 51.8 51.8

    5. Generator 96 54.4 52.6 52.0 51.9 51.9 51.8 51.8 51.8 51.8

    6. Fork Lift 100 56.7 53.6 52.3 52.0 51.9 51.9 51.9 51.8 51.8

    7. Caterpillar 103 59.0 54.9 52.8 52.3 52.1 52.0 51.9 51.8 51.8

    8. Crane 104 59.8 55.5 53.0 52.4 52.1 52.0 51.9 51.9 51.8

    9. Loader 104 59.8 55.5 53.0 52.4 52.1 52.0 51.9 51.9 51.8

    10. Ditcher 104 59.8 55.5 53.0 52.4 52.1 52.0 51.9 51.9 51.8

    11. Concrete Mixer 105 60.6 56.0 53.3 52.5 52.2 52.1 52.0 51.9 51.8

    12. Dragline 105 60.6 56.0 53.3 52.5 52.2 52.1 52.0 51.9 51.8

    13. Pile Driver 105 60.6 56.0 53.3 52.5 52.2 52.1 52.0 51.9 51.8

    Composite Noise of

    Generator + Concrete

    Mixer +L dn

    105.5 61.1 56.4 53.5 52.6 52.3 52.1 52.0 51.9 51.8

    Composite Noise of

    Generator + Concrete

    Mixer + Loader +L dn

    107.8 63.2 58.0 54.3 53.1 52.6 52.3 52.1 51.9 51.8

    In order to find out the impact of plants construction noise at a receptor point, thecomposite Ldn and plants construction equipment noise (L c) over distances has been

    computed by applying standard noise propagation and addition formula (Para, 4.3.3.1);

    the values are given in Table 4.3 with following abbreviations:

    Ldn = Background day-night noise level = 51.8 dB (A) (Chapter 3, Table 3.5.4)

    Lc = Composite noise in dB (A) of construction equipments (2 or more equipments

    running simultaneously.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    19/35

    Lc,dn = Composite noise, Lc of construction equipments clubbing with background noise,

    Ldn

    The reduction in cumulative noise (L c+Ldn) over distances for generator, loader and

    concrete mixer, clubbing with background noise have been plotted in Figure 4.1.

    Lc= Composite noise of generator (96 dB (A)), loader (104 dB (A)) and concrete mixer(105 dB (A))

    Ldn=Back ground day-night noise; 51.8 dB (A)

    Figure 4.1: Reduction in Cumulative Noise (L c+L dn ) over Distance

    Impact due to Individual and Cumulative Construction Equipments

    Operation Noise

    It may be seen from Table 000 that:

    Beyond, approximately, 200 mt, no construction equipment (S. No. 1-13) shall

    contribute more than 1 decibel noise (i.e. >52.8 dB(A)) to the back ground noise

    (51.8 dB(A)) of the study area. This distance is very much within the plants

    premises.

    Between 200 mt to 2 km, there shall be insignificant contribution of 1

    dB (A) to the ambient noise beyond 200mt and between 200 m to 2 km there shall

    be insignificant contribution of

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    20/35

    The composite noise, L c of generator, concrete mixer and loader is not

    contributing >1 dB (A) to the ambient noise beyond 300mt and between 300 mt to

    2 km there shall be insignificant contribution of

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    21/35

    The noise level near the construction equipments and nearby areas shall be

    regularly monitored. In case of higher noise, appropriate action shall be taken to

    bring it down to tolerable limit.

    With these measures it may be ensured that the noise level during construction phase

    surrounding the core area shall be controlled to permissible standard. However, the noisegeneration will be confined within the immediate surrounding areas of the construction

    site and only for a short term. Localized and reversible insignificant impact is expected

    due to noise emissions generated during the construction stage.

    Impact on Water Environment

    The water requirements during the construction phase of the proposed plant would be

    small as construction will be more related to mechanical fabrication, assembly and

    erection. Following action shall be taken to avoid any impact on the surface and ground

    water quality during construction phase.

    1. Storm water drains will be made immediately after starting construction activity.

    The drains will be properly aligned in conformity with the site drainage pattern so

    that the alteration is kept to the minimum and flooding or soil erosion does not

    occur.

    2. Sedimentation pits will be provided at appropriate location to trap the silt laden

    runoff water and prevent excessive silt from going outside.

    3. The storm water drains will be suitably diverted to the water reservoir to collect

    the runoff. This stored water will be utilized for construction purposes.

    4. No wastewater will go out of the plant premises during the construction stage and

    contaminate the surrounding water bodies in any manner.

    5. Temporary sanitation facilities (septic tanks and soak pits) will be set-up for

    disposal of sanitary sewage generated by the workforce.

    6. Rainwater harvesting/recharge structures will be made at suitable points to collect

    the excessive runoff generated from the paved areas of the plant site and divert

    them for recharging the groundwater table.

    With the above measures, it may be envisaged that overall impact on water environment during

    construction phase due to proposed project shall be insignificant.

    Impact on Flora & Fauna

    The initial construction work at the project site involves site clearance. The site is almost

    barren land with some thorny bushes and very scanty vegetation cover is observed at the

    plant site. No ecologically sensitive floral species exist in the proposed site. As such the

    construction activities shall have insignificant impact on the flora. Moreover greenbelt

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    22/35

    will be developed phase wise during construction to improve the aesthetic value in the

    area and to screen out the fugitive dust generated during construction.

    No wild life sanctuary, national park or faunal species of significance have been observed

    in the study area. Similarly, no domestic animals were encountered at the proposed site;

    the reason may be the lack of food, water or shelter inside the proposed site. Few speciesof birds are sighted in and around the site. Plantations will improve the habitat of

    avifauna.

    Short term, localized insignificant impact on ecology is anticipated during the

    construction stage.

    Socio-Economic Impacts

    The project shall create both direct or indirect job opportunities. This indicates the

    availability of sizeable manpower locally, required for the construction activity. There

    shall also be migration of semi-skilled/skilled labor force from outside in the study area

    during construction phase, which may put some pressure on the local settlements and

    resources. However temporary accommodation, with necessary facilities, shall be created

    on-site. Also this shall be temporary in nature and limited to the construction period.

    However, the flow of workforce and material will affect the socio-economic status of the

    people in the area. Growth/expansion of shops, dhabas , small hotels and other allied

    services will also open up avenues for employment. The subsequent improvement in the

    status of the people will also help in increasing the health and education status of the

    people. As such the positive impact is envisaged on socio-economic aspects of the

    surrounding population.

    It may also be highlighted that there is no cultural heritage site (temple, mass bathing site

    during religious festivals, etc) is located close to the project site that could be affected

    during the construction stage. As such positive impact is anticipated on the socio-

    economic status of the people residing, particularly, in the vicinity of the proposed plant

    area.

    Impact on Workers Health, Sanitation and SafetyThe health of workers will be checked for general illness-first time upon employment and

    thereafter at periodic intervals, as per the local laws and regulations. Health centre and

    ambulance facility will be provided to workers. Workers exposed to dust and noise will

    be given personnel protective equipment like nose masks, face shields, ear plugs, etc. Job

    rotation schemes will be practiced for over-exposed persons. Facilities planned for

    construction workers include temporary shelters, fuel, toilet, safe drinking water, medical

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    23/35

    facilities and crche. Insignificant impact is anticipated on the workers health and safety

    during the construction stage.

    4.2.9 Solid Waste Disposal

    Solid waste during the construction phase will consist primarily of scrapped building

    materials, excess concrete and cement, rejected components and materials, packing andshipping materials (pallets, crates, Styrofoam, plastics etc.) and human waste. However, it

    is expected that there will be generation of sizeable amount of garbage, for which suitable

    disposal methods shall be devised:

    Careful design, planning and good site management would minimize waste of

    materials such as concrete, mortars and cement grouts.

    Construction wastes will be segregated as much as possible at site itself to

    increase the feasibility of recycling concrete and masonry as filling material and

    steel pieces as saleable scrap.

    Litter collection points will be established around the work sites and disposed off

    through the facility of the local authority.

    Empty packaging materials, drums, glass, tin, paper, plastic, pet bottles, wood,

    thermocol and other packaging materials will be disposed through recyclers

    (locally called kabadis).

    The construction spoils including top soil will be temporarily stored at designated

    dumpsite located inside the plant premises. Later on these wastes will be used for

    land filling, leveling, developing garden, lawns etc., within the plant premises.

    Impact on Sensitive Targets

    The sensitive targets include the following:

    1. Religious and historical places

    2. Archaeological monuments

    3. Scenic areas

    4. Hill resorts

    5. Beach resorts

    6. Health resorts

    7. Estuaries

    8. Biosphere reserves

    9. National Parks and sanctuaries

    10. Natural lakes, swamps

    11. Seismic zone

    12. Tribal settlements

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    24/35

    13. Areas of scientific and geological interests

    14. Defense installations

    15. Border areas (international) and

    16. Air Ports

    There exist no such targets and as such there shall be no impact on any of the above targetdue to proposed plant activities.

    Overall Impact Statement

    The plant site is basically a land devoid of population. No reserve forest or important

    historic place is situated at the proposed site or in the vicinity. There exist no notified

    rare species of flora in the study area which would be affected due to the plant operational

    activities.

    Since all necessary pollution control measures to maintain the emission levels of dust

    particles, Sulphur Dioxide, Nitrogen Oxides and noise within the permissible limits

    would be taken and all generated liquid effluent after due treatment shall be in-house

    utilized, there shall be insignificant impact on the surrounding area.

    Other provisions for pollution such as on line monitoring and control, to ensure

    compliance with the requirements of the State Pollution Control Board will be made.

    It is evident from above that the various mitigation measures proposed to be adopted

    during the construction phase shall reduce the scale of environmental impacts to

    insignificant level.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    25/35

    ENVIRONMENT MANAGEMENT PLAN

    Environmental Management Plan is the key to ensure that the environmental quality of thearea does not deteriorate during construction period of the proposed plant under study. The

    probable impacts during construction stage have been discussed in above paragraphs.

    Management plan consists of the following activities:

    Specific action plan for implementing mitigation measures Monitoring of Environmental Quality Rainwater Harvesting Training Statutory requirements and Implementation Documentation Green Belt Plantation Social Responsibility

    Environment Management Plan (EMP) is aimed at mitigating the possible adverse impacts of a

    project and for ensuring maintenance of existing environmental quality. Formulation and

    implementation of EMP also reinforces beneficial impacts of a project. The EMP covers all

    aspects of planning, construction and operation of the project, which are relevant to the

    environment. It is essential to implement the EMP right from the planning stage and then

    continuing it throughout the construction and operation stages. Therefore the main objective of

    the EMP is to identify the project specific activities that would have to be considered for

    investigation of the significant adverse impacts and the mitigation measures required.

    Environment Management Plan during Construction Phase

    The major construction activities that have potential environmental impacts involve pre-

    construction site preparation and installation of temporary and permanent facilities to meet the

    future requirements for success of the project. However, except for permanent change in locallandscape and land use pattern of the project site, the constructional phase impacts are temporary

    and localized phenomena.

    To implement the Environment Management Plan (EMP), a structured Environment

    Management Group (EMG) shall be created. The EMG shall undertake regular monitoring of

    the environment during the construction (as well as operation phase) of the project. It shall also

    check that the stipulated measures are being satisfactorily implemented. It shall also co-ordinate

    with local authorities and ensures filing of relevant reports to statutory bodies.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    26/35

    The success of environmental control measure can only be understood by proper monitoring of

    the environmental parameters. A detailed monitoring for different environmental parameters

    will be carried out as per direction of West Bengal Pollution Control Board. Monitoring

    methodologies will follow standard methods prescribed by Central Pollution Control

    Board (CPCB), Bureau of Indian Standards (BIS) etc. Major monitoring parameters arediscussed below.

    Environmental Management Plan during Construction Phase

    Environmental

    Component Remedial Measures Time frame

    Responsibility

    Prime Secondary

    Water Ground Water As for as possible No extraction

    of groundwater

    Throughout

    Construction Phase

    CO CA

    Surface water sources No disposal of any

    Waste water out side.

    Through out

    Construction Phase

    CO CA

    Drinking Water

    Requirement

    Arrange water without

    Affecting local requirement

    Throughout

    Construction Phase

    CO CA

    Waste water from

    Workers' camp

    Ensure proper sanitation and

    Drainage. No direct

    waste water discharge in

    water bodies or the rivers

    Throughout

    Construction Phase

    CO CA

    Dust Generation Spraying of water wherever

    required

    Throughout

    Construction Phase

    CO CA

    Gaseous Emission from

    Construction work.

    / vehicles

    Ensure checking of vehicular

    Emission and obtaining

    Pollution

    Throughout

    Construction Phase

    CO CA

    Noise from machineries

    And construction

    Ensure machineries meeting

    Noise level standards

    Throughout

    Construction Phase

    CO CA

    Land Development Preserve the excavated

    Top soil to be used for green

    belt development

    Throughout

    Construction Phase

    CO CA

    Solid Waste from Construction work

    Ensure dumping at Preselected location

    Throughout Construction Phase

    CO CA

    Occupational Health Ensure necessary facilities

    According to Factories Act

    Throughout

    Construction Phase

    CO CA

    CA Consultancy

    CO Construction Agency

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    27/35

    Periodic Preventive Maintenance

    All pollution control, monitoring and safety equipments shall be periodically checked

    and calibrated.

    Safety & Health

    Periodic monitoring of the health of the workers will be carried out as required by

    Factories Act for safety, mock drill of the concerned employees for handling the

    emergency situation will be carried out, as apart of On-Site Emergency Plan. Air

    Quality at the work place will be measured intermittently.

    Green Belt Development

    There will be all efforts for improving the environmental quality of the plant complex

    through tree planting in organized manner. The trees will be planted inside the plant in

    vacant areas, along the boundary walls in rows to develop a wide green belt and also in

    dust prone area along with vacant area for landscaping including gardening.

    The predominant species list for greening is as follows:

    Acacia auriculaeformis (akasmoni), Alstoniascholaris (chatim), Cassia fistula

    (bandarlathi), Lagerstroemeaparviflora (jarul), Terminaliacatappa (kathbadam),

    Spathodeacampanulata (spathodea), Grevelliarobusta(silveroak), Delonixregia

    (gulmohar), Peltophorumpterocarpum (radhachura), Gmelinaarberea (gamar) etc.Rainwater Harvesting

    Rainwater harvesting is now an important component of wise resource use and

    environmental management During construction / operation of the plant following

    approach will be taken to implement the Rain water harvesting plan. Rain water from

    the roofs of all the Station Buildings of the units, storm water drains adjoining the roads

    of the plant shall be collected in a rainwater collection tank. All storm water drains of

    the main plant area shall be connected to the rain water collection tank. Rain water

    collected in the rainwater tank is to be utilized for further use. This is achieved byinstalling a suitable pump at one end of the tank. This shall pump the collected water to

    the synthetic PVC tank installed on the roof of superstructures Building. The size of the

    synthetic tank shall be suitably sized based on the rain fall intensity and the runoff

    there-of. Additional tanks could be installed as and when the underground tanks are

    added. PVC pipe is proposed for pumping water from the rain water collection tank to

    the tanks on top of the buildings.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    28/35

    Collected water from the synthetic tank is distributed by gravity to desired

    locations for non-potable use like gardening, cleaning etc.

    Training

    Training is of much importance in environmental management. Environmental

    science is a developing subject and the people implementing environmental strategiesshould remain up to date with the environmental control processes. The person in

    charge of the environmental jobs should attend suitable training courses. Besides, there

    shall be training programme for the general employees at different level.

    Statutory Requirements and

    Implementation

    Each industry needs to meet a number of statutory requirements under Water

    (Prevention & Control of Pollution) Act; Air (Prevention & Control of Pollution) Act;

    Environment (Protection) Act; Hazardous Waste (Management &Handling) Rules;

    Manufacture, Storage and Import of Hazardous Chemicals Rules etc. Company has

    also to submit yearly Environmental Statements. Environment Management plan

    will ensure that these entire statutory requirements are met in time.

    Documentation

    Documentation is an important step in implementing Environmental Management Plan.

    All statutory norms should be kept at one place for quick references. All monitoring

    results should be kept at selected folders which can be easily accessed. The presentation

    of the results should also be planned. Graphs and diagrams can be used to show the

    trend in environmental quality or achievement. Documents should be kept at a declared

    position.

    Documentation will include

    o Major technical information in operationo Organizational Chartso Environmental Monitoring Standardso

    Environmental and related legislationo Operational Procedureo Monitoring Recordso Quality Assurance Plan for Monitoringo Emergency plans

    Safety and Infrastructure Services for Personnel

    Manpower required during construction phase is expected to be approx. 100.

    Construction personnel shall be made aware of possible hazards and safety measures that

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    29/35

    need to be taken during construction activities through proper training. Adequate

    personal protective equipments such as dust masks, goggles, earplugs/earmuffs, safety

    gloves, safety belts, shoes with toe protection, gumboots shall be made available at the

    construction site and the construction company shall strictly observe applicable safety

    norms.Temporary accommodation facilities shall be created for staff and construction workers

    and necessary arrangements shall be made to meet the basic requirements, as highlighted

    below:

    Temporary shelters Canteen facility Fuel facility (so that they do not cut any fuel wood) Safe drinking water facility

    Sanitation/toilets with septic tank Rest room Medical facility Crche MSW disposal facility at nearest municipal waste collection site.

    Land Environment Management

    Topography of the proposed site is almost flat and no major filling/cutting works are

    anticipated except for the purpose of foundation. Dust generated due to earthwork

    including excavation and transportation activities, especially during dry weather

    conditions, shall be controlled by water sprinkling. The earth generated during excavation

    shall be used in refilling, leveling and landscaping the area.

    No nallas or water courses are present at the project site. Natural drainage pattern shall

    not be disturbed as far as possible.

    The approach road to project site shall be appropriately widened to facilitate vehicular

    movement.

    Before starting-up of earthwork during construction, work on development of the

    greenbelt area shall be initiated and plantation of trees taken up.

    The measures, which would be followed to prevent soil erosion and contamination, are

    summarized below:

    Maximize use of top soil for landscaping To prevent soil contamination by oil/grease, leak proof containers shall beused for

    storage and transportation of oil/grease. Wash off from the oil/grease handling

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    30/35

    area shall be drained through impervious drains and treated appropriately before

    disposal.

    Removal of as little vegetation as possible during the development Plantation of trees in green belt area.

    Handling of Construction EquipmentVehicles and machinery deployed for construction work, transportation of debris and

    other materials shall be properly maintained and handled to minimize emissions of

    particulates and gaseous pollutants. The vehicles maintenance shall be monitored

    regularly so as to avoid noise pollution and accidental spillage of oils and greasy matters.

    Loading and unloading operations and movement of trucks shall be properly regulated to

    minimize the impact of noise on the personnel engaged in civil, mechanical and erection

    works.

    Solid Waste during Construction Phase

    A. Non-Hazardous Solid Waste

    i) Construction Debris: Construction debris is bulky and heavy and re-utilization

    and recycling is an important strategy for management of such waste. As concrete

    and masonry constitute the majority of waste generated, recycling of this waste by

    conversion to aggregate and as a sub-base for road construction can offer benefits

    of reduced landfill space.

    ii)Metal Scrap : Metal scrap from structural steel, piping, concrete reinforcement

    and sheet metal work shall be removed from the site by construction contractors.

    A significant portion of wood scrap can be reused on site. Recyclable wastes such

    as plastics, glass fiber insulation, roofing etc shall be sold to recyclers.

    B. Hazardous Waste

    Construction sites are sources of many toxic substances, such as paints, solvents, wood

    preservatives, pesticides, adhesives and sealants. Hazardous waste generated during

    construction phase shall be stored in sealed containers, labeled, and disposed of as

    required by the Hazardous Wastes Management and Handling Act Amendment Rules(MoEF, 2003).

    Some management practices to be developed are:

    Paintbrushes and equipment for water and oil based paints shall be cleaned within

    a contained area and shall not be allowed to contaminate site soils, watercourses

    or drainage systems.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    31/35

    Provide adequate hazardous waste storage facilities, hazardous waste collection

    containers are conveniently located and designate hazardous waste storage areas

    away from storm drains or watercourses.

    Potentially hazardous waste shall be segregated from non-hazardous construction

    site debris. All hazardous waste shall be clearly labeled.

    Air Quality Management

    The dust nuisance created by the excavation, leveling and transportation activities shall be

    properly controlled by

    Sprinkling water on roads, Providing dust arresting panels/sheets, Tree plantation to act as dust barriers,

    Regular removing of construction waste material, Proper storage of building material in sheds or under plastic covers, stockpiling

    along predominant wind direction, maintaining stockpile height close to boundary

    height (and use of tin sheets to provide wind barrier in case height exceeds

    boundary height),

    Use of cover sheets on trucks used for transportation, Avoiding of truck overloading and implementation of speed limits for vehicles. Emissions from vehicles and construction equipment shall be controlled by

    ensuring that vehicles used during construction undergo periodic pollution control

    checks and use cleaner fuels.

    The ambient air quality shall be monitored at the project site every quarter for

    RSPM, SPM, SO 2 and NO X.

    Noise Level Management

    Noise resulting from operation of construction machinery and vehicular movement,

    though localized, may constitute an additional environmental stress.

    Recommended mitigation measures for noise pollution are:

    Good maintenance of vehicles, construction equipment and roads. Restriction of noisy construction activities to day time only. Plantation of trees in the greenbelt area and around the plant boundary to attenuate

    the noise.

    Provision of earplugs and earmuffs to workers for work in unavoidable noisy

    operations.

    Acoustic housing for DG sets.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    32/35

    The Ambient Noise Levels shall be monitored quarterly. In case a source is found

    making significantly higher noise, immediate action shall be taken to bring down

    its noise to a tolerable limit

    Water Quality Management

    The mitigation measures recommended for water quality management are as follows: The open drains carrying construction waste-water shall be collected in cemented

    trenches for reutilization to a greater extent.

    Storm water drains shall be constructed for storm water collection into a reservoir,

    water from which shall be used in construction activities and green belt

    development.

    Soak pit for construction workers/canteen. The vehicle maintenance area shall be located in such a manner so as to prevent

    contamination of ground water by accidental spillage of oil. Oil and grease trap

    shall be provided at equipment maintenance area.

    Unauthorized dumping of waste oil shall be prohibited. Site of deposition of building material wastes shall be cordoned. Groundwater quality of the site area shall be regularly monitored preferably once

    in a quarter during the development period.

    Ecological Management

    In order to prepare the site for the construction work, there might be cleaning of shrubs

    present at the site. To compensate, proper landscaping and tree plantation activities shall

    be initiated during construction phase itself. More than 30% land has been earmarked for

    green belt development. Large size species of trees shall be planted at the time of

    preparation of site so that they would grow to considerable size by the time of

    commissioning of the proposed project. Construction workers shall be provided domestic

    fuel (kerosene oil) so as to prevent cutting of trees for firewood.

    Socio-economic

    Any construction activity shall benefit the local population in a number of ways. Theproject shall generate both direct and indirect employment opportunities. In addition,

    development of infrastructure in the area, and other secondary developments shall provide

    ample opportunity to the locals to up-lift their living standards.

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    33/35

    RECOMMENDATIONS

    Prior Consent-to-Establish (NOC) for the proposed project must have been obtained from

    WBPCB before commencement of construction, if any is missing the same shall be

    immediately taken up by the construction agency. All other statutory clearances should be

    obtained by project proponent from the competent authorities and a copy of the same

    shall be kept in a docket specially containing all documents / reports related to

    environmental aspect of this project.

    A separate Environmental Management Cell should immediately be established to

    implement the management plan. The cell shall have proper representation from

    Consultancy and construction agency and shall be headed by some official of RVNL.

    The cell shall regularly, at least once in a month, collect all information, analysis the

    same and in turn shall report to CPM for all matters related to environment. The cell

    shall ensure the suitability, adequacy and effectiveness of the Environment

    Management Programme. The management review process will ensure that the

    necessary information is collected to allow management to carry out its evaluation. This

    review should be documented and periodically audit to establish its usefulness.

    This should be strictly monitored that all the mitigation measures in the EIA document

    above are properly adhered and all reports / documents are properly recorded and

    forwarded to the competent authorities well within the stipulated period mentioned there

    in / required as per Government policies under Environmental acts / rules.

    The following important points shall be given special care while doing routine inspectionof the work,

    The project proponent shall comply with all the environmental protection measures and

    safeguards recommended. Further, the unit must undertake socio-economic development

    activities in the surrounding villages like community development programmes,

    educational programmes, drinking water supply and health care etc.

    Provision should be made for the supply of kerosene or cooking gas to the labourers

    during construction phase. All the labourers to be engaged for construction works should

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    34/35

  • 8/10/2019 Corrected Dankuni Eia and Empreport

    35/35