COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay...

24
Footer Text September 2016 COPANO BAY LBJ CAUSEWAY DEMOLITION Integrated ACM Abatement September 2016

Transcript of COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay...

Page 1: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

COPANO BAYLBJ CAUSEWAY DEMOLITIONIntegrated ACM Abatement

September 2016

Page 2: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Integrated ACM Abatement

Integrating ACM Abatement into Bridge Demolition

PS&E and Long-Duration Demolition

2

Page 3: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Project Background

SH35 - LBJ Causeway

Confluence of Copano Bay and Aransas

Bay

Fulton, Aransas County

Constructed in 1967

Length: 9,232 ft

Two 13-ft Lanes; 2-ft Shoulders

Old Clearance: 50 ft

Undersized for Current Traffic Flow

Traffic Cannot Pass if Accident or

Breakdown

Structurally Deficient

3

Page 4: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Project Background (Cont.)

Need for Project

– Improve Safety

– Improve Mobility

Demolition and Replacement

Length: 11,010 ft

Four 12-ft Lanes; Two 4-ft Inside Shoulders;

Two 10-ft Outside Shoulders (bicyclists &

pedestrians)

New Clearance: 75 ft

Allow Traffic to Pass if Accident or

Breakdown

Improve Hurricane Evacuation Route

4

Page 5: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Hazmat ISA and ACM/LCP Inspections

2009 - NEPA Hazmat ISA

Competed

– No Hazmat Sites within ROW

– Bridge Demolition Planned

Feb 2010 - ACM/LCP Inspection

Nov 2010 - Categorical Exclusion

2011 - PS&E Prepared

2011 - Project Let/Construction

of New Bridge

2014 - ACM/LCP Re-inspection

2014 - Change Order

May 2015 - Demo/ACM

Abatement

5

Page 6: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

ACM on Bridge

ACM: Bearing Pad, Railing Stanchion Gasket, & Sealant in Pier Core Hole

ACM = >1% asbestos; Regulated ACM = 260 LF pipe, 160 SF coatings, or 35

CF where length or area not previously measured

6

Page 7: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Federal Project Authorization Agreement (FPAA)

Federally Funded Projects may be Eligible for

Federal Reimbursement of Abatement

Request Federal Funds at Beginning of

Hazmat Projects

Submit FPAA Request to Avoid Potential

Funding Problem (New or Amended Projects)

TxDOT FIN Online Request for FPAA approval:

http://iapps/apps/f225/

Electronically Submit FHWA Request

FHWA Processes Request in 3 - 7 days

Daniel Dargevics

([email protected])

TxDOT Federal Team, Letting Management

7

Page 8: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

CE Commitments

Notification, Abatement and Disposal per Federal and State Regulations

Federal Regulations

– 40 CFR 61.145 (Renovation and Demolition of Structures – Asbestos

NESHAP)

– OSHA 29 CFR 1926.1101 (Asbestos Standard for Construction)

State Regulations

– 12 TOC 1954 (Texas Asbestos Health Protection Act)

– 25 TAC 295, Subchapter C (Texas Asbestos Health Protection Rules;

TAHPR)

8

Page 9: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

PS&E – General Notes

General Notes

9

Page 10: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

PS&E – General Notes

General Notes

ITEM 496

– Hazardous Materials on Bridge

– Notify TDSHS (Individual Notification for each Bridge)

– Demolition by Blasting Prohibited

– Disassemble, Deliver, and Neatly Stack Elements

• Contractor to Move Elements

– Secure Temporary Storage of ACM Elements

10

Page 11: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

PS&E – General Notes

General Notes (contd.)

ITEM 496 (contd.)

– ACM Removal and Disposal by TxDOT

– ACM Removal Concurrent with Disassembly

– ACM Removal Incremental and Batch

• Railing Stanchion Gaskets (496 SF)

• Bent Bearing Pads (17,742 SF)

• Pier Core Hole Sealant (12 SF)

– ACM Marine Recovery Added to Scope

• Favored Incremental Removal (Batch Not Implemented)

• Lower Daily Labor (Manpower), but Longer Schedule

11

Page 12: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

PS&E – Demolition Plan

ACM: Bearing Pad, Railing Stanchion Gasket, & Sealant in Pier Core Hole

12

Revised based on updated ACM inspection report, resulting in scope change.

Page 13: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

PS&E – EPIC Sheet

13

Page 14: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

TDSHS Notification

TDSHS – 10-day Notification per NESHAP

and/or TAHPR

– Required for Demolition of a Bridge

Regardless of ACM Presence

– Combined or Separate Demolition and

Abatement Notifications

– Phased Demolition/Abatement:

• 3 Months Expanded to 12 Months

• 5 Abatement Notice Amendments

• 3 Demolition Notice Amendments

14

Page 15: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Traffic Control

Traffic Control Area Managed by Bridge

Construction/Demolition Contractor

Traffic Control may be Managed by ENV Contractor,

District Contractor, or Demolition Contractor

Project Conditions will Dictate the Most Cost-effective

Approach

District may Prefer ENV Contractor to Manage Traffic

Control for Abatement-only Projects

Requires Careful Coordination and Scheduling

Complex Traffic Control Plans to be Sealed by an Engineer

Require Use of Engineering Contract

ENV may Require Assistance Evaluating Adequacy of Plan

Careful Management of Liability Issues for TxDOT and ENV

15

Page 16: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Remove ACM Railing Gaskets

Remove Guard Railings and Expose ACM Gaskets Beneath Stanchions

Remove ACM Gaskets from Concrete Rail Footing

16

Page 17: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Expose ACM Felt Bearing Pads

Remove Concrete Road Deck and Expose ACM Felt Bearing Pads

Marine Recovery of Felt Bearing Pad Pieces

17

Page 18: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Remove Residual ACM Felt Bearing Pad from Deck

Transport Deck to Abatement Area

Remove Residual ACM Felt Bearing Pad from Deck

18

Page 19: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Remove Felt Bearing Pads from Caps

Remove Concrete Pier Caps and Transport to Abatement Area

Remove Residual ACM Felt Bearing Pad from Caps

19

Page 20: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Remove ACM Sealant from Piers

Remove Concrete Piers and Transport to Abatement Area

Remove ACM Sealant from Core Holes in Piers

Manifesting/Offsite Disposal of ACM Waste (Tessman Road Landfill, San Antonio)

20

Page 21: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Reuse and Disposal of Abated Concrete Elements

Bury Concrete Elements to Counter Subsidence and Prevent Erosion

Build Breakwater with Concrete Elements

21

Page 22: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Contracting Options

Guidance for Handling Asbestos in Construction

Projects (Jan. 26, 2007)

Multiple Contracting Options:

1. ENV Remediation/Abatement Contract

2. District-wide Contract

3. Develop Abatement Specifications to be

included in PS&E for let Construction or

Maintenance project

4. Develop Abatement Specifications to be

included in PS&E for Prime Contractor

5. Purchase of Service Contract (<$15,000)

6. Emergency Contract

22

Page 23: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Contracting

ENV PO Contract

Tetra Tech NUS, Inc. (contractor)

1 Priority Environmental Services (subcontractor)

4 PO Releases – Demo 4X Longer and Added Marine Recovery of ACM

Abatement Cost: $1.56MM ($436K + $232K + $434K + $453K)

Managing Abatement Contractor

– Daily Reports

– On-Site TxDOT Superintendent

23

Page 24: COPANO BAY LBJ CAUSEWAY DEMOLITION · SH35 - LBJ Causeway Confluence of Copano Bay and Aransas Bay Fulton, Aransas County Constructed in 1967 Length: 9,232 ft Two 13-ft Lanes; 2-ft

Footer Text September 2016

Integration of ACM Abatement into Demolition

Incorporated into PS&E, and Demolition Process

No Impact to Expanded Demolition Schedule

– Planned for 3 months

– Expanded to 12 months

Conducted Wherever and Whenever Convenient

– Lay Down Area, Truck Bed, Construction Yard, or Disposal Area

Marine Recovery of ACM

Use Abated Concrete Elements as Landfill Material and Breakwater

24