Control Software Integration
German SchumacherT&S Software Lead
![Page 2: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/2.jpg)
2
Integration Context
The Observatory Control System (OCS) is the primary high level master control system that schedules, commands, coordinates and monitors the observatory, for conducting the survey.
LSE-72LSE-71LSE-73
LSE-70LSE-209
![Page 3: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/3.jpg)
3
Telescope & Site Integration
![Page 4: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/4.jpg)
4
Integration Process
• Periodic workshops and telecons– Timeline established
• The agenda and minutes can be found at:– https://confluence.lsstcorp.org/display/SYSENG/
CCS-DAQ-OCS-DM+Workshops
![Page 5: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/5.jpg)
5
Workshop I
• 2014 Nov 11 – 14: SLAC– Review state of ICDs between principal LSST
subsystems.– Plan for locations and calendar of the subsystems
integration process.– Commanding and Sequencing• Commanding protocol• Component Interface model
![Page 6: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/6.jpg)
6
Workshop II
• 2015 Feb 19 20: TUCSON– Software infrastructure– Commanding – Software components
• 2015 Apr 07: Telecon– LSE-71 OCS CCS ICD timing– SAL API
![Page 7: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/7.jpg)
7
Communications Protocol Interface
![Page 8: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/8.jpg)
8
Component Interface Base
![Page 9: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/9.jpg)
9
Component Interface Extension
![Page 10: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/10.jpg)
10
Workshop III
• 2015 May 06-08: SLAC– Component Interface model refined– EFD large files system– Common IT infrastructure• Linux CentOS
– Refine Software/Hardware handoff milestones
![Page 11: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/11.jpg)
11
Workshop IV
• 2015 July 8 – 10: NCSA– Communication integration between OCS-CCS-
DMCS software platforms, using the SAL package.• C/C++, Java, Python
– Configuration– Common infrastructure
![Page 12: Control Software Integration German Schumacher T&S Software Lead.](https://reader034.fdocuments.in/reader034/viewer/2022051416/56649e375503460f94b26cb8/html5/thumbnails/12.jpg)
12
Future Milestones• 2015 Oct
– ICDs status review• 2015 Dec
– ICDs updates– Simulators delivery
• 2016 Jan– OCS – CCS Communications tests
• 2016 June– EFD Camera telemetry population
• 2016 Aug– Middleware V3.5– Simulators with full capacity
• 2016 Nov– OCS – CCS – TCS – DMCS Start/End of night tests– EFD replication– Middleware V4