Aeroportos Brasil Viracopos S.A. – Project Status
![Page 2: Construction update viracopos](https://reader033.fdocuments.in/reader033/viewer/2022052505/5557693dd8b42a94728b4f9e/html5/thumbnails/2.jpg)
2
Construction of the structural pillars for the new passenger
terminal
![Page 3: Construction update viracopos](https://reader033.fdocuments.in/reader033/viewer/2022052505/5557693dd8b42a94728b4f9e/html5/thumbnails/3.jpg)
3
Aeroportos Brasil Viracopos – Project Status
![Page 4: Construction update viracopos](https://reader033.fdocuments.in/reader033/viewer/2022052505/5557693dd8b42a94728b4f9e/html5/thumbnails/4.jpg)
4
Aeroportos Brasil Viracopos – Project Status
![Page 5: Construction update viracopos](https://reader033.fdocuments.in/reader033/viewer/2022052505/5557693dd8b42a94728b4f9e/html5/thumbnails/5.jpg)
5
Construction of the blocks and
pillars
Aeroportos Brasil Viracopos – Implementation of the
infrastructure and mesostructure in the Pier-C region
Preparing structural reinforcements Preparation for block construction and stake
leveling
Detail of the scaffolding used for pillar
construction
![Page 6: Construction update viracopos](https://reader033.fdocuments.in/reader033/viewer/2022052505/5557693dd8b42a94728b4f9e/html5/thumbnails/6.jpg)
6
Aeroportos Brasil Viracopos – Implementation of the Pier C
Infrastructure
Bulldozed area in the region of the NTPS corridor
Pouring lean concrete into the base of block BL-1
in the NTPS corridor area
Semi-completed foundations to support
the corridor blocks Preparing blocks in the NTPS corridor area.
![Page 7: Construction update viracopos](https://reader033.fdocuments.in/reader033/viewer/2022052505/5557693dd8b42a94728b4f9e/html5/thumbnails/7.jpg)
7
Aeroportos Brasil Viracopos – Implementation of the Pier A
Infrastructure
Implementing the infrastructure for NTPS Pier A
Excavation of BL-4 to raze the stake heads and
prepare lean concrete for NTPS Pier A. Enclosure for pouring concrete into a block at Pier
A Block awaiting concrete at NTPS Pier A
![Page 8: Construction update viracopos](https://reader033.fdocuments.in/reader033/viewer/2022052505/5557693dd8b42a94728b4f9e/html5/thumbnails/8.jpg)
8
Aeroportos Brasil Viracopos S. A. - Concession
Concession: 30 years
Regulatory Agency ANAC
Share held by Triunfo: 23%
Operation Start Date: November 2012
Construction Start Date: August 2012
Capital Structure:
![Page 9: Construction update viracopos](https://reader033.fdocuments.in/reader033/viewer/2022052505/5557693dd8b42a94728b4f9e/html5/thumbnails/9.jpg)