CONSTRUCTION SPECIFICATIONS and CONTRACT DOCUMENTS …
Transcript of CONSTRUCTION SPECIFICATIONS and CONTRACT DOCUMENTS …
CONSTRUCTION SPECIFICATIONS
and
CONTRACT DOCUMENTS
for
FRONT ROYAL GOLF CLUB
STORMWATER MANAGEMENT PLAN
Warren County, Virginia
PREPARED FOR
Warren County 220 North Commerce Avenue Front Royal, Virginia 22630
(540) 636-4600
PREPARED BY Pennoni Associates Inc.
117 East Piccadilly Street, Suite 200 Winchester, Virginia 22601
(540) 667-2139
March 2017
DETAILED SPECIFICATIONS
for
FRONT ROYAL GOLF CLUB
STORMWATER MANAGEMENT PLAN
OWNER
Warren County 220 North Commerce Avenue Front Royal, Virginia 22630
(540) 636-4600
PREPARED BY
Pennoni Associates Inc. 117 E. Piccadilly Street, Suite 200
Winchester, Virginia (540) 667-2139
March 2017
Front Royal Golf Club Stormwater Management Plan
Warren County, Virginia
Table of Contents
Bidding Requirements, Contract Documents and General Conditions Request for Bids Information for Bidders Bid Proposal Bid Bond Bidder Questionnaire Equal Employment Opportunity Statement Drug Free Workplace Statement Construction Contractor Agreement Payment Bond Performance Bond Notice of Award Notice to Proceed Change Order General Conditions Detailed Specifications Division No. Division Title
01 General
01100 General 01200 Measurement and Payment 02 Site Work and Utilities 02220 Earthwork 03 Concrete 03300 Cast In Place Concrete
04-16 Not Used Drawing Index Page No. Title
1 Cover Sheet 2 Notes and Legends 3 Stormwater Management Plan 4 Stormwater Management Plan 5 Stormwater Management Plan 6 Bioretention Plan 7 Bioretention Planting Plan 8 Bioretention Details 9 Stormwater Manaagement Details 10 Open Space Designation Plan
RFB - 1
Request for Bids Sealed proposals for the construction of “Front Royal Golf Club – Stormwater Management Plan” will be received by the County of Warren, Office of the County Administrator, 220 N. Commerce Avenue, Suite 100, Front Royal, Virginia 22630 until 2:00 p.m. local time, Wednesday, March 29, 2017 at which time they will be opened and read aloud. Bids received after that time will be returned unopened. Plans and specifications are available for inspection at the Warren County Administrator’s office at 220 N. Commerce Avenue, Suite 100, Front Royal, VA 22630 and Pennoni Associates Inc., 117 E. Piccadilly Street, Suite 200, Winchester, Virginia 22601. Prospective bidders may obtain copies of the plans and specifications from the Winchester office of Pennoni Associates Inc. Each bid must be accompanied by a Bid Bond or Cashier’s Check of not less than five percent (5%) of the gross sum named in the bid. The Owner reserves the right to reject any and all bids and to waive any irregularities therein. No bidder may withdraw his bid within ninety (90) days after the actual date of the opening thereof, unless the bidder follows Procedure 1 as specified in the Code of Virginia, §2.2-4330. The principle features of the contract are as follows:
The project consists of grading for relocation of approximately 9 acres of gravel parking/laydown areas along with removal of sediment basins and construction of bioretention filters and dry swales on a site related to the Dominion Power project in Warren County, VA.
The contractor is reminded that all roadwork must be in accordance with the Virginia Department of Transportation specifications and utility work in accordance with the Town of Front Royal Specifications. A non-mandatory pre bid meeting will be conducted on Wednesday, March 15, 2017 at 10:00 a.m. at the Warren County Government Center, 220 N. Commerce Avenue, Suite 101, Front Royal, Virginia 22630. Bidders must be registered as Contractors in the Commonwealth of Virginia as provided by Chapter 7 of Title 54 of the Code of Virginia of 1950, as amended which requires evidence of a certificate of registration prior to submittal of a bid. Bids shall be addressed to Mr. Douglas P. Stanley , County Administrator, Warren County, 220 N. Commerce Avenue, Suite 100, Front Royal, Virginia 22630, and on the outside of the envelope plainly marked “Front Royal Golf Club – Stormwater Management Plan.” DATE: March 2, 2017 /s/ Douglas P. Stanley, County Administrator, County of Warren
Information for Bidders - 1
INFORMATION FOR BIDDERS
BIDS will be received by the County of Warren (herein called the “OWNER”) at the Office of the
County Administrator, 220 N. Commerce Avenue, Suite 100, Front Royal, Virginia 22630 until 2:00
p.m. local time, Wednesday, March 29, 2017 at which time they will be opened and read aloud. Bids
received after this time will be returned unopened. Each BID must be submitted in a sealed envelope, addressed to: Mr. Douglas P. Stanley, County Administrator County of Warren 220 N. Commerce Avenue, Suite 100 Front Royal, Virginia 22630
Each sealed envelope containing a BID must be plainly marked on the outside containing a bid for
“Front Royal Golf Club – Stormwater Management Plan” and the envelope shall bear on the
outside the name of the bidder, his address, and his Virginia contractor's license number. If
forwarded by mail, the sealed envelope containing the BID must be enclosed in another envelope
addressed to the OWNER.
All BIDS must be made on the required BID PROPOSAL form. All blank spaces for BID prices must
be filled in, in ink or typewritten, and the BID must be fully completed and executed when submitted.
Only one copy of the BID form and supporting documents is required.
The OWNER may waive any informalities or minor defects or reject any and all BIDS. Any BID may
be withdrawn prior to the scheduled time and date for the opening of BIDS or any authorized
postponement thereof. Any BID received after the time and date specified shall not be considered.
No BIDDER may withdraw a BID within 90 days after the actual date of opening thereof.* Should
there be reasons why the contract cannot be awarded within the 90 day period, the time may be
extended by mutual agreement between the OWNER and the BIDDER.
BIDDERS must satisfy themselves of the accuracy of the estimated quantities in the contract
documents by examination of the site and a review of the drawings and specifications including
ADDENDA. After BIDS have been submitted, the BIDDER shall not assert that there was a
misunderstanding concerning the quantities of WORK or of the nature of the WORK to be done.
A non-mandatory pre bid meeting will be conducted on Wednesday, March 15, 2017 at 10:00 a.m. at the Warren County Government Center, 220 N. Commerce Avenue, Suite 101, Front Royal, Virginia 22630.
The OWNER shall provide to BIDDERS prior to BIDDING, all information which is pertinent to, and
delineates and describes, the land owned and rights-of-way acquired or to be acquired by the
OWNER.
The CONTRACT DOCUMENTS contain the provisions required for the construction of the
PROJECT. Information obtained from any officer, agent, or employee of the OWNER or any other
person shall not affect the risks or obligations assumed by the CONTRACTOR or relieve him from
fulfilling any conditions of the contract. A performance BOND and a payment BOND, each in the amount of 100 percent of the CONTRACT PRICE, with a corporate surety approved by the OWNER, will be required for the faithful performance of the contact. *Unless the BIDDER follows Procedure 1 as specified in the Code of Virginia, §2.2-4330.
Information for Bidders - 2
Attorneys-in-fact who sign BID BONDS or Payment BONDS and Performance BONDS must file with each BOND a certified and effective dated copy of their power of attorney. Each bid must be accompanied by a BID BOND or Cashier’s Check payable to the OWNER of not less than five (5) percent of the total amount of the bid. As soon as the BID prices have been compared, the OWNER will return the BONDS except the three lowest BIDDERS. When the Agreement is executed the BONDS of the two remaining unsuccessful BIDDERS will be returned. The BID BOND of the successful BIDDER will be retained until the Payment BOND and Performance BOND have been executed and approved, after which it will be returned. The party to whom the contract is awarded will be required to execute the Agreement and obtain the performance BOND and payment BOND within ten (10) calendar days from the date when the NOTICE OF AWARD is delivered to the BIDDER. The NOTICE OF AWARD shall be accompanied by the necessary Agreement and BOND forms. In the case of failure of the BIDDER to execute the Agreement, the OWNER may at his option consider the BIDDER in default, in which case the BID BOND accompanying the proposal shall become the property of the OWNER. The OWNER, within ten (10) days of receipt of an acceptable performance BOND and payment BOND and Agreement signed by the party to who the Agreement was awarded, shall sign the Agreement and return to such party an executed duplicate of the Agreement. Should the OWNER not execute the Agreement within such period, the BIDDER may by WRITTEN NOTICE withdraw his signed Agreement. Such notice of withdrawal shall be effective upon receipt of the notice by the OWNER. The NOTICE TO PROCEED shall be issued within ten (10) days of the execution of the Agreement by the OWNER. Should there be reasons why the NOTICE TO PROCEED cannot be issued within such period, the time may be extended by mutual agreement between the OWNER and CONTRACTOR. IF the NOTICE TO PROCEED has not been issued within the ten (10) day period or within the period mutually agreed upon, the CONTRACTOR may by WRITTEN NOTICE terminate the Agreement without further liability on the part of either party. The OWNER may make such investigations as he deems necessary to determine the ability of the BIDDER to perform the WORK, and the BIDDER shall furnish the OWNER all such information and data for this purpose as the OWNER may require. The OWNER reserves the right to reject any BID if the evidence submitted by, or the investigation of, such BIDDER fails to satisfy the OWNER that such BIDDER is properly qualified to carry out the obligations of the Agreement and to complete the WORK contemplated therein. A conditional or qualified BID will not be accepted. Time is of the essence. Contract award will be made to the lowest responsive responsible BIDDER. All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the project shall apply to the contract throughout. Each BIDDER is responsible for inspecting the site and for reading and being thoroughly familiar with the CONTRACT DOCUMENTS. The failure or omission of any BIDDER to do any of the foregoing shall in no way relieve any BIDDER from any obligation in respect to his BID. The low BIDDER will provide the names and addresses of major material SUPPLIERS and SUBCONTRACTORS when requested to do so by the OWNER. The ENGINEER for the PROJECTS is: Pennoni Associates Inc. Ronald Mislowsky, P.E. 117 E. Piccadilly Street, Suite 200 Winchester, Virginia 22601 (540) 667-2139
BP - 1
BID
FRONT ROYAL GOLF CLUB
STORMWATER MANAGEMENT PLAN
Proposal of (hereinafter called
“BIDDER), organized and existing under the laws of the State of
Doing business as *.
To County of Warren (hereinafter call “OWNER”). In compliance with your Advertisement for Bids, BIDDER hereby proposes to perform all work for the construction of “Front Royal Golf Club – Stormwater Mangement Plan” in strict accordance with the CONTRACT DOCUMENTS, within the time set forth therein, and at the prices stated below. By submission of this BID, each BIDDER certifies, and in the case of a joint BID each party thereto certifies as to his own organization, that this BID has been arrived at independently, without consultation, communication, or agreement as to any matter relating to this BID with any other BIDDER or with any competitor. BIDDER hereby agrees to commence WORK under this contract on or before a date to be specified in the NOTICE TO PROCEED and to fully complete the PROJECT within 90 days following the Notice to Proceed unless extended. BIDDER further agrees to pay as liquidated damages, but not as a penalty, the sum of $500.00 for each consecutive calendar day thereafter as provided in Section 15 of the General Conditions. BIDDER acknowledges receipt of the following ADDENDUM:
* Insert “a corporation”, “partnership”, or “an individual” as applicable.
BP - 2
BID PROPOSAL
Front Royal Golf Club – Stormwater Management Plan
Item No.
Total
1. Furnish & Install all labor, materials and equipment to construct the Front Royal Golf Club -
Stormwater Management Plan.
( ) Lump Sum
$
Words
TOTAL BID ITEM (Item 1)
$
The following is an outline of the project Schedule of Values for bid evaluation by the ENGINEER and OWNER.
Item Description Lump Sum Total Cost
PART A GENERAL 1. Mobilization LS
2. Performance & Payment Bonds LS
3. Construction Survey LS
4. Permits LS
Subtotal Part A:
PART B SITE IMPROVEMENTS 1. Grading & Earthwork LS
2. Relocation of gravel LS
3. Topsoil and seeding LS
LS
Subtotal Part B :
PART C STORMWATER 1. Construct bioretention filter BRF-A LS
2. Construct dry swale LS
3. Construct diversion dike LS
4. Construct bioretention filter BRF-B LS
5. Remove sediment Basin - north LS
6. Remove sediment Basin - south LS
Subtotal Part C:
BP - 3
Item Description Lump Sum Total Cost
PART D EROSION AND SEDIMENT CONTROL 1.
Install construction entrances, silt fences, safety fence, inlet and outlet protection, seeding and mulching in accordance with the E&S Narrative, Phase 1 & 2 ESC Plans and the SWPPP. LS
Subtotal Part D:
TOTAL PARTS A, B, C, & D:
Respectfully Submitted:
Signature Address
Title Date
Virginia Contractor's License Number ATTEST (Seal - If BID is by a corporation)
Bid Bond - 1
BID BOND
KNOW ALL MEN BY THESE PRESENTS, that we, the undersigned,
________________________________________________________________ as Principal, and
________________________________________________________ as Surety, are hereby
held and firmly bound unto _________________________________________ as OWNER
in the penal sum of ______________________________________________ for the payment of
which, well and truly to be made, we hereby jointly and severally bind ourselves, successors
and assigns.
Signed, this ___________ day of ___________________________ , 20 ___
The Condition of the above obligation is such that whereas the Principal has submitted to
a certain BID, attached hereto and hereby
made a part hereof to enter into a contract in writing, for the ______________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
NOW THEREFORE,
(a) If said BID shall be rejected, or
(b) If said BID shall be accepted and the Principal shall execute and deliver a contract in the Form of Contract attached hereto (properly completed in accordance with said BID) and shall furnish a BOND for his faithful performance of said contract, and for the payment of all persons performing labor or furnishing materials in connection therewith, and shall in all other respects perform the agreement created by the acceptance of said BID,
then this obligation shall be void, otherwise the same shall remain in force and effect; it being expressly understood and agreed that the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal amount of this obligation as herein stated.
Bid Bond - 2
The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and its BOND shall be in no way impaired or affected by any extension of the time within which the OWNER may accept such BID; and said Surety does hereby waive notice of any such extension. IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals, and such of them as are corporations have caused their corporate seals to be hereto affixed and these presents to be signed by their proper officers, the day and year first set forth above.
_____________________________________ Principal BY: __________________________________ _____________________________________ Surety BY: __________________________________
IMPORTANT – Surety companies executing BONDS must appear on the Treasury Department’s most current list (Circular 570 as amended) and be authorized to transact business in the state where the project is located.
Bidder Questionnaire - 1
BIDDER QUESTIONNAIRE
(Must be filled out in its entirety and submitted with Bid Proposal)
Submitted By ___________________________________________________________________
(Name of Bidder)
( ) an Individual, ( ) a Partnership, ( ) a Corporation.
Principal Office Address:____________________________________________
The bidder guarantees the truth and accuracy of all statements and all answers to questions hereinafter
made.
1. How many years has your organization been in business and as a contractor under
your present business name? years
2. How many years’ experience in utility and earthwork construction has your
organization had as a general contractor? _____ As a sub-contractor? ____
3. List below the requested information concerning projects your organization has
completed in the last five years for the type of work required in this project.
Project Title Contract Amount Req. Completion Time Actual Completion Time Name/Address/Phone# of Owner
4. Identify proposed subcontractors and their activities in this project.
Equal Employment Opportunity
EQUAL EMPLOYMENT OPPORTUNITY (Must be submitted with Bid Proposal)
During the performance of this Contract the Contractor agrees as follows:
a. The Contractor will not discriminate against any employee or applicant because of race, color, religion, sex, or national origin. The Contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment, without regard to race, color, religion, sex, or national origin. Such action shall include but not be limited to the following: employment, upgrading, demotion, or transfer, recruitment or recruitment advertising, layoff or termination, rates of pay or other forms of compensation, and selection for training, including apprenticeship. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of the nondiscrimination clause.
b. The contractor will, in all solicitations or advertisements for employees placed by
or on behalf of the Contractor, state that all qualified applicant will receive consideration for employment without regard to race, color, religion, sex or national origin.
c. The Contractor will send to each labor union or representative of workers with
which he has a collective bargaining agreement or other Contract understanding, a notice, to be provided, advising the labor union or worker’s representative of the Contractor’s commitments under the Equal Employment Opportunity Section of this Contract, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
d. In the event of the Contractor’s noncompliance with the nondiscrimination
clauses of this Contract or with any of such rules, regulations or orders, this Contract may be canceled, terminated, or suspended in whole or in part and the Contractor may be declared ineligible for further OWNER contracts.
e. The Contractor will include the provisions of this section in every subcontract or
purchase order of Ten Thousand Dollars ($10,000.00) or more unless exempted by rules, regulations, or orders of the OWNER so that such provisions will be binding upon each Subcontractor or vendor.
Corporate Name Attest: By:
Title: Title:
Date:
Drug Free Workplace
DRUG FREE WORKPLACE
During the performance of this Contract the Contractor agrees as follows:
(a) Provide a drug-free workplace for the Contractor’s employees,
(b) Post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the Contractor’s workplace and specifying the actions that will be taken against employees for violations of such prohibition,
(c) State in all solicitations or advertisements for employees placed by or on behalf
of the Contractor that the contractor maintains a drug-free workplace; and
(d) Includes the provisions of the foregoing clauses in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each Subcontractor or vendor.
For the purposes of this section, “drug-free workplace” means a site for the performance of work done in connection with this specific contract awarded to a Contractor in accordance with this chapter, the employees of whom are prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession or use of any controlled substance or marijuana during the performance of the contract.
Corporate Name Attest: By:
Title: Title:
Date:
Page 1 of 6
THE COUNTY of WARREN
CONSTRUCTION CONTRACTOR AGREEMENT
THIS AGREEMENT (hereinafter the "County/Contractor Agreement", the “Owner/Contractor
Agreement” or "Agreement") made as of the _____ day of _________________, 2017, by and between
the County of Warren, Virginia, a political subdivision of the Commonwealth of Virginia, acting by and
through its Board of Supervisors (hereinafter the "Owner" or "County”), Virginia, and the “Contractor”:
Name of Contractor
Virginia Class _____ Contractor
Contractor Number:
For development/construction of the following Project:
Furnish and provide all necessary services, supervision, labor, materials, tools and
equipment and other items and personnel necessary to complete the Stormwater
Management Plan at Front Royal Golf Club in Warren County, Virginia, as indicated,
described and defined by the attached specifications prepared by Pennoni Associates, Inc.
For and in consideration of the mutual covenants contained herein, the County and the Contractor
agree as set forth below.
Article 1
The Contract Documents
1.1 The Contract Documents include the Invitation for Bids, Information for Bidders, County of
Warren/Contractor Agreement, the Conditions of the Contract (General and Supplementary), the
Drawings, the Specifications, Bids, Bonds, Notice of Award, Waiver and Release of Liens, and
all Addenda issued prior to and all Modifications issued after execution of the Agreement. These
form the Contract, and are as fully a part of the Contract as if attached to the Agreement. The
Contract Documents are further enumerated and defined in Article 1 of the General Conditions.
Article 2
Statement of the Work
2.1 The Contractor shall furnish all supervision, labor, materials and equipment needed for the
construction of the Project, as required by the Contract Documents.
Page 2 of 6
Article 3
Contract Time and Liquidated Damages
3.1 Time is of the essence. The Work to be performed under this Contract shall be commenced after
issuance of the Notice to Proceed and the Work shall be completed within 90 days as stated in
Owner’s Notice to Proceed.
3.2 See also Article 8 "Time" of the General Conditions.
3.3 In case the Contractor shall fail to finally complete the work hereunder in accordance with the
Specifications and to the satisfaction of the Owner within the time stated in the Owner/Contractor
Agreement or any written extension thereof by the Owner, the Contractor shall and will pay to the
Owner the sum of $500, for each and every calendar day that the Work exceeds the time set forth
by the Contract Documents, including all time extensions under Article 8.
Due to the parties' inability to estimate the Owner's actual damages with precision, the sum is
hereby agreed upon, fixed and determined by the parties hereto as the liquidated damages that the
Owner will suffer by reason of said delay, default and inability to use said improvements at the
time specified for completion, and not as a penalty. Owner shall and may deduct and retain the
amount of such liquidated damages out of any monies which may be due or become due from it
to the Contractor.
Article 4
Contract Price and Payments to the Contractor
4.1 In consideration of the Performance of the Contract, the Owner agrees to pay the Contractor as
compensation for his services the firm, fixed price of: _____________________________.
4.2 See also Article 9 "Payments and Completion" of the General Conditions.
Article 5
Owner's Authorized Representative
5.1 Owner's Authorized Representative
For the purposes of this Contract, the term "Owner's Authorized Representative" as used in the
Conditions of the Contract shall be:
Jeffrey L. Hayes, Clerk of the Works
County of Warren, Virginia
220 N. Commerce Avenue, Suite 100
Front Royal, Virginia 22630
(540) 636-4600
FAX: (540) 636-6066
Page 3 of 6
Article 6
Notice
6.1 Notice: The term "Notice" as used herein shall mean and include written notice. Any legal notice
by any party shall be deemed to have been duly given if either delivered personally or enclosed in
a registered, postpaid envelope addressed to:
The Owner:
County of Warren, Virginia
220 N. Commerce Avenue, Suite 100
Front Royal, Virginia 22630
(540) 635-4600
FAX (540) 636-6066
The Owner's Authorized Representative:
Jeffrey L. Hayes, Clerk of the Works
County of Warren, Virginia
220 N. Commerce Avenue, Suite 100
Front Royal, Virginia 22630
(540) 636-4600
FAX: (540) 636-6066
The Contractor:
_________________________________
Article 7
Miscellaneous
7.1 Non-Discrimination: During the performance of this agreement, Contractor agrees that
Contractor will not discriminate against any employee or applicant for employment because of
race, religion, color, sex, or natural origin except where religion, sex, or natural origin is a bona
fide occupational qualification reasonably necessary for the normal operation of the Contractor.
Contractor agrees to post in conspicuous places available to employees and applicants for
employment notices setting forth the provisions of this non-discrimination clause. Contractor in
all solicitations or advertisements for employees placed by or on behalf of Contractor will state
that Contractor is an equal opportunity employer. Contractor will include the provisions of this
paragraph in every sub-contract or purchase order of over $10,000.00 so that the provisions will
Page 4 of 6
be binding upon each sub-contractor or vendor. The County of Warren does not discriminate
against faith-based organizations.
7.2 Services Rendered: Contractor shall perform all services to be rendered pursuant to this
Contract at the location specified above. Contractor agrees to maintain all facilities and
equipment used by Contractor under this Contract in clean, sanitary, and safe condition and free
from defects of every kind.
7. 3 Licenses and Permits: Contractor agrees that it has procured all licenses, permits, or other like
permission required by law to conduct or engage in the activity provided for in this Contract; that
it will procure all additional licenses, permits, or like permission required by law during the term
of this Contract; and that it will keep such licenses, permits, and permissions in full force and
effect during the term of this Contract
7.4 Independent Contractor: Contractor understands and agrees that the relationship of service
provider to the County arising out of this Contract shall be that of independent contractor. It is
understood that the Contractor, or its staff and employees, are not employees of the County and
are, therefore, not entitled to any benefits provided employees of the County. Contractor shall be
responsible for reporting and accounting for all State, Federal, Social Security, and local taxes
where applicable.
7.5. Insurance: Contractor shall procure and maintain general liability insurance for protection from
claims arising out of performance of services caused by a negligent error, omission or act for
which he is legally liable. Contractor shall deliver to Owner, upon execution of this Agreement,
certificates of such insurance. Such insurance shall provide for coverage in the following amounts
and be effective through the date of the end of the Project unless as further specified in general or
supplemental conditions prepared by the Engineer and made a part of this Agreement. Such
insurance shall name the County as an additional insured and shall contain a provision that
coverages afforded under the policies shall not be terminated, cancelled or otherwise allowed to
expire until at least thirty (30) days prior written notice has been given to the Owner:
Commercial General Liability having limits no less than the following:
Bodily Injury and Property Damage $1,000,000 each occurrence
$2,000,000 aggregate per project
Business Auto liability having limits no less than the following:
Bodily Injury and Property Damage $1,000,000 combined single limit
Umbrella Liability Insurance covering the excess over the limits specified for all
commercial general liability and business auto liability insurance required
hereunder with minimum limits of $5,000,000 aggregate per policy year.
Workers Compensation as required by Virginia law
Page 5 of 6
7.6 Standard of Care: Contractor shall perform the services herein described expeditiously and
diligently and in accordance with the standard of care and skill ordinarily exercised under similar
conditions by reputable members of its profession or trade practicing in the same or similar
locality within the Commonwealth of Virginia existing as of the date such services are provided
and in accordance with all applicable laws, codes, and regulations in effect as of the date such
services are provided.
7.7 Compliance with Immigration Laws: The Service Provider agrees and represents that it does
not now, nor will it during the performance of this contract, knowingly employ an unauthorized
alien as defined in the federal Immigration Reform and Control Act of 1986.
7.8 Service Provider Authorized to Transact Business in Virginia: During the performance of
this contract, the Service Provider agrees to be authorized to transact business in the
Commonwealth of Virginia as a domestic or foreign business entity if so required by Title 13.1 or
Title 50 of the Code of Virginia (1950), as amended, or as otherwise required by law.
7.9 Drug-free Workplace:
A. During the performance of this contract, the Service Provider agrees to (i) provide a drug-free
workplace for the Service Provider's employees; (ii) post in conspicuous places, available to
employees and applicants for employment, a statement notifying employees that the unlawful
manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or
marijuana is prohibited in the Service Provider's workplace and specifying the actions that will be
taken against employees for violations of such prohibition; (iii) state in all solicitations or
advertisements for employees placed by or on behalf of the Service Provider that the Service
Provider maintains a drug-free workplace; and (iv) include the provisions of the foregoing clauses
in every subcontract or purchase order of over ten thousand dollars ($10,000), so that the
provisions will be binding upon each subcontractor or vendor.
B. For the purposes of this section, "drug-free workplace" means a site for the performance of
work done in connection with a specific contract awarded to a Service Provider in accordance
with this chapter, the employees of whom are prohibited from engaging in the unlawful
manufacture, sale, distribution, dispensation, possession or use of any controlled substance or
marijuana during the performance of the contract.
This Agreement executed the day and year first written above.
THE COUNTY OF WARREN Name of Contractor
Acting by and through its
Board of Supervisors
By: ______________________________ By: ________________________________________
Douglas P. Stanley
County Administrator
Page 6 of 6
STATE OF VIRGINIA:
COUNTY OF WARREN, TO-WIT:
I, _________________________________, a Notary Public in and for the State of Virginia, do
hereby certify that Douglas P. Stanley, whose name is signed to the foregoing Agreement, has this day
personally appeared and acknowledged the same before me in my State and County aforesaid.
Given under my hand this _______ day of ________________, 2017.
________________________________
NOTARY PUBLIC
Commission expiration date:___________
Notary registration number:___________
STATE OF VIRGINIA:
COUNTY/CITY OF _______________, TO-WIT:
I, _________________________________, a Notary Public in and for the State of Virginia, do
hereby certify that _________________________, whose name is signed to the foregoing Agreement, has
this day personally appeared and acknowledged the same before me in my State and County aforesaid.
Given under my hand this _______ day of _____________________, 2017.
________________________________
NOTARY PUBLIC
Commission expiration date:___________
Notary registration number:___________
Approved as to Form:
__________________________
Dan N. Whitten
County Attorney
END OF OWNER/CONTRACTOR AGREEMENT
SCC - 1
LABOR AND MATERIAL PAYMENT BOND
KNOW ALL MEN BY THESE PRESENTS: That we, the undersigned, _______________
______________________________________________________________, as Principal, and
___________________________________________________________________________, as Surety,
acknowledge ourselves held and firmly bound unto the County of Warren, Virginia as Obligee in the
amount of _________________________________ for the payment of which, well and truly to be made,
we hereby jointly and severally bind ourselves, our heirs, executors, administrators, successors and
assigns.
WHEREAS, the said _______________________________ did, on the _____ day of ______________,
2017, enter into a contract with the County of Warren, Virginia, to complete the Stormwater
Management Plan at Front Royal Golf Club in Warren County, Virginia, which said contract is by
reference made a part hereof, as fully and is hereinafter referred to as the Contract.
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Principal shall
promptly make payment to all claimants as hereinafter defined, for all labor and material used or
reasonably required for use in the performance of the Contract, then this obligation shall be void;
otherwise it shall remain in full force and effect, subject, however to the following conditions:
1. A claimant is defined as one having a direct contract with the Principal or with a
subcontractor of the Principal for labor, material, or both, used or reasonably required for
use in the performance of the Contract, labor and material being construed to also include
that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of
equipment directly applicable to the Contract.
2. The above-named Principal and Surety hereby jointly and severally agree with the
County that every claimant as herein defined, who has not been paid in full before the
expiration of a period ninety (90) days after the date on which the last of such claimant's
work or labor was done or performed, or materials were furnished by such claimant, may
SCC - 2
sue on this bond for such sum or sums as may be justly due claimant, and have execution
thereon. The County shall not be liable for the payment of any costs or expenses of any
such suit.
3. No suit or action shall be commenced hereunder by any claimant:
A. Unless claimant, other than one having a direct contract with the Principal, shall
have given written notice of the following: The Principal, the County, and the
Surety above named, within ninety (90) days after such claimant did or
performed the last of the work or labor, or furnished the last of the materials for
which said claim is made, stating with substantial accuracy the amount claimed
and the name of the party to whom the materials were furnished or for whom the
work or labor was done or performed.
Such notice shall be served by mailing the same by registered or certified mail,
postage prepaid, in an envelope addressed to the Principal, County and Surety, at
any place where an office is regularly maintained for the transaction of business,
or served in any manner in which legal process may be served in the state in
which the aforesaid project is located, save that such service need not be made by
a public officer.
B. After the expiration of one (1) year following the date on which Principal ceased
work on said Contract, it being understood, however, that if any limitation
embodied in this Bond is prohibited by any law controlling the construction
hereof such limitation shall be deemed to be amended so as to be equal to the
minimum period of limitation permitted by such law.
C. Other than in a state court of competent jurisdiction in and for the county or other
political subdivision of the state in which the Project, or any part thereof, is
situated, or in the United States District Court for the district in which the
Project, or any part thereof, is situated, and not elsewhere.
SCC - 3
4. The amount of this bond shall be reduced by and to the extent of any payment or
payments made in good faith hereunder, inclusive of the payment by Surety of
mechanics' liens, which may be filed of record against said improvement, whether or not
claim for the amount of such lien be presented under and against this bond.
SIGNED AND SEALED this ______ day of _________________, 2017.
__________________________________
Contractor
BY ____________________________________
ATTEST:
__________________________________________
__________________________________
Surety
BY _____________________________________
ATTORNEY-IN-FACT
_________________________________
Resident Virginia Agent of Surety
(if original agent is non-resident)
Submit with Power of Attorney
APPROVED AS TO FORM
________________________
Dan N. Whitten
County Attorney
SCC- 1
PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS: That we, the undersigned ________________
________________________________________________________________, as Principal, and
_____________________________________________________________________, as Surety,
acknowledge ourselves held and firmly bound unto the County of Warren, Virginia as Obligee, in
the amount of ___________________________________for the payment of which, well and truly to
be made, we hereby jointly and severally bind ourselves, our heirs, executors, administrators,
successors and assigns.
WHEREAS, the said _____________________________did, on the _____ day of ______________,
2017, enter into a contract with the County of Warren, Virginia, to complete the Stormwater
Management Plan at Front Royal Golf Club in Warren County, Virginia which said contract is
by reference made a part hereof, is hereinafter referred to as the Contract.
NOW, THEREFORE, the condition of this obligation is such that if the Principal shall in all respects
promptly and faithfully comply with and fulfill all the terms and conditions of said contract, then this
obligation shall be void; otherwise it shall remain in full force and effect.
The Surety hereby waives notice of any change, alteration or addition to the terms of the Contract or
extension of time made by the Owner.
Whenever Principal shall be, and declared by Obligee to be in default under the Contract, the Surety
may promptly remedy the default, or shall promptly
1. Complete the Contract in accordance with its terms and conditions, or
2. Obtain a bid or bids for completing the Contract in accordance with its terms and
conditions, and upon determination by Surety of the lowest responsible bidder, or,
if the Obligee elects, upon determination by the Obligee and Surety jointly of the
lowest responsible bidder, arrange for a contract between such bidder and Obligee,
SCC- 2
and make available as work progresses (even though there should be a default or a
succession of defaults under the contract or contracts of completion arranged
under this paragraph) sufficient funds to pay the cost of completion less the
balance of the contract price; but not exceeding, including other costs and
damages for which the Surety may be liable hereunder, the amount set forth in the
first paragraph hereof. The term "balance of the contract price", as used in this
paragraph, shall mean the total amount payable by the Obligee to Principal under
the Contract and any amendments thereto, less the amount properly paid by
Obligee to Principal.
It is hereby expressly further understood and agreed that this Bond is also given and made
against defective material and workmanship in the said work covered by the said Contract,
provided, however, that no suit, action or proceeding, by reason of any defect whatever, shall
be brought upon this Bond after one (1) year following the date of final acceptance of the
completed project by the Owner.
No right of action shall accrue on this bond to or for the use of any person or corporation other than
the Obligee named herein or the heirs, executors, administrators or successors of Obligee.
SCC- 3
SIGNED AND SEALED this _____ day of __________________, 2017.
PRINCIPAL
BY_______________________________
ATTEST:
_____________________________
________________________________
SURETY
BY_______________________________
ATTORNEY-IN-FACT
COUNTERSIGNED:
________________________________
Resident Virginia Agent of Surety
(if original Agent is non-resident)
Submit with Power of Attorney
APPROVED AS TO FORM
________________________
Dan N. Whitten
Interim County Attorney
Notice of Award - 1
NOTICE OF AWARD
To:
PROJECT Description: Front Royal Golf Club – Stormwater Management Plan
The OWNER has considered the BID submitted by you for the above described WORK dated , 2017. You are hereby notified that your BID has been accepted for items in the amount of $ . You are required to execute the Agreement and furnish the required CONTRACTOR'S Certificates of Insurance within ten (10) calendar days from the date of this Notice to you. If you fail to execute said Agreement and to furnish said BONDS within ten (10) days from the date of this Notice, said OWNER will be entitled to consider all your rights arising out of the OWNER'S acceptance of your BID as abandoned and as a forfeiture of your BID BOND. The OWNER will be entitled to such other rights as may be granted by law. You are required to return an acknowledged copy of this NOTICE OF AWARD to the OWNER. Dated this day of , 2017. By Douglas P. Stanley Title County Administrator, The County of Warren
ACCEPTANCE OF NOTICE
Receipt of the above NOTICE OF AWARD is hereby acknowledged
By
This the Day of , 2017
By ______________________________________
Title_____________________________________
Notice to Proceed - 1
NOTICE TO PROCEED To:
Date:
, 2017
Project: Front Royal Golf Club,
Stormwater Management Plan
You are hereby notified to commence WORK in accordance with the Agreement
dated , 2017, on or before , 2017 and you are to complete the WORK
prior to 2017 . The date of completion of all WORK is therefore , 2017.
The County of Warren
Owner
By
Title
ACCEPTANCE OF NOTICE
Receipt of the above NOTICE TO PROCEED
is hereby acknowledged by:
this
the
day
of , 2017.
By
Title
CHANGE ORDER
Order No.: Date: Agreement Date: NAME OF PROJECT:
OWNER:
CONTRACTOR:
The following changes are hereby made to the CONTRACT DOCUMENTS:
Justification: Change to CONTRACT PRICE:
Original CONTRACT PRICE $ Current CONTRACT PRICE adjusted by previous CHANGE ORDER $
The CONTRACT PRICE due to this CHANGE ORDER will be increased by: $ The CONTRACT PRICE including this CHANGE ORDER will be $ Change to CONTRACT TIME: The CONTRACT TIME will be (increased) (decreased) by Calendar days. The date for completion of all work will be (Date) Approvals Required: To be effective this Order must be approved by the Federal agency if it changes the scope of objective of the PROJECT, or as may otherwise be required by the SUPPLEMENTAL GENERAL CONDITIONS. Requested By: ________________________________________________________________________________ Recommended By: ____________________________________________________________________________ Ordered By: __________________________________________________________________________________
Accepted By: _________________________________________________________________________________
GENERAL CONDITIONS
GENERAL CONDITIONS (i)
THE COUNTY OF WARREN, VIRGINIA
GENERAL CONDITIONS
For Construction of
Front Royal Golf Club Stormwater Management Plan County of Warren
March 1, 2017
TABLE OF ARTICLES
Page
ARTICLE 1: CONTRACT DOCUMENTS ................................................................................................................................... 4
1.1 DEFINITIONS ................................................................................................................................................ 4
1.2 EXECUTION, CORRELATION AND INTENT ............................................................................................ 5
1.3 OWNERSHIP AND USE OF DOCUMENTS ................................................................................................ 6
ARTICLE 2: OWNER'S AUTHORIZED REPRESENTATIVE ................................................................................................... 6
2.1 DEFINITIONS ................................................................................................................................................ 6
2.2 SERVICES OF THE OWNER'S AUTHORIZED REPRESENTATIVE ........................................................ 6
ARTICLE 3: OWNER .................................................................................................................................................................... 7
3.1 DEFINITIONS ............................................................................................................................................... 7
3.2 INFORMATION, SERVICES AND RIGHTS OF THE OWNER .................................................................. 7
3.3 OWNER'S RIGHT TO STOP OR TO SUSPEND WORK ............................................................................. 7
3.4 OWNER'S RIGHT TO CARRY OUT THE WORK ....................................................................................... 8
3.5 EXAMINATION OF RECORDS ..................................................................................................................... 8
ARTICLE 4: CONTRACTOR ........................................................................................................................................................ 9
4.1 DEFINITION .................................................................................................................................................... 9
4.2 REVIEW OF CONTRACT DOCUMENTS ...................................................................................................... 9
4.3 SUPERVISION AND CONSTRUCTION PROCEDURES ............................................................................. 9
4.4 INSPECTION OF CONSTRUCTION ........................................................................................................... 10
4.5 CONTRACTOR'S REPRESENTATIONS ..................................................................................................... 10
4.6 LABOR AND MATERIALS.......................................................................................................................... 11
4.7 WARRANTY ................................................................................................................................................. 12
4.8 TAXES ........................................................................................................................................................... 13
4.9 PERMITS, FEES AND NOTICES ................................................................................................................. 13
4.10 SUPERINTENDENT ..................................................................................................................................... 13
4.11 PROJECT SCHEDULES................................................................................................................................ 13
4.12 RESPONSIBILITY FOR COMPLETION ..................................................................................................... 13
4.13 DOCUMENTS, SAMPLES AND OTHER SUBMITTALS AT THE SITE .................................................. 14
4.14 SHOP DRAWINGS, PRODUCT DATA, SAMPLES AND OTHER SUBMITTALS .................................. 14
4.15 CLEANING UP .............................................................................................................................................. 14
4.16 ROYALTIES AND PATENTS ...................................................................................................................... 14
4.17 INDEMNIFICATION .................................................................................................................................... 15
4.18 PERSONS AUTHORIZED TO SIGN DOCUMENTS .................................................................................. 15
ARTICLE 5: SUBCONTRACTORS
5.1 DEFINITIONS ............................................................................................................................................... 16
GENERAL CONDITIONS
GENERAL CONDITIONS (ii)
5.2 AWARD OF SUBCONTRACTS AND OTHER CONTRACTS FOR PORTIONS OF THE WORK .......... 16
5.3 SUBCONTRACTUAL RELATIONS ............................................................................................................ 16
5.4 QUALIFICATION SUBMITTALS................................................................................................................ 17
ARTICLE 6: WORK BY OWNER OR BY SEPARATE CONTRACTORS .............................................................................. 17
6.1 OWNER'S RIGHT TO PERFORM WORK AND TO AWARD SEPARATE CONTRACTS ...................... 17
6.2 MUTUAL RESPONSIBILITY....................................................................................................................... 17
6.3 OWNER'S RIGHT TO PERFORM DISPUTED WORK ............................................................................... 18
6.4 COORDINATION OF THE WORK .............................................................................................................. 18
ARTICLE 7: MISCELLANEOUS PROVISIONS ....................................................................................................................... 18
7.1 GOVERNING LAW ....................................................................................................................................... 18
7.2 SUCCESSORS AND ASSIGNS .................................................................................................................... 18
7.3 CLAIMS FOR DAMAGES ............................................................................................................................ 18
7.4 DISPUTES ...................................................................................................................................................... 19
7.5 TESTS ............................................................................................................................................................ 19
7.6 UNENFORCEABILITY OF ANY PROVISION ........................................................................................... 20
7.7 AVAILABILITY OF LANDS ........................................................................................................................ 20
ARTICLE 8: TIME ....................................................................................................................................................................... 20
8.1 DEFINITIONS ............................................................................................................................................... 20
8.2 PROGRESS AND COMPLETION ................................................................................................................ 21
8.3 DELAYS AND EXTENSIONS OF TIME ..................................................................................................... 21
ARTICLE 9: PAYMENTS AND COMPLETION ........................................................................................................................ 21
9.1 CONTRACT PRICE....................................................................................................................................... 21
9.2 SCHEDULE OF VALUES ............................................................................................................................. 21
9.3 APPLICATIONS FOR PAYMENT ............................................................................................................... 22
9.4 CERTIFICATES FOR PAYMENT ................................................................................................................ 22
9.5 PROGRESS PAYMENTS .............................................................................................................................. 22
9.6 PAYMENTS WITHHELD ............................................................................................................................. 23
9.7 SUBSTANTIAL COMPLETION ................................................................................................................... 23
9.8 FINAL COMPLETION AND FINAL PAYMENT ........................................................................................ 24
9.9 PARTIAL OCCUPANCY OR USE ............................................................................................................... 25
ARTICLE 10: PROTECTION OF PERSONS AND PROPERTY ................................................................................................ 26
10.1 SAFETY PRECAUTIONS AND PROGRAMS ............................................................................................. 26
10.2 SAFETY OF PERSONS AND PROPERTY .................................................................................................. 26
10.3 EMERGENCIES ............................................................................................................................................ 27
ARTICLE 11: BONDS AND INSURANCE ................................................................................................................................. 27
11.1 BONDS ........................................................................................................................................................... 28
11.2 CONTRACTOR'S LIABILITY INSURANCE ............................................................................................. 28
11.3 OWNER’S LIABILITY INSURANCE .......................................................................................................... 29
11.4 PROJECT MANAGEMENT PROTECTIVE LIABILITY INSURANCE ..................................................... 29
11.5 PROPERTY INSURANCE ............................................................................................................................ 29
ARTICLE 12: CHANGES IN THE WORK ................................................................................................................................. 31
12.1 CHANGES IN THE WORK .......................................................................................................................... 31
12.2 FIELD ORDER .............................................................................................................................................. 31
12.3 REQUEST FOR PROPOSAL ........................................................................................................................ 31
12.4 PROPOSED CHANGE ORDER .................................................................................................................... 32
12.5 CHANGE ORDER ........................................................................................................................................ 33
12.6 UNILATERAL CHANGE ORDER ............................................................................................................... 34
12.7 DECREASES AND WORK NOT PERFORMED ......................................................................................... 34
12.8 CHANGES IN LINE AND GRADE .............................................................................................................. 35
12.9 DIFFERING SITE CONDITIONS ................................................................................................................. 35
GENERAL CONDITIONS
GENERAL CONDITIONS (iii)
12.10 CLAIMS FOR ADDITIONAL COST AND/OR TIME ................................................................................. 35
12.11 ATTORNEYS' FEES AND OTHER EXPENSES ......................................................................................... 36
ARTICLE 13: UNCOVERING AND CORRECTION OF WORK .............................................................................................. 36
13.1 UNCOVERING OF WORK ........................................................................................................................... 36
13.2 CORRECTION OF WORK ............................................................................................................................ 36
13.3 ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK ......................................................... 37
ARTICLE 14: TERMINATION OF THE CONTRACT ............................................................................................................... 37
14.1 TERMINATION FOR THE CONVENIENCE OF THE OWNER ................................................................ 37
14.2 ALLOWABLE CONVENIENCE TERMINATION COSTS ......................................................................... 37
14.3 DEFAULT TERMINATION .......................................................................................................................... 38
14.4 GENERAL TERMINATION PROVISIONS ................................................................................................. 39
GENERAL CONDITIONS
GENERAL CONDITIONS (4)
THE COUNTY OF WARREN, VIRGINIA
GENERAL CONDITIONS
ARTICLE 1: CONTRACT DOCUMENTS
1.1 DEFINITIONS
1.1.1 The Contract Documents The Contract Documents consist of the Advertisement or Invitation for Bids, Information for Bidders, Insurance
Checklist, Bids, Bonds, the Notice of Award and the County/Contractor Agreement, including Conditions of the
Contract (General and Supplementary Conditions), the Drawings, the Specifications, all Addenda issued prior to
and all Modifications issued after execution of the Agreement. A Modification is either a written Change Order
issued pursuant to the provisions of Article 12.1, or a written order for a minor change in the Work issued by the
Owner pursuant to Article 12.5. The Owner has the right to include the Offeror's Bid or Proposal in the Contract
Documents.
1.1.2 The Contract The Contract is the sum of all the Contract Documents. This Contract represents the entire and integrated
agreement between the Owner and the Contractor and supersedes all prior negotiations, representations, or
agreements, either written or oral. The Contract may be changed only by a Modification as defined in Article
1.1.1.
1.1.3 The Work The Work comprises the completed construction required by the Contract Documents and includes all labor,
material, equipment, supplies and other facilities or things necessary to produce such construction, and all
materials, equipment and supplies incorporated or to be incorporated in such construction.
1.1.4 The Project The Project is the total construction of which the Work performed under the Contract Documents may be the
whole or a part.
1.1.5 Furnish, Install, Provide The terms "Furnish" or "Install" or "Provide," unless specifically limited in context, mean: furnishing and
incorporating a specified item, product or material in the Work, including all labor, materials, and equipment
necessary to perform the work required, ready to use.
1.1.7 Firm, Fixed Price or Lump Sum The terms "Firm, Fixed Price" or "Lump Sum" mean that the Contract Work shall be performed for the price
stated in the Contract without any adjustment based on the Contractor's actual costs unless such adjustment is
made by a properly executed Contract Change or Modification.
1.1.8 Schedule of Values The term "Schedule of Values" means the unit prices for portions of the Work submitted by the Contractor and
approved by the Owner's Authorized Representative for use in preparing Applications for Payment and pricing
Contract Changes. The Schedule of Values shall not alter the Firm, Fixed Price or Lump Sum value of the
Contract.
1.1.9 Miscellaneous Words or Terms Whenever they refer to the Work or its performance, "Directed," "Required," "Permitted," "Ordered,"
"Designated," "Prescribed," and words of like import shall imply the direction, requirements, permission, order,
designation or prescription of the Owner and/or the Owner's Authorized Representative, and "Approved,"
"Acceptable," "Satisfactory," "in the judgment of," and words of like import shall mean approved by or acceptable
to or satisfactory to or in the judgment of the Owner and/or the Owner's Authorized Representative. "Approved"
GENERAL CONDITIONS
GENERAL CONDITIONS (5)
means approved in writing, including subsequent written confirmation of prior oral approval and "Approval"
means approval in writing, including all aforesaid.
1.2 EXECUTION, CORRELATION AND INTENT
1.2.1 The Contract Documents shall be signed in not less than duplicate by the Owner and the Contractor and each set
shall be deemed an original, but all sets shall constitute one and the same instrument.
1.2.2 By executing the Contract, the Contractor represents that he has familiarized himself with, and assumes full
responsibility for having familiarized himself with, the nature and extent of the Contract Documents, Work,
locality, and with all local conditions and federal, state and local laws, ordinances, rules and regulations that may
in any manner affect performance of the Work, and represents that he has correlated his study and observations
with the requirements of the Contract Documents. The Contractor also represents that he has studied all surveys
and investigation reports of subsurface and latent physical conditions referred to in the Contract Documents and
made such additional surveys and investigations as he deems necessary for the performance of the Work at the
Contract Price in accordance with the requirements of the Contract Documents and that he has correlated the
results of all such data with the requirements of the Contract Documents.
1.2.3 The intent of the Contract Documents is to include all items necessary for the proper execution and completion of
the Work. The Contract Documents are complimentary, and what is required by any one shall be as binding as if
required by all. Should any work or material be required which is not denoted in the drawings and specifications
either directly or indirectly, but which is nevertheless necessary for the proper carrying out of the intent thereof, it
is understood and agreed that the same is implied and required and that the Contractor shall perform such work
and furnish such materials as fully as if they were completely delineated and prescribed.
Words and abbreviations which have well-known technical or trade meanings are used in the Contract Documents
in accordance with such recognized meanings unless otherwise specifically defined herein. The Table of Articles,
titles, headings, and running headlines contained herein and in said documents are solely to facilitate reference to
various provisions of the Contract Documents and in no way affect, limit or cast light upon the interpretation of
the provisions to which they refer.
1.2.4 The organization of the specifications into divisions, sections and articles, and the arrangement of drawings are
for clarity only, and shall not control the Contractor in dividing the Work among subcontractors or in establishing
the extent of Work to be performed by any trade. The Contractor may subcontract the Work in such divisions as
he sees fit and he is ultimately responsible for furnishing all work shown on the drawings and/or in the
specifications. The Owner shall furnish to Contractor up to five (5) copies of the Contract Documents, and
additional copies will be furnished, upon request, at the cost of reproduction.
1.2.5 Anything shown on the drawings and not mentioned in the specifications or mentioned in the specifications and
not shown on the drawings shall have the same effect as if shown or mentioned respectively in both. Technical
specifications take priority over general specifications and detail drawings take precedence over general drawings.
Any work shown on one drawing shall be construed to be shown in all drawings and the contractor will
coordinate the work and the drawings. If any portion of the Contract Documents shall be in conflict with any
other portion, the various documents comprising the Contract Documents shall govern in the following order of
precedence: The County/Contractor Agreement; Changes; Addenda; the Supplementary Conditions; the General
Conditions; the Specifications; the drawings; the bonds; the advertisement for bids or invitation or request for
proposal; information for bidders; bids; the notice of award; as between schedules and information given on
drawings and the scaled measurements, the figures shall govern; as between large-scale drawings and small-scale
drawings, the larger scale shall govern. Any such conflict or inconsistency between or in the drawings shall be
submitted to the Owner's Authorized Representative whose decision thereon shall be final and conclusive.
1.2.6 The Contractor acknowledges and agrees that this Contract is not intended to create, nor shall any provision be
interpreted as creating, any contractual relationship between the Owner and any third parties including all
Subcontractors.
1.2.7 The Provisions of this Contract cannot be changed, varied or waived in any respect except by a written
Modification or Change Order. The Contractor is hereby given notice that no person has authority to orally
GENERAL CONDITIONS
GENERAL CONDITIONS (6)
waive, or to release the Contractor from any of the Contractor's duties or obligations under or arising out of this
Contract. Any waiver, approval or consent granted by Changes to the Contractor shall be limited to those matters
specifically and expressly stated thereby to be waived, approved or consented to and shall not relieve the
Contractor of the obligation to obtain any future waiver, approval or consent.
1.3 OWNERSHIP AND USE OF DOCUMENTS
1.3.1 All drawings, specifications, and copies thereof furnished by or to the Owner under this Contract are and shall
remain the property of the Owner. They are to be used only with respect to this Project and are not to be used in
whole or in part for any other purpose.
END OF ARTICLE 1
ARTICLE 2: OWNER'S AUTHORIZED REPRESENTATIVE
2.1 DEFINITIONS
2.1.1 The term hereinafter "Owner's Authorized Representative" as used or set forth in the Contract Documents, shall
mean the entity so identified in the County/Contractor Agreement or its duly authorized representatives.
2.1.2 The Owner's Authorized Representative is identified in the County/Contractor Agreement and is referred to
throughout the Contract Documents as if singular in number and masculine in gender.
2.2 SERVICES OF THE OWNER'S AUTHORIZED REPRESENTATIVE
2.2.1 The Owner's Authorized Representative will serve during construction and until the end of the warranty period.
The Owner's Authorized Representative will advise and consult with the Owner.
2.2.2 The Owner's Authorized Representative will inform the Owner and the Contractor whenever in his reasonable
opinion any of the Work is proceeding contrary to the requirements of the Contract Documents and will be
unacceptable. Failure of the Contractor to take corrective action to make the Work conform to the Contract
Documents will subject the Contractor to any and all remedies available to the Owner, including, without
limitation, termination pursuant to Article 14 hereof. Such notification by the Owner's Authorized Representative
will not be a cause for the Contractor to claim either delay of the Work or any increase in the Contract Price.
2.2.3 The Owner's Authorized Representative will not be responsible for and will not have control or charge of
construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in
connection with the Work.
2.2.4 The Owner's Authorized Representative shall at all times have access to the Work wherever it is in preparation or
progress, to include off-site facilities of subcontractors and suppliers at any tier. The Contractor shall provide safe
facilities for such access so the Owner's Authorized Representative may perform his functions under the Contract
Documents.
2.2.5 All communications, correspondence, submittals and documents exchanged between the Owner's Authorized
Representative and the Contractor in connection with the Project shall be through or in the manner prescribed by
the Owner and consistent with Article 6 of the County/Contractor Agreement.
2.2.6 The Owner's Authorized Representative shall make recommendations to the Owner in matters relating to aesthetic
effect; the decision of the Owner on such aesthetic matters will be final.
END OF ARTICLE 2
GENERAL CONDITIONS
GENERAL CONDITIONS (7)
ARTICLE 3: OWNER
3.1 DEFINITIONS
3.1.1 "Owner" means the County of Warren, Virginia, unless the County/Contractor Agreement provides otherwise.
The Owner shall hereinafter be referred to as the "County," or as the "Owner."
3.1.2 The Owner's Authorized Representative means the entity or individual identified as such in the County/Contractor
Agreement.
3.1.3 "Contractor" means the person or persons, firm or company whose bid or proposal has been accepted by the
Owner and includes the Contractor's representatives, successors and assigns permitted by the Owner.
3.2 INFORMATION, SERVICES AND RIGHTS OF THE OWNER
3.2.1 The Owner and/or the Owner's Authorized Representative will provide administration of the Contract as
hereinafter described.
3.2.2 The Owner will review and process all Progress Payments, including the Final Payment.
3.2.3 The Owner shall have the authority to reject the work when, in its opinion, the Work does not conform to the
Contract Documents.
3.2.4 Whenever in the Owner's reasonable opinion it is necessary or advisable for the implementation of the intent of
the Contract Documents, the Owner will have authority to require special inspection or testing of the Work in
accordance with the provisions of the Contract Documents, whether or not such Work be then fabricated, installed
or completed.
3.2.5 The Owner shall have the authority and discretion to call, schedule and conduct job meetings to be attended by the
Contractor, representatives of his Subcontractors, and the Owner's Authorized Representative to discuss such
matters as procedures, progress, problems and scheduling.
3.2.6 The Owner or the Owner's Authorized Representative will establish procedures to be followed for processing all
Shop Drawings, samples, catalogs and other project submittals, reports and other documentation such as test
reports and maintenance manuals.
3.2.7 The Owner will review all requests for changes and shall implement the processing of Change Orders, including
applications for extension of the Contract Time.
3.2.8 The Owner or the Owner's Authorized Representative shall at all times have access to the Work wherever it is in
preparation or progress. The Contractor shall provide safe facilities for such access.
3.2.9 The Owner or the Owner's Authorized Representative shall not be responsible for or have control or charge of the
construction means, methods, techniques, sequences, or procedures, or for the safety precautions and programs in
connection with the Work, and will not be responsible for the Contractor's failure to carry out the Work in
accordance with the Contract Documents.
3.2.10 The Owner or the Owner's Authorized Representative shall not be responsible or liable to the Contractor for the
acts, errors or omissions of the Contractor, any separate Subcontractor, any separate Contractor or any
Contractor's or Subcontractor's agents or employees, or any other persons performing any of the Work.
3.2.11 The foregoing rights are in addition to other rights of the Owner enumerated herein and those provided by law.
3.3 OWNER'S RIGHT TO STOP OR TO SUSPEND WORK
3.3.1 If the Contractor fails to correct defective Work as required by Article 13.2 "CORRECTION OF WORK," or fails
to carry out the Work or supply labor and materials in accordance with the Contract Documents, the Owner by
GENERAL CONDITIONS
GENERAL CONDITIONS (8)
written order may order the Contractor to stop the Work, or any portion thereof, without monetary compensation
to the Contractor until the cause for such order has been eliminated.
3.3.2 The Owner may order the Contractor in writing to suspend, delay, or interrupt all or any part of the Work for such
period of time as he may determine to be appropriate for the convenience of the Owner.
3.3.3 If the performance of all or any part of the Work is, for an unreasonable period of time, suspended, delayed, or
interrupted by the Owner or the Owner's Authorized Representative in the administration of this Contract, or by
failure of any one of them to act within the time specified in this Contract (or if no time is specified, within a
reasonable time), an adjustment shall be made for an increase in the actual time required for performance of the
Work by the Contractor, due solely to such unreasonable suspension, delay, or interruption and the Contract shall
be modified in writing accordingly. However, no claim for an extension of time shall be made under this Article
3.3.3 for any suspension, delay, or interruption pursuant to Article 3.4.1, or for which claim is provided or
excluded under any other provision of this Contract. ................................................................................
No claim under this Article 3.3.3 shall be allowed for any claim for an extension of time required for
performance, unless within twenty (20) days after the act or failure to act involved, the Contractor submits to the
Owner's Authorized Representative a written statement setting forth, as then practicable, the extent of such
claimed time extension and unless the claim for an extension of time is submitted with supporting data within
thirty (30) days after the termination of such suspension, delay, or interruption.
3.3.4 In the event of a suspension of work or delay or interruption of work, the Contractor will and will cause his
Subcontractors to protect carefully his, and their, materials and work against damage from the weather and
maintain completed and uncompleted portions of the work as required by the Contract Documents. If, in the
opinion of the Owner's Authorized Representative, any work or material shall have been damaged by reason of
failure on the part of the Contractor or any of his Subcontractors to so protect same, such work and materials shall
be removed and replaced at the expense of the Contractor.
3.3.5 No claim by the Contractor under Article 3.3.3 shall be allowed if asserted after Final Payment under this
Contract.
3.4 OWNER'S RIGHT TO CARRY OUT THE WORK
3.4.1 If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails
within seven (7) days after receipt of written notice to commence and continue correction of such default or
neglect with diligence and promptness, the Owner or the Owner's Authorized Representative may, after seven (7)
days following receipt by the Contractor of an additional written notice and without prejudice to any other remedy
he may have, make good such deficiencies and may further elect to complete all Work thereafter through such
means as the Owner may select, including the use of a new Contractor. In such case an appropriate Change Order
shall be issued deducting from the payments then or thereafter due the Contractor the cost of correcting such
deficiencies, including compensation for services of the Owner's Authorized Representative and any other
additional services made necessary by such default, neglect or failure. If the payments then or thereafter due the
Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner.
3.4.3 The Owner will not be liable or accountable to the Contractor for the method by which the work or any portion
thereof, performed by the Owner or by separate contractors pursuant to Article 3.4 is accomplished or for the
price paid therefor. Notwithstanding the Owner's right to carry out a portion of the Work, maintenance and
protection of the Work remains the Contractor's responsibility.
3.5 EXAMINATION OF RECORDS
3.5.1 The Contractor agrees that the Owner, or any duly authorized representative, shall, until the expiration of three (3)
years after final payment hereunder, have access to and the right to examine and copy any directly pertinent
books, documents, papers and records of the Contractor involving transactions related to this Contract.
3.5.2 The Contractor further agrees to include in any subcontract for more than $10,000 entered into as a result of this
Contract, a provision to the effect that the subcontractor agrees that the Owner or any duly authorized
GENERAL CONDITIONS
GENERAL CONDITIONS (9)
representative shall, until the expiration of three (3) years after final payment under the Contract, have access to
and the right to examine and copy any directly pertinent books, documents, papers and records of such contractor
involved in transactions related to such subcontract, or this Contract. The term subcontract as used herein shall
exclude subcontracts or purchase orders for public utility services at rates established for uniform applicability to
the general public.
3.5.3 The period of access provided in Subparagraphs 3.5.1 and 3.5.2 above for records, books, documents and papers
which may relate to any arbitration, litigation, alternative dispute resolution ("ADR") or the settlement of claims
arising out of the performance of this contract or any subcontract shall continue until any appeals, arbitration,
litigation, ADR or claims shall have been finally concluded.
END OF ARTICLE 3
ARTICLE 4: CONTRACTOR
4.1 DEFINITION
4.1.1 The Contractor is the person or organization identified as such in the County/Contractor Agreement. The term
Contractor means the Contractor or his authorized representative, who shall have authority to bind the Contractor
in all matters pertinent to this Contract.
4.1.2 The Contractor is not an agent for the Owner but is an independent contractor engaged in the business of
providing the services and performing the Work described in the Contract Documents.
4.2 REVIEW OF CONTRACT DOCUMENTS
4.2.1 Before submitting his bid or proposal to the Owner, and continuously after execution of the Contract, the
Contractor shall carefully study and compare the Contract Documents and shall at once report to the Owner any
error, inconsistency or omission he may discover, including any requirement that may be contrary to any law,
ordinance, rule, regulation or order of any public authority bearing on the performance of the Work. By
submitting his bid or proposal for the Contract and the Work under it, the Contractor agrees that the Contract
Documents appear accurate, consistent and complete. The Contractor shall perform no portion of the Work at any
time without Contract Documents and, where required, approved shop drawings, product data, samples, mock ups
or other submittals for such portion of the Work.
4.2.2 The Contractor and his Subcontractors shall keep at the site of the Work at least one copy of the full size
drawings, specifications, approved shop drawings, product data, samples, mock ups, and other approved
submittals, and shall at all times give the Owner or the Owner's Authorized Representative, inspectors, as well as
other representatives of the Owner access thereto. Further, said drawings shall be approved sets issued to the
Contractor by the Owner.
4.3 SUPERVISION AND CONSTRUCTION PROCEDURES
4.3.1 The Contractor shall supervise and direct the Work, using his best skill and attention. He shall be solely
responsible for and have control over all construction means, uses, sequences, procedures, safety precautions and
programs, and for coordinating all portions of the Work under the Contract.
4.3.2 The Contractor shall be responsible to the Owner for the acts and omissions of his employees, Subcontractors,
Suppliers, their agents and employees, and other persons performing any of the work and for their compliance
with each and every requirement of the Contract Documents, in the same manner as if they were fully employed
by the Contractor.
4.3.3 The Contractor shall not be relieved from his obligations to perform the Work in accordance with the Contract
Documents either by acts, failures to act or duties of the Owner or the Owner's Authorized Representative in their
GENERAL CONDITIONS
GENERAL CONDITIONS (10)
administration of the Contract, or by inspections, tests, or approvals (or the lack thereof) required or performed
under Article 4.4 "INSPECTION" or Article 7.5 "TESTS" by persons other than the Contractor.
4.3.4 The Contractor shall employ no plant, equipment, materials, methods or persons to which the Owner or Owner's
Authorized Representative reasonably objects.
4.3.5 The Contractor shall not remove any portion of the Work or stored materials from the site of the Work.
4.4 INSPECTION OF CONSTRUCTION
4.4.1 The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the
Work called for by this Contract conforms to Contract requirements. The Contractor shall maintain complete
inspection records and make them available to the Owner and Owner's Authorized Representative. All work is
subject to inspection and testing at all places and at all reasonable times before acceptance to ensure strict
compliance with the terms of the Contract.
4.5 CONTRACTOR'S REPRESENTATIONS
4.5.1 By entering into this Contract with the Owner, the Contractor represents and warrants the following, together with
all other representations and warranties in the Contract Documents:
.1 That he is experienced in and competent to perform the type of work required and to furnish the
plant, materials, supplies or equipment to be so performed or furnished by him;
.2 That he is financially solvent, able to pay his debts as they mature, and possessed of sufficient
working capital to initiate and complete the Work and Changes required under the Contract;
.3 That he is familiar with all laws, ordinances, permits, regulations and resolutions that may in any
way affect the Work or those employed therein, including but not limited to any special laws or
regulations related to the Work or any part thereof;
.4 That such temporary and permanent work required by the Contract Documents
that is to be done by him will be satisfactorily constructed and fit for use for its
intended purpose and that such construction will not injure any person, or damage
any property;
.5 That he will fully comply with all requirements of the Contract Documents;
.6 That he will perform the Work in a skillful manner consistent with good
workmanship, sound business practice, and in the most expeditious and
economical manner consistent with the best interests of the Owner;
.7 That he will furnish efficient business administration and experienced superintendence and an
adequate supply of workmen, equipment, tools, and materials at all times;
.8 That he has carefully reviewed the Work required and that the Work can be planned and executed
in a normal and orderly sequence of Work and reasonably scheduled so as to insure completion
of the work in accordance with the Contract Documents, allowing for normal and reasonably
foreseeable weather, labor and other delays, interruptions and disruptions of the Work at the site
designated;
.9 That he will complete the Work within the Contract Time and all portions thereof
within any required Contract milestones; and
.10 That his Contract Price is based upon the labor, materials, systems and equipment
required by the Contract Documents, without exception.
GENERAL CONDITIONS
GENERAL CONDITIONS (11)
4.6 LABOR AND MATERIALS
4.6.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for all labor,
materials, equipment, supplies, tools, construction equipment and machinery, heat, utilities, transportation, and
other facilities and services necessary or proper for or incidental to the execution and completion of the Work
required by and in accordance with the Contract Documents and any applicable code or statute, whether
specifically required by the Contract Documents, or whether their provision may reasonably be inferred as
necessary to produce the intended results, whether temporary or permanent and whether or not incorporated or to
be incorporated in the Work. Final Payment will not be made until the Work is so completed.
4.6.2 Whenever materials or equipment are specified or described in the Drawings or Specifications by using the name
of a proprietary item or the name of a particular manufacturer, fabricator, supplier, or distributor, the naming of
the item is intended to establish the type, function, and quality required. Unless the name is followed by words
indicating that no substitution is permitted, materials or equipment of other manufacturers, fabricators, suppliers
or distributors may be accepted by the Owner's Authorized Representative if sufficient information is submitted
by the Contractor to allow the Owner's Authorized Representative to determine that the material or equipment
proposed is equivalent to that name.
4.6.3 Requests for review of substitute items of material and equipment will not be accepted by the Owner's Authorized
Representative from anyone other than the Contractor. If the Contractor wishes to furnish or use a substitute item
of material or equipment, the Contractor shall make written application to the Owner's Authorized Representative
for acceptance thereof, certifying that the proposed substitute will perform adequately the functions called for by
the general design, be similar and of equal substance to that specified, and be suited to the same use and capable
of performing the same function as that specified. The application shall state whether or not acceptance of the
substitute for use in the work will require a change in the drawings or specifications to adapt the design to the
substitute and whether or not incorporation or use of the substitute in connection with the work is subject to
payment of an license fee or royalty. All variations of the proposed substitute from that specified shall be
identified in the application and available maintenance, repair, and replacement service shall be indicated.
4.6.4 The application shall also contain an itemized estimate of all costs that will result directly or indirectly from
acceptance of such substitute, including costs of redesign and claims of other contractors affected by the resulting
change. All of the foregoing shall be considered by the Owner's Authorized Representative in evaluating the
proposed substitute. The Owner's Authorized Representative may require the Contractor to furnish at the
Contractor's expense additional data about the proposed substitute. The Owner's Authorized Representative shall
make a recommendation to the Owner concerning the acceptability. The Owner shall be the sole judge of
acceptability, and no substitute shall be ordered or installed without the Owner's prior written acceptance. The
Owner may require the Contractor to furnish at the Contractor's expense a special performance guarantee or other
surety with respect to any substitute.
4.6.5 Manufactured articles, material and equipment shall be applied, installed, connected, erected, used, cleaned, and
conditioned as directed by the manufacturer unless herein specified to the contrary.
4.6.6 Whenever it is specified that any material, process, or equipment shall conform to the standard specifications of
any of the societies or associations which publish such standards, the meaning of the specifications shall be that
the latest supplement, edition or revision of the standard specified shall apply, unless specifically noted otherwise.
4.6.7 All equipment, apparatus and/or devices of any kind to be incorporated into the Work that are shown or indicated
on the drawings or called for in the specifications or required for the completion of the Work shall be entirely
satisfactory to the Owner's Authorized Representative as regards operations, capacity, and/or performance. No
approval, either written or verbal, of any drawings, descriptive data, or samples of such equipment, apparatus,
and/or device shall relieve the Contractor of his responsibility to turn over the same in good working order for its
intended purpose at the completion of the Work in complete accordance with the Contract Documents. Any
equipment, apparatus and/or device not fulfilling these requirements shall be removed and replaced by proper and
acceptable equipment, etc., or put in good working order satisfactory to the Owner's Authorized Representative
without additional cost to the Owner.
GENERAL CONDITIONS
GENERAL CONDITIONS (12)
4.6.8 The Contractor shall at all times enforce strict discipline and good order among his employees and shall not
employ on the Work any unfit person or anyone not skilled in the task assigned to him. The Owner may, by
written notice, require the Contractor to remove from the Work any employee the Owner deems incompetent,
careless or otherwise objectionable.
4.7 WARRANTY
4.7.1 The Contractor guarantees and warrants to the Owner all work as follows:
.1 That all materials and equipment furnished under this Contract will be new and
the best of its respective kind unless otherwise specified;
.2 That all Work will be first-class quality and free of omissions and faulty, poor
quality, imperfect or defective materials or workmanship;
.3 That where no standard is specified for such workmanship or materials, they shall
be the best of their respective kinds;
.4 That all applicable Work shall be entirely watertight and leakproof in accordance
with all applicable industry customs and practices, and shall be free of shrinkage
and settlement;
.5 That the Work, including but not limited to, mechanical and electrical machines,
devices and equipment shall be fit and fully usable for its intended and specified
purpose and shall operate satisfactorily with ordinary care;
.6 That consistent with requirements of the Contract Documents, the Work shall be
installed and oriented in such a manner as to facilitate unrestricted access for the
operation and maintenance of fixed equipment; and
.7 That the Work will be free of abnormal or unusual deterioration that occurs
because of poor quality materials, workmanship or unsuitable storage.
4.7.2 All work not conforming to guarantees and warranties specified in the Contract Documents, including
substitutions not properly approved and authorized, may be considered defective. If required by the Owner's
Authorized Representative, the Contractor shall furnish satisfactory evidence as to the kind and quality of
materials and equipment. This warranty is not limited by the provisions of Article 13 "UNCOVERING AND
CORRECTION OF WORK."
4.7.3 The warranties set forth in this Article 4.7 and elsewhere in the Contract Documents shall survive Final
Completion of the Work under Article 9.8 "FINAL COMPLETION AND FINAL PAYMENT."
4.7.4 If, within one (1) year after the Date of Final Completion of the Work or designated portion thereof or within one
(1) year after acceptance by the Owner of designated equipment or within such longer period of time as may be
prescribed by law or by the terms of the applicable special warranty required by the Contract Documents, any of
the Work is found to be defective, not in accordance with the Contract Documents, or not in accordance with the
guarantees and warranties specified in the Contract Documents, the Contractor shall correct it within five (5)
working days, or such other period as mutually agreed, after receipt of written notice from the Owner or Owner's
Authorized Representative to do so.
4.7.5 If at any time deficiencies in the Work are discovered that are found to have resulted from latent defects, gross
mistakes, fraud or misrepresentation by the Contractor, any Subcontractor or Supplier, the Contractor will be
liable for replacement or correction of such Work and/or any damage that the Owner has incurred, or will incur,
related thereto, regardless of the time limit of any guarantees or warranty.
4.7.6 Any materials or other portions of the Work, installed, furnished, or stored on site that are not of the character or
quality required by the specifications, or are otherwise not acceptable to the Owner's Authorized Representative
GENERAL CONDITIONS
GENERAL CONDITIONS (13)
shall be immediately removed and replaced by the Contractor to the satisfaction of the Owner's Authorized
Representative when notified to do so by the Owner's Authorized Representative.
4.7.7 If the Contractor fails to correct defective or nonconforming Work as required by Article 4.7.4 or Article 4.7.5 or,
if the Contractor fails to remove defective or nonconforming Work from the site, as required by Article 4.7.6, the
Owner may elect to either correct such Work in accordance with Article 3.4 "OWNER'S RIGHT TO CARRY
OUT THE WORK" or remove and store materials and equipment at the expense of the Contractor.
4.7.8 The Contractor shall bear the cost of making good all work of the Owner, separate contractors or others, destroyed
or damaged by such correction or removal required under this Article, Article 13 "UNCOVERING AND
CORRECTION OF WORK" or elsewhere in the Contract Documents.
4.8 TAXES
4.8.1 The Contractor shall pay all applicable Federal, State, and local taxes and duties for the Work or portions thereof
provided by the Contractor that are legally enacted at the time the Contract is awarded, whether or not yet
effective. Increases in the rates of such taxes and duties during performance of the Contract shall be the
responsibility of the Contractor.
4.9 PERMITS, FEES AND NOTICES
4.9.1 The Contractor shall secure and pay for all permits, fees, licenses and inspections necessary for the proper
execution and completion of the Work that are legally required at the time the proposals are received.
4.9.2 The Contractor shall give all notices and comply with all laws, ordinances, rules, regulations and lawful orders of
any public authority bearing on the performance of the Work.
4.10 SUPERINTENDENT
4.10.1 The Contractor shall employ a competent Superintendent and necessary assistants who shall be in attendance at
the Project site during the progress of the Work. The Superintendent shall be an authorized representative of the
Contractor and all communications given to the Superintendent shall be as binding as if given to the Contractor.
4.10.2 The Superintendent shall be in attendance at the Project site not less than eight (8) hours per day, five (5) days per
week, unless the job is closed down due to a general strike or conditions beyond the control of the Contractor or
until termination of the Contract in accordance with the Contract Documents. It is understood that such
Superintendent shall be approved in writing by the Owner and shall be the one who will continue in that capacity
for the duration of the Project, unless the Superintendent ceases to be on the Contractor's payroll or his withdrawal
is required or approved by the Owner. The Superintendent shall not be employed on any other project for or by
the Contractor or any other entity during the course of the Work.
4.11 PROJECT SCHEDULES
4.11.1 The Contractor shall prepare and submit to the Owner's Authorized Representative for the Owner's review, such
Schedules for the Work as are required by the Supplementary Conditions or other Contract Documents.
4.12 RESPONSIBILITY FOR COMPLETION
4.12.1 The Contractor shall furnish such labor, materials, tools, equipment, and professional services and shall work such
hours, including night shifts, overtime operations and Sundays and holidays, as may be necessary to ensure the
performance of the Work within Milestone and Completion dates specified in the County/Contractor Agreement.
If it becomes apparent to the Owner's Authorized Representative that the Work will not be Completed within
required Milestone or Completion dates, the Contractor agrees to undertake some or all of the following actions,
at no additional cost to the Owner, in order to ensure, in the opinion of the Owner's Authorized Representative,
that the Contractor will comply with all Milestone and Completion date requirements:
.1 Increase labor, materials, tools, equipment and professional services;
GENERAL CONDITIONS
GENERAL CONDITIONS (14)
.2 Increase the number of working hours per shift, shifts per working day, working
days per week, or any combination of the foregoing; and
.3 Reschedule activities to achieve maximum practical concurrency of
accomplishment of activities.
4.13 DOCUMENTS, SAMPLES AND OTHER SUBMITTALS AT THE SITE
4.13.1 The Contractor and his Subcontractors shall maintain at the site, and at all times make available to the Owner and
the Owner's Authorized Representative one record copy of all Drawings, Specifications, Addenda, Change
Orders, and other Modifications, in good order and marked currently to record all changes made during
construction, and approved Shop Drawings, Product Data, Samples, Mock Ups and other Submittals. These shall
be delivered to the Owner's Authorized Representative no later than with the application for Final Payment.
4.14 SHOP DRAWINGS, PRODUCT DATA, SAMPLES AND OTHER SUBMITTALS
4.14.1 The term "shop drawings" shall mean all drawings, diagrams, illustrations, brochures, schedules and other data
which are prepared by Contractor, a subcontractor, manufacturer, supplier or distributor and which illustrate the
equipment, material or some portion of the Work.
4.14.2 The Contractor shall review, approve and submit with reasonable promptness and in such sequence as to cause no
delay in the Work or in the work of the Owner or any separate Contractor, all Shop Drawings, Product Data,
Manuals, Samples, and Submittals required by the Contract Documents.
4.14.3 By approving and submitting Shop Drawings, Product Data, Manuals, Samples and Submittals, the Contractor
represents that he has determined and verified all materials, field measurements, and field construction criteria
related thereto, and that he has checked and coordinated the information contained within such submittals with the
requirements of the Work and of the Contract Documents. The Contractor shall adhere to any supplementary
processing and scheduling instructions pertaining to any submittals that may be issued by the Owner's Authorized
Representative.
4.14.3.1 Parts and details not fully indicated on the Contract Drawings shall be detailed by the Contractor in accordance
with standard engineering practice. Dimensions on the Contract Drawings, as well as detailed drawings
themselves, are subject in every case to measurements of existing, adjacent, incorporated and completed work,
that shall be taken by the Contractor before undertaking any work dependent on such data.
4.14.4 The Contractor shall not be relieved of responsibility for any deviation from the requirements of the Contract
Documents by virtue of the review by the Owner or the Owner's Authorized Representative of Shop Drawings,
Product Data, Samples or Manuals unless the Contractor has specifically informed the Owner's Authorized
Representative in writing of such deviation at the time of submission and the Owner's Authorized Representative
has given written approval to the specific deviation. The Contractor shall not be relieved from responsibility for
errors or omissions in the Shop Drawings, Product Data, Samples or Manuals by the Owner or Owner's
Authorized Representative's review thereof.
4.15 CLEANING UP
4.15.1 The Contractor at all times shall keep the premises free from accumulation of waste materials or rubbish cased by
his operations. At the completion of the Work and before Final Payment is made, he shall remove all his waste
materials and rubbish from and about the Project as well as all his tools, equipment and surplus materials.
4.15.2 If the Contractor fails to clean up during or at the completion of the Work, the Owner may do so as provided in
Article 6.3 "OWNER'S RIGHT TO PERFORM DISPUTED WORK" and the cost thereof shall be charged to the
Contractor.
4.16 ROYALTIES AND PATENTS
GENERAL CONDITIONS
GENERAL CONDITIONS (15)
4.16.1 Contractor shall pay all license fees and royalties and assume all costs incident to the use in the performance of
the Work of any invention, design, process, product or device which is the subject of patent rights or copyrights
held by others. If a particular invention, design, process, product or device is specified in the Contract Documents
for use in the performance of the Work and if to the actual knowledge of the Owner or Owner's Authorized
Representative its use is subject to patent rights or copyrights calling for the payment of any license fee or royalty
to others, the existence of such rights shall be disclosed by Owner in the Contract Documents. Contractor shall
indemnify, defend and hold harmless Owner and Owner's Authorized Representative and anyone directly or
indirectly employed by either of them from and against all claims, damages, losses and expenses (including
attorneys' fees) arising out of any infringement of patent rights or copyrights incident to the use in the
performance of the Work of any invention, design, process, product or device not specified in the Contract
Documents, and shall defend all such claims in connection with any alleged infringement of such rights.
4.17 INDEMNIFICATION
4.17.1 To the fullest extent permitted by law, the Contractor shall, at his sole cost and expense, indemnify, defend, and
hold harmless, the Owner, the Owner's Authorized Representative, their agents, representatives, employees,
successors and assigns from and against all claims, actions, judgments, costs, liabilities, penalties, damages, losses
and expenses, including but not limited to, attorney's fees, arising out of or resulting from the performance of the
Work, provided that any such claim, action, judgment, cost, liability, penalty, damage, loss or expense is:
.l Attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible
property (other than the Work itself) including loss of use resulting therefrom; and
.2 Is caused in whole or in part by any negligent act or omission of the Contractor,
any Subcontractor or supplier, anyone directly or indirectly employed by any of
them or anyone for whose acts any of them may be liable, regardless of whether
or not it is caused in part by a party indemnified hereunder.
Such obligation shall not be construed to negate, abridge, or otherwise reduce any other right or obligation of
indemnity that would otherwise exist as to any party or person described in this Article 4.17.
4.17.2 In any and all claims against the Owner and the Owner's Authorized Representative or any of their agents,
representatives, or employees by any employee of the Contractor, any Subcontractor, anyone directly or indirectly
employed by any of them, or anyone for whose acts any of them may be liable, the indemnification obligation
under this Article 4.17 shall not be limited in any way by any limitation on the amount or type of damages,
compensation or benefits payable by or for the Contractor or any Subcontractor under workers' or workmen's
compensation acts, disability benefit acts or other employee benefit acts.
4.17.3 No provision of Article 4.17 shall give rise to any duties on the part of the Owner or the Owner's Authorized
Representative, or any of their agents, representatives or employees.
4.17.4 The obligations of the Contractor under Article 4.17 shall not extend to the liability of the Owner's Authorized
Representative, and/or the Owner's design architect or engineers, their agents or employees arising out of (a) the
preparation or approval of maps, drawings, opinions, reports, surveys, Change Orders, designs or specifications or
(b) the giving of or the failure to give directions or instructions by Owner's Authorized Representative, his agents
or employees provided such giving or failure to give is the primary cause of injury or damage.
4.18 PERSONS AUTHORIZED TO SIGN DOCUMENTS
4.18.1 The Contractor, within five (5) days after the earlier of the date of a Notice to Proceed or the date of the
County/Contractor Agreement shall file with the Owner's Authorized Representative a list of all persons who are
authorized to sign documents such as contracts, certificates and affidavits on behalf of the Contractor and to fully
bind the Contractor to all the conditions and provisions of such documents.
END OF ARTICLE 4
GENERAL CONDITIONS
GENERAL CONDITIONS (16)
ARTICLE 5: SUBCONTRACTORS
5.1 DEFINITIONS
5.1.1 A Subcontractor is any firm, supplier, distributor or vendor that performs work for or furnishes services,
equipment or supplies to or for the Contractor or another Subcontractor in conjunction with the Contract. The
term Subcontractor is referred to throughout the Contract Documents as if singular in number and masculine in
gender and means a Subcontractor or his authorized representative. Although the term Sub-subcontractor may
appear within the Contract Documents, the term Subcontractor includes any person or entity who has a direct or
indirect contract with the Contractor to perform any of the Work.
5.1.2 The Contractor shall be fully responsible for all acts and omissions of his Subcontractors, and of persons and
organizations directly or indirectly employed by them, and of persons and organizations for whose acts any of
them may be liable, to the same extent that he is responsible for the acts and omissions of persons directly
employed by him.
5.1.3 Nothing contained in the Contract Documents is intended to, nor shall it create, any contractual relationship
between the Owner, the Owner's Authorized Representative, or any of their agents, consultants, employees,
independent contractors, or representatives and any Subcontractor, but the Owner shall be entitled to performance
of all obligations intended for its benefit, and to enforcement thereof.
5.1.4 The Owner's Authorized Representative will not deal directly with any Subcontractor. Communication will be
made only through the Contractor. Subcontractors shall route requests for information or clarification through the
Contractor to the Owner's Authorized Representative.
5.2 AWARD OF SUBCONTRACTS AND OTHER CONTRACTS FOR PORTIONS OF THE WORK
5.2.1 The Contractor, in compliance with the requirements of the Contract Documents, shall furnish to the Owner's
Authorized Representative in writing the names of the persons or entities (including those who are to furnish
materials or equipment fabricated to a special design) proposed for each of the principal portions of the Work.
The Owner's Authorized Representative will promptly reply to the Contractor in writing stating whether the
Owner has objection to any such proposed person or entity.
5.2.2 The Contractor shall not contract with any such proposed Subcontractor to whom the Owner has made objection
under the provisions of Article 5.2.1. The Contractor shall not be required to contract with anyone to whom he
has an objection.
5.2.3 If the Owner objects to any proposed Subcontractor under Article 5.2.1, the Contractor shall name a substitute to
whom the Owner has no objection within fifteen (15) days.
5.2.4 The Contractor shall make no substitution for any Subcontractor previously proposed by the Contractor and not
objected to by the Owner's Authorized Representative if the Owner makes objection to such substitution.
5.3 SUBCONTRACTUAL RELATIONS
5.3.1 By an appropriate agreement, written where legally required for validity, the Contractor shall require each
Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by
the terms of the Contract Documents, and to assume toward the Contractor all the obligations and responsibilities
that the Contractor, by these Documents, assumes toward the Owner.
Said agreement shall preserve and protect the rights of the Owner under the Contract Documents with respect to
the Work to be performed by the Subcontractor so that the subcontracting thereof will not prejudice such rights,
and shall allow to the Subcontractor, unless specifically provided otherwise in the Contractor-Subcontractor
Agreements, the benefit of all rights, remedies and redress against the Contractor that the Contractor, by these
Contract Documents, has against the Owner. Where appropriate, the Contractor shall require each Subcontractor
to enter into similar agreements with his Subcontractors.
GENERAL CONDITIONS
GENERAL CONDITIONS (17)
The Contractor shall make available to each proposed Subcontractor, prior to the execution of the Subcontract,
copies of the Contract Documents to which the Subcontractor will be bound by this Article 5.3, and identify to the
Subcontractor any terms and conditions of the proposed Subcontract that may be at variance with the Contract
Documents. Each Subcontractor shall similarly make copies of such Contract Documents available to his Sub-
subcontractors or Suppliers.
5.3.2 The Contractor shall be liable to and indemnify, defend and hold the Owner harmless from all costs, expenses,
fees, attorney's fees, accountant's fees, damages and claims arising because of the Contractor's failure to comply
with the provisions of this Article 5.3.
5.4 QUALIFICATION SUBMITTALS
5.4.1 Specific qualification submittals may be required of Subcontractors for certain critical items of the Work.
Required qualification submittals are set forth in detail in the Contract Documents and shall be collected and
submitted by the Contractor to the Owner’s Authorized Representative for review and approval by the Owner and
Owner's Authorized Representative. All information required of a single Subcontractor shall be contained in a
single, complete submittal. The Contractor shall submit the required qualification information within ten (10)
days after receipt of the Owner's Authorized Representative's request.
5.4.2 The Owner may reject any proposed Subcontractor, or any qualification submittals related thereto, for the
following reasons:
.1 The Contractor's failure to submit requested information within the specified time; or
.2 The Contractor's failure to provide all of the requested information; or
.3 The Contractor's submission of a Subcontractor, or qualifications thereof, that are
unacceptable to the Owner.
5.4.3 Should the Owner have objection to any proposed Subcontractor, the Contractor shall submit another firm for
approval within fifteen (15) days.
END OF ARTICLE 5
ARTICLE 6: WORK BY OWNER OR BY SEPARATE CONTRACTORS
6.1 OWNER'S RIGHT TO PERFORM WORK AND TO AWARD SEPARATE CONTRACTS
6.1.1 The Owner reserves the right to perform work related to the Project with its own forces, and to award separate
contracts in connection with other portions of the Project or other work on the site.
6.1.2 When separate contracts are awarded for different portions of the Project or other work on the site, the term
Contractor in the Contract Documents in each case shall mean the Contractor who executes each separate
County/Contractor Agreement.
6.2 MUTUAL RESPONSIBILITY
6.2.1 The Contractor shall afford other Contractors and the Owner reasonable opportunity for the introduction and
storage of their materials and equipment and the execution of their work and shall properly connect and
coordinate the Work with that of the Owner and other Contractors, to store his tools, materials and equipment in
such orderly fashion at the site of the Work as will not unduly or unreasonably interfere with the progress of the
Work or the work of any other Contractors.
GENERAL CONDITIONS
GENERAL CONDITIONS (18)
6.2.1.1 If the execution or result of any part of the Work depends upon any work of the Owner or of any separate
Contractor, the Contractor shall, prior to proceeding with the Work, inspect and promptly report in writing to the
Owner's Authorized Representative any apparent discrepancies or defects in such work of the Owner or of any
separate Contractor that render it unsuitable for such proper execution or result of any part of the Work under this
Contract.
6.2.1.2 Failure of the Contractor to so inspect and report shall constitute an acceptance of the Owner or separate
Contractor's work as fit and proper to receive the Work, except as to defects that may develop in the Owner's or
separate Contractor's work after completion of the Work, and that the Contractor could not have discovered by its
inspection prior to completion of the Work under this Contract.
6.2.2 Should the Contractor cause damage to the Work or property of the Owner or of any separate Contractor on the
Project, or to other work on the site, or delay or interfere with the Owner's work on ongoing operations or facilities
or adjacent facilities of said separate Contractor's work, the Contractor shall be liable for the same.
6.3 OWNER'S RIGHT TO PERFORM DISPUTED WORK
6.3.1 If a dispute arises between the Contractor and separate Contractors as to their responsibility for cleaning up as
required by Article 4.15 "CLEANING UP" or for accomplishing coordination as required by Article 6.4
"COORDINATION OF THE WORK," the Owner may carry out such Work and charge the cost thereof to the
Contractors responsible therefor as the Owner's Authorized Representative shall determine.
6.4 COORDINATION OF THE WORK
6.4.1 By entering into this Contract, Contractor acknowledges that there may be separate Contractors on the Site whose
work will be coordinated with that of his own. Contractor expressly warrants and guarantees that he will
cooperate with separate Contractors, and will do nothing to delay, hinder or interfere with the Work of other
separate Contractors, the Owner or the Owner's Authorized Representative.
END OF ARTICLE 6
ARTICLE 7: MISCELLANEOUS PROVISIONS
7.1 GOVERNING LAW
7.1.1 The Contract shall be governed by the law of the Commonwealth of Virginia, and the conflicts of law provisions
shall not be employed to apply the laws of any state other than those of the Commonwealth of Virginia to this
Contract.
7.1.2 Each and every provision of law and clause required by law to be inserted in this Contract shall be deemed to be
inserted herein and the Contract shall be read and enforced as though it were included herein. If through mistake
or otherwise, any provision is not inserted or is not correctly or fully inserted, then upon the application of either
party, the Contract shall be modified to include such provision.
7.2 SUCCESSORS AND ASSIGNS
7.2.1. The Contractor each binds himself, his partners, successors, assigns and legal representatives to the Owner hereto
in respect to all covenants, agreements and obligations contained in the Contract Documents. The Contractor
shall not assign the Contract or sublet it as a whole without the written consent of the Owner, nor shall the
Contractor assign any monies due or to become due to him hereunder, without the previous written consent of the
Owner.
7.3 CLAIMS FOR DAMAGES
GENERAL CONDITIONS
GENERAL CONDITIONS (19)
7.3.1 Should the Contractor suffer injury or damage to person or property because of any act or omission of the Owner
or of any of its employees, agents or others for whose acts either is legally liable, claim shall be made in writing to
the Owner within seven (7) days after the first observance of such injury or damage; otherwise, the Contractor
shall have waived any and all rights he may have against the Owner, or its employees, representatives and agents.
7.4 DISPUTES
7.4.1 A claim by the Contractor shall be made in writing and submitted to the Owner's Authorized Representative or his
Delegee, who shall produce his decision in writing and mail or otherwise furnish a copy thereof to the Contractor.
7.4.2 This decision shall be final and binding unless within thirty (30) days from the date of such decision, an appeal is
made to the County Board of Supervisors as authorized by the County of Warren Procurement Code.
7.4.3 The decision of the County Board of Supervisors shall be final and binding unless set aside by the Warren County
Circuit Court as fraudulent, capricious, arbitrary, or so grossly erroneous as to necessarily imply bad faith.
Pending the final determination of a properly appealed decision of the County Board of Supervisors, the
Contractor shall proceed diligently with the performance of the Contract in accordance with that decision.
7.4.4 Upon the written mutual consent of the parties hereto, claims and disputes arising out of the Contract may be
addressed in such Alternative Dispute Resolution ("ADR") procedures as the parties may mutually select. An
election to engage in ADR shall not operate as a waiver or elimination of any notice requirements or time periods
governing claim submittals or appeals established in the Contract, or applicable statutes of limitations, unless
expressly waived, extended or otherwise modified by the parties' written agreement to engage in ADR.
7.4.5 Notwithstanding any other provision hereof, the Contractor expressly waives all claims against the Owner for
consequential damages arising out of or relating to this Contract. This waiver includes losses of financing,
business and reputation, bonding capacity, and loss of profit other than profit arising directly from the Work
where otherwise permitted in the Contract.
7.5 TESTS
7.5.1 If the Contract Documents, laws, ordinances, rules, regulations or orders of any public authority having
jurisdiction require any portion of the Work to be inspected, tested, or approved, the Contractor shall give the
Owner's Authorized Representative five (5) days notice of its readiness so the Owner's Authorized Representative
may observe such inspection, testing or approval. The Contractor shall bear all costs of such inspections, tests or
approvals conducted by public authorities.
7.5.2 If the Owner's Authorized Representative determines that any Work requires special inspection, testing, or
approval that Article 7.5.1 does not include, the Owner's Authorized Representative will order the Contractor to
make arrangements for such special inspection, testing or approval, and the Contractor shall give the Owner's
Authorized Representative five (5) days notice of such inspection. If such special inspection or testing reveals a
failure of the Work to comply with:
.1 The requirements of the Contract Documents, or
.2 The conformance of the Work with laws, ordinances, rules, regulations, or orders
of any public authority having jurisdiction,
the Contractor shall bear all costs thereof, including compensation for the Owner's Authorized Representative and
any additional services made necessary by such failure.
7.5.3 Inspections and tests required under Article 7.5.2 to establish compliance with the Contract Documents will be
made by a testing agency employed by the Owner. When the initial tests indicate non-compliance with the
Contract Documents, any subsequent testing occasioned by non-compliance shall be performed by the same
agency and the cost thereof shall be borne by the Contractor. Representatives of the testing agency shall have
GENERAL CONDITIONS
GENERAL CONDITIONS (20)
access to the Work at all times. The Contractor shall provide facilities for such access in order that the agency
may properly perform its functions.
7.5.4 Certificates of inspection, testing or approval required by public authorities shall be secured by the Contractor and
promptly delivered by him to the Owner's Authorized Representative, in adequate time to avoid delays in the
Work or Final Payment therefor.
7.5.5 The Contractor shall pay for and have sole responsibility for inspection or testing performed exclusively for his
own convenience.
7.6 UNENFORCEABILITY OF ANY PROVISION
7.6.1 If any provision of this Contract is held as a matter of law to be unenforceable or unconscionable, the remainder
of the Contract shall be enforceable without such provision.
7.7 AVAILABILITY OF LANDS
7.7.1 Owner shall furnish, as indicated in the Contract Documents, the lands upon which the work is to be done, rights-
of-way or easements for access thereto. The Owner reserves the right to delay the notice to proceed with the
Contract Work in order to secure rights of way, easements or to relocate utilities, such as sewer, water, gas,
electricity, cable television and other services.
END OF ARTICLE 7
ARTICLE 8: TIME
8.1 DEFINITIONS
8.1.1 The Contract Time is the period of time set forth in the County/Contractor Agreement for Final Completion of the
Work as defined in Article 8.1.4, including authorized extensions thereto.
8.1.2. The date of commencement of the Work is the date established in the Notice to Proceed issued by the Owner.
Submission by the Contractor of all Certificates of Insurance, Performance and Payment Bonds and their approval
by the Owner are conditions precedent to the issuance of the Notice to Proceed. Availability of lands under
Article 7.7 is also a condition precedent to the issuance of the Notice to Proceed. The Contractor shall not
commence the Work or store materials or equipment on site until written Notice to Proceed is issued or until the
Contractor otherwise receives the written consent of the Owner.
8.1.3 The date of Substantial Completion of the Work or designated portion thereof is the date certified by the Owner's
Authorized Representative when the Work or a designated portion thereof is sufficiently complete, in accordance
with the Contract Documents, so the Owner can fully occupy or deliver the Work or designated portion thereof
for the use for which it is intended, with all of the Project's parts and systems operable as required by the Contract
Documents. Only punch list work and any final cleaning beyond that needed for the Owner's full use may remain
for Final Completion.
8.1.4 The date of Final Completion of the Work is the date certified by the Owner's Authorized Representative when
the Work is totally complete, to include punch list work and final clean up, in accordance with the Contract
Documents and the Owner may fully occupy or fully utilize the Work for the use for which it is intended.
8.1.5 If the date or time of completion is included in the Contract, it shall be the Date of Final Completion as defined in
Article 8.1.4, including authorized extensions thereto, unless otherwise provided.
GENERAL CONDITIONS
GENERAL CONDITIONS (21)
8.1.6 The term Day as used in the Contract Documents shall mean calendar day unless otherwise specifically designated. All
dates shall mean midnight of the indicated day unless otherwise stipulated.
8.2 PROGRESS AND COMPLETION
8.2.1 All time limits stated in the Contract Documents are of the essence of this Contract.
8.2.2 The Contractor shall prosecute the Work diligently to Final Completion.
8.3 DELAYS AND EXTENSIONS OF TIME
8.3.1 The time during which the Contractor is delayed in the performance of the Work, by the acts or omissions of the
Owner, the Owner's Authorized Representative or their employees or agents, acts of God, unusually severe and
abnormal climatic conditions, fires, floods, epidemics, quarantine restrictions, strikes (not to exceed the actual
duration of the strike), riots, civil commotions or freight embargoes, or other conditions beyond the Contractor's
control and that the Contractor could not reasonably have foreseen and provided against, shall be added to the
Contract Time; provided, however, that no claim by the Contractor for an extension of time for delays will be
considered unless made in compliance with the requirements of this Article and other provisions of the Contract
Documents.
8.3.2 The Contract Time shall be adjusted only for Change Orders pursuant to Article 12, "CHANGES IN THE
WORK," Article 3.3, "OWNER'S RIGHT TO STOP OR SUSPEND THE WORK," and Article 8.3, "DELAYS
AND EXTENSIONS OF TIME ." In the event the Contractor requests an extension of the Contract Time, he
shall furnish such justification and supporting evidence as the Owner's Authorized Representative may deem
necessary for a determination of whether the Contractor is entitled to an extension of time under the provisions of
the Contract.
8.3.3 The burden of proof to substantiate a claim for an extension of the Contract Time shall rest with the Contractor,
including evidence that the cause was beyond his control. The Owner's Authorized Representative shall base his
findings of fact and decision on such justification and supporting evidence and shall advise the Contractor in
writing thereof.
8.3.4 The Contractor shall not be entitled to and hereby expressly waives any extension of time resulting from any
condition or cause unless said request for extensions of time is made in writing to the Owner's Authorized
Representative within seven (7) days of the first instance of delay.
END OF ARTICLE 8
ARTICLE 9: PAYMENTS AND COMPLETION
9.1 CONTRACT PRICE
9.1.1. The Contract Price is stated in the County/Contractor Agreement and, including authorized adjustments thereto, is
the firm, fixed price amount payable by the Owner to the Contractor for the performance of the Work under the
Contract Documents. The Contract Price includes all applicable Federal, State and local taxes and duties.
9.2 SCHEDULE OF VALUES
9.2.1 Within ten (10) days after the Notice to Proceed is issued, the Contractor shall submit to the Owner's Authorized
Representative a Schedule of Values, allocated to the various portions of the Work including mobilization and
demobilization. This schedule, supported by data from the approved Progress Schedule, shall be used as a basis
for the Contractor's Applications for Payment upon approval by the Owner's Authorized Representative. The
Schedule of Values shall not alter in any way the firm, fixed price or lump sum contract price. The Contractor
shall not front-end load his Schedule of Values.
GENERAL CONDITIONS
GENERAL CONDITIONS (22)
9.3 APPLICATIONS FOR PAYMENT
9.3.1 The Owner shall make progress payments monthly as the Work proceeds on Applications for Payment approved
by the Owner's Authorized Representative.
9.3.2 Prior to the date for each progress payment established in the County/Contractor Agreement, the Contractor, in
accordance with any Supplementary Conditions concerning schedules and/or payments, shall submit to the
Owner's Authorized Representative an itemized Application for Payment, supported by such data substantiating
the Contractor's right to payment as the Owner's Authorized Representative may require, including but not limited
to the Contractor's certification that all work for which payment is requested has been completed in full
accordance with the Contract Documents, copies of requisitions from Subcontractors and reflecting retainage, if
any, as provided elsewhere in the Contract Documents. The Contractor shall certify that he has paid all due and
payable amounts for which previous Certificates for Payment were issued and payments received from the Owner.
9.3.3 The Owner will retain five (5) percent of the amount of all progress payments until the Work is substantially
completed and accepted, whether or not the Owner has occupied any or all of the Project before such time. After
fifty (50) percent of the Work has been completed, the Contractor may request the Owner to retain less than five
(5) percent of the amount of all progress payments for the Work performed beyond the fifty (50) percent stage of
completion. The decision of the Owner concerning reduction of retention shall be final and binding upon the
Contractor.
9.3.4 The Contractor warrants that title to all Work, materials and equipment covered by an Application for Payment
will pass to the Owner either by incorporation in the construction or upon the receipt of payment by the
Contractor, whichever occurs first, free and clear of all liens, claims, security interests or encumbrances,
hereinafter referred to in this Article 9 as "LIENS"; and that no Work, materials or equipment covered by an
Application for Payment will have been acquired by the Contractor, or by any other person performing Work at
the site or furnishing materials and equipment for the Project, subject to an agreement under which an interest
therein or an encumbrance thereon is retained by the seller or otherwise imposed by the Contractor or such other
person.
9.4 CERTIFICATES FOR PAYMENT
9.4.1 The Owner's Authorized Representative will within five (5) days after receipt of the Contractor's Application for
Payment, either approve the Application for Payment for such amount as he determines is properly due, or notify
the Contractor in writing of his reasons for not approving the Application for Payment as provided in Article 9.6
"PAYMENTS WITHHELD."
9.4.2 The submission and approval of the Progress Schedule and monthly updates thereof, as required by any
Supplementary Conditions concerning Schedules, shall be part of the application upon which progress payment
shall be made. The Contractor shall be entitled to progress payments only as determined from the currently
Approved and Updated Progress Schedule.
9.5 PROGRESS PAYMENTS
9.5.1 After an Application for Payment has been approved by the Owner's Authorized Representative, the Owner shall
make payment in the manner and within the time provided in the Contract Documents.
9.5.2 The Contractor shall promptly pay each Subcontractor providing labor or furnishing material for the Work, upon
receipt of payment from the Owner, out of the amount paid to the Contractor on account of Subcontractor's work,
the amount to which said Subcontractor or supplier is entitled, reflecting the percentage actually retained, if any,
from payments to the Contractor on account of such Subcontractor's work. The Contractor shall, by an
appropriate agreement with each Subcontractor, also require each Subcontractor to make payments to his
Subcontractors in similar manner.
9.5.3 The Owner's Authorized Representative may, on request and at his discretion, furnish to any Subcontractor, if
practicable, information regarding the percentages of completion or the amounts applied for by the Contractor,
GENERAL CONDITIONS
GENERAL CONDITIONS (23)
and the action taken thereon by the Owner's Authorized Representative on account of Work done by such
Subcontractor.
9.5.4 The Owner has no obligation to pay or to see to the payment of any moneys to any Subcontractor except as may
otherwise be required by law.
9.5.5 No Application for Payment, nor any progress payment, nor any partial or entire use or occupancy of the Project
by the Owner, shall constitute an acceptance of any Work which is not in accordance with the Contract
Documents.
9.6 PAYMENTS WITHHELD
9.6.1 The Owner's Authorized Representative may decline to approve the Application for Payment or reduce payment
or because of subsequently discovered evidence or subsequent observations, he may nullify the whole or any part
of any Application for Payment previously approved to such extent as may be necessary in his opinion to protect
the Owner from loss, because of:
.1 Defective work not remedied;
.2 Third party claims filed, whether in court, in arbitration or otherwise, or
reasonable evidence indicating probable filing of such claims;
.3 Failure of the Contractor to make payments properly to Subcontractors;
.4 Reasonable evidence that the Work cannot be completed for the unpaid balance of
the Contract Price;
.5 Damage to the Owner or to a separate contractor;
.6 Reasonable evidence that the Work will not be completed within the Contract
Time, or within any Contract Milestones as established in the Contract
Documents;
.7 Failure or refusal of the Contractor to carry out the Work in accordance with or to
otherwise substantially or materially comply with the Contract Documents;
.8 Failure or refusal of the Contractor to properly schedule and coordinate the Work,
or to provide Progress Schedules, reports and updates; and
.9 Failure or refusal of the Contractor to fully comply with the provisions of Article
4.13 "DOCUMENTS AND SAMPLES AND OTHER SUBMITTALS AT THE
SITE."
9.6.2 When the above grounds in Article 9.6.1 are removed, payment shall be made for amounts withheld because of
them.
9.7 SUBSTANTIAL COMPLETION
9.7.1 When the Contractor considers that the Work, or a designated portion thereof which is acceptable to the Owner's
Authorized Representative, is substantially complete as defined in Article 8.1.3., the Contractor shall prepare for
submission to the Owner's Authorized Representative a list of items that in his opinion are to be completed or
corrected and shall request in writing that the Owner's Authorized Representative perform a Substantial
Completion inspection. The Owner's Authorized Representative shall review the Contractor's list and will
compile a punch list of items to be corrected and completed. The failure to include any items on such list does not
alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. When
the Owner's Authorized Representative on the basis of an inspection determines that the Work or designated
GENERAL CONDITIONS
GENERAL CONDITIONS (24)
portion thereof is substantially complete, he will then prepare a Certificate of Substantial Completion that will
establish the Date of Substantial Completion, state the responsibilities of the Owner and the Contractor for
security, maintenance, heat, utilities, damage to the Work, and insurance, and shall fix the time within which the
Contractor shall complete the items listed therein.
Warranties required by the Contract Documents shall commence on the Date of Substantial Completion of the
Work or designated portion thereof unless otherwise provided in the Certificate of Substantial Completion. The
Certificate of Substantial Completion shall be issued to the Contractor for his written acceptance of the
responsibilities assigned to him in such Certificate and returned to the Owner's Authorized Representative within
five (5) days.
9.7.2 The Contractor shall have thirty (30) days from the Date of Substantial Completion to complete all items on the
punch list to the satisfaction of the Owner's Authorized Representative. The Owner's Authorized Representative
shall have the option to correct any and all punch list items not completed by the Contractor within thirty (30)
days from the Date of Substantial Completion by utilizing his own forces, those of the Owner, or by a separate
Contractor. The cost of such correction of remaining punch list items by the Owner or others shall be deducted
from the Final Payment to the Contractor. If the Contractor does not complete all punch list items within this time
period specified in Article 9.7.2, all warranties and guarantees for such incomplete Punch List items shall become
effective upon issuance of Final Payment.
9.7.3 The issuance of the Certificate of Substantial Completion does not indicate final acceptance of the Project by the
Owner, and the Contractor is not relieved of any responsibility for the Project except as specifically stated in the
Certificate of Substantial Completion.
9.7.4 Should the Owner's Authorized Representative determine that the Work or a designated portion thereof is not
substantially complete, he shall provide the Contractor a written notice stating why the project or designated
portion is not substantially complete. The Contractor shall expeditiously complete the Work and shall request in
writing that the Owner's Authorized Representative perform a Substantial Completion reinspection and the costs,
if any, associated with such reinspection shall be assessed to the Contractor.
9.8 FINAL COMPLETION AND FINAL PAYMENT
9.8.1 Upon receipt of the documentation required by Article 9.8.3, and of written notice that the Work is ready for final
inspection and acceptance, the Owner's Authorized Representative will promptly make such inspection and, when
he finds the Work acceptable under the Contract Documents and the Contract fully performed, he will issue a
Certificate of Final Completion to the Contractor. Upon his receipt of the Final Completion Certificate, the
Contractor may submit his Application for Final Payment to the Owner's Authorized Representative for his
approval. Final Payment shall be made in full to the Contractor within thirty (30) calendar days after the approval
by the Owner's Authorized Representative of the Application for Final Payment provided that the requirements of
Article 9 have been fulfilled, except for an amount mutually agreed upon for any work remaining uncompleted for
which the Owner is entitled a credit under the Contract Documents.
9.8.2 Should the Owner's Authorized Representative determine that the Work or a designated portion thereof is not
complete, he shall provide the Contractor a written notice stating why the Project or designated portion is not
complete. The Contractor shall expeditiously complete the Work and shall request in writing that the Owner's
Authorized Representative perform a Final Completion reinspection and the costs, if any, associated with such
reinspection shall be assessed to the Contractor.
9.8.3 Neither the Final Payment nor the remaining retained percentage shall become due until the Work is free and clear
of any and all Liens and the Contractor submits to the Owner's Authorized Representative:
.1 An affidavit that all payrolls, bills for materials and equipment, and other indebtedness connected
with the Work for which the Owner or its property might in any way be responsible, have been
paid or otherwise satisfied;
GENERAL CONDITIONS
GENERAL CONDITIONS (25)
.2 Consent of surety to Final Payment, if necessary;
.3 As-built drawings, operation and maintenance manuals and other project close-out submittals, as
required by the Contract Documents;
.4 A fully executed and notarized Release of claims in such form as may be designated by the
Owner; and
.5 A written certification that:
(1) the Contractor has reviewed the requirements of the Contract Documents;
(2) the Work has been inspected by the Contractor for compliance with all requirements
of the Contract Documents;
(3) pursuant to this inspection, the Contractor certifies and represents that the Work
complies in all respects with the requirements of the Contract Documents; and
(4) the Contractor further certifies and represents that all equipment and systems have
been installed and tested in accordance with the Contract Documents and the Owner
personnel training in the proper operation and maintenance of equipment is complete.
9.8.4 The making of Final Payment shall constitute a waiver of all claims by the Owner against the Contractor except
those arising from:
.1 Unsettled liens and claims against the Owner;
.2 Faulty, defective or non-conforming Work discovered or appearing after Substantial or Final
Completion;
.3 Failure of Work to comply with the requirements of the Contract Documents; and
.4 Terms of any warranties contained in or required by the Contract Documents.
9.8.5 The acceptance of Final Payment shall constitute a waiver of all claims by the Contractor except those previously
made in writing and identified by the Contractor as unsettled at the time of the Application for Final Payment.
9.9 PARTIAL OCCUPANCY OR USE
9.9.1 The Owner may occupy or use any completed or partially completed portion of the Work at any stage when such
portion is designated by separate agreement with the Contractor, provided such occupancy or use is consented to
by the insurer as required under Article 11.5.1.5 and authorized by public authorities having jurisdiction over the
Work. Such partial occupancy or use may commence whether or not the portion is substantially complete,
provided the Owner and the Contractor have accepted in writing the responsibilities assigned to each of them for
payments, retainage, if any, security, maintenance, heat, utilities, damage to the Work and insurance, and have
agreed in writing concerning the period for correction of the Work and commencement of warranties required by
the Contract Documents. When the Contractor considers a portion substantially complete, the Contractor shall
prepare and submit a list to the Owner’s Authorized Representative as provided under Article 9.7. Consent of the
Contractor to partial occupancy or use shall not be unreasonably withheld. The stage of the progress of the Work
shall be determined by written agreement between the Owner’s Authorized Representative and the Contractor or,
if no agreement is reached, by decision of the Owner’s Authorized Representative.
9.9.2 Immediately prior to such partial occupancy or use, the Owner and/or the Owner’s Authorized Representative,
and the Contractor shall jointly inspect the area to be occupied or portion of the Work to be used in order to
determine and record the condition of the Work.
GENERAL CONDITIONS
GENERAL CONDITIONS (26)
9.9.3 Unless otherwise agreed upon, partial occupancy or use of a portion or portions of the Work shall not constitute
acceptance of Work not complying with the requirements of the Contract Documents.
END OF ARTICLE 9
ARTICLE 10: PROTECTION OF PERSONS AND PROPERTY
10.1 SAFETY PRECAUTIONS AND PROGRAMS
10.1.1 The Owner and the Owner's Authorized Representative are not responsible for the means, methods, techniques,
sequences or procedures utilized by the Contractor, or for safety precautions and programs in connection with the
Work. The Contractor shall be solely responsible for initiating, maintaining, and supervising all safety
precautions and programs in connection with the Work. This requirement applies continuously throughout the
Contract performance, until Final Payment is made, and is not limited to regular working hours.
10.2 SAFETY OF PERSONS AND PROPERTY
10.2.1 The Contractor shall take reasonable precautions for safety of, and shall provide reasonable protection to prevent
damage, injury or loss, to:
.1 All employees on the Work and other persons who may be affected thereby;
.2 All the Work and materials and equipment to be incorporated therein whether in
storage off the site, under the care, custody or control of the Contractor or any of
his Subcontractors, machinery and equipment. All hazards shall be guarded or
eliminated in accordance with all applicable safety regulations; and
.3 Other property at or adjacent to the Work, including trees, shrubs, lawns, walks,
pavements, roadways, structures and utilities not designated for removal,
relocation or replacement in the course of construction.
10.2.2 The Contractor shall give all notices and comply with applicable laws, ordinances, permits, rules, regulations and
orders of any public authority bearing on the safety of persons or property or their protection from damage, injury
or loss.
10.2.2.1 The Contractor shall at all times safely guard the Owner's property from injury or losses in connection with this
Contract. He shall at all times safely guard and protect his own work and adjacent property as provided by law
and the Contract Documents from damage. All security personnel, passageways, guard fences, lights, and other
facilities required for protection of the property and the Work described herein shall be provided and maintained
at the Contractor's expense.
10.2.3 The Contractor shall erect and maintain, as required by existing conditions and progress of the Work, all
reasonable safeguards for safety and protection, including danger signs and other warnings against hazards,
promulgating safety regulations and notifying owners and users of adjacent utilities.
10.2.4 When the use or storage of explosives or other hazardous materials or equipment is necessary for the execution of
the Work, the Contractor shall exercise the utmost care and shall carry on such activities under the supervision of
properly qualified personnel.
10.2.5 The Contractor shall promptly remedy at his own cost and expense all damage or loss to any property referred to
in Articles 10.2.1.2 and 10.2.1.3. The Contractor shall perform such restoration by underpinning, repainting,
rebuilding, replanting, or otherwise restoring as may be required or directed by the Owner's Authorized
Representative or shall make good such damage in a satisfactory and acceptable manner. In case of failure on the
part of the Contractor to promptly restore such property or make good such damage, the Owner may, upon two (2)
GENERAL CONDITIONS
GENERAL CONDITIONS (27)
days written notice, proceed to repair, rebuild or otherwise restore such property as may be necessary, and the cost
thereof will be deducted from any monies due or to become due to the Contractor under the Contract.
10.2.6 The Contractor shall give notice in writing at least 48 hours before breaking ground, to the Owner, all persons,
Public Utility Companies, superintendents, inspectors or those otherwise in charge of property, streets, water
pipes, gas pipes, sewer pipes, telephone cables, electric cables, railroads or otherwise, who may be affected by the
Contractor's operation, in order that they may remove any obstruction for which they are responsible and have a
representative on site to see that their property is properly protected. The Contractor is responsible for any
damages or claims resulting from any excavation and shall defend, fully indemnify, and hold harmless the Owner
from all actions resulting from such work regardless of whether the Contractor gave proper notice under this
clause.
10.2.7 The Contractor shall protect all utilities encountered while performing its work, whether indicated on the Contract
Documents or not. The Contractor shall maintain utilities in service until moved or abandoned. The Contractor
shall exercise due care when excavating around utilities and shall restore any damaged utilities to the same
condition or better as existed prior to starting the Work, at no cost to the Owner. The Contractor shall maintain
operating utilities or other services, even if they are shown to be abandoned on the Contract Drawings, in service
until new facilities are provided, tested and ready for use.
10.2.8 The Contractor shall return all improvements on or about the site and adjacent property that are not shown to be
altered, removed or otherwise changed to conditions that existed prior to starting work.
10.2.9 The Contractor shall protect the Work, including but not limited to, the site, stored materials and equipment,
excavations, and excavated or stockpiled soil or other material, intended for use in the Work, and shall take all
necessary precautions to prevent or minimize damage to same or detrimental effect upon his performance or that
of his subcontractors, caused by or due to rain, run-off, floods, temperature, wind, dust, sand, and flying debris;
for example, but not by way of limitation, Contractor shall, when necessary, utilize temporary dikes, channels or
pumping to carry-off, divert or drain water, and as necessary tie-down or otherwise secure the Work and employ
appropriate covers and screens.
10.2.10 The Contractor shall be responsible for the prevention of accidents and the protection of material, equipment and
property.
10.2.11 The Contractor shall not load or permit any part of the Work to be loaded so as to endanger the safety of the
Work, persons or adjacent property.
10.2.12 The Contractor has sole and complete responsibility for the correction of any safety violation and sole liability for
the consequences of said violation. The Contractor shall give prompt written notice of any safety violation to the
Owner's Authorized Representative.
10.3 EMERGENCIES
10.3.1 In any emergency affecting the safety of persons or property, the Contractor shall act to prevent threatened
damage, injury or loss. The Contractor shall notify the Owner's Authorized Representative of the situation and all
actions taken immediately thereafter. If, in the opinion of the Contractor, immediate action is not required, the
Contractor shall notify the Owner's Authorized Representative of the emergency situation and take necessary
steps. Provided, however, if any loss, damage, injury or death occurs that could have been prevented by the
Contractor's prompt and immediate action or the emergency resulted from acts or omissions of the Contractor or
his Subcontractors, or anyone directly or indirectly employed by any of them, or by anyone whose acts any of
them may be liable, the Contractor shall defend, fully indemnify and hold harmless the Owner (including
attorney's fees) from all actions relating thereto. Any additional compensation or extension of time claimed by the
Contractor on account of emergency work shall be determined as provided in Article 12 "CHANGES IN THE
WORK."
END OF ARTICLE 10
GENERAL CONDITIONS
GENERAL CONDITIONS (28)
ARTICLE 11: BONDS AND INSURANCE
11.1 BONDS
11.1.1 The Contractor shall furnish to the Owner a performance bond in the sum of the contract price executed by a
surety legally authorized to do business in Virginia payable to the County of Warren, Virginia, or such other
entity as may be identified in the County/Contractor Agreement, and conditioned upon the faithful performance of
the contract in strict conformity with the plans, specifications, and conditions of the Contract Documents.
11.1.2 The Contractor shall furnish to the Owner a payment bond in the amount of the contract price payable to the
County of Warren or such other entity as may be identified in the County/Contractor Agreement, and executed by
a surety legally authorized to do business in Virginia. Such bond shall be conditioned on the prompt payment to
all claimants who have and fulfill contracts to supply labor or materials to the Contractor for all material furnished
or labor supplied or performed in the prosecution of the Work. "Labor and materials" shall include public utility
services and reasonable rentals of equipment, but only for periods when the equipment rented is actually used at
the project site.
11.1.3 If the surety on any Bond furnished by the Contractor is declared bankrupt or becomes insolvent or its right to do
business is terminated in any state where any part of the Project is located, the Contractor shall within five (5)
days thereafter substitute another Bond and surety, both of which shall be acceptable to the Owner.
11.2 CONTRACTOR’S LIABILITY INSURANCE
11.2.1 The Contractor shall purchase from and maintain in a company or companies lawfully authorized to do business
in the State of Virginia such insurance as will protect the Contractor from claims set forth below which may arise
out of or result from the Contractor’s operations under the Contract and for which the Contractor may be legally
liable, whether such operations be by the Contractor or by a Subcontractor or by anyone directly or indirectly
employed by any of them, or by anyone for whose acts any of them may be liable:
.1 claims under workers’ compensation, disability benefit and other similar
employee benefit acts which are applicable to the Work to be performed;
.2 claims for damages because of bodily injury, occupational sickness or disease, or
death of the Contractor’s employees;
.3 claims for damages because of bodily injury, sickness or disease, or death of any
person other than the Contractor’s employees;
.4 claims for damages insured by usual personal injury liability coverage;
.5 claims for damages, other than to the Work itself, because of injury to or
destruction of tangible property including loss of use resulting therefrom;
.6 claims for damages because of bodily injury, death of a person or property
damage arising out of ownership, maintenance or use of a motor vehicle;
.7 claims for bodily injury or property damage arising out of completed operations;
and
.8 claims involving contractual liability insurance applicable to the Contractor’s
obligations under Article 4.17.
11.2.2 The insurance required by Article 11.2.1 shall be written for not less than limits of liability specified in the
Contract Documents or required by law, whichever coverage is greater. Coverages, whether written on an
occurrence or claims-made basis, shall be maintained without interruption from date of commencement of the
Work until date of final payment and termination of any coverage required to be maintained after final payment.
GENERAL CONDITIONS
GENERAL CONDITIONS (29)
11.2.3 Certificates of insurance acceptable to the Owner shall be filed with the Owner prior to commencement of the
Work. These certificates and the insurance policies required by this Article 11.2 shall contain a provision that
coverages afforded under the policies will not be canceled or allowed to expire until at least thirty (30) days prior
written notice has been given to the Owner. If any of the foregoing insurance coverages are required to remain in
force after final payment and are reasonably available, an additional certificate evidencing continuation of such
coverage shall be submitted with the final Application for Payment as required by Article 9.8. Information
concerning reduction of coverage on account of revised limits or claims paid under the General Aggregate, or
both, shall be furnished by the Contractor with reasonable promptness in accordance with the Contractor’s
information and belief.
11.3 OWNER’S LIABILITY INSURANCE
11.3.1 The Owner shall be responsible for purchasing and maintaining the Owner’s usual liability insurance.
11.4 PROJECT MANAGEMENT PROTECTIVE LIABILITY INSURANCE
11.4.1 Optionally, the Owner may require the Contractor to purchase and maintain Project Management Protective
Liability insurance from the Contractor’s usual sources as primary coverage for the Owner’s, Contractor’s and
Owner’s Authorized Representative’s vicarious liability for construction operations under the Contract. Unless
otherwise required by the Contract Documents, the Owner shall reimburse the Contractor by increasing the
Contract Sum to pay the cost of purchasing and maintaining such optional insurance coverage, and the Contractor
shall not be responsible for purchasing any other liability insurance on behalf of the Owner. The minimum limits
of liability purchased with such coverage shall be equal to the aggregate of the limits required for Contractor’s
Liability Insurance under Articles 11.2.1.2 through 11.2.1.5.
11.4.2 To the extent damages are covered by Project Management Protective Liability insurance, the Owner, Contractor
and Owner’s Authorized Representative waive all rights against each other for damages, except such rights as
they may have to the proceeds of such insurance. The policy shall provide for such waivers of subrogation by
endorsement or otherwise.
11.4.3 The Owner shall not require the Contractor to include the Owner, the Owner’s Authorized Representative or other
persons or entities as additional insureds on the Contractor’s Liability Insurance coverage under Article 11.2.
11.5 PROPERTY INSURANCE
11.5.1 Unless otherwise provided, the Owner shall purchase and maintain, in a company or companies lawfully
authorized to do business in the jurisdiction in which the Project is located, property insurance written on a
builder’s risk "all-risk" or equivalent policy form in the amount of the initial Contract Sum, plus value of
subsequent Contract modifications and cost of materials supplied or installed by others, comprising total value for
the entire Project at the site on a replacement cost basis without optional deductibles. Such property insurance
shall be maintained, unless otherwise provided in the Contract Documents or otherwise agreed in writing by all
persons and entities who are beneficiaries of such insurance, until final payment has been made as provided in
Article 9.8 or until no person or entity other than the Owner has an insurable interest in the property required by
this Article 11.5 to be covered, whichever is later. This insurance shall include interests of the Owner, the
Contractor, Subcontractors and Sub-subcontractors in the Project.
11.5.1.1 Property insurance shall be on an "all-risk" or equivalent policy form and shall include, without limitation,
insurance against the perils of fire (with extended coverage) and physical loss or damage including, without
duplication of coverage, theft, vandalism, malicious mischief, collapse, earthquake, flood, windstorm, falsework,
testing and startup, temporary buildings and debris removal including demolition occasioned by enforcement of
any applicable legal requirements, and shall cover reasonable compensation for Owner’s Authorized
Representative’s and Contractor’s services and expenses required as a result of such insured loss.
11.5.1.2 If the Owner does not intend to purchase such property insurance required by the Contract and with all of the
coverages in the amount described above, the Owner shall so inform the Contractor in writing prior to
GENERAL CONDITIONS
GENERAL CONDITIONS (30)
commencement of the Work. The Contractor may then effect insurance which will protect the interests of the
Contractor, Subcontractors and Sub-subcontractors in the Work, and by appropriate Change Order the cost thereof
shall be charged to the Owner. If the Contractor is damaged by the failure or neglect of the Owner to purchase or
maintain insurance as described above, without so notifying the Contractor in writing, then the Owner shall bear
all reasonable costs properly attributable thereto.
11.5.1.3 If the property insurance requires deductibles, the Owner shall pay costs not covered because of such deductibles.
11.5.1.4 This property insurance shall cover portions of the Work stored off the site, and also portions of the Work in
transit.
11.5.1.5 Partial occupancy or use in accordance with Article 9.9 shall not commence until the insurance company or
companies providing property insurance have consented to such partial occupancy or use by endorsement or
otherwise. The Owner and the Contractor shall take reasonable steps to obtain consent of the insurance company
or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use
that would cause cancellation, lapse or reduction of insurance.
11.5.2 Boiler and Machinery Insurance. The Owner shall purchase and maintain boiler and machinery insurance
required by the Contract Documents or by law, which shall specifically cover such insured objects during
installation and until final acceptance by the Owner; this insurance shall include interests of the Owner,
Contractor, Subcontractors and Sub-subcontractors in the Work, and the Owner and Contractor shall be named
insureds.
11.5.3 Loss of Use Insurance. The Owner, at the Owner’s option, may purchase and maintain such insurance as will
insure the Owner against loss of use of the Owner’s property due to fire or other hazards, however caused. The
Owner waives all rights of action against the Contractor for loss of use of the Owner’s property, including
consequential losses due to fire or other hazards however caused.
11.5.4 If the Contractor requests in writing that insurance for risks other than those described herein or other special
causes of loss be included in the property insurance policy, the Owner shall, if possible, include such insurance,
and the cost thereof shall be charged to the Contractor by appropriate Change Order.
11.5.5 If during the Project construction period the Owner insures properties, real or personal or both, at or adjacent to
the site by property insurance under policies separate from those insuring the Project, or if after final payment
property insurance is to be provided on the completed Project through a policy or policies other than those
insuring the Project during the construction period, the Owner shall waive all rights in accordance with the terms
of Article 11.5.7 for damages caused by fire or other causes of loss covered by this separate property insurance.
All separate policies shall provide this waiver of subrogation by endorsement or otherwise.
11.5.6 Before an exposure to loss may occur, the Owner shall file with the Contractor a copy of each policy that includes
insurance coverages required by this Article 11.5. Each policy shall contain all generally applicable conditions,
definitions, exclusions and endorsements related to this Project. Each policy shall contain a provision that the
policy will not be canceled or allowed to expire, and that its limits will not be reduced, until at least thirty (30)
days prior written notice has been given to the Contractor.
11.5.7 Waivers of Subrogation. The Owner and Contractor waive all rights against (1) each other and any of the
subcontractors, sub-subcontractors, agents and employees, each of the other, and (2) the Owner’s Authorized
Representative and/or his consultants, separate contractors described in Article 6, if any, and any of their
subcontractors, sub-subcontractors, agents and employees, for damages caused by fire or other causes of loss to
the extent covered by property insurance obtained pursuant to this Article 11.5 or other property insurance
applicable to the Work, except such rights as they have to proceeds of such insurance held by the Owner as
fiduciary. The Owner or Contractor, as appropriate, shall require of the Owner’s Authorized Representative
and/or his consultants, separate contractors described in Article 6, if any, and the subcontractors, sub-
subcontractors, agents and employees of any of them, by appropriate agreements, written where legally required
for validity, similar waivers each in favor of other parties enumerated herein. The policies shall provide such
waivers of subrogation by endorsement or otherwise. A waiver of subrogation shall be effective as to a person or
entity even though that person or entity would otherwise have a duty of indemnification, contractual or otherwise,
GENERAL CONDITIONS
GENERAL CONDITIONS (31)
did not pay the insurance premium directly or indirectly, and whether or not the person or entity had an insurable
interest in the property damaged.
11.5.8 A loss insured under Owner’s property insurance shall be adjusted by the Owner as fiduciary and made payable to
the Owner as fiduciary for the insureds, as their interests may appear, subject to requirements of any applicable
mortgagee clause and of Article 11.5.10. The Contractor shall pay Subcontractors their just shares of insurance
proceeds received by the Contractor, and by appropriate agreements, written where legally required for validity,
shall require Subcontractors to make payments to their Sub-subcontractors in similar manner.
11.5.9 If required in writing by a party in interest, the Owner as fiduciary shall, upon occurrence of an insured loss, give
bond for property performance of the Owner’s duties. The cost of required bonds shall be charged against
proceeds received as fiduciary. The Owner shall deposit in a separate account proceeds so received, which the
Owner shall distribute in accordance with such agreement as the parties in interest may reach. If after such loss
no other special agreement is made and unless the Owner terminates the Contract for convenience, replacement of
damaged property shall be performed by the Contractor after notification of a Change in the Work in accordance
with Article 12.
11.5.10 The Owner as fiduciary shall have power to adjust and settle a loss with insurers unless one of the parties in
interest shall object in writing within five days after occurrence of loss to the Owner’s exercise of this power; if
such objection is made, the dispute shall be resolved as provided in Article 7.4. The Owner as fiduciary shall, in
the case of disputes, make settlement with insurers in accordance with orders of the Court.
END OF ARTICLE 11
ARTICLE 12: CHANGES IN THE WORK
12.1 CHANGES IN THE WORK
12.1.1 The Owner, without invalidating the Contract and without notice to the surety, may order a Change in the Work
consisting of additions, deletions, modifications or other revisions to the general scope of the Contract, or changes
in the sequence of the performance of the Work. The Contract Price and the Contract Time shall be adjusted
accordingly. All such Changes in the Work shall be authorized by written Change Order, and all Work involved
in a Change shall be performed in accordance with the terms and conditions of this Contract. If the Contractor
should proceed with a Change in the Work upon an oral order, by whomever given, it shall constitute a waiver by
the Contractor of any claim for an increase in the Contract Price and/or Contract Time, on account thereof.
12.1.2 When the Owner and the Contractor have agreed upon a Change in the Work, but a written Change Order
Document has not yet been executed, the Owner may, at its sole discretion and option, direct in writing the
Contractor to proceed with the Change in the Work pending the execution of the formal Change Order.
Contractor shall proceed in accordance with such direction.
12.2 FIELD ORDER
12.2.1 A Field Order is a written order to the Contractor signed by the Owner or the Owner's Authorized Representative
interpreting or clarifying the Contract Documents or directing the Contractor to perform minor changes in the
Work. Any work relating to the issuance of a Field Order shall be performed promptly and expeditiously and
without additional cost to the Owner and within the Contract Time, unless the Contractor submits a Proposed
Change Order, defined below, which is approved by the Owner. Field Orders shall be numbered consecutively by
date of issuance by the Owner or the Owner's Authorized Representative.
12.3 REQUEST FOR PROPOSAL
12.3.1 A Request For Proposal describes a proposed Change in the Work. The Contractor is required to submit a
complete proposal for the total cost and additional time, if any, necessary to perform the proposed Change in the
GENERAL CONDITIONS
GENERAL CONDITIONS (32)
Work. Requests For Proposals shall be numbered consecutively by date of issuance by the Owner or the Owner's
Authorized Representative.
12.3.2 Requests for Proposals shall be in the form prescribed by the Owner's Authorized Representative, including all
appropriate back up material.
12.4 PROPOSED CHANGE ORDER
12.4.1 A Proposed Change Order is a written request from the Contractor to the Owner requesting a change in the
Contract Price and/or Contract Time. A Proposed Change Order is submitted as a proposal in response to a
Request For Proposal or as a claim for an increase in the Contract Price or Contract Time pursuant to the issuance
of a Field Order. A Proposed Change Order must be submitted within twenty (20) days of the issuance of a
Request For Proposal or a Field Order. Proposed Change Orders shall be numbered consecutively by date of
issuance by the Contractor. The Contractor shall also indicate on the Proposed Change Order the number of the
Request For Proposal or the Field Order to which it responds.
12.4.2 The Contractor's Proposed Change Order shall be determined by the applicable Schedule of Values, if any, as
provided for in the Contract.
12.4.3 The portion of the proposal relating to labor, whether by the Contractor's forces or the forces of any of his
Subcontractors, may include reasonably anticipated gross wages of Job Site labor, including foremen, who will be
directly involved in the Change in the Work (for such time as they will be so involved), plus payroll costs
(including premium costs of overtime labor, if overtime is authorized, Social Security, Federal or State
unemployment insurance taxes and fringe benefits required by collective bargaining agreements entered into by
the Contractor or any such Subcontractor in connection with such labor).
12.4.4 The portion of the proposal relating to materials may include the reasonably anticipated direct costs to the
Contractor or to any of his Subcontractors of materials to be purchased for incorporation in the Change in the
Work, plus transportation and applicable sales or use taxes.
12.4.5 The proposal may further include the Contractor's and any of his Subcontractor's reasonably anticipated
equipment rental costs, except small hand tools, in connection with the Change in the Work. For rented
equipment an hourly rental rate will be used which will be determined by using the monthly rental rates taken
from the current edition of the Rental Rate Blue Book for Construction Equipment and dividing it by 176. An
allowance will be made for operating costs for each and every hour the equipment is actually operating in
accordance with the rates listed in the aforesaid Rental Book. The Contractor will be allowed only sixty-five (65)
percent of the rental rate on Contractor owned equipment after adjustments for standby, age, region, etc. as
applicable.
12.4.6 Base Cost is defined as the total of labor, material and equipment rentals as described in subparagraphs 12.4.3,
12.4.4 and 12.4.5. The actual net cost to the Owner for the Change in the Work shall be computed as follows:
.1 If the Contractor performs the Change in the Work, his compensation will be the
Base Costs as described above, plus (1) a mark-up of fifteen (15) percent or
$2,000, whichever is greater, on Base Costs greater than $10,000, or (2) a mark-
up of twenty (20) percent on Base Costs less or equal to $10,000, for overhead
and profit. If the Contractor's customary mark-up is less than the mark-up
allowed by 12.4.6.1 those rates shall apply for overhead and profit.
.2 If the work is performed by a bona fide Subcontractor, his compensation will be
the Base Costs as described above plus a mark-up as described in Article 12.4.6.1
for overhead and profit. The Contractor's compensation will be a mark-up of ten
(10) percent of the Subcontractor's Base Costs for his overhead.
GENERAL CONDITIONS
GENERAL CONDITIONS (33)
.3 If the work is performed by a bona fide Sub-subcontractor, his compensation will
be the Base Costs as herein described plus a mark-up as described in Article
12.4.6.1 for overhead and profit. The Subcontractor's compensation will be a
mark-up of ten (10) percent of the Sub-subcontractor's Base Costs for his
overhead. The Contractor's compensation will be a mark-up of ten (10) percent of
the Sub-subcontractor Base Costs for his overhead.
12.4.7 The mark-up on the cost of labor, materials, and equipment described in Article 12.4.6 shall compensate the
Contractor, Subcontractor or Sub-subcontractor for all indirect costs associated with or relating to the Change in
the Work including, but not limited to, gross receipts tax, superintendent, small tools, reproduction,
administration, insurance, unrelated safety requirements, temporary structures and offices, all other general and
administrative, home office and field office expenses.
12.4.8 The mark-up on the cost of labor, materials, and equipment described in Articles 12.4.6.2 and 12.4.6.3 shall
compensate the Contractor or Subcontractor for all indirect costs associated with or relating to the Change in the
Work including but not limited to, gross receipt tax, superintendent, reproduction, administration, insurance and
bonds.
12.4.9 In the event it is necessary to increase the Contract Time in order to perform the Change in the Work, the
Contractor shall provide an estimate of the increase in the Contract Time which shall be negotiated by the parties
to the Contract. The Contractor's request for a time extension shall be evaluated in accordance with the criteria
described in Article 8.
12.4.10 If the Contractor's Proposed Change Order is rejected by the Owner as being within the scope of the Work
required by the Contract Documents the Owner may, at its sole option and discretion, direct the Contractor to
perform the Work which is the subject of the said Proposed Change Order; the Contractor shall then promptly
proceed with said Work. Nothing herein shall excuse the timely performance by the Contractor of the Work
because any Proposed Change Order is pending.
12.5 CHANGE ORDER
12.5.1 A Change Order is a written order to the Contractor signed by the Owner and the Owner's Authorized
Representative, issued after execution of the Contract, authorizing a Change in the Work or an adjustment in the
Contract Price and/or the Contract Time. The Contract Price and the Contract Time may be changed only by
Change Order. A Change Order signed by the Contractor indicates his agreement therein, including the
adjustment in the Contract Price and/or the Contract Time. Change Orders shall be numbered consecutively by
date of issuance by the Owner or the Owner's Authorized Representative and shall, if applicable, indicate the
number of the Field Order(s), Request For Proposal(s) and/or Proposed Change Order(s) to which it relates.
12.5.1.1 If the Owner and the Owner's Authorized Representative determine that the Contractor's Proposed Change Order,
submitted pursuant to Article 12.4 for a change in the Contract Price or Contract Time, is acceptable, the Owner's
Authorized Representative shall prepare and issue, or cause to be prepared and issued, a Change Order which will
authorize the Contractor to proceed with the Change in the Work for the cost and time stated in the Proposed
Change Order, or as otherwise may be agreed upon by the parties. The amounts stated in the Change Order for
the cost and time to perform the Change in the Work shall be binding on the parties.
12.5.2 After issuance of the Change Order, the Contractor shall ensure that the amount of the Performance and Payment
Bond coverage has been revised to reflect the increase in the Contract Price due to the Change Order.
12.5.3 If the Contractor's Proposed Change Order is not acceptable to the Owner and the Owner's Authorized Representative
or if the parties are unable to otherwise agree as to the cost and time necessary to perform the Change in the Work, the
Owner may, at its sole option and discretion, direct the Contractor to perform the Work on a time and material basis.
The Contractor shall then promptly proceed with the Work.
12.5.4 If the Owner and the Owner's Authorized Representative elect to have the Change in the Work performed on a
time and material basis, the same shall be performed, whether by the Contractor's forces or the forces of any of his
Subcontractors or Sub-subcontractor's, at actual cost to the entity performing the Change in the Work (without
GENERAL CONDITIONS
GENERAL CONDITIONS (34)
any charge for administration, clerical expense, supervision or superintendent of any nature whatsoever, or the
cost, use or rental of tools or plant). The percent mark-ups for the Contractor, Subcontractors and Sub-
subcontractors shall be as described in Articles 12.4.6.1, 12.4.6.2 and 12.4.6.3.
12.5.4.1 Prior to starting the work on a time and material basis, the Contractor shall notify the Owner's Authorized
Representative in writing as to what labor, materials, equipment or rentals are to be used for the Change in the
Work. During the performance of the Change, the Contractor shall submit to the Owner daily time and material
tickets, which shall list the categories and amounts of labor and equipment for which Change Order compensation
is to be charged for the previous work day. Such tickets shall specifically include the following information:
location and description of the Change in the Work, the classification of labor employed, including names and
social security numbers of laborers, labor trades used, manhours, wage rates, insurance, taxes and fringe benefits,
equipment and materials suppliers' quotations with detailed break-out and pricing, rental equipment hours and
rates, and materials quantities and unit prices and such other evidence of cost as the Owner may require.
12.5.4.2 The Contractor shall commence submission of daily time and material tickets immediately upon commencement
of the Change Order Work and continue to submit them until completion of the Change Order Work. The Owner
may require authentication of all time and material tickets and invoices by persons designated by the Owner for
such purpose.
12.5.4.3 The failure of the Contractor to provide any required authentication shall, if the Owner elects to treat it as such,
constitute a waiver by the Contractor of any claim for the cost of that portion of the Change in the Work covered
by a non-authenticated ticket or invoice; provided, however, that the authentication of any such ticket or invoice
by the Owner shall not constitute an acknowledgment by the Owner that the items thereon were reasonably
required for the Change in the Work.
12.5.4.5 The Contractor shall submit his complete submission of the reasonable actual cost and time to perform the
Change in the Work within twenty (20) days of the request of the Owner's Authorized Representative to do so.
The Owner and the Owner's Authorized Representative shall review the costs and time submitted by the
Contractor on the basis of reasonable expenditures and savings of those performing the Change in the Work. If
such costs and time are acceptable to the Owner and the Owner's Authorized Representative, or if the parties
otherwise agree to the actual reasonable cost to perform the Change in the Work, the Owner's Authorized
Representative shall issue a Change Order for the cost and time agreed upon. The amounts stated in the Change
Order for the cost and time to perform the Change in the Work shall be binding upon the parties.
12.5.5 The Contractor shall be entitled to costs as provided for in Article 12.4 which the Contractor, or his
Subcontractors, may incur as a result of delays, interferences, suspensions, changes in sequence or the like, which
are unreasonable arising from the performance of any and all changes in the Work, caused by acts or omissions of
the Owner, performed pursuant to this Article 12.
12.6 UNILATERAL CHANGE ORDER
12.6.1 In the event that the parties are unable to agree as to the reasonable cost and time to perform the Change in the
Work and the Owner does not elect to have the Change in the Work performed on a time and material basis, the
Owner and the Owner's Authorized Representative shall make a unilateral determination of the reasonable cost
and time to perform the Change in the Work, based upon their own estimates, the Contractor's submission or a
combination thereof. A Change Order shall be issued for the amounts of cost and time determined by the Owner
and the Owner's Authorized Representative and shall become binding upon the Contractor unless the Contractor
submits his protest in writing to the Owner within ten (10) days of the issuance of the Change Order. The
procedure for the resolution of the Contractor's protest shall be as described in Article 12.10. The Owner has the
right to direct in writing the Contractor to perform the Change in the Work, which is the subject of such Unilateral
Change Order. Failure of the parties to reach an agreement regarding the cost and time of performing the Change
in the Work, or any pending protest, shall not relieve the Contractor from performing the Change in the Work
promptly and expeditiously.
12.7 DECREASES AND WORK NOT PERFORMED
GENERAL CONDITIONS
GENERAL CONDITIONS (35)
12.7.1 Should it be deemed expedient by the Owner or the Owner's Authorized Representative at any time that the
Contract Work is in progress to decrease the dimensions, quantity of material or work, or vary in any other way
the work herein contracted for, the Owner or the Owner's Authorized Representative shall have the full power to
do so, and shall order and direct, in writing, such decreases to be made or performed without in any way affecting
the enforcement of said Contract. The Contractor shall, in pursuance of such written orders and directions from
the Owner or the Owner's Authorized Representative, execute the work thereby ordered and directed, and the
difference in expense occasioned by such decrease or diminution so ordered shall be deducted from the amount
payable under this Contract.
12.7.2 If work is not performed, and such deletion of work is not approved by the Owner, the Owner's Authorized
Representative shall ascertain the amount of the credit due the Owner, based on the reasonable value of the labor
and materials so deleted, for the lesser amount of materials and labor required.
12.7.3 If work is deleted from the Contract by Change Order, the amounts to be credited to the Owner shall reflect the
same current pricing as if the work were being added to the Contract at the time the deletion is ordered, and
documentation will be required for a credit as specified in Article 12.5.4.1. If such deleted materials and
equipment shall have already been purchased and stored on site and cannot be used in other projects or returned
for credit or cannot be returned for credit at the price paid by the Contractor at the time of purchase, the
Contractor shall be entitled, upon proper documentation and certification, to an adjustment in the pricing of the
credit to avoid hardship to the Contractor. If necessary in order to establish such reasonable value, the Contractor
may be required to submit a detailed breakdown of his original bid for the items or work involved.
12.8 CHANGES IN LINE AND GRADE
12.8.1 The Owner reserves the right through the Owner's Authorized Representative to make such alterations in the line
and grade of various structures or pipe lines shown on the drawings, as may be necessitated by conditions found
during construction or that in the judgment of the Owner's Authorized Representative appears advisable. The
Contractor shall not claim forfeiture of Contract by reason of such changes by the Owner's Authorized
Representative.
12.8.2 In case of a fixed price contract, the price of the work shall be negotiated as herein provided. If such alterations or
changes diminish the quantity of work to be done, they shall not constitute a claim for damages or for loss of
anticipated profits in the work which may be dispensed with, and the work as constructed shall be paid for in
accordance with the Contract prices as established for such work under this Contract.
12.9 DIFFERING SITE CONDITIONS
12.9.1 The Contractor shall promptly, and before the conditions are disturbed, give written notice to the Owner's
Authorized Representative of (a) subsurface or latent physical conditions at the site which differ materially from
those indicated in the Contract Documents, or (b) unknown physical conditions at the site, of an unusual nature,
which differ materially from those ordinarily encountered and generally recognized as inhering in work of the
character provided for in the Contract and which were not reasonably anticipated as a result of the investigation
required by Article 1.2.2.
12.9.2 The Owner's Authorized Representative shall investigate the site conditions promptly after receiving the notice. If
the conditions do materially so differ and cause an increase or decrease in the cost or time of performance, the
provisions of Article 12 "Changes in the Work" shall apply.
12.9.3 No request by the Contractor for a Change Order under this Article shall be allowed, unless the Contractor has
given the required written notice.
12.9.4 No request by the Contractor for a Change Order under this Article shall be allowed if made after final payment
under the Contract.
12.10 CLAIMS FOR ADDITIONAL COST AND/OR TIME
GENERAL CONDITIONS
GENERAL CONDITIONS (36)
12.10.1 If the Contractor wishes to make a claim for an increase in the Contract Price and/or Contract Time, he shall give
the Owner written notice thereof within seven (7) calendar days after the occurrence of the event giving rise to
such claim. This notice shall be given by the Contractor before proceeding to execute the Work, except in an
emergency endangering life or property in which case the Contractor shall proceed as provided in Article 10. No
claim shall be allowed and no amounts shall be paid for any and all costs incurred more than twenty (20) days
prior to the time notice is given to the Owner as herein provided. Any change in the Contract Price and/or
Contract Time resulting from such claim shall be authorized by Change Order. The Contractor's complete claim
submittal for an increase in the Contract Price shall be submitted no later than twenty (20) calendar days after the
work for which the claim is made has been completed or after the request of the Owner or the Owner's Authorized
Representative.
12.10.2 If the Contractor claims that additional cost or time is involved because of, but not limited to, any of the following
circumstances, the Contractor shall make such claim as provided in Subparagraph 12.10.1: (1) any written
interpretation pursuant to Article 2, (2) any order by the Owner to stop the Work pursuant to Article 3 where the
Contractor was not at fault, (3) failure of payment by the Owner pursuant to Article 9, or (4) any written order for
a minor change in the Work issued pursuant to Article 12.8.1.
12.11 ATTORNEYS' FEES AND OTHER EXPENSES
12.11.1 In recognition of the public monies being administered by the Owner to fund this Contract, the Contractor hereby
agrees that he will not submit, assert, litigate or otherwise pursue any frivolous or unsubstantiated delay claims.
In the event that the Contractor's delay claim, or any separate item of a delay claim, is determined through
litigation or other dispute resolution process to be false or to have no basis in law or fact, the Contractor shall be
liable to the Owner and shall pay it for all Investigation Costs costs incurred by the Owner which include
investigating, analyzing, negotiating, appealing, defending, and litigating the false or baseless delay claims,
including, but not limited to, attorneys' fees, audit costs, accountants' fees, expert witness' fees, additional
architect/engineer expenses and any other consultant costs. The amount to be paid hereunder to the Owner shall
be the percentage of the Owner’s total Investigation Costs in an amount equal to the percentage of the
Contractor’s total delay claim which is determined to be false or to have no basis in fact.
12.11.2 If any dispute should arise between the parties with respect to an increase or decrease in the Contract Price or an
extension or reduction in the Contract Time or as a result of a Change in the Work, the Contractor shall not
suspend performance of a Change in the Work or the Work itself unless otherwise so ordered by the Owner's
Authorized Representative in writing. Disputes shall be resolved pursuant to Article 7.4 of the Contract. The
Owner will, however, pay the Contractor up to the Owner's Authorized Representative's estimated value of the
Change in the Work, regardless of the dispute, if said Change in the Work results in an increase in the Contract
Price; and the Owner will have the right to decrease the Contract Price up to the Owner's Authorized
Representative's estimated value of the Change in the Work, regardless of the dispute, if said Change in the Work
results in a decrease in the Contract Price.
END OF ARTICLE 12
ARTICLE 13: UNCOVERING AND CORRECTION OF WORK
13.1 UNCOVERING OF WORK
13.1.1 If any portion of the Work should be covered contrary to the request of the Owner's Authorized Representative or
to requirements specifically expressed in the Contract Documents or to requirements of applicable Construction
Permits, it must, if required in writing by the Owner's Authorized Representative, be uncovered for its observation
and shall be replaced at the Contractor's expense.
13.1.2 If any portion of the Work has been covered that the Owner's Authorized Representative has not specifically
requested to observe prior to being covered, the Owner's Authorized Representative may request to see such Work
GENERAL CONDITIONS
GENERAL CONDITIONS (37)
and it shall be uncovered by the Contractor. If such Work complies with the Contract Documents, the cost of
uncovering and replacement shall, by appropriate Change Order, be charged to the Owner. If such Work does not
comply with the Contract Documents, the Contractor shall pay such costs unless the Owner caused this condition,
in which event the Owner shall pay such costs.
13.2 CORRECTION OF WORK
13.2.1 The Contractor shall promptly reconstruct, replace or correct all work rejected by the Owner's Authorized
Representative as defective or as failing to conform to the Contract Documents or as not in accordance with the
guarantees and warranties specified in the Contract Documents whether observed before or after Substantial
Completion and whether or not fabricated, installed or completed. The Contractor shall bear all costs of
correcting such rejected Work, including compensation for the Owner's Authorized Representative and any other
additional services made necessary thereby.
13.2.2 The Contractor, unless removal is waived by the Owner, shall remove from the site all portions of the Work that
are defective or non-conforming, or if permitted or required, he shall correct such Work in place at his own
expense promptly after receipt of notice, and such rejected Work shall not thereafter be tendered for acceptance
unless the former rejection or requirement for correction is disclosed.
13.2.3 If the Contractor does not proceed with the correction of such defective or non-conforming Work within a
reasonable time fixed by written notice from the Owner's Authorized Representative, the Owner may either:
.1 By separate contract or otherwise replace or correct such Work and charge the
Contractor the cost occasioned the Owner thereby and remove and store the
materials or equipment at the expense of the Contractor; or
.2 Terminate this Contract as provided in Article 14.3 "DEFAULT
TERMINATION."
13.2.4 The Contractor shall bear the cost of making good all work of the Owner or separate Contractors destroyed or
damaged by such correction or removal.
13.2.5 Nothing contained in this Article 13.2 shall be construed to establish a period of limitation with respect to any
other obligation that the Contractor might have under the Contract Documents, including Article 4.7
"WARRANTY" hereof. The establishment of the time period of one (1) year after the Date of Substantial
Completion or such longer period of time as may be prescribed by law or by the terms of any warranty required
by the Contract Documents relates only to the specific obligation of the Contractor to correct the Work, and has
no relationship to the time within which his obligation to comply with the Contract Documents may be sought to
be enforced, nor to the time within which proceedings may be commenced to establish the Contractor's liability
with respect to his obligations other than specifically to correct the Work.
13.3 ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK
13.3.1 If the Owner's Authorized Representative prefers to accept defective or non-conforming Work, it may do so instead of
requiring its removal and correction, in which case a Change Order will be issued to reflect a reduction in the Contract
Price where appropriate and equitable, or the Owner may elect to accept payment in materials or services, in lieu of a
reduction in the Contract Price. If the amount of a reduction is determined after Final Payment, it shall be paid to the
Owner by the Contractor.
END OF ARTICLE 13
ARTICLE 14: TERMINATION OF THE CONTRACT
14.1 TERMINATION FOR THE CONVENIENCE OF THE OWNER
GENERAL CONDITIONS
GENERAL CONDITIONS (38)
14.1.1 The Owner may, at any time upon ten (10) days written notice to the Contractor, terminate, without prejudice to
any right or remedy of the Owner, the whole or any portion of the Work for the convenience of the Owner. This
Notice of Termination shall specify that portion of the Work to be terminated and the effective date of
termination. The Contractor's sole remedy, in the event of such termination, will be the allowable termination
costs permitted by Article 14.2 "ALLOWABLE CONVENIENCE TERMINATION COSTS."
14.1.2 The Contractor shall include termination clauses identical to Article 14 in all subcontracts and purchase orders
related to the Work. Failure to include these termination clauses in any subcontracts or purchase orders shall
preclude recovery of any termination costs related to that subcontract or purchase order.
14.2 ALLOWABLE CONVENIENCE TERMINATION COSTS
14.2.1 After complying with the provisions of Article 14.4, the Contractor shall submit a termination claim, in no event
later than six (6) months after the effective date of its termination, unless one or more extensions of three (3)
months each are granted by the Owner in response to the Contractor's written request.
14.2.2 The Owner shall pay the Contractor's reasonable costs of termination, plus a mark-up of ten (10) percent for profit
and overhead. In no event shall this amount be greater than the original contract price, reduced by any payments
made prior to Notice of Termination, and further reduced by the price of the supplies not delivered, or the service
not provided. This Contract shall be amended accordingly, and the Contractor shall be paid the agreed amount.
14.2.3 In the event that the parties cannot agree on the whole amount to be paid to the Contractor by reason of
termination under this clause, the Owner shall pay to the Contractor the amounts, as determined by the Owner's
Authorized Representative as follows, without duplicating any amounts which may have already been paid under
the preceding paragraph of this clause:
.1 With respect to all Contract performance prior to the effective date of Notice of
Termination, the total of:
(1) cost of work performed or supplies delivered;
(2) the costs of settling and paying any reasonable claims as provided in
Article 14.4; and
(3) a mark-up of ten (10) percent for profit and overhead.
.2 The total sum to be paid under .1 above shall not exceed the contract price, as
reduced by the amount of payments otherwise made, and as further reduced by
the contract price of work not done or supplies not delivered.
14.2.4 In the event that the Contractor is not satisfied with any payments which the Owner's Authorized Representative
shall determine to be due under this clause, the Contractor may proceed in accordance with Article 7.4
"DISPUTES."
14.2.5 If the Contractor would have sustained a loss on the entire Contract had it been completed, no profit shall be
included or allowed hereunder and an appropriate adjustment shall be made reducing the amount of the settlement
to reflect the indicated rate of loss.
14.3 DEFAULT TERMINATION
14.3.1 The Owner may, upon ten (10) days written notice to the Contractor, terminate, without prejudice to any right or
remedy of the Owner, the Contract for default, in whole or in part, and may take possession of the Work and
complete the Work by contract or otherwise in any of the following circumstances:
.1 The Contractor refuses or fails to prosecute the Work or any separable part
thereof with such diligence as will ensure the Substantial Completion of the Work
within the Contract Time, or fails to meet any milestones established in the
GENERAL CONDITIONS
GENERAL CONDITIONS (39)
Contract Documents or fails to substantially complete the Work within said
period;
.2 The Contractor is in default in carrying out any provision of the Contract for a
cause within his or his Subcontractors' control;
.3 The Contractor fails to supply a sufficient number of properly skilled workmen or
proper equipment or materials;
.4 The Contractor fails to make prompt payment to Subcontractors or for materials
or labor;
.5 The Contractor disregards laws, permits, ordinances, rules, regulations, or orders
of any public authority having jurisdiction;
.6 The Contractor breaches any provision of the Contract Documents;
.7 The voluntary abandonment of the Project by the Contractor;
.8 Judicial proceedings in any State and/or any United States Federal Court as
follows:
(1) The filing by the Contractor of a voluntary petition in bankruptcy or in solvency, or a
petition for reorganization;
(2) The consent to an involuntary petition in bankruptcy or the failure to
vacate within sixty (60) calendar days from the date of entry thereof
any order approving an involuntary petition by the Contractor;
(3) The appointment of a receiver for all or any substantial portion of the
property of the Contractor; and
(4) The entering of an order, judgment or decree by any court of
competent jurisdiction, on the application of a creditor, that
adjudicates the Contractor as bankrupt or insolvent or approves a
petition seeking reorganization, or appoints a receiver, trustee or
liquidator of all or a substantial part of such party's assets, and such
order, judgment or decree continues unstayed and in effect for any
period of one hundred twenty (120) consecutive days.
.9 Upon at least one hundred twenty (120) calendar days prior written notice by the
Owner to the Contractor, at any time during the term of the Agreement, the
Owner determines that maintaining the Agreement in force will harm, bring into
disrepute, or effect the integrity of the Owner.
14.3.2 Upon termination of this Agreement under this Article, the Contractor shall remove all of his employees and
property from the Project in a smooth, orderly, and cooperative manner.
14.3.3 The right of the Contractor to proceed shall not be terminated under Article 14.2 because of any delays in the
completion of the Work due to unforeseeable causes beyond the control and without the fault or negligence of the
Contractor or his Subcontractors as specifically set forth in Article 8.3 "DELAYS AND EXTENSIONS OF
TIME."
14.3.4 If, after the Contractor has been terminated for default pursuant to Article 14.3, it is determined that none of the
circumstances set forth in Article 14.3.1 exist, then such termination shall be considered a termination for
convenience pursuant to Article 14.1. In such case, the Contractor's sole remedy will be costs permitted by
Article 14.2.
GENERAL CONDITIONS
GENERAL CONDITIONS (40)
14.3.5 If the Owner terminates the Contract, the Contractor shall not be entitled to receive any further payment until the
Work is finished. If the unpaid balance of the Contract Price exceeds the cost of completing the Work including
compensation for additional managerial, administrative and inspection services and any damages for delay, such
excess amount shall be paid to the Contractor. If such expenses exceed the unpaid balance, the Contractor and his
sureties shall be liable to the Owner for such excess amount.
14.3.6 If the right of the Contractor to proceed with the Work is partially or fully terminated, the Owner may take
possession of and utilize in completing the Work such materials, appliances, supplies, plant and equipment as may
be on the site of the terminated portion of the Work and necessary for the completion of the Work. If the Owner
does not fully terminate the right of the Contractor to proceed, the Contractor shall continue to perform the part of
the Work that is not terminated.
14.4 GENERAL TERMINATION PROVISIONS
14.4.1 After receipt of a Notice of Termination from the Owner, pursuant to Article 14.1 or 14.3, and except as otherwise
directed by the Owner, the Contractor shall:
.1 Stop Work under the Contract on the date and to the extent specified in the Notice of
Termination;
.2 Place no further purchase orders or subcontracts for materials, services, or
facilities, except as may be necessary for completion of such portion of the Work
under the Contract that is not terminated;
.3 Terminate all purchase orders and subcontracts to the extent that they relate to the
performance of Work terminated by the Notice of Termination;
.4 At the option of the Owner, assign to the Owner in the manner, at the times and to
the extent directed by the Owner, all of the rights in the contracts so terminated, in
which case, the Owner shall have the right, at his discretion, to settle or pay any
or all claims arising out of the termination of such purchase orders and
subcontracts;
.5 Settle all outstanding liabilities and all claims arising out of such termination of
purchase orders and subcontracts, with the approval or ratification of the Owner,
to the extent he may require, which approval or ratification shall be final for all
the purposes of this Article;
.6 Transfer title and deliver to the entity or entities designated by the Owner, in the
manner, at the times and to the extent directed by the Owner to the extent
specifically produced or specifically acquired by the Contractor for the
performance of such portion of the Work as has been terminated, the following:
(1) The fabricated or unfabricated parts, work in progress, partially
completed supplies and equipment, materials, parts, tools, dies, jigs,
and other fixtures, completed work, supplies and other material
produced as part of, or acquired in connection with the performance
of, the work terminated by the Notice of Termination; and
(2) The completed or partially completed plans, drawings, shop drawings,
submittals, information, releases, manuals, and other property related
to the Work and which, if the Contract had been completed, would
have been required to be furnished to the Owner.
.7 Use his best efforts to sell, in the manner, at the times, to the extent and at the
price or prices directed or authorized by the Owner or Owner's Authorized
GENERAL CONDITIONS
GENERAL CONDITIONS (41)
Representative, any property of the types referred to in Article 14.4.1.6; provided,
however, that the Contractor:
(1) Shall not be required to extend credit to any buyer; and
(2) May acquire such property under the conditions prescribed by and at a
price or prices approved by the Owner; and provided further that the
proceeds of any such transfer or disposition shall be applied in
reduction of any payments to be made by the Owner to the Contractor
under the Contract or shall otherwise be credited to the Contract Price
covered by the Contract or paid in such other manner as the Owner
may direct;
.8 Complete performance of such part of the Work as shall not have been terminated
by the Notice of Termination; and
.9 Take such action as may be necessary, or as the Owner or Owner's Authorized
Representative may direct for the protection and preservation of the property
related to the Contract that is in the possession of the Contractor and in which the
Owner has or may acquire an interest.
14.4.2 If the convenience termination, pursuant to Article 14.1, is partial, the Contractor may file with the Owner a claim
for an equitable adjustment of the Contract Price relating to the continued portion of the Contract (the portion not
terminated by the Notice of Termination) for costs increased because of such partial termination. Such equitable
adjustment as may be agreed upon shall be made in the Contract Price. Any claim by the Contractor for an
equitable adjustment under this Article must be submitted in writing to the Owner's Authorized Representative
within sixty (60) days from the Notice of Termination.
14.4.3 The Contractor shall refund to the Owner any amounts paid by the Owner to the Contractor in excess of costs
reimbursed under Article 14.4 within sixty (60) days of receipt of a written request from the Owner to do so.
END OF ARTICLE 14
General 01100 - 1
SECTION 01100 GENERAL
1. GENERAL The work covered by these specifications comprises the furnishing of all plant, labor, material and equipment, and installation and construction of all items, and performances of all works necessary to complete the project as shown on the drawings and described in these specifications in a satisfactory and acceptable manner. 2. LICENSES AND PERMITS Prior to beginning construction, the Contractor shall obtain and display all Town, County and State licenses required by law in the operation of his business. 3. REFERENCE TO MANUFACTURERS N/A Any reference to manufacturers is not intended to limit the equipment to that manufacturer, but is given to establish a standard of quality and to indicate the type of material desired. If a change in the details of construction and equipment accessories is necessary to meet the particular type of equipment selected, no additional increase in the Contract price will be allowed in connection with such changes. Any such change shall be approved by the Engineer and shall be accompanied by detailed drawings if deviation from the Contract drawings is required. The Contractor shall list in the Bid Proposal manufacturers of the major equipment that he intends to furnish. 4. DETAILED AND MANUFACTURER'S DRAWINGS The Contractor shall submit for the approval of the Engineer, prior to start of construction, detailed or shop drawings of all equipment he contemplates furnishing under this Contract. Equipment shall not be fabricated until shop drawings have been approved. All shop drawings shall be checked and signed or stamped by the Contractor before submission to the Engineer. The approval of Contractor's shop drawing will be general and shall not relieve the Contractor from the responsibility for adherence to the Contract, nor shall it relieve him of the responsibility for any error which may exist. Where such errors or omissions are discovered later, they shall be made good by the Contractor irrespective of any approval by the Engineer. 5. AS-BUILT DATA Promptly after completion of any portion of the work provided for in this Contract, the Contractor shall deliver to the Engineer all data necessary to revise the plans and specifications to the as-built condition. The Contractor will be held responsible for the accuracy of such data and shall bear any costs incurred in the location of other work as a result of incorrect as-built data furnished by the Contractor. 6. REQUIREMENT OF MANUFACTURERS N/A Equipment described in these specifications shall be installed in complete accordance with the manufacturer's recommendations, and, except where operational guarantees are required, proof must be given by the manufacturer that similar equipment of his make has been in satisfactory operation under comparable conditions for a period of at least two (2) years unless otherwise stated.
General 01100 - 2
7. MATERIAL APPROVAL All materials furnished by the Contractor shall be new and as indicated in the applicable specifications or shown on the drawings. The Contractor shall, if required, furnish satisfactory evidence for the approval of the Engineer, as to the kind and quality of materials. Copies of specific tests called for in the specifications shall be furnished. Before beginning work, the Contractor shall advise and shall obtain the approval of the Engineer in writing, of any optional materials allowable under the various headings, which he proposes to use. 8. STORAGE OF MATERIALS Suitable storage facilities shall be furnished by the Contractor. All materials, supplies and equipment intended for use in the work shall be stored by the Contractor to prevent damage from exposure, admixture with foreign substances, or vandalism. The Engineer will refuse to accept, or sample for testing, materials, supplies or equipment that have been improperly stored. Materials found unfit for use shall not be incorporated in the work and shall immediately be removed from the construction or storage site. 9. ERECTION SUPERVISION N/A The installation or erection of all major equipment shall be supervised by factory trained personnel representing the manufacturer of the equipment. Major equipment shall be considered as those items listed in the "Equipment Schedule" in the Bid Proposal. The Contractor shall be responsible for the notification to the equipment manufacturer or supplier to assure presence of responsible personnel to supervise installation or erection of equipment involved. 10. PROGRESS OF WORK If at any time, the materials and appliances to be used, appear to the Engineer as insufficient or improper for securing the quality of work required, or the required rate of progress, he may order the Contractor to increase his efficiency or to improve the character of his work and the Contractor shall conform to such an order; but the failure of the Engineer to demand any increase of such efficiency or any improvement shall not release the Contractor from his obligation to secure the quality of work or the rate of progress necessary to complete the work within the limits imposed by the Contract. 11. SCHEDULE OF WORK The work shall be scheduled to minimize interference with the existing traffic. It shall be the Contractor's responsibility to maintain the plant in operation at all times. The Contractor shall submit a schedule of work to the Engineer for his approval and shall up-date this schedule bi-monthly if actual progress does not follow original schedule. The Engineer shall have the right to re-schedule work where objectionable interference is indicated. 12. TOOLS N/A The Contractor shall provide one (1) kit of service tools with each piece of mechanical equipment furnished under these specifications. The tools shall be of first quality and as furnished or recommended by the manufacturer of the equipment to be serviced. 13. SALVAGED EQUIPMENT OR MATERIALS N/A In the absence of special provisions to the Contract, salvaged materials, equipment or supplies that occur are the property of the Owner and shall be cleaned and stored as directed by the Engineer. Contractor will not be required to haul salvaged materials from the site of work unless otherwise specified on the drawings.
General 01100 - 3
14. OPERATING AND MAINTENANCE INSTRUCTIONS N/A The Contractor for this project shall provide to the Owner two sets of brochures containing spare parts, data and operating and maintenance instructions on all major equipment furnished for the project. This material shall be furnished before the completion of the project and before final payment is made to the Contractor. 15. PHOTOGRAPHS The Contractor shall make provisions for photographs to be taken of any unusual conditions during the course of construction where a photographic record is desirable and required by the Engineer. The cost of this item will be provided for as an extra under a Contract Change Order. The photographs desired are to be approximately 8 x 10 inches in size. Two prints and the negative of each picture shall be delivered to the Engineer. 16. PRESERVATION OF PROPERTY The Contractor shall preserve from damage all property along the line of the work, or which is in the vicinity of or is in any way affected by the work, the removal or destruction of which is not called for by the plans. This applies to public utilities, sod, walks, trees, monuments, fences, pipe and underground structures, public streets, or highways, except natural wear and tear of streets or highways resulting from legitimate use thereof by the Contractor. Wherever such property is damaged due to the activities of the Contractor, it shall be immediately restored to its original condition by the Contractor at his own expense. In case of failure on the part of the Contractor to restore such property or make good such damage or injury, the Owner may, after 48 hours notice to the Contractor, proceed to repair, rebuild or otherwise restore such property as may be deemed necessary and the cost thereof will be deducted from any moneys due or which may become due the Contractor from receiving proper compensation for the removal, damage or replacement of any public or private property, not shown on the plans, when same is made necessary by alteration of grade or alignment, and such work is authorized by the Engineer, provided that such property has not been damaged through fault of the Contractor, his employees or agents. 17. TEMPORARY DESK SPACE N/A The Contractor shall provide the Engineer with a temporary desk and drawing board space located in a suitable area where the work is being performed. He shall provide a suitable desk, drafting board, chair, telephone service, facsimile machine, adequate lighting and means to securely lock the space during the Engineer's absence. 18. CLEANUP Attention is directed to the "Cleaning Up" provisions specified in the General Conditions of the Contract Documents, wherein it is the Contractors responsibility to "Maintain at all times work and other areas, clear of debris, trash and other objectionable matter". Contractor's schedule of work as submitted under the provisions of paragraph 11 of this section shall reflect the Contractor's planning for this work. The schedule shall indicate that a 30-day period will not be exceeded from the time of starting excavation for trenches and manholes to completion of cleanup in the scheduled work area. The Contractor shall remove surplus excavated materials and materials for construction as the work progresses, and shall render the site suitable, safe and convenient for traffic. Before final acceptance of the work, the Contractor shall clean the plant site leaving it in as good condition as originally found, and shall remove all machinery, tools, surplus materials, temporary buildings and
General 01100 - 4
other structures from the site of work. Furthermore, the sewers, manholes, inlets and other structures shall be cleared of all scaffolding, centering, surplus mortar, rubbish or dirt, and left in a clean and proper condition. 19. GUARANTY The Contractor for the work herein specified, in consideration of the prices bid and to be received therefore, guarantees that the workmanship and materials furnished under the specifications and used in said work, are first class in all respects, and are of such kind, quality and amount, that for a period of one year after the completion and final acceptance thereof by the Owner, the work shall require no repairs or renewals of defects in workmanship or materials.
If, during the said guaranty period, the improvement shall in the opinion of the Engineer or the Owner, require any repairs or renewals which in his or its judgment are necessitated by reason of settlement of foundation, structure forthwith upon notification by the Engineer or the Owner of the necessity for such repairs or renewals, make such repairs or renewals at his own cost and expense. Should the Contractor fail to make such repairs or renewals within a reasonable time after notification, the Owner may cause such work to be done, either by contract or otherwise, and the Contractor or his sureties shall pay the entire cost and expense thereof. 20. STANDARD SPECIFICATIONS Reference to ASTM, Federal, AWWA, or other standards and specifications refers to the latest issue or revision. 21. OR EQUAL CLAUSE Whenever a material or article required is specified or shown on the plans by using the name of the proprietary product or of a particular manufacturer or vendor, any material or article which will perform adequately the duties imposed by the general design will be considered equal and satisfactory providing the material or article so proposed is of equal substance and function. 22. PLANS AND SPECIFICATIONS The Contractor shall be provided four (4) sets of plans and specifications at no charge, within ten days after a Notice to Proceed is issued. Any additional sets, if requested, will be paid for by the Contractor at the current rate charged by the Engineer. 23. SANITARY FACILITIES AND REFUSE COLLECTION The Contractor shall provide his own sanitary facilities and refuse collection in accordance with all legal codes and bear all costs.
SECTION 01200 MEASUREMENT AND PAYMENT
NOTES: 1. Contractor is responsible for removal and replacement of topsoil
and temporary and permanent seeding as required. 1. General For the information and guidance of bidders, the following explanation of the bid form is made herein. The omission of reference to any item in this description shall not, however, alter the bid form or relieve the Contractor of the necessity of furnishing such as a part of the contract. The owner reserves the right to increase or decrease the scope of work during the progress of construction. Payments shall be made on the basis of work actually performed in completing each item in the contract proposal, such work including, but not limited to the furnishing of all necessary labor, materials, equipment, transportation, cleanup and all other appurtenances to complete the construction and installation as shown on the drawings and as described in the specifications. 2. Furnish and Install Front Royal Golf Club – Stormwater Management Plan Payment for construction of this project will be made at the lump sum prices or unit prices as reflected in the Bid Proposal and shall include full compensation for all work including but not limited to erosion control, excavation including rock, or any other substance or structure encountered, backfill, specified subgrade, surface asphalt, underdrains, dewatering if necessary and all other appurtenances and requirements for the parking lot improvements to be constructed per the specifications and as shown on the plans. All work to be in accordance with latest Virginia Department of Transportation standards and specifications and the Town of Front Royal Water & Sewer Standards.
Earthwork 02200 - 1
SECTION 02200 EARTHWORK
PART 1 GENERAL The work covered by this section of the specifications consists of furnishing all plant, labor, equipment and materials and in performing all operations in connection with clearing, grubbing, excavating, filling, backfilling, and grading required for work covered by these specifications. Refer to utility specifications for additional earthwork requirements. 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only. AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM) ASTM C33 1986 Concrete Aggregate ASTM C136 1984 (Rev. A) Sieve Analysis of Fine and Coarse Aggregates ASTM D698 1978 Moisture-Density Relations of Soils and Soil-
Aggregate Mixtures Using 5.5-lb (2.49-kg) Rammer and 12-in. (305-mm) Drop
ASTM D1140 1954 (R 1971) Amount of Material in Soils Finer Than the No. 200 (75-Micrometer) Sieve
ASTM D1556 1982 Density of Soil in Place by the Sand-Cone Method ASTM D1557 1978 Moisture-Density Relations of Soils and Soil-
Aggregate Mixtures Using 10-lb (4.54-kg) Rammer and 18-in. (457-mm) Drop
ASTM D2321 1983 (Rev. A) Underground Installation of Flexible Thermoplastic Sewer Pipe
ASTM D2487 1985 Classification of Soils for Engineering Purposes ASTM D2922 1981 Density of Soil and Soil-Aggregate in Place by
Nuclear Methods (Shallow Depth) ASTM D3017 1988 Water Content of Soil and Rock in Place by Nuclear
Methods (Shallow Depth) ASTM D4318 1984 Liquid Limit, Plastic Limit, and Plasticity Index of
Soils AMERICAN WATER WORKS ASSOCIATION (AWWA) AWWA C600 1987 Installation of Ductile-Iron Water Mains and Their Appurtenances ARMY CORPS OF ENGINEERS (COE) COE EM-385-1-1 1987 Safety and Health Requirements Manual FEDERAL SPECIFICATIONS (FS) FS O-F-241 (Rev. D) Fertilizer, Mixed, Commercial
Earthwork 02200 - 2
1.2 DEFINITIONS 1.2.1 Hard Materials Weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" but which usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal. 1.2.2 Rock Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1 cubic yard in volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production. Blasting is not allowed for this project. 1.2.3 Cohesive Materials Materials ASTM D2487 classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesive only when the fines have a plasticity index greater than zero. 1.2.4 Cohesionless Materials Materials ASTM D2487 classified as GW, GP, SW, and SP. Materials classified as GM and SM will be identified as cohesionless only when the fines have a plasticity index of zero. 1.2.5 Excavation Classification All excavation shall be considered unclassified. The expense of excavating, removal, hauling, dewatering and disposal of all materials including hard materials, rock materials and other materials specified herein shall be included in the lump sum contract pricing. No additional compensation will be made for excavation of hard and rock material. 1.3 SUBMITTALS 1.3.1 Design Data a. Supporting system calculations - Submit drawings and calculations by a registered professional engineer. Calculations shall include data and references used. 1.3.2 Plans N/A a. Blasting work plan - Submit before starting work. 1.3.3 Field Test Reports a. Fill and backfill test b. Select material test c. Porous fill test for capillary water barrier d. Density test
Earthwork 02200 - 3
1.4 DELIVERY, STORAGE, AND HANDLING
Perform in a manner to prevent contamination or segregation of materials.
1.5 CRITERIA FOR BIDDING
Base bids on the following criteria:
a. Surface elevations are as indicated. b. Pipes or other artificial obstructions, including those indicated, may be
encountered. c. Ground water elevations indicated by the boring log were those existing
at the time subsurface investigations were made and do not necessarily represent ground water elevation at the time of construction.
d. Material character is indicated by the boring logs. e. All solid waste disposal and any burning must comply with Department of
Environmental Quality requirements.
PART 2 PRODUCTS
2.1 SOIL MATERIALS
Free of debris, roots, wood, scrap material, vegetation, refuse, soft unsound particles, and frozen, deleterious, or objectionable materials. Unless specified otherwise, the maximum particle diameter shall be one-half the lift thickness at the intended location.
2.1.1 Common Fill
Approved, unclassified soil material with the characteristics required to compact to the soil density specified for the intended location.
2.1.2 Backfill and Fill Material
ASTM D2487, classification GW, GP, GM, SW, SP, SM, with a maximum ASTM D4318 liquid limit of 35, maximum ASTM D4318 plasticity index of 12, and a maximum of 25 percent by weight passing ASTM D1140, No. 200 sieve.
2.1.3 Topsoil
Natural, friable soil representative of productive, well-drained soils in the area, free of subsoil, stumps, rocks larger than one inch diameter, brush, weeds, toxic substances, and other material detrimental to plant growth. Amend topsoil pH range to obtain a pH of 5.5 to 7. Unless otherwise indicated on the drawings, topsoil meeting the requirements specified herein shall be stripped from areas to be excavated. Topsoil shall be stockpiled for use during the finish grading and seeding operations. If sufficient suitable topsoil is not available onsite to complete finish grading and seeding operations, then additional suitable topsoil shall be imported to the project. The cost of imported topsoil shall be borne by the Contractor. 2.1.4 Select Material ASTM D2487, classification GW, GP, SW, SP with a maximum of 10 percent by weight passing ASTM D1140, No. 200 sieve. 2.2 POROUS FILL FOR CAPILLARY WATER BARRIER ASTM C33 fine aggregate grading with a maximum of 3 percent by weight passing ASTM D1140, No. 200 sieve, or coarse aggregate Size 57, 67, or 77 and conforming to the general soil material requirements specified in paragraph entitled "Soil Materials."
Earthwork 02200 - 4
2.3 BORROW Obtain borrow materials required in excess of those furnished from excavations from approved offsite sources. 2.4 UTILITY IDENTIFICATION TAPE Aluminum foil plastic-backed tape or magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape shall be detectable by an electronic detection instrument. Provide tape in rolls, 3 inches minimum width, color-coded for the utility involved, with warning and identification imprinted in bold black letters continuously over entire tape length. Warning and identification shall read "CAUTION BURIED (INTENDED SERVICE) LINE BELOW" or similar wording. Use permanent code and letter coloring unaffected by moisture and other substances contained in trench backfill material. PART 3 EXECUTION 3.1 SURFACE PREPARATION 3.1.1 Clearing and Grubbing Unless indicated otherwise, remove trees, stumps, logs, shrubs, and brush within the clearing and grading limits. Remove stumps entirely. Grub out matted roots and roots over 2 inches in diameter to at least 18 inches below existing surface. 3.1.2 Unsuitable Material Remove vegetation, debris, organic material, decayed vegetable matter, sod, mulch, and rubbish underneath paved areas or concrete slabs. 3.2 PROTECTION 3.2.1 Protection Systems Provide shoring, bracing, and sheeting in accordance with COE EM-385-1-1. 3.2.2 Site Drainage Provide for the collection and disposal of surface and subsurface water encountered during construction. 3.2.2.1 Surface Drainage So that construction operations progress successfully, completely drain construction site during periods of construction to keep soil materials sufficiently dry. Provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified herein. 3.2.2.2 Subsurface Drainage Base on site surface and subsurface conditions, available soil, and hydrological data. Remove water by pumping or other methods to prevent softening of surfaces exposed by excavation. Use filters on dewatering devices to prevent removal of fines
Earthwork 02200 - 5
from soil. Provide erosion control at outlet of piping to prevent erosion. Operate dewatering system continuously until construction work below existing water levels is complete. After placement of initial slabs and backfill, water level may be allowed to rise, but never above one foot below the prevailing level of excavation or backfill. Relieve hydrostatic head in pervious zones below subgrade elevation in layered soils to prevent uplift. 3.2.3 Underground Utilities Location of the existing utilities indicated is approximate. The Contractor shall physically verify the location and elevation of the existing utilities indicated prior to starting construction. The Contractor shall contact "Miss Utilities" for assistance in locating existing utilities. 3.2.4 Machinery and Equipment Movement of construction machinery and equipment over pipes during construction shall be at the Contractor's risk. Repair, or remove and provide new pipe for existing or newly installed pipe that has been displaced or damaged. 3.3 EXCAVATION Excavate to contours, elevation, and dimensions indicated. Reuse excavated materials that meet the specified requirements for the material type required at the intended location. Keep excavations free from water. Excavate soil disturbed or weakened by Contractor's operations, soils softened or made unsuitable for subsequent construction due to exposure to weather. Refill with backfill and fill material and compact to 95 percent of ASTM D1557 maximum density. Unless specified otherwise, refill excavations cut below indicated depth with backfill and fill material and compact to 95 percent of ASTM D1557 maximum density.
3.3.1 Structures With Spread Footings
Ensure that footing subgrades have been inspected and approved by the Geotechnical Engineer prior to concrete placement. Fill overexcavations with concrete during foundation placement. 3.3.2 Pipe Trenches Excavate to the dimension indicated. Grade bottom of trenches to provide uniform support for each section of pipe after pipe bedding placement.
3.3.3 Hard Material and Rock Excavation
Remove hard material and rock to elevations indicated in a manner that will leave foundation material in an unshattered and solid condition. Roughen level surfaces and cut sloped surfaces into benches for bond with concrete. Protect shale from conditions causing decomposition along joints or cleavage planes and other types of erosion. Areas to receive structural foundations or slabs that are overexcavated by machinery or blasting shall be backfilled with approved materials as specified herein for the intended location. Shattered rock and hard material are considered excavated materials.
3.4 FILLING AND BACKFILLING
Fill and backfill to contours, elevations, and dimensions indicated. Compact each lift before placing overlaying lift.
Earthwork 02200 - 6
3.4.1 Common Fill Placement
Provide for general site. Place in 6-inch lifts. Compact areas not accessible to rollers or compactors with mechanical hand tampers. Aerate material excessively moistened by rain to a satisfactory moisture content. Finish to a smooth surface by blading, rolling with a smooth roller, or both.
3.4.2 Backfill and Fill Material Placement Provide for paved areas and under concrete slabs, except where select material is provided. Place in 6-inch lifts. Place backfill material adjacent to structures as the structural elements are completed and accepted. Backfill against concrete only when approved. Place and compact material to avoid loading upon or against the structure.
3.4.3 Select Material Placement
Provide under porous fill of structures. Place in 6-inch lifts. Backfill adjacent to structures shall be placed as structural elements are completed and accepted. Backfill against concrete only when approved. Place and compact material to avoid loading upon or against structure. 3.4.4 Porous Fill Placement Provide under floor slab on a compacted subgrade. Place in 4-inch lifts. 3.4.5 Trench Backfilling Backfill as rapidly as construction, testing, and acceptance of work permits. Place and compact backfill under structures and paved areas in 6 inch lifts to top of trench and in 6-inch lifts to one foot over pipe outside structures and paved areas. Over excavations shall be backfilled with bedding material. 3.4.5.1 Bedding Requirements Except as specified otherwise in the individual piping section, provide bedding for buried piping in accordance with AWWA C600, Type 4, except as specified herein. Backfill to top of pipe shall be compacted to 95 percent of ASTM D698 maximum density. Plastic piping shall have bedding to spring line of pipe. Provide ASTM D2321 materials as follows: a. Class I: Angular, 6 to 40 mm (0.25 to 1.5 inches), graded stone, including a number of fill materials that have regional significance such as coral, slag, cinders, crushed stone, and crushed shells. b. Class II: Coarse sands and gravels with maximum particle size of 40 mm (1.5 inches), including various graded sands and gravels containing small percentages of fines, generally granular and noncohesive, either wet or dry. Soil Types GW, GP, SW, and SP are included in this class as specified in ASTM D2487. 3.4.5.2 Utility Identification Tape Placement Provide buried utility lines with utility identification tape. Bury tape 12 inches below finished grade, except under pavements and slabs, bury tape 6 inches below top of subgrade.
Earthwork 02200 - 7
3.5 COMPACTION Expressed as a percentage of maximum density. Determine in-place density of existing subgrade; if required density exists, no compaction of existing subgrade will be required. 3.5.1 General Site Compact underneath areas designated for vegetation and areas outside the 5-foot line of the structure to 85 percent of ASTM D1557. 3.5.2 Structures, Spread Footings, and Concrete Slabs Compact top 12 inches of subgrades to 95 percent of ASTM D1557. Compact select material to 95 percent of ASTM D1557. 3.5.3 Porous Fill for Capillary Water Barrier Compact with two passes of a hand-operated, plate type vibratory compactor. Compact areas within 5 feet of structures to 90 percent of ASTM D1557. 3.5.4 Adjacent Area Compact areas within 5 feet of structures to 90 percent of ASTM D1557. 3.5.5 Paved Areas Compact top 12 inches of subgrades to 95 percent of ASTM D1557. Compact fill and backfill materials to 95 percent of ASTM D1557. 3.6 FINISH OPERATIONS 3.6.1 Grading Finish grades as indicated within one-tenth of one foot. Grade areas to drain water away from structures. For existing grades that will remain but which were disturbed by Contractor's operations, grade as directed. 3.6.2 Seed Scarify existing subgrade. Provide 4 inches of topsoil for newly graded finish earth surfaces and areas disturbed by the Contractor. Topsoil shall meet the requirements of topsoil as defined herein before. Seed shall be as indicated on the drawings. Provide seed at 5 pounds per 1000 square feet. Provide FS O-F-241, Type I, Class 2, 10-10-10 analysis fertilizer at 25 pounds per 1000 square feet. Provide commercial agricultural limestone of 94-80-14 analysis at 70 pounds per 1000 square feet. Provide mulch and water to establish an acceptable stand of grass. 3.6.3 Protection of Surfaces Protect newly graded areas from traffic, erosion, and settlements that may occur. Repair or reestablish damaged grades, elevations, or slopes.
Earthwork 02200 - 8
3.7 DISPOSITION OF SURPLUS MATERIAL Waste of site surplus or other soil material not required or suitable for filling or backfilling, shall be disposed of offsite by the Contractor at his expense. Brush, stumps, roots, and timber shall be disposed of offsite by the Contractor at his expense. Burning will be allowed at the approval of local authorities. The contractor shall obtain all permits and pay fees relating to burning. Refuse shall be disposed of offsite in a lawful manner.
3.8 FIELD QUALITY CONTROL 3.8.1 Sampling Take the number and size of samples required to perform the following tests. All materials testing shall be performed by project Geotechnical Engineer at the contractor's expense. 3.8.2 Testing Perform one of each of the following tests for each material used. Provide additional tests for each source change. 3.8.2.1 Fill and Backfill Material Testing Test fill and backfill material in accordance with ASTM C136 for conformance to ASTM D2487 gradation limits; ASTM D1140 for material finer than the No. 200 sieve; ASTM D4318 for liquid limit and for plastic limit; ASTM D698 or ASTM D1557 for moisture density relations, as applicable. 3.8.2.2 Select Material Testing Test select material in accordance with ASTM C136 for conformance to ASTM D2487 gradation limits; ASTM D1140 for material finer than the No. 200 sieve; ASTM D698 or ASTM D1557 for moisture density relations, as applicable. 3.8.2.3 Porous Fill Testing Test porous fill in accordance with ASTM C136 for conformance to gradation specified in ASTM C33. 3.8.2.4 Density Tests Onsite density testing shall be performed by the project Geotechnical Engineer at the owner's expense. If it is determined that insufficient density has been obtained, or if materials have been incorrectly placed; the cost of retesting and inspections shall be at the contractor's expense. Test density in accordance with ASTM D1556, or ASTM D2922 and ASTM D3017. When ASTM D2922 and ASTM D3017 density tests are used, verify density test results by performing an ASTM D1556 density test at a location already ASTM D2922 and ASTM D3017 tested as specified herein. Perform an ASTM D1556 density test at the start of the job, and for every 10 ASTM D2922 and ASTM D3017 density tests thereafter. Test each lift at randomly selected locations every 1000 square feet of existing grade in fills for structures and concrete slabs, and every 2500 square feet for other fill areas and every 2000 square feet of subgrade in cut.
Cast-In-Place Concrete
03300 - 1
SECTION 03300
CAST-IN-PLACE CONCRETE
PART 1 GENERAL
1.1 SUMMARY
The work described in this section includes plant, labor and materials for providing cast in place
concrete for buildings, structures and sitework. The contractor shall provide all miscellaneous materials, equipment
and labor to complete the concrete construction.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The
publications are referred to in the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO M182 1960 (Rev. 1974) Burlap Cloth Made From Jute or Kenaf
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 211.1 1981 Selecting Proportions for Normal, Heavyweight, and Mass Concrete
ACI 301 1984 Structural Concrete for Buildings
ACI 302.1R 1980 Guide for Concrete Floor and Slab Construction
ACI 304 1973 (Rev. 1983) Measuring, Mixing, Transporting, and Placing Concrete
ACI 305R 1982 Hot Weather Concreting
ACI 306R 1978 Cold Weather Concreting
ACI 315 1980 Details and Detailing of Concrete Reinforcement
ACI 347 1978 (Rev. 1984) Concrete Formwork
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
ASTM A82 1979 Cold-Drawn Steel Wire for Concrete Reinforcement
ASTM A185 1979 Welded Steel Wire Fabric for Concrete Reinforcement
ASTM A496 1978 Deformed Steel Wire for Concrete Reinforcement
ASTM A497 1979 Welded Deformed Steel Wire Fabric for Concrete Reinforcement
ASTM A615 1982 Deformed and Plain Billet-Steel Bars for Concrete Reinforcement
ASTM C31 1984 Making and Curing Concrete Test Specimens in the Field
ASTM C33 1984 Concrete Aggregates
ASTM C39 1983 (Rev. B) Compressive Strength of Cylindrical Concrete Specimens
ASTM C42 1984 (Rev. A) Obtaining and Testing Drilled Cores and Sawed Beams of Concrete
ASTM C94 1983 Ready-Mixed Concrete
ASTM C143 1978 Slump of Portland Cement Concrete
ASTM C150 1984 Portland Cement
Cast-In-Place Concrete
03300 - 2
ASTM C171 1969 (R 1980) Sheet Materials for Curing Concrete
ASTM C172 1982 Sampling Freshly Mixed Concrete
ASTM C173 1978 Air Content of Freshly Mixed Concrete by the Volumetric Method
ASTM C231 1982 Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260 1977 Air-Entraining Admixtures for Concrete
ASTM C309 1981 Liquid Membrane-Forming Compounds for Curing Concrete
ASTM C330 1982 (Rev. A) Lightweight Aggregates for Structural Concrete
ASTM C494 1982 Chemical Admixtures for Concrete
ASTM C595 1983 (Rev. A) Blended Hydraulic Cements
ASTM C618 1984 (Rev. A) Fly Ash and Raw or Calcined Natural Pozzolan for Use as a Mineral
Admixture in Portland Cement Concrete
ASTM C881 1978 (R 1983) Epoxy-Resin-Base Bonding Systems for Concrete
ASTM C920 1979 Elastomeric Joint Sealants
ASTM C989 1982 Ground Iron Blast-Furnace Slag for Use in Concrete and Mortars
ASTM D1190 1974 (R 1980) Concrete Joint Sealer, Hot-Poured Elastic Type
ASTM D1751 1983 Preformed Expansion Joint Filler for Concrete Paving and Structural
Construction (Nonextruding and Resilient Bituminous Types)
ASTM D1752 1984 Preformed Sponge Rubber and Cork Expansion Joint Fillers for Concrete
Paving and Structural Construction
ASTM D1850 1974 (R 1979) Concrete Joint Sealer, Cold-Application Type
ASTM D4397 1984 Polyethylene Sheeting for Construction, Industrial and Agricultural
Application
AMERICAN WELDING SOCIETY, INC. (AWS)
AWS D1.4 1979 Structural Welding Code - Reinforcing Steel
ARMY CORPS OF ENGINEERS (COE)
COE CRD-C-572 1974 Specifications for Polyvinylchloride Waterstop
COE CRD-C-621 1983 Handbook for Concrete and Cement, Specification for Nonshrink Grout,
Volume II (1949 Edition)
U.S. DEPARTMENT OF COMMERCE PRODUCT STANDARDS (PS)
PS-1 1983 Construction and Industrial Plywood
1.3 SUBMITTALS
Submit the following to the Engineer for approval.
1.3.1 Design Data
a. Contractor mix design
Cast-In-Place Concrete
03300 - 3
Thirty days minimum prior to concrete placement, submit a mix design for each
strength and type of concrete. Furnish a complete list of materials including type; brand; source and amount of
cement, fly ash, pozzolan, ground slag, and admixtures; applicable reference specifications; and copies of test reports
showing that the mix has been successfully tested to produce concrete with the properties specified and will be
suitable for the job conditions. Provide fly ash and pozzolan test results performed within 6 months of submittal date.
Obtain approval before concrete placement. An identical concrete mix design previously approved within the past 12
months by the Virginia Department of Transportation, may be used without further approval, provided that copies of
the previous approval and fly ash and pozzolan test results performed within 6 months of submittal date are
submitted. Obtain acknowledgment of receipt prior to concrete placement. Submit additional data regarding concrete
aggregates if the source of aggregate changes.
1.3.2 Manufacturer's Catalog Data
a. Waterstops
b. Materials for curing concrete
c. Joint sealant
d. Joint filler
e. Vapor barrier
f. Epoxy bonding agents
1.3.3 Drawings
a. Reinforcing steel
b. Formwork
Reproductions of contract drawings are unacceptable.
1.3.3.1 Reinforcing Steel
ACI 315. Indicate bending diagrams, assembly diagrams, splicing and laps of
bars, shapes, dimensions, and details of bar reinforcing, accessories, and concrete cover. Do not scale dimensions
from structural drawings to determine lengths of reinforcing rods.
1.3.4 Certificates of Compliance
a. Aggregates
b. Admixtures
c. Reinforcement
d. Cement
e. Fly ash
f. Pozzolan
g. Ground slag
Cast-In-Place Concrete
03300 - 4
1.4 MODIFICATION OF REFERENCES
In the ACI publications referred to herein, the advisory provisions shall be considered to be
mandatory, as though the word "shall" has been substituted for "should" wherever it appears; reference to the
"Building Official," the "Structural Engineer," and the "Architect/Engineer" shall be interpreted to mean the Project
Engineer.
1.5 DELIVERY
Do not deliver concrete until vapor barrier, forms, reinforcement, embedded items, and chamfer
strips are in place and ready for concrete placement.
1.6 STORAGE
ACI 301 for job site storage of concrete aggregates. Store reinforcement of different sizes and
shapes in separate piles or racks raised above the ground to avoid excessive rusting. Protect from contaminants such
as grease, oil, and dirt. Provide for accurate identification after bundles are broken and tags removed.
PART 2 PRODUCTS
2.1 CONCRETE
2.1.1 Contractor-Furnished Mix Design
ACI 211.1 and ACI 301 except as otherwise specified. Concrete shall have a 28-day
compressive strength of 3000 psi for sitework and 4000 psi for all building construction unless indicated or specified
otherwise. Provide ASTM C33 aggregate Size No. 57, 67. Provide 5 to 8 percent air entrainment for concrete
exposed to the weather. Accomplish air entrainment using an air-entraining admixture. The maximum chloride
content shall not exceed one percent. Maximum water-cement ratio for air-entrained concrete shall be 0.49 for 3000
psi mix and 0.45 for 4000 psi mix. Air entrained concrete with the minimum 28 day compressive strength indicated
prepared in accordance with the Virginia Department of Transportation "Road and Bridge Specifications" may meet
the requirements of this specification subject to the Engineer's approval.
2.1.1.1 Slump Requirements
The maximum allowable slump may be increased to 5 inches for concrete
utilizing either fly ash, pozzolan, or ground slag for 20 to 25 percent, minimum, of the total cementitious material.
Element Minimum Maximum
Walls, columns, and grade beams 2 4
Floors, exterior slabs, pavement, walks, curbs and other
building construction 1 3
Cast-In-Place Concrete
03300 - 5
2.2 MATERIALS
2.2.1 Cement
ASTM C150, Type I or II or ASTM C595, Type IP(MS) or IS (MS) blended cement
except as modified herein. The blended cement shall consist of a mixture of ASTM C150 cement and one of the
following materials: ASTM C618 pozzolan or fly ash, or ASTM C989 ground iron blast furnace slag. The pozzolan
or fly ash content shall not exceed 25 percent by weight of the total cementitious material and the ground iron blast
furnace slag shall not exceed 50 percent by weight of total cementitious material. For exposed concrete, use one
manufacturer for each type of cement, ground slag, fly ash, and pozzolan.
2.2.1.1 Fly Ash and Pozzolan
ASTM C618, Type N, F, or C, except that the maximum allowable loss on
ignition shall be 6 percent for Types N and F. Add with cement.
2.2.1.2 Ground Iron Blast-Furnace Slag
ASTM C989, Grade 100 or 120.
2.2.2 Water
Water shall be fresh, clean, and potable.
2.2.3 Aggregates
ASTM C33, except as modified herein. Obtain aggregates for exposed concrete surfaces
from one source. Aggregates shall not contain any substance which may be deleteriously reactive with the alkalies in
the cement.
2.2.4 Nonshrink Grout
COE CRD-C-621.
2.2.5 Admixtures
2.2.5.1 Air-Entraining ASTM C260
2.2.5.2 Accelerating ASTM C494, Type C
2.2.5.3 Retarding ASTM C494, Type B, D, or G
2.2.5.4 Water Reducing ASTM C494, Type A, E, or F
Cast-In-Place Concrete
03300 - 6
2.2.6 Materials for Forms
Provide wood, plywood, or steel. Use plywood or steel forms where a smooth form
finish is required. Lumber shall be square edged or tongue-and-groove boards, free of raised grain, knotholes, or
other surface defects. Plywood: PS-1, B-B concrete form panels or better. Steel form surfaces shall not contain
irregularities, dents, or sags.
2.2.7 Reinforcement
2.2.7.1 Reinforcing Bars
ACI 301 unless otherwise specified. ASTM A615 including supplementary
requirement S1 with the bars marked.
2.2.7.2 Welded Wire Fabric
ASTM A185 or ASTM A497. Provide flat sheets of welded wire fabric for
slabs and toppings.
2.2.7.3 Wire
ASTM A82 or ASTM A496.
2.2.8 Vapor Barrier
ASTM D4397 polyethylene sheeting, minimum 6 mil thickness.
2.2.9 Polyvinylchloride Waterstops
Provide waterstop materials as indicated.
2.2.10 Materials for Curing Concrete
2.2.10.1 Impervious Sheeting
ASTM C171; waterproof paper, clear or white polyethylene sheeting,
or polyethylene-coated burlap.
2.2.10.2 Previous Sheeting
AASHTO M182.
2.2.10.3 Liquid Membrane-Forming Compound
ASTM C309, white-pigmented, Type 2, Class B.
Cast-In-Place Concrete
03300 - 7
2.2.11 Liquid Chemical Sealer-Hardener Compound
Compound shall be magnesium fluosilicate which when mixed with water seals and
hardens the surface of the concrete. Do not use on exterior slabs exposed to freezing conditions. Compound shall not
reduce the adhesion of resilient flooring, tile, paint, roofing, waterproofing, or other material applied to concrete.
2.2.12 Expansion/Contraction Joint Filler
ASTM D1751 or ASTM D1752, 1/2-inch thick, unless otherwise indicated.
2.2.13 Joint Sealants
2.2.13.1 Horizontal Surfaces (3 Percent Slope, Maximum)
a. Outside Buildings: ASTM D1190.
b. Inside Buildings: ASTM D1190 or ASTM D1850.
2.2.13.2 Vertical Surfaces (Greater Than 3 Percent Slope)
ASTM C920, Type M, Grade NS, Class 25, Use T.
2.2.14 Epoxy Bonding Compound
ASTM C881, Type II, Grade 1, Class A (if placement temperature is below 40 degrees
F); Class B (if placement temperature is between 40 and 60 degrees F); or Class C (if placement temperature is above
60 degrees F). Provide Grade 1 or 2 for horizontal surfaces and Grade 3 for vertical surfaces.
PART 3 EXECUTION
3.1 FORMS
ACI 301. Provide forms, shoring, and scaffolding for concrete placement unless indicated or
specified otherwise. Concrete for footings may be placed in excavations without forms upon inspection and approval
by the Engineer. Excavation width shall be a minimum of 4 inches greater than indicated. Set forms mortar-tight and
true to line and grade. Chamfer above grade exposed joints, edges, and external corners of concrete 0.75 inch unless
otherwise indicated. Provide formwork with clean-out openings to permit inspection and removal of debris. Forms
submerged in water shall be watertight.
3.1.1 Coating
Before concrete placement, coat the contact surfaces of forms with a nonstaining mineral
oil, nonstaining form coating compound, or two coats of nitrocellulose lacquer. Do not use mineral oil on forms for
surfaces to which adhesive, paint, or other finish material is to be applied.
Cast-In-Place Concrete
03300 - 8
3.1.2 Removal of Forms
Prevent concrete damage during form removal. After placing concrete, forms shall
remain in place for the following minimum time periods, not necessarily consecutive, where minimum temperatures
specified in paragraph entitled "Curing Periods and Minimum Temperatures" are maintained adjacent to the concrete
and formwork. The minimum time period for removal of forms shall govern where it exceeds the minimum specified
curing period. Where the formwork for one element supports the formwork for another element, the greater time
period shall apply to both elements.
Time Period
Element (Days Minimum)
Walls, columns, and girders, and slabs on grade 1
Joist, beam, or girder soffits: 14
3.1.2.1 Special Requirements for Reduced Time Period
Forms may be removed earlier than specified if ASTM C39 test results of field-
cured samples from a representative portion of the structure indicate that the concrete has reached 85 percent
(minimum) of the design strength.
3.1.3 Reshoring
Reshore concrete elements where forms are removed prior to the specified time period.
Do not permit elements to deflect or accept loads during form stripping or reshoring. Where columns, walls, or other
load-bearing concrete members are placed in advance of other framing and forms are needed for future use, forms
may be stripped after 2 days if loads are not applied to load-bearing members, and if members are cured as specified
in paragraph entitled "Curing and Protection." After forms are removed, slabs and beams over 10 feet in span and
cantilevers over 4 feet shall be reshored for the remainder of the specified time period in paragraph entitled "Removal
of Forms." Perform reshoring operations to prevent subjecting concrete members to overloads, eccentric loading, or
reverse bending. Reshoring elements shall have the same load-carrying capabilities as original shoring and shall be
spaced similar to original shoring. Firmly secure and brace reshoring elements to provide solid bearing and support.
3.2 PLACING REINFORCEMENT AND MISCELLANEOUS MATERIALS
ACI 301. Provide bars, wire fabric, wire ties, supports, and other devices necessary to install and
secure reinforcement. Reinforcement shall not contain rust, scale, oil, grease, clay, and foreign substances that would
reduce the bond. Rusting of reinforcement is a basis of rejection if the effective cross sectional area or the nominal
weight per foot of the reinforcement has been reduced to less than specified in paragraph entitled "Reinforcing Bars."
Remove loose rust prior to placing steel. Tack welding is prohibited.
Cast-In-Place Concrete
03300 - 9
3.2.1 Vapor Barrier Placement
Provide beneath the on-grade concrete floor slab. Use the greatest widths and lengths
practicable to eliminate joints wherever possible. Lap joints a minimum of 12 inches. Remove torn, punctured, or
damaged vapor barrier material and provide with new vapor barrier prior to placing concrete. Concrete placement
shall not damage vapor barrier material.
3.2.2 Tolerances
Place reinforcement and secure with galvanized or noncorrodible chairs, spacers, or metal
hangers. Use concrete or other noncorrodible material for supporting reinforcement on the ground.
3.2.3 Splicing
AWS D1.4, except as otherwise indicated or specified. Splices shall be approved prior to
use. Do not splice at points of maximum stress. Overlap welded wire fabric the spacing of the cross wires, plus 2
inches.
3.2.4 Cover
ACI 301 for minimum coverage, unless otherwise indicated.
3.2.5 Setting Miscellaneous Material
Place and secure anchors and bolts, pipe sleeves, conduits, and other such items in
position before concrete placement. Plumb anchor bolts and check location and elevation. Temporarily fill voids in
sleeves with readily removable material to prevent the entry of concrete.
3.2.6 Construction Joints
Provide as detailed on drawings.
3.2.7 Expansion Joints and Contraction Joints - for Pavement Slabs
Provide expansion joint at edges of interior floor slabs on grade abutting vertical surfaces,
and as indicated. Make expansion joints 1/2-inch wide unless indicated otherwise. Fill expansion joints not exposed
to weather with preformed joint filler material. Completely fill joints exposed to weather with joint filler material and
joint sealant. Do not extend reinforcement or other embedded metal items bonded to the concrete through any
expansion joint unless an expansion sleeve is used. Provide contraction joints, either formed or saw cut or cut with a
jointing tool, to the indicated depth after the surface has been finished. Sawed joints shall be completed within 4 to
12 hours after concrete placement. Protect joints from intrusion of foreign matter.
Cast-In-Place Concrete
03300 - 10
3.2.8 Form Ties and Accessories
The use of wire alone is prohibited. Form ties and accessories shall not reduce the
effective cover of the reinforcement.
3.3 MEASURING, MIXING, TRANSPORTING, AND PLACING CONCRETE
ASTM C94, ACI 301, ACI 302.1R, and ACI 304, except as modified herein. Provide mandatory
batch ticket information for each load of ready mix concrete.
3.3.1 Measuring
Make moisture, weight, and air determinations at intervals as specified in paragraph
entitled "Sampling and Testing." Allowable tolerances for measuring cement and water shall be 1 percent; for
aggregates, 2 percent; and for admixtures, 3 percent.
3.3.2 Mixing
ASTM C94 and ACI 301. Machine mix concrete. Begin mixing within 30 minutes after
the cement has been added to the aggregates. Place concrete within 90 minutes of either addition of mixing water to
cement and aggregates or addition of cement to aggregates if the air temperature is less than 85 degrees F. Reduce
mixing time and place concrete within 60 minutes if the air temperature is greater than 85 degrees F. Additional
water may be added, provided that both the specified maximum slump and water-cement ratio are not exceeded. If
the entrained air content falls below the specified limit, add a sufficient quantity of admixture to bring the entrained
air content within the specified limits. Dissolve admixtures in the mixing water and mix in the drum to uniformly
distribute the admixture throughout the batch.
3.3.3 Transporting
Transport concrete from the mixer to the forms as rapidly as practicable. Prevent
segregation or loss of ingredients. Clean transporting equipment thoroughly before each batch. Do not use aluminum
pipe or chutes. Remove concrete which has segregated in transporting and dispose of as directed.
3.3.4 Placing
Place concrete as soon as practicable after the forms and the reinforcement have been
inspected and approved. Do not place concrete when weather conditions prevent proper placement and consolidation;
in uncovered areas during periods of precipitation; or in standing water. Prior to placing concrete, remove dirt,
construction debris, water, snow, and ice from within the forms. Deposit concrete as close as practicable to the final
position in the forms. Do not exceed a free vertical drop of 3 feet from the point of discharge. Place concrete in one
continuous operation from one end of the structure towards the other. Position grade stakes on 10-foot centers
maximum in each direction when pouring interior slabs and on 20-foot centers maximum for exterior slabs.
Cast-In-Place Concrete
03300 - 11
3.3.4.1 Vibration
ACI 301. Furnish a spare vibrator on the job site whenever concrete is placed.
Consolidate concrete slabs greater than 4 inches in depth with high frequency, internal, mechanical vibrating
equipment supplemented by hand spading and tamping. Consolidate concrete slabs 4 inches or less in depth by wood
tampers, spading, and settling with a heavy leveling straight edge. Operate vibrators with vibratory element
submerged in the concrete, with a minimum frequency of not less than 6000 impulses per minute when submerged.
Do not use vibrators to transport the concrete in the forms. Insert and withdraw vibrators approximately 18 inches
apart. Penetrate the previously placed lift with the vibrator when more than one lift is required. Place concrete in 18-
inch maximum vertical lifts. External vibrators shall be used on the exterior surface of the forms when internal
vibrators do not provide adequate consolidation of the concrete.
3.3.4.2 Application of Epoxy Bonding Compound
Apply a thin coat of compound to dry, clean surfaces. Scrub compound into the
surface with a stiff-bristle brush. Place concrete while compound is stringy. Do not permit compound to harden prior
to concrete placement. Follow manufacturer's instructions regarding safety and health precautions when working
with epoxy-resins.
3.3.5 Cold Weather
ACI 306R. Provide 50 degrees F minimum concrete temperature. Obtain approval prior
to placing concrete when the ambient temperature is below 40 degrees F or when concrete is likely to be subjected to
freezing temperatures within 24 hours. Cover concrete and provide sufficient heat to maintain 50 degrees F minimum
adjacent to both the formwork and the structure while curing. Limit the rate of cooling to 5 degrees F in any one hour
and 50 degrees F per 24 hours after heat application.
3.3.6 Hot Weather
ACI 305R. Provide and maintain required concrete temperature using Figure 2.1.5 in
ACI 305R to prevent the evaporation rate from exceeding 0.2 pound of water per square foot of exposed concrete per
hour. Cool ingredients before mixing or use other suitable means to control concrete temperature and prevent rapid
drying of newly placed concrete. Shade the fresh concrete as soon as possible after placing. Start curing when the
surface of the fresh concrete is sufficiently hard to permit curing without damage. Provide water hoses, pipes,
spraying equipment, and water hauling equipment (where worksite is remote to water source) to maintain a moist
concrete surface throughout the curing period. Provide burlap cover or other suitable, permeable material with fog
spray or continuous wetting of the concrete when weather conditions prevent the use of either liquid membrane curing
compound or impervious sheets. For vertical surfaces, protect forms from direct sunlight and add water to top of
structure once concrete is set.
Cast-In-Place Concrete
03300 - 12
3.4 SURFACE FINISHES (EXCEPT FLOOR, SLAB, AND PAVEMENT FINISHES)
3.4.1 Provide finish on walls as follows:
LOCATION FINISH
Top of Walls Match adjacent finishes
Buried Walls As-Cast Rough Form
Submerged Walls (below low water level) As-Cast Rough Form
Utility Vault Interior Walls As-Cast Rough Form
Wet Well Interior Walls As-Cast Rough Form
Exposed Walls, (retaining walls, foundation walls,
non-submerged treatment unit walls*, interior pipe
trenches, interior concrete walls) Rubbed Finish
3.4.2 Defects (all walls)
Repair formed surfaces by removing minor honeycombs, pits greater than one square
inch surface area or 0.25 inch maximum depth, or otherwise defective areas. Provide edges perpendicular to the
surface and patch with nonshrink grout. Patch tie holes and defects when the forms are removed. Concrete with
extensive honeycomb (including exposed steel reinforcement, cold joints, entrapped debris, separated aggregate, or
other defects) which affect the serviceability or structural strength will be rejected, unless correction of defects is
approved. Obtain approval of corrective action prior to repair. The surface of the concrete shall not vary more than
the allowable tolerances of ACI 347. Exposed surfaces shall be uniform in appearance and finished to a smooth form
finish unless otherwise specified.
3.4.3 Not Against Forms (Top of Walls)
Surfaces not otherwise specified shall be finished with wood floats to even surfaces.
Finish shall match adjacent finishes.
3.3.4. Formed Surfaces
3.4.4.1 As-Cast Rough Form
Remove fins and other projections exceeding 0.25 inch in height; level abrupt
irregularities.
3.4.4.2 As-Cast Smooth Form
Form facing material shall produce a smooth, hard, uniform texture on the concrete.
Remove fins and other projections.
Cast-In-Place Concrete
03300 - 13
3.4.4 Rubbed Finish
Provide rubbed finish as follows:
a. Smooth Rubbed: Provide on newly hardened concrete within 24 hours
following form removal. Wet surfaces and rub with an abrasive tool to produce uniform color and texture. Use only
the cement paste drawn from the concrete rubbing process.
b. Grout Cleaned: Finishing operations shall not begin until adjacent surfaces to
be cleaned are completed and accessible. Cleaning as the work progresses shall not be permitted. Mix one part
cement and 1.5 parts fine sand with sufficient water to produce a grout with the consistency of thick paint. Substitute
white cement for a part of the gray cement in order to produce a color matching the color of the surrounding concrete,
as determined by a trial patch. Wet the surface of the concrete sufficiently to prevent absorption of water from the
grout. Apply the grout uniformly with brushes or spray gun. Immediately after applying the grout, scrub the surface
vigorously with a cork float or stone to coat the surface and fill air bubbles and holes. Remove excess grout while
still plastic by working the surface with a rubber float, sack, or other approved method. When dry, rub the surface
vigorously with clean burlap. Keep damp for 36 hours minimum after final rubbing.
c. Cork Floated: Mix one part portland cement and one part fine sand with
sufficient water to produce a stiff mortar. Dampen the surface and apply mortar with firm rubber float or trowel,
filling surface voids. Compress mortar into voids using a slow-speed grinder or stone. If the mortar surface dries too
rapidly to permit proper compaction and finishing, apply a small amount of water with a fog sprayer. Produce the
final texture with a cork float using a swirling motion.
3.5 FLOOR, SLAB, & PAVEMENT FINISHES & MISCELLANEOUS CONSTRUCTION
ACI 302.1R, unless otherwise specified. Slope floors uniformly to drains where drains are
provided. Provide interior floor slabs with a steel troweled finish unless an alternate finish is specified. After
trowelling and moist curing are completed, apply a liquid chemical sealer-hardener compound on interior floor slabs
that do not receive floor covering.
3.5.1 Finish
Place, consolidate, and immediately strike off concrete to obtain proper contour, grade,
and elevation before bleedwater appears. Permit concrete to attain a set sufficient for floating and supporting the
weight of the finisher and equipment. If bleedwater is present prior to floating the surface, drag the excess water off
or remove by absorption with porous materials. Do not use dry cement to absorb bleedwater.
3.5.1.1 Floated
Provide for machinery pads, floors of process treatment units, and other exterior
slabs where not otherwise specified. Float the surface by hand with a wood or magnesium float, or use a power-
driven float. Floating of any one area shall be the minimum necessary to produce an even finish, level within 1/4 inch
Cast-In-Place Concrete
03300 - 14
in 10 feet for exterior work and process treatment unit floors, and level within 1/8 inch in 10 feet for interior work
where floor drains are not provided.
3.5.1.2 Steel Troweled
First, provide a floated finish. When slab attains a proper set, trowel to a
smooth, hard, dense finish. Finished surfaces shall be free of troweled marks, uniform in texture, and a true plane,
flat within 0.01 foot (approximately 1/8 inch) in 10 feet. Hand-finish portions of the slab not accessible to power
finishing equipment (e.g., edges, corners) to match the remainder of the slab. Power trowel once and finally hand
trowel where a finished floor covering (e.g., tile, carpet) is specified. Power trowel twice and finally hand trowel for
exposed concrete floors. [Power trowel three times and finally hand trowel to provide an extra dense wearing surface
as indicated.
3.5.1.3 Broomed
Provide for exterior walks, platforms, patios, and ramps, unless otherwise
indicated. Provide a floated finish, then finish with a flexible bristle broom. Permit surface to harden sufficiently to
retain the scoring or ridges. Broom transverse to traffic or at right angles to the slope of the slab.
3.5.1.4 Pavement
Screed the concrete with a template advanced with a combined longitudinal and
crosswise motion. Maintain a slight surplus of concrete ahead of the template. After screeding, float the concrete
longitudinally. Use a straight edge to check slope and flatness; correct and refloat as necessary. Obtain final finish
by a burlap drag. Drag a strip of clean, wet burlap from 3-to 10-feet wide and 2-feet longer than the pavement width
across the slab. Produce a fine, granular, sandy textured surface without disfiguring marks. Round edges and joints
with an edger having a radius of 1/8 inch.
3.5.2 Concrete Walks
Provide 4 inches thick minimum. Provide contraction joints spaced every 5 linear feet
unless otherwise indicated. Cut contraction joints 3/4-inch deep with a jointing tool after the surface has been
finished. Provide 0.5 inch thick transverse expansion joints at changes in direction where sidewalk abuts curb, steps,
rigid pavement, or other similar structures; space expansion joints every 50 feet maximum apart. Provide walks with
a broomed finish. Provide a transverse slope as indicated. Limit variation in cross section to 1/4 inch in 5 feet.
Provide turned-down-edge and medians as indicated. Provide jointing and finish as
specified for concrete walks.
3.5.3 Pits and Trenches
Provide as indicated.
Cast-In-Place Concrete
03300 - 15
3.5.4 Curbs and Gutters
Provide contraction joints spaced every 10 feet maximum unless otherwise indicated.
Cut contraction joints 3/4-inch deep with a jointing tool after the surface has been finished. Provide expansion joints
1/2-inch thick and spaced every 100 feet maximum unless otherwise indicated. Provide a pavement finish.
3.5.5 Splash Blocks
Provide at outlets of downspouts emptying at grade. Splash blocks may be precast
concrete, and shall be 24 inches long, 12 inches wide, and 6 inches thick, unless otherwise indicated, with smooth-
finished countersunk dishes sloped to drain away from the building.
3.6 CURING AND PROTECTION
ACI 301 unless otherwise specified. Begin curing immediately following form removal. Protect
concrete from injurious action by sun, rain, flowing water, frost, mechanical injury, tire marks, and oil stains. Do not
allow concrete to dry out from time of placement until the expiration of the specified curing period. Do not use
membrane-forming compound on surfaces where appearance would be objectionable, on any surface to be painted,
where coverings are to be bonded to the concrete, or on concrete to which other concrete is to be bonded. If forms are
removed prior to the expiration of the curing period, provide another curing procedure specified herein for the
remaining portion of the curing period. Provide moist curing for those areas receiving liquid chemical sealer-
hardener.
3.6.1 Moist Curing
Provide for the removal of water without erosion or damage to the structure.
3.6.1.1 Ponding or Immersion
Continually immerse the concrete throughout the curing period. Water shall not
be more than 20 degrees F less than the temperature of the concrete. For temperatures between 40 and 50 degrees F,
increase the curing period by 50 percent.
3.6.1.2 Fog Spraying or Sprinkling
Provide uniform and continuous application of water throughout the curing
period. For temperatures between 40 and 50 degrees F, increase the curing period by 50 percent.
3.6.1.3 Pervious Sheeting
Completely cover surface and edges of the concrete with two thicknesses of wet
sheeting. Overlap sheeting 6 inches over adjacent sheeting. Sheeting shall be at least as long as the width of the
surface to be cured. During application, do not drag the sheeting over the finished concrete or over sheeting already
placed. Wet sheeting thoroughly and keep continuously wet throughout the curing period.
Cast-In-Place Concrete
03300 - 16
3.6.1.4 Impervious Sheeting
Wet the entire exposed surface of the concrete thoroughly with a fine spray of
water and cover with impervious sheeting throughout the curing period. Lay sheeting directly on the concrete surface
and overlap edges 12 inches minimum. Provide sheeting not less than 18 inches wider than the concrete surface to be
cured. Secure edges and transverse laps to form closed joints. Repair torn or damaged sheeting or provide new
sheeting. Cover or wrap columns, walls, and other vertical structural elements from the top down with impervious
sheeting, overlap and continuously tape sheeting joints, and introduce sufficient water to soak the entire surface prior
to completely enclosing.
3.6.2 Liquid Membrane-Forming Compound Curing
Seal or cover joint openings prior to application of curing compound. Prevent curing
compound from entering the joint. Provide and maintain compound on the concrete surface throughout the curing
period. Do not use this method of curing where the use of Figure 2.1.5 in ACI 305R indicates that hot weather
conditions will cause an evaporation rate exceeding 0.2 pound of water per square foot per hour.
3.6.2.1 Application
Unless the manufacturer recommends otherwise, apply compound immediately
after the surface loses its water sheen and has a dull appearance, and before joints are sawed. Mechanically agitate
curing compound thoroughly during use. Use approved power-spraying equipment to uniformly apply two coats of
compound in a continuous operation. The total coverage for the two coats shall be 200 square feet maximum per
gallon of undiluted compound unless otherwise recommended by the manufacturer's written instructions. The
compound shall form a uniform, continuous, coherent film that will not check, crack, or peel. Immediately apply an
additional coat of compound to areas where the film is defective. Respray concrete surfaces subjected to rainfall
within 3 hours after the curing compound application.
3.6.2.2 Protection of Treated Surfaces
Prohibit foot and vehicular traffic and other sources of abrasion for not less than
72 hours after compound application. Maintain continuity of the coating for the entire curing period and immediately
repair any damage.
3.6.3 Liquid Chemical Sealer-Hardener
Apply sealer-hardener to interior floors not receiving floor covering and floors located
under access flooring. Apply the sealer-hardener in accordance with manufacturer's recommendations. Seal or cover
joints and openings in which joint sealant is to be applied as required by the joint sealant manufacturer. The sealer-
hardener shall not be applied until the concrete has been moist cured and has aged for a minimum of 30 days. Apply
a minimum of 2 coats of sealer-hardener.
Cast-In-Place Concrete
03300 - 17
3.6.4 Curing Periods and Minimum Temperatures
After placing concrete, maintain air temperature adjacent to the concrete at 50 degrees F
minimum for the specified time period, or 70 degrees F minimum for a period of 3 days after placing, and 40 degrees
F minimum for the remainder of the specified time period.
Time Period Concrete Structure or Cement Type
(Days Minimum)
3 ASTM C150, Type III concrete not specified otherwise.
7 ASTM C150, Type I or II, either with or without fly ash, pozzolan, or ground slag; and
ASTM C595 cement for concrete not specified otherwise.
10 Retaining walls that will be subjected to frost action or similar deteriorating conditions;
pavement not under a roof, chimneys.
14 Water tanks for potable and nonpotable water; structures that will be in contact with
water; decks and similar parts of waterfront structures over seawater that will not
ordinarily be wetted by seawater.
21 Concrete that will be in full-time or intermittent contact with seawater, salt spray, alkali
soil or waters, or similar destructive agents; tanks that will be used for corrosive liquids
and mineral oils.
3.6.4.1 Additional Curing
Double the required curing period if either one or the average of both 7-day test
cylinders indicate less than 90 percent of the strength specified (f'c).
3.6.5 Requirements for Type III (High-Early-Strength) Portland Cement
The curing periods, minimum periods during which supporting forms and shores shall be
left in place, and minimum periods for maintaining curing temperatures shall be not less than one-quarter of those
specified for portland cement, but in no case less than 72 hours.
3.7 SAMPLING AND TESTING
All concrete sampling and testing shall be at the contractor's expense. All concrete sampling and
testing shall be performed by a test laboratory under the supervision of a licensed Professional Engineer, licensed in
the Commonwealth of Virginia. Two copies of all test reports shall be provided directly to the Project Engineer.
Collection of concrete samples shall be only by qualified technicians under the supervision of the
testing laboratory.
3.7.1 Sampling
ASTM C172. Collect samples of fresh concrete to perform tests specified. ASTM C31
for making test specimens.
Cast-In-Place Concrete
03300 - 18
3.7.2 Testing
3.7.2.1 Slump Tests
ASTM C143. Take concrete samples during concrete placement. The
maximum slump may be increased as specified with the addition of an approved admixture provided that the water-
cement ratio is not exceeded. Perform tests at commencement of concrete placement, when test cylinders are made,
and for each batch (minimum) or every 10 cubic yards (maximum) of concrete.
3.7.2.2 Temperature Tests
Test the concrete delivered and the concrete in the forms. Perform tests in hot
or cold weather conditions (below 50 degrees F and above 80 degrees F) for each batch (minimum) or every 10 cubic
yards (maximum) of concrete, until the specified temperature is obtained, and whenever test cylinders and slump tests
are made.
3.7.2.3 Compressive Strength Tests
ASTM C39. Make five test cylinders for each set of tests in accordance with
ASTM C31. Test two cylinders at 7 days, two cylinders at 28 days, and hold one cylinder in reserve. Samples for
strength tests of each mix design of and for concrete placed each day shall be taken not less than once a day, nor less
than once for each 50 cubic yards of concrete, nor less than once for each 2500 square feet of surface area for slabs or
walls. For the entire project, there shall be no less than five sets of samples taken and strength tests performed for
each mix design of concrete placed. Each strength test result shall be the average of two cylinders from the same
concrete sample tested at 28 days. If the average of any three consecutive strength test results is less than f'c or if any
strength test result falls below f'c by more than 500 psi, take a minimum of three ASTM C42 core samples from the
in-place work represented by the low test cylinder results and test. Concrete represented by core test shall be
considered structurally adequate if the average of three cores is equal to at least 85 percent of f'c and if no single core
is less than 75 percent of f'c. Locations represented by erratic core strengths shall be retested. Remove concrete not
meeting strength criteria and provide new acceptable concrete. Repair core holes with nonshrink grout. Match color
and finish of adjacent concrete.
3.7.2.4 Air Content
ASTM C173 or ASTM C231 for normal weight concrete. Test air-entrained
concrete for air content at the same frequency as specified for slump tests.