1667construction Contract and Specifications

download 1667construction Contract and Specifications

of 85

Transcript of 1667construction Contract and Specifications

  • 8/11/2019 1667construction Contract and Specifications

    1/85

    An Najah National University

    Faculty of Engineering

    Dr. Nabil Dmaidi

    Eng. Mohammed Abu Neamah

    CONSTRUCTION CONTRACTS

    COST ESTIMATE AND

    SPECIFICATIONS

  • 8/11/2019 1667construction Contract and Specifications

    2/85

    Course Description

    The course is designed to give students, a working

    knowledge of construction contracts, contractual

    relationships within the construction industry and

    fundamentals of construction specification writing.

  • 8/11/2019 1667construction Contract and Specifications

    3/85

    Course Outline

    Introduction

    Elements of the total construction project cycle and processes.

    project delivery methods,

    Construction contracts types

    bidding process

    Contract documents

    Type of bonds

    Specifications

    Drawings

    General Conditions

  • 8/11/2019 1667construction Contract and Specifications

    4/85

    Course Outline

    Claims

    Dispute resolution

    Quantity surveying

    Estimating construction cost

    Pricing

  • 8/11/2019 1667construction Contract and Specifications

    5/85

    Grading System

    Grading policy for this course will be based on the following:

    Project 30%

    Midterm Exam 30%

    Final Exam 40%

  • 8/11/2019 1667construction Contract and Specifications

    6/85

    Text Book & References

    Text Book:

    Estimating Construction Cost, Robert R. Peurifoy

    Hinze, Jimmie (2003) Construction Contracts. 3rd Edition,

    McGraw-Hill Book Company, New York.

    References:

    Edward R. Fisk & Wayne D. Reynolds, Construction Project

    Administration, 9thEdition.

    Smith, Currie & Hancock (2005) Common Sense Construction

    Law. 3rd Edition, John Wiley and Sons, Hoboken , New Jersey

  • 8/11/2019 1667construction Contract and Specifications

    7/85

    Aims and Objectives

    At the completion of this course, the student will:

    Describe the relationships between the parties in the construction

    process (the owner, contractor, and architect) as well as their

    roles, duties, and responsibilities. Understanding the projects delivery systems and different

    contracts organizations. And understanding the different

    construction contracts types, documents and specifications.

    Understanding the various bidding procedures and ability toprepare bid documents and contract documents, in addition to

    ability to understand the types of bonds.

  • 8/11/2019 1667construction Contract and Specifications

    8/85

    Aims and Objectives

    At the completion of this course, the student will:

    Ability to estimate various cost components in construction

    projects.

    Understand the quantity surveying techniques and methods.

  • 8/11/2019 1667construction Contract and Specifications

    9/85

    Introduction

    Definition of Terms:

    Construction Management

    Construction Contracting

    Construction Administration

    One-to-One Concept (in organization)

  • 8/11/2019 1667construction Contract and Specifications

    10/85

    Construction Management

    Construction:

    The process by which material, equipment,

    machineries are assembled into a permanent facility.

    Management

    The planning, directing, and controlling of resources

    (Material, Manpower, Machines, Money) to achieve

    the desired goal (Time, Cost, Quality)

  • 8/11/2019 1667construction Contract and Specifications

    11/85

    Construction Contracting

    Contracting:

    The legal and business activities needed for initiating,

    executing, and terminating a construction contract.

  • 8/11/2019 1667construction Contract and Specifications

    12/85

    Construction Administration

    Construction Administration:

    Closely related to construction management.

    Can be defined as the implementation of constructionmanagement principles.

  • 8/11/2019 1667construction Contract and Specifications

    13/85

    Construction Administration

    Covers the following area:

    Planning and Scheduling

    Business and communication system

    Material control

    Payment procedure

    Changes to the work

    Inspection and acceptance

  • 8/11/2019 1667construction Contract and Specifications

    14/85

    One-to-One Concept

    Previous Administration functions involve different

    parties (Owner, contractors, Engineers)

    To minimize confusion, conflicts, claims, use:

    One to One concept Each party has a single representative who

    communicates important project information and

    orders.

  • 8/11/2019 1667construction Contract and Specifications

    15/85

    Classification of Construction Projects:

    By Size: Small, Medium, Large, Mega.

    By Ownership: Private, Public, Military.

    By Usage: Residential, Commercial, Industrial,

    Utility. (Usage can be expanded to subcategories). By Scope (preferred):

    Building (Residential, non residential), emphasis

    on aesthetics. Engineering (Highway, Heavy, Utility) emphasis

    on function

    Industrial: emphasis on production

  • 8/11/2019 1667construction Contract and Specifications

    16/85

    The Construction Participants

    Three key players in the game:

    The client (or Owner or stakeholder)

    The A/E or consultant

    The contractor (or Constructor or Builder)

  • 8/11/2019 1667construction Contract and Specifications

    17/85

    Relationship Among Parties

    OwnerGeneral

    Contractor

    SubsA/E

    Project

    contract

    contract

    own

    Design

    build

    build

    contract

  • 8/11/2019 1667construction Contract and Specifications

    18/85

  • 8/11/2019 1667construction Contract and Specifications

    19/85

    The Owner

    The owner, (also called the client)

    A client maybe an individual.

    A group of people.

    A partnership.

    A limited liability company.

    A local or central government authority

  • 8/11/2019 1667construction Contract and Specifications

    20/85

    The Owner

    The owner is responsible for:

    Funding and paying bills for the construction of project.

    Determining what the project will include (also called the

    scope of the project), when the project can begin and must

    end (the schedule),

    Receive the ultimate benefits of the finished project.

  • 8/11/2019 1667construction Contract and Specifications

    21/85

    The Owner

    Owner organizations can be broken into two major categories,

    public and private.

    A public agency exists for the ultimate benefit of the

    citizens, the general public. Examples of public projects:,an highway, or an University.

    A private organization can be described as any individual,

    partnership, corporation, or institution that builds a project

    for its own use or for resale.

    The owner enters into separate contract with Architect and

    contractor.

  • 8/11/2019 1667construction Contract and Specifications

    22/85

    The Design Professional

    The consultant is a party of the contractual relationship has

    professional skills in engineering whether civil, structure,

    architectural, mechanical. Etc.

    Who acts in behalf of the client.

  • 8/11/2019 1667construction Contract and Specifications

    23/85

    The Design Professional

    The major role of the design professional:

    Is to interpret or assist the owner in developing the project's scope,

    budget, and schedule and to prepare construction documents that

    will be used by the construction contractor to build the project.

    The architect typically sub-contracts portions of work to other

    design professionals such as structural engineers, landscape

    architects, electrical & mechanical engineers

    In almost all cases the design professional is a licensed, registered

    professional who is responsible for the physical integrity of the

    project.

  • 8/11/2019 1667construction Contract and Specifications

    24/85

    The Contractor

    A contractor is an individual or an entity that enters into a

    contract with the owner to carry out the construction work.

    If only one contractor is appointed he may be known as the

    main/prime contractor.

    The Contractor is responsible for the interpretation of the contract

    documents into physical facility. Transform idea to reality

  • 8/11/2019 1667construction Contract and Specifications

    25/85

    The Contractor

    In most cases the prime contractor divides the work among

    many specialty contractors called subcontractors. On a large

    project these subcontractors may also divide up the work into

    even smaller work packages

    In a traditional arrangement where the owner, design

    professional, and contractor are separate companies, the

    contractor is termed a prime contractor and is contractually

    responsible for delivering a completed project in accordance

    with the contract documents.

  • 8/11/2019 1667construction Contract and Specifications

    26/85

    The Subcontractors

    A contractor assigned and work under the supervision of the

    main contractor and who has special skills, experiences and

    equipment to deal with specialized aspects of the work.

    Nominated subcontractor

    Non-nominated subcontractors

  • 8/11/2019 1667construction Contract and Specifications

    27/85

    Project Life Cycle

    The major phases in the project cycle that are common to

    most design and construction projects are:

    Project Planning

    DesignSchematic Design

    Design Development

    Contract Documents

    Construction Procurement (Bidding Phase)

    Construction

    Occupancy

  • 8/11/2019 1667construction Contract and Specifications

    28/85

    Project Planning Phase

    During this phase of the project the owner makes decision that

    set the tone for the project. All projects begin with an idea or a

    need

    During this stage the owner :

    Selects the project site, and

    Establishes a conceptual estimate, schedule.

    The most critical decision that is made during this project

    phase is to make a decision as to whether or not to proceed

    with the project (called a go/no go decision).

  • 8/11/2019 1667construction Contract and Specifications

    29/85

    Project Planning Phase

    Phase activities:

    Feasibility studies

    Facility programming

    BudgetingProject delivery system selection

    Scheduling

    Site selection/acquisition

    Site investigation

    Financing

    Design services procurement

  • 8/11/2019 1667construction Contract and Specifications

    30/85

    Design Phase

    Design process involves:

    Schematic Design

    Talk to owner, rough sketches

    Design Development

    Major Systems & component selected

    Contract Documents

    Preliminary Cost estimate

    Develop Preliminary working drawings

    Develop working drawings with Specifications

  • 8/11/2019 1667construction Contract and Specifications

    31/85

    Schematic Design

    The A/E reviews and evaluates the owners program and budget

    requirements and discusses with the owner alternative approaches to

    the design and construction

    During schematic design, the A/E prepares conceptual design

    documents. These may include: Preliminary sketches ,Small scale

    schematic plans, elevations, sections, diagrams, renderings, and other

    graphic and written documents, General written description of

    project.

    The completion of the schematic design phase represents

    approximately 30 percent design completion for the project

  • 8/11/2019 1667construction Contract and Specifications

    32/85

    Design Development

    The design development phase takes the project from about 30

    percent to approximately 60 percent design.

    It is the time when the design team will be evaluating and selecting

    all the major systems and components of the project.

    During this phase of the project the design team is involved in the

    evaluation and finalization of all the architectural components and

    project systems.

    The project's budget and schedule continue to be monitored and

    adjusted.

  • 8/11/2019 1667construction Contract and Specifications

    33/85

    Contract Documents

  • 8/11/2019 1667construction Contract and Specifications

    34/85

  • 8/11/2019 1667construction Contract and Specifications

    35/85

    Construction Procurement:

    Contractor qualification/bidder list

    Solicitation

    Proposal preparation

    Bid/proposal opening

    Bid/proposal evaluation

    Award of contract

    Final negotiation

  • 8/11/2019 1667construction Contract and Specifications

    36/85

    Construction

    Mobilization

    Subcontracting

    Purchasing

    Permits

    Site preparation

    Foundations

    Interior finishes and equipment

  • 8/11/2019 1667construction Contract and Specifications

    37/85

    Occupancy/ Post Construction:

    Start-up and testing

    Leasing

    Operation

    Correction

    Repairs/maintenance

    Building evaluation

  • 8/11/2019 1667construction Contract and Specifications

    38/85

    Cost Influence Curve

  • 8/11/2019 1667construction Contract and Specifications

    39/85

    Level of Influence

    Influence

    ProjectCost

    Time

  • 8/11/2019 1667construction Contract and Specifications

    40/85

    Project Delivery Systems (PDS)

  • 8/11/2019 1667construction Contract and Specifications

    41/85

    Project Delivery Systems

    Project Delivery Methods

    Definition

    Types of Project Delivery Methods

    Traditional

    Design-Build

    Professional Construction Management (PCM)

    BOT ( Build Operate Transfer)

    Advantages & Disadvantages of various PDM

  • 8/11/2019 1667construction Contract and Specifications

    42/85

    Project Delivery Method

    The term delivery method means the approach used to

    organize the project team so as to manage the entire designing

    and building process.

    The owner needs to decide which designers to hire, when to

    hire them, and under what type of contract ?

    The owner also needs to decide when to hire the

    construction professional and under what type of contract ?

    Which organization gets hired first? Do both organizations

    report to the owner, or does one report to the other?

  • 8/11/2019 1667construction Contract and Specifications

    43/85

    Project Delivery Method

    project delivery systems

    describe how the

    participants are organized

    to interact, transforming

    the owners project goalsand objectives into a

    finished facility. Also its is

    the method by which a

    construction project isexecuted.

  • 8/11/2019 1667construction Contract and Specifications

    44/85

    Project Delivery Method

    It is the first allocation of base responsibilities between the

    owner, design professional and contractor. Thus, the project

    delivery system is the foundation on which all subsequent

    negotiations will be based.

  • 8/11/2019 1667construction Contract and Specifications

    45/85

  • 8/11/2019 1667construction Contract and Specifications

    46/85

  • 8/11/2019 1667construction Contract and Specifications

    47/85

  • 8/11/2019 1667construction Contract and Specifications

    48/85

  • 8/11/2019 1667construction Contract and Specifications

    49/85

    Type of Project Delivery Systems

    Traditional (Design-Bid-Build)

    a) Design-Bid-Build with prime contractorb) Design-Bid-Build with multiple contractors

    Design-Build (Turnkey)

    Self performance (In house) or (force account work)

    Professional Construction Management (PCM)

    BOT ( Build Operate Transfer)

    Choose one of these classifications depends up the client goal

    suitability.

  • 8/11/2019 1667construction Contract and Specifications

    50/85

    TraditionalApproach

    Also known as Design-Bid-Build or hard money or Competitive bidcontract.

    Has three sequential phases: Design - Bid - Construction

    The owner hires a design professional who prepares a complete set of

    contract documents for the owner for a design fee.

    The owner either negotiates a price with a general contractor or bids out thework.

    The general contractor is totally responsible for delivering the completed

    project as spelled out in the contract documents.

    The general contractor may subcontract out parts of the project, with each

    subcontractor reporting directly to the general contractor.The designer may be involved in overseeing the construction work in the

    field.

    In this delivery method no direct, formal relationship exists between the

    designer and the builder. They communicate only through the owner

  • 8/11/2019 1667construction Contract and Specifications

    51/85

    a) Design-Bid-Build with prime contractor

    Owner

    Prime

    Contractor

    subcontractor Supplierssubcontractor

    A/E

    Design consultant

    b) i id ild i h l i l

  • 8/11/2019 1667construction Contract and Specifications

    52/85

    b) Design-Bid-Build with multiple

    primes/GC (separate contracting)

    Owner

    Prime

    Contractor

    subcontractor

    M. Prime

    Contractor

    E. Prime

    Contractor

    A/E

    Design consultant

    subcontractorsubcontractor

    b) i id ild i h l i l

  • 8/11/2019 1667construction Contract and Specifications

    53/85

    b) Design-Bid-Build with multiple

    primes/GC (separate contracting)

    The client has a direct contract with consultant.

    The client also has direct contracts with many contractors to

    carry out construction

    The contractors also have contracts with the material suppliers

    and other specialized subcontractors.

  • 8/11/2019 1667construction Contract and Specifications

    54/85

    Typical DBB Process

    The four phases:

  • 8/11/2019 1667construction Contract and Specifications

    55/85

    Advantages of Traditional PDS:

    Familiarity: Most owners, designers, and builders have workedunder this framework on many projects and therefore are familiar

    with the system.

    Overall Job coordination: Their control systems, documentation,

    and organizations are all set up to manage this process. The workers,

    subcontractors, and vendors also understand the system, improving

    overall job coordination.

    Owner can get a firm fixed price for the project before any work

    begins. The owner knows before construction begins what the cost of

    the project will be.

    Opportunity to get good price competition from the open market.

  • 8/11/2019 1667construction Contract and Specifications

    56/85

    Disadvantages of Traditional PDS:

    The approach takes a long of time.

    Design does not benefit from construction experience

    Conflicts between owner & G.C. and between A/E & G.C.

    Changes in work may lead to disputes, litigation , claims and

    may increase cost.

  • 8/11/2019 1667construction Contract and Specifications

    57/85

    Design-Build (Turnkey)

    In this approach, a single organization is responsible for performing bothdesign and construction .

    Within the design-build organization, parts of the design may be

    subcontracted to specialist consultants.

    Being responsible for both design and construction, the design-build

    contractor carries most of the project risks, and this can mean additional cost

    to owner.

    The owner's role in this approach is minimal and is only to express his or

    her objectives and specifications precisely before detailed design is started.

    Consultant maybe appointed to prepare tender and evaluation

    Contractor consultant if the first is unable to perform design skills.

  • 8/11/2019 1667construction Contract and Specifications

    58/85

    Design-Build DB (Turnkey)

    Owner

    Design-Build

    Contractor

    subcontractor suppliersubcontractor

    Design consultant

    Some times

  • 8/11/2019 1667construction Contract and Specifications

    59/85

    Design-Build DB (Turnkey)

  • 8/11/2019 1667construction Contract and Specifications

    60/85

    Typical Design-Build Process

    The four phases

  • 8/11/2019 1667construction Contract and Specifications

    61/85

    Design-Build Advantages

    Good communication occurs between the design team and theconstruction team. Allows for constructability analyses and value

    engineering.

    Single point of responsibility for owner.

    This collaboration allows the project to be easily fast-tracked, cutting

    down on the design-build time for the project.

    Good cost estimating and scheduling should occur throughout the

    entire project.

    In general, this arrangement allows easier incorporation of changes

    due to changed scope or unforeseen conditions than in the other

    arrangements, since the coordination is to occur within the same

    company.

    Claims reduction

  • 8/11/2019 1667construction Contract and Specifications

    62/85

    Design-Build Disadvantages

    Cost may not be known until the end of design

    Design-build company may sacrifice quality to insure

    profitability

    Reduced owner involvement in the design process may result

    in less than expected results

    All your eggs in one basket

    Heavy overhead due to large multi-disciplined staff

    requirements

  • 8/11/2019 1667construction Contract and Specifications

    63/85

    Forms of Design Build Organization

    Identity of the design-builder:

    Integrated Design-Build Firm

    Contractor as lead

    A/E as lead

    Joint Venture

  • 8/11/2019 1667construction Contract and Specifications

    64/85

  • 8/11/2019 1667construction Contract and Specifications

    65/85

  • 8/11/2019 1667construction Contract and Specifications

    66/85

  • 8/11/2019 1667construction Contract and Specifications

    67/85

  • 8/11/2019 1667construction Contract and Specifications

    68/85

    Self performance

    Owner

    subcontractor suppliersubcontractor

    Design consultant

    worker

  • 8/11/2019 1667construction Contract and Specifications

    69/85

    Self performance

    The client has a direct contract with consultants. (some times

    not)

    Owner is responsible for both design and construction

    The client has no contracts with contractors to carry out

    construction.

    Best suited when volume of work is large and continuous.

    He is the one who will perform the job.

  • 8/11/2019 1667construction Contract and Specifications

    70/85

    Professional Construction Management

    In this approach, the owner appoints a PCM organization (also known asown construction management organization) to manage and coordinate the

    design and construction phases of a project using a teamwork design

    approach.

    The design may be provided by specialist design firms and in some casesby the PCM organization.

    With a high level of coordination between the participants, innovative

    approaches of overlapping design and construction (i.e., fast-tracking) can

    be adopted.

    The PCM organization aims at holding a friendly position similar to that of

    the consultants in the traditional approach.

    The services offered by the PCM organization overlap those traditionally

    performed by the architect, the engineer, and the contractor.

  • 8/11/2019 1667construction Contract and Specifications

    71/85

    Professional Construction Management

    These services may include:

    management and programming of design;

    cost forecasting and financial arrangements;

    preparation of tender documents; tender analysis

    and selection of contractors;

    selection of methods of construction;

    planning and scheduling construction works;

    materials procurement and delivery expedition

  • 8/11/2019 1667construction Contract and Specifications

    72/85

    Professional Construction Management

    Although this approach is likely to prove marginally more expensivethan the traditional approach, it offers greater guarantee of

    performance and the potential to avoid time overruns and to reduce

    the cost of claims.

    The payment to the PCM organization is usually a fixed fee orpercentage of the total project cost.

    Use of PCM approach, should be considered when there is a need for

    time saving and flexibility for design changes, and the owner has

    insufficient management resources

  • 8/11/2019 1667construction Contract and Specifications

    73/85

    a) Management Contracting (CM @ risk)

    Owner

    subcontractor suppliersubcontractor

    A/E

    Design consultant

    Management

    Contractor

  • 8/11/2019 1667construction Contract and Specifications

    74/85

    a) Management Contracting (CM @ risk)

    The client contracts a contractor acts as a management

    contractor.

    Provide purely management services.

    Management contractors contracts directly with other

    contractors to carry out the work

    The client contracts consultant to provide design and cost.

  • 8/11/2019 1667construction Contract and Specifications

    75/85

    b) Construction management (Agent)

    Owner

    subcontractor suppliersubcontractor

    A/E

    Design consultant

    Construction

    ManagerPrime

    Contractor

    b) i ( )

  • 8/11/2019 1667construction Contract and Specifications

    76/85

    b) Construction management (Agent)

    The clients directly contracts with a

    professional construction manager.

    Design and cost consultant

    Construction Contractor to carry out the work

    The construction manager is the agent of the client.

  • 8/11/2019 1667construction Contract and Specifications

    77/85

    PCM Advantages and Disadvantages

    Advantages: Construction skills can be utilized at all stages of the project

    Independent evaluation of cost, schedule, and construction performance

    CM often assumes greater DEGREE of control over contractor

    Full time coordination between design and construction

    Opportunity to use value engineering and constructability review

    Disadvantages: CM

    Does not guarantee construction cost or time Involve additional fee up to 4%

    Is not responsible for their performance

    Success of the entire program depends on the skills of C. Mgr.

  • 8/11/2019 1667construction Contract and Specifications

    78/85

    Built Operate Transfer (BOT)

    The term Build-Operate-Transfer (BOT) was first coined by Ministerof Turkey, in1984

    Essentially in a BOT project delivery method, a private entity,usually a consortium is responsible for financing, construction,

    operation and maintenance of the facility for agreed duration knownas Concession period and at the end of the period, transfers theownership of the facility to the government.

    A BOT mechanism is a complex structure comprising multiple, inter-dependent agreements among various participants.

    The concession agreement is between the government and theconcessionaire. The concession agreement is regarded as the heartof a BOT project

  • 8/11/2019 1667construction Contract and Specifications

    79/85

    Examples on (BOT) Projects

  • 8/11/2019 1667construction Contract and Specifications

    80/85

    (BOT) Contractual Structure

  • 8/11/2019 1667construction Contract and Specifications

    81/85

    Built Operate Transfer (BOT)

    Characteristics of BOT projects:

    Project financing is totally provided by the private sector.

    Projects are large scale infrastructure, such as power plants,transportation, telecommunications.

    The delivery is a complex system involving many

    independent agreements with various parties.

    Projects involve high risk.

  • 8/11/2019 1667construction Contract and Specifications

    82/85

    Advantages of Built Operate Transfer

    Facilitate building public projects which otherwise can not bedone due to tight government budget.

    The project and its associated services will be produced more

    efficiently, since private organizations are more efficient andinnovative than public organizations.

    BOT projects attract direct foreign investment and create

    business opportunities for the local private sectors.

    BOT projects help in transferring technology in the host

    country.

  • 8/11/2019 1667construction Contract and Specifications

    83/85

    Disadvantages of Built Operate Transfer

    BOT is not an easy method and requires high capability ofpromoters and expertise.

    Not suitable for small projects

    Transaction costs are high, they amount to 5-10% of total

    project cost

    Requires assurance that the revenues generated in the operation

    phase are high enough to result in attractive Return OnInvestment (ROI)

    S l i li h d

  • 8/11/2019 1667construction Contract and Specifications

    84/85

    Selecting Delivery Method

    Three main factors:

    Time

    Cost

    Quality

    S l i D li M h d

  • 8/11/2019 1667construction Contract and Specifications

    85/85

    Selecting Delivery Method

    All the systems mentioned provide adequate Performance.

    However, they all provide different emphasis and different

    levels of risk.

    Economy & Speed Design & Build

    Individual buildingwith longer program Traditional

    Fast Completion withinnovation Management