Construction Processok

download Construction Processok

of 61

Transcript of Construction Processok

  • 7/27/2019 Construction Processok

    1/61

    Chapter 5:

    Construction Process

    by Azman Jaafar

  • 7/27/2019 Construction Processok

    2/61

  • 7/27/2019 Construction Processok

    3/61

  • 7/27/2019 Construction Processok

    4/61

    Project Development

    The conceptual design and scope of work aredeveloped to include an approximate estimateof cost.

    The decision is made to proceed with thedevelopment of final design documents, whichfully define the project for purposes ofconstruction.

    Based on the final design documents, theproject is advertised and proposals to includequotations for construction of the work aresolicited.

  • 7/27/2019 Construction Processok

    5/61

  • 7/27/2019 Construction Processok

    6/61

    Project Development

    In complex projects, a period of testing

    decides if the facility operates as designed

    and planned. This period is typical of

    industrial projects and is referred to as projectstart-up.

    The facility operates and is maintained during

    a specified service life.

    The facility is disposed of if appropriate or

    maintained in perpetuity.

  • 7/27/2019 Construction Processok

    7/61

    Process

    A process is defined as a system of operationsin the design, development, and production ofsomething, such as a project.

    A process is a series of actions, changes, oroperations that bring about an end result cost,schedule, technical performance objectives.

    A process is that it is a course or passage of

    time in which something is created an ongoingmovement or progression.

    (Ireland & Iceland, 2002)

  • 7/27/2019 Construction Processok

    8/61

    Construction Processes

    The process of purchase begins with aclient who has need for a facility.

    The nature of risk is influenced by this

    process of purchasing construction. In construction, since the item purchased

    is to be produced, there are many complex

    issues which can lead to failure tocomplete the project in a functional and/ortimely manner.

  • 7/27/2019 Construction Processok

    9/61

    Managing the Project Life Cycle

    Phase 1

    Conceptual Phase

    Phase 2

    Planning phase

    Phase 3

    Execution phase

    Phase 4

    Termination

    Determine that a

    project is needed.

    Establish goal.

    Estimate theresources that the

    organization is

    willing to commit.

    Sell the

    organization on the

    need for a projectapproach.

    Make key

    personnel

    appointment.

    Define the project

    organization

    approach.

    Define projectstarget.

    Prepare the

    schedule for

    execution phase.

    Define and allocate

    tasks andresources.

    Build the project

    team.

    Perform the work

    of the project (i.e.

    design, construction,

    production, siteactivation, testing,

    delivery, etc.).

    Assist in transfer of

    project product.

    Transfer human

    and nonhumanresources to other

    organizations.

    Transfer or

    complete

    commitments.

    Terminate project. Reward personnel.

    Cleland & King, 1983

  • 7/27/2019 Construction Processok

    10/61

    Construction Process

    The construction process may be subdivided

    into the stages considered below:

    1. Conceptual stage: the client identifies the need for

    the item of construction and appoints and briefsconsultants who study the clients requirement,

    propose an outline of the design and assess the

    feasibility of the project.

    2. Design stage: the concept of the project is furtherdeveloped and production information and contract

    documentation prepared. Tenders are called.

  • 7/27/2019 Construction Processok

    11/61

    Construction Process

    3. Construction stage: production programmes

    are prepared and construction carried out on

    site.

    4. Operation and maintenance stage: thecompleted building or works is maintained,

    repaired or altered as required over the

    course of its life.

  • 7/27/2019 Construction Processok

    12/61

  • 7/27/2019 Construction Processok

    13/61

  • 7/27/2019 Construction Processok

    14/61

    Activities at Various Stages of a

    construction projectSubstage Activities

    Tender Invites tenders. Quantity Surveyor

    evaluates the tenders and report to

    client. Recommends to Client. Clientsigns a contract with the successful

    bidder.

    Project

    planning

    Prepares a programme for the project

    and mobilises resources forconstruction on sie.

  • 7/27/2019 Construction Processok

    15/61

    Activities at Various Stages of a

    construction projectSubstage Activities

    Site

    Operation

    Main Contractor and subcontractors

    transform the production information

    into a physical facility. Members of thedesign team supervise construction.

    Architect/engineer issues payment

    certificates periodically on the

    recommendation of the QuantitySurveyor. Site Meeting. On completion,

    Architect, applies for a temporary

    occupation license. Application for a

    final certificate.

  • 7/27/2019 Construction Processok

    16/61

  • 7/27/2019 Construction Processok

    17/61

    On time and within budget

    A quality facility on time and within budget

  • 7/27/2019 Construction Processok

    18/61

    Construction Process

    The construction process involves the

    translation of a clients needs and

    intentions.

    Then prepare documentations; cost plan,

    BQ, Specifications, Drawings.

    Finally, the construction phase.

  • 7/27/2019 Construction Processok

    19/61

  • 7/27/2019 Construction Processok

    20/61

  • 7/27/2019 Construction Processok

    21/61

    Activities During Construction

    Construction Activities

    Variation Order

    Progress Payment Certificate of Practical Completion (CPC)

    Certificate of Fitness (CF)

  • 7/27/2019 Construction Processok

    22/61

    Site Preparation

    Site clearing

    Earthwork

    Setting Out & Levelling

    Hoarding

    Dewatering systems

    Temporary buildings Access

  • 7/27/2019 Construction Processok

    23/61

    Detail Process

    1. Decision of a client in order to invest ornot.

    2. The client acquires a piece of land for

    project development.3. The client will engage professionals to

    prepare documentation including

    drawings, specifications, a form ofcontract, BQ. All about consultancyworks.

  • 7/27/2019 Construction Processok

    24/61

    Key Players

    The owner/Employer

    The designer/Estimator

    Architect/Planner

    C&S Engineers

    M&E Engineers

    QS

    The constructor Main

    Subcont.

  • 7/27/2019 Construction Processok

    25/61

    Clients

    Initiator of the construction process.

    Will be financing the project.

    An employer May be the public and private sectors.

    Parties Involved in the

  • 7/27/2019 Construction Processok

    26/61

    SUPPLIER CONTRACTOR

    MANPOWER

    AUTHORITIES

    FINANCIER

    CONSULTANTS

    CLIENT

    Project Management Consultant

    Planner

    Architect

    Engineers; C&S, M, E

    Quantity SurveyorLand Surveyor

    Interior Designer

    Landscape Architect

    Administration

    Site Management

    Site Worker

    Domestic Sub Contractor

    Nominated Sub Contractor

    Main Contractor

    Nominated Supplier

    Manufacturer

    Vendor

    Distributor

    Bank

    Finance Company

    Credit Corporation

    Leasing Company

    Federal

    State

    Local

    Private SectorPublic Sector

    Construction Industry

  • 7/27/2019 Construction Processok

    27/61

    The process will be organised into the

    sequence of activities/works differ from

    one project to another.

  • 7/27/2019 Construction Processok

    28/61

  • 7/27/2019 Construction Processok

    29/61

  • 7/27/2019 Construction Processok

    30/61

    Planning

    What are we aiming for and why?

    In the execution of this function, the

    organizations mission, objectives, goals,

    and strategies are determined.

  • 7/27/2019 Construction Processok

    31/61

    Control

    Construction monitored by ProjectManager.

    Based on work programme as planned

    vs. actual progress. IT - Microsoft project & Primavera

    (sometime Excel).

    Cash Flow (Financial Progress) Inspection & Observation (Physical

    Progress).

  • 7/27/2019 Construction Processok

    32/61

    WHY THERE HAS TO BE A PLAN?

    INTERNAL (STRATEGIC) OR

    EXTERNAL (CLIENTS REQUEST)

    TO AVOID RISK

    TO TRACK PROGRESS

    TO MAKE CORRECTION

  • 7/27/2019 Construction Processok

    33/61

    WHY SCHEDULE?

    To communicate the

    construction plan

    To establish production goal

    To monitor and measure

    progress

    To manage change

  • 7/27/2019 Construction Processok

    34/61

    INTRODUCTION

    The task of monitoring and controlling help

    to determine the objectives are within

    reach

    Monitoring and control has to start at early

    stage of the project development since it

    has more impact on cost

    Focusing on monitoring and control at theconstruction stage since many

    acknowledge of its difficulty

  • 7/27/2019 Construction Processok

    35/61

    MONITORING and CONTROL

    Monitoring is comparing the planned

    against actual

    Using software can easily be updated and

    preparation of reports are standardised

    Several methods used to monitor the work

    progress these include time weightage,

    cost weightage, man-days and quality

    Most common is using cost weightage

  • 7/27/2019 Construction Processok

    36/61

    Progress Curves

    Table 3.4 Combination between S-Curves and Bar Charts

    No. Description Month

    1 2 3 4 5 6 7 8 9 10

    1 Mobilization

    2 Foundation Excavation

    3 Diversion Stage

    4 Foundation Grouting

    5 Dam Concrete

    6 Install Outlet Gates

    7 Install Trash Racks

    8 Prestress

    9 Radial Gates

    10 Spillway Bridge

    11 Curtain Grout

    12 Dismantle Plant, Clean Up

    Original Schedule

    Actual progress

    Cumulativeprogress(%)

    100

    0

  • 7/27/2019 Construction Processok

    37/61

    Project Controlling Procedure

    - What performance measures should be

    selected?

    - What data should be used to

    estimate the current value of each

    performance measure?

    - How should raw data be collected,

    from which sources, and in what

    frequency?

    - How should the data be analyzed to

    detect current and future

    deviations?

    - How should the results of theanalysis be reported, in what

    format, to whom, and how often?

    Project

    plan

    Project

    implementation

    Project

    control

    Project

    updating

    Measurement

    Of work performance

    Figure 3.12 Project Controlling Procedure

  • 7/27/2019 Construction Processok

    38/61

    Project Controlling

    Figure 3.13 Implementation of Project Controlling in Construction Project

    Implementation of

    Project Controlling

    Project Site

    Main office

    Constructio

    n

    Design

    Subcontrac

    t

    Procurement

  • 7/27/2019 Construction Processok

    39/61

    Elements of Project Controlling

    Figure 3.14 Elements of Project Controlling

    Action Plan

    BudgetElements of

    Project ControllingTools

    Milestone

    Forecasting

  • 7/27/2019 Construction Processok

    40/61

    Figure below presents a Gantt Chart generated by Microsoft Project.

    Gantt Chart:

    The Gantt chart (invented by Henry L. Gantt in 1900's)

    is a bar chart presentation showing a horizontal bar for each task,the length of the bar representing the duration of the task.

  • 7/27/2019 Construction Processok

    41/61

  • 7/27/2019 Construction Processok

    42/61

  • 7/27/2019 Construction Processok

    43/61

    Factors causing delay in construction project

    Procurement of resources which is not on schedule

    Inappropriate work capacity

    Low productivity Ineffective project management

    There are some redesign and extra work to the project

    Bad communication among parties involved in project

    Inefficient decision making Force majeur, etc.

    Time Controlling

    Need an effective supervision

  • 7/27/2019 Construction Processok

    44/61

    Suggestion of Practices

    Some of the practices can be incorporated in the

    monitoring and control process system these

    include:

    Daily monitoring Morning discussion with the foreman

    Afternoon discussion

    Discussion the resources requirement every forth

    nightly Using bonus system to improve productivity

    Using damages clause to control supplier and sub-

    contractor

    Th Pl i & S h d li P

  • 7/27/2019 Construction Processok

    45/61

    The Planning & Scheduling Process

    IDENTIFY THE PROJECT ACTIVITIES

    EXTIMATE DURATION OF ACTIVITY

    DEVELOPED THE PROJECT PLAN

    SCHEDULE PROJECT ACTIVITIES

    REVIEW AND ANALYSE THE SCHEDULE

    OK?IMPLEMENTYES NO

  • 7/27/2019 Construction Processok

    46/61

    Historical Background

    During world war 1, Henry L.Gantt develop agraphical technique of displaying bar type lineupon specific time.

    The technique was known as Bar Chart.

    In 1956 E.I. du Pont de Nemours & Companydeveloped network concept known as CriticalPath Method

    Booz Allen & Hamilton develop Project

    Evaluation Review Technique (PERT) Scheduling software application are Primavera,Microsoft Project, Artemis, Timeline etc

  • 7/27/2019 Construction Processok

    47/61

    Choice of Scheduling Method

    Factors that governed the choice of the

    technique are:

    Familiarity on the technique to be used

    Type and size of project

    Purpose of scheduling

  • 7/27/2019 Construction Processok

    48/61

    Familiarity on the technique to be used

    A planner should not engaged any

    technique which he has a limited

    knowledge on its application

    Main objective of the schedule as a

    communication tool

    Important to have a schedule technique

    which is acceptable by all parties.

  • 7/27/2019 Construction Processok

    49/61

    Type and Size of the Project

    Project with few but repetitive tasksLine

    of Balance

    Medium to Large Project(Critical Path

    Method) like Precedence Method or Arrow

    Diagram

    Small ProjectGantt Chart or Bar Chart

  • 7/27/2019 Construction Processok

    50/61

  • 7/27/2019 Construction Processok

    51/61

    ACTIVITY DEFINED

    FIVE CHARACTERISTICS

    Must consume time

    Mostly consume resourse

    Have a defineable start and finish

    Measurable

  • 7/27/2019 Construction Processok

    52/61

    ACTIVITY IDENTIFICATION

    THINGS TO BE REVIEWED

    Plans and specification

    Agreement

    Contract conditions

    BQ

    Other information

  • 7/27/2019 Construction Processok

    53/61

    ACTIVITY IDENTIFICATION

    CRITERIA FOR BREAKING DOWNPROJECTS:

    WHAT?

    WHERE?

    WHO?

    WHEN?

    HOW?

  • 7/27/2019 Construction Processok

    54/61

    ACTIVITY DETAIL

    DEPENDS ON THE FOLLOWING:

    >Purpose Complexity

    >Philosophy

    >Information

    >Responsibility

    >Effect of detail

  • 7/27/2019 Construction Processok

    55/61

  • 7/27/2019 Construction Processok

    56/61

    WORK BREAKDOWN STRUCTURES (WBS)

    A PLANNING TOOL AND NOT A SCHEDULING METHOD

    BREAKS A PROJECT DOWN INTO GREATER DETAIL BY

    LEVEL

    ORGANISES WITHOUT SCHEDULING

    PROVIDES A FRAMEWORK FOR ORGANISING ANDORDERING ACTIVITIES

  • 7/27/2019 Construction Processok

    57/61

    Work Sequence

    Stages of construction activity.

    Normally from site clearing until project

    handover.

    Logical sequence of activities.

    Needs an experience and knowledge

    during planning and scheduling process.

  • 7/27/2019 Construction Processok

    58/61

  • 7/27/2019 Construction Processok

    59/61

    Act. ID Description Duration (days) Successors

    1200 Rough HVAC 3 13001300 Rough Electrical 3 1000

    1400 Shingles 3 1000, 1600, 2700

    1500 Ext siding 3 20000

    1600 Ext finish carpentry 2 1500

    1700 Hang drywall 4 1800

    1800 Finish drywall 4 1900, 2400, 2500

    1900 Cabinets 2 2100, 2300

    2000 Ext paint 3 2200

    2100 Internal finish carpentry 4 2200

    2200 Internal paint 3 2600

    2300 Finish plumbing 2 2200

    2400 Finish HVAC 3 2200

    2500 Finish electrical 2 2200

    2600 Flooring 3 2800

    2700 Grading and landscaping 4 2800

    2800 Punch list 2

  • 7/27/2019 Construction Processok

    60/61

  • 7/27/2019 Construction Processok

    61/61