Construction Processok
Transcript of Construction Processok
-
7/27/2019 Construction Processok
1/61
Chapter 5:
Construction Process
by Azman Jaafar
-
7/27/2019 Construction Processok
2/61
-
7/27/2019 Construction Processok
3/61
-
7/27/2019 Construction Processok
4/61
Project Development
The conceptual design and scope of work aredeveloped to include an approximate estimateof cost.
The decision is made to proceed with thedevelopment of final design documents, whichfully define the project for purposes ofconstruction.
Based on the final design documents, theproject is advertised and proposals to includequotations for construction of the work aresolicited.
-
7/27/2019 Construction Processok
5/61
-
7/27/2019 Construction Processok
6/61
Project Development
In complex projects, a period of testing
decides if the facility operates as designed
and planned. This period is typical of
industrial projects and is referred to as projectstart-up.
The facility operates and is maintained during
a specified service life.
The facility is disposed of if appropriate or
maintained in perpetuity.
-
7/27/2019 Construction Processok
7/61
Process
A process is defined as a system of operationsin the design, development, and production ofsomething, such as a project.
A process is a series of actions, changes, oroperations that bring about an end result cost,schedule, technical performance objectives.
A process is that it is a course or passage of
time in which something is created an ongoingmovement or progression.
(Ireland & Iceland, 2002)
-
7/27/2019 Construction Processok
8/61
Construction Processes
The process of purchase begins with aclient who has need for a facility.
The nature of risk is influenced by this
process of purchasing construction. In construction, since the item purchased
is to be produced, there are many complex
issues which can lead to failure tocomplete the project in a functional and/ortimely manner.
-
7/27/2019 Construction Processok
9/61
Managing the Project Life Cycle
Phase 1
Conceptual Phase
Phase 2
Planning phase
Phase 3
Execution phase
Phase 4
Termination
Determine that a
project is needed.
Establish goal.
Estimate theresources that the
organization is
willing to commit.
Sell the
organization on the
need for a projectapproach.
Make key
personnel
appointment.
Define the project
organization
approach.
Define projectstarget.
Prepare the
schedule for
execution phase.
Define and allocate
tasks andresources.
Build the project
team.
Perform the work
of the project (i.e.
design, construction,
production, siteactivation, testing,
delivery, etc.).
Assist in transfer of
project product.
Transfer human
and nonhumanresources to other
organizations.
Transfer or
complete
commitments.
Terminate project. Reward personnel.
Cleland & King, 1983
-
7/27/2019 Construction Processok
10/61
Construction Process
The construction process may be subdivided
into the stages considered below:
1. Conceptual stage: the client identifies the need for
the item of construction and appoints and briefsconsultants who study the clients requirement,
propose an outline of the design and assess the
feasibility of the project.
2. Design stage: the concept of the project is furtherdeveloped and production information and contract
documentation prepared. Tenders are called.
-
7/27/2019 Construction Processok
11/61
Construction Process
3. Construction stage: production programmes
are prepared and construction carried out on
site.
4. Operation and maintenance stage: thecompleted building or works is maintained,
repaired or altered as required over the
course of its life.
-
7/27/2019 Construction Processok
12/61
-
7/27/2019 Construction Processok
13/61
-
7/27/2019 Construction Processok
14/61
Activities at Various Stages of a
construction projectSubstage Activities
Tender Invites tenders. Quantity Surveyor
evaluates the tenders and report to
client. Recommends to Client. Clientsigns a contract with the successful
bidder.
Project
planning
Prepares a programme for the project
and mobilises resources forconstruction on sie.
-
7/27/2019 Construction Processok
15/61
Activities at Various Stages of a
construction projectSubstage Activities
Site
Operation
Main Contractor and subcontractors
transform the production information
into a physical facility. Members of thedesign team supervise construction.
Architect/engineer issues payment
certificates periodically on the
recommendation of the QuantitySurveyor. Site Meeting. On completion,
Architect, applies for a temporary
occupation license. Application for a
final certificate.
-
7/27/2019 Construction Processok
16/61
-
7/27/2019 Construction Processok
17/61
On time and within budget
A quality facility on time and within budget
-
7/27/2019 Construction Processok
18/61
Construction Process
The construction process involves the
translation of a clients needs and
intentions.
Then prepare documentations; cost plan,
BQ, Specifications, Drawings.
Finally, the construction phase.
-
7/27/2019 Construction Processok
19/61
-
7/27/2019 Construction Processok
20/61
-
7/27/2019 Construction Processok
21/61
Activities During Construction
Construction Activities
Variation Order
Progress Payment Certificate of Practical Completion (CPC)
Certificate of Fitness (CF)
-
7/27/2019 Construction Processok
22/61
Site Preparation
Site clearing
Earthwork
Setting Out & Levelling
Hoarding
Dewatering systems
Temporary buildings Access
-
7/27/2019 Construction Processok
23/61
Detail Process
1. Decision of a client in order to invest ornot.
2. The client acquires a piece of land for
project development.3. The client will engage professionals to
prepare documentation including
drawings, specifications, a form ofcontract, BQ. All about consultancyworks.
-
7/27/2019 Construction Processok
24/61
Key Players
The owner/Employer
The designer/Estimator
Architect/Planner
C&S Engineers
M&E Engineers
QS
The constructor Main
Subcont.
-
7/27/2019 Construction Processok
25/61
Clients
Initiator of the construction process.
Will be financing the project.
An employer May be the public and private sectors.
Parties Involved in the
-
7/27/2019 Construction Processok
26/61
SUPPLIER CONTRACTOR
MANPOWER
AUTHORITIES
FINANCIER
CONSULTANTS
CLIENT
Project Management Consultant
Planner
Architect
Engineers; C&S, M, E
Quantity SurveyorLand Surveyor
Interior Designer
Landscape Architect
Administration
Site Management
Site Worker
Domestic Sub Contractor
Nominated Sub Contractor
Main Contractor
Nominated Supplier
Manufacturer
Vendor
Distributor
Bank
Finance Company
Credit Corporation
Leasing Company
Federal
State
Local
Private SectorPublic Sector
Construction Industry
-
7/27/2019 Construction Processok
27/61
The process will be organised into the
sequence of activities/works differ from
one project to another.
-
7/27/2019 Construction Processok
28/61
-
7/27/2019 Construction Processok
29/61
-
7/27/2019 Construction Processok
30/61
Planning
What are we aiming for and why?
In the execution of this function, the
organizations mission, objectives, goals,
and strategies are determined.
-
7/27/2019 Construction Processok
31/61
Control
Construction monitored by ProjectManager.
Based on work programme as planned
vs. actual progress. IT - Microsoft project & Primavera
(sometime Excel).
Cash Flow (Financial Progress) Inspection & Observation (Physical
Progress).
-
7/27/2019 Construction Processok
32/61
WHY THERE HAS TO BE A PLAN?
INTERNAL (STRATEGIC) OR
EXTERNAL (CLIENTS REQUEST)
TO AVOID RISK
TO TRACK PROGRESS
TO MAKE CORRECTION
-
7/27/2019 Construction Processok
33/61
WHY SCHEDULE?
To communicate the
construction plan
To establish production goal
To monitor and measure
progress
To manage change
-
7/27/2019 Construction Processok
34/61
INTRODUCTION
The task of monitoring and controlling help
to determine the objectives are within
reach
Monitoring and control has to start at early
stage of the project development since it
has more impact on cost
Focusing on monitoring and control at theconstruction stage since many
acknowledge of its difficulty
-
7/27/2019 Construction Processok
35/61
MONITORING and CONTROL
Monitoring is comparing the planned
against actual
Using software can easily be updated and
preparation of reports are standardised
Several methods used to monitor the work
progress these include time weightage,
cost weightage, man-days and quality
Most common is using cost weightage
-
7/27/2019 Construction Processok
36/61
Progress Curves
Table 3.4 Combination between S-Curves and Bar Charts
No. Description Month
1 2 3 4 5 6 7 8 9 10
1 Mobilization
2 Foundation Excavation
3 Diversion Stage
4 Foundation Grouting
5 Dam Concrete
6 Install Outlet Gates
7 Install Trash Racks
8 Prestress
9 Radial Gates
10 Spillway Bridge
11 Curtain Grout
12 Dismantle Plant, Clean Up
Original Schedule
Actual progress
Cumulativeprogress(%)
100
0
-
7/27/2019 Construction Processok
37/61
Project Controlling Procedure
- What performance measures should be
selected?
- What data should be used to
estimate the current value of each
performance measure?
- How should raw data be collected,
from which sources, and in what
frequency?
- How should the data be analyzed to
detect current and future
deviations?
- How should the results of theanalysis be reported, in what
format, to whom, and how often?
Project
plan
Project
implementation
Project
control
Project
updating
Measurement
Of work performance
Figure 3.12 Project Controlling Procedure
-
7/27/2019 Construction Processok
38/61
Project Controlling
Figure 3.13 Implementation of Project Controlling in Construction Project
Implementation of
Project Controlling
Project Site
Main office
Constructio
n
Design
Subcontrac
t
Procurement
-
7/27/2019 Construction Processok
39/61
Elements of Project Controlling
Figure 3.14 Elements of Project Controlling
Action Plan
BudgetElements of
Project ControllingTools
Milestone
Forecasting
-
7/27/2019 Construction Processok
40/61
Figure below presents a Gantt Chart generated by Microsoft Project.
Gantt Chart:
The Gantt chart (invented by Henry L. Gantt in 1900's)
is a bar chart presentation showing a horizontal bar for each task,the length of the bar representing the duration of the task.
-
7/27/2019 Construction Processok
41/61
-
7/27/2019 Construction Processok
42/61
-
7/27/2019 Construction Processok
43/61
Factors causing delay in construction project
Procurement of resources which is not on schedule
Inappropriate work capacity
Low productivity Ineffective project management
There are some redesign and extra work to the project
Bad communication among parties involved in project
Inefficient decision making Force majeur, etc.
Time Controlling
Need an effective supervision
-
7/27/2019 Construction Processok
44/61
Suggestion of Practices
Some of the practices can be incorporated in the
monitoring and control process system these
include:
Daily monitoring Morning discussion with the foreman
Afternoon discussion
Discussion the resources requirement every forth
nightly Using bonus system to improve productivity
Using damages clause to control supplier and sub-
contractor
Th Pl i & S h d li P
-
7/27/2019 Construction Processok
45/61
The Planning & Scheduling Process
IDENTIFY THE PROJECT ACTIVITIES
EXTIMATE DURATION OF ACTIVITY
DEVELOPED THE PROJECT PLAN
SCHEDULE PROJECT ACTIVITIES
REVIEW AND ANALYSE THE SCHEDULE
OK?IMPLEMENTYES NO
-
7/27/2019 Construction Processok
46/61
Historical Background
During world war 1, Henry L.Gantt develop agraphical technique of displaying bar type lineupon specific time.
The technique was known as Bar Chart.
In 1956 E.I. du Pont de Nemours & Companydeveloped network concept known as CriticalPath Method
Booz Allen & Hamilton develop Project
Evaluation Review Technique (PERT) Scheduling software application are Primavera,Microsoft Project, Artemis, Timeline etc
-
7/27/2019 Construction Processok
47/61
Choice of Scheduling Method
Factors that governed the choice of the
technique are:
Familiarity on the technique to be used
Type and size of project
Purpose of scheduling
-
7/27/2019 Construction Processok
48/61
Familiarity on the technique to be used
A planner should not engaged any
technique which he has a limited
knowledge on its application
Main objective of the schedule as a
communication tool
Important to have a schedule technique
which is acceptable by all parties.
-
7/27/2019 Construction Processok
49/61
Type and Size of the Project
Project with few but repetitive tasksLine
of Balance
Medium to Large Project(Critical Path
Method) like Precedence Method or Arrow
Diagram
Small ProjectGantt Chart or Bar Chart
-
7/27/2019 Construction Processok
50/61
-
7/27/2019 Construction Processok
51/61
ACTIVITY DEFINED
FIVE CHARACTERISTICS
Must consume time
Mostly consume resourse
Have a defineable start and finish
Measurable
-
7/27/2019 Construction Processok
52/61
ACTIVITY IDENTIFICATION
THINGS TO BE REVIEWED
Plans and specification
Agreement
Contract conditions
BQ
Other information
-
7/27/2019 Construction Processok
53/61
ACTIVITY IDENTIFICATION
CRITERIA FOR BREAKING DOWNPROJECTS:
WHAT?
WHERE?
WHO?
WHEN?
HOW?
-
7/27/2019 Construction Processok
54/61
ACTIVITY DETAIL
DEPENDS ON THE FOLLOWING:
>Purpose Complexity
>Philosophy
>Information
>Responsibility
>Effect of detail
-
7/27/2019 Construction Processok
55/61
-
7/27/2019 Construction Processok
56/61
WORK BREAKDOWN STRUCTURES (WBS)
A PLANNING TOOL AND NOT A SCHEDULING METHOD
BREAKS A PROJECT DOWN INTO GREATER DETAIL BY
LEVEL
ORGANISES WITHOUT SCHEDULING
PROVIDES A FRAMEWORK FOR ORGANISING ANDORDERING ACTIVITIES
-
7/27/2019 Construction Processok
57/61
Work Sequence
Stages of construction activity.
Normally from site clearing until project
handover.
Logical sequence of activities.
Needs an experience and knowledge
during planning and scheduling process.
-
7/27/2019 Construction Processok
58/61
-
7/27/2019 Construction Processok
59/61
Act. ID Description Duration (days) Successors
1200 Rough HVAC 3 13001300 Rough Electrical 3 1000
1400 Shingles 3 1000, 1600, 2700
1500 Ext siding 3 20000
1600 Ext finish carpentry 2 1500
1700 Hang drywall 4 1800
1800 Finish drywall 4 1900, 2400, 2500
1900 Cabinets 2 2100, 2300
2000 Ext paint 3 2200
2100 Internal finish carpentry 4 2200
2200 Internal paint 3 2600
2300 Finish plumbing 2 2200
2400 Finish HVAC 3 2200
2500 Finish electrical 2 2200
2600 Flooring 3 2800
2700 Grading and landscaping 4 2800
2800 Punch list 2
-
7/27/2019 Construction Processok
60/61
-
7/27/2019 Construction Processok
61/61