Construction Delays & Best Practices

44
Construction Construction Construction Construction Delays & Best Delays & Best Delays & Best Delays & Best Practices Practices Practices Practices Gene Wortham Idaho Transportation Department

Transcript of Construction Delays & Best Practices

Page 1: Construction Delays & Best Practices

Construction Construction Construction Construction Delays & Best Delays & Best Delays & Best Delays & Best

PracticesPracticesPracticesPracticesGene Wortham

Idaho Transportation Department

Page 2: Construction Delays & Best Practices

“Time is Money”

Page 3: Construction Delays & Best Practices
Page 4: Construction Delays & Best Practices

Who pays the Who pays the Who pays the Who pays the

Money for the Money for the Money for the Money for the

Time?Time?Time?Time?

Page 5: Construction Delays & Best Practices

Effects of Construction

Delays• Acceleration

• Schedule Change - Inefficiency

• Delayed project completion

• Missed intermediate completion dates

• Liquidated Damages

• Frustration – claims

• Increased Costs

Page 6: Construction Delays & Best Practices

Delay Causes

• Labor Strikes

• Weather

• Third Party

• Plan Errors

• Change Orders

• Contractor Errors

• Suspension of Work

• Utilities

• Differing Site Conditions

• Archaeological Finds

• The list goes on

Page 7: Construction Delays & Best Practices

Costs of Delays

• Delays in most cases always cause

additional costs

• Direct Costs

• Indirect Costs

• Impact Costs

Page 8: Construction Delays & Best Practices

Delay

Excusable Non-Excusable

No TimeNon-Compensable

Entitlement for time

Compensable

Non-Compensable

Page 9: Construction Delays & Best Practices

When a Delay Occurs

Time for delay needs

to be addressed

immediately

Page 10: Construction Delays & Best Practices

Arbitration

Appeal

Claim

Disagreement

Problem

DRB

DRB

Project Level

Higher UpCRB

Page 11: Construction Delays & Best Practices

Contract Clause for

Determination and Extension

of Contract Time

Most Owner’s contracts

have this clause giving

guidelines for time

requests

Page 12: Construction Delays & Best Practices

Contractual Requirements for

Contractor Scheduling (CPM)• Without a Schedule, how does

Owner/Contractor determine how a delay affects time?

• Initial Schedule

• Schedule Updates

• Contract completion date

• Contractor’s scheduled completion date

• Substantial completion

• Float

Page 13: Construction Delays & Best Practices

Types of Non-Excusable Delay

Non-Excusable (Within control of the Contractor)

– Under estimate of production rates

– Inadequate scheduling or management

– Construction mistakes

– Equipment problems

– Bad Luck

– Liquidated Damages or Termination of Contract

The list goes on

Bottom line - Construction is a risky business

Page 14: Construction Delays & Best Practices

Types of Excusable Delay

• Unusually Severe Weather

• Changes and Extra Work

• Differing Site Conditions

• Delays from unforeseeable causes beyond control of the Contractor

• Labor Disputes

• Utilities

• Etc.

Page 15: Construction Delays & Best Practices

•Foreseeability

•Beyond the Control

•Without fault or negligence

Excusable Delay

Page 16: Construction Delays & Best Practices

Excusable Delay – Time

Consideration

• May entitle Contactor to an extension of time (refer to your contract specifications)

• Contractor not charged Liquidated Damages or terminated if the Delay is Excusable – Time should be forthcoming

• If time extension is requested by Contractor and not granted and proven to be excusable –Constructive Acceleration may exist and costs owed by Owner

• Above may be overturned by a “No Damage for Delay” clause in contract

Page 17: Construction Delays & Best Practices

Excusable Delay

(Compensable or Non-

Compensable)

• Non-Compensable Delay – Unforeseeable and beyond the control and without fault or negligence by the Owner or Contractor (may be entitled to time)

• Compensable Delay – The Contractor is entitled to an adjustment for increases in costs to the performance of the contract

Page 18: Construction Delays & Best Practices

Compensable Time Extensions

The following clauses are placed in the contract to prevent a breach by the Owner

• Changes and Extra Work clause

• Differing Site Condition clause

• Suspension of Work clause

• Utility Work clause

Page 19: Construction Delays & Best Practices

Changes and Extra Work Clause

The Changes and Extra Work may be

compensable – time may be given if

proven to affect the critical path

Page 20: Construction Delays & Best Practices

Differing Site Conditions Clause

• Direct Costs

• Indirect Costs (OH & profit)

Amount to be paid can be limited to Contract

wording.

• The Changes and Differing Site Conditions clauses are not generally referred to as delay or suspension of work

Page 21: Construction Delays & Best Practices

Suspension of Work Clause

Delays by the Owner for an unreasonable time fall under this clause and are most likely compensable. Very risky for liability on the Owner

• The Suspension of Work clause should provide contractual guidance for an equitable adjustment to the Contractor for time and money excluding profit

• Ground rules for Delay generally come from Contract Law. The Owner is liable for their actions/inactions that result in unreasonably delaying or disrupting the Contractor

• There is an implied obligation on the part of the Owner not to delay, interfere with or hinder the Contractor’s performance of their contract

Page 22: Construction Delays & Best Practices

Utility Facilities clause

Refer to your State contract requirements to determine your rules for compensation and time the Owner is liable to the Contractor for a Utility delay. Should exclude profit.

Page 23: Construction Delays & Best Practices

Burden of Proof for Damage

Must be Proven by

Contractor (Time and Money)• The contract performance was delayed

• Delay was excusable

• Delay was for unreasonable period of time– Unreasonable means not originally

anticipated, customary or inherent in the construction industry

– Some States define this unreasonable time by days

• Contractor did incur additional expenses

Page 24: Construction Delays & Best Practices

Defective Plans and Specifications

• Contractor does not have to prove unreasonable time delay

• Any Delay due to Defective Plans/Specifications is unreasonable

Page 25: Construction Delays & Best Practices

Third Party Delay

• This is a delay without the fault or negligence of either the Owner or Contractor

• Generally eligible for time but not compensable

Page 26: Construction Delays & Best Practices

Concurrent Delay

• Both Owner and Contractor are contributing to the Delay time

• Neither Party can recover damages (non-compensable)

• Contract time may be extended

Page 27: Construction Delays & Best Practices

Delay Costs

The cost of the delay must be traced directly to the claimed delay in a clear cause and effect relationship

Page 28: Construction Delays & Best Practices

Acceleration

Acceleration is action taken by the Contractor in order to speed up the progress of the project to accomplish early completion or to make up for lost time

• Voluntary

• Constructive (not ordered by the Owner but attributed to the Owner

• Direction from the Owner

Page 29: Construction Delays & Best Practices

Constructive Acceleration

• Constructive Acceleration occurs when the Contractor is induced by the actions/inactions of the Owner to complete the work in accordance with schedules not updated to include all time extensions from excusable delays.

Page 30: Construction Delays & Best Practices

Contract Completion

The contract must be specific in terms of the time required to perform the work

Page 31: Construction Delays & Best Practices

Contractor’s Scheduled Completion

• This is the date the Contractor presents on his schedule as to when the work will completed.

Page 32: Construction Delays & Best Practices

Substantial Completion

• Most contracts define what constitutes substantial completion

• Substantial completion is primarily used to stop time accounting

Page 33: Construction Delays & Best Practices

No Damage for Delay cause

• An effort to reduce claims for delay• Exculpatory Language – precludes damages for delay

• Generally, the Contractors sole remedy is only a time extension if so stated in the contract

• Validity of this clause varies from State to State

• Clause must be very clear and unambiguous• Enforceable – with following exceptions

– Jurisdiction allows the clause– Delay was not contemplated by the parties to the contract– Delay caused by fraud, gross negligence, active interference– Delay is so unreasonable that it is tantamount to an

abandonment of the Contract by the Owner– All of the above have been completely reversed by the courts

and rulings made in various ways

Page 34: Construction Delays & Best Practices

Best Practices

Survey Says ………..

Page 35: Construction Delays & Best Practices

Owner caused suspension or delay

for unreasonable period of time

Excusable – 100%

Compensable – 100%

Page 36: Construction Delays & Best Practices

Unavoidable Utility Delay

Excusable – 95%

Compensable – 56%

Page 37: Construction Delays & Best Practices

Unusual Severe Weather

Excusable – 95%

Compensable – 8%

Page 38: Construction Delays & Best Practices

Unavoidable area-wide material

shortage that occurs after bid

Excusable – 90%

Compensable – 0%

Page 39: Construction Delays & Best Practices

Labor strikes that occur after bid

Excusable – 81%

Compensable – 9%

Page 40: Construction Delays & Best Practices

Unforeseeable and unavoidable;

such as fires, floods, and natural

disasters

Excusable – 100%

Compensable – 29%

Page 41: Construction Delays & Best Practices

Third party delay without fault or

negligence of either Owner or

Contractor

Excusable – 88%

Compensable – 31%

Page 42: Construction Delays & Best Practices

Differing Site Conditions

Excusable – 100%

Compensable – 95%

Page 43: Construction Delays & Best Practices

Damage to permanent work prior to

acceptance

Excusable – 64%

Compensable – 47%

Page 44: Construction Delays & Best Practices