ConstructioConstruction Planning Oraganisation and Equipment (CIE 403) RCS.pdfn Planning...
-
Upload
mohit-goyal -
Category
Documents
-
view
212 -
download
0
description
Transcript of ConstructioConstruction Planning Oraganisation and Equipment (CIE 403) RCS.pdfn Planning...
Reg. No:
MANIPAL INSTTUTE OF TECHNOLOGY (A Constituent College of Manipal University)
Manipal -576 104
SEVENTH SEMESTER B.E (CIVIL)
SEMESTER EXAMINATION
CONSTRUCTION PLANNING ORGANISATION AND EQUIPMENT (CIE 403)
(Revised Credit System)
Date: 5-12-2012
TIME: 3 Hours] [Max. Marks: 50
NOTE: 1. Answer any FIVE Full questions.
2. Any missing data may be suitably assumed.
1(a) Write a brief note on " Project life cycle phase" (04) 1(b) The following data pertain to the activities making up a project. Draw a neat network
diagram and number the events. (06)
Activity Predecessor
Activity
Activity Predecessor
Activity
Activity Predecessor
Activity
A - F C K F
B A G B,E L H,I
C - H B,E M F
D C I G,A,D,F N L,M,J,K
E A J G,A,D,F
2(a) Write a brief note on CPM Updating. (03)
2(b) Table below shows activity and time estimates. Determine slack, and locate the critical path. (07)
Activity to tm to Activity to tm tP
1-2 2 4 12 4-7 2 5 8
1-3 5 6 7 4-8 i 6 9
1-5 1 2 3 5-6 2 4 12
1-6 2 4 6 5-7 3 5 7
2-4 1 3 5 6-8 1 5 9
2-3 0 0 0 7-8 5 6 7
3-5 4 6 8 6-7 2 3 4
3(a) Define the terms: i) Earliest expected time, ii) Latest allowable occurrence time, iii) Optimistic time iv) Total float. (02)
3(b) The following data are available regarding the activities, their duration and cost for a
particular project. The indirect cost of the project is Rs 500 per week. Determine
optimum duration and minimum cost. (08)
Activity Normal duration Crash duration Normal cost Crash cost
1-2 7 5 1,000 2,000
1-3 9 5 2,000 6,000
1-4 6 4 3,000 5,600
2-5 6 3 2,000 2,900
3-5 8 6 4,000 4,500
4-5 6 5 3,500 4,100
4(a) Determine the probable cost of owning and operating a 10 Cum electrically operated
Mobile batching plant with following particulars.
Power required 15 units/hour; Life of equipment 20 years; Total cost of batching plant
including its transportation and erection is Rs 0.8 Crores. Total hours utilization of equipment
per year is 1300
Also compute what is the hiring price of equipment (06)
4(b) Compare Straight line and SOY methods of computing depreciation cost (04)
5(a) What are the financial alternatives in deciding deployment of equipment (05)
5(b) What are the costs involved in owning and operating an equipment (05)
6. Explain determinants of organization structure (10)