Community Meeting – Construction Update Presentation August 17, 2016

12
Construction Update Meeting August 17, 2016

Transcript of Community Meeting – Construction Update Presentation August 17, 2016

Page 1: Community Meeting – Construction Update Presentation August 17, 2016

Construction Update Meeting

August 17, 2016

Page 2: Community Meeting – Construction Update Presentation August 17, 2016

Oakland Children’s Hospital

Page 3: Community Meeting – Construction Update Presentation August 17, 2016

3

• Doug Nelson – Executive Director of Development & Construction, UCSF Benioff Children’s Hospital Oakland

• Nick Chiu and Tony Solano – JLL

• Darrel Graef, Tyler Hester – Project Superintendent, Turner Construction Company

• Ed Walsh and Abhishek Gupta – Turner Construction Company

Welcome

Page 4: Community Meeting – Construction Update Presentation August 17, 2016

4

UCSF Benioff Children’s Hospital / Turner – General Discussion

Project Communication

Upcoming Construction Activities

Where is Waldo?

Agenda

Page 5: Community Meeting – Construction Update Presentation August 17, 2016

5

• Project Communication

• Project Communication– Darrel Graef (Turner Supt) 510-764-3059– Flyers and Project Website

• notifications of change to site conditions as it pertains to the neighborhood

• http://chonext100.org

• Concerns/Issue Reporting—Contact information are posted on Site Signage and Project Website

Communication & Reporting

Page 6: Community Meeting – Construction Update Presentation August 17, 2016

6

• Metal Stud Framing at OPC-2• Overhead Mechanical & Plumbing at OPC-2• Rebar / Concrete install at Ground Floor OPC-2• Fire Proofing 7/11 – 8/26• Exterior wall Attachment • Upcoming Weekend Work. (Saturday 8:00 am – 5:00pm)

* August 27th – Prepare loading S.O.G with heavy material. This would be approximately 8 people on site.

* September 10th – Prepare to set AHUs. This would be approximately 6 workers setting up the barrier.

* September 17th – Set AHUs and other curbs. We would need 8 people on site to perform this work. A crane would be brought in as well to hoist the equipment.

* September 24th – Finalize and load the remaining equipment on the roof. This would be a couple crews stocking the building, totaling approximately 8 people.

Upcoming Major Construction Activities

Page 7: Community Meeting – Construction Update Presentation August 17, 2016

7

Progress Photos

Page 8: Community Meeting – Construction Update Presentation August 17, 2016

8

Progress Photos

Page 9: Community Meeting – Construction Update Presentation August 17, 2016

9

Progress Photos

Page 10: Community Meeting – Construction Update Presentation August 17, 2016

Oakland Children’s Hospital

Page 11: Community Meeting – Construction Update Presentation August 17, 2016

12

Questions/Discussion?

Page 12: Community Meeting – Construction Update Presentation August 17, 2016

Oakland Children’s Hospital