Community information sessions presentation

30

Transcript of Community information sessions presentation

Page 1: Community information sessions presentation
Page 2: Community information sessions presentation

Earlwood to Summer Hill cable project

Community information sessions

Tuesday 21 June - Canterbury Hurlstone Park RSL Club

Thursday 23 June - Ashfield Civic Centre

Page 3: Community information sessions presentation

3

Tonight’s session:

• Introduction to project team

• Two short presentations:

– Ausgrid overview, project need and project planning (Matthew Irla)

– What to expect during construction (Mayur Kulkarni)

• Questions, comments, feedback (community & project

team):

• Next steps:

- how your feedback will be used in the project planning

- project key dates

Page 4: Community information sessions presentation

Replacing cables between Earlwood

and Summer Hill

Area Development Manager

Matthew Irla

Page 5: Community information sessions presentation

5

Overview of electricity network

Ausgrid

Page 6: Community information sessions presentation

6

The Ausgrid network area

• 1.6 million customers – households

and businesses

• Network covers 22,275 square km

– 30,000 substations

– 48,000km of power lines and

– 500,000 power poles

• Building our network today would

cost an estimated $38 billion

• Currently owned by the NSW Gov.

Page 7: Community information sessions presentation

7

Existing cable route between Earlwood and Summer Hill

Page 8: Community information sessions presentation

8

Project need

• Existing cables:

– 33,000 Volt gas filled

– In service for approximately 50 years.

• Dedicated engineers to monitor cables

• Approaching end of service life:

– Reliability concern

33,000 Volt cable cross section

Page 9: Community information sessions presentation

9

What can we do?

1. Do nothing

2. Maintain and repair

3. Replace License requirements: To maintain a safe and reliable supply of electricity to our customers

Page 10: Community information sessions presentation

10

How we plan projects

Sustainable decisions must balance all of these factors

Page 11: Community information sessions presentation

11

Planning so far

• Initial investigations

• Pinch point areas highlighted

• Site visits and investigations

• Potential route options

• Desktop analysis

• Council meetings

• Refine to feasible route

options

Page 12: Community information sessions presentation

12

Where we are at now

Page 13: Community information sessions presentation

13

Any questions?

• Questions?

• Comments?

• Feedback?

Page 14: Community information sessions presentation

What to expect during construction

Project Manager

Mayur Kulkarni

Page 15: Community information sessions presentation

15

Typical underground cable project - excavation

Page 16: Community information sessions presentation

16

Typical underground cable project – cable trench

Page 17: Community information sessions presentation

17

Modern typical cable installation – 33,000 Volt cables

backfill

backfill

Page 18: Community information sessions presentation

18

Conduit installation

Page 19: Community information sessions presentation

19

Semi-permanent restoration following conduit install

Page 20: Community information sessions presentation

20

Joint bay installation

Page 21: Community information sessions presentation

21

Conduits entering joint bay and communications pit

Page 22: Community information sessions presentation

22

Cable pulling

Page 23: Community information sessions presentation

23

Cable joining

Page 24: Community information sessions presentation

24

Testing

Page 25: Community information sessions presentation

25

Underground 33,000 volt cable installation

Page 26: Community information sessions presentation

26

Similar recent/current cable projects

• Surry Hills to Rose Bay cable project

• Engadine cable project

• Sydney Olympic Park cable project

• Beaconsfield to Kogarah cable project

• Homebush to Rozelle cable project

• North Shore cable upgrade project

• Carlingford cable project

• Pyrmont to Camperdown cable project

• Pymble to Lindfield project

Page 27: Community information sessions presentation

27

Summary

• Modern cable installation is less disruptive, but there are still

impacts we need to manage.

• Factors to consider when planning to install cables are many

and sometimes competing.

• Experience of previous projects informs planning.

• Local knowledge is a key part of the process.

Page 28: Community information sessions presentation

28

Any questions?

• Questions?

• Comments?

• Feedback?

Page 29: Community information sessions presentation

29

Next steps:

• How your feedback will be used in the project

planning process.

– Feedback forms

– Consolidation and

incorporation into plans

– Decision

– Environmental assessment

Page 30: Community information sessions presentation

30

Key dates: