Community information sessions presentation
Transcript of Community information sessions presentation
Earlwood to Summer Hill cable project
Community information sessions
Tuesday 21 June - Canterbury Hurlstone Park RSL Club
Thursday 23 June - Ashfield Civic Centre
3
Tonight’s session:
• Introduction to project team
• Two short presentations:
– Ausgrid overview, project need and project planning (Matthew Irla)
– What to expect during construction (Mayur Kulkarni)
• Questions, comments, feedback (community & project
team):
• Next steps:
- how your feedback will be used in the project planning
- project key dates
Replacing cables between Earlwood
and Summer Hill
Area Development Manager
Matthew Irla
5
Overview of electricity network
Ausgrid
6
The Ausgrid network area
• 1.6 million customers – households
and businesses
• Network covers 22,275 square km
– 30,000 substations
– 48,000km of power lines and
– 500,000 power poles
• Building our network today would
cost an estimated $38 billion
• Currently owned by the NSW Gov.
7
Existing cable route between Earlwood and Summer Hill
8
Project need
• Existing cables:
– 33,000 Volt gas filled
– In service for approximately 50 years.
• Dedicated engineers to monitor cables
• Approaching end of service life:
– Reliability concern
33,000 Volt cable cross section
9
What can we do?
1. Do nothing
2. Maintain and repair
3. Replace License requirements: To maintain a safe and reliable supply of electricity to our customers
10
How we plan projects
Sustainable decisions must balance all of these factors
11
Planning so far
• Initial investigations
• Pinch point areas highlighted
• Site visits and investigations
• Potential route options
• Desktop analysis
• Council meetings
• Refine to feasible route
options
12
Where we are at now
13
Any questions?
• Questions?
• Comments?
• Feedback?
What to expect during construction
Project Manager
Mayur Kulkarni
15
Typical underground cable project - excavation
16
Typical underground cable project – cable trench
17
Modern typical cable installation – 33,000 Volt cables
backfill
backfill
18
Conduit installation
19
Semi-permanent restoration following conduit install
20
Joint bay installation
21
Conduits entering joint bay and communications pit
22
Cable pulling
23
Cable joining
24
Testing
25
Underground 33,000 volt cable installation
26
Similar recent/current cable projects
• Surry Hills to Rose Bay cable project
• Engadine cable project
• Sydney Olympic Park cable project
• Beaconsfield to Kogarah cable project
• Homebush to Rozelle cable project
• North Shore cable upgrade project
• Carlingford cable project
• Pyrmont to Camperdown cable project
• Pymble to Lindfield project
27
Summary
• Modern cable installation is less disruptive, but there are still
impacts we need to manage.
• Factors to consider when planning to install cables are many
and sometimes competing.
• Experience of previous projects informs planning.
• Local knowledge is a key part of the process.
28
Any questions?
• Questions?
• Comments?
• Feedback?
29
Next steps:
• How your feedback will be used in the project
planning process.
– Feedback forms
– Consolidation and
incorporation into plans
– Decision
– Environmental assessment
30
Key dates: