Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack...

21
Common CEMS RATA Failures and Risks Paula Metz Alliance Source Testing, LLC Technical Services Assistant Manager

Transcript of Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack...

Page 1: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common CEMS RATA Failures

and Risks

Paula Metz

Alliance Source Testing, LLC

Technical Services Assistant Manager

Page 2: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Introduction

Stack Testing is a labor and time intensiveprocess and requires thorough planning andcommunication to be conducted successfully.

Typically, an hour or two of pre-project planning(especially with input from production andmaintenance) can save thousands of dollars indelays, postponements and most importantly,lost production time.

Page 3: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Objectives

• Common Pitfalls

• Performance Specifications

• Certification Events and Testing Requirements

• Common Causes of Failures

• Flare Sampling Considerations

• Test Protocol and Reporting Requirements

Page 4: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Pitfalls

• Technical Review

• Electrical Power Availability

• Stack Set-up

• Site Safety

Page 5: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Pitfalls:Technical Review (cont.)

Stack Gas Data

• Temperature?

• Estimated flow rate?

• Type of flow? (i.e. induced or natural draft, fixed or variable drive fan)

• Static pressure?

• Moisture Content?

Page 6: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Pitfalls:Technical Review (cont.)

Stack Gas Data

• O2 & CO2 concentrations?

• Target parameters?

• Expected concentrations and permit limits of target parameters?

• Are any hazardous pollutants present?

Page 7: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Pitfalls:Electrical Power Availability

Disclaimer: All Mobile Laboratories are not created equal…check with your tester to verify their

power requirements.

• How close is power supply to the mobile laboratory staging

location?

• Is 480V power available? 240V power? 120V power?

• Does the source provide enough power to operate the mobile

laboratory?

• Can generators be used as an alternative to plant power?

• Is 120V power available on the stack or in close proximity to

the sampling location?

Page 8: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Pitfalls:Stack Test Setup – Stack Data

• Is the stack vertical or horizontal?

• Height to test ports from ground?

• Is the stack circular or rectangular?

• Stack diameter (circular) or width/depth (rectangular)?

• Are cyclonic flow conditions anticipated?

Page 9: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Pitfalls:Stack Test Setup – Test Ports

• Are test ports installed? How many?

• Are they located 90 degrees apart or in center of equal areas?

• What are the diameters of the test ports?

• What are the nipple lengths?

• What is the height of the test ports?

• What is the minimum EPA Method 1 criteria?

Page 10: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Typical Stack Diagram

Page 11: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Pitfalls:Site Safety• Is there a safe means available to access the test ports (i.e. ladder, stairs, man lift,

elevator)?

• Is there a safe location to conduct testing (i.e. platform, scaffolding, man lift)?

• Can the area below test location be secured?

• How high are the handrails? Are handrails cut?

• Any site specific safety issues (heat stress, respiratory concerns)?

• Work area conditions due to plant operations?

• Weather?

Page 12: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Performance Specifications:40 CFR 60 Appendix B

• PS-1 Opacity

• PS-2 SO2 and NOx (PS standard)

• PS-3 O2 and CO2

• PS-4,4A, 4B CO

• PS-5 TRS

• PS-6 Flow Rate

• PS-7 H2S

• PS-8, 8A VOC, THC

• PS-9 VOC/GC

• PS-11 PM

• PS-12A & 12B Mercury

• PS-15 FTIR

• PS-16 PEMS

• PS-18 HCl

Page 13: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Certification Events and Testing Requirements:Typical CEMS Testing Requirements

Initial Performance Testing

• Calibration Drift Test

• Linearity Test

• Response Time Test

• Interference Check

• Calibration Error Test

• Relative Accuracy Test Audit

• Continuous Opacity Meter Audit

Routine Testing (Quarterly/Annual)

• Relative Accuracy Test Audit

• Cylinder Gas Audit

• Relative Accuracy Audit

• Continuous Opacity Meter Audit

Page 14: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Causes of CEMS Failure

• Pre-test failure to properly correlate CEMS and

Reference Method Systems (DAS times, response

times)

• Incorrect calculations, rounding procedures (ex.

emission rate calculations using same molecular

weight)

• Flue gas characteristics require dilution (higher than

expected concentrations, moisture, particulate)

• Dilution CEMS vs extractive CEMS error (wet vs. dry)

• Cyclonic Flow

Page 15: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Causes of CEMS Failure

NOx Performance Trailer 4 System #1 Vs. Unit CEMS

0.90

1.10

1.30

1.50

1.70

1.90

2.10

2.30

2.50

11:33:0

0

11:34:0

0

11:35:0

0

11:36:0

0

11:37:0

0

11:38:0

0

11:39:0

0

11:40:0

0

11:41:0

0

11:42:0

0

11:43:0

0

11:44:0

0

11:45:0

0

11:46:0

0

11:47:0

0

11:48:0

0

11:49:0

0

11:50:0

0

11:51:0

0

11:52:0

0

11:53:0

0

11:54:0

0

11:55:0

0

11:56:0

0

11:57:0

0

Time

pp

m

NOx_1 ppm

Outlet NOx PPM

RM NOx, ppm

CEMS NOx, ppm

Page 16: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Causes of CEMS Failure

• Flue gas location/stratification problems

• Interferences by other flue gases

• Incorrect calibration gases (calibration dilution system; bad mixture)

• Improper calibration methods, failure to properly calibrate

• Uncorrected ambient or source effects (T, P, %H2O, especially for flow

RATAs)

• DAS problems (programmed equations, input parameters, etc.)

• System design/operation problems

Page 17: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Common Causes of CEMS Failure

• Continuous monitoring systems are approved only after they have been

installed, a 7-day drift test has been performed, and a relative accuracy

test audit has been conducted.

• Reference methods are located in 40 CFR 60, Appendix A, performance

specifications are located in 40 CFR 60, Appendix B and the quality

assurance procedures are located in 40 CFR 60, Appendix F

• More certifying methods are found in 40 CFR Part 75 Appendix A

• Most initial RATAs are due within the first 180 days of operation

• Modifications to the CEMS require recertification.

Page 18: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Flare Sampling Considerations

• Flares often can not be accessed completely independent of the

CEMS sample system.

• This is a deviation and must be approved at the protocol stage

• Isolation or cut-off valve

• If sample point can be positioned on the flare, pass-through ball valve

• The more detail provided, the better prepared your testers will be

• Excess sampled gas

• Special routing of potentially harmful gases

• Proper test trailer ventilation (if applicable)

• Mobile Laboratory Location

• Non-explosive atmosphere

Page 19: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Test Protocol & Reporting Requirements

• Due Dates

• Part 60 Testing – 30 Days Prior

• Part 63 Testing – 60 Days Prior

• Permit Testing – Varies by State

• Test Plan Requirements – SSTP, State Specific Protocol Requirements, Etc.

• Facility Information / Site Contact

• Current Permit & Limits

• Process Operating / Control System Data

Page 20: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Test Protocol & Reporting Requirements

• Basic Requirements

• Summary of Results

• Facility & Source Information

• CEMS Analyzer Information

• Methodology

• Field Data & QA/QC Data

• Process/Control System Data

• Feed Rate, Fuel, Production Rate, etc.

• Scrubber Flow, Baghouse DP, etc.

Page 21: Common CEMS RATA Failures and Risks - 4C …...Stack Test Setup –Stack Data • Is the stack vertical or horizontal? • Height to test ports from ground? • Is the stack circular

Questions/Comments

http://www.stacktest.com/resources

http://www.stacktest.com/tools

http://www.stacktest.com/capabilities

http://www.stacktest.com/industrial-services

Paula Metz

[email protected]

(281) 938-2214

70+ Stack Testing Personnel

30+QSTI Certified

Technical Services Team