COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting...

58
COMMISSIONING COMMISSIONING FIRE-LIFE SAFETY FIRE-LIFE SAFETY SYSTEMS SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning! Best Practices for Total Building Commissioning!

Transcript of COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting...

Page 1: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

COMMISSIONINGCOMMISSIONING FIRE-LIFE SAFETY FIRE-LIFE SAFETY

SYSTEMSSYSTEMS

Presenter: Mark Leafstedt, PE, CxA

2008 ACG Annual Meeting

Best Practices for Total Building Commissioning!Best Practices for Total Building Commissioning!

Page 2: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

AgendaAgenda

¡¡ Viva Las Vegas Viva Las Vegas !!

Fire Life Safety Building CodesFire Life Safety Building Codes

Means & Methods of Fire Life Means & Methods of Fire Life Safety CommissioningSafety Commissioning

ConclusionConclusion

Page 3: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

StatisticsAccording to 2005 statistics published by Insider Viewpoint Las Vegas:

80+ major casinos 133,000 hotel rooms w/ 89.2% occupancy (20,000+

more open by 2010) 38.6 million tourists• >25 billion $ in current construction • 7 out of the top 10 world’s largest hotels reside within a

five-mile radius of each other in Las Vegas • The largest hotel has approximately 5500 guest rooms

Viva Las VegasViva Las Vegas

Page 4: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Relationship to Commissioning

100% growth each year since 1950 = More construction

Schedule = Liquidated damages of up to $7 million a day

Dependency on tourism = Occupant comfort is paramount

Reputation = Need for safety and strictest codes in the country

High occupancy = Little to no time for maintenance

Viva Las VegasViva Las Vegas

Page 5: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Building Commissioning is an owner-driven requirements.

Smoke Control/ Life Safety Commissioning is a Code driven requirement.

Life Safety Cx vs Building Cx

Viva Las VegasViva Las Vegas

Page 6: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

The MGM Grand Fire

1980 fire swept through the 26-story hotel, killing 84 and injuring 679.

There were about 5,000 people in the hotel at the time.

This was the second largest hotel fire in history.

It started in the first floor restaurant and spread at a rate of 19 feet per second.

A massive fireball traveled through the casino and blew through the glass entrance doors, injuring people and destroying cars.

WHAT?

Viva Las VegasViva Las Vegas

Page 7: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

The MGM Grand Fire

The Hotel had refused to pay for the $192,000 sprinkler system.

WHY?

A wire was not properly grounded.

A compressor was not properly installed.

A supposedly smoke-free stairwell that was a crucial escape route filled with smoke.

A piece of copper was not insulated correctly.

…all of which “could have been found had the area been inspected.”

Source: Sunday, November 19, 2000, Copyright © Las Vegas Review-Journal “MGM GRAND FIRE: THE DEADLIEST DAY” by Glenn Puit

The laundry chutes failed to seal, and defects existed in the HVAC system -- all contributing to the spread of smoke.”

A fire alarm never sounded.

Viva Las VegasViva Las Vegas

Page 8: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

MGM GRAND FIRE OF 1980MGM GRAND FIRE OF 1980

Just one bad Building?

Just 3 months later, there was a fire in the Las Vegas Hilton that resulted in 8 dead and 198 injured.

Page 9: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Results of the MGM Fire

• $223 million in legal settlements

• Extensive Changes in NFPAIncluding fire protection for seismic joints, elevator standards, smoke-proof enclosures, active/passive fire protection systems

• Evolution of the following building codes for high-rise buildings1994 UBC, section 9051997 UBC, section 9052003 IBC, section 909

Globally

Viva Las VegasViva Las Vegas

Page 10: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

• History of the Building Codes

• Smoke Control Requirements

• Fundamentals of Smoke Control Systems

• Section 909 of 2003 IBC

Fire Life Safety Building Codes

AgendaAgenda

Page 11: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Building regulations date back to the beginning of recorded history. The Code of Hammurabi (2200B.C) included simple but effective building code provision. “If any architect built a house so negligently that it fell down and killed the owner’s son, then the architect’s son was put to death.”

In 1630, the City of Boston mandated that “no man shall build his chimney with wood nor cover his roof with thatch”.

The enforcement authority is derived from the 10th Amendment of the US Constitution which gives states the right to legislate for the protection of the public health, safety and welfare.

Code OverviewCode Overview

Page 12: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

History Prior to the issuance of the IBC, there were three

organizations of building officials who were responsible for developing and enforcing building codes in the United States: Building Officials and Code Administrators (BOCA)

in the Northeast and Midwest International Conference of Building Officials

(ICBO) in the West Southern Building Code Congress International

(SBCCI) in the Southeast

Code OverviewCode Overview

Page 13: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Definition

“A combination of architectural, electrical & mechanical system design approach that utilized air flow and/or pressure to contain or remove smoke during a fire event”

Code OverviewCode Overview

Page 14: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Requirements High Rise Exit

Enclosures Atriums Covered Malls Underground

Building

Code OverviewCode Overview

Page 15: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Fundamentals

Active:An active smoke control system utilizes mechanical air handling equipment, i.e. supply fans, relief fans or smoke exhaust fans to contain or remove smoke in the zone of origin.

Passive:A passive smoke control system utilizes construction barriers to maintain the smoke in the zone of origin. (Typical passive smoke control systems would be found in equipment rooms, motel rooms.)

Types of Smoke Control:

Code OverviewCode Overview

Page 16: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Section 909 of 2003 IBCSection 909.18: This section discusses:

Acceptance Testing Individual Device Testing

Detection Devices Duct Traverses

Dampers Inlet/Outlet Air Quantities

Fans Smoke Barriers

Special Inspection Reports

Code OverviewCode Overview

Page 17: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

• How Hard Can it Be? • Roles & Responsibilities• Commissioning Phases

Means & Methods of Fire Life Safety Systems Commissioning

AgendaAgenda

Page 18: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

How Hard Can it Be? Introduction Detail Timing Intensity

Means & MethodsMeans & Methods

Page 19: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

How Hard Can it Be? Introduction

Similar Process to Mechanical Cx Failures Critical Special Inspector

Means & MethodsMeans & Methods

Page 20: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

How Hard Can it Be? Detail

Simplistic in Concept Complexity in Detail & Quantity Requirements Code Prescribed 100% Testing

Means & MethodsMeans & Methods

Page 21: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

How Hard Can it Be? Timing

“DONE” Done prior to Certificate of Occupancy

Testing Concurrent w/ Construction No Post-Occupancy Deficiencies &

Issues

Means & MethodsMeans & Methods

Page 22: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

How Hard Can it Be? Intensity

Critical Construction Sequencing C3 Syndrome (Construction Completion Conjestion)

Panic

Means & MethodsMeans & Methods

Page 23: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Roles & Responsibilities Prime Contractor Subcontractors Designer Owner Commissioning Provider

Means & MethodsMeans & Methods

Page 24: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Roles & Responsibilities Prime Contractor

Construction of the Envelope Coordination Communication Scheduling Advocate!

Means & MethodsMeans & Methods

Page 25: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Roles & Responsibilities Subcontractor(s)

Provide Input into the schedule Attend meetings Provide realistic completion information Avoid defensive posturing Assist in finding resolutions Proactively & quickly respond to

deficiencies

Means & MethodsMeans & Methods

Page 26: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Roles & Responsibilities Designer

Provide detailed smoke control diagrams

Respond timely to to questions, issues, & changes

Means & MethodsMeans & Methods

Page 27: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Roles & Responsibilities Owner

Hire the Commissioning Provider (req’d by code)

Remain calm amidst the chaos Provide Contractor direction (if

necessary) to respond to Cx issues & deficiencies

Means & MethodsMeans & Methods

Page 28: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Roles & Responsibilities Commissioning Provider - General

Part coach, task-master, expert, judge & mediator

Build a Team!! Coordinate & Manage Cx Activities Obtain, assemble, create & submit Cx

documentation Meet & coordinate with the AHJ

Means & MethodsMeans & Methods

Page 29: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning Phases Life Safety System Commissioning

Phases Design & Construction Document

Review Document Development Pre-Functional Testing Functional Testing Commissioning Completion

Means & MethodsMeans & Methods

Page 30: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning Phases Life Safety System Design Review

Fire Protection Report provided? Equivalent to Design Intent (Referred to

as a “Rational Analysis”

Means & MethodsMeans & Methods

Page 31: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

FIRE PROTECTION REPORT AUGUST 6, 2004

SMOKE CONTROL

1. The overall concept includes a combination of mechanical systems and passive containment for the building. The building’s fire alarm system will be used to control, monitor and activate the mechanical smoke control systems.

2. Guestroom Levels (Levels 3-32).

a. Upon activation of a corridor smoke detector, the corridor air-handling units will shut down and elevator lobby doors will close. The smoke exhaust fans located on the roof will start. Dampers will be installed on a common shaft that will normally be used to supply outside air to the corridors and provide smoke exhaust functions during an event/alarm. All dampers will close throughout the floors served by the common shafts except the exhaust dampers will open on the fire floor. Exhaust will be sized based on Section 905 of the UBC to maintain a minimum negative pressure of 0.05 inches of water column relative to the adjacent units, elevator lobbies and stairwell vestibules on the floor of origin.

b. Each guestroom, elevator lobby, maid closet, and similar type room will be treated as passive areas. Units with interconnecting doors will be treated as one common passive area.

c. The bathroom exhaust vents are not considered a part of the smoke control system, and are not subject to pressure or leakage testing. Exhaust fans serving the toilet rooms will continue to operate and be provided with emergency power. 22-inch sub-ducts will be provided within the toilet exhaust shafts.

d. A minimum of 2 guestrooms per floor (one on each side of the corridor, with selection from both wings) will be tested as passive zones. The suites will be pressurized through the use of an approved door fan test assembly to a minimum 0.05 inches of water column to determine whether leakage is within the allowable range, as defined in Section 905 of the Building Code.

e. Verification of compliance for the corridor exhaust system will be as follows:

f. The pressure difference between the corridor and adjoining guestrooms, stairway vestibules, rooms and elevator lobbies will be confirmed to be a minimum 0.05 inches of water negative pressure.

g. Dampers will be confirmed to be in their correct position.

h. Since corridor supply is not part of the smoke control system, supply ducts will not be tested for pressure or leakage. This testing will only be conducted on ducts that are a portion of the smoke control system (exhaust/return ducts).

3. Service Level (between Levels 26 and 27).

a. The Service Level contains back-of-house areas, including storage rooms, mechanical rooms, and electrical rooms. The Service Level will be a passive zone. It will be provided with exhaust fans for Fire Department mop-up operations.

b. The exhaust fans will be manually operated by the Fire Department.

c. Verification of compliance for the Service Level system will be as follows:

i. Each area of the passive zone will be tested for leakage with a door fan test. The door fan test will be to confirm that the leakage is in compliance with UBC Section 905.2.3.

4. Tram Station Level (Level 2.5).

Means & MethodsMeans & Methods

Page 32: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning Phases Life Safety System Design Review

Are the smoke control diagrams complete?

Are all fire/smoke dampers shown? Do the sprinkler zones & smoke

boundaries match?

Means & MethodsMeans & Methods

Page 33: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

DESIGN DOCUMENTATIONSmoke Control

Diagrams - Floor Plans

Means & MethodsMeans & Methods

Page 34: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning Phases Design & Submittal Review

Are all smoke control devices included? Is the equipment compliant with the

code? Does the smoke control system

contractor’s design-build design meet the Engineer’s design, codes & AHJ criteria?

Means & MethodsMeans & Methods

Page 35: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Smoke Control Diagrams - Functional Matrix

Means & MethodsMeans & Methods

Page 36: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Passive Zone Leakage Calculations

Means & MethodsMeans & Methods

Page 37: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning Phases Document Development

Develop the commissioning plan Detailed roadmap of expectations

Develop functional testing scenarios Must include an individual check-off for

EVERY piece of equipment Submit Cx plan to the AHJ

Means & MethodsMeans & Methods

Page 38: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

DOCUMENTATION DEVELOPMENT

Means & MethodsMeans & Methods

Page 39: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

DOCUMENTATION DEVELOPMENT

Means & MethodsMeans & Methods

Page 40: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning PhasesSection Life Safety System Outline HVAC System Outline

1 Acceptance Letter Executive Summary

2 Executive Summary Commissioning Team

3 Commissioning Team Mechanical System Overview

4 Overview of Acceptance Testing Procedures Overview of Commissioning Procedures

5 Fire Protection Report Record Document - Sequences of Operation

6 Smoke Management Sequences/Matrix Pre-Functional Testing Checklists

7 Component Testing Forms Functional Testing Procedures

8 Functional Testing Scenarios & Results Deficiencies & Issues Log

9 Test & Balance Report Daily Logs

10 Product Data Sheets Miscellaneous Data

11 Deficiencies & Issues Log

12 Daily Inspection Reports

13 Non-Compliance Reports

14 Miscellaneous Data

Means & MethodsMeans & Methods

Page 41: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning Phases Pre-Functional

Assist in component pre-testing before functional

Individually confirm F/S Damper commands and status feedback.

Confirm fan command & status Review FAS software “rules”

Means & MethodsMeans & Methods

Page 42: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

COMPONENT INSPECTIONPressurization Fan

Means & MethodsMeans & Methods

Page 43: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

COMPONENT INSPECTION Fire Smoke Damper

Means & MethodsMeans & Methods

Page 44: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

COMPONENT INSPECTION Fire Command

Means & MethodsMeans & Methods

Page 45: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

COMPONENT INSPECTIONFire Fighter’s Smoke Control Panel

Means & MethodsMeans & Methods

Page 46: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

COMPONENT INSPECTIONFire Protection Flow Station

Means & MethodsMeans & Methods

Page 47: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning Phases Pre-Functional

Provide site observations & barrier inspection

Means & MethodsMeans & Methods

Page 48: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

BOUNDARY INSPECTION

Conduit Penetrations

Means & MethodsMeans & Methods

Page 49: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

BOUNDARY INSPECTIONFloor Slab Penetrations

Means & MethodsMeans & Methods

Page 50: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

BOUNDARY INSPECTIONDuct Penetrations

Means & MethodsMeans & Methods

Page 51: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

BOUNDARY INSPECTIONElevator Shaft Enclosure

Means & MethodsMeans & Methods

Page 52: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning Phases Functional Testing

When does FT begin? Does construction have to be complete? How can FT be phased? How can multiple tests be avoided?

Means & MethodsMeans & Methods

Page 53: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning Phases Functional Testing

Assist in or define testing teams Witness functionality testing of the

system Include component interaction Track deficiencies

Means & MethodsMeans & Methods

Page 54: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

PASSIVE ZONE TESTING

Means & MethodsMeans & Methods

Page 55: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

DUCT DETECTOR TESTING

Means & MethodsMeans & Methods

Page 56: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Commissioning Phases Commissioning Completion

Submit final report to AHJ Correct report deficiencies Assist in coordination & scheduling of

AHJ Assist during the AHJ inspection ALL SYSTEMS TESTING!

Means & MethodsMeans & Methods

Page 57: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Summary Discussed Critical Nature of Life

Safety Systems Reviewed Code Requirements Discussed Life Safety System

Commissioning Means & Methods Encourage Life Safety System

Commissioning in other Cities

ConclusionConclusion

Page 58: COMMISSIONING FIRE-LIFE SAFETY SYSTEMS Presenter: Mark Leafstedt, PE, CxA 2008 ACG Annual Meeting Best Practices for Total Building Commissioning!

Questions Questions ?? Thanks for your

attention!

www.testmarc.com