Building Commissioning & Optimization CHANGING CODES, GREEN CERTIFICATIONS, AND FUNDING JUNE 22, 2017

Transcript of Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding...

Page 1: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Building Commissioning & OptimizationCHANGING CODES,  GREEN CERTIFICATIONS, AND FUNDING

JUNE 22,  2017 

Page 2: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Learning ObjectivesWhy We Commission Buildings

Understanding CMAA Sustainability Guidelines

2016 CA Title 24 Commissioning Updates

2016 CA CHPS and LEED v4 Updates

How Owners Apply High Performance Standards and Funds

Commissioning Process

Hiring a Commissioning Agent 

Page 3: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Presenters

Vince MadsenDirector, Facilities PlanningWiseburn Unified School District13530 Aviation Blvd.Hawthorne, California 90250O: (310) [email protected]

Jim Ogden, LEED Fellow, CxA+BEPrincipal, Southern California Region155 N Lake, Suite |Pasadena|CA 91203O: (949) 681-7084 | C: (916) [email protected]

James Becker, PE, CxA, EMPPrincipal950 Glenn Drive, Suite 200|Folsom|CA 95630O: (916) 496-8400 | C: (530) [email protected]

Page 4: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

WiseburnUnified School DistrictEstablished in 1896

November 5, 2013 ‐Wiseburn becomes a unified school district permitting it to establish a high school.

Top Rated Schools

2,500+ Students

Aerospace, Corporate, and Hi‐Tec Community

Great Business Partnerships

Page 5: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

3QC –Enlightened BuildingsCommissioning & Sustainability Services Firm

Title 24, LEED and CHPS Experts

Celebrating 14 Years

Offices in Los Angeles, San Diego, and Sacramento

Technical Experts – Licensed Engineers, Cx Agents, EMP’s

PM / CM Background and Approach

Metrics Oriented

Collaborative and Integrative Process

Certified Small Business

Page 6: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

MessageNeed To Educate and Inform

Quality Process

Saves Money

Facilitates Schedule

Benefits Entire Team

REQUIRED BY CODE !!!!

Page 7: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Why Commission?AB 32

Moving to Zero

Code Required

Saves Resources

Wellness

Comfort

Reduce Risk

User Satisfaction

$$ Incentives

Page 8: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

We Commission to ZeroGreenhouse Gas Reduction

Time Dependent Value –Societal Based

Zero Net Energy – Source Based

Energy Use/Utilization Index –Move to Zero

Renewable Energy Credit

2020 target for all residential new construction to reach

2030 target for all commercial new construction to reach

Page 9: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

We Commission to ConserveEnergy  and Water

Time of Use

Energy Sources

Reliability

Page 10: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

We Commission for WellnessTemperature

Light and Views

Acoustics

Tenant Comfort

Page 11: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

TemperatureThermal ComfortControls and ControllabilityEnergy Efficiency

Page 12: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

LightGlare vs DaylightingControlsEnergy Savings

Page 13: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

LightDaylighting Dark StopsIneffective ClearstoryNot Integrated or Modelled

Page 14: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

AcousticsMechanical VibrationDucts

Page 15: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

We Commission to Reduce RiskReduce Change Orders

Reduce Warranty Claims

Improve Collaboration

Reduce First Cost

Improve O&M Turnover

Improved Thermal Comfort

Optimize Systems

Page 16: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Optimized SystemsIntegrated and ComplexSystems Manual / Operations and Maintenance Plan

Page 17: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

User SatisfactionPost‐Occupancy EvaluationWarranty Reviews

Page 18: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Owner’sProject

Requirements

BasisOf

Design

CxPlan

DesignDevelopReview

CxSpecifications

COMMISSIONING BEST PRACTICES

CDReview

SiteVisits &

Inspections

IssuesLog

Quality Checklists

OwnerTraining

Cx ReportFunctionalTesting

SubmittalReview

SystemsManual

SeasonalTesting

WarrantyReview &LessonsLearned

ACCEPTANCECONSTRUCTION OCCUPANCYDESIGN

GoalsWorkshop

PRE‐DESIGN

Monitor &Measure

OccupantSurvey

MEASUREVERIFY

Page 19: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Codes, Standards & Rating SystemsTitle 24CMAA Sustainability GuidelinesGreen Rating Systems

Page 20: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Title 24 ClarificationPart 1 ‐ California Building Standards Admin Code

Part 2 ‐ California Building Code

Part 3 ‐ California Electrical Code

Part 4 ‐ California Mechanical Code

Part 5 ‐ California Plumbing Code

Part 6 ‐ California Energy Code

Part 7 ‐ California Elevator Safety Construction Code

Part 8 ‐ California Historical Building Code

Part 9 ‐ California Fire Code

Part 10 ‐ California Code for Building Conservation

Part 11 – California Green Building Standard (CalGreen)

All Energy Related Systems (including plumbing) and CxA Qualifications

Irrigation & Controls

Page 21: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Title 24 Design ReviewsPhase Deliverable

Pre‐Design Owners Project Requirements (OPR)

Schematic Design Basis of Design (BOD)

Design Review Kick‐Off Meeting

Design Development Commissioning Specifications

Construction Documents Commissioning Plan

95% Design Review

Agency Forms

Page 22: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

T24 Envelope Commissioning2016 Title 24 Requires:

Design Review at 95% CD’s

Joints & Other Openings

Insulation & Roofing Products

NRCC‐CXR‐02‐E Design Review Checklist

BECx

Page 23: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

CMAA Sustainability GuidelinesSustainable development is development that meets the needs of the present without compromising the ability of future generations to meet their own needs.

Page 24: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

2016 CA‐CHPS RequirementsEffective based on DSA Intake

3rd Party CxA for All Projects

Combines Fundamental and Enhanced as Prerequisite

Pre‐Design Commissioning to Warranty Review

Participates in Integrated Design Workshops

Irrigation Cx in Water Category

Extra Credit for Building Envelope Cx

Extra Credit for PE or RA Cx Leader

Extra Points for BMS

Page 25: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

2016 CA‐CHPS SystemsMECHANICAL

HVAC systems (such as hot water systems, chilled water systems, central air systems, ventilation systems)

Domestic hot water systems Energy management system Renewable energy heating systems Plumbing Systems: Flow control devices Pumping systems Special hazardous waste treatment

systems Graywater systems (if applicable)

ELECTRICAL

Lighting systems and lighting controls (daylight, occupancy, timing switches, etc.)

On‐site renewable solar electric or wind system

Page 26: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Other GuidelinesLiving Building Challenge

WELL 

Envision

Breeam

GRESB

ParkSmart

Green Globes

Energy Star

Page 27: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

LEED v4OCTOBER 31, 2016 RAISING THE BAR

Page 28: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

LEED 2009 to v4 Cx ChangesEnhanced Cx has increased from 2 points to 3 points

LEED v4 now requires the CxA to be engaged before the design development phase is complete.

The electrical and plumbing scopes have been expanded.

Elements of envelope commissioning are now incorporated in the OPR and BOD.

An operations and maintenance plan is now required.

Page 29: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Integrative ProcessSynergies & Strategies for energy and water

Start in Schematic Design & continue thru Design Phase 

Conduct prelim energy & water researchSimple box energy model during SDsWater budget analysis

OPR / Goal setting workshop

Evaluate Strategies

Document how analysis informed design, OPR & BOD

Page 30: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Integrative Process

Design‐BuilderDesigns and Builds to OPR

CommissioningEnsure Design Performance

OPRProject Goals & Objectives

Energy ModelingInforms Design, Comfort, and Predicts Performance

Measure & VerifyTrack & Manage 

Performance

PolicyEstablishes Direction

Page 31: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Integrative Process

1

2 5

OPRImportant to the Owner

BODPerformance Criteria

SpecsPerformance Requirements

ReviewCommunicatePerformance 

SubmittalsCompliantEquipment 

Test PlanPerformanceVerification 

3

COMMISSIONING FOR ZNE

6

4

Page 32: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Energy MeteringPrerequisite & Code: Building Level Energy Metering

Building level meters for total bldg energy consumption: electric, natural gas, chilled water, steam, fuel oil, propane, etc

Compile data monthly, manual or automated

Commit to share for 5 years

Optional: Advanced Energy Metering

Whole building energy sources, plus

Major users >10% of total load

Record to remote location

<1hr intervals, remotely accessible

Record consumption & demand

Page 33: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Fundamental CommissioningDoes NOT Comply with T24 Alone

List of  12 things CxA does

ASHRAE Guideline 0 & 1.1

Envelope included in OPR, BOD, & Design Reviews

CxA on board by end of DDs

Prepare & Maintain Facilities Requirements & OM Plan

Design Review

Elec & Plumbing Scope Expanded

Page 34: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Enhanced CommissioningOption 1

Path 1:  (3 points)◦ Enhanced Cx, similar to LEED 2009◦ Added Seasonal Testing◦ Added Re Cx Plan

Path 2:  (4 points)◦ Path 1 + Monitoring Based Measurement & Verification of Energy & Water Systems

Option 2

Envelope Cx  (2 points)

Don’t have to do Option 1 to earn Option 2

Page 35: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Envelope Commissioning

BECx Design Reviews

Cx Design Reviews

OPRZNE

Submittals

Begin Functional Testing

Begin Prefunctional 

Testing

Mock‐Up Testing

Final Site Visit & Field Test

Initial Site Visit

Shop Drawings

Initial Field Test

MEP SYSTEMS

ENVELOPE SYSTEMS

Page 36: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Connecting the Dots2016 Title 24, Part 6 and 11 LEED v4 BD+C 2016 CHPS

HVAC & Controls HVAC & Controls HVAC & Controls

Lighting & Controls Lighting & Controls Lighting & Controls

Service Hot Water Service Hot Water Domestic Hot Water

Irrigation Controls Irrigation Controls

Building Level Water Meters Building Level Water Meters Building Level Water Meters

Building Enclosure (Design Review Only)

Building Enclosure (Design Review Only)

Building Enclosure (Design Review Only)

Demand Response (DesignReview Only)

Demand Response Demand Response

Electric Service & Distribution Systems

Hazardous Waste (lab)

Plumbing Pumps and Controls

Pumps and Flow Control Devices

Page 37: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

How Owners Should Apply High Performance Standards 

Lessons Still Being Learned

Page 38: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Wiseburn Unified School DistrictJuan de Anza Elementary School

Juan Cabrillo Elementary School

Peter Burnett Elementary School

Richard Henry Dana Middle School

Da Vinci Innovation Academy

Da Vinci Communications

Da Vinci Design

Da Vinci Science

Page 39: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

School Bond EffortsMeasure A($32.6M) – June 2007: Build Cabrillo ESReplace 60‐year old facility, construct, acquire and improve school facilities Measure AA ($88M) ‐ Nov. 2010:New high school for WiseburnProvide state of the art computers, labs and modern classroom technologyMeasure CL ($11M) – Nov. 2012:Maintain educational programs

Page 40: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Facilities ManagementProject Delivery

PM / CM

Commissioning Agent

LEED Certifications

Renewable Energy

Collaboration

Green Operations & Maintenance

District Sustainable and Energy Project Manager

Facilities

CxA Energy Specialist PgM

Architects

Contractors

CM

Page 41: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

District SustainabilityWe think we’re already sustainable. Isn’t that the Architect’s job? Doesn’t the building code make us sustainable?What did we do on the other sites? Oh wait, what does sustainability really mean?

Page 42: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Wiseburn High School330,000 SF

4‐Story Building

$160M

LEED Silver

Design/Bid/Build

Architect‐Gensler: designed to support an interdisciplinary curriculum where students engage in a hands‐on learn‐by‐doing model

Page 43: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Wiseburn High SchoolHouses Da Vinci’s three independent charter high schools: 

Da Vinci Communications

Da Vinci Design

Da Vinci Science 

Each floor designated to a specific school with its own principal and faculty.

District Goal – Complete Phase 1 by Aug. 2017 and initiate Phase II by Dec. 2016 with a scheduled completion of Jan. 2018.

Page 44: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Gymnasium & PoolAn additional phase of work on the new Wiseburn High School campus. 

The gymnasium is approx. 41,000SF 

Includes:

Ticket offices (City/District)

Men’s & women’s shower/locker rooms

Student restrooms

Multi‐purpose room

LEED Enhanced Cx

Page 45: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Process Lesson: Engage CxA EarlyCommissioning isn’t important until the end of the project.

◦ Symptom: Hired after Bid Phase. Chaotic commissioning process with high degrees of stress. CxA playing catch‐up while still trying to deliver value to the Owner. 

◦ Consequences: Quality suffers. Poor communications between Owner, A/E, M&O stakeholders and the Commissioning Agent. 

◦ Solution: Engage the Commissioning Agent prior to Schematic Design. PM/CM understands commissioning benefits and realizes how to manage the CxA to contribute to a satisfied Owner and User experience.

Page 46: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Process Lesson: Missing or Inadequate OPRFailure to start with the end in mind.

◦ Symptom: Validation of project successes  are difficult or impossible to perform due to lack of project performance goals. 

◦ Consequences: Operations continue without a high level of confidence that design intent will be reached and maintained. 

◦ Solution: CxA facilitates an OPR Workshop prior to Schematic Design. Establish a disciplined project goals documentation process to maintain the focus on human comfort goals and equipment expectations.

Page 47: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Process Lesson: Failure to Understand RolesDelineation of individual roles is a critical project requirement.

◦ Symptom: Multiple individuals are attempting to fulfill the same role, or several individuals are taxed with too many responsibilities. Misallocated risks and gaps. Critical control sequences left to D/B or GC.

◦ Consequences: ASSumptions. Invalid submittals, delayed testing schedules, need to repeat tests, lack of team cooperation.

◦ Solution: Partnering. Specifications and Cx Plan will provide clear delineation of roles of A/E, Contractors, Commissioning Agent, Facility and IT staff in terms of who performs which series of tasks and the required deliverables for each.

Page 48: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Process Lesson: Identifying Weak LinksCommissioning reviews and Constructability reviews are different.

◦ Symptom: CxA’s first review is delayed until 95% CDs. Various component operational parameters are not identified and left for the subcontractor to determine. 

◦ Consequences:  Critical path time is spent determining how the systems operate together. 

◦ Solution: A Cx checklist of anticipated functionality inputs and outputs is derived for each critical component and together as an integrated system during the design phase. Use an Interdisciplinary Matrix. 

Page 49: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Process Lesson: Invalid Operational SequencesCritical systems require more definition.

◦ Symptom: The intent is unclear and is misinterpreted by various members of the team. CxA can’t define how to test.

◦ Consequences: Commissioning tests experience a series of false starts and commissioning steps are incomplete. Increased likelihood of occupant complaints and costly adjustments once the facility is operating.

◦ Solution: Draft the Functional Test Plans while reviewing design documents. Rehearse the sequences during the design phase with Engineer of Record to ensure all procedures are understood and testable. 

Page 50: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Process Lesson: Facilities Staff InvolvementFailure to engage early in the process.

◦ Symptom: “I don’t have the time”. “Nobody listens to us anyway”. Operators are absent until turn‐over. Systems run in manual/hand mode. 

◦ Consequences: Commissioning and systems operational quality suffer at critical transition point. Unnecessary warranty calls.

◦ Solution: Involve Facilities Staff early in the design process. Encourage participation in commissioning meetings and testing. Require O&M manuals prior to training. 

Page 51: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Process Lesson: Compressed ScheduleFailure to consider the impact of a compressed schedule on commissioning activities.

◦ Symptom: Commissioning team is consistently logging long hours. Functional Testing is interrupted or compromised entirely.

◦ Consequences: Shortcuts or loss of logical sequence continuity jeopardizes quality and comfort.  Lack of coordination putting significant pressure on the ability to complete commissioning work in a timely fashion. 

◦ Solution: Before committing to a reduced schedule, understand the following sequences:

Installation Verification         Start‐Up/Pre‐Functional       TAB 

TAB Validation         Functional Testing        Building Flush

Page 52: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Process Lesson: Failure to Understand ValueCommissioning is only for “green” projects &  adds bureaucracy.

◦ Symptom: ‘It costs too much”. Budget cuts under the guise of  “value engineering” diminish the role of the Commissioning Agent. 

◦ Consequences: Commissioning and systems operational quality takes back‐seat to schedule and budget. Plan‐check kick‐back.

◦ Solution: Incorporate commissioning budgets early in the project process and be prepared to often restate the benefits of commissioning. Maintain Issues Log and resolutions. Track avoided costs due to commissioning and share with stakeholders.

Page 53: Building Commissioning & Optimization - CMAASCcmaasc.org/pdfs/062217presentation.pdfBuilding Commissioning & Optimization ... Does NOT Comply with T24 Alone List of 12 things CxA does

Questions & Answers

Vince MadsenDirector, Facilities PlanningWiseburn Unified School District13530 Aviation Blvd.Hawthorne, California 90250O: (310) [email protected]

Jim Ogden, LEED Fellow, CxA+BEPrincipal, Southern California Region155 N Lake, Suite |Pasadena|CA 91203O: (949) 681-7084 | C: (916) [email protected]

James Becker, PE, CxA, EMPPrincipal950 Glenn Drive, Suite 200|Folsom|CA 95630O: (916) 496-8400 | C: (530) [email protected]