Commissioning: Concepts and Applications May 6, 2011 Steven M. Patterson, PE, CEM.
-
Upload
georgiana-page -
Category
Documents
-
view
223 -
download
0
Transcript of Commissioning: Concepts and Applications May 6, 2011 Steven M. Patterson, PE, CEM.
2011 VEPGA Annual Meeting2
• Commissioning – A process to ensure a system works in accordance with
design intent
– Different Sub-Types
Introduction
2011 VEPGA Annual Meeting3
Main Benefits
• Building / Systems Works Properly!
• Energy Savings
• Reduced Maintenance Costs
• Extend Equipment Life
• Improved Space Comfort
• Building Certification
2011 VEPGA Annual Meeting4
• Commissioning – New Car (at the factory)
• Recommissioning– Vintage Car Restoration
• Retrocommissioning– First Time Doctor Visit (physical)
• Continuous Commissioning ™– OnStar™ Vehicle Diagnostics System
Types of Commissioning
2011 VEPGA Annual Meeting5
American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc.
National Institute of Building Sciences / Whole Bldg Design Guide
Online Cx Document Generation/Mgmt Tool by Energy Design Resource
Portland Energy Conservation, Inc.
Building Commissioning Association
California Commissioning Collaborative
Mechanical Service Contractors of America & Mechanical Contractors
Association of America
AABC Commissioning Group (ACG) a subsidiary of Associated Air Balance Council (AABC)
Association of Energy Engineers National Energy Management Institute / Testing Adjusting and Balancing Bureau
National Environmental Balancing Bureau V
Commissioning Applicability
Commissioning Type Most Applicable Scenario
Commissioning New Building / System
Recommissioning Existing Newer (<5yrs) Building / System
Retrocommissioning Older Building / System
Continuous Commissioning™ New or Existing Building / System
2011 VEPGA Annual Meeting6
American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc.
National Institute of Building Sciences / Whole Bldg Design Guide
Online Cx Document Generation/Mgmt Tool by Energy Design Resource
Portland Energy Conservation, Inc.
Building Commissioning Association
California Commissioning Collaborative
Mechanical Service Contractors of America & Mechanical Contractors
Association of America
AABC Commissioning Group (ACG) a subsidiary of Associated Air Balance Council (AABC)
Association of Energy Engineers National Energy Management Institute / Testing Adjusting and Balancing Bureau
National Environmental Balancing Bureau V
• American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (ASHRAE)• Guidelines
• GL 0-2005 (Cx Process)• GL 1.1-2007 (HVAC Cx Process)
• National Institute of Building Sciences (NIBS) / Whole Bldg Design Guide• Guidelines
• GL 3-2006 (Exterior Enclosure)• GL 2, 4, 5, 6, 7, 8 (different building systems)
Protocols & Guidelines
2011 VEPGA Annual Meeting7
American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc.
National Institute of Building Sciences / Whole Bldg Design Guide
Online Cx Document Generation/Mgmt Tool by Energy Design Resource
Portland Energy Conservation, Inc.
Building Commissioning Association
California Commissioning Collaborative
Mechanical Service Contractors of America & Mechanical Contractors
Association of America
AABC Commissioning Group (ACG) a subsidiary of Associated Air Balance Council (AABC)
Association of Energy Engineers National Energy Management Institute / Testing Adjusting and Balancing Bureau
National Environmental Balancing Bureau V
1. Portland Energy Conservation, Inc. (PECI)
2. Building Commissioning Association (BCA)
3. National Energy Management Institute / Testing Adjusting and Balancing Bureau (TABB)
4. National Environmental Balancing Bureau (NEBB)
5. California Commissioning Collaborative (CCC)
6. Mechanical Service Contractors of America & Mechanical Contractors Association of America (MSCA, MCAA)
7. American Commissioning Group (ACG) a subsidiary of Associated Air Balance Council (AABC)
8. Association of Energy Engineers (AEE)
9. Online Cx Document Generation / Mgmt Tool by Energy Design Resource (EDR)
Popular Resources
2011 VEPGA Annual Meeting8
• Definition – QA Process of documentation, testing, adjusting, verification and training to ensure completed building operates in accordance with requirements and construction documents.
• Applicable – New Systems / Building
• Project Objectives– Construct a building, Performance, Timeline, LEED
• Documentation– Design docs
• The Team – Commissioning Agent is part of the TEAM
Commissioning (New Car)
2011 VEPGA Annual Meeting9
Process (ASHRAE)1. Pre-Design
• Reqs, scope, budget
2. Design• BOD, Des review
3. Construction• Final plan, submittals,
procedures
4. Acceptance• O&M Manual review,
Training, Funct. Testing, Deficiencies
5. Post-Acceptance• Maint Mgmt, Off season
testing
Commissioning
2011 VEPGA Annual Meeting10
• Cost – 0.5-0.75% of total Const Cost per RS Means
• How to Buy – Certified Commissioning Authority hired by Owner or GC
Commissioning
• Keys– Expertise/Experience/
Qualifications– Accurate Scope Definition– Integral to project team– Coordination among Team
members– Turnover – Docs, Training,
Equipment, Cx it !
2011 VEPGA Annual Meeting11
• Definition– Systematic Process to Return Systems/Building to original design
Intent; (Intent – Retest Periodically)
• Applicable – Existing Newer Building / System
• Project Objectives
Recommissioning (Vintage Car)
• Documentation– As-builts, Utility Bills, O&M
Documents, Previous Commissioning Reports
• The Team
2011 VEPGA Annual Meeting13
• How to Buy – – Owner hires professional firm– Can be stand-alone or part of turnkey improvement
program– Necessary to pursue prerequisites for LEED certif.
• Cost / Payback – Varies greatly; Up to $0.20/sq.ft– Payback is attractive depending on SOW!
• Keys– Same as for Commissioning– More open ended – focus on objective and plan
Recommissioning
2011 VEPGA Annual Meeting14
• Definition– Systematic Process to Optimize Buildings’ Operation
• Applicable – Older Building / System
• Project Objectives - Examples– Verify that a facility and its systems meet the Current Facility
Requirements– Improve building performance by saving energy and reducing
operational costs– Identify and resolve building system operation, control and
maintenance problems
Retrocommissioning (Doctor visit)
2011 VEPGA Annual Meeting15
• Documentation– As-builts, Utility Bills, O&M Documents
• Process (BCA)
Retrocommissioning
2011 VEPGA Annual Meeting16
• The Team – Maint Staff, Engineering, Leader
• How to Buy – Hire a professional firm
• Cost / Payback*– Cost: $0.10 - $0.20/sq.ft.– Payback: 1-3 years
• Keys– Same as Commissioning & Recommissioning
* Source: A Retrocommissioning Guide for Building Owners by PECI
Retrocommissioning
2011 VEPGA Annual Meeting17
Retrocommissioning
Source: PECI
Most Frequently Implemented
Optimize airside economizer
Reduce equipment runtime
Reduce / reset DSP setpoint
Revise control sequence
Add / optimize SAT reset
Add VFD to pump
Reduce lighting schedule
Replace/repair/calibrate sensor
Top Savings/Sq.Ft.
Tune / Upgrade controls
Add / Optimize HWST reset
Relocate / shield temp sensor
Add / optimize boiler lockout
Add small A/C unit
Add VFD to chiller
Add / optimize chiller staging
Lower / reset VAV box flow
Optimize waterside economizer
2011 VEPGA Annual Meeting18
Retrocommissioning
Source: PECI
Most Frequently Implemented
Optimize airside economizer
Reduce equipment runtime
Reduce / reset DSP setpoint
Revise control sequence
Add / optimize SAT reset
Add VFD to pump
Reduce lighting schedule
Replace/repair/calibrate sensor
Top Savings/Sq.Ft.
Tune / Upgrade controls
Add / Optimize HWST reset
Relocate / shield temp sensor
Add / optimize boiler lockout
Add small A/C unit
Add VFD to chiller
Add / optimize chiller staging
Lower / reset VAV box flow
Optimize waterside economizer
2011 VEPGA Annual Meeting19
“Top 10” HVAC Opportunities
1. Verify lighting controls schedules/effectiveness2. Terminal unit tune-ups – dampers & valves3. Improve cooling tower sequencing/lower condenser
water temps4. Improve chiller sequencing5. Return VFDs to variable speed operation6. Optimize supply air static pressure set points7. Ensure proper ventilation airflow rate8. Optimize/restore economizer operation9. Implement reset schedules to eliminate simultaneous
heating and cooling10.Turn off equipment when not needed (Scheduled S/S)Source: EMC Engineers, Inc.
2011 VEPGA Annual Meeting20
• Building Works Well…. TODAY!• Entropy is not our Friend
• Definition– Ongoing process to resolve oper problems, improve
comfort, reduce energy using monitoring technology– AKA: Monitoring Commissioning, On-Going
Commissioning
• Another Definition – using energy management systems + internet + computers + engineering expertise to monitor and operate the building to maintain peak performance
Continuous Commissioning™ (OnStar™)
2011 VEPGA Annual Meeting21
• Process– Set up:
• Initial audit to gather, archive and analyze data.
• System Connectivity
– Manage:• Gather and archive data remotely on an continuous basis.
• Analytics are used to identify suspect building behavior.
• Advanced heuristics (using experience to learn) identify trends and deviations that humans can’t detect.
• Fieldwork to define and document suspect behavior, diagnose and correct deficiencies, and make improvements.
Continuous Commissioning™
2011 VEPGA Annual Meeting22
• Complex systems require 24/7 monitoring to ensure timely detection of and response to issues.
• Alarm Management– Centralized Operations –expert source to collect and report critical alarms.– Critical alarm history is archived.– A notification service.
• Alarm Response– Diagnosis of alarms and remote resolution– Typical notification by e-mail, text message, or voice call.– Intelligent mobilization of local resources. Local resources arrive with a probable
diagnosis and recommended response – this yields lower repair costs and faster return to normal operations.
– A monitoring and digital response service combined with physical response.
• These yield energy savings in a few ways:– Alarms based on energy usage can substantially
impact demand charges– Alarms based on equipment behavior can impact
consumption charges– Reviewing alarm history can provide clues to
performance issues
Remote Monitoring
2011 VEPGA Annual Meeting23
Current Model:Problem Recognition and Correction
Spring PM
Fall PM
Problem Occurrence
Intelligent Services:
Problem Occurrence
Immediate Recognition Enabling Fast Resolution
Energy Cost Avoidance
Performance Reports
Documented Value
En
erg
y u
sag
e
Time
Continuous Commissioning
2011 VEPGA Annual Meeting24
Did you ever consider . . .
• The bulk of your energy conservation rests on four sensors:– CO2 (Demand Control Ventilation)– Enthalpy (OA temp and RH)– Photocell (light/shade control)– Rain (irrigation)
• The decisions made on the data from these sensors are then executed through switches or actuators
• Each of these components costs around $300, or about the same as 3000 kWh of electrical consumption.
• You likely bought these through a low bid process
2011 VEPGA Annual Meeting25
What the pros know:
• CO2 sensors typically have one, three, or five year calibration requirements (or nowadays, replacement)
• Humidity sensors are notoriously prone to drift
• Birds think photocells were specifically designed for them to foul
• Rain sensors are a favored home for spiders and dirt
• Actuators and dampers are moving parts
2011 VEPGA Annual Meeting26
Project Documentation
• Project is only as good as Project Documentation
• Request sample prior to hiring
• Request samples while working on a project
• Store the final documents carefully
2011 VEPGA Annual Meeting27
Call to Action
• You have building improvement opportunities
• Technology and Processes NOW exist to help you
• Expertise to support your objectives exists
• Manage your Building Portfolio Wisely
• Set your Goals and Get Started!
Contact Information:Steve PattersonBoland Trane30 W. Watkins Mill RoadGaithersburg, MD240-306-3250 [email protected]