Commission for Regulation of Utilities Greenlink ... · Ireland, interconnectors can allow cheaper...
Transcript of Commission for Regulation of Utilities Greenlink ... · Ireland, interconnectors can allow cheaper...
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
Determination Paper
Reference: CRU/18/216 Date Published: 18/10/2018 Closing Date: N/A
An Coimisiún um Rialáil Fóntas
Commission for Regulation of Utilities
Greenlink Electricity
Interconnector
Determination
www.cru.ie
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
1
Executive Summary
The Greenlink Interconnector is a proposed 500 MW HVDC electricity interconnector, which
is being developed by Element Power, linking the power grid in Ireland and GB. It is
anticipated that the link will provide a new grid connection between the Great Island
transmission substation in Wexford and Pembroke transmission substation in South Wales.
Figure 0: Graphical Illustration of Greenlink (Image source: Element Power)
In December 2017, Element Power submitted an interconnector application under Section 2A
of the Electricity Regulation Act 1999. In its application Element Power requested the CRU
to:
1. determine if the construction of the Greenlink interconnector is in the public interest
for the project to be considered to be part of the transmission system for the purposes
of calculating and imposing charges for the use of the transmission system; and
2. approve the proposed charging methodology for Greenlink pursuant to section 35 of
the Act which is based on a 25 year Cap and Floor regime.
In June 2018, the CRU published Element Power’s application and a CRU consultation
paper (CRU18119) requesting views on the initial assessment of Greenlink by the CRU. The
CRU noted in the consultation paper that the assessment of Greenlink involves two stages:
1. testing the public interest case of the proposed interconnector by reviewing a Cost
Benefit Analysis (CBA) of the project; and
2. determine the best approach on a Cap and Floor mechanism.
This determination paper focuses on the first stage, i.e. the public interest test. The precise
details of any cap and floor regime would need to be consulted upon and determined at a
later stage.
The CRU has reviewed the consultation responses and considered the points raised by
respondents. In addition, the CRU has conducted its own CBA of Greenlink to test the
boundaries of Element Power’s CBA and the key inputs and assumptions which may drive
better or worse outcomes for Irish consumers and other stakeholders. The CRU has
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
2
modelled ENTSO-E TYNDP scenarios and compared the CBA results to those of Element
Power.1
The consultation paper noted that if the CRU CBA revealed that Greenlink would generate
overall (net) benefits to Irish consumers then the CRU would go on to consider the
appropriate regulatory regime that is justified by public interest.
The focus of this paper is to set out CRU’s determination that the Greenlink application
meets the public interest.
The results of the CRU CBA2 of Greenlink are summarised below:
• Although there are differences between CBA modelling scenarios and assumptions
adopted by the CRU and Element Power, overall the CRU CBA results are consistent
with the findings of Element Power. They show that Greenlink has the potential to
deliver benefits for Irish consumers where significant decarbonisation of electricity
generation occurs.
• The CRU modelling indicates that in relatively conservative scenarios of
decarbonisation of electricity generation in Europe, Greenlink does not drive benefits
for Irish consumers.
• In a scenario where another new interconnector is added alongside Greenlink, e.g.
another interconnector to France, consumer benefits from Greenlink appear to be
significantly reduced.
• There are potential security of supply benefits for the Single Electricity Market (SEM)
with the introduction of Greenlink.
• The CRU Brexit sensitivity3 assumes that there would be trading frictions4 between
GB and the countries it is connected to via an interconnector. Trading frictions
between countries would result in less efficient trading, less efficient interconnector
usage, greater price divergence, and hence potentially higher cost for consumers. As
a consequence of these frictions, the overall net benefits in SEM are lower under the
Brexit sensitivity than under a no Brexit scenario. Because of the underlying
inefficiencies, introducing a new interconnector may unlock more benefits to Irish
consumers compared to a no Brexit scenario where no trading frictions are present.
• The addition of Greenlink would have a small negative impact on annual power sector
gas demand and an even smaller corresponding impact on total annual gas demand.
• Both CRU’s CBA and Element Power’s CBA show that Greenlink reduces RES
curtailment and improves captured electricity prices for Irish consumers, i.e. average
annual electricity prices are expected to be lower in the SEM when Greenlink is in
service compared to prices that would be captured without Greenlink.
1 The CRU has been supported by independent economic and technical advisors. 2CRU modelled Vision 1 from the ENTSO-E TYNDP 2016 scenarios and Sustainable Transition and Global Climate Action from the ENTSO-E TYNDP 2018 scenarios. At the time of conducting the CBA study, the TYNDP 2018 scenarios were still in draft form. 3 See Section 3.5 for a description of the Brexit sensitivity. 4 Trading frictions were modelled as a transmission cost on all GB electricity interconnectors.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
3
The CRU CBA of Greenlink indicates that, at the time of assessing the Greenlink application,
Greenlink has the potential to provide a net benefit to Irish consumers and Ireland as a
whole. As such, the CRU is minded to determine, at this early stage, the Greenlink
interconnector application passes the public interest test.
The CRU notes that this paper outlines the CRU determination if the Greenlink
interconnector is in the public interest. The CRU does not require any further comments on
this determination paper.
The precise details of any Cap and Floor regime will be consulted upon and determined at
the next stage, after sufficiently detailed financial and technical submissions provided by the
Greenlink developers to the CRU for a detailed assessment.
The CRU notes that in the next stage the CRU will engage with the Ofgem to explore the
potential for a Final Project Assessment process that takes both the Irish and GB regulatory
separate decision-making processes into account.
Notwithstanding this determination on the public interest test, if any subsequent information
is given to the CRU before making its final decision would lead the CRU to consider that the
basis of its public interest test decision has materially changed, then the CRU may revisit this
determination. In this case, the CRU may re-run its analysis in order to confirm whether or
not the project continues to be in the public interest.
Greenlink developers are required to regularly update the CRU on progress against their key
development milestones. Furthermore, the CRU expects the Greenlink developers to give
formal written notice of any material change to the project design.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
4
Public Impact Statement
Electricity interconnectors are physical links which allow the transfer of electricity across
borders. New interconnectors should be built only to the extent that they benefit the public at
large. That is, as long as the benefits of adding interconnection capacity outweigh or equal
the costs. Therefore, the CRU’s assessment of each electricity interconnection application
will balance potential benefits of a new interconnector to the Irish consumers against its
costs.
Generally, new electricity interconnectors can offer multiple potential benefits:
• lowering costs for consumers if power can be generated abroad and imported to
Ireland at a lower price (lower prices);
• reducing emissions by facilitating the integration of renewable power into the energy
system (renewable energy integration); and
• providing an additional layer of security (security of supply).
In relation to lower prices, interconnectors can transport power in both directions, i.e. import
and export. This allows them to utilise differences in the power systems, and electricity
prices, between countries. Electricity between interconnected markets flows from the lower-
priced market to the higher-priced one. For instance, at times of high electricity price in
Ireland, interconnectors can allow cheaper electricity from another country to be imported
into Ireland, thereby raising the supply of electricity and lowering its price. Conversely, if
Ireland was the lower-priced market, export of its (cheaper) electricity to a higher-priced
market would increase the price in Ireland and bring the price down for the consumers
abroad.
In summary, a new interconnector tends to increase prices in the lower-priced market and
decrease prices in the higher-priced market. As prices converge, consumers in the higher-
priced market will benefit from lower prices, while the lower-priced market consumers will
have to pay a higher price. Therefore, whether a new interconnector lowers electricity prices
for Irish consumers would depend on whether it connects to a country where electricity prices
are typically lower than in Ireland.
Regarding renewable energy, on very windy or sunny days there can be more renewable
power available than the electricity system can accept. When this happens, renewable
generators are dispatched down or “curtailed off”, that is, blocked from supply, and a large
volume of renewable energy goes unused. This is because, at present, renewable energy
cannot displace conventional power plants below the minimum level needed for certain grid
stability services. Additional interconnection could reduce this effect and allow more
renewable energy onto the electricity system (as it can safely be exported).
Finally, regarding security of supply, interconnectors allow physical imports of electricity to
meet domestic demand. As such, a new interconnector would give Ireland yet another
potential import route for electricity, diversifying Ireland’s energy supply. This diversification
can have various dimensions. First, a new interconnector can provide geographic
diversification if it links Ireland with a new country or supplies power to a new (different) point
on the Irish electricity system. A new interconnector can also provide economic
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
5
diversification, as it supplies electricity according to the price dynamics between the two
interconnected countries. Finally, a new interconnector also provides technological
diversification in that it links markets with different technology choices or having different
natural resources determining their energy mix. Each of these dimensions enables security
of supply risks to be spread and reduced.
Building a new interconnector can be costly for the Irish consumers, depending on the way it
is regulated and funded. Interconnectors derive their revenues from sales of interconnection
capacity to users who wish to move electricity between markets with different prices
(congestion revenues).
There are various approaches to regulate interconnectors and determine who bears the risk
of the interconnector being able to earn congestion revenues. In a merchant model, which is
exceptional in Europe, the interconnector is fully reliant on its congestion revenues and bears
all the risks of not being able to recover its investment. In a fully regulated model, which is
most common in Europe, investment costs are recovered through network tariffs. In this
model, it is the end consumer that pays the investment costs in full and receives all the
revenues from sales of interconnection capacity. Interconnectors can also be partly
regulated, and therefore partly funded by the tariffs. For instance, in a so-called cap and floor
model, an interconnector’s sales revenues that are below the floor are topped up by network
tariffs and its sales revenues above the cap are returned to the end consumer.
Hence, regulated and partially regulated interconnectors can have a positive or negative
impact on network tariffs, and ultimately on end consumers, depending on their performance.
If interconnectors underperform financially, then this can translate into a cost to electricity
consumers by increasing network tariffs. In contrast, if electricity interconnectors over-
perform financially they can reduce electricity network tariffs. Therefore, the risk of
underperformance and its potential cost to Irish consumers must be balanced against the
potential benefits that a new interconnector may bring in the medium to long term.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
6
Table of Contents
Table of Contents ...................................................................................................... 6
1. Introduction ...................................................................................................... 10
1.1. Commission for Regulation of Utilities ........................................................................... 10
1.2. Background ........................................................................................................................ 10
1.3. Greenlink Project – PCI 1.9.1............................................................................................ 11
1.4. Purpose of this Paper ....................................................................................................... 11
1.5. Legal and Policy Context .................................................................................................. 11
1.5.1. Electricity Regulation Act 1999, Section 2A ................................................................ 12
1.5.2. Electricity Regulation Act 1999, Section 9 .................................................................. 12
1.5.3. Electricity Regulation Act 1999, Section 16A .............................................................. 12
1.5.4. ENTSO-E’s TYNDP ......................................................................................................... 13
1.5.5. ENTSO-E’s CBA Guideline ............................................................................................ 13
1.5.6. CRU’s policy to date ...................................................................................................... 14
1.5.7. Government’s Policy on Electricity Interconnection ................................................. 15
1.6. Structure of this Paper ...................................................................................................... 15
2. Summary of Responses Received .................................................................. 16
2.1. Are there any other specific factors that the CRU should consider in assessing the
Greenlink CBA? ........................................................................................................................ 16
2.2. Is there any additional information the CRU should consider when determining
whether the Greenlink interconnector is in the public interest or not? ............................. 18
2.3. Are there any other specific factors that the CRU should consider in assessing the
Greenlink technical overview report? .................................................................................... 19
2.4. Are there other specific factors that the CRU should consider in selecting the
appropriate regulatory approach? ......................................................................................... 20
2.5. Other comments ................................................................................................................ 21
3. CRU CBA of Greenlink ..................................................................................... 23
3.1. Methodology and Modelling Approach ........................................................................... 23
3.2. CRU CBA Results of Greenlink ........................................................................................ 26
3.3. CRU CBA Results Across all Scenarios ......................................................................... 27
3.3.1. TYNDP 2018 ST vs Element Power Reference Case .................................................. 28
3.3.2. TYNDP 2016 V1 vs Element Power Low Case ............................................................. 30
3.3.3. TYNDP 2018 GCA vs Element Power High Case ........................................................ 31
3.4. RES Integration .................................................................................................................. 32
3.5. Impact of Greenlink on Security of Supply .................................................................... 32
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
7
3.6. Impact of Brexit on Greenlink .......................................................................................... 34
3.7. Impact of Greenlink on Gas Transmission Tariffs ......................................................... 38
4. CRU CBA Summary ......................................................................................... 40
5. CRU’s Determination ....................................................................................... 42
6. Next Steps ........................................................................................................ 43
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
8
Glossary of Terms and Abbreviations
Abbreviation or Term
Definition or Meaning
ACER Agency for the Cooperation of Energy Regulators
CBA Cost Benefit Analysis
CBCA Cross-border cost allocation
CEF Connecting Europe Facility
CRU Commission for Regulation of Utilities
DCCAE Department of Communications, Climate Action and the Environment
EENS Expected Energy Not Served
ENSTO-E European Network of Transmission System Operators for Electricity
ESB Electricity Supply Board
GB Great Britain
UK United Kingdom
FFR Fast Frequency Response
FPA Final Project Assessment
HVAC High Voltage Alternating Current
HVDC High Voltage Direct Current
IFA Interconnexion France-Angleterre (Interconnector between France and
GB)
IPA Initial Project Assessment
SEM Single Electricity Market
I-SEM Integrated Single Electricity Market
LOLE Loss of Load Expectation
NPV Net Present Value
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
9
Abbreviation or Term
Definition or Meaning
NRA National Regulatory Agency
O&M Operations and Management
Ofgem Office of Gas and Electricity Markets (GB Energy Regulatory Authority)
PCI Project of Common Interest
RTÉ Réseau de transport d'électricité (French Transmission System
Operator)
TEN-E
Regulation
Trans-European Energy Infrastructure Regulation (EU Regulation (EC)
No 347/2013)
TSO Transmission System Operator
KPI Key Performance Indicator
CRE French Regulator
SNSP System Non-Synchronous Penetration
V1 Vision 1
ST Sustainable Transition
GCA Global Climate Action
RES Renewable energy sources
CO2 Carbon dioxide
TYNDP Network development plan for the next ten years
DfD Contracts for Differences
VoLL Value of Lost Load
EENS Expected energy not served
PPA Power Purchase Agreements
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
10
1. Introduction
1.1. Commission for Regulation of Utilities
The Commission for Regulation of Utilities (“CRU”) is Ireland’s independent energy and
water regulator. The CRU’s mission is to regulate water, energy and energy safety in the
public interest.
Further information on the CRU’s role and relevant legislation can be found on the CRU’s
website at www.cru.ie.
1.2. Background
In December 2017, Element Power submitted an application for an interconnector between
GB and the Republic of Ireland, i.e. the Greenlink interconnector under Irish Legislation
(Electricity Regulation Act 1999 (the Act)). The application consisted of a cost-benefit
analysis of Greenlink, a technical description of the project, project financial information as
well as a description of the charging methodology and regulatory regime Greenlink is seeking
to be regulated under. In its application Element Power requested the CRU to:
1. determine if the construction of the Greenlink Interconnector (a Project of Common
Interest (PCI) connecting Great Britain (GB) and Ireland) is in the public interest for
the project to be considered to be part of the transmission system for the purposes of
calculating and imposing charges for the use of the transmission system; and
2. approve the proposed charging methodology for Greenlink pursuant to section 35 of
the Act which is based on a 25-year Cap and Floor regime.5
This determination pertains to the first stage outlined above. The CRU assessed the “public
interest” stage by conducting its own CBA and comparing the results to those provided by
Element Power.
The CRU considered the application and issued a public consultation seeking comments
from stakeholders on the CRU’s initial assessment of Greenlink’s electricity interconnector
application.
In June 2018, the CRU published Element Power’s application and a CRU consultation
paper (CRU18119) requesting views on the initial assessment of the Greenlink’s electricity
interconnector application by the CRU. In the consultation paper the CRU indicated that it
would conduct its own CBA of Greenlink to test the boundaries of Element Power’s CBA and
the key inputs and assumptions which may drive better or worse outcomes for Irish
consumers and other stakeholders. The CRU also noted that if the CRU CBA revealed that
Greenlink would generate overall (net) benefits to Irish consumers, the CRU would then
consider the appropriate regulatory regime that is in the public interest.
5 Greenlink requested from the CRU a Cap and Floor regime in respect of 50% of Greenlink’s revenues. Greenlink is seeking a regime that is symmetrical with Ofgem’s 25-year Cap and Floor regime that would apply to Greenlink in GB, i.e. the Greenlink Interconnector would be, in principle, half underwritten by GB consumers and the other half underwritten by Irish consumers.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
11
1.3. Greenlink Project – PCI 1.9.1
The Greenlink Interconnector is a proposed 500 MW HVDC electricity interconnector, which
is being developed by Element Power, linking the power grid in Ireland and GB. It is
anticipated that the link will provide a new grid connection between the Great Island
transmission substation in Wexford and Pembroke transmission substation in South Wales.
Figure 2: Graphical Illustration of Greenlink (Image source: Element Power)
Greenlink has been designated as a PCI by the European Commission and has been
granted, by Ofgem, a Cap and Floor regulatory regime 6. The interconnector is focused on
increasing the ability of the all-island SEM and GB markets to integrate low carbon electricity
generation, particularly through renewable generation, as the penetration of renewable
electricity generation increases. Element Power considers the interconnector can also help
wind and solar energy avoid curtailment by allowing surplus output to be exported during
periods where supply outstrips demand.
1.4. Purpose of this Paper
The purpose of this paper is to outline the CRU determination following an assessment on
the Greenlink interconnector application seeking to understand whether the interconnector
would be in the public interest.
1.5. Legal and Policy Context
The CRU has several competences in relation to assessing electricity interconnection
projects and deciding on their regulatory treatment. An overview of those competencies
under the Irish and the European law is provided in a CRU information paper (CRU18056).
When assessing electricity interconnection applications, the CRU is mindful of the
Government’s policy on electricity interconnection. Moreover, the CRU takes into
consideration the European guidance and best practices for such assessments.
6 Regulatory framework that sets the maximum (cap) and a minimum (floor) on the level of revenues that can be gained/lost by interconnector project promoters.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
12
The CRU notes that Element Power has submitted the Greenlink Interconnector application
and requested from the CRU to make a determination pursuant to Section 2A of the
Electricity Regulation Act 1999 (as amended) (the Act) that it is in the public interest for
Greenlink to be considered to be part of the transmission system for the purposes of
calculating charges and imposing charges for use of the transmission system, and approve
the proposed charging methodology for Greenlink pursuant to section 35 of the Act which is
based on a 25 year Cap and Floor regime.
1.5.1. Electricity Regulation Act 1999, Section 2A
Under the Act interconnector developers may apply directly to the CRU for a determination
on their application.
Section 2A of the Act states that an interconnector owned by a person other than the Board
(i.e. ESB) may, where the CRU determines that it is in the public interest, be considered to
be part of the transmission system for the purposes of calculating and imposing charges for
the use of the transmission system (as set out in Section 35 - Charges for connection to and
use of transmission or distribution system).
1.5.2. Electricity Regulation Act 1999, Section 9
Pursuant to Section 9 of the Act, the CRU has responsibilities which include:
• protect the interests of final customers;
• promote competition, efficiency and the use of renewable and sustainable energy;
• not discriminate unfairly between relevant stakeholders;
• contribute to the development of the internal market and to the development of
compatible regulatory frameworks between regions of the European Union, by
engaging, co-operating and consulting with other national regulatory authorities, the
Agency and with the European Commission in regard to cross-border issues;
• cooperate with other regulatory authorities at a regional level to foster operational
arrangements to enable an adequate level of interconnection capacity within the
region and between regions to allow the development of effective competition and
improvement of Security of Supply; and
• cooperate with other regulatory authorities at a regional level to develop rules on
access to cross border infrastructure including allocation of capacity and congestion
management.
1.5.3. Electricity Regulation Act 1999, Section 16A
Section 16A of the Act provides that, with the consent of the Minister, the CRU may secure
the construction of an interconnector by:
• a competitive tender;
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
13
• an authorisation granted to a person without a prior competitive tender where the
person demonstrates, to the satisfaction of the CRU, that the granting of an
authorisation, subject to such conditions as the CRU deems necessary and
appropriate, is in the long term interests of final customers; or
• requesting the transmission system operator to provide for the construction of an
interconnector in its development plan.
1.5.4. ENTSO-E’s TYNDP
The European Commission selects PCI projects from a list of projects included in ENTSO-
E’s pan-European network development plan for the next ten years (TYNDP). The principal
aim of the plan is to provide a consistent view of the pan-European electricity infrastructure,
signal potential gaps in future investment and capture the wider dynamics of the European
electricity market. ENTSO-E use several scenarios to represent future developments of the
power system. ACER recommends that project promoters use TYNDP scenarios in their
CBAs submitted to NRAs, while noting that additional robust scenarios can also be provided.
ENTSO-E update their plan every two years.7 The previous edition, the TYNDP 2016, was
published in December 2016. The 2018 edition is currently under preparation.8
1.5.5. ENTSO-E’s CBA Guideline
The ENTSO-E has developed guidelines for the CBA of grid development projects, including
interconnectors9. According to these guidelines, the scenarios considered in the economic
assessment should:
• be coherent, comprehensive and internally consistent;
• consider interaction of economic key parameters such as economic growth, fuel
prices, CO2 prices, etc. as well as the impact of any significant risk affecting the
results of the CBA over the investment horizon; and
• be characterised by:
• a generation portfolio, including a forecast of power plant installations and
retirements, type of generation, etc.;
• a demand forecast, e.g. impact of efficiency measures, rate of growth, shape
of demand curve, etc.; and
• exchange patterns with the systems outside the studied region.
The ENTSO-E Guideline also provides an economic assessment framework that considers a
project’s benefits, cost and impact on society, as summarised in the figure below.
7 See TYNDP website for updates. 8 As such, CRU CBA modelling is based on draft TYNDP 2018 scenarios. 9 ENTSO-E Guideline for Cost Benefit Analysis of Grid Development Projects, 29th July 2016
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
14
Figure 3: ENTSO-E economic assessment framework
ACER recommends that project-specific CBAs are consistent with the ENTSO-E’s economic
assessment framework.
1.5.6. CRU’s policy to date
Since late 2015, the CRU has published six documents which outline the CRU process in the
development of a regulatory framework for assessing electricity interconnectors, in particular
those with a PCI status. These documents are listed below:
• CER/15/269: Information on PCI Incentive Methodology in accordance with Article
13(6) of EU Regulation 347/2013;
• CER/15/284: Consultation on Review of Connection and Grid Access Policy: Initial
Thinking & Proposed Transitional Arrangements;
• CER/16/239: Information on Policy for Electricity Interconnectors – Consultation
Process and Call for Initial Comments;
• CRU17300: Direction on Grid Connections for Electricity Interconnectors with PCI
status;
• CRU18056: Information on Electricity Interconnectors;
• CRU18119: Consultation on Greenlink Electricity Interconnector;
• CRU18131: Consultation on Assessment Criteria for Electricity Interconnection
Applications.
• CRU18221: Decision on Assessment Criteria for Electricity Interconnection
Applications.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
15
1.5.7. Government’s Policy on Electricity Interconnection
When assessing electricity interconnectors, the CRU is mindful of the Government’s policy
on electricity interconnection. Relevant Government’s policy documents:
• Government Policy Statement on the Strategic Importance of Transmission and Other
Energy Infrastructure;
• Ireland’s Transition to a Low Carbon Energy Future 2015-2030;
• Draft National Policy on Electricity Interconnection in Ireland: Public Consultation;
• National Policy Statement on Electricity Interconnection.
1.6. Structure of this Paper
This paper is structured as follows:
• Section 1, provides an introduction to the CRU and provides background information
to this paper.
• Section 2, provides a summary of the responses received and the CRU’s position.
• Section 3, provides an overview of the CRU CBA of Greenlink.
• Section 4, summarises the key findings of the CRU assessment.
• Section 5, outlines the CRU’s determination on the application “Public Interest Test”.
• Section 6, provides the next steps with regards to the Greenlink Interconnector
application.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
16
2. Summary of Responses Received
On 18 June 2018 the CRU published a consultation on the Greenlink electricity
interconnector application. The CRU requested comments on the questions raised in the
consultation paper. There were:
• Are there any other specific factors that the CRU should consider in assessing the
Greenlink CBA?
• Is there any additional information the CRU should consider when determining
whether the Greenlink interconnector is in the public interest or not?
• Are there any other specific factors that the CRU should consider in assessing the
Greenlink technical overview report?
• Are there other specific factors that the CRU should consider in selecting the
appropriate regulatory approach?
The CRU received 18 responses to the consultation paper, of which none were confidential.
The main points made by respondents are summarised below. The submissions are
published on the CRU’s website alongside this paper.
2.1. Are there any other specific factors that the CRU
should consider in assessing the Greenlink CBA?
In the consultation paper (CRU18119) the CRU requested respondents’ views on the factors
that the CRU should consider in its CBA of Greenlink. The majority of respondents stated
that Security of Supply and de-rating factors should be considered.
Several respondents noted that it is necessary to examine whether Greenlink would lead to
any increase in costs elsewhere in the energy system, that the energy user would be
required to cover. A number of respondents highlighted that the impact on existing gas-fired
power plants should be considered, in particular where additional interconnection results in
lower Load Factors.
Some respondents noted that the CRU should consider if investment in alternative
infrastructure be more beneficial to Irish consumers.
With respect to Brexit impacts, a few respondents noted that related impacts on efficiency of
interconnector flows and costs between the two countries need to be taken into account. One
respondent noted that the CRU should consider if the I-SEM would still be a single market.
A number of respondents suggested that the level of reliability of Greenlink needs to be
taken into account.
The majority of respondents stated that the CRU CBA needs to look at whole-system costs
including deep reinforcement costs, any knock-on effect on the wider market and any
ramifications for energy policy goals such as decarbonisation, sustainability and competition.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
17
CRU Response
The CRU has considered the points submitted regarding the Greenlink CBA assessment.
The CRU notes that while interconnectors may provide security of supply benefits, as some
respondents acknowledge, those benefits are difficult to quantify. An interconnector provides
security of supply benefits if it improves the power system's ability to ensure adequate
supplies to meet demand. Security of supply events (i.e. instances when supply falls short of
demand) tend to be relatively rare, and therefore the analysis of security of supply benefits
requires a probabilistic assessment of many system conditions (including temperature, wind
speed, generator outage patterns, correlation with other markets, etc.). Such data was not
readily available, and therefore the CRU CBA did not quantify security of supply benefits in
this manner. Instead, a simpler security of supply analysis was conducted with the available
data, which is described below in section 3 of this paper.
Some stakeholders have raised the issue of de-rating factors for interconnectors in the
context of security of supply. These de-rating factors determine the amount of capacity that
interconnectors can offer into the Capacity Market. If the interconnectors clear in the
Capacity Market but fail to provide that amount of de-rated capacity during stress events, it
may have security of supply implications. The CRU has modelled a sensitivity on the
Greenlink interconnector availability. In the sensitivity the CRU has assumed an availability
rate of 70% for Greenlink instead of 97%. This sensitivity shows that when Greenlink
availability is lower, there are more flows on other interconnectors to Ireland, e.g. EWIC or
Moyle. The sensitivity also shows that although net benefits are lower compared to the case
where Greenlink availability is assumed to be 97%, the interconnector still generates positive
net benefits to Irish consumers and other stakeholders.
In relation to additional costs in the energy system, the CRU has monetised Social Economic
Welfare (i.e. consumer surplus, producer surplus, congestion rents, etc.) and security of
supply.10 In its CBA the CRU has sought to estimate the potential impact of the
interconnector on gas tariffs through its impact on power sector gas demand (i.e.
interconnector imports displacing some domestic gas-fired generation). This is discussed
further in section 3 of this paper.
The CRU notes the respondents’ comments in relation to investment in alternative
technology solutions. Regarding investments, the CRU notes that in a free market economy,
a vast majority of investment decisions should be driven by market forces. The Government
may seek to incentivise investments in particular technologies to achieve its national and EU
policy objectives. The CRU’s role is to ensure a well-functioning and efficient energy market
for the benefit of Irish consumers, rather than determining or promoting certain investment
decisions.
The CRU has considered the potential impact of Brexit on the Greenlink interconnector.
CRU’s Brexit sensitivity assumes that GB is no longer part of the EU’s Internal Energy
10 Any benefits associated with the integration of renewable generation and CO2 emissions were already monetised under Social Economic Welfare.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
18
Market but that the Republic of Ireland (ROI) and Northern Ireland (NI) remain coupled. This
is discussed further in section 3 of this paper.
The CRU is aware that availability of EWIC and Moyle has been relatively low in recent
years. In its CBA the CRU has assumed the same (relatively high) level of availability of all
new and existing interconnectors. The higher availability of existing interconnectors results in
more conservative CBA results for Greenlink, since existing interconnectors would compete
with Greenlink.
In relation to other costs, the CRU CBA of Greenlink has considered whole-system costs.
These include:
• shallow connection costs;
• ongoing maintenance costs;
• network reinforcement costs; and
• Greenlink capital and operational expenditure.
The CRU notes that EirGrid assessed the need for any additional transmission network
needs that are driven by the connection of Greenlink to the Irish system. EirGrid’s analysis
shows that the solutions required are relatively minor in relation to the scale of Greenlink’s
application and consist of a number of 110kV network solutions.
2.2. Is there any additional information the CRU
should consider when determining whether the
Greenlink interconnector is in the public interest or
not?
Element Power submitted the Greenlink interconnector application under Section 2A of the
Act and required the CRU to consider whether Greenlink is “in the public interest”. The CRU
requested respondents’ opinions on the public interest assessment. The majority of
responses received agreed with the CRU’s approach to conduct its own CBA of Greenlink
and identify the potential benefits and costs to Irish consumers.
Several respondents highlighted that the CRU should consider EU and National renewable
targets and policy objectives. The respondents highlighted that Greenlink could help to
integrate renewables and reduce wind curtailment.
A number of respondents stated that the CRU needs to consider the interaction with the gas
market. The respondents noted that additional interconnection could have an impact on the
gas network and could ultimately increase the price of gas and electricity.
A few respondents noted that the CRU should consider the potential impact of Brexit when
determining whether the Greenlink Interconnector is in the public interest or not and
consideration should also be given to the potential impact on other European energy
projects.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
19
The majority of respondents noted that the Security of Supply should be taken into
consideration. One respondent noted that Greenlink can make a positive contribution to
Security of Supply and system reliability.
Some respondents noted that the most efficient solution for meeting national and EU targets
may be delivered by alternative technology solutions. The respondents noted that alternative
options should be considered.
CRU Response
The CRU has considered the points made by all respondents regarding the public interest.
The CRU has conducted its own CBA of Greenlink to test the boundaries of Element Power’s
own CBA of the Greenlink interconnector and the key inputs and assumptions which may
drive better or worse outcomes for Irish consumers and other stakeholders, i.e. whether the
Greenlink interconnector is likely to be in the public interest. This is discussed further in
section 3 of this paper.
In its CBA the CRU has also undertaken a high-level assessment of other Greenlink impacts,
including on Irish gas transmission tariffs, Security of Supply, Renewable energy sources
integration (RES), and the Greenlink interconnector impacts under a Brexit scenario. In
addition, the CRU examined how other potential interconnectors connecting Ireland to other
countries (e.g. another interconnector to France) would impact the incremental benefits
driven by Greenlink.
With regards to Security of Supply benefits, the CRU notes that the analysis of Security of
Supply benefits requires a probabilistic assessment of many system conditions (including
temperature, wind speed, generator outage patterns, correlation with other markets, etc.).
The CRU notes that Element Power did not conduct a probabilistic assessment of Security of
Supply benefits. Instead, Element Power used the de-rating factor of the Greenlink
interconnector multiplied by the Capacity Market clearing price.11 The CRU considered the
Security of Supply benefits driven by Greenlink in one of its scenarios using a simplified
approach that is based on ten different climatic years.12 Further information on the Security of
Supply benefits can be found in section 3 of this paper.
In relation to alternative technology solutions to meet national and EU targets. As noted
above, Government may seek to incentivise investments in particular technologies to achieve
its national and EU policy objectives.
2.3. Are there any other specific factors that the CRU
should consider in assessing the Greenlink technical
overview report?
In the consultation paper (CRU18119) the CRU requested respondents’ views on the
Greenlink technical overview report and other specific factors that the CRU should consider.
11 See section 3.4. 12 See section 3.5.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
20
Several respondents believe that the proposed technology for Greenlink is now quite
extensively established and a high level of performance and reliability in service can be
expected. However, some respondents noted that the CRU should seek further information
regarding the technical details. Some of the respondents advised that before any final
decision is made on the Greenlink interconnector, a detailed technical assessment should be
carried out.
One respondent raised concerns regarding the risks posed to the project from shipping traffic
in the area, particularly given past events relating to interconnectors/pipelines and anchors
from ships.
Another respondent suggested the consideration of interconnector ancillary services, sub-
synchronous response and ramp rates in the CRU assessment.
One respondent noted that the CRU should ensure that the Greenlink interconnector
complies with all of the EirGrid system requirements and satisfies Grid Code conditions and
will support system security requirements as necessary including ancillary services and DS3
provisions.
CRU Response
The CRU notes the views and comments submitted regarding the Greenlink technical
requirements.
The CRU notes that this paper is focused on the public interest test. The CRU accepts that
further detail and clarity need to be provided by Greenlink developers to the CRU for a
detailed technical assessment of the Greenlink interconnector before any final project
assessment decision is made. In the next stage of the assessment, the CRU will require
Greenlink developers to submit details on the seabed surveys and additional technical & cost
details.
With reference to the EirGrid system requirements and Grid Code conditions, the CRU notes
that the interconnector operator licence requires the interconnector owner to comply with the
provisions of the Grid Code, Distribution Code, Metering Code and the SEM Trading and
Settlement Code.
2.4. Are there other specific factors that the CRU
should consider in selecting the appropriate
regulatory approach?
Ofgem has provisionally granted a Cap and Floor for Element Power, which would apply to
50% of the project costs and revenues.13 Element Power proposed a symmetrical Cap and
Floor regulatory approach to the one provisionally granted by Ofgem, which would apply to
the remaining 50% of the project costs and revenues.14 In the consultation paper
13 Ofgem, Decision on the Initial Project Assessment of the Greenlink interconnector, 30th September 2015 14 p9, Greenlink interconnector application
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
21
(CRU18119) the CRU requested views from respondents regarding the proposed regulatory
approach for Greenlink.
There was a broad support for further CRU consultation on the appropriate regulatory
regime. The respondents in general recognised the need for a careful consideration on a
Cap and Floor regulatory regime.
One respondent noted that the duration of the Cap and Floor regime needs to be defined.
The same respondent requested a clarification of whether the regulatory regime would
remain fixed for the duration of the regime.
A number of respondents were concerned that variability in the operation of the
interconnector could have an impact on network tariffs for Irish electricity consumers, which
could have broader economic impacts.
Another respondent advised to take into account possible Brexit scenarios and a recent
decision by the French Regulator (CRE) in their deliberation 2017-25315.
One respondent noted that the CRU should set out a clear set of Key Performance Indicators
(KPI) to ensure that the interconnector is operated as efficiently as possible.
CRU Response
The CRU considered the views and recommendations submitted regarding the regulatory
approach for the Greenlink interconnector. The CRU notes that this paper is focused on the
CBA of Greenlink and the public interest question. The CRU also noted that if the CRU CBA
revealed that Greenlink would generate overall (net) benefits to Irish consumers, then the
CRU would consider and consult upon the appropriate regulatory regime that is justified by
public interest, e.g. a Cap and Floor regime for Greenlink.
The CRU notes that in the next stage the CRU will engage with the Ofgem to explore the
potential for a Final Project Assessment process that takes both the Irish and GB regulatory
separate decision-making processes into account.
2.5. Other comments
A few respondents noted that the Greenlink interconnector application should be assessed
against the criteria set out in (CRU18131). One respondent noted that Greenlink’s Brexit
scenarios modelling should be shared publicly.
15The CRE delayed a decision on a proposed interconnector to the UK pending Brexit negotiations -https://www.google.ie/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cad=rja&uact=8&ved=2ahUKEwibkMfgk-rcAhUQM8AKHXM_DHcQFjAAegQIABAC&url=https%3A%2F%2Fwww.cre.fr%2Fen%2Fcontent%2Fdownload%2F16726%2F206259&usg=AOvVaw03tuj9Bf-UmmBlx6MVCu96
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
22
CRU Response
The CRU notes that the assessment criteria for electricity interconnector applications
(CRU18131) is developed for the assessment of applications the CRU has received, or will
receive, from the developers of the electricity interconnection projects. The CRU assessed
the Greenlink interconnector application considering the CRU criteria.16 In addition, the CRU
CBA modelling approach of Greenlink is based on ENTSO-E Guideline.
The CRU highlights that following Greenlink’s project submission in December 2017, it
submitted additional analysis on:
• The potential Security of Supply benefits associated with Greenlink; and
• The impact of Greenlink on Social Economic Welfare in a Brexit world.
16The CRU carries out a holistic assessment against all of the criteria and its decision will depend on the specific case. In other words, the application will be viewed in the round against the criteria, and failure to provide certain information or meet certain criteria will not necessarily mean that the application will be rejected or negatively assessed.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
23
3. CRU CBA of Greenlink
The CRU reviewed the CBA of Greenlink interconnector submitted by Element Power and
considered that further analysis was needed to understand the boundaries of impacts on
consumers and other stakeholders before a determination can be reached on whether the
Greenlink interconnector is in the public interest. The CRU has conducted its own CBA of
Greenlink supported by independent economic and technical advisors. The results of the
CRU CBA of Greenlink are summarised below.
3.1. Methodology and Modelling Approach
To assess the potential costs and benefits of Greenlink, the CRU has modelled three
scenarios and two sensitivities of the European electricity market to assess the impact of
Greenlink on Social Economic Welfare. The CRU’s CBA modelling approach is based on
ENTSO-E CBA Guideline.17
The CRU has modelled scenarios based on the TYNDP 2016 and 2018 scenarios produced
by ENTSO-E.
For TYNDP 2016, ENTSO-E developed four ‘visions’ out to 2030 along two main
dimensions:
• The x-axis represents the degree of European cooperation to reduce greenhouse gas
emissions by 80-95% on 1990 levels by 2050; and
• The y-axis relates to the relative speed of green transition.
Both axes provide a spectrum of progress. Vision 1 projects the slowest progress in
decarbonising electricity generation (see figure 4 below).
Figure 4: TYNDP 2016 Visions
17 See section1.5.5 for details.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
24
For TYNDP 2018, ENTSO-E considered three storylines for 2030 and 2040. The CRU has
modelled the two storylines highlighted in light blue below:
• Sustainable Transition; and
• Global Climate Action.
Figure 5: TYNDP 2018 Scenarios
The scenarios modelled (highlighted in light blue in Figures 4 and 5 above) were:
• TYNDP 2016 Vision 1 (V1)18 – Out of the TYNDP 2016 Visions, Vision 1 projects the
slowest progress towards decarbonisation, and therefore provides the lowest case for
renewables deployment. This scenario resulted in the lowest benefits compared to
other scenarios (snapshots years 2020 and 2030);
• TYNDP 2018 Sustainable Transition (ST) 19 – Out of the three possible storylines,
ST represents the most likely future in 2030, but also the ‘lower’ of the storylines, with
electrification of heat and transport occurring at the slowest pace. ST 2030 was
selected over DG 2030, as the latter presents a future that departs significantly from
current projections (snapshot years 2025, 2030 and 2040); and
• TYNDP 2018 Global Climate Action (GCA) – Beyond 2030, the CRU has also
modelled GCA in 2040 (in addition to ST), as the emphasis in this storyline is on rapid
18 The CRU notes that the TYNDP 2016 V1 scenario was modelled for 10 climatic years reflective of a variety of system conditions including temperature, wind speed, generator outage patterns, correlation with other markets, etc. The potential Security of Supply impacts of Greenlink (discussed below) were also considered for this scenario. 19 The TYNDP 2018 ST and GCA scenarios are based on one climatic year that represents average conditions with respect to weather, demand, and plant availability (i.e. 2007). Additionally, we note that the TYNDP 2018 scenarios used for this analysis are still in draft form.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
25
decarbonisation and large-scale renewables, which both have an impact on the
benefits provided by interconnectors20 (snapshot year 204021).
The CRU has considered these scenarios with and without an additional interconnector
project to France (referred to as ‘IE-FR interconnector’ in figures and tables).
A summary for the adopted scenarios is set out in the figure below.
Figure 6: Scenarios and Simulations
To quantify the costs and benefits of Greenlink, the simulations with and without Greenlink
were compared, as shown in the figure below:
Figure 7: Quantifying the change in costs and benefits due to Greenlink
In addition to the scenarios, the CRU has modelled two sensitivities on the ST scenarios.
These sensitivities are:
• Brexit sensitivity – to model the potential impact of Brexit on Greenlink; and
20 Although the TYNDP 2018 Distributed Generation (DG) pathway is also an interesting scenario for the EU electricity system, the CRU has not modelled this pathway for the assessment of the Greenlink CBA. The DG pathway is driven by prosumers, decentralised development, with focus on end-user technology, high penetration of electric vehicles, the assumption that PV and batteries are widespread and that high levels of demand side response are available. 21 This scenario is not active until 2040 and offers an alternative future to the ST scenario post-2030, whereby sudden action is taken, and rapid decarbonisation occurs after 2040, above that projected in the ST scenario.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
26
• System Non-Synchronous Penetration (SNSP) – the SNSP limit of 75% of non-
synchronous generation22 was added to the ST scenario. The SNSP includes the
non-synchronous generation and net interconnector imports as a percentage of the
demand and net interconnector exports. This was done for SEM only as CRU
assumes that only the day-ahead markets are coupled, and the SNSP limit applies in
other trading timeframes, i.e. the intraday and balancing markets.
A summary for the adopted sensitivities is set out in the figure 8 and figure 9.
Figure 8: Brexit Sensitivities
Figure 9: SNSP Sensitivity
The CRU has also undertaken a high-level assessment of other Greenlink impacts, including
on Security of Supply and on Irish gas transmission tariffs as a result of changes in gas fired
generation in the SEM.
3.2. CRU CBA Results of Greenlink
In this section, the CRU presents the results of its CBA for the modelled scenarios and
sensitivities.
The CRU has monetised the benefits and costs of:
• Improved security of supply (€);
• Social Economic Welfare (€);
• Total interconnector project expenditures (€).
The CRU has also quantified:
• RES integration (MWh);
• CO2 emissions (tonnes).
22 Non-synchronous generation, i.e. wind, solar, interconnection
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
27
The benefits of RES integration and CO2 emissions are monetised as part of Social
Economic Welfare.
In the following sub-section, the CRU compares Element Power’s CBA results against its
own CBA results of the Greenlink interconnector.
For comparison purposes and consistency with ENTSO-E CBA Guideline, the CRU excluded
two items from Element Power’s costs and benefits calculations:
• Market integration23; and
• Cap and Floor payments.
The CRU has also discounted the Element Power CBA results using a 4% (instead of 3.5%)
discount rate for comparison purposes.24
The CRU notes that the scenarios modelled are also different from those modelled by
Element Power. For example, the CRU low scenario based on TYNDP 2016 V1 assumed
higher fossil fuel prices than the Low scenario in the Element Power CBA. Similarly, the CRU
has modelled the TYNDP 2018 scenarios while Element Power used scenarios developed
in-house by their economic advisor.
The CRU has not quantified any additional (dis)benefits associated with ancillary services,
capacity market, network losses25, cap and floor payments or power purchase agreements
as these impacts are not part of the ENTSO-E CBA Guideline. Furthermore, the CRU did not
assess the impact on market power caused by the addition of Greenlink as this analysis
requires confidential data as input. Additionally, the impact of future assets on current market
power is a short-term aspect while the assessment of an investment decision is a long-term
commitment.
3.3. CRU CBA Results Across all Scenarios
In the following sub-sections, the CRU explains the Social Economic Welfare impacts and
resulting changes in consumer surplus and producer surplus for all three scenarios.
Figures 9 and 10 summarise CRU’s quantification of the impacts of Greenlink on Social
Economic Welfare for SEM, as well as the results of Greenlink’s CBA.
23 This benefit is driven by two main factors: (1) the (positive) impact of the interconnector on the average price that wind/solar generators can earn (e.g. because with higher interconnector capacity they can export some of their excess generation to higher-priced markets, and thus earn higher market price on average); and (2) the assumption that all new generators are supported by long-term Power Purchase Agreements (PPAs). CRU agrees with (1) - this is also captured in CRU’s CBA. With regards to (2), CRU notes that some generators are likely to be supported by PPAs or CfDs but not all of them are likely to have such contracts in place. Additionally, (2) is fully distributional - i.e. it is a transfer between producers and consumers, and it does not affect net social welfare. As such, including (2) in social welfare results in a transfer from producers to consumers in such a way that consumers appear better off. 24 Consistent with ENTSO-E PCI CBA guidance and Ireland public sector guidance of assessment of capital projects 25The CRU has modelled an energy markets model, and as such, cannot quantify any (dis)benefits related to internal constraints or system losses.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
28
Figure 10: CRU CBA results for Greenlink (change in SEM welfare impacts)
Figure 11: Element Power CBA results for Greenlink (change in SEM welfare impacts)
3.3.1. TYNDP 2018 ST vs Element Power Reference Case
For the TYNDP 2018 ST scenario26, CRU CBA results are compared to Element Power’s
Reference Case CBA. As described above, Element Power’s Reference Case CBA results
are adjusted to remove distributional items and a 4% discount rate is used. The results are
summarised below.
Table 1: Element Power Reference Case CBA – NPV results
€m NPV @ 4% (real 2017) Ref. Case with Greenlink only Total NPV – with Greenlink & IE-
FR interconnector
Change in producer surplus -410 605
Change in consumer surplus 1,150 -29
26 The ST scenario assumes Greenlink has an availability rate of 97%.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
29
Change in interconnector
surplus27 -36 -185
SEM (net benefit) 704 391
In contrast, CRU’s TYNDP 2018 ST CBA results yield the following impacts in NPV terms:
Table 2: CRU CBA – NPV results
CRU TYNDP 2018 ST (€m, real 2017) Total NPV – with Greenlink only
Total NPV – with Greenlink & IE-FR interconnector
Change in producer surplus -2,329 525
Change in consumer surplus 3,365 -3
Change in congestion rent -255 -156
Greenlink project expenditure -241 -241
SEM (net benefit) 539 125
In summary, a comparison of CRU’s TYNDP 2018 ST simulations and Element Power’s
Reference Case CBA highlights the following key points regarding the CRU’s public interest
test:
• The overall net social welfare impact of Greenlink on SEM in Element Power’s
Reference Case scenario is positive both with and without another interconnector to
France. In CRU’s TYNDP 2018 ST scenario, in a simulation without another
interconnector to France, Greenlink has a positive impact on net social welfare in
SEM. However, in a simulation with another interconnector to France, net social
welfare in SEM remains positive, but is considerably lower.
• In Element Power’s Reference Case scenario, Greenlink has a positive impact on
SEM net social welfare with and without another interconnector to France. However,
the drivers of the positive change in net social welfare differ depending on the
interconnector simulation. In the case with another interconnector to France,
Greenlink drives a positive impact on producer surplus on SEM. In contrast, in the
case with Greenlink only, Greenlink increases SEM consumer surplus and reduces
producer surplus (SEM interconnector surplus reduces in both cases).
• Similarly, in CRU’s TYNDP 2018 ST simulations, SEM net social welfare is positive
both with and without another interconnector to France. However, at a consumer
level, Greenlink marginally decrease consumer surplus where another interconnector
to France is assumed in the modelling and, as is the case in Element Power’s
Reference Case, it is electricity producers in SEM that predominantly benefit from the
development of Greenlink where another interconnector to France exists.
• The positive consumer surplus in CRU’s simulations is driven by lower electricity
prices captured in the SEM market due to the addition of Greenlink.
27 Element Power’s item “Change in interconnector surplus” is equivalent to CRU’s congestion rent and Greenlink project expenditure combined.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
30
• A comparison between Element Power’s Reference Case CBA and CRU’s TYNDP
2018 ST simulations, highlights that changes in Social Economic Welfare related to
Greenlink are sensitive to the development of an additional interconnector in Ireland.
From the Irish consumer perspective, Greenlink drives significant benefits in NPV
terms where no additional interconnector is in service, but under the assumption that
Greenlink co-exists with another interconnector, the incremental benefits driven by
Greenlink are significantly reduced.
3.3.2. TYNDP 2016 V1 vs Element Power Low Case
For the TYNDP 2016 V1 scenario, the CRU compares its CBA results to Element Power’s
Low Case CBA as both are relatively conservative scenarios for the Greenlink CBA. The
results are presented below.
Table 3: Element Power Reference Case CBA – NPV results
€m NPV @ 4% (real 2017) Low Case with Greenlink only Ref. Case with Greenlink & IE-FR
interconnector
Change in producer surplus -106 -48
Change in consumer surplus 143 -35
Change in interconnector surplus -107 -96
SEM (net benefit) -70 -180
In contrast, CRU’s CBA results using the TYNDP 2016 V1 scenario yield the following
impacts in NPV terms:
Table 4: CRU CBA – NPV results
CRU TYNDP 2016 V1 (€m, real 2017) Total NPV – with Greenlink only
Total NPV – with Greenlink & IE-FR interconnector
Change in producer surplus 668 640
Change in consumer surplus -294 -406
Change in congestion rent -84 -59
Greenlink project expenditure -241 -241
Greenlink security of supply benefits
8 0
SEM (net benefit) 56 -67
A comparison of CRU’s TYNDP 2016 V1 simulations and Element Power’s Low Case CBA
highlights the following key points regarding the CRU’s public interest test:
• The overall net social welfare impact of Greenlink on SEM in Element Power’s Low
Case scenario is negative under both cases. However, CRU’s TYNDP 2016 V1
scenario is positive with Greenlink only, and negative with Greenlink and another
interconnector to France.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
31
• In Element Power’s Low Case scenario with Greenlink and another interconnector to
France, CBA results suggest that the addition of Greenlink would reduce producer,
consumer and interconnector welfare. However, importantly in the case without
another interconnector to France, Greenlink still increases SEM consumer surplus,
although SEM net social welfare overall reduces.
• In contrast, in CRU’s TYNDP 2016 V1 simulations, SEM net social welfare is positive
in a case without another interconnector to France but negative in a case with
another interconnector to France. However, at a consumer level, the addition of the
Greenlink interconnector reduces consumer surplus in both cases (with and without
another interconnector to France) and it is SEM producers that predominantly benefit
from the development of Greenlink (through increased producer surplus).
3.3.3. TYNDP 2018 GCA vs Element Power High Case
For the TYNDP 2018 GCA scenario, CRU CBA results are compared to Element Power’s
High Case CBA. The results are summarised below.
Table 5: Element Power High Case CBA – NPV results
€m NPV @ 4% (real 2017) High Case with Greenlink only Total NPV – with Greenlink & IE-FR
interconnector
Change in producer surplus -92 533
Change in consumer surplus 919 305
Change in interconnector surplus 228 -97
SEM (net benefit) 1,056 741
CRU’s CBA results for TYNDP 2018 GCA scenario yield the following impacts in NPV terms:
Table 6: CRU CBA – NPV results
CRU TYNDP 2018 GCA (€m, real 2017)
Total NPV – with Greenlink only Total NPV – with Greenlink & IE-FR interconnector
Change in producer surplus -1,290 494
Change in consumer surplus 2,156 74
Change in congestion rent 16 32
Greenlink project expenditure -241 -241
SEM (net benefit) 640 359
A comparison of CRU’s TYNDP 2018 GCA simulations and Element Power’s Reference
Case CBA highlights the following key points regarding the CRU’s public interest test:
• The overall net social welfare impact of Greenlink on SEM in Element Power’s High
Case scenario and CRU’s TYNDP 2018 GCA scenario is positive, with and without
another interconnector to France.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
32
• In Element Power’s High Case scenario there is a positive change in consumer
surplus with and without another interconnector to France, although producer surplus
reduces in the case with Greenlink only.
• In CRU’s TYNDP 2018 GCA simulations, SEM net social welfare is also positive both
in a case with and without another interconnector to France. However, at a consumer
level, CRU’s simulations suggest that the change in SEM consumer surplus in a case
with Greenlink and another interconnector to France is lower than in Element Power’s
High Case with another interconnector to France.
3.4. RES Integration
The CRU’s TYNDP 2018 GCA scenario has very high RES penetration and introducing an
interconnector has a much larger impact on avoided curtailment than in a scenario with lower
RES penetration (i.e. TYNDP 2016 V1). The table below shows how Greenlink affects RES
curtailment (TWh) in all three scenarios and how this compares to Element Power’s results.
Table 7: Impact on curtailment of SEM wind and solar generators – CRU vs Element Power comparison
Impact on curtailment of SEM wind and solar generators over the period 2023-2047
Total avoided curtailment (TWh)
Wind Solar
CRU28 Element Power
CRU Element Power
Reference Case including IE-FR interconnector
3.9 5.5 0.2 0.8
Reference Case excluding IE-FR interconnector
8.5 10.7 0.3 0.8
Low Case including IE-FR interconnector 0.0 0.3 0.0 0.0
Low Case excluding IE-FR interconnector 0.7 1.2 0.0 0.0
High Case including IE-FR interconnector 16.3 5.4 2.2 1.7
High Case excluding IE-FR interconnector 22.0 8.8 2.4 1.8
The CRU notes that adding Greenlink results in a considerable reduction in RES curtailment
in Ireland, implying greater RES integration benefits from the addition of Greenlink across all
scenarios. This is consistent with the findings of Element Power.
3.5. Impact of Greenlink on Security of Supply
The CRU has estimated the Security of Supply benefits from Greenlink using 10 different
climatic years in Artelys Crystal Super Grid software. The simulation results were extracted,
and Security of Supply benefits were calculated by multiplying the ACER Value of Lost Load
28 Based on CRU’s TYNDP scenarios. TYNDP 2018 ST is compared to Element Power’s Reference Case. TYNDP 2018 GCA is compared to Element Power’s High Case. TYNDP 2016 V1 is compared to Element Power’s Low Case.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
33
(VoLL) for each country with the Expected Energy Not Served (EENS). This approach is
different from the ENTSO-E approach of modelling Security of Supply, which uses Monte
Carlo analysis, requiring a larger number of stochastic simulations and the use of a different
software.
Element Power’s approach to quantifying Security of Supply benefits, as part of the
Greenlink CBA, is also different from ENTSO-E’s approach. Element Power used the de-
rating factor of the Greenlink interconnector multiplied by the Capacity Market clearing price
(used as a proxy for the value of generation capacity in the Irish system). Using a capacity
market model, Element Power estimated only the impacts on generators’ capacity market
revenues – this approach appears to be more in line with a capacity adequacy study rather
than a Security of Supply analysis and does not assess the impact of Greenlink on expected
energy not served in Ireland and neighbouring countries.
The CRU’s SEM Security of Supply analysis results are shown in the figure below. The
results show that the introduction of Greenlink could reduce EENS within SEM, albeit the
level of EENS present in the scenarios without new interconnectors is small. Therefore, the
reduction in EENS, and the monetised Security of Supply benefit caused by Greenlink, is
negligible.
Figure 12: SEM EENS with and without Greenlink
This analysis suggests that Security of Supply benefits for SEM could reach up to
approximately €6m in NPV terms (for the period 2023 to 2047), in the Greenlink only
simulation. In contrast, the modelling results in a world with another interconnector to France
have no EENS or loss of load hours for SEM. Hence, there are no additional Security of
Supply benefits associated with the introduction of Greenlink.
The figure below shows EENS with and without Greenlink across the 10 climatic years (test
cases). While some countries other than GB and Ireland also experience some expected
unserved energy (MWh) and therefore, loss of load (hours) without Greenlink, with the
exception of Belgium in Test Case 8, the level of expected unserved energy does not change
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
34
with the addition of Greenlink. Thus, the CRU finds Security of Supply benefits only in Ireland
and Belgium.
Figure 13: EENS in V1 2030 with and without Greenlink
The monetised Security of Supply benefit for Belgium is small and is only experienced in
Test Case 8, where EENS is reduced slightly with the introduction of Greenlink. Using a
weighted-average of the VoLL for non-domestic sectors in Belgium, based on ACER’s recent
VoLL study, of approximately €4,000/MWh, the Security of Supply benefit to Belgium are
estimated to be approximately €1.5m on an NPV basis, notably lower than the amount
expected in SEM. Adding another interconnector to France has no impact on this benefit.
3.6. Impact of Brexit on Greenlink
The CRU has modelled Brexit sensitivities on the TYNDP 2018 ST scenario. Within this
sensitivity, it is assumed that NI and ROI remain coupled, e.g. SEM, but that GB is no longer
coupled with the rest of Europe. Therefore, friction is present between GB and the countries
it is connected to via an interconnector.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
35
Two levels of friction were modelled using the following assumptions29:
• For GB, friction has been implemented firstly through market inefficiency costs. The
CRU has tested two levels of market inefficiency costs: 0.25 EUR/MWh and 0.50
EUR/MWh. These were applied to all GB interconnectors – represented as a
transmission cost in the CRU energy market model.
• The CRU has also modelled friction through lower effective interconnector capacity,
due to coordination problems that occur within in a ‘decoupled’ market, where the
interconnector flows are unlikely to follow price differentials at all times. Interconnectors
are therefore unlikely to be used at full capacity30.
The CRU has compared the Brexit sensitivities (where a friction is introduced to power flows
between GB and EU markets) with and without an additional interconnector to France to
quantify the additional (dis)benefits from Greenlink under Brexit31. The results of the Brexit
simulations are presented below:
Figure 14: CRU CBA – Country breakdown of net welfare change under Brexit with Greenlink only
The addition of Greenlink under a Brexit sensitivity results in a positive change in consumer
surplus, i.e. €4,129m in SEM. However, when both Greenlink and another interconnector to
France co-exist under a Brexit sensitivity, the change in consumer surplus driven by
Greenlink is significantly lower, i.e. €46m in SEM.
29Note that the chosen approach does not result in interconnector flows against price differentials, i.e. from higher-priced markets to lower-priced markets, but the simulated flows are less than optimal. 30 This was applied by reducing the actual capacity of all GB interconnectors, reducing them to 80% of total capacity. For example, it can be assumed that Greenlink’s capacity effectively available is 80%, i.e. 400 MW instead of 500MW. Reduced capacity was applied to all GB interconnectors. 31 Note that the chosen approach does not result in interconnector flows against price differentials, i.e. from higher-priced markets to lower-priced markets, but the simulated flows are less than optimal.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
36
Figure 15: CRU CBA – Country breakdown of net welfare change under Brexit with Greenlink and another
interconnector to France
The table below compares the Brexit sensitivity results to the ST scenario (without Brexit).
The change in SEM net benefit under Brexit is lower than under the ST scenario due less
efficient trades between countries. However, the change in SEM consumer surplus is greater
under Brexit compared to the change in SEM consumer surplus under the ST scenario. This
is because the addition of Greenlink in a market with trading frictions provides an additional
link to import/export route and hence consumers are better off than without the addition of a
new interconnector.
Table 8: CRU CBA ST scenario vs. Brexit Sensitivity - NPV results32
Breakdown (€m, real 2017) ST scenario Brexit sensitivity33
Total NPV – with Greenlink only
Total NPV – with Greenlink & IE-FR interconnector
Total NPV – with Greenlink only
Total NPV – with Greenlink & IE-FR interconnector
SEM 539 125 490 199
Change in producer surplus -2,329 525 -3,277 434
Change in consumer surplus 3,365 -3 4,129 46
Change in congestion rent -255 -156 -121 -41
Greenlink project expenditure
-241 -241 -241 -241
The graph below shows the consumer surplus in absolute terms (NPV) in the Republic of
Ireland for the ST scenario and the Brexit sensitivity. Consumer surplus is negative because
it is represented as costs incurred by consumers, hence the negative sign. The yellow bars
32 The CRU modelled two levels of market inefficiency costs: €0.25/MWh and €0.50/MWh applied to GB interconnectors in both directions. The CRU’s modelling suggests that these market inefficiency costs generate very similar electricity prices and CBA results. As such, the CRU presents its analysis for the €0.50/MWh market inefficiency cost only. 33 Market inefficiency cost – 0.5 EUR/MWh
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
37
show the change in consumer surplus from the addition of Greenlink, i.e. the change is
positive.
Figure 16: Consumer surplus in absolute terms (NPV) in the Republic of Ireland: ST scenario and Brexit
sensitivity (0.5 €/MWh transmission cost)
In the round, under the Brexit sensitivity modelled by the CRU, the addition of Greenlink
generates benefits to SEM consumers, while where Greenlink and another interconnector to
France co-exist, the change in consumer surplus in Ireland due to Greenlink is only marginal.
Comparing the ST scenario to the Brexit sensitivity highlights the following:
• When Greenlink is in service, there is an improvement in consumer surplus (i.e.
€2.6b) in the ST scenario. This is also the case in the Brexit sensitivity, where the
improvement in consumer surplus is even more pronounced (i.e. €3.2b). However,
consumer surplus is even lower under Brexit (€-30.8b) than under the ST scenario (€-
30.7b) with Greenlink only. This suggests that under Brexit, Greenlink could provide
more benefits to consumers than under a No Brexit scenario.
• When looking at scenarios that also include another interconnector to France, there is
an improvement in consumer surplus compared to the ST scenario Base Case
without any new interconnectors (1) and with Greenlink only (2) but the addition of
Greenlink when another interconnector is already in service has no impact on
consumer surplus. This is also true in the Brexit sensitivity where the same level of
consumer surplus in a simulation with another interconnector only (7) and with both
Greenlink and another interconnector (8).
• The differences between (3) and (7) and (4) and (8) suggest that there are more
benefits related to the addition of another interconnector to France than Greenlink in
a Brexit sensitivity.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
38
3.7. Impact of Greenlink on Gas Transmission Tariffs
The CRU has analysed the modelled impact of Greenlink on gas demand in Ireland in its
CBA simulations, and has then undertaken simplified modelling of potential impacts on gas
transmission tariffs for the TYNDP 2018 BE 2025 snapshot year, resulting from changes in
the generation mix related to the Greenlink interconnector.
The CRU then calculated an implied percentage change in total gas demand34 (assuming
other gas demand components remain fixed as per GNI assumptions) and fed it through the
proprietary GNI Matrix Model35.
The CRU’s approach can only provide an estimate of the impact of the interconnector on
power sector gas demand and gas transmission tariffs, i.e. the percentage change in tariffs.36
However, CRU acknowledges that additional aspects might impact gas tariffs. For instance, if
the profile of gas generation across the year changes because of new electricity
interconnectors, then the way shippers book gas transmission capacity may also change. For
example, this could take the form of a shift to booking shorter-term products away from
annual capacity bookings, with a knock on impact on the calculation of annual capacity tariffs
each year. The CRU has not attempted to model changes in capacity bookings as this would
need to make assumptions of how generators would re-optimise their booking strategies in
light of new electricity interconnectors in Ireland.
CRU analysis of the change in power sector gas demand suggests that the addition of
Greenlink would have a small negative impact on annual power sector gas demand (a
reduction of 2.1% see the figure 17 below), and an even smaller corresponding impact on
total annual gas demand (a reduction of 0.9%37). Furthermore, total peak-day demand for
gas is expected to decrease marginally with the addition of Greenlink (by c.0.03%38).
34 The impact of an x% change in power sector gas demand on total gas demand is calculated based on the Gas Networks Ireland (GNI) 2017 Network Development Plan (NDP) sector composition projections for 2025/26. Note that total system demand in the NDP includes the ROI, NI and the Isle of Man (IOM). 35 For the purposes of this analysis, GNI allowed revenues are set as per PC4 forecasts for 2021/22 and extrapolated forward in time, assuming that they are unaffected by the new interconnector(s). Additionally, CRU’s analysis is limited to the impact on GNI tariffs and only considers existing domestic entry/exit points (i.e. the following were out of scope: (i) Corrib component of the Bellanaboy capacity entry tariff, (ii) Gormanston and Twynholm exit tariffs, and (iii) any potential new entry/exit points that may become operational in the meantime). 36 Note that the assumed electricity demand in the TYNDP 2018 (and 2016) scenarios is significantly lower than in EirGrid’s Generation Capacity Statement (on which the Gas Networks Ireland (GNI) 2017 Network Development Plan (NDP) is based). All else equal, this would imply significantly lower gas demand (and likely higher gas tariffs) under the TYDNP scenarios. These differences are out of scope. 37 Calculated based on a forecast from GNI that power sector gas demand will represent 42% of gas total demand in 2025. See table A2-10 in GNI’s 2017 Network Development Plan (NDP). 38 This figure reflects the impact of a 0.1% reduction in peak day power sector gas demand observed in CRU’s results, scaled by the percentage contribution of peak day power sector gas demand to total peak day demand. This percentage is forecasted to be 47% in 2025 as per Table A2-7 in GNI’s 2017 Network Development Plan (NDP).
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
39
Figure 17: Total power sector gas demand in 2025 in the Republic of Ireland (TYNDP 2018)
This analysis of the impacts from changes in power sector gas demand in 2025, would
suggest Greenlink will have relatively minor impacts on gas tariffs.
Specifically, there would be a negligible impact on entry and exit commodity charges
(charged per MWh and reflective of total annual gas demand), and a minor impact on entry
and equalised exit capacity charges (charged per peak day MWh and reflective of forecast
peak day bookings).
Where both Greenlink and another interconnector to France co-exist, the interconnectors
would have a negligible impact on entry commodity charges, an impact of approximately
0.5% on exit commodity changes and equalised exit capacity charges, and a minor impact
on entry capacity charges.
Table 9: Estimated interconnector impact on GNI gas tariffs (in percentage terms)
Interconnector impact on gas tariffs Greenlink only Greenlink & IE-FR
interconnector
Entry commodity charge negligible negligible
Exit commodity charge negligible +0.454%
Equalised exit capacity charge negligible +0.535%
Entry capacity charges – Bellanaboy +0.013% +0.029%
Entry capacity charges – Moffat +0.026% +0.057%
Entry capacity charges – Inch +0.073% +0.163%
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
40
4. CRU CBA Summary
This section of the paper sets out the key findings from the CRU CBA of Greenlink:
• Although there are differences between CBA modelling scenarios and assumptions
adopted by the CRU and Element Power, overall the CRU CBA results are consistent
with the findings of Greenlink. They show that Greenlink has the potential to deliver
benefits for Irish consumers where significant decarbonisation of electricity generation
occurs.
• The CRU modelling indicates that in relatively conservative scenarios of
decarbonisation of electricity generation in Europe, Greenlink does not drive benefits
for Irish consumers.
• In a scenario where another new interconnector is added alongside Greenlink, i.e.
another interconnector to France, consumer benefits from Greenlink appear to be
significantly reduced.
• There are potential security of supply benefits for the Single Electricity Market (SEM)
with the introduction of Greenlink.
• The CRU Brexit sensitivity39 assumes that there would be trading frictions40 between
GB and the countries it is connected to via an interconnector. Trading frictions
between countries would result in less efficient trading, less efficient interconnector
usage, greater price divergence, and hence potentially higher cost for consumers. As
a consequence of these frictions, the overall net benefits in SEM are lower under the
Brexit sensitivity than under a no Brexit scenario. Because of the underlying
inefficiencies, introducing a new interconnector may unlock more benefits to Irish
consumers compared to a no Brexit scenario where no trading frictions are present.
• The addition of Greenlink would have a small negative impact on annual power sector
gas demand and an even smaller corresponding impact on total annual gas demand.
• Both CRU’s CBA and Element Power’s CBA show that Greenlink reduces RES
curtailment and improves captured electricity prices for Irish consumers, i.e. average
annual electricity prices are expected to be lower in the SEM when Greenlink is in
service compared to prices that would be captured without Greenlink.
39 See Section 3.5 for a description of the Brexit sensitivity. 40 Trading frictions were modelled as a transmission cost on all GB electricity interconnectors.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
41
Table 10: Summary of CRU CBA results
€m NPV @ 4% (real 2017)
TYNDP 2018 ST Greenlink only
TYNDP 2018 ST with Greenlink & IE-FR interconnector
TYNDP 2016 V1 Greenlink only
TYNDP 2016 V1 with Greenlink & IE-FR interconnector
TYNDP 2018 GCA Greenlink only
TYNDP 2018 GCA with Greenlink & IE-FR interconnector
SEM 539 125 56 -67 640 359
Change in producer surplus
-2,329 525 668 639 -1,290 494
Change in consumer surplus
3,365 -3 -294 -406 2,156 74
Change in congestion rents
-255 -156 -84 -60 16 32
Greenlink project costs
-241 -241 -241 -241 -241 -241
Security of supply benefits
NA NA 8 0 NA NA
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
42
5. CRU’s Determination
In the previous sections of this determination paper the CRU has outlined its position on the
issues raised in the consultation paper and its views on the responses to that consultation as
well as the results of its CBA analysis of Greenlink. This section of the paper sets out the
CRU determination following an assessment and consultation on the Greenlink application,
primarily looking at whether the Greenlink interconnector is in the public interest.
As the CRU noted in the Greenlink consultation paper (CRU18119), assessing the Greenlink
interconnector application involves two stages:
• the first stage is testing the public interest case of the proposed interconnector; and
• the next stage is to decide which regulatory approach is justified based on the public
interest test.
This determination paper focuses on the first stage, i.e. the public interest test. The precise
details of any Cap and Floor regime would need to be consulted upon and determined at a
later stage.
The CRU has reviewed the consultation responses and considered the points raised by
respondents. In addition, the CRU has conducted its own CBA of Greenlink to test the
boundaries of Element Power’s own CBA of the Greenlink interconnector and the key inputs
and assumptions which may drive better or worse outcomes for Irish consumers and other
stakeholders. The CRU has modelled ENTSO-E TYNDP scenarios and compared the CBA
results to those of Element Power.
The CRU CBA of Greenlink indicates that, at the time of assessing the Greenlink application
and based on the draft ENTSO-E TYNDP scenarios, Greenlink has the potential to provide a
net benefit to the Irish consumers and Ireland as a whole. As such, the CRU has determined
that the Greenlink interconnector application passes the public interest test.
Notwithstanding this determination on the public interest test, if any subsequent information
is given to the CRU before making its final decision would lead the CRU to consider that the
basis of its public interest test decision has materially changed, then the CRU may revisit this
determination. In this case, the CRU may re-run its analysis in order to confirm whether or
not the project continues to be in the publics’ interest.
The CRU notes that Element Power is required to regularly update the CRU on progress
against their key project development milestones. Furthermore, the CRU expects the
Greenlink developers to give formal written notice of any material change to the project
design.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
43
6. Next Steps
As part of the next stage, following by sufficiently detailed financial and technical
submissions from the Greenlink developers the CRU expects to consult on a Cap and Floor
regime in H1 2019.
The CRU notes that in the next stage the CRU will engage with the Ofgem to explore the
potential for a Final Project Assessment process that takes both the Irish and GB regulatory
separate decision-making processes into account.