Capacity Mechanisms: management of Interconnectors and cross-border effects
description
Transcript of Capacity Mechanisms: management of Interconnectors and cross-border effects
Capacity Mechanisms: management of Interconnectors and cross-border
effects
David Newbery
University of Cambridge
Cambridge Spring Research Seminar16th May 2014
http://www.eprg.group.cam.ac.uk
D Newbery 2
Outline
• What is the problem?• Energy-only markets and capacity payments: theory
– policy failures, price caps
• Proposed EMR capacity auction– defended by missing money (VOLL > max energy price)
– complications: risk, market coupling rules
• Interconnectors: problems
Energy PolicyResearch Group
What is the problem?Ofgem’s derated capacity margin
Source: DECC IA
System Operator’sproblem
First Capacity Auction delivery
D Newbery 4
Interconnectors by 2018IFA to France 2 GWBritned to NL 1 GWMoyle to NI 0.5 GW (or 0.25?)EWIC to RoI 0.5 GWNEMO to Belgium 1 GWEclink to France 1 GW
Total 6 GW• potential swing 12 GW = 20% peak demand• emergency SO actions cannot reverse IC flow
Key question - what contributon to derated capacity?Poyry (2012): 50-80% depending on margins abroad
Energy PolicyResearch Group
D Newbery 5
Energy-only markets• If generators can (and are allowed to) bid
scarcity prices no problem?– France (de facto monopoly) bids high peak prices– GB has adequate capacity and flat prices
• Wind, PV, cheap coal, low C prices drive clean spark spreads negative (in DE especially)– electricity prices affected by policy
=> policy uncertainty undermines peaking investments neededCapacity contracts to address policy failure
Energy PolicyResearch Group
France much peakier than GBEuropean power exchanges 2012
€ 0
€ 10
€ 20
€ 30
€ 40
€ 50
€ 60
€ 70
€ 80
€ 90
€ 100
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percent time price higher than
Eu
ros/
MW
h
FranceUK MIP (Euros)Germany 2012Netherlands
€ 0€ 100€ 200€ 300€ 400€ 500€ 600€ 700€ 800€ 900
€ 1,000
0.0% 0.5% 1.0% 1.5% 2.0%
Newbery 2014 77
Capacity payments: theoryEfficient price = SMC + CP
SMC = system marginal cost, CP = capacity payment
CP = LoLP*(VoLL - SMC)LoLP = Loss of Load Probability in each hour
LOLE = LoLP over year (Loss of Load Expectation) set at 3 hrs in GB
=> VoLL = Value of Lost Load = £17,000/MWh• Max price in Euphemia day-ahead = €3,000/MWh
– Max price in France = €3,000/MWh
– Max price in SEM (Ireland) = €1,000/MWh
D Newbery 8
Experience in the Pool and BETTA
• The Pool (1990-2001) had an explicit CP at LoLP*(VoLL-SMP), VoLL = £(2013)5,000/MWh – (but SMP is as bid, not SMC)
• NETA/BETTA was an energy-only market with a Balancing Mechanism, System Buy and Sell prices– reformed many times, long side defaults to prompt price
– initially pay-as-bid, then average of last N MW
– consulting on Significant Code Review to deal with 2015/16
How well did they signal scarcity?
Energy PolicyResearch Group
Pool prices were peakier than spot market as they had a capacity payment
UK price duration curves 2012 and Pool Purchase price 1998-9
-£20
£0
£20
£40
£60
£80
£100
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percentage price higher than
£(2
01
2)/
MW
h
UKRPD Cal 2012
N2EX 2011-12
APX 2011-12
PPP 1998-9 at RPI
Price duration
£0
£50
£100
£150
£200
£250
£300
£350
£400
0.0% 0.5% 1.0% 1.5% 2.0%
percentage price higher than
£/M
Wh
CP in the Pool - 50% revenue in 1.8% (158) hoursPPP-SMP 1998-9 at 2012 RPI prices
£0
£20
£40
£60
£80
£100
0% 5% 10% 15% 20%
£(2
01
2)
/MW
h
0%
20%
40%
60%
80%
100%
capacity payment percent total capacity revenue
£0
£50
£100
£150
£200
£250
£300
0.00% 0.50% 1.00% 1.50% 2.00%
Pool prices 1998-9 and System Buy Price 2008Price duration curves Pool 1998-99 and Balancing 2008 at 2013 CPI prices
£0
£50
£100
£150
£200
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percent price higher than
PP
P £
(20
13
)/M
Wh
PPP PPP-SMP System Buy Price 2008
£0
£100
£200
£300
£400
£500
£600
£700
£800
0% 1% 2% 3% 4% 5%
Balancing prices peakier than Pool
Imbalance prices not adequately marginal?Price duration of System Buy Price 2013-4
£0
£20
£40
£60
£80
£100
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Percent time price higher than
£/M
Wh
£0
£50
£100
£150
£200
£250
£300
£350
0% 1% 1% 2% 2% 3% 3%
D Newbery 13
GB Balancing Market
• Ofgem conducts Significant Code Review of BM• Proposes:
– single marginal price
– load shedding bids at proxy Value of Lost Load• pVOLL = £3,000 rising to £6,000/MWh by 2018
• DECC sets VOLL at £17,000/MWh
– STOR bids in at f(pVOLL,LoLP)
BM price has never hit even £3,000/MWh
Missing money: 3hrs*(£17,000-6,000)/MWh
Energy PolicyResearch Group
Capacity to be replaced
Source: DECC IA
Seems small - can it be covered by interconnectors?
D Newbery 15
GB Capacity Auction
• Pay-as-clear descending clock auction in 2014 for delivery 2018/19– max energy price assumed £6/kWh– LOLE = 3 hrs => VOLL = £17/kWh– => missing money = 3 hrs*(17-6)/kWh = £33/kW
• new build gets 15 yr contract at auction price– existing plant: 1 yr contract unless major refurbish
• must be price taker unless good cause, entrants set price• existing plant can delay until later auction (2017)
• DSR auctioned from 2016: 1 yr contracts
Energy PolicyResearch Group
Illustrative auction demand curve
Source: DECC IA
New plant sets high price for all
No new plant and price is low
£75/kW year
Net benefit is difference between large producer surplus and large consumer loss
Initially adverse
GB coupledto NWE 4/2/14
SWE coupled toNWE 13/5/14
SEM not until 2016
D Newbery 19
Issues with interconnectors
• Interconnectors increase security of supply– provided they are free to respond to scarcity
=> they should have a positive derated capacity– Poyry estimates 50-80%
• Efficient pricing benefits trading country– if partner mis-prices they lose
=> efficient pricing drives out inefficient pricing
• But Euphemia imposes €3,000/MWh cap
Energy PolicyResearch Group
D Newbery 20
Cross-border capacity procurement
• EU wants any capacity market to be EU-wide• What contract can deliver capacity from abroad?
– How does specific foreign plant guarantee to export to GB in stress hours?
• PTR defaults to FTR on the day, but GB price may not signal true scarcity (and there is a price cap)
– Would it not likely do so anyway without a CP?
• Why not have a contract with the SO for imports over the interconnector in stress hours?– Devolve to SO securing supply
– or SO auctions for capacity over IC?
Energy PolicyResearch Group
D Newbery 21
Investment in interconnectors
• The economics of investment look good anyway– and get better with more wind, PV, carbon price floor
• recognising contribution to security increases value– DC interconnectors are controllable
– GB Interconnectors are logical suppliers of capacity
• problem: TO’s cannot contract for generation – but SO (abroad) could run auction for capacity and access
=> rent collected by ICs
EU open access to CP needs firm access to ICs
and penalties for non-delivery
Energy PolicyResearch Group
D Newbery 22
Conclusions
• Theory of scarcity pricing clear– leads to CP = LoLP*(VoLL-SMC)– energy-only markets could do this in theory
• and hedge with reliability options
• main failures: policy uncertainty and price caps– and lack of credible distant futures markets
• Capacity markets can address these– but potentially large transfers from consumers
And need much higher Euphemia price cap
Energy PolicyResearch Group
Appendix Capacity Mechanisms: management of Interconnectors and cross-border effects
David Newbery
University of Cambridge
Cambridge Spring Research Seminar16th May 2014
http://www.eprg.group.cam.ac.uk
D Newbery 24
AcronymsBM Balancing mechanism (or market)CONE Cost of new entry (net = net of revenue from selling power)CP, CM Capacity payment, capacity marketDSR demand side responseEMR (UK) Electricity Market ReformF(P)TR Financial (physical) transmission rightIC InterconnectorLOLE Loss of load expectation = LoLP over yearLoLP Loss of Load probabilityPV Photo voltaicSEM Single Electricity Market for IrelandSMC(P) System marginal cost (price)SO system operatorSRMC short-run marginal costSTOR short-term operating reserveTEM Target Electricity MarketTO transmission ownerVOLL Value of Lost Load (£17,000/MWh in GB)
Energy PlicyResearch Group
References
• DECC (2102) Electricity Market Reform – Capacity Market Impact Assessment at https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/252743/Capacity_Market_Impact_Assessment_Oct_2013.pdf •Poyry (2012) Poyry (2012) Impact Of EMR On Interconnection: A report to DECC at https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/252744/Poyry_Report_on_Impact_of_CM_on_Interconnection.pd?
1
D Newbery 26
Capacity payments in Irish SEM
• Bidding Code of Practice requires generation to bid into Pool at SRMC
=> missing money => CP based on VoLL & LoLP• generators get ex post system MC (SMC) + CP• VoLL scaled to deliver adequate payment for new
entry, paid part on ex ante LoLP, part on ex post– stabilises revenue, reduces volatility
• paid on imports, charged to exports
ex post pricing incompatible with TEM
Energy PolicyResearch Group
Average €7/MWh
SEM Capacity Payments 2012 and 2013
€ 0
€ 10
€ 20
€ 30
€ 40
€ 50
0%
5%
10
%
15
%
20
%
25
%
30
%
35
%
40
%
45
%
50
%
55
%
60
%
65
%
70
%
75
%
80
%
85
%
90
%
95
%
% time
Eu
ros
/MW
h
0%
20%
40%
60%
80%
100%
pe
rce
nt
of
tota
l c
ap
ac
ity
pa
ym
en
t
2012 2013 percent of total cap pay
€ 0
€ 50
€ 100
€ 150
€ 200
€ 250
0.0% 0.2% 0.4% 0.6% 0.8% 1.0%
50% revenue in 12% hours
28
Base case: each country matches average production to consumptionarbitrages over coupled IC’s, no shared balancing or reserves
Source: DG ENER (2013)
Benefits of market integration for EU 27+2 relative to base case
0
2
4
6
8
10
12
14
16
18
Integrated low TX self-secure shared balancing DSR
Scenario
Bil
lio
n E
uro
s/y
ea
r
2015 2020 2030
Optimal TX,shared reserves,
not balancing
Only halfoptimal TX built
No shared reserves
Remarkably little extra compared to
integration