LTC Rick ChildersAlan FeistnerWalla Walla District6 Oct 2020
2
WALLA WALLA DISTRICT BOUNDARIES
2
Mill Creek Dam(Bennington Lake)
McNary Lock & DamIce Harbor Lock & Dam
Lower Monumental Lock & Dam
Little Goose Lock & DamLower Granite
Lock & Dam
Dworshak DamLucky Peak Dam Jackson Hole Levees
• Civil Works Boundary focused on the Snake River Basin
• Covers 107,000 square miles
• Includes parts of 6 States• Regulatory Boundary is
Idaho border
3
AGENDA
District OverviewLower Monumental Guidewall
Channel Maintenance
2020 Fish Passage Improvement
2021 March NavLock Maintenance
McNary Update
Long Term Outage Planning
3
Broken Lower Monumental floating guidewall cables removed by divers in September 2020.
4
Above: The deadman anchor cable for the floating guidewall at Lower Monumental Lock and after being removed from the riverbed.
Top: Slack in the service cable connected to the guidewall was found on June 13, an indicator of broken cable.Above left: The anchor chain that replaced the anchor cable. The chain is twice as strong and not susceptible to damage by abrasion.Above right: A towboat held the floating guidewall in place from Aug. 1 to Sept. 22, even through the days were air quality was hazardous dues to fires and dust storms.
Above: A contractor was brought in to dredge the area around the cables and replace the damaged cables.
LOWER MONUMENTAL FLOATING GUIDEWALLEMERGENCY REPAIR
Anchor cable holding the floating guidewall in place separated in June 2020, requiring an emergency repair that was completed in September
5CHANNEL MAINTENANCE
• Channel Maintenance – Two primary concurrent actions post CRSO EIS
Accomplish Programmatic Sediment Management Study (2-year effort)- Complete hydraulic study - Begin NEPA- Complete Study; propose permanent federal navigation channel location
Interim Dredging Action - Coordinating scope and funding needs
- Value engineering dredging alternatives to reduce cost of dredging
• Lower Snake River Sediment Management Forum (Virtual, Wednesday 28 October, 9AM-2PM)
6
2020 FISH PASSAGE UPDATE
• Adult returns well below 10-year average; poor ocean conditions (BC, WA, OR); Fall Chinook and Sockeye showed promise, B-run Steelhead returns improved over 2019
• Fish Facility improvements– Lower Granite spillway PIT system successfully detecting fish – Automated water temperature monitoring in fish ladders– New transport trucks for Lower Granite
• 2020 Spill program changes– Spring (Apr-Jun ) increased spill volume to reach 125% gas cap at all projects– Additional spill in fall (Oct 1- Nov 15) and late winter (March 1-30) to assist
migrating adults in reaching natal tributaries • Evaluated early juvenile fish facilities startup
– 2020 – Lower Granite and McNary dams
6
7
MARCH 2021 MAINTENANCE PLANNING
Start: 6 am, Saturday, 6 March 2021
End: 11:59 pm Sunday, 21 March 2021 (2 weeks)• McNary• Ice Harbor• Lower Monumental • Little Goose
End: 11:59 pm Sunday, 28 March 2021 (3 weeks)• Lower Granite
7
8
MCNARY DOWNSTREAM MITER GATE MAINTENANCE HISTORY
File Name
8
The 65-year old D/S gate is a two-leafed, arched miter gate - 106 feet tall by 86 feet wide. Each gate leaf weighs 400 tons.
• 2011 Inspection - Steel/weld cracks of concern• 2014 major crack repairs• 2015 Inspection - Cracks increased in length• 2016 Welded and bolted repairs• 2018/2019 No significant crack repairs required• Embedded gudgeon anchor frames determined to be highest risk element
Crack growth indicates the D/S miter gate is past its fatigue life
9
MCNARY DOWNSTREAM MITER GATEMONITORING AND NEAR-TERM ACTIONS
File Name
9
o Semi-annual inspectionso Real-time stress monitoring of miter
gate and gudgeon anchorso Structural analysis of gate
• Update with new data• Advanced fatigue analysis
o Gudgeon anchor inspection• Will require minor concrete
removal in first quarter FY21• Weld inspection/analysis
o Crack repairs as needed• Minor crack repairs are completed
annually by maintenance staff each outage
Typical Weld Repair
10
MCNARY DOWNSTREAM MITER GATEFUTURE ACTIONS
File Name
10
Replace the D/S miter gate, gudgeon anchors and operating machineryInterim: Extend the life of the D/S miter gate• Monitor and repairs
• Real time monitoring – to determine if significant change occurred
• Gudgeon anchor replacement in Spring 2024 to eliminate highest risk element leading to catastrophic failure
• Quoins and miter required along with gudgeon anchor replacement • Emergency repairs as needed
The D/S Miter Gate is at or past it’s service life.
11
MCNARY NAVIGATION LOCKIN SERVICE SINCE 1954
File Name
11
Nav Lock Needs/Issues• Gudgeon Anchor Replacement• U/S & D/S Derrick Cranes Replacement• D/S Miter Gate Replacement• Power and Controls Upgrade• U/S & D/S Drainage and unwatering pumps• Tainter Valve Replacement
Strategy• Perform instrumentation monitoring and repairs
of gate until replaced• Incremental/Level Funding• Minimize extended outages• Early acquisition (longer lead items)• Replace highest risk assets first• Reduce schedule risk during extended outages
12
OTHER ITEMS
Long Term Outage PlanningWalla Walla is striving to extend the interval to the next extended outage by:
o Prioritizing replacement/refurbishment of highest identified riskso Replace McNary Navlock derrick cranes to reduce schedule risk during outageo Coordinating for early McNary gate prefabrication/delivery to mitigate risko 8-12 week outage Spring 2024 for McNary gate gudgeon anchor replacement to
mitigate risks prior to FY30 extended outage
Other Required Worko Little Goose upstream gate and machinery replacement o McNary navlock power and controls replacemento Lower Monumental navlock power and controls replacement
12
13
QUESTIONS
13
14
BACKUP SLIDES
15
MCNARY LOCK & DAM (2 WEEKS)
15
• Annual navigation lock maintenance • Inspect new tainter valves (1 & 3) to
establish baseline and monitor• Inspect original tainter valves (2 & 4)
to monitor known cracks and lifting eye issues
• Downstream miter gate crack mapping and monitoring
• Inspect gudgeon anchors for cracks• Install piping for new upstream
tainter valve unwatering systemMcNary’s NavLock
16
ICE HARBOR LOCK & DAM (2 WEEKS)
16
• Annual navigation lock maintenance
• Five-year Dam Safety culvert inspection requires complete dewatering of navlock
• Repair concrete spalling at Tainter Valve #3
• Complete replacement of remaining service & safety cables on floating guide wallFloating Guide wall cable broken
strands
Dewatered Navlock Chamber
17
LOWER MONUMENTAL LOCK & DAM (2 WEEKS)
17
• Annual navigation lock maintenance
• Replace tainter valve #2 lift cylinder
New Tainter Valve Cylinder and Piping Installed in 2020
18
LITTLE GOOSE LOCK & DAM (2 WEEKS)
18
• Annual navigation lock maintenance
• Gudgeon anchor instrumentation work
• Drain valve inspection & repairs, possibly fill valve repairs if needed and time allows
Navigation Lock Downstream Sill Inspection April 2020
19
LOWER GRANITE LOCK & DAM (3 WEEKS)
19
• Annual navigation lock maintenance• Tainter valves inspection• Remove bird netting from miter
gates• Complete miter gate cleaning and
inspection
Miter Gate – Failed Bird Netting and Required Cleaning
Failed Bird Netting