Cogentrix power project case

9
COGENTRIX POWER PROJECT CASE BY: SWAGATIKA PATASAHANI LLM (CORPORATE LAW) ROLL NO: 042

Transcript of Cogentrix power project case

Page 1: Cogentrix power project case

COGENTRIX POWER PROJECT CASE

BY: SWAGATIKA PATASAHANI

LLM (CORPORATE LAW)ROLL NO: 042

Page 2: Cogentrix power project case

FACTS OF THE CASE

In 1992, the Karnataka State Electricity Board signed a power purchase agreement for a thousand MW thermal power plant at Mangalore with an American company, cogentrix energy Inc. Karnataka State Electricity Board promised to purchase power from cogentrix for a period of 30 years.

The state cabinet issued an office order authorising the state government to enter into MOU for 250 MW project in Mangalore and Bangalore. In July 1992, in violation of Government of Karnataka order, memorandum of understanding where signed with cogentrix for Two 500 MW projects. Also in violation of its own orders, Government of Karnataka, in the MOU with cogentrix,allowed the company to bring in any partners the wished..

Page 3: Cogentrix power project case

In February 1993,a committee of secretaries of the state government recommended the approval of the project. In March 1993, a government order permitted cogentrix to sell power directly to industrial units at mutually negotiated rates. Subsequently, this order was overturned and the government asked Karnataka State Electricity Board to buy all power from cogentrix.

The plant at Bangalore was cancelled and the plant at Mangalore was allowed to double its capacity to 1000 MW.

With the shift of location, a new set of problems emerged. Since all the power generated generated in Mangalore locally was not required the power has to be transmitted to Bangalore. This transmission of electricity from mangalore to Bangalore required new transmission lines, which called for an additional investment of 270 crores.

Page 4: Cogentrix power project case

ISSUESThe state government was to sign a power project agreement with cogentrix. In January 1994, the central government made it a precondition that the PPA be vetted by independent Experts if it has to issue a counter guarantee. A team of experts from India together with American and German firms issued a report that was severely critical of the PPA. They were of the opinion that the PPA was one sided and that the capital cost of the plant was too high.

In August 1995 a company from Hong Kong, China and power was brought in as a co sponsor in the project. The Memorandum of understanding entered between the two parties was not disclosed. The balance sheet of the mangalore Power Corporation for the period 1995 to 96, did not show any expenses incurred in India or abroad. However between 92-96, the balance sheet of cogentrix showed approximately 175 crore had been incurred as developmental expenses on the Indian project.

Page 5: Cogentrix power project case

Writ petition was filed in the High Court of Karnataka by Arun Kumar Agarwal and S.K. Kantha seeking for investigation by appropriate agencies into the various allegations made by them and to initiate criminal proceedings against the guilty persons as per law. It was also prayed to 'set aside the power project entered by Karnataka Electricity Board (KEB) with Mangalore Power Corporation (MPC) and real lot the power project through an open bidding process

In response to the petition,a division bench of the High Court issued a directive for a CBI enquiry into the matter. However, supreme Court bench stayed this order of the Karnataka High Court.

Page 6: Cogentrix power project case

SUPREME COURT JUDGEMENT

IN THE SUPREME COURT OF INDIAC.A. No. 7231 of 1999Decided On: 13.12.1999Appellants:State of Karnataka Vs.Respondent: Arun Kumar Agarwal & Ors.

Court found High Court's Order erroneous - acts of persons in such case should not be subject of criminal investigation unless crime is reported to have committed or reasonable suspicion thereto arises - investigation cannot be subject of merely conjectures and surmises - impugned Order of High Court set aside.

Page 7: Cogentrix power project case

It is difficult to visualise that when an agreement had been entered into with a foreign company it has been done under suspicious circumstances, particularly when it had stood the test of scrutiny under three different Governments headed by at least three different Chief Ministers and when the examination of theproject and its approval was considered by different statutory and other agencies of the Government of India. Could it still be said that there had been kickbacks to any one of them or all of them in the matter of entering into a Memorandum of Understanding or in continuation of the same? The law, in fact, is otherwise.

Page 8: Cogentrix power project case

 The acts of persons will not be subject of criminal investigation unless a crime is reported to have been committed or reasonable suspicion thereto arises. On mere conjecture or surmise as a flight of fancy that some crime might have been committed, somewhere, by somebody but the crime is not known, the persons involved in it or the place of crime unknown, cannot be termed to be reasonable basis at all for starting a criminal investigation. However, condemnable be the nature or extent of corruption in the country, not all acts could be said to fall in that category. The attempt made by the High Court in this case appears to us to be in the nature of blind shot fired in the dark without even knowing whether there is a prey at all. 

In the result, we think that the order made by the High Court has got to be set aside

Page 9: Cogentrix power project case