Cofferdam
-
Upload
sukhwinder-singh-gill -
Category
Documents
-
view
55 -
download
1
description
Transcript of Cofferdam
Objectives:• Definition Of Cofferdam• Types Of Cofferdam• General Design Considerations Of Cofferdams• Advantages And Disadvantages Of Cofferdam• Typical Items Needed For Constructions Of
Cofferdam• Overview Of Steel Sheet Piling• Pictures Of Basic Construction Procedures
For a Braced-Cofferdam• Pictorial Presentation Of Olmsted Lock Project
What is a Cofferdam??
• “A cofferdam is a temporary structuredesigned to keep water and/or soil outof the excavation in which a bridgepier or other structure is built.”
-Standard Handbook of Heavy Construction
Types of Cofferdams • Braced
• Earth-Type
• Timber Crib
• Double Walled Sheet Pile
• Cellular
Braced Cofferdams
• •Formed from a single wall of sheet piling•Driven into the ground to form a boxaround the excavation site•The “box” is then braced on the inside•Interior is dewatered•Primarily used for bridge piers in shallowwater (30 - 35 ft depth)
Earth-Type Cofferdams
•Simplest Type of Cofferdam•Consists of an earth bank w/ a
clay core or vertical sheetpiling enclosing the excavation•Used for low-level waters with
low velocity•Easily scoured by water rising
over the top
Timber Crib Cofferdam
•Cellular-Type Cofferdam•Constructed on land and floated into place•Lower portion of each cell matched with
contour of river bed•Uses rock ballast and soil to decrease
seepage and and sink into place•Also known as “Gravity Dam”
Timber Crib Cofferdam (cont.) • Usually consists of 12’ x 12’ cells• Used in rapid currents or on rocky river
beds• Must be properly designed to resist lateral
forces such as: -Tiping/Overturning -Sliding
Double-Walled Cofferdam *Two-parallel rows of steel sheet piles
driven into the ground*Tied together with anchors and wales,then filled with soil*Three principle types:–Box: Consists of straight flush walls–Semicircular cells connected bydiaphragms–Circular cells connected with tie-rods ordiaphragms
Cellular Cofferdams • Two main types are circular and segmental• Can be used on temporary or permanent basis• Forces are resisted by the mass of the cofferdam
Cofferdam Design Considerations
• Scouring or undermining by rapidly flowingwater•Stability against overturning or tilting•Upward forces on outside edge due to tilting•Stability against vertical shear•Effects of forces resulting from:–Ice, Wave, Water, Active Earth and PassiveEarth Pressures
Advantages of Cofferdams
• •Allow excavation and construction ofstructures in otherwise poor environment•Provides safe environment to work•Contractors typically have designresponsibility•Steel sheet piles are easily installed andremoved•Materials can typically be reused on otherprojects
Disadvantages of Cofferdams
• •Special equipment required•Relatively expensive•Typically very time consuming & tedious•If rushed, sheets can be driven out of locksor out of plumb•When in flowing water “log jams” mayoccur creating added stress on structure
Items needed for installation
•Pile driving hammer–Vibratory or Impact•Crane of sufficient size•Steel sheet piles are typically used•H-piles and/or wide-flange beams for walesand stringers•Barges may be required
Pictures of Pile Hammers
Impact hammer
Vibratory Pile Driver
Steel Sheet Piling Properties
•Moderately watertight•High shear and bending strength•High interlock strength•Easy to install/remove•Reusable•Can be cantilevered but typically requireadditional structural member (i.e. wales andcross bracing)
Traditional Sheet Pile Shapes
Z-Type (Z)Used for intermediate to deep wall construction
Larson / “U” Type (U)Used for applications Similar to Z-Type
Arch shaped & lightweightUsed for shallower wall construction
Flat / Straight Type (SA),(S)Used for filled cell construction
Steel Sheet Pile Interlocks •No industry Standard
•Interlocks Should:–provide relative water or earth-tightconnections–permit reasonable free sliding to to connectsheets during installation–provide minimum guaranteed pull strength–allow minimum swing between locks in orderto form a circle
Typical Types of Interlocks
Ball & Socket (BS)Single Jaw (SJ)
Double Jaw (DJ) Hook & Grip (HG)
Double Hook (DH)
Thumb & FingerOne Point Contact (TFX)
Thumb & FingerThree Point Contact (TF)
Braced Cofferdam Construction •Install Wale and Strut System for Framework /
Template
Braced Cofferdam Construction• Install Wale and Strut System for Framework/Template
Braced Cofferdam Construction• Install Sheet piles using the Framework as Template
Braced Cofferdam Construction• Install Sheet piles using the Framework as Template
Braced Cofferdam ConstructionTips for installing sheet piles: -Always set up a template system -Rule of thumb:Crane Boom length should be twice that of the sheets -Drive the sheets with the “male” interlock leading in order to avoid soil plugs -If the “female” interlock must lead,place a bolt or other object at the bottom to avoid
debris filling the slot -Align the plumb the first two sheets and drive carefully and accurately -Drive sheet in pairs when possible placing the hammer in the center of the pair -Some contractors recommend not driving a sheet more than 1/3 its length before
driving the adjacent pile -letting the sheets “freefall” and drop in order to aid in penetration will generally
cause the sheet to fall ”out of plumb” -Cellular cofferdam require that all sheets are set and “closed” before any driving is
done -Finally…never rush the pile Foreman!!
Olmstead Lock & Dam Project •
Lock construction
•Project required massive cofferdam for Lock construction
Rendering of completed project
Olmsted Cofferdam Project • •Overview of Cofferdam Construction
–“U-shaped” cellular cofferdam–Consisted of 50 round cells and 49 peanut shapedconnecting arcs–Cells have 63’ diameter and place 81’ on center–Round cells consist of 120 sheets and arcs consistof 50 sheets (25 inside & out)–Sheet piling ranged from 50’ to 109’ in length–All cells filled with approx. 675,000 CY of sand
Olmsted Cofferdam Project -Pictorial Presentation of Cofferdam Construction
Site before construction
Olmsted Cofferdam Project
First six months of construction. Excavation of terrain performed to avoid “sliding” While lock foundation was being excavated.
1 Nov 1993
Olmsted Cofferdam Project Several high water events during the fall of1993 and spring of 1994Slowed the river work
4,Mar,1994
Olmsted Cofferdam Project Deflector and cell being constructed simultaneously
cells
Deflectors
11,July,1994
Olmsted Cofferdam Project
Typical Cell Framework and Construction
Olmsted Cofferdam Project
Typical Pile driving operationUsing a vibratory hammer.Impact hammer were also used.
Olmsted Cofferdam Project
Construction status improved significantly due during Summer and fall of 1994 due to extremely good river conditions
1,Nov,1994
Olmsted Cofferdam Project
Typical Cell Filling Operation
Olmsted Cofferdam Project
Typical Round Cell Construction
Location of connecting arc
Olmsted Cofferdam Project
2,May,1995
Olmsted Cofferdam Project
Dewatering of cofferdam was delayed due to a flood,in this photoThe water is within 1 foot of the top of cofferdam
28,May,1995
Olmsted Cofferdam Project
Dewatering of cofferdam took approx. 40 days,beginning in July of 1995
8,Aug,1995
Olmsted Cofferdam Project
Completed Cofferdam , turned over to lock contractor
28,Dec,1995
Olmsted Lock Project
Typical day of operations within the Cofferdam
Sept,1998
Olmsted Lock Project
Overview shot of project as of Dec,9,1998