Clementhorpe Ward meeting
Clementhorpe Flood Alleviation Scheme
15 July 2019
Purpose of this eveningWhat we will cover
2
1. Why we need to close Terry Avenue
2. Our draft Construction Traffic Management Plan
3
The Clementhorpe schemeWhy we need to close Terry Avenue?
The Clementhorpe schemeBetter protecting 148 properties
4
Our aim
To better protect Clementhorpe and South Bank, one of the city’s few
undefended communities, from its existing flood risk and the future implications
of climate change. We want to:
• provide a continuous line of defence and a high standard of
protection against flooding between Skeldergate Bridge and
Rowntree Park;
• Reduce the consequences of flooding in South Bank by installing
Property Flood Resilience products whilst supporting City of York Council
and the Clementhorpe Emergency Planning Group to increase
community resilience;
• utilise this ‘once in a lifetime’ opportunity to secure funding for a
scheme.
The Clementhorpe schemeWaterfront House and Clementhorpe/Terry Avenue junction
5
The Clementhorpe schemeThe underground work
6
What are we looking at?
Different construction methods to provide cut off
along Terry Avenue.
The Clementhorpe schemeSite complexity
7
8
Outline traffic management planHow we identified our proposed access route
ClementhorpeWhat do we need and how do we get there?
9
• Identify access points to the river frontage
• Confirm what is needed on site• Equipment
• Materials
• Personnel
• Confirm what can be brought in from a compound area• Equipment
• Materials
Access option 1Terry Avenue via Skeldergate
10
11
Access option 1Terry Avenue via Skeldergate
Height restrictions
Parking suspensions
What could we use this for?
• Staff access
• Staff parking
Access option 2Bishopgate Street
12
Access option 2Bishopgate Street
13
Access onto Bishopgate Street Bishopgate Street and Terry Avenue junction
What could we use this for?
• Staff exit from Terry Avenue
Access option 3Clementhorpe
14
Access option 3Clementhorpe
15
Resident parking suspensions
Turning circle
What could we use this for?
No access proposed
Access option 4Lower Darnborough Street via Cherry Street
16
Access option 4Lower Darnborough Street
17
Residents parking suspensions
Access to Dukes Wharf
Access through Dukes Wharf and access for residents
What could we use this for?
• No access proposed for full scheme
• Dukes Wharf construction period
Access option 5Vine Street through Caravan Park
18
Access option 5Vine Street through Caravan Park
19
Resident parking suspensions
Streets off Vine Street
Caravan Park Cesspit
Suspension of caravan site pitches – financial compensation
Caravan site security
Local flood defence construction
What could we use this for?
• No access proposed for full
scheme
• Caravan park construction period
Access option 6Terry Avenue via Butcher Terrace
20
Access option 6Terry venue via Butcher Terrace
21
• Residents parking suspensions
• Construction vehicles and public
• Public safety
• Vegetation
• Byway reinstatement including passing places
What are we looking at?
• Compound location
• Mitigation options
• Segregation