Clair Ridge Development - Environmental Statement

373

Click here to load reader

description

BP Exploration Operating Company published September 2010

Transcript of Clair Ridge Development - Environmental Statement

  • Clair Ridge DevelopmentEnvironmental Statement

    September 2010

  • Clair Ridge DevelopmentEnvironmental Statement

    Information |September 2010 1

    Standard Information Sheet

    Project (Installation) Name Clair Ridge Development

    DECC Reference number D/4091/2010

    Type of Project Field development with two bridge-linked platforms,

    wells and tie-in to existing export pipelines

    Undertaker name BP Exploration Operating Company Ltd

    Undertaker address Farburn Industrial Estate,

    Dyce, Aberdeen, AB21 7PB

    Licensees/Owners BP Exploration Operating Company Limited _ _ _ _ _ _ _ _ _ 27.6%

    Britoil plc _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 1.0%

    ConocoPhillips (U.K.) Limited _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 24.0%

    Chevron North Sea Limited _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 19.4%

    Clair UK Limited _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 9.3%

    Enterprise Oil Limited _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 18.7%

    Short description The project is the second stage of development of the Clair

    oil field. It will involve the installation of two bridge-linked

    platforms, one supporting drilling and production and the other

    supporting accommodation and utilities, on the West Shetland

    Continental Shelf in UKCS Block 206/8 (5.6 km northeast of

    Clair Phase 1 platform which started production in 2005 and

    93 km southeast of the UK/Faroe transboundary line). The Clair

    Ridge oil export pipeline will tie into the existing Clair Phase 1

    pipeline to Sullom Voe Terminal, Shetland and the gas export

    pipeline will tie into the existing West of Shetland Pipeline

    System. Of 36 wells to be drilled, several will be drilled from a

    semi-submersible drilling rig before the platforms are installed.

    The remaining production and water injection wells will be

    drilled from the drilling and production platform. The reservoir

    fluids will be fully processed on the platform and the produced

    water re-injected into the reservoir.

    Anticipated commencement of works First oil is targeted for second quarter of 2015.

    Signicant environmental impacts identied None

    Statement prepared by BP Exploration Operating Company Ltd

    Designed and Printed by Tay-CAD Ltd

  • Clair Ridge DevelopmentEnvironmental Statement

    Contents |September 2010 1

    Contents

    1 Introduction 1.1 Project background and purpose _ _ _ _ _ _ _ 1 | 1

    1.2 Scope and aims of the environmental statement _ _ _ _ _ _ _ _ _ _ _ _ 1 | 4

    1.3 Regulatory context _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 1 | 5

    1.4 BP environmental policy and requirements _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 1 | 6

    2 Consideration of Alternatives

    2.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 2 | 1

    2.2 Basis for Clair Ridge Development _ _ _ _ _ 2 | 2

    2.3 Concept selection (high level decisions) _ _ 2 | 2

    2.4 Second-level decisions _ _ _ _ _ _ _ _ _ _ _ _ _ _ 2 | 6

    2.5 Decisions remaining to be made _ _ _ _ _ _ _ 2 | 13

    3 The Development

    3.1 Development overview _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 1

    3.2 Reservoir characteristics _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 1

    3.3 Fluid characteristics and expected production _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 3

    3.4 Wells and drilling _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 6

    3.5 Pipelines and subsea infrastructure _ _ _ _ _ 3 | 13

    3.6 Jackets and topsides _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 15

    3.7 Production _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 17

    3.8 Commissioning _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 22

    3.9 Decommissioning _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 22

    4 The Environment

    4.1 Overview _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 4 | 1

    4.2 The physical environment _ _ _ _ _ _ _ _ _ _ _ _ 4 | 3

    4.3 The biological environment _ _ _ _ _ _ _ _ _ _ _ 4 | 12

    4.4 Commercial fisheries _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 4 | 27

    4.5 Other sea users _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 4 | 32

    4.6 Conservation interests _ _ _ _ _ _ _ _ _ _ _ _ _ _ 4 | 34

    5 The Environmental Assessment Process

    5.1 Overview _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 5 | 1

    5.2 Environmental screening and categorisation _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 5 | 2

    5.3 Scoping and consultation _ _ _ _ _ _ _ _ _ _ _ _ 5 | 2

    5.4 Environmental issues identification (ENVID) _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 5 | 8

    5.5 Assessment of residual impacts _ _ _ _ _ _ _ 5 | 14

    5.6 EIA integration with overall environmental management _ _ _ _ _ _ _ _ _ _ 5 | 14

    6 Physical Presence

    6.1 Seabed impacts _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 6 | 1

    6.2 Interactions with other sea users _ _ _ _ _ _ 6 | 7

    7 Discharges to Sea

    7.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 7 | 1

    7.2 Regulatory control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 7 | 1

    7.3 Drilling discharges _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 7 | 2

    7.4 Installation, commissioning and operational discharges _ _ _ _ _ _ _ _ _ _ _ 7 | 12

    8 Underwater Noise

    8.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 8 | 1

    8.2 Regulatory control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 8 | 2

    8.3 Hearing and use of sound by species at Clair Ridge _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 8 | 2

    8.4 Noise sources and potential impacts _ _ _ _ 8 | 5

    8.5 Mitigation measures _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 8 | 14

    8.6 Residual impacts _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 8 | 15

    8.7 Cumulative and transboundary impacts _ _ 8 | 16

    8.8 Assessing the likelihood of an offence _ _ _ 8 | 17

  • Clair Ridge DevelopmentEnvironmental Statement

    | Contents September 20102

    9 Atmospheric Emissions

    9.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 9 | 1

    9.2 Regulatory control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 9 | 3

    9.3 Sources of potential impacts _ _ _ _ _ _ _ _ _ _ 9 | 4

    9.4 Management and mitigation _ _ _ _ _ _ _ _ _ _ 9 | 9

    9.5 Residual impacts _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 9 | 12

    9.6 Cumulative and transboundary impacts _ _ 9 | 15

    10 Risk of Oil and Chemical Spills

    10.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 10 | 1

    10.2 Regulatory control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 10 | 2

    10.3 Oil spills _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 10 | 3

    10.4 Oil spill response strategy _ _ _ _ _ _ _ _ _ _ 10 | 28

    10.5 Cumulative and transboundary risk _ _ _ _ 10 | 31

    10.6 Chemical spills _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 10 | 32

    11 Waste Management

    11.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 11 | 1

    11.2 Regulatory control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 11 | 2

    11.3 Waste management policy _ _ _ _ _ _ _ _ _ _ 11 | 3

    11.4 Clair Ridge waste management strategy _ _ _ _ _ _ _ _ _ _ _ _ _ 11 | 3

    12 Environmental Management

    12.1 Clair Ridge environmental management and commitments _ _ _ _ _ _ 12 | 1

    12.2 The BP environmental management process _ _ _ _ _ _ _ _ _ _ _ _ _ 12 | 4

    12.3 Environmentally critical equipment (ECE) _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 12 | 5

    12.4 Environmental monitoring _ _ _ _ _ _ _ _ _ _ _ 12 | 5

    12.5 Environmental awareness and training _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 12 | 6

    12.6 Interface with contractors _ _ _ _ _ _ _ _ _ _ _ 12 | 6

    13 Conclusion

    13.1 Approach _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 13 | 1

    13.2 Potential environmental issues _ _ _ _ _ _ _ 13 | 1

    13.3 Cumulative and transboundary impacts _ 13 | 3

    13.4 Protected areas and species _ _ _ _ _ _ _ _ _ 13 | 4

    13.5 Environmental management _ _ _ _ _ _ _ _ _ 13 | 4

    13.6 Final remarks _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 13 | 4

    14 References

    Abbreviations and Glossaries

    APPENDIX A Summary of environmental legislation

    APPENDIX B

    Claire Ridge forecast production data

    APPENDIX C

    Vessel usage

    APPENDIX D

    Map of environmental surveys

    APPENDIX E Summary of informal consultations

    APPENDIX F ENVID matrices

    APPENDIX G

    The DREAM model

    APPENDIX H Underwater noise modelling methods

    APPENDIX I Emissions quantification data

    APPENDIX J Data for appropriate assessments

    APPENDIX K Claire Ridge commitments register

  • Clair Ridge DevelopmentEnvironmental Statement

    Non-Technical Summary |September 2010 1

    Introduction

    This Environmental Statement (ES) presents the findings of

    the environmental impact assessment (EIA) conducted by

    BP for the proposed Clair Ridge Development. The project

    is the second stage of development of the Clair reservoir

    and is located in the northeast Atlantic in UK Continental

    Shelf (UKCS) Block 206/8, approximately 55 km west of

    Shetland and 93 km southeast of the UK/Faroe median line

    (Figure S.1).

    Project background and purpose

    The Clair reservoir is the largest known hydrocarbon

    resource on the UKCS, occupying an area of some

    220 km2. Due to its size and complexity it is being

    developed in a series of phases.

    The first phase of development included the installation of

    the Clair Phase 1 platform and an export pipeline system

    in the summer of 2004 (Figure S.1); first oil was achieved

    in February 2005. The success of the Clair Phase 1

    Development now paves the way for further investment

    in the Clair field.

    The proposed second phase of development, Clair Ridge,

    aims to exploit the oil and gas reserves in the Ridge

    section of the reservoir to the northeast of Clair Phase 1

    (Figure S.1). The design of the Clair Ridge Development

    has built on the environmental and design work

    completed for the Clair Phase 1 project and takes

    account of BPs operational experience of the

    Clair Phase 1 facilities. The new development will

    have a greater oil handling capacity than Clair Phase 1

    and will be pre-equipped with facilities to support a

    number of subsea developments in other parts of the

    Clair field, should these be required in the future. Note

    that any further phases of Clair development would be

    the subject of additional environmental assessment

    and approval from the Department of Energy and

    Climate Change (DECC).

    Non-Technical Summary

    Figure S.1 Location of the Clair eld and the proposed Clair Ridge Development

  • Clair Ridge DevelopmentEnvironmental Statement

    | Non-Technical Summary September 20102 | Non-Technical Summary

    Environmental philosophy

    BP is committed to conducting activities in compliance

    with all applicable legislation and in a manner which contributes to BPs stated goals of no accidents, no harm to people and no damage to the environment. In order to achieve these goals there is a hierarchy of common policies, commitments and expectations that identify policy and regulatory requirements and provide tools to assist in compliance and performance improvements.

    During operations, the Clair Ridge Development will conform to the requirements of the Environmental Management System (EMS) established for the BP North Sea Strategic Performance Unit (SPU), which is certified to ISO 14001.

    Assessment of alternatives

    Throughout concept selection, through initial engineering and going forward into detailed design the Clair Ridge project team is utilising a holistic process of option analysis in order to facilitate and document decisions in a transparent and objective way - utilising criteria such as environmental impact, safety, technical feasibility, cost, ability to meet project needs, and stakeholder concerns. This holistic approach ensures environmental considerations are on an equal footing with other factors such as safety and technical viability.

    A number of processing and exporting concepts for the Clair Ridge fluids were considered during early project planning, resulting in selection of twin steel platforms with bridge link, with maximum production of 120,000 barrels of oil per day. Following selection of this concept, 2nd level options were appraised, using operational experience gained from Clair Phase 1. Appraisal included, but was not limited to, the oil export route, the power generation concept and the gas turbine configuration. Some decisions are still to be made, including the method of pipeline installation and the type of flotel to be used; the EIA is based upon the option that would represent the highest environmental impact for each receptor. For example, in considering seabed impacts it has been assumed that an anchored pipelay barge might be used and in considering noise generation and atmospheric impacts it has been assumed that a

    dynamically positioned pipelay barge might be used.

    Development concept and schedule

    The proposed development consists of two installations, one for drilling and production facilities (DP platform) and the other for accommodation and utilities (QU platform), with a bridge-link connection between them. Oil will be exported to Sullom Voe Terminal (SVT) in Shetland via a new pipeline tying into the existing Clair Phase 1 pipeline. Similarly, gas export to SVT will be via a new pipeline tying into the West of Shetland Pipeline System (WOSPS).

    In 2011, an eight slot drilling template will be installed and some wells will subsequently be pre-drilled (i.e. drilled from a mobile drilling rig prior to platform installation) and suspended for later tie-in. Export pipelines will be installed in 2012 and the platforms and subsea structures during 2013 and 2014. Following hook-up and commissioning, the current BP schedule is for first oil in 2015, although the timing of activities may change during project development. In total, over 104 million cubic metres of oil are expected to be recovered over the forty-year life of the platform.

    Environmental Statement Remit

    This ES has been prepared in accordance with applicable legislation and guidelines, including the Offshore Petroleum Production and Pipelines (Assessment of Environmental Effects) Regulations 1999 (as amended) which require evaluation of projects likely to have a significant effect on the offshore environment.

    The aim of the EIA is to assess the potential environmental impacts that may arise from the proposed Clair Ridge Development and to identify measures that will be put in place during design and operations to prevent or minimise these impacts. The ES summarises the EIA process and outcomes.

    The scope of the EIA was developed and agreed during a scoping consultation process. The EIA has addressed all aspects of this offshore development, from early drilling activities and installation and commissioning, through the operational phase to decommissioning.

  • Non-Technical Summary |

    Clair Ridge DevelopmentEnvironmental Statement

    Non-Technical Summary |September 2010 3

    The Development

    Reservoir and uid characteristics

    Clair Ridge fluids and conditions are relatively favourable,

    i.e. the oil is not at a high temperature or pressure and

    does not contain hydrogen sulphide.

    Wells and drilling

    The development is anticipated to involve the drilling of

    36 wells. Of these, 26 will be oil producing wells and 10

    will be for water injection to maintain reservoir pressure

    and enhance oil recovery. The producing wells are

    provided with gas lift facilities.

    Between three and seven wells (assumed to be six

    for the purposes of the EIA) will be pre-drilled and

    suspended for later tie-in by a semi-submersible drilling

    rig via a steel seabed template in the two year period

    prior to jacket installation. This will allow efficient

    production ramp-up on initial platform commissioning.

    The platform drilling programme will be continual after

    the initial tie-in of the pre-drilled wells and is expected to

    last approximately twelve years.

    The wells will be drilled in a series of sections of

    decreasing diameters. Of the 36 planned wells, it is

    expected that approximately 50% will be drilled with

    three sections, or strings, with hole diameters of 32,

    17 and 12. Five-string wells may be required where

    there is a large horizontal distance to the reservoir

    target (maximum step-out approximately 6 km), or to

    provide extra protection when drilling through the Lower

    Cretaceous region of the formation. These wells will

    have hole diameters of 32, 23, 17, 12 and 9.

    Two further liner strings can be added if required. The

    pre-drilled wells include a four-string well design involving

    36, 26, 17, and 12 diameter holes.

    Drilling uids (muds) and cuttings handling

    Drilling muds generally consist of a weighting agent

    such as barite suspended in water (water based mud or

    WBM) or some type of oil (oil based mud or OBM). Other

    chemicals may be added for specific functions depending

    on the geological formations being drilled and on the

    viscosity and specific characteristics required of the

    drilling fluid. Different types of mud are used for different

    parts of a well and final fluid selection for each section

    will be based on technical requirements for each type of

    well (producer or injector).

    The top-hole sections of each well (the 36 and 26

    sections for the pre-drilled wells and the 32 section

    for the platform wells) will be drilled using a seawater

    based solution and the inert cuttings generated from

    these sections will be deposited directly on the seabed,

    around the hole. A riser (pipe) will then be installed which

    connects the well to the platform and all other cuttings

    can be circulated back up to the drilling rig or platform.

    Cleaning and separation systems will enable the recovery

    of drilling fluids and partitioning of the drill cuttings for

    appropriate disposal.

    Well control equipment and well testing

    The primary well control barrier is the use of

    weighted drilling fluids which are sufficiently heavy to

    counterbalance the formation pressure. The secondary

    barrier will be the blow out preventer (BOP) system

    which exists to prevent uncontrolled flow from the well

    by positively closing the well-bore when required.

    Testing of the platform-drilled wells will be necessary

    for effective reservoir management and assessment

    of reservoir performance. This involves the production

    of a limited amount of fluid from the well into a test

    separator, where metering equipment will monitor the

    wells performance. The fluids will then pass into the

    main process system and no flaring will be required.

    The pre-drilled wells will be cleaned-up and tested

    briefly from the drilling rig, with produced crude oil and

    gas being flared; there is no plan to include an extended

    well test.

  • Clair Ridge DevelopmentEnvironmental Statement

    | Non-Technical Summary September 20104 | Non-Technical Summary

    DP topsides facilities

    The production process facilities are designed to collect

    the produced fluids from the wells and deliver crude

    oil, gas and water of sufficient quality to meet outlet

    specifications. The main process systems, situated

    on the DP platform, are illustrated in Figure S.3 and

    include the separation system which removes gas and

    water from the production fluid to obtain the required

    oil product specification. The produced water system

    removes residual oil to less than 30 milligrams per litre

    (mg/l) from the water separated from the produced

    fluids. Produced water can be directed overboard

    should the water injection system be unavailable. The

    are system provides a safe means of disposal of

    hydrocarbon gases during emergency situations, start-up

    and maintenance operations. A vapour recovery unit

    captures any gases in the flare system during normal

    operations and routes these back to the process, rather

    than being flared. The hazardous and non-hazardous

    drainage systems collect and treat contaminated water,

    ensuring that prior to discharge it contains less than

    40 mg/l of dispersed oil, in line with legal limits. The

    oil export system cools the crude oil and increases

    pressure to the specification required for delivery into the

    oil export pipeline.

    Figure S.2 Clair Ridge platforms

    (view looking northeast)

    Pipelines and subsea infrastructure

    The oil and gas pipelines from the Clair Ridge DP

    platform will tie into a subsea isolation valve (SSIV)

    installed approximately 200 m from the platform. The

    Clair Ridge oil will then flow to the Clair Phase 1 SSIV/

    Wye assembly via a new 6.5 km oil export pipeline.

    The DP platform will also be tied into the WOSPS via a

    14.0 km gas export pipeline. The tie-in point will be at

    the existing Clair Phase 1 WOSPS Tee. A new tie-in skid

    adjacent to this Tee will house isolation valves and allow

    gas import from WOSPS to Clair Ridge when required.

    The export pipelines will be laid on top of the seabed.

    The concrete-coating of the oil pipeline will provide it

    with sufficient weight and stability, but the gas export

    pipeline will be protected and stabilised with rock along

    its entire length. The hard seabed in this area means

    that pipeline trenching is not possible. The pipeline tie-in

    sections will be covered with concrete mattresses for

    stability and protection.

    During pipeline commissioning, the pipeline will be

    pressure tested using water treated with biocide

    and oxygen scavenger (to ensure that the pipeline

    is protected from corrosion) and dye (to enable the

    detection of any leaks).

    Platforms and processing facilities

    The twin platform design consists of two jackets

    supporting the DP and QU topsides (Figure S.2).

    The jackets will be transported onto location and installed

    using barges and heavy lift vessels and then piled

    into the seabed. The topsides will be transported and

    positioned onto the jackets using heavy lift ships and

    a heavy lift vessel. A flotel will be used to house the

    workforce throughout the hook-up and commissioning

    phase of the platforms.

  • Non-Technical Summary |

    Clair Ridge DevelopmentEnvironmental Statement

    Non-Technical Summary |September 2010 5

    Figure S.3 Simplied process ow diagram

    QU topsides facilities

    The QU topsides facilities house the utility systems.

    These include the main power generation system, i.e.

    four dual-fuel gas turbines (one of which is on standby)

    with waste heat recovery units (WHRU) which recover

    heat from the exhausts to heat the process fluids. Also

    included is the LoSalTM unit, a membrane separation

    package producing desalinated seawater for injection

    into the reservoir (via the DP platform) for improved

    oil recovery. Other utility systems include the closed

    circuit heating medium, closed circuit cooling medium,

    seawater lift, nitrogen generation and instrument air

    system. These utilities are distributed across the bridge

    link to the DP platform. The living quarters are also

    situated on the QU platform, with the fresh-water maker

    and sewage system.

    Commissioning

    The commissioning strategy seeks to minimise offshore

    commissioning activities by maximising the amount of

    onshore commissioning of process, utility and subsea

    systems. This will maximise production ramp-up and

    minimise flaring.

    Decommissioning

    A detailed decommissioning plan will be established

    prior to decommissioning to ensure there is minimal

    impact on the marine environment and other sea

    users. BP will evaluate options for facilities and pipeline

    decommissioning and will undertake decommissioning

    activities in compliance with regulatory requirements

    in force at the time of decommissioning. All technically

    feasible options will be considered. The present

    regulations for decommissioning require the complete

    removal of the Clair Ridge platforms and template to

    shore for reuse, recycling or final disposal on land.

  • Clair Ridge DevelopmentEnvironmental Statement

    | Non-Technical Summary September 20106 | Non-Technical Summary

    Overview of the environment

    An understanding of the environment in the vicinity

    of the Clair Ridge Development (located on the outer

    West Shetland Continental Shelf in the northeast

    Atlantic (Figure S.1) in water depths of 140 m), draws

    upon regional and site-specific environmental surveys

    and on research that has been carried out in the area.

    This includes the extensive data collation and review

    undertaken as part of the Clair Phase 1 Development

    EIA, updated where appropriate. The focus is on the

    offshore areas around the platforms and the tie-in

    pipeline routes. Consideration has also been given to the

    coastal characteristics throughout the area that would be

    vulnerable in the unlikely event of a large oil spill.

    Water current patterns in this area are often complex

    with various non-tidal components of current flow

    interacting with relatively weak tidal flow. Water column

    stratification occurs during the summer months when

    there is a distinct boundary between warmer surface

    waters and cooler bottom waters.

    Strong winds are characteristic of the northeast

    Atlantic, particularly during the winter months, and calm

    conditions are rarely recorded. Southerly and westerly

    winds tend to predominate for much of the year from

    July through to March. In contrast there is a greater

    evenness of wind distribution during the spring months

    (April to June).

    The seabed at the proposed platform locations is

    comprised of very gravelly sand with cobbles and

    numerous boulders overlain in places by thin ribbons of

    sand with occasional megaripples and scattered cobbles

    and boulders as shown in Figure S.4, taken in 2009.

    Key environmental sensitivities

    Based on previous experience, studies and consultation

    conducted for both the Clair Phase 1 and Clair Ridge

    projects, it has been possible to identify the key

    environmental sensitivities to the proposed development.

    These are summarised for the offshore environment

    in Table S.1. Seasonal ecological sensitivity offshore is

    highest between February and July due to high seabird

    vulnerability to surface pollution at these times.

    The combination of the shelf edge environment and the

    influence of the Gulf Stream to the west of Shetland

    results in a diversity of habitats and a particularly rich

    number of cetaceans. The distribution of cetacean

    species is related to oceanographic features such as sea

    temperature, salinity, water depth and sea floor relief and

    prey distribution and abundance. To the west of Shetland,

    different species show a tendency towards shelf, slope

    or deep water habitats.

    Figure S.4 Seabed in the vicinity of

    the Clair Ridge Development

  • Non-Technical Summary |

    Clair Ridge DevelopmentEnvironmental Statement

    Non-Technical Summary |September 2010 7

    Table S.1 Offshore environmental sensitivities

    Plankton Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

    A peak in phytoplankton (plant) productivity in late spring is followed by lower, yet constant, productivity until autumn. Zooplankton (animal) productivity follows a similar pattern with a one or two month delay. Zooplankton provides an important source of food for many fish species. Plankton communities are not generally subjected to pressures from human activities.

    Seabed animals Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

    Surveys showed the seabed to consist of gravelly sands with pebbles and cobbles supporting sparce surface living animal life (epifauna). It is unlikely that any particular seasonal sensitivities exist in the benthic communities present.

    Fish Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

    The development lies within spawning (March to May) and nursery areas for Norway pout and nursery areas for blue whiting and mackerel, as well as a mackerel migration route. Nonetheless sensitivity is generally low throughout the year since identified spawning and nursery areas extend over much wider areas (throughout UK and European waters).

    Seabirds Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

    Seabirds offshore are particularly vulnerable to oil spill. Fulmar, northern gannet, herring gull, great black-backed gull, kittiwake, common guillemot, razorbill and puffin are present in the west of Shetland area all year round, with many other species present at certain times of the year. In the vicinity of the Clair Ridge Development, densities of some species can be moderate to high during spring and summer. The European storm petrel (listed under Annex I of the EU Birds Directive) is present in the area in high densities during September and occurs in internationally important numbers. Overall sensitivity to surface oil pollution is greatest during February and March and between May and June.

    Cetaceans Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

    Large baleen whales migrate through the Faroe-Shetland Channel to summer feeding grounds in the north and winter breeding areas in the south. Long-finned pilot whales, Atlantic white-sided and killer whales also inhabit deep waters of the channel, while minke whales and several dolphin species have been observed over the shelf. Sightings tend to peak during the summer months, although this may be a consequence of seasonality in survey effort.

    Conservation Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

    There are no designated offshore sites in the vicinity of the Clair Ridge Development. Additionally, there are no potentially protected habitats such as sandbanks, reef structures or pockmarks nearby.

    Fisheries Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

    Different areas of the continental shelf west of Shetland are important for fisheries throughout the year. Demersal species are generally fished all year round. Pelagic fisheries exhibit some seasonality and exact seasons may change year to year. High-value mackerel are landed in winter months, herring are landed exclusively in July, and saithe are predominantly landed in the first half of the year. The level of demersal fishing effort in the area is moderate and the level of pelagic fishing effort is low, in comparison to the rest of the UK.

    Low Moderate HighGeneral sensitivity

    With regards to the coastal environment, the ecological

    sensitivity of the Shetland coastline ranges from low

    to moderately high with numerous specific areas with

    an elevated level of local sensitivity, usually related to

    bird and marine mammal breeding and nesting areas.

    The most sensitive period is during the summer months

    when most species are breeding and rearing young.

    The winter months are also important due to the

    presence of overwintering seabird and wildfowl

    populations. Spring appears to be the least sensitive time

    of the year.

    Other potential sensitivities to oil spills in coastal areas

    include fishing, mariculture, tourism and amenity value of

    the coastal landscape.

  • Clair Ridge DevelopmentEnvironmental Statement

    | Non-Technical Summary September 20108 | Non-Technical Summary

    Conservation interests

    The proposed development area does not lie within or

    close to any designated offshore conservation sites

    under Annex I of the EU Habitats Directive. An area of

    potential Annex I habitat (stony reef) lies along the shelf

    break downslope from the Clair Ridge Development.

    However, seabed surveys indicate that the proposed

    development area does not support stony reef habitat

    according to criteria developed by JNCC.

    The JNCC is currently working to identify important

    hotspots for seabirds in the offshore area, including

    several areas around Shetland, with a view to designating

    marine Special Protected Areas (SPAs). However, as yet

    no offshore SPAs have been identified for feeding or

    overwintering.

    A number of marine species in UK waters have been

    identified for protection under Annex II of the European

    Habitats Directive. The harbour porpoise is the only listed

    species likely to occur with any frequency in the vicinity

    of the proposed development. Although the JNCC is

    seeking to identify areas suitable for designation for

    harbour porpoise, the species is widely distributed in

    UK waters, and the area to the west of Shetland is not

    considered unique. European storm petrels, listed on

    Annex I of the Birds Directive, are widely distributed over

    the whole shelf break west of Shetland between May

    and November.

    The Shetland coastline supports internationally and

    nationally important populations of breeding seabirds. The

    coastline also has numerous boggy areas, which support

    approximately half of the British breeding population

    of red-throated diver. The west coast of Orkney is

    characterised by high cliffs and supports internationally

    important breeding seabirds.

    Shetland and Orkney also support internationally important

    breeding populations of common seal and Shetland

    supports one of the densest otter populations in Europe.

    Assessment of potential impactsThe main aim of the Clair Ridge project environmental

    strategy has been to design out, or reduce, issues

    believed to impact on the environment or on users of

    the environment.

    Project design and operational planning has succeeded

    in the removal or reduction of many of the key

    environmental issues. Using data and understanding

    relating to the proposed design, the sensitivity of the

    environment and consultation feedback, the core task of

    the EIA process has been to:

    Assess potential residual issues from the project, both from routine operations and possible accidents

    Define mitigation and management measures to be addressed during the detailed design phase and

    subsequent operations

    The following sections of the non technical summary

    present the findings of the EIA for the residual

    environmental issues remaining following design and

    operational planning. The issues are addressed under the

    following categories:

    1 Physical Presence 3 Underwater Noise

    2 Discharges to Sea 4 Atmospheric Emissions

    Operational issues

    5 Risk of Oil and Chemical Spills

    Accidental events

    The potential for cumulative or transboundary impacts

    is also addressed.

  • Non-Technical Summary |

    Clair Ridge DevelopmentEnvironmental Statement

    Non-Technical Summary |September 2010 9

    1 Physical presence

    The anchoring of the drilling rig, flotel and other vessels,

    and the installation and presence of the drilling template,

    jackets, pipelines and other subsea structures, have the

    potential to affect the seabed and associated animals.

    In addition, offshore activities associated with all stages

    of the development, and the physical presence of

    structures, could interact with other users operating

    within the same area of the marine environment.

    Seabed impacts

    Mechanisms for direct impact include disturbance of

    sediments and damage to seabed species; as well

    as localised loss or change of habitat through the

    introduction of novel substrata. Indirect impacts may

    be caused by the re-suspension and re-settlement

    of sediments.

    The total area of seabed directly impacted, including

    all anticipated anchor placements, rock dumping and

    mattressing, is estimated to be approximately 0.3 km2.

    This represents approximately 0.002% of the total West

    Shetland Continental Shelf area. Considering the small

    area likely to be impacted, the ability of some species

    to move out of the area and the absence of rare or

    protected species, the residual impact of direct physical

    injury or habitat loss to seabed fauna will be minor. The

    pipeline and other seabed structures will provide new

    stable hard substrata, equivalent to natural rock outcrops,

    in the already mixed substratum environment, which are

    expected to be colonised by any epifaunal animals (those

    living on the surface of the seabed) present in the area.

    Any anchor mounds that are generated will be eroded by

    the relatively strong bottom currents. Recovery of seabed

    affected by transient operations such as anchoring is

    expected to be rapid (less than five years) via sediment

    mobility and faunal re-colonisation.

    Any re-suspension of sediments will be localised and

    restricted to the installation phase, i.e. temporary,

    therefore the majority of species present will not be

    adversely affected and impacts are likely to be negligible.

    Interactions with other sea users

    The marine environment within which the Clair Ridge

    Development will be located is utilised by a number

    of other sea users, primarily the fishing and shipping

    industries. The increase in vessel traffic during installation

    and the physical presence of the structures potentially

    increases the risk of collisions. In addition, the proposed

    activities, vessels and structures will exclude fishermen

    and shipping from the Clair Ridge location and potentially

    increases the risk of gear and catch being damaged

    through interaction with subsea structures.

    Increased vessel traffic

    The increase in the number of vessels in the area during

    drilling, and installation and commissioning, is of limited

    duration. Standard communication and notification

    measures will be in place to ensure that all vessels

    operating the area are aware of the activities. Since a low

    number of vessels frequent waters within a 10 nautical

    mile radius of the Clair Ridge Development, and given

    the fact that the presence of the existing Clair Phase 1

    platform means that shipping and fishing interests are

    aware of field-specific vessel movements in the area,

    the temporarily increased vessel presence around the

    Clair Ridge Development is expected to have little or no

    significant residual impact.

  • Clair Ridge DevelopmentEnvironmental Statement

    | Non-Technical Summary September 201010 | Non-Technical Summary

    Fishing interference

    Snagging risks cannot be eliminated entirely and a

    number of mitigation measures will be in place to reduce

    them significantly, including the use of overtrawlable

    subsea infrastructure, consultation and notices to

    mariners. The measures BP will adopt are standard

    across the industry and have previously assisted in

    reducing the impact of oil and gas associated activities to

    other sea users.

    A specialist fishing study commissioned for the EIA

    noted higher vessel sightings occurring along the 200 m

    contour to the north and lower vessel sightings occurring

    towards the southwest of the Clair field.

    The presence of long-term exclusion zones around the

    drilling rig and subsequently the platforms, will prevent

    fishing vessels from operating in 0.009% of potential

    fishing grounds in the West Shetland Continental Shelf.

    Pipelines can interfere with demersal fishing activities

    due to the increased risk of snagging and damage. The

    fishing study indicated that pipelines, which can act as

    fish aggregation devices, may be preferentially targetted

    for fishing and concluded that the risks inherent in fishing

    over and along fishing friendly untrenched pipelines are

    within acceptable limits.

    Anchor mounds may pose a risk to fishing vessels.

    However, due to the small numbers of anchor

    placements and the temporary nature of the anchor

    mounds (as discussed above), it is likely that the threat to

    fishing in the Clair Ridge area is minor.

    2 Discharges to sea

    BP aims to reduce the impact of discharges on the

    environment, with emphasis placed upon pollution

    prevention and impact minimisation at source. Key

    design features of the Clair Ridge Development, such

    as a re-injection target of 98% of produced water and

    its associated chemicals, reduce residual levels of

    discharges to sea.

    The residual discharges from the Clair Ridge

    Development and the management and mitigation

    measures employed in order to adhere to legislation and

    achieve BPs goals are discussed below.

    Drilling discharges

    Discharge to sea of OBM cuttings is prohibited and these

    will be re-injected or, if cuttings re-injection (CRI) is not

    available, shipped to shore for onshore processing.

    Cuttings from the tophole sections of the wells, drilled

    with a seawater-based fluid, will be deposited on the

    seabed adjacent to the well. Where WBM are used for

    the lower sections of the wells, WBM cuttings will also

    be re-injected when CRI facilities are available, otherwise

    they will be discharged to sea through a caisson. As the

    precise quantity of WBM cuttings which can be

    re-injected is unknown, assessment assumed that WBM

    is used for all 23 and 17 well sections and no CRI

    is available for WBM. The worst-case quantity of WBM

    cuttings that would therefore be discharged ranges from

    238 tonnes for a pre-drilled well to 1,172 tonnes for a

    5-string, long platform well.

    Due to rapid dilution soon after release, and settlement

    of particles to the seabed, the impacts in the water

    column from these discharges will be negligible.

    Cuttings dispersion modelling predicted that, for a

    5-string platform well, deposition would occur on the

    seabed in a thin oval-shaped area lying predominantly to

    the northeast of the drilling centre. Any adverse risk as

    defined by the environmental impact factor (EIF) will be

    limited to a central area up to 300 m from the discharge

    location in the direction of the predominant current and

    approximately 50 m in other directions.

  • Non-Technical Summary |

    Clair Ridge DevelopmentEnvironmental Statement

    Non-Technical Summary |September 2010 11

    These impacts will be largely attributable to grain size

    alteration and thickness of deposition.

    The environmental impact factor (EIF) is an estimate

    of the area of seabed within which there exists a

    possibility of injury to 5 % of the most sensitive

    species.

    The environmental impact of the drilling discharges is

    expected to be loss of benthic community near the

    wellhead due to complete burial, and limited changes

    in the communities further from the discharge location.

    Available information for the Clair Ridge site suggests

    that no species were particularly sensitive to increased

    suspended solids or limited deposition and that

    recoverability of the species was high or very high.

    Further modelling considered the discharges from

    all platform drilled wells (30), to investigate potential

    cumulative impacts. As a worst case the discharges

    were assumed to occur immediately after each other

    with no time interval incorporated between modelling

    of individual well discharges to allow for recovery of

    the sediment. In this case the area of adverse risk, as

    defined by the EIF, extends to approximately 3.5 km from

    the discharge location in the direction of the dominant

    current and 250 m in other directions.

    In reality, the 30 wells are planned to be drilled over a

    12-year period. This will extend the duration of impacts,

    but reduce the scale of impact at any point in time, and

    reduce the likely recovery time following cessation of the

    drilling programme. A combination of sediment transport

    and redistribution, and recolonisation and bioturbation

    of the sediment, is expected to return the sediment to

    its natural state within a few years of completion of the

    drilling programme.

    Commissioning discharges

    The Clair Ridge pipelines will be flooded with seawater

    containing chemicals (eg biocides, oxygen scavengers

    and scale inhibitors) and hydrotested. Before start up,

    the pipelines will be dewatered. Although there will be

    discharges associated with each of these operations,

    they will be short-term and have only a localised effect.

    The risk to the environment was assessed as negligible.

    Produced water

    Following treatment of the produced water to ensure it

    contains an oil-in-water concentration of less than

    30 mg/l, a target of 98 % will be re-injected into the

    reservoir. The re-injection of produced water will limit the

    quantities of oil discharged and will also ensure minimal

    discharge of other chemicals added during processing.

    The impacts of any produced water discharges to sea

    during periods of produced water re-injection down-time

    were assessed as being negligible.

    Discharges from LoSalTM unit

    Use of the LoSalTM unit results in the discharge of

    high salinity water containing added chemicals such

    as biocide and anti-scalant. Predictive modelling

    indicates that the plume sinks rapidly to the seabed

    and that its concentration decreases to less than

    1 % above background salinity levels within 35 m of

    the discharge point.

    The risk to the environment from the LoSalTM discharge

    is predominantly from the batch discharge of a biocide

    which will be dosed on a weekly basis. However, this

    potential impact is very localised to within approximately

    1 km of the discharge point and short-term, lasting for

    approximately 24 hours after dosing.

  • Clair Ridge DevelopmentEnvironmental Statement

    | Non-Technical Summary September 201012 | Non-Technical Summary

    3 Underwater noise

    This EIA has utilised up-to-date scientific information and

    applied the most recent JNCC guidelines in an attempt to

    assess the significance of any potential impacts from the

    Clair Ridge Development.

    Sources of noise generation from activities associated

    with the development which have the potential to impact

    upon marine species in the vicinity of the development

    include pile driving, drilling, vessel activity and offshore

    pipelay activities. The potential impacts of most noise

    sources on marine mammals were assessed as being

    negligible or minor.

    A specialist modelling study was commissioned to

    inform the assessment of the impacts from the noisiest

    operations, the piling of the drilling template and jackets.

    The study indicated that the entire range in which injury

    may be caused will be contained within the marine

    mammal mitigation zone, i.e. within the area where

    measures can be taken that seek to ensure no marine

    mammals are in the area of impact prior to pile driving

    being initiated.

    Considering the very short time period during which pile

    driving will actually occur, and the nomadic behaviour of

    cetaceans (which imply that they will actively avoid loud

    noise sources), it is unlikely that any will be exposed to

    sound which would cause significant behavioural effects.

    Assessing the likelihood of an offence

    The EIA also includes an assessment of whether or

    not the proposed operations will cause disturbance of

    European Protected Species (EPS) under the Habitat

    Regulations and Offshore Marine Regulations.

    The nature of the piling activity and the proposed

    mitigation measures mean there will be a negligible risk

    of injury or disturbance offence as a result of the Clair

    Ridge activities. BP therefore considers that application

    for an EPS licence is not required.

    4 Atmospheric emissions

    The use of energy optimisation and BAT studies for

    power generation, and key design decisions regarding

    flaring, have minimised the atmospheric emissions

    associated with the development. The ES details

    the expected residual levels of emissions from the

    installation and operation of the Clair Ridge Development

    and models the dispersion of emissions from the major

    operational sources, i.e. the gas turbines and

    safety-related flaring.

    To reduce the total level of flaring from Clair Ridge

    operations, the development includes a vapour recovery

    unit. This means that vapours that would otherwise be

    flared can be recovered and processed.

    The naturally low driving force of the Clair reservoir

    means that the Clair Ridge Development starts from a

    position of considerable disadvantage when comparing

    energy required per barrel of oil production against many

    other BP assets. Notwithstanding, energy efficiency

    and minimisation of atmospheric emissions has been

    evaluated as part of the decision-making process when

    assessing options around the main energy consumption

    items e.g. power generation, gas compression, artificial

    lift, water injection and oil export.

    Local impacts

    Throughout the installation, commissioning, and

    operation of the Clair Ridge Development there will be

    additional levels of NOX, SO2, and VOCs released into the

    environment. However, the effects from these pollutants

    will be very localised and, due to the dispersive nature of

    the offshore environment and the remote location, they

    will have a negligible effect on the nearest receptors

    on Shetland.

    Contribution to global greenhouse gases

    The average annual CO2 equivalent emissions from

    the Clair Ridge Development, including both direct and

    indirect greenhouse gases have been estimated to be

    approximately 377 kte which represent approximately

    0.85% of the total offshore UKCS CO2 emissions.

  • Non-Technical Summary |

    Clair Ridge DevelopmentEnvironmental Statement

    Non-Technical Summary |September 2010 13

    5 Risk of oil and chemical spills

    The ES describes the measures that will be put in place

    during the Clair Ridge Development to prevent spills, and

    proposed contingency measures that will be employed

    to ensure an effective response in the unlikely event

    of a spill.

    It is BPs aim to cause zero damage to the environment,

    minimising the risk of spills using measures relating to

    plant, people and processes. Therefore in light of the

    Deepwater Horizon incident in the Gulf of Mexico, the

    ES incorporates emerging, relevant information from the

    incident while recognising that the Clair Ridge drilling

    programme consists of development drilling in 140 m of

    water into a reservoir which does not contain fluids at

    high pressure or temperature and in which more than 30

    wells have been drilled since the 1970s.

    Oil spills

    Analysis of industry spill frequency indicates that the

    most probable spills from the Clair Ridge Development

    are small spills of < 1 tonne and focus has been given to

    prevention of these spills through design, specification

    and implementation of agreed operational procedures.

    Larger blowout and pipeline spills that could reach the

    coastline are considered to be remote or extremely

    remote events, i.e. low probability.

    The consequences of a significant release of

    hydrocarbons from the Clair Ridge Development will vary

    depending on factors such as wind speed and direction

    and sea state, as well as the time of year and the length

    of coastline affected. For example, after the breeding

    season ends in June, moulting auks (guillemot, razorbill

    and puffin) disperse from their coastal colonies into

    offshore waters and kittiwake, gannet and fulmar are

    present in significant numbers, making high numbers of

    birds particularly vulnerable to oil pollution.

    As the probability of spills of this magnitude occurring

    is considered remote or extremely remote, the overall

    risk of an oil spill from the Clair Ridge Development

    adversely impacting Shetland is very low. To address

    the small residual risk of spill which remains, even

    with comprehensive prevention measures in place, BP

    implements a range of response/mitigation measures, as

    detailed in the spill response strategies.

    Spill response strategy

    Procedures and protocols have been implemented for the

    Clair Phase 1 oil export pipeline to prevent and minimise

    the risk of an oil spill from the pipeline, and respond in

    the unlikely event of a spill. These will be updated, as

    appropriate, to incorporate the Clair Ridge oil export

    pipeline tie-in.

    The BP Onshore Oil Spill Plan was implemented for the

    Clair Phase 1 Development in addition to immediate

    offshore response. As part of this plan, BP have

    contracted OSR to have strategically located mobile

    response packages, and trained response personnel,

    that can be engaged to combat oil spills approaching

    inshore areas of Shetland. This plan will be reviewed

    and modified to incorporate any changes required for the

    inclusion of the Clair Ridge Development.

    Detailed and fully tested oil spill response strategies,

    appropriate to local environmental sensitivities will be

    developed and finalised for both drilling and production

    prior to the commencement of operations. These will

    be documented in the Oil Pollution Emergency Plans

    (OPEPs) for the drilling rig and the Clair Ridge platforms.

    In light of the Deepwater Horizon incident in the Gulf of

    Mexico. The OPEPs will consider, and where appropriate

    incorporate information gained from the Deepwater

    Horizon incident in the Gulf of Mexico. The OPEPs will be

    submitted for approval by the regulator in sufficient time

    to allow full consideration of the proposals.

  • Clair Ridge DevelopmentEnvironmental Statement

    | Non-Technical Summary September 201014 | Non-Technical Summary

    6 Cumulative and transboundary issues

    Cumulative effects are those that impact on the

    environment outside the local scale and those that add to

    existing or reasonably foreseeable future impacts. Clair

    Phase 1 was the third oil and gas field to be developed

    in the area to the west of Shetland, following Foinaven

    and Schiehallion. Approval has also been granted for

    the combined subsea development of the Laggan and

    Tormore gas fields.

    Transboundary environmental impacts originate in one

    country but have an effect on the environment in another

    country. Clair Ridge is located approximately 93 km (58

    miles) from the UK/Faroes boundary and

    236 km (147 miles) from the UK/Norwegian boundary

    (Figure S.1).

    The main aim of the Clair Ridge environmental philosophy

    has been to design out, or reduce, issues believed to

    present significant risk to the environment or users of

    the environment. Project planning and operational design

    has removed or substantially reduced key issues such as

    the discharge to sea of drill cuttings, produced water and

    associated chemicals and certain atmospheric emissions.

    Modelling of residual discharges to sea and atmospheric

    emissions, and consideration of interference of the

    development with other sea users indicated that the

    potential for cumulative or transboundary environmental

    impacts attributable to these is limited.

    As indicated by historical data, the likelihood of one major

    spill occuring is remote or extremely remote, limiting the

    potential cumulative oil spill impact from Clair Ridge and

    other existing installations. Detailed contingency plans

    are in place for each installation, outlining the response

    measures to be implemented in the event of any spill.

    Oil spill modelling undertaken - which assumed no

    response measures were implemented - indicates

    some probability that, in the event of a worst case

    spill, oil could move across international boundaries,

    particularly into Norwegian waters. The assessment of

    spill likelihood, based on historical UKCS and international

    incident data, demonstrates that the likelihood of a spill

    large enough to lead to such a transboundary impact

    is remote extremely remote, i.e. low probability.

    Therefore BP believes that consultation under the

    Espoo convention is not required as a result of the Clair

    Ridge Development, the Espoo convention requiring

    notification and consultation only on projects likely to

    have a significant adverse environmental impact across

    boundaries.

    The risk of oil spill having transboundary impact,

    particularly from the North Sea operations, is recognised

    by the UK Government and other governments around

    the North Sea. Agreements are in existence for dealing

    with international oil spill incidents with states bordering

    the UK. In the event of a major spill which is predicted

    to drift into Norwegian waters the NORBRIT plan will be

    activated. The NORBRIT plan is a joint UK/Norway oil

    spill contingency plan operating within the framework of

    the 2006 National Contingency Plans; the plan is oriented

    towards major spills resulting from, for example,

    blow-outs. It becomes operational when agreement

    to the request for its implementation is reached.

    Responsibility for implementing joint action rests with

    the Action Co-ordinating Authority (ACA) of the country

    on whose side of the median line a spill originated. The

    UKs ACA is the Counter Pollution Branch of the Maritime

    and Coastguard Agency (MCA).

  • Non-Technical Summary |

    Clair Ridge DevelopmentEnvironmental Statement

    Non-Technical Summary |September 2010 15

    The way forward

    Environmental considerations have played, and will

    continue to play, an important role in the decision-

    making process throughout the Clair Ridge project.

    Throughout the project, considerable efforts have been

    made to remove or significantly reduce issues that could

    lead to possible impacts on the environment. Where

    this has not been possible, detailed attention has been

    given to defining residual issues and seeking ways of

    minimising any potential impacts.

    Several key decisions led to removal or major reduction

    in activities considered likely to have significant impacts

    onto the environment, in particular:

    Oil/Gas pipeline oil and gas exported to shore via short tie-ins to existing pipelines, thus reducing the

    environmental impact that would result at landfall and

    to the seabed from new export pipelines.

    Routine flaring the flaring philosophy for the Clair Ridge Development is not to flare gas routinely

    during normal operations, and to have a closed flare

    system with flare gas recovery in order to reduce

    atmospheric emissions such as CO2, NOx, SOx and

    unburnt hydrocarbons.

    CRI OBM drill cuttings and drilling slops will routinely be re-injected into the formation. WBM drill cuttings

    and drilling slops (other than those of the top hole

    sections drilled riserless) will be considered for CRI.

    Each well will be reviewed on a case-by-case basis to

    assess if re-injecting such materials would significantly

    reduce the availability of CRI wells for re-injection of

    OBM cuttings. CRI will reduce any potential impacts

    on seabed and fauna.

    PWRI and LoSalTM produced water and its associated chemicals will be re-injected into the

    reservoir, thus reducing potential impacts on the

    water column. Low salinity water injection using

    LoSalTM will reduce the risk of reservoir souring and

    sulphate scaling. This will reduce the overall chemical

    requirement, reducing potential impacts on the water

    column.

    Power generation the selection of a centralised electrical power generation system allows for recovery

    of the waste heat from Gas Turbines as useful heat to

    meet the process requirements, removing the need

    for separate fired heaters or large electrical heaters.

    Key Residual Issues

    Overall it is considered that, following application of

    management and mitigation measures identified in

    this ES, the Clair Ridge Development will not cause

    significant environmental impacts.

    However, there are aspects of the project that will need

    to be managed sensitively in order to minimise potential

    environmental effects. These include the following key

    residual issues:

    Underwater noise pile driving is seen as the Clair Ridge Development activity generating the greatest

    underwater noise levels. BP will implement a number

    of measures to mitigate noise impacts based on the

    principles of the JNCC guideline for piling activities

    to address any potential for injury and non-trivial

    disturbance. As the most commonly sighted marine

    mammals species in the development vicinity are

    considered less susceptible to low frequency sounds,

    and that pile driving noise will be emitted over a

    short period of time, significant, residual injury or

    disturbance impacts occurring as a result of the piling

    activities at Clair Ridge are considered unlikely.

    Risk of oil spills the focus of the Clair Ridge project has been on spill prevention. The highlighted

    prevention methods will considerably reduce the risk

    of oil spill. However, a residual risk of oil spill remains

    and therefore an oil spill response strategy has been

    developed. This strategy will be taken on into detailed

    OPEPs which will include further consultation with the

    statutory authorities and appraisal of existing response

    arrangements.

  • Clair Ridge DevelopmentEnvironmental Statement

    1 |September 2010 1

    Introduction1

    1.1 Project background and purpose1.1.1 History of the Clair eld

    The Clair field, discovered in 1977 and extending over an

    area of about 220 km2, is the largest known hydrocarbon

    resource on the UKCS. It is a challenging fractured

    sandstone reservoir of Devonian to Carboniferous age,

    which is being developed in a series of phases.

    Ten appraisal wells were drilled into the reservoir (by four

    different operator groups) from field discovery through

    to 1990. The information obtained demonstrated that

    the reservoir covered a large geographical area but failed

    to confirm the presence of economically recoverable

    reserves. Between 1990 and 1995 the operators with

    an interest in the Clair field drilled a further five appraisal

    wells and commissioned a 3D seismic survey. Although

    not sufficient to establish commercial viability, this

    activity did demonstrate that one geological segment

    of the reservoir known as the Core was the focal area

    for any possible development. In 1996 an extended well

    test demonstrated that the Core area was capable

    of sustained production performance. A further two

    appraisal wells drilled in 1997 into other areas of the

    This Environmental Statement (ES) presents the findings of the environmental impact assessment (EIA) conducted

    by BP for the proposed Clair Ridge Development. The project is the second stage of development of the Clair oil

    reservoir and is located in the northeast Atlantic in UK Continental Shelf (UKCS) Block 206/8, approximately 55 km

    west of Shetland and 93 km southeast of the UK/Faroe median line, in water depths of 140 m (Figure 1.1).

    The proposed development consists of two installations, one for drilling and process facilities (DP platform) and the

    other for accommodation and utilities (QU platform), with a bridge-link connection between them. Oil will be exported

    to Sullom Voe Terminal (SVT) in Shetland via a new 22 diameter 6.5 km pipeline tying into the existing Clair Phase 1

    pipeline. Similarly, gas export to SVT will be via a new 6 14 km pipeline tying into the existing West of Shetland Pipeline

    System (WOSPS).

    This chapter explains the background and purpose of the proposed development and describes the scope and aims of the EIA process carried out. The underlying regulatory and BP environmental requirements are also outlined.

    reservoir supported initiation of development concept

    studies for a first phase of development.

    Initial development (Clair Phase 1) of the Clair field

    centred on the Core, Graben and Horst reservoir areas

    in the central part of the reservoir (Figure 1.1). An EIA

    was completed for Clair Phase 1 and the resultant ES

    was submitted and approved in 2002 (BP, 2001; DTI

    reference number: D/1228/2001).

    The Clair Phase 1 platform and export pipelines were

    installed offshore during the summer of 2004 and the

    field achieved first oil in February 2005. Oil from Clair

    Phase 1 is exported to SVT via a 105 km pipeline, whilst

    gas is exported through a 10 km spur line into the

    WOSPS (Figure 1.1). Oil production from Phase 1 built up

    to a plateau of around 50 thousand barrels per day (mbd

    ca 7,950 m3 per day) in 2007. By the end of 2010 the Clair

    Phase 1 Development will have produced 70 million stock

    tank barrels (mmstb) of oil (approximately 11.5 million

    m3) from the Lower Clair Group reservoir. The success of

    the Clair Phase 1 Development now paves the way for

    further investment in the Clair field.

  • Clair Ridge DevelopmentEnvironmental Statement

    | 1 September 20102 | 1

    1.1.2 The Clair Ridge Development

    The second phase of the development, Clair Ridge

    (originally named Clair Phase 2), commenced with a

    programme of appraisal drilling involving three wells

    drilled between 2005 and 2007. These wells, together

    with an ocean bottom cable (OBC) seismic survey

    acquired in 2006, have given sufficient confidence to

    proceed with the Clair Ridge project. This aims to exploit

    the oil and gas reserves in the Ridge section of the

    reservoir (the elongated up-thrown part of the field

    to the northeast of Clair Phase 1; Figure 1.1).

    Figure 1.1 Location of the Clair eld and the proposed Clair Ridge Development

  • 1 |

    Clair Ridge DevelopmentEnvironmental Statement

    1 |September 2010 3

    Table 1.1 Ownership of the Clair eld

    The design of the Clair Ridge Development has built

    on the environmental and design work completed for

    the Clair Phase 1 project and takes account of BPs

    operational experience of the Clair Phase 1 facilities.

    The Clair Ridge facility will have 36 well slots, compared

    to the 28 of Clair Phase 1; a higher process capacity

    (ca 19,000 m3 or 120 mbd oil handling capacity compared

    to ca 11,000 m3 or 67 mbd) and will be pre-equipped with

    facilities to support a number of subsea developments

    in other parts of the Greater Clair field, should these

    be required in the future. Any further activities and

    development related to possible further phases of

    Clair development would be the subject of additional

    environmental impact assessment and submission

    of statutory environmental documentation to the

    Department of Energy and Climate Change (DECC).

    Concept selection for the Clair Ridge Development

    occurred during 2008 and 2009. In 2011, an eight slot

    template will be installed and a number of wells are

    expected to be pre-drilled (i.e. drilled before installation

    of the DP platform), cleaned, completed and suspended.

    The subsea pipelines will be installed in 2012. This will

    be followed by installation of the platforms and subsea

    structures during 2013 and 2014. Following hook-up

    and commissioning (HUC), the current BP schedule

    is to achieve first oil in 2015 (Figure 1.2), although the

    proposed timing of activities may change during project

    development. In total, over 104 million m3 (638 mmstb)

    of oil are expected to be recovered over the forty-year life

    of the platform.

    BP is the nominated operator of the Clair field

    partnership (Table 1.1).

    Figure 1.2 Preliminary schedule for development of Clair Ridge

    Unit Owner Interest %1

    BP Exploration Operating Company Limited2 27.6

    Britoil plc2 1.0

    ConocoPhillips (U.K.) Limited 24.0

    Chevron North Sea Limited 19.4

    Clair UK Limited3 9.3

    Enterprise Oil Limited3 18.7

    1 Unit Interests are rounded to one decimal place.2 BP Exploration Operating Company Limited and Britoil plc

    are wholly owned subsidiaries of BP plc.3 Enterprise Oil Limited and Clair UK Limited are wholly

    owned subsidiaries of Royal Dutch Shell plc.

  • Clair Ridge DevelopmentEnvironmental Statement

    | 1 September 20104 | 1

    1.2 Scope and aims of the environmental statementThe aim of the EIA is to assess the potential

    environmental impacts that may arise from the proposed

    Clair Ridge Development and to identify measures that

    will be put in place to prevent or minimise these impacts.

    The EIA process is integral to the project, assessing

    potential impacts and setting design and operational

    challenges to ensure that the final impacts of the project

    are minimal. The process also provides for the potential

    concerns of stakeholders to be identified and addressed

    as far as possible at an early stage, and ensures that the

    planned activities comply with environmental legislative

    requirements and with BPs Environmental Policy.

    The ES is a report summarising the EIA process and

    outcomes. It also includes details of how the project

    decision-making was undertaken and how environmental

    criteria were incorporated into that process. The scope

    of the EIA was developed and agreed during the

    scoping consultation process (see Chapter 5). The ES is

    submitted to DECC to inform the decision on whether or

    not the project may proceed, based on the acceptability

    or otherwise of the residual levels of impact, and is

    subject to formal public consultation.

    The EIA process has addressed the following

    components of the Clair Ridge Development:

    Template installation and drilling prior to

    jacket installation

    Jackets and topsides installation and presence;

    New pipelines and subsea infrastructure installation

    and presence

    Hook-up and commissioning

    Operational phase activities including fluids processing

    and export, platform drilling, waste management and

    subsea activities

    Decommissioning

    The assessment has included both routine and abnormal

    events (such as production upsets) and considered the

    risk of accidental events with possible environmental

    implications.

    The following project components were not within the

    scope of the EIA and are therefore not addressed within

    this ES:

    Existing pipeline infrastructure, e.g. WOSPS and the

    Clair Phase 1 oil export line

    Clair Phase 1 topsides modifications required for the

    Clair Ridge tie-in to the existing export pipelines

    Any modifications at SVT that may be required

    as a result of receiving, storing and exporting

    Clair Ridge fluids

    Potential, future subsea tie-backs1

    Offsite fabrication of jackets, topsides, utility

    packages, pipes, etc. (BP implements an assurance

    process to verify the environmental management

    systems and processes adopted by project

    contractors, including those contracted to complete

    offsite fabrication)

    Full details of the methodology applied during the EIA

    process is described in Chapter 5. This ES reports the

    outcome of the process and includes the following:

    A non-technical summary of the whole ES

    Justification for the field development and the role

    of the EIA (Chapter 1)

    Description of the options considered for the

    Clair Ridge Development and how environmental

    considerations were integrated into the decision-

    making process (Chapter 2)

    Description of the selected concept (Chapter 3)

    Description of the environment in the vicinity of

    Clair Ridge and the key sensitivities of the nearest

    coastlines (Chapter 4)

    Methods used to identify and evaluate the

    environmental issues associated with the proposed

    field development (Chapter 5)

    1 However, calculations and modelling included in this ES for the operational phase of the development are based on the full production profile for which the Clair Ridge platforms has been designed, incorporating potential future subsea tiebacks. Further explanation is provided in Section 3.3.

  • 1 |

    Clair Ridge DevelopmentEnvironmental Statement

    1 |September 2010 5

    Detailed assessment of each issue, including the

    potential for any cumulative or transboundary

    impacts (Chapters 6 to 10)

    Environmental management and control measures

    that will be in place during the development,

    including waste management procedures

    (Chapters 11 and 12)

    Conclusions (Chapter 13)

    1.3 Regulatory context

    1.3.1 Requirement for an EIA

    The EIA reported in this ES has been carried out in

    accordance with the requirements of the Offshore

    Petroleum Production and Pipelines (Assessment of

    Environmental Effects) Regulations 1999 (as amended).

    These regulations require the undertaking of an

    environmental assessment and production of an ES for

    certain types of offshore oil and gas projects likely to

    have a significant effect on the environment. Approval

    of the ES is required before approval can be granted to

    the Field Development Plan under the Petroleum Act

    1998. An environmental assessment is mandatory for

    any development that is expected to produce more than

    500 tonnes (ca. 3.1 mbd) of oil per day and more than

    500,000 m3 (ca. 17.4 mmscf) gas per day. The proposed

    development will exceed these threshold quantities and

    therefore an EIA is mandatory for Clair Ridge.

    1.3.2 Key environmental legislationThe Clair Ridge project will be subject to the

    requirements of UK and EU legislation in addition to other

    international treaties and agreements such as the Oslo

    and Paris Commission (OSPAR). As the development

    lies outwith UK territorial waters (ie more than 12 nm

    from land), the majority of the activities undertaken will

    be governed under the applicable legislation regarding

    offshore oil and gas activities, rather than that governing

    inshore waters.

    The key environmental regulatory drivers applicable

    to the Clair Ridge Development, listed below, are

    summarised in Appendix A. In addition, key legislation

    and guidance relating to the main environmental issues

    associated with the development are presented in the

    relevant chapters of the ES (Chapters 6 to 11).

    Petroleum Act 1998;

    Coast Protection Act 1949;

    Petroleum Licensing (Production) (Seaward

    Areas) Regulations 2008;

    Food and Environment Protection Act 1985;

    Offshore Petroleum Activities (Oil Pollution

    Prevention and Control) Regulations 2005;

    Offshore Combustion Installations (Prevention

    and Control of Pollution) Regulations 2001;

    Offshore Chemical Regulations 2002;

    Offshore Petroleum Activities (Conservation of

    Habitats) Regulations 2001 (as amended);

    Offshore Marine Conservation (Natural Habitats

    &c.) Regulations 2007;

    Merchant Shipping (Prevention of Pollution by

    Garbage) Regulations 1998;

    Oil Pollution Preparedness, Response and

    Co-operation Convention Regulations 1998,

    Emergency Pollution Control

    Regulations 2002.

  • Clair Ridge DevelopmentEnvironmental Statement

    | 1 September 20106 | 1

    1.3.3 Evolving environmental legislation

    BP recognises that environmental legislation is subject

    to change as technology advances and understanding

    of the impacts of human activities on the environment

    develops. Therefore, an important factor throughout the

    EIA process has been the consideration of both known

    evolving legislation and other potential future regulation.

    A Future Legislation Review (Xodus Group, 2010a) was

    conducted to provide an overview of current and evolving

    UK environmental legislation that has implications for the

    design of the Clair Ridge Development and that should

    be considered as part of the detailed design process.

    Potential future legislative of relevance to the EIA are

    described in the appropriate ES chapter. For example,

    EU Emissions Trading Scheme (ETS) requirements are

    described in Chapter 9 Atmospheric Emissions.

    1.4 BP environmental policy and requirementsBP and its Partners are committed to conducting

    activities in compliance with all applicable legislation

    and in a manner which contributes to BPs stated goals

    of no accidents, no harm to people and no damage

    to the environment. In order to achieve these goals

    there is a hierarchy of common policies, commitments

    and expectations that identify policy and regulatory

    requirements and provide tools to assist in compliance

    and performance improvements.

    In addition to relevant UK and EU legislation and

    international standards, the Clair Ridge project is subject

    to the following BP environmental requirements:

    BP Group Defined Practice (GDP) on Environment

    (see Section 12.1) which defines BPs approach

    to achieving consistent, environmentally sound

    operations in new projects, including the requirement

    for environmental assessment of new developments

    such as Clair Ridge

    The North Sea Strategic Performance Unit (SPU)

    HSE policy (see over)

    Clair Ridge Environmental principles (see Section 12.1)

    as defined in the Clair Ridge Environmental Philosophy

    These requirements, together with applicable legislation,

    have been applied from the start of the Clair Ridge

    project, informing the concept selection and early

    design processes with the aim of eliminating or limiting

    environmental impact by design.

    During operations, the Clair Ridge Development will

    conform to the requirements of the Environmental

    Management System (EMS) established for the BP

    North Sea Strategic Performance Unit (SPU), which is

    accredited to ISO 14001 (see Section 12.2).

    Details of BPs environmental policy and management

    processes, and how they will be applied to the Clair

    Ridge Development and implemented during the

    operational phase, are provided in Chapter 12.

  • 1 |

    Clair Ridge DevelopmentEnvironmental Statement

    1 |September 2010 7

  • Clair Ridge DevelopmentEnvironmental Statement

    2 |September 2010 1

    2.1 Introduction

    The Environmental Impact Assessment (EIA) Directive

    (85/337/EEC) requires that where appropriate, an outline

    of the main alternatives studied by a developer and an

    indication of the main reasons for choice, taking into

    account the environmental effects be provided.

    DECC Guidance notes on the Offshore Petroleum

    Production and Pipelines (Assessment of Environmental

    Effects) Regulations 1999 (DECC, 2009) require that

    the Environmental Statement (ES) should describe

    the main alternatives to the proposed activity that have

    been considered. The advantages and disadvantages of

    each option should be clearly stated with the specific

    environmental implications indicated for each. The main

    reasons for the selection of the preferred option should

    be described, taking into account the environmental

    effects. Other factors influencing the choice of

    alternatives should be noted e.g. feasibility, technical

    constraints and cost effectiveness. If a formal option

    appraisal has been carried out it should be described

    and the relevant decision factors noted. Options such

    as alternative sites, timing, construction practices, plant

    and equipment, operating processes and pipeline routes

    should be considered where appropriate.

    2.1.1 The decision-making process

    From the earliest stages of concept assessment, the

    Clair Ridge project team introduced a holistic process

    of option analysis in order to facilitate and document

    decisions in a transparent and objective way.

    The strength of the process is ensured through having

    the right people involved which enables experienced and

    multi-disciplined input to the decision making process.

    Decision evaluation included analysis of five factors

    (Figure 2.1) to characterise the concept or technical

    options under consideration. During concept selection

    consideration was also given to capital expenditure

    (CAPEX) and operational expenditure (OPEX). This holistic

    approach ensured environmental considerations were

    on an equal footing with other factors such as safety and

    technical viability.

    Consideration of Alternatives2

    This chapter outlines the main options considered for the Clair Ridge Development at both the conceptual and Front End Engineering Design (FEED) stages of the project. It describes the evaluation and decision-making process that has been caried out. The decisions made have resulted in the removal or major reduction by design of several sources of potential environmental impact.

  • Clair Ridge DevelopmentEnvironmental Statement

    | 2 September 20102 | 2

    Describethe Issue

    Outline options/alternative

    Analyse options

    Decide

    Implementdecision

    Flexibility toClair Ridge development

    Flexibility toClair field development

    Safety

    Project deliverability

    Environment

    This process has been applied by the Clair Ridge project

    during concept selection, through FEED and will continue

    into detailed design after project sanction. The decisions

    taken to date are typically cross-discipline, high impact,

    and where transparency was considered essential, i.e.

    for DECC, Health and Safety Executive (HSE), partners,

    and external stakeholders.

    BP has used a variety of tools to support the

    decision-making process, including Best Practicable

    Environmental Option (BPEO) and Best Available

    Technology (BAT) studies, comparative assessment,

    and environmental issues identification (ENVID). The

    BPEO concept involves assessing the performance of

    alternative options against key objectives for various

    criteria, including technical feasibility and cost as well

    as environmental performance, in order to identify the

    option that performs best overall.

    2.2 Basis for Clair Ridge DevelopmentAs described in Chapter 1, the first phase of the Clair

    field development included the installation of an export

    pipeline system and the Clair Phase 1 platform. Clair

    Ridge, the second phase of the development, is targeting

    the elongated up-thrown part of the field to the northeast

    of Clair Phase 1 (see Figure 1.1).

    The overall size of the Clair field, the volume of the

    available hydrocarbon reserves at Clair Ridge and the

    requirement to use dry Xmas trees1 do not allow for

    the Clair Ridge area to be developed as a tie-back to the

    existing Clair Phase 1 platform. Therefore, a stand-alone

    installation is required in order to access and exploit the

    hydrocarbon reserves in the Ridge area of the Clair field.

    2.3 Concept selection (high level decisions)2.3.1 Concepts considered

    A number of potential processing and exporting facilities

    for the Clair Ridge fluids were considered during early

    project planning. The concept options were centred on

    commissioning a new platform (concrete tower/steel

    jacket), a jack-up installation or a Floating, Production,

    Storage and Offloading (FPSO) facility (Table 2.1).

    The facility concept options were screened in

    terms of engineering feasibility and practicability,

    safety, environment and cost. The options that were

    deemed impractical or had an unacceptable level of

    environmental risk were not carried forward for further

    detailed engineering consideration.

    NOTE: Flexibility to Clair Ridge Development: Options potential to adapt to the changes in fluids/conditions brought through production of the Ridge segments of the Clair reservoir.

    Flexibility to Clair field development: Options potential to adapt to different fluids/conditions brought by future tie-backs to Clair Ridge or different areas of the Clair reservoir.

    Figure 2.1 Decision making process

    1 Due to the nature of the Clair reservoir, a requirement for frequent well interventions is anticipated. It is thus deemed impractical to leave Xmas trees on the seabed (Aurora, 2001).

  • 2 |