Clair Ridge Development - Environmental Statement
Click here to load reader
-
Upload
gerry-macdonald -
Category
Documents
-
view
479 -
download
65
description
Transcript of Clair Ridge Development - Environmental Statement
-
Clair Ridge DevelopmentEnvironmental Statement
September 2010
-
Clair Ridge DevelopmentEnvironmental Statement
Information |September 2010 1
Standard Information Sheet
Project (Installation) Name Clair Ridge Development
DECC Reference number D/4091/2010
Type of Project Field development with two bridge-linked platforms,
wells and tie-in to existing export pipelines
Undertaker name BP Exploration Operating Company Ltd
Undertaker address Farburn Industrial Estate,
Dyce, Aberdeen, AB21 7PB
Licensees/Owners BP Exploration Operating Company Limited _ _ _ _ _ _ _ _ _ 27.6%
Britoil plc _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 1.0%
ConocoPhillips (U.K.) Limited _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 24.0%
Chevron North Sea Limited _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 19.4%
Clair UK Limited _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 9.3%
Enterprise Oil Limited _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 18.7%
Short description The project is the second stage of development of the Clair
oil field. It will involve the installation of two bridge-linked
platforms, one supporting drilling and production and the other
supporting accommodation and utilities, on the West Shetland
Continental Shelf in UKCS Block 206/8 (5.6 km northeast of
Clair Phase 1 platform which started production in 2005 and
93 km southeast of the UK/Faroe transboundary line). The Clair
Ridge oil export pipeline will tie into the existing Clair Phase 1
pipeline to Sullom Voe Terminal, Shetland and the gas export
pipeline will tie into the existing West of Shetland Pipeline
System. Of 36 wells to be drilled, several will be drilled from a
semi-submersible drilling rig before the platforms are installed.
The remaining production and water injection wells will be
drilled from the drilling and production platform. The reservoir
fluids will be fully processed on the platform and the produced
water re-injected into the reservoir.
Anticipated commencement of works First oil is targeted for second quarter of 2015.
Signicant environmental impacts identied None
Statement prepared by BP Exploration Operating Company Ltd
Designed and Printed by Tay-CAD Ltd
-
Clair Ridge DevelopmentEnvironmental Statement
Contents |September 2010 1
Contents
1 Introduction 1.1 Project background and purpose _ _ _ _ _ _ _ 1 | 1
1.2 Scope and aims of the environmental statement _ _ _ _ _ _ _ _ _ _ _ _ 1 | 4
1.3 Regulatory context _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 1 | 5
1.4 BP environmental policy and requirements _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 1 | 6
2 Consideration of Alternatives
2.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 2 | 1
2.2 Basis for Clair Ridge Development _ _ _ _ _ 2 | 2
2.3 Concept selection (high level decisions) _ _ 2 | 2
2.4 Second-level decisions _ _ _ _ _ _ _ _ _ _ _ _ _ _ 2 | 6
2.5 Decisions remaining to be made _ _ _ _ _ _ _ 2 | 13
3 The Development
3.1 Development overview _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 1
3.2 Reservoir characteristics _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 1
3.3 Fluid characteristics and expected production _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 3
3.4 Wells and drilling _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 6
3.5 Pipelines and subsea infrastructure _ _ _ _ _ 3 | 13
3.6 Jackets and topsides _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 15
3.7 Production _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 17
3.8 Commissioning _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 22
3.9 Decommissioning _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 3 | 22
4 The Environment
4.1 Overview _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 4 | 1
4.2 The physical environment _ _ _ _ _ _ _ _ _ _ _ _ 4 | 3
4.3 The biological environment _ _ _ _ _ _ _ _ _ _ _ 4 | 12
4.4 Commercial fisheries _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 4 | 27
4.5 Other sea users _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 4 | 32
4.6 Conservation interests _ _ _ _ _ _ _ _ _ _ _ _ _ _ 4 | 34
5 The Environmental Assessment Process
5.1 Overview _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 5 | 1
5.2 Environmental screening and categorisation _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 5 | 2
5.3 Scoping and consultation _ _ _ _ _ _ _ _ _ _ _ _ 5 | 2
5.4 Environmental issues identification (ENVID) _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 5 | 8
5.5 Assessment of residual impacts _ _ _ _ _ _ _ 5 | 14
5.6 EIA integration with overall environmental management _ _ _ _ _ _ _ _ _ _ 5 | 14
6 Physical Presence
6.1 Seabed impacts _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 6 | 1
6.2 Interactions with other sea users _ _ _ _ _ _ 6 | 7
7 Discharges to Sea
7.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 7 | 1
7.2 Regulatory control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 7 | 1
7.3 Drilling discharges _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 7 | 2
7.4 Installation, commissioning and operational discharges _ _ _ _ _ _ _ _ _ _ _ 7 | 12
8 Underwater Noise
8.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 8 | 1
8.2 Regulatory control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 8 | 2
8.3 Hearing and use of sound by species at Clair Ridge _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 8 | 2
8.4 Noise sources and potential impacts _ _ _ _ 8 | 5
8.5 Mitigation measures _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 8 | 14
8.6 Residual impacts _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 8 | 15
8.7 Cumulative and transboundary impacts _ _ 8 | 16
8.8 Assessing the likelihood of an offence _ _ _ 8 | 17
-
Clair Ridge DevelopmentEnvironmental Statement
| Contents September 20102
9 Atmospheric Emissions
9.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 9 | 1
9.2 Regulatory control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 9 | 3
9.3 Sources of potential impacts _ _ _ _ _ _ _ _ _ _ 9 | 4
9.4 Management and mitigation _ _ _ _ _ _ _ _ _ _ 9 | 9
9.5 Residual impacts _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 9 | 12
9.6 Cumulative and transboundary impacts _ _ 9 | 15
10 Risk of Oil and Chemical Spills
10.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 10 | 1
10.2 Regulatory control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 10 | 2
10.3 Oil spills _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 10 | 3
10.4 Oil spill response strategy _ _ _ _ _ _ _ _ _ _ 10 | 28
10.5 Cumulative and transboundary risk _ _ _ _ 10 | 31
10.6 Chemical spills _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 10 | 32
11 Waste Management
11.1 Introduction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 11 | 1
11.2 Regulatory control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 11 | 2
11.3 Waste management policy _ _ _ _ _ _ _ _ _ _ 11 | 3
11.4 Clair Ridge waste management strategy _ _ _ _ _ _ _ _ _ _ _ _ _ 11 | 3
12 Environmental Management
12.1 Clair Ridge environmental management and commitments _ _ _ _ _ _ 12 | 1
12.2 The BP environmental management process _ _ _ _ _ _ _ _ _ _ _ _ _ 12 | 4
12.3 Environmentally critical equipment (ECE) _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 12 | 5
12.4 Environmental monitoring _ _ _ _ _ _ _ _ _ _ _ 12 | 5
12.5 Environmental awareness and training _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 12 | 6
12.6 Interface with contractors _ _ _ _ _ _ _ _ _ _ _ 12 | 6
13 Conclusion
13.1 Approach _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 13 | 1
13.2 Potential environmental issues _ _ _ _ _ _ _ 13 | 1
13.3 Cumulative and transboundary impacts _ 13 | 3
13.4 Protected areas and species _ _ _ _ _ _ _ _ _ 13 | 4
13.5 Environmental management _ _ _ _ _ _ _ _ _ 13 | 4
13.6 Final remarks _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 13 | 4
14 References
Abbreviations and Glossaries
APPENDIX A Summary of environmental legislation
APPENDIX B
Claire Ridge forecast production data
APPENDIX C
Vessel usage
APPENDIX D
Map of environmental surveys
APPENDIX E Summary of informal consultations
APPENDIX F ENVID matrices
APPENDIX G
The DREAM model
APPENDIX H Underwater noise modelling methods
APPENDIX I Emissions quantification data
APPENDIX J Data for appropriate assessments
APPENDIX K Claire Ridge commitments register
-
Clair Ridge DevelopmentEnvironmental Statement
Non-Technical Summary |September 2010 1
Introduction
This Environmental Statement (ES) presents the findings of
the environmental impact assessment (EIA) conducted by
BP for the proposed Clair Ridge Development. The project
is the second stage of development of the Clair reservoir
and is located in the northeast Atlantic in UK Continental
Shelf (UKCS) Block 206/8, approximately 55 km west of
Shetland and 93 km southeast of the UK/Faroe median line
(Figure S.1).
Project background and purpose
The Clair reservoir is the largest known hydrocarbon
resource on the UKCS, occupying an area of some
220 km2. Due to its size and complexity it is being
developed in a series of phases.
The first phase of development included the installation of
the Clair Phase 1 platform and an export pipeline system
in the summer of 2004 (Figure S.1); first oil was achieved
in February 2005. The success of the Clair Phase 1
Development now paves the way for further investment
in the Clair field.
The proposed second phase of development, Clair Ridge,
aims to exploit the oil and gas reserves in the Ridge
section of the reservoir to the northeast of Clair Phase 1
(Figure S.1). The design of the Clair Ridge Development
has built on the environmental and design work
completed for the Clair Phase 1 project and takes
account of BPs operational experience of the
Clair Phase 1 facilities. The new development will
have a greater oil handling capacity than Clair Phase 1
and will be pre-equipped with facilities to support a
number of subsea developments in other parts of the
Clair field, should these be required in the future. Note
that any further phases of Clair development would be
the subject of additional environmental assessment
and approval from the Department of Energy and
Climate Change (DECC).
Non-Technical Summary
Figure S.1 Location of the Clair eld and the proposed Clair Ridge Development
-
Clair Ridge DevelopmentEnvironmental Statement
| Non-Technical Summary September 20102 | Non-Technical Summary
Environmental philosophy
BP is committed to conducting activities in compliance
with all applicable legislation and in a manner which contributes to BPs stated goals of no accidents, no harm to people and no damage to the environment. In order to achieve these goals there is a hierarchy of common policies, commitments and expectations that identify policy and regulatory requirements and provide tools to assist in compliance and performance improvements.
During operations, the Clair Ridge Development will conform to the requirements of the Environmental Management System (EMS) established for the BP North Sea Strategic Performance Unit (SPU), which is certified to ISO 14001.
Assessment of alternatives
Throughout concept selection, through initial engineering and going forward into detailed design the Clair Ridge project team is utilising a holistic process of option analysis in order to facilitate and document decisions in a transparent and objective way - utilising criteria such as environmental impact, safety, technical feasibility, cost, ability to meet project needs, and stakeholder concerns. This holistic approach ensures environmental considerations are on an equal footing with other factors such as safety and technical viability.
A number of processing and exporting concepts for the Clair Ridge fluids were considered during early project planning, resulting in selection of twin steel platforms with bridge link, with maximum production of 120,000 barrels of oil per day. Following selection of this concept, 2nd level options were appraised, using operational experience gained from Clair Phase 1. Appraisal included, but was not limited to, the oil export route, the power generation concept and the gas turbine configuration. Some decisions are still to be made, including the method of pipeline installation and the type of flotel to be used; the EIA is based upon the option that would represent the highest environmental impact for each receptor. For example, in considering seabed impacts it has been assumed that an anchored pipelay barge might be used and in considering noise generation and atmospheric impacts it has been assumed that a
dynamically positioned pipelay barge might be used.
Development concept and schedule
The proposed development consists of two installations, one for drilling and production facilities (DP platform) and the other for accommodation and utilities (QU platform), with a bridge-link connection between them. Oil will be exported to Sullom Voe Terminal (SVT) in Shetland via a new pipeline tying into the existing Clair Phase 1 pipeline. Similarly, gas export to SVT will be via a new pipeline tying into the West of Shetland Pipeline System (WOSPS).
In 2011, an eight slot drilling template will be installed and some wells will subsequently be pre-drilled (i.e. drilled from a mobile drilling rig prior to platform installation) and suspended for later tie-in. Export pipelines will be installed in 2012 and the platforms and subsea structures during 2013 and 2014. Following hook-up and commissioning, the current BP schedule is for first oil in 2015, although the timing of activities may change during project development. In total, over 104 million cubic metres of oil are expected to be recovered over the forty-year life of the platform.
Environmental Statement Remit
This ES has been prepared in accordance with applicable legislation and guidelines, including the Offshore Petroleum Production and Pipelines (Assessment of Environmental Effects) Regulations 1999 (as amended) which require evaluation of projects likely to have a significant effect on the offshore environment.
The aim of the EIA is to assess the potential environmental impacts that may arise from the proposed Clair Ridge Development and to identify measures that will be put in place during design and operations to prevent or minimise these impacts. The ES summarises the EIA process and outcomes.
The scope of the EIA was developed and agreed during a scoping consultation process. The EIA has addressed all aspects of this offshore development, from early drilling activities and installation and commissioning, through the operational phase to decommissioning.
-
Non-Technical Summary |
Clair Ridge DevelopmentEnvironmental Statement
Non-Technical Summary |September 2010 3
The Development
Reservoir and uid characteristics
Clair Ridge fluids and conditions are relatively favourable,
i.e. the oil is not at a high temperature or pressure and
does not contain hydrogen sulphide.
Wells and drilling
The development is anticipated to involve the drilling of
36 wells. Of these, 26 will be oil producing wells and 10
will be for water injection to maintain reservoir pressure
and enhance oil recovery. The producing wells are
provided with gas lift facilities.
Between three and seven wells (assumed to be six
for the purposes of the EIA) will be pre-drilled and
suspended for later tie-in by a semi-submersible drilling
rig via a steel seabed template in the two year period
prior to jacket installation. This will allow efficient
production ramp-up on initial platform commissioning.
The platform drilling programme will be continual after
the initial tie-in of the pre-drilled wells and is expected to
last approximately twelve years.
The wells will be drilled in a series of sections of
decreasing diameters. Of the 36 planned wells, it is
expected that approximately 50% will be drilled with
three sections, or strings, with hole diameters of 32,
17 and 12. Five-string wells may be required where
there is a large horizontal distance to the reservoir
target (maximum step-out approximately 6 km), or to
provide extra protection when drilling through the Lower
Cretaceous region of the formation. These wells will
have hole diameters of 32, 23, 17, 12 and 9.
Two further liner strings can be added if required. The
pre-drilled wells include a four-string well design involving
36, 26, 17, and 12 diameter holes.
Drilling uids (muds) and cuttings handling
Drilling muds generally consist of a weighting agent
such as barite suspended in water (water based mud or
WBM) or some type of oil (oil based mud or OBM). Other
chemicals may be added for specific functions depending
on the geological formations being drilled and on the
viscosity and specific characteristics required of the
drilling fluid. Different types of mud are used for different
parts of a well and final fluid selection for each section
will be based on technical requirements for each type of
well (producer or injector).
The top-hole sections of each well (the 36 and 26
sections for the pre-drilled wells and the 32 section
for the platform wells) will be drilled using a seawater
based solution and the inert cuttings generated from
these sections will be deposited directly on the seabed,
around the hole. A riser (pipe) will then be installed which
connects the well to the platform and all other cuttings
can be circulated back up to the drilling rig or platform.
Cleaning and separation systems will enable the recovery
of drilling fluids and partitioning of the drill cuttings for
appropriate disposal.
Well control equipment and well testing
The primary well control barrier is the use of
weighted drilling fluids which are sufficiently heavy to
counterbalance the formation pressure. The secondary
barrier will be the blow out preventer (BOP) system
which exists to prevent uncontrolled flow from the well
by positively closing the well-bore when required.
Testing of the platform-drilled wells will be necessary
for effective reservoir management and assessment
of reservoir performance. This involves the production
of a limited amount of fluid from the well into a test
separator, where metering equipment will monitor the
wells performance. The fluids will then pass into the
main process system and no flaring will be required.
The pre-drilled wells will be cleaned-up and tested
briefly from the drilling rig, with produced crude oil and
gas being flared; there is no plan to include an extended
well test.
-
Clair Ridge DevelopmentEnvironmental Statement
| Non-Technical Summary September 20104 | Non-Technical Summary
DP topsides facilities
The production process facilities are designed to collect
the produced fluids from the wells and deliver crude
oil, gas and water of sufficient quality to meet outlet
specifications. The main process systems, situated
on the DP platform, are illustrated in Figure S.3 and
include the separation system which removes gas and
water from the production fluid to obtain the required
oil product specification. The produced water system
removes residual oil to less than 30 milligrams per litre
(mg/l) from the water separated from the produced
fluids. Produced water can be directed overboard
should the water injection system be unavailable. The
are system provides a safe means of disposal of
hydrocarbon gases during emergency situations, start-up
and maintenance operations. A vapour recovery unit
captures any gases in the flare system during normal
operations and routes these back to the process, rather
than being flared. The hazardous and non-hazardous
drainage systems collect and treat contaminated water,
ensuring that prior to discharge it contains less than
40 mg/l of dispersed oil, in line with legal limits. The
oil export system cools the crude oil and increases
pressure to the specification required for delivery into the
oil export pipeline.
Figure S.2 Clair Ridge platforms
(view looking northeast)
Pipelines and subsea infrastructure
The oil and gas pipelines from the Clair Ridge DP
platform will tie into a subsea isolation valve (SSIV)
installed approximately 200 m from the platform. The
Clair Ridge oil will then flow to the Clair Phase 1 SSIV/
Wye assembly via a new 6.5 km oil export pipeline.
The DP platform will also be tied into the WOSPS via a
14.0 km gas export pipeline. The tie-in point will be at
the existing Clair Phase 1 WOSPS Tee. A new tie-in skid
adjacent to this Tee will house isolation valves and allow
gas import from WOSPS to Clair Ridge when required.
The export pipelines will be laid on top of the seabed.
The concrete-coating of the oil pipeline will provide it
with sufficient weight and stability, but the gas export
pipeline will be protected and stabilised with rock along
its entire length. The hard seabed in this area means
that pipeline trenching is not possible. The pipeline tie-in
sections will be covered with concrete mattresses for
stability and protection.
During pipeline commissioning, the pipeline will be
pressure tested using water treated with biocide
and oxygen scavenger (to ensure that the pipeline
is protected from corrosion) and dye (to enable the
detection of any leaks).
Platforms and processing facilities
The twin platform design consists of two jackets
supporting the DP and QU topsides (Figure S.2).
The jackets will be transported onto location and installed
using barges and heavy lift vessels and then piled
into the seabed. The topsides will be transported and
positioned onto the jackets using heavy lift ships and
a heavy lift vessel. A flotel will be used to house the
workforce throughout the hook-up and commissioning
phase of the platforms.
-
Non-Technical Summary |
Clair Ridge DevelopmentEnvironmental Statement
Non-Technical Summary |September 2010 5
Figure S.3 Simplied process ow diagram
QU topsides facilities
The QU topsides facilities house the utility systems.
These include the main power generation system, i.e.
four dual-fuel gas turbines (one of which is on standby)
with waste heat recovery units (WHRU) which recover
heat from the exhausts to heat the process fluids. Also
included is the LoSalTM unit, a membrane separation
package producing desalinated seawater for injection
into the reservoir (via the DP platform) for improved
oil recovery. Other utility systems include the closed
circuit heating medium, closed circuit cooling medium,
seawater lift, nitrogen generation and instrument air
system. These utilities are distributed across the bridge
link to the DP platform. The living quarters are also
situated on the QU platform, with the fresh-water maker
and sewage system.
Commissioning
The commissioning strategy seeks to minimise offshore
commissioning activities by maximising the amount of
onshore commissioning of process, utility and subsea
systems. This will maximise production ramp-up and
minimise flaring.
Decommissioning
A detailed decommissioning plan will be established
prior to decommissioning to ensure there is minimal
impact on the marine environment and other sea
users. BP will evaluate options for facilities and pipeline
decommissioning and will undertake decommissioning
activities in compliance with regulatory requirements
in force at the time of decommissioning. All technically
feasible options will be considered. The present
regulations for decommissioning require the complete
removal of the Clair Ridge platforms and template to
shore for reuse, recycling or final disposal on land.
-
Clair Ridge DevelopmentEnvironmental Statement
| Non-Technical Summary September 20106 | Non-Technical Summary
Overview of the environment
An understanding of the environment in the vicinity
of the Clair Ridge Development (located on the outer
West Shetland Continental Shelf in the northeast
Atlantic (Figure S.1) in water depths of 140 m), draws
upon regional and site-specific environmental surveys
and on research that has been carried out in the area.
This includes the extensive data collation and review
undertaken as part of the Clair Phase 1 Development
EIA, updated where appropriate. The focus is on the
offshore areas around the platforms and the tie-in
pipeline routes. Consideration has also been given to the
coastal characteristics throughout the area that would be
vulnerable in the unlikely event of a large oil spill.
Water current patterns in this area are often complex
with various non-tidal components of current flow
interacting with relatively weak tidal flow. Water column
stratification occurs during the summer months when
there is a distinct boundary between warmer surface
waters and cooler bottom waters.
Strong winds are characteristic of the northeast
Atlantic, particularly during the winter months, and calm
conditions are rarely recorded. Southerly and westerly
winds tend to predominate for much of the year from
July through to March. In contrast there is a greater
evenness of wind distribution during the spring months
(April to June).
The seabed at the proposed platform locations is
comprised of very gravelly sand with cobbles and
numerous boulders overlain in places by thin ribbons of
sand with occasional megaripples and scattered cobbles
and boulders as shown in Figure S.4, taken in 2009.
Key environmental sensitivities
Based on previous experience, studies and consultation
conducted for both the Clair Phase 1 and Clair Ridge
projects, it has been possible to identify the key
environmental sensitivities to the proposed development.
These are summarised for the offshore environment
in Table S.1. Seasonal ecological sensitivity offshore is
highest between February and July due to high seabird
vulnerability to surface pollution at these times.
The combination of the shelf edge environment and the
influence of the Gulf Stream to the west of Shetland
results in a diversity of habitats and a particularly rich
number of cetaceans. The distribution of cetacean
species is related to oceanographic features such as sea
temperature, salinity, water depth and sea floor relief and
prey distribution and abundance. To the west of Shetland,
different species show a tendency towards shelf, slope
or deep water habitats.
Figure S.4 Seabed in the vicinity of
the Clair Ridge Development
-
Non-Technical Summary |
Clair Ridge DevelopmentEnvironmental Statement
Non-Technical Summary |September 2010 7
Table S.1 Offshore environmental sensitivities
Plankton Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
A peak in phytoplankton (plant) productivity in late spring is followed by lower, yet constant, productivity until autumn. Zooplankton (animal) productivity follows a similar pattern with a one or two month delay. Zooplankton provides an important source of food for many fish species. Plankton communities are not generally subjected to pressures from human activities.
Seabed animals Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
Surveys showed the seabed to consist of gravelly sands with pebbles and cobbles supporting sparce surface living animal life (epifauna). It is unlikely that any particular seasonal sensitivities exist in the benthic communities present.
Fish Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
The development lies within spawning (March to May) and nursery areas for Norway pout and nursery areas for blue whiting and mackerel, as well as a mackerel migration route. Nonetheless sensitivity is generally low throughout the year since identified spawning and nursery areas extend over much wider areas (throughout UK and European waters).
Seabirds Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
Seabirds offshore are particularly vulnerable to oil spill. Fulmar, northern gannet, herring gull, great black-backed gull, kittiwake, common guillemot, razorbill and puffin are present in the west of Shetland area all year round, with many other species present at certain times of the year. In the vicinity of the Clair Ridge Development, densities of some species can be moderate to high during spring and summer. The European storm petrel (listed under Annex I of the EU Birds Directive) is present in the area in high densities during September and occurs in internationally important numbers. Overall sensitivity to surface oil pollution is greatest during February and March and between May and June.
Cetaceans Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
Large baleen whales migrate through the Faroe-Shetland Channel to summer feeding grounds in the north and winter breeding areas in the south. Long-finned pilot whales, Atlantic white-sided and killer whales also inhabit deep waters of the channel, while minke whales and several dolphin species have been observed over the shelf. Sightings tend to peak during the summer months, although this may be a consequence of seasonality in survey effort.
Conservation Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
There are no designated offshore sites in the vicinity of the Clair Ridge Development. Additionally, there are no potentially protected habitats such as sandbanks, reef structures or pockmarks nearby.
Fisheries Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
Different areas of the continental shelf west of Shetland are important for fisheries throughout the year. Demersal species are generally fished all year round. Pelagic fisheries exhibit some seasonality and exact seasons may change year to year. High-value mackerel are landed in winter months, herring are landed exclusively in July, and saithe are predominantly landed in the first half of the year. The level of demersal fishing effort in the area is moderate and the level of pelagic fishing effort is low, in comparison to the rest of the UK.
Low Moderate HighGeneral sensitivity
With regards to the coastal environment, the ecological
sensitivity of the Shetland coastline ranges from low
to moderately high with numerous specific areas with
an elevated level of local sensitivity, usually related to
bird and marine mammal breeding and nesting areas.
The most sensitive period is during the summer months
when most species are breeding and rearing young.
The winter months are also important due to the
presence of overwintering seabird and wildfowl
populations. Spring appears to be the least sensitive time
of the year.
Other potential sensitivities to oil spills in coastal areas
include fishing, mariculture, tourism and amenity value of
the coastal landscape.
-
Clair Ridge DevelopmentEnvironmental Statement
| Non-Technical Summary September 20108 | Non-Technical Summary
Conservation interests
The proposed development area does not lie within or
close to any designated offshore conservation sites
under Annex I of the EU Habitats Directive. An area of
potential Annex I habitat (stony reef) lies along the shelf
break downslope from the Clair Ridge Development.
However, seabed surveys indicate that the proposed
development area does not support stony reef habitat
according to criteria developed by JNCC.
The JNCC is currently working to identify important
hotspots for seabirds in the offshore area, including
several areas around Shetland, with a view to designating
marine Special Protected Areas (SPAs). However, as yet
no offshore SPAs have been identified for feeding or
overwintering.
A number of marine species in UK waters have been
identified for protection under Annex II of the European
Habitats Directive. The harbour porpoise is the only listed
species likely to occur with any frequency in the vicinity
of the proposed development. Although the JNCC is
seeking to identify areas suitable for designation for
harbour porpoise, the species is widely distributed in
UK waters, and the area to the west of Shetland is not
considered unique. European storm petrels, listed on
Annex I of the Birds Directive, are widely distributed over
the whole shelf break west of Shetland between May
and November.
The Shetland coastline supports internationally and
nationally important populations of breeding seabirds. The
coastline also has numerous boggy areas, which support
approximately half of the British breeding population
of red-throated diver. The west coast of Orkney is
characterised by high cliffs and supports internationally
important breeding seabirds.
Shetland and Orkney also support internationally important
breeding populations of common seal and Shetland
supports one of the densest otter populations in Europe.
Assessment of potential impactsThe main aim of the Clair Ridge project environmental
strategy has been to design out, or reduce, issues
believed to impact on the environment or on users of
the environment.
Project design and operational planning has succeeded
in the removal or reduction of many of the key
environmental issues. Using data and understanding
relating to the proposed design, the sensitivity of the
environment and consultation feedback, the core task of
the EIA process has been to:
Assess potential residual issues from the project, both from routine operations and possible accidents
Define mitigation and management measures to be addressed during the detailed design phase and
subsequent operations
The following sections of the non technical summary
present the findings of the EIA for the residual
environmental issues remaining following design and
operational planning. The issues are addressed under the
following categories:
1 Physical Presence 3 Underwater Noise
2 Discharges to Sea 4 Atmospheric Emissions
Operational issues
5 Risk of Oil and Chemical Spills
Accidental events
The potential for cumulative or transboundary impacts
is also addressed.
-
Non-Technical Summary |
Clair Ridge DevelopmentEnvironmental Statement
Non-Technical Summary |September 2010 9
1 Physical presence
The anchoring of the drilling rig, flotel and other vessels,
and the installation and presence of the drilling template,
jackets, pipelines and other subsea structures, have the
potential to affect the seabed and associated animals.
In addition, offshore activities associated with all stages
of the development, and the physical presence of
structures, could interact with other users operating
within the same area of the marine environment.
Seabed impacts
Mechanisms for direct impact include disturbance of
sediments and damage to seabed species; as well
as localised loss or change of habitat through the
introduction of novel substrata. Indirect impacts may
be caused by the re-suspension and re-settlement
of sediments.
The total area of seabed directly impacted, including
all anticipated anchor placements, rock dumping and
mattressing, is estimated to be approximately 0.3 km2.
This represents approximately 0.002% of the total West
Shetland Continental Shelf area. Considering the small
area likely to be impacted, the ability of some species
to move out of the area and the absence of rare or
protected species, the residual impact of direct physical
injury or habitat loss to seabed fauna will be minor. The
pipeline and other seabed structures will provide new
stable hard substrata, equivalent to natural rock outcrops,
in the already mixed substratum environment, which are
expected to be colonised by any epifaunal animals (those
living on the surface of the seabed) present in the area.
Any anchor mounds that are generated will be eroded by
the relatively strong bottom currents. Recovery of seabed
affected by transient operations such as anchoring is
expected to be rapid (less than five years) via sediment
mobility and faunal re-colonisation.
Any re-suspension of sediments will be localised and
restricted to the installation phase, i.e. temporary,
therefore the majority of species present will not be
adversely affected and impacts are likely to be negligible.
Interactions with other sea users
The marine environment within which the Clair Ridge
Development will be located is utilised by a number
of other sea users, primarily the fishing and shipping
industries. The increase in vessel traffic during installation
and the physical presence of the structures potentially
increases the risk of collisions. In addition, the proposed
activities, vessels and structures will exclude fishermen
and shipping from the Clair Ridge location and potentially
increases the risk of gear and catch being damaged
through interaction with subsea structures.
Increased vessel traffic
The increase in the number of vessels in the area during
drilling, and installation and commissioning, is of limited
duration. Standard communication and notification
measures will be in place to ensure that all vessels
operating the area are aware of the activities. Since a low
number of vessels frequent waters within a 10 nautical
mile radius of the Clair Ridge Development, and given
the fact that the presence of the existing Clair Phase 1
platform means that shipping and fishing interests are
aware of field-specific vessel movements in the area,
the temporarily increased vessel presence around the
Clair Ridge Development is expected to have little or no
significant residual impact.
-
Clair Ridge DevelopmentEnvironmental Statement
| Non-Technical Summary September 201010 | Non-Technical Summary
Fishing interference
Snagging risks cannot be eliminated entirely and a
number of mitigation measures will be in place to reduce
them significantly, including the use of overtrawlable
subsea infrastructure, consultation and notices to
mariners. The measures BP will adopt are standard
across the industry and have previously assisted in
reducing the impact of oil and gas associated activities to
other sea users.
A specialist fishing study commissioned for the EIA
noted higher vessel sightings occurring along the 200 m
contour to the north and lower vessel sightings occurring
towards the southwest of the Clair field.
The presence of long-term exclusion zones around the
drilling rig and subsequently the platforms, will prevent
fishing vessels from operating in 0.009% of potential
fishing grounds in the West Shetland Continental Shelf.
Pipelines can interfere with demersal fishing activities
due to the increased risk of snagging and damage. The
fishing study indicated that pipelines, which can act as
fish aggregation devices, may be preferentially targetted
for fishing and concluded that the risks inherent in fishing
over and along fishing friendly untrenched pipelines are
within acceptable limits.
Anchor mounds may pose a risk to fishing vessels.
However, due to the small numbers of anchor
placements and the temporary nature of the anchor
mounds (as discussed above), it is likely that the threat to
fishing in the Clair Ridge area is minor.
2 Discharges to sea
BP aims to reduce the impact of discharges on the
environment, with emphasis placed upon pollution
prevention and impact minimisation at source. Key
design features of the Clair Ridge Development, such
as a re-injection target of 98% of produced water and
its associated chemicals, reduce residual levels of
discharges to sea.
The residual discharges from the Clair Ridge
Development and the management and mitigation
measures employed in order to adhere to legislation and
achieve BPs goals are discussed below.
Drilling discharges
Discharge to sea of OBM cuttings is prohibited and these
will be re-injected or, if cuttings re-injection (CRI) is not
available, shipped to shore for onshore processing.
Cuttings from the tophole sections of the wells, drilled
with a seawater-based fluid, will be deposited on the
seabed adjacent to the well. Where WBM are used for
the lower sections of the wells, WBM cuttings will also
be re-injected when CRI facilities are available, otherwise
they will be discharged to sea through a caisson. As the
precise quantity of WBM cuttings which can be
re-injected is unknown, assessment assumed that WBM
is used for all 23 and 17 well sections and no CRI
is available for WBM. The worst-case quantity of WBM
cuttings that would therefore be discharged ranges from
238 tonnes for a pre-drilled well to 1,172 tonnes for a
5-string, long platform well.
Due to rapid dilution soon after release, and settlement
of particles to the seabed, the impacts in the water
column from these discharges will be negligible.
Cuttings dispersion modelling predicted that, for a
5-string platform well, deposition would occur on the
seabed in a thin oval-shaped area lying predominantly to
the northeast of the drilling centre. Any adverse risk as
defined by the environmental impact factor (EIF) will be
limited to a central area up to 300 m from the discharge
location in the direction of the predominant current and
approximately 50 m in other directions.
-
Non-Technical Summary |
Clair Ridge DevelopmentEnvironmental Statement
Non-Technical Summary |September 2010 11
These impacts will be largely attributable to grain size
alteration and thickness of deposition.
The environmental impact factor (EIF) is an estimate
of the area of seabed within which there exists a
possibility of injury to 5 % of the most sensitive
species.
The environmental impact of the drilling discharges is
expected to be loss of benthic community near the
wellhead due to complete burial, and limited changes
in the communities further from the discharge location.
Available information for the Clair Ridge site suggests
that no species were particularly sensitive to increased
suspended solids or limited deposition and that
recoverability of the species was high or very high.
Further modelling considered the discharges from
all platform drilled wells (30), to investigate potential
cumulative impacts. As a worst case the discharges
were assumed to occur immediately after each other
with no time interval incorporated between modelling
of individual well discharges to allow for recovery of
the sediment. In this case the area of adverse risk, as
defined by the EIF, extends to approximately 3.5 km from
the discharge location in the direction of the dominant
current and 250 m in other directions.
In reality, the 30 wells are planned to be drilled over a
12-year period. This will extend the duration of impacts,
but reduce the scale of impact at any point in time, and
reduce the likely recovery time following cessation of the
drilling programme. A combination of sediment transport
and redistribution, and recolonisation and bioturbation
of the sediment, is expected to return the sediment to
its natural state within a few years of completion of the
drilling programme.
Commissioning discharges
The Clair Ridge pipelines will be flooded with seawater
containing chemicals (eg biocides, oxygen scavengers
and scale inhibitors) and hydrotested. Before start up,
the pipelines will be dewatered. Although there will be
discharges associated with each of these operations,
they will be short-term and have only a localised effect.
The risk to the environment was assessed as negligible.
Produced water
Following treatment of the produced water to ensure it
contains an oil-in-water concentration of less than
30 mg/l, a target of 98 % will be re-injected into the
reservoir. The re-injection of produced water will limit the
quantities of oil discharged and will also ensure minimal
discharge of other chemicals added during processing.
The impacts of any produced water discharges to sea
during periods of produced water re-injection down-time
were assessed as being negligible.
Discharges from LoSalTM unit
Use of the LoSalTM unit results in the discharge of
high salinity water containing added chemicals such
as biocide and anti-scalant. Predictive modelling
indicates that the plume sinks rapidly to the seabed
and that its concentration decreases to less than
1 % above background salinity levels within 35 m of
the discharge point.
The risk to the environment from the LoSalTM discharge
is predominantly from the batch discharge of a biocide
which will be dosed on a weekly basis. However, this
potential impact is very localised to within approximately
1 km of the discharge point and short-term, lasting for
approximately 24 hours after dosing.
-
Clair Ridge DevelopmentEnvironmental Statement
| Non-Technical Summary September 201012 | Non-Technical Summary
3 Underwater noise
This EIA has utilised up-to-date scientific information and
applied the most recent JNCC guidelines in an attempt to
assess the significance of any potential impacts from the
Clair Ridge Development.
Sources of noise generation from activities associated
with the development which have the potential to impact
upon marine species in the vicinity of the development
include pile driving, drilling, vessel activity and offshore
pipelay activities. The potential impacts of most noise
sources on marine mammals were assessed as being
negligible or minor.
A specialist modelling study was commissioned to
inform the assessment of the impacts from the noisiest
operations, the piling of the drilling template and jackets.
The study indicated that the entire range in which injury
may be caused will be contained within the marine
mammal mitigation zone, i.e. within the area where
measures can be taken that seek to ensure no marine
mammals are in the area of impact prior to pile driving
being initiated.
Considering the very short time period during which pile
driving will actually occur, and the nomadic behaviour of
cetaceans (which imply that they will actively avoid loud
noise sources), it is unlikely that any will be exposed to
sound which would cause significant behavioural effects.
Assessing the likelihood of an offence
The EIA also includes an assessment of whether or
not the proposed operations will cause disturbance of
European Protected Species (EPS) under the Habitat
Regulations and Offshore Marine Regulations.
The nature of the piling activity and the proposed
mitigation measures mean there will be a negligible risk
of injury or disturbance offence as a result of the Clair
Ridge activities. BP therefore considers that application
for an EPS licence is not required.
4 Atmospheric emissions
The use of energy optimisation and BAT studies for
power generation, and key design decisions regarding
flaring, have minimised the atmospheric emissions
associated with the development. The ES details
the expected residual levels of emissions from the
installation and operation of the Clair Ridge Development
and models the dispersion of emissions from the major
operational sources, i.e. the gas turbines and
safety-related flaring.
To reduce the total level of flaring from Clair Ridge
operations, the development includes a vapour recovery
unit. This means that vapours that would otherwise be
flared can be recovered and processed.
The naturally low driving force of the Clair reservoir
means that the Clair Ridge Development starts from a
position of considerable disadvantage when comparing
energy required per barrel of oil production against many
other BP assets. Notwithstanding, energy efficiency
and minimisation of atmospheric emissions has been
evaluated as part of the decision-making process when
assessing options around the main energy consumption
items e.g. power generation, gas compression, artificial
lift, water injection and oil export.
Local impacts
Throughout the installation, commissioning, and
operation of the Clair Ridge Development there will be
additional levels of NOX, SO2, and VOCs released into the
environment. However, the effects from these pollutants
will be very localised and, due to the dispersive nature of
the offshore environment and the remote location, they
will have a negligible effect on the nearest receptors
on Shetland.
Contribution to global greenhouse gases
The average annual CO2 equivalent emissions from
the Clair Ridge Development, including both direct and
indirect greenhouse gases have been estimated to be
approximately 377 kte which represent approximately
0.85% of the total offshore UKCS CO2 emissions.
-
Non-Technical Summary |
Clair Ridge DevelopmentEnvironmental Statement
Non-Technical Summary |September 2010 13
5 Risk of oil and chemical spills
The ES describes the measures that will be put in place
during the Clair Ridge Development to prevent spills, and
proposed contingency measures that will be employed
to ensure an effective response in the unlikely event
of a spill.
It is BPs aim to cause zero damage to the environment,
minimising the risk of spills using measures relating to
plant, people and processes. Therefore in light of the
Deepwater Horizon incident in the Gulf of Mexico, the
ES incorporates emerging, relevant information from the
incident while recognising that the Clair Ridge drilling
programme consists of development drilling in 140 m of
water into a reservoir which does not contain fluids at
high pressure or temperature and in which more than 30
wells have been drilled since the 1970s.
Oil spills
Analysis of industry spill frequency indicates that the
most probable spills from the Clair Ridge Development
are small spills of < 1 tonne and focus has been given to
prevention of these spills through design, specification
and implementation of agreed operational procedures.
Larger blowout and pipeline spills that could reach the
coastline are considered to be remote or extremely
remote events, i.e. low probability.
The consequences of a significant release of
hydrocarbons from the Clair Ridge Development will vary
depending on factors such as wind speed and direction
and sea state, as well as the time of year and the length
of coastline affected. For example, after the breeding
season ends in June, moulting auks (guillemot, razorbill
and puffin) disperse from their coastal colonies into
offshore waters and kittiwake, gannet and fulmar are
present in significant numbers, making high numbers of
birds particularly vulnerable to oil pollution.
As the probability of spills of this magnitude occurring
is considered remote or extremely remote, the overall
risk of an oil spill from the Clair Ridge Development
adversely impacting Shetland is very low. To address
the small residual risk of spill which remains, even
with comprehensive prevention measures in place, BP
implements a range of response/mitigation measures, as
detailed in the spill response strategies.
Spill response strategy
Procedures and protocols have been implemented for the
Clair Phase 1 oil export pipeline to prevent and minimise
the risk of an oil spill from the pipeline, and respond in
the unlikely event of a spill. These will be updated, as
appropriate, to incorporate the Clair Ridge oil export
pipeline tie-in.
The BP Onshore Oil Spill Plan was implemented for the
Clair Phase 1 Development in addition to immediate
offshore response. As part of this plan, BP have
contracted OSR to have strategically located mobile
response packages, and trained response personnel,
that can be engaged to combat oil spills approaching
inshore areas of Shetland. This plan will be reviewed
and modified to incorporate any changes required for the
inclusion of the Clair Ridge Development.
Detailed and fully tested oil spill response strategies,
appropriate to local environmental sensitivities will be
developed and finalised for both drilling and production
prior to the commencement of operations. These will
be documented in the Oil Pollution Emergency Plans
(OPEPs) for the drilling rig and the Clair Ridge platforms.
In light of the Deepwater Horizon incident in the Gulf of
Mexico. The OPEPs will consider, and where appropriate
incorporate information gained from the Deepwater
Horizon incident in the Gulf of Mexico. The OPEPs will be
submitted for approval by the regulator in sufficient time
to allow full consideration of the proposals.
-
Clair Ridge DevelopmentEnvironmental Statement
| Non-Technical Summary September 201014 | Non-Technical Summary
6 Cumulative and transboundary issues
Cumulative effects are those that impact on the
environment outside the local scale and those that add to
existing or reasonably foreseeable future impacts. Clair
Phase 1 was the third oil and gas field to be developed
in the area to the west of Shetland, following Foinaven
and Schiehallion. Approval has also been granted for
the combined subsea development of the Laggan and
Tormore gas fields.
Transboundary environmental impacts originate in one
country but have an effect on the environment in another
country. Clair Ridge is located approximately 93 km (58
miles) from the UK/Faroes boundary and
236 km (147 miles) from the UK/Norwegian boundary
(Figure S.1).
The main aim of the Clair Ridge environmental philosophy
has been to design out, or reduce, issues believed to
present significant risk to the environment or users of
the environment. Project planning and operational design
has removed or substantially reduced key issues such as
the discharge to sea of drill cuttings, produced water and
associated chemicals and certain atmospheric emissions.
Modelling of residual discharges to sea and atmospheric
emissions, and consideration of interference of the
development with other sea users indicated that the
potential for cumulative or transboundary environmental
impacts attributable to these is limited.
As indicated by historical data, the likelihood of one major
spill occuring is remote or extremely remote, limiting the
potential cumulative oil spill impact from Clair Ridge and
other existing installations. Detailed contingency plans
are in place for each installation, outlining the response
measures to be implemented in the event of any spill.
Oil spill modelling undertaken - which assumed no
response measures were implemented - indicates
some probability that, in the event of a worst case
spill, oil could move across international boundaries,
particularly into Norwegian waters. The assessment of
spill likelihood, based on historical UKCS and international
incident data, demonstrates that the likelihood of a spill
large enough to lead to such a transboundary impact
is remote extremely remote, i.e. low probability.
Therefore BP believes that consultation under the
Espoo convention is not required as a result of the Clair
Ridge Development, the Espoo convention requiring
notification and consultation only on projects likely to
have a significant adverse environmental impact across
boundaries.
The risk of oil spill having transboundary impact,
particularly from the North Sea operations, is recognised
by the UK Government and other governments around
the North Sea. Agreements are in existence for dealing
with international oil spill incidents with states bordering
the UK. In the event of a major spill which is predicted
to drift into Norwegian waters the NORBRIT plan will be
activated. The NORBRIT plan is a joint UK/Norway oil
spill contingency plan operating within the framework of
the 2006 National Contingency Plans; the plan is oriented
towards major spills resulting from, for example,
blow-outs. It becomes operational when agreement
to the request for its implementation is reached.
Responsibility for implementing joint action rests with
the Action Co-ordinating Authority (ACA) of the country
on whose side of the median line a spill originated. The
UKs ACA is the Counter Pollution Branch of the Maritime
and Coastguard Agency (MCA).
-
Non-Technical Summary |
Clair Ridge DevelopmentEnvironmental Statement
Non-Technical Summary |September 2010 15
The way forward
Environmental considerations have played, and will
continue to play, an important role in the decision-
making process throughout the Clair Ridge project.
Throughout the project, considerable efforts have been
made to remove or significantly reduce issues that could
lead to possible impacts on the environment. Where
this has not been possible, detailed attention has been
given to defining residual issues and seeking ways of
minimising any potential impacts.
Several key decisions led to removal or major reduction
in activities considered likely to have significant impacts
onto the environment, in particular:
Oil/Gas pipeline oil and gas exported to shore via short tie-ins to existing pipelines, thus reducing the
environmental impact that would result at landfall and
to the seabed from new export pipelines.
Routine flaring the flaring philosophy for the Clair Ridge Development is not to flare gas routinely
during normal operations, and to have a closed flare
system with flare gas recovery in order to reduce
atmospheric emissions such as CO2, NOx, SOx and
unburnt hydrocarbons.
CRI OBM drill cuttings and drilling slops will routinely be re-injected into the formation. WBM drill cuttings
and drilling slops (other than those of the top hole
sections drilled riserless) will be considered for CRI.
Each well will be reviewed on a case-by-case basis to
assess if re-injecting such materials would significantly
reduce the availability of CRI wells for re-injection of
OBM cuttings. CRI will reduce any potential impacts
on seabed and fauna.
PWRI and LoSalTM produced water and its associated chemicals will be re-injected into the
reservoir, thus reducing potential impacts on the
water column. Low salinity water injection using
LoSalTM will reduce the risk of reservoir souring and
sulphate scaling. This will reduce the overall chemical
requirement, reducing potential impacts on the water
column.
Power generation the selection of a centralised electrical power generation system allows for recovery
of the waste heat from Gas Turbines as useful heat to
meet the process requirements, removing the need
for separate fired heaters or large electrical heaters.
Key Residual Issues
Overall it is considered that, following application of
management and mitigation measures identified in
this ES, the Clair Ridge Development will not cause
significant environmental impacts.
However, there are aspects of the project that will need
to be managed sensitively in order to minimise potential
environmental effects. These include the following key
residual issues:
Underwater noise pile driving is seen as the Clair Ridge Development activity generating the greatest
underwater noise levels. BP will implement a number
of measures to mitigate noise impacts based on the
principles of the JNCC guideline for piling activities
to address any potential for injury and non-trivial
disturbance. As the most commonly sighted marine
mammals species in the development vicinity are
considered less susceptible to low frequency sounds,
and that pile driving noise will be emitted over a
short period of time, significant, residual injury or
disturbance impacts occurring as a result of the piling
activities at Clair Ridge are considered unlikely.
Risk of oil spills the focus of the Clair Ridge project has been on spill prevention. The highlighted
prevention methods will considerably reduce the risk
of oil spill. However, a residual risk of oil spill remains
and therefore an oil spill response strategy has been
developed. This strategy will be taken on into detailed
OPEPs which will include further consultation with the
statutory authorities and appraisal of existing response
arrangements.
-
Clair Ridge DevelopmentEnvironmental Statement
1 |September 2010 1
Introduction1
1.1 Project background and purpose1.1.1 History of the Clair eld
The Clair field, discovered in 1977 and extending over an
area of about 220 km2, is the largest known hydrocarbon
resource on the UKCS. It is a challenging fractured
sandstone reservoir of Devonian to Carboniferous age,
which is being developed in a series of phases.
Ten appraisal wells were drilled into the reservoir (by four
different operator groups) from field discovery through
to 1990. The information obtained demonstrated that
the reservoir covered a large geographical area but failed
to confirm the presence of economically recoverable
reserves. Between 1990 and 1995 the operators with
an interest in the Clair field drilled a further five appraisal
wells and commissioned a 3D seismic survey. Although
not sufficient to establish commercial viability, this
activity did demonstrate that one geological segment
of the reservoir known as the Core was the focal area
for any possible development. In 1996 an extended well
test demonstrated that the Core area was capable
of sustained production performance. A further two
appraisal wells drilled in 1997 into other areas of the
This Environmental Statement (ES) presents the findings of the environmental impact assessment (EIA) conducted
by BP for the proposed Clair Ridge Development. The project is the second stage of development of the Clair oil
reservoir and is located in the northeast Atlantic in UK Continental Shelf (UKCS) Block 206/8, approximately 55 km
west of Shetland and 93 km southeast of the UK/Faroe median line, in water depths of 140 m (Figure 1.1).
The proposed development consists of two installations, one for drilling and process facilities (DP platform) and the
other for accommodation and utilities (QU platform), with a bridge-link connection between them. Oil will be exported
to Sullom Voe Terminal (SVT) in Shetland via a new 22 diameter 6.5 km pipeline tying into the existing Clair Phase 1
pipeline. Similarly, gas export to SVT will be via a new 6 14 km pipeline tying into the existing West of Shetland Pipeline
System (WOSPS).
This chapter explains the background and purpose of the proposed development and describes the scope and aims of the EIA process carried out. The underlying regulatory and BP environmental requirements are also outlined.
reservoir supported initiation of development concept
studies for a first phase of development.
Initial development (Clair Phase 1) of the Clair field
centred on the Core, Graben and Horst reservoir areas
in the central part of the reservoir (Figure 1.1). An EIA
was completed for Clair Phase 1 and the resultant ES
was submitted and approved in 2002 (BP, 2001; DTI
reference number: D/1228/2001).
The Clair Phase 1 platform and export pipelines were
installed offshore during the summer of 2004 and the
field achieved first oil in February 2005. Oil from Clair
Phase 1 is exported to SVT via a 105 km pipeline, whilst
gas is exported through a 10 km spur line into the
WOSPS (Figure 1.1). Oil production from Phase 1 built up
to a plateau of around 50 thousand barrels per day (mbd
ca 7,950 m3 per day) in 2007. By the end of 2010 the Clair
Phase 1 Development will have produced 70 million stock
tank barrels (mmstb) of oil (approximately 11.5 million
m3) from the Lower Clair Group reservoir. The success of
the Clair Phase 1 Development now paves the way for
further investment in the Clair field.
-
Clair Ridge DevelopmentEnvironmental Statement
| 1 September 20102 | 1
1.1.2 The Clair Ridge Development
The second phase of the development, Clair Ridge
(originally named Clair Phase 2), commenced with a
programme of appraisal drilling involving three wells
drilled between 2005 and 2007. These wells, together
with an ocean bottom cable (OBC) seismic survey
acquired in 2006, have given sufficient confidence to
proceed with the Clair Ridge project. This aims to exploit
the oil and gas reserves in the Ridge section of the
reservoir (the elongated up-thrown part of the field
to the northeast of Clair Phase 1; Figure 1.1).
Figure 1.1 Location of the Clair eld and the proposed Clair Ridge Development
-
1 |
Clair Ridge DevelopmentEnvironmental Statement
1 |September 2010 3
Table 1.1 Ownership of the Clair eld
The design of the Clair Ridge Development has built
on the environmental and design work completed for
the Clair Phase 1 project and takes account of BPs
operational experience of the Clair Phase 1 facilities.
The Clair Ridge facility will have 36 well slots, compared
to the 28 of Clair Phase 1; a higher process capacity
(ca 19,000 m3 or 120 mbd oil handling capacity compared
to ca 11,000 m3 or 67 mbd) and will be pre-equipped with
facilities to support a number of subsea developments
in other parts of the Greater Clair field, should these
be required in the future. Any further activities and
development related to possible further phases of
Clair development would be the subject of additional
environmental impact assessment and submission
of statutory environmental documentation to the
Department of Energy and Climate Change (DECC).
Concept selection for the Clair Ridge Development
occurred during 2008 and 2009. In 2011, an eight slot
template will be installed and a number of wells are
expected to be pre-drilled (i.e. drilled before installation
of the DP platform), cleaned, completed and suspended.
The subsea pipelines will be installed in 2012. This will
be followed by installation of the platforms and subsea
structures during 2013 and 2014. Following hook-up
and commissioning (HUC), the current BP schedule
is to achieve first oil in 2015 (Figure 1.2), although the
proposed timing of activities may change during project
development. In total, over 104 million m3 (638 mmstb)
of oil are expected to be recovered over the forty-year life
of the platform.
BP is the nominated operator of the Clair field
partnership (Table 1.1).
Figure 1.2 Preliminary schedule for development of Clair Ridge
Unit Owner Interest %1
BP Exploration Operating Company Limited2 27.6
Britoil plc2 1.0
ConocoPhillips (U.K.) Limited 24.0
Chevron North Sea Limited 19.4
Clair UK Limited3 9.3
Enterprise Oil Limited3 18.7
1 Unit Interests are rounded to one decimal place.2 BP Exploration Operating Company Limited and Britoil plc
are wholly owned subsidiaries of BP plc.3 Enterprise Oil Limited and Clair UK Limited are wholly
owned subsidiaries of Royal Dutch Shell plc.
-
Clair Ridge DevelopmentEnvironmental Statement
| 1 September 20104 | 1
1.2 Scope and aims of the environmental statementThe aim of the EIA is to assess the potential
environmental impacts that may arise from the proposed
Clair Ridge Development and to identify measures that
will be put in place to prevent or minimise these impacts.
The EIA process is integral to the project, assessing
potential impacts and setting design and operational
challenges to ensure that the final impacts of the project
are minimal. The process also provides for the potential
concerns of stakeholders to be identified and addressed
as far as possible at an early stage, and ensures that the
planned activities comply with environmental legislative
requirements and with BPs Environmental Policy.
The ES is a report summarising the EIA process and
outcomes. It also includes details of how the project
decision-making was undertaken and how environmental
criteria were incorporated into that process. The scope
of the EIA was developed and agreed during the
scoping consultation process (see Chapter 5). The ES is
submitted to DECC to inform the decision on whether or
not the project may proceed, based on the acceptability
or otherwise of the residual levels of impact, and is
subject to formal public consultation.
The EIA process has addressed the following
components of the Clair Ridge Development:
Template installation and drilling prior to
jacket installation
Jackets and topsides installation and presence;
New pipelines and subsea infrastructure installation
and presence
Hook-up and commissioning
Operational phase activities including fluids processing
and export, platform drilling, waste management and
subsea activities
Decommissioning
The assessment has included both routine and abnormal
events (such as production upsets) and considered the
risk of accidental events with possible environmental
implications.
The following project components were not within the
scope of the EIA and are therefore not addressed within
this ES:
Existing pipeline infrastructure, e.g. WOSPS and the
Clair Phase 1 oil export line
Clair Phase 1 topsides modifications required for the
Clair Ridge tie-in to the existing export pipelines
Any modifications at SVT that may be required
as a result of receiving, storing and exporting
Clair Ridge fluids
Potential, future subsea tie-backs1
Offsite fabrication of jackets, topsides, utility
packages, pipes, etc. (BP implements an assurance
process to verify the environmental management
systems and processes adopted by project
contractors, including those contracted to complete
offsite fabrication)
Full details of the methodology applied during the EIA
process is described in Chapter 5. This ES reports the
outcome of the process and includes the following:
A non-technical summary of the whole ES
Justification for the field development and the role
of the EIA (Chapter 1)
Description of the options considered for the
Clair Ridge Development and how environmental
considerations were integrated into the decision-
making process (Chapter 2)
Description of the selected concept (Chapter 3)
Description of the environment in the vicinity of
Clair Ridge and the key sensitivities of the nearest
coastlines (Chapter 4)
Methods used to identify and evaluate the
environmental issues associated with the proposed
field development (Chapter 5)
1 However, calculations and modelling included in this ES for the operational phase of the development are based on the full production profile for which the Clair Ridge platforms has been designed, incorporating potential future subsea tiebacks. Further explanation is provided in Section 3.3.
-
1 |
Clair Ridge DevelopmentEnvironmental Statement
1 |September 2010 5
Detailed assessment of each issue, including the
potential for any cumulative or transboundary
impacts (Chapters 6 to 10)
Environmental management and control measures
that will be in place during the development,
including waste management procedures
(Chapters 11 and 12)
Conclusions (Chapter 13)
1.3 Regulatory context
1.3.1 Requirement for an EIA
The EIA reported in this ES has been carried out in
accordance with the requirements of the Offshore
Petroleum Production and Pipelines (Assessment of
Environmental Effects) Regulations 1999 (as amended).
These regulations require the undertaking of an
environmental assessment and production of an ES for
certain types of offshore oil and gas projects likely to
have a significant effect on the environment. Approval
of the ES is required before approval can be granted to
the Field Development Plan under the Petroleum Act
1998. An environmental assessment is mandatory for
any development that is expected to produce more than
500 tonnes (ca. 3.1 mbd) of oil per day and more than
500,000 m3 (ca. 17.4 mmscf) gas per day. The proposed
development will exceed these threshold quantities and
therefore an EIA is mandatory for Clair Ridge.
1.3.2 Key environmental legislationThe Clair Ridge project will be subject to the
requirements of UK and EU legislation in addition to other
international treaties and agreements such as the Oslo
and Paris Commission (OSPAR). As the development
lies outwith UK territorial waters (ie more than 12 nm
from land), the majority of the activities undertaken will
be governed under the applicable legislation regarding
offshore oil and gas activities, rather than that governing
inshore waters.
The key environmental regulatory drivers applicable
to the Clair Ridge Development, listed below, are
summarised in Appendix A. In addition, key legislation
and guidance relating to the main environmental issues
associated with the development are presented in the
relevant chapters of the ES (Chapters 6 to 11).
Petroleum Act 1998;
Coast Protection Act 1949;
Petroleum Licensing (Production) (Seaward
Areas) Regulations 2008;
Food and Environment Protection Act 1985;
Offshore Petroleum Activities (Oil Pollution
Prevention and Control) Regulations 2005;
Offshore Combustion Installations (Prevention
and Control of Pollution) Regulations 2001;
Offshore Chemical Regulations 2002;
Offshore Petroleum Activities (Conservation of
Habitats) Regulations 2001 (as amended);
Offshore Marine Conservation (Natural Habitats
&c.) Regulations 2007;
Merchant Shipping (Prevention of Pollution by
Garbage) Regulations 1998;
Oil Pollution Preparedness, Response and
Co-operation Convention Regulations 1998,
Emergency Pollution Control
Regulations 2002.
-
Clair Ridge DevelopmentEnvironmental Statement
| 1 September 20106 | 1
1.3.3 Evolving environmental legislation
BP recognises that environmental legislation is subject
to change as technology advances and understanding
of the impacts of human activities on the environment
develops. Therefore, an important factor throughout the
EIA process has been the consideration of both known
evolving legislation and other potential future regulation.
A Future Legislation Review (Xodus Group, 2010a) was
conducted to provide an overview of current and evolving
UK environmental legislation that has implications for the
design of the Clair Ridge Development and that should
be considered as part of the detailed design process.
Potential future legislative of relevance to the EIA are
described in the appropriate ES chapter. For example,
EU Emissions Trading Scheme (ETS) requirements are
described in Chapter 9 Atmospheric Emissions.
1.4 BP environmental policy and requirementsBP and its Partners are committed to conducting
activities in compliance with all applicable legislation
and in a manner which contributes to BPs stated goals
of no accidents, no harm to people and no damage
to the environment. In order to achieve these goals
there is a hierarchy of common policies, commitments
and expectations that identify policy and regulatory
requirements and provide tools to assist in compliance
and performance improvements.
In addition to relevant UK and EU legislation and
international standards, the Clair Ridge project is subject
to the following BP environmental requirements:
BP Group Defined Practice (GDP) on Environment
(see Section 12.1) which defines BPs approach
to achieving consistent, environmentally sound
operations in new projects, including the requirement
for environmental assessment of new developments
such as Clair Ridge
The North Sea Strategic Performance Unit (SPU)
HSE policy (see over)
Clair Ridge Environmental principles (see Section 12.1)
as defined in the Clair Ridge Environmental Philosophy
These requirements, together with applicable legislation,
have been applied from the start of the Clair Ridge
project, informing the concept selection and early
design processes with the aim of eliminating or limiting
environmental impact by design.
During operations, the Clair Ridge Development will
conform to the requirements of the Environmental
Management System (EMS) established for the BP
North Sea Strategic Performance Unit (SPU), which is
accredited to ISO 14001 (see Section 12.2).
Details of BPs environmental policy and management
processes, and how they will be applied to the Clair
Ridge Development and implemented during the
operational phase, are provided in Chapter 12.
-
1 |
Clair Ridge DevelopmentEnvironmental Statement
1 |September 2010 7
-
Clair Ridge DevelopmentEnvironmental Statement
2 |September 2010 1
2.1 Introduction
The Environmental Impact Assessment (EIA) Directive
(85/337/EEC) requires that where appropriate, an outline
of the main alternatives studied by a developer and an
indication of the main reasons for choice, taking into
account the environmental effects be provided.
DECC Guidance notes on the Offshore Petroleum
Production and Pipelines (Assessment of Environmental
Effects) Regulations 1999 (DECC, 2009) require that
the Environmental Statement (ES) should describe
the main alternatives to the proposed activity that have
been considered. The advantages and disadvantages of
each option should be clearly stated with the specific
environmental implications indicated for each. The main
reasons for the selection of the preferred option should
be described, taking into account the environmental
effects. Other factors influencing the choice of
alternatives should be noted e.g. feasibility, technical
constraints and cost effectiveness. If a formal option
appraisal has been carried out it should be described
and the relevant decision factors noted. Options such
as alternative sites, timing, construction practices, plant
and equipment, operating processes and pipeline routes
should be considered where appropriate.
2.1.1 The decision-making process
From the earliest stages of concept assessment, the
Clair Ridge project team introduced a holistic process
of option analysis in order to facilitate and document
decisions in a transparent and objective way.
The strength of the process is ensured through having
the right people involved which enables experienced and
multi-disciplined input to the decision making process.
Decision evaluation included analysis of five factors
(Figure 2.1) to characterise the concept or technical
options under consideration. During concept selection
consideration was also given to capital expenditure
(CAPEX) and operational expenditure (OPEX). This holistic
approach ensured environmental considerations were
on an equal footing with other factors such as safety and
technical viability.
Consideration of Alternatives2
This chapter outlines the main options considered for the Clair Ridge Development at both the conceptual and Front End Engineering Design (FEED) stages of the project. It describes the evaluation and decision-making process that has been caried out. The decisions made have resulted in the removal or major reduction by design of several sources of potential environmental impact.
-
Clair Ridge DevelopmentEnvironmental Statement
| 2 September 20102 | 2
Describethe Issue
Outline options/alternative
Analyse options
Decide
Implementdecision
Flexibility toClair Ridge development
Flexibility toClair field development
Safety
Project deliverability
Environment
This process has been applied by the Clair Ridge project
during concept selection, through FEED and will continue
into detailed design after project sanction. The decisions
taken to date are typically cross-discipline, high impact,
and where transparency was considered essential, i.e.
for DECC, Health and Safety Executive (HSE), partners,
and external stakeholders.
BP has used a variety of tools to support the
decision-making process, including Best Practicable
Environmental Option (BPEO) and Best Available
Technology (BAT) studies, comparative assessment,
and environmental issues identification (ENVID). The
BPEO concept involves assessing the performance of
alternative options against key objectives for various
criteria, including technical feasibility and cost as well
as environmental performance, in order to identify the
option that performs best overall.
2.2 Basis for Clair Ridge DevelopmentAs described in Chapter 1, the first phase of the Clair
field development included the installation of an export
pipeline system and the Clair Phase 1 platform. Clair
Ridge, the second phase of the development, is targeting
the elongated up-thrown part of the field to the northeast
of Clair Phase 1 (see Figure 1.1).
The overall size of the Clair field, the volume of the
available hydrocarbon reserves at Clair Ridge and the
requirement to use dry Xmas trees1 do not allow for
the Clair Ridge area to be developed as a tie-back to the
existing Clair Phase 1 platform. Therefore, a stand-alone
installation is required in order to access and exploit the
hydrocarbon reserves in the Ridge area of the Clair field.
2.3 Concept selection (high level decisions)2.3.1 Concepts considered
A number of potential processing and exporting facilities
for the Clair Ridge fluids were considered during early
project planning. The concept options were centred on
commissioning a new platform (concrete tower/steel
jacket), a jack-up installation or a Floating, Production,
Storage and Offloading (FPSO) facility (Table 2.1).
The facility concept options were screened in
terms of engineering feasibility and practicability,
safety, environment and cost. The options that were
deemed impractical or had an unacceptable level of
environmental risk were not carried forward for further
detailed engineering consideration.
NOTE: Flexibility to Clair Ridge Development: Options potential to adapt to the changes in fluids/conditions brought through production of the Ridge segments of the Clair reservoir.
Flexibility to Clair field development: Options potential to adapt to different fluids/conditions brought by future tie-backs to Clair Ridge or different areas of the Clair reservoir.
Figure 2.1 Decision making process
1 Due to the nature of the Clair reservoir, a requirement for frequent well interventions is anticipated. It is thus deemed impractical to leave Xmas trees on the seabed (Aurora, 2001).
-
2 |