City of Vancouver General Section 01005 Triangle Park ...

140
City of Vancouver General Section 01005 Triangle Park Instructions Page PS10074 1 1 GENERAL 1.1 Description of Work .1 The principal works to be undertaken under this contract include, but are not limited to: .1 Site Preparation .1 Excavation and relocation of existing fill materials. .2 Protection of adjacent existing works and reinstatement of any damaged existing works to its original condition. .3 Re-grading as required. .4 Compaction of existing ground surfaces as required. .5 Off-site disposal of surplus existing fill. .6 Supply and placement of sub-surface drainage system. .2 Soft Landscape .1 Supply and installation of trees, shrubs, groundcover and sod lawn inclusive of growing medium and mulch. .2 Supply and installation of automatic irrigation system. .3 Hard Landscape .1 Supply and installation of granite sett paving, at grade granite edging, granite curb edging, compacted crushed granite and associated steel edger at pavillion post bases. .2 Supply and installation of curved Cast-in-place concrete seat walls with custom wood and metal top. .3 Supply and installation of Cast-in-place concrete retaining wall and its associated Cast-in-place concrete banding at both ends. .4 Architectural Features .1 Supply and installation of steel pavillion. .5 Maintenance .1 Maintenance of soft landscaping immediately after planting, all park elements including but not limited to: steel pavillion, site furnishings, paving, walls, lighting, sub-surface drainage system, and irrigation. Removal of snow and ice, litter and garbage. Maintenance to last a period of 1 year after substantial completion. .6 Electrical .1 Supply and installation of all lighting and its associated works necessary for a fully functional lighting system for the steel pavillion and custom wood/metal benches.

Transcript of City of Vancouver General Section 01005 Triangle Park ...

Page 1: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver General Section 01005 Triangle Park Instructions Page PS10074

1

1 GENERAL 1.1 Description of Work

.1 The principal works to be undertaken under this contract include, but are not limited to:

.1 Site Preparation .1 Excavation and relocation of existing fill materials. .2 Protection of adjacent existing works and reinstatement of

any damaged existing works to its original condition. .3 Re-grading as required. .4 Compaction of existing ground surfaces as required. .5 Off-site disposal of surplus existing fill. .6 Supply and placement of sub-surface drainage system.

.2 Soft Landscape

.1 Supply and installation of trees, shrubs, groundcover and sod lawn inclusive of growing medium and mulch.

.2 Supply and installation of automatic irrigation system. .3 Hard Landscape

.1 Supply and installation of granite sett paving, at grade granite edging, granite curb edging, compacted crushed granite and associated steel edger at pavillion post bases.

.2 Supply and installation of curved Cast-in-place concrete seat walls with custom wood and metal top.

.3 Supply and installation of Cast-in-place concrete retaining wall and its associated Cast-in-place concrete banding at both ends.

.4 Architectural Features

.1 Supply and installation of steel pavillion. .5 Maintenance

.1 Maintenance of soft landscaping immediately after planting, all park elements including but not limited to: steel pavillion, site furnishings, paving, walls, lighting, sub-surface drainage system, and irrigation. Removal of snow and ice, litter and garbage. Maintenance to last a period of 1 year after substantial completion.

.6 Electrical

.1 Supply and installation of all lighting and its associated works necessary for a fully functional lighting system for the steel pavillion and custom wood/metal benches.

Page 2: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver General Section 01005 Triangle Park Instructions Page PS10074

2

1.2 Measurement and Payment

.1 Measurement and Payment for work of this section shall be undertaken in accordance with Section 01006 Measurement and Payment.

2 PRODUCTS

.1 Not applicable to this section

3 EXECUTION 3.1 Documents Required

.1 The Contractor shall maintain a minimum of one copy of the following

documentation at job site at all times that work is in progress. The Contractor shall make such documentation available to the Engineer upon request:

.1 Contract drawings;

.2 Specifications;

.3 Addenda;

.4 Change Orders;

.5 Other modifications to Contract;

.6 Field test reports;

.7 Copy of approved work schedule;

.2 As the work progresses, the Contractor shall maintain accurate records

to show all deviations from the Contract Drawings. Such records shall be made available to the Engineer upon request.

3.2 Schedule

.1 The following documentation shall be provided to the Engineer within seven (7) days of Contract Award:

.1 WCB Notice of Construction Project; .2 Insurance documentation as specified on the tender form; .3 Bonds as specified on the tender form;

Page 3: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver General Section 01005 Triangle Park Instructions Page PS10074

3

.4 Work Schedule, in bar chart form. The Engineer will issue the Notice to Proceed to the Contractor once the Contract documentation is in order.

.2 Interim reviews of work progress, based on the work schedule, will be

conducted weekly by the Engineer. The Contractor shall update the Work Schedule in conjunction with and to the approval of the Engineer.

3.3 Contractor's Use of Site

.1 The Contractor’s use of the site shall be limited to immediate areas of work and such additional adjacent areas assigned by the Engineer for office, storage, equipment, stock piles, sanitary facilities, etc.

.2 Contractor’s are advised that work under separate contracts may be in progress or initiated during execution of work envisaged by this contract. Contractor shall cooperate with and coordinate work of this contract with other site work and shall execute work in such a manner as to avoid unduly restricting adjacent work.

3.4 Codes and Standards

.1 Perform work in accordance with the most recent edition of the National Building Code of Canada (NBC) and any other code of provincial or local application provided that, in any case of conflict or discrepancy, the more stringent requirements shall apply.

.2 Meet or exceed requirements of contract documents, specified standards, codes and referenced documents.

3.5 Environmental Constraints

.1 Refer to section 01561 Environmental Protection.

3.6 Project Meetings

.1 The Engineer will arrange project meetings and assume responsibility for setting times and recording and distributing minutes.

3.7 Setting Out of Work

.1 The Contractor shall set grades and lay out work in detail from control points, benchmarks, and monuments established by Contract Documents.

.2 All grades and elevations in the contract shall be referenced to City of Vancouver Datum.

Page 4: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver General Section 01005 Triangle Park Instructions Page PS10074

4

.3 Assume full responsibility for and execute complete layout of work to locations, lines and elevations indicated.

.4 Supply stakes and other devices required for layout of work.

.5 Use survey equipment acceptable to the Engineer.

3.8 Existing Services

.1 Where unknown services are encountered, immediately advise the Engineer and confirm findings in writing. Await instructions by the Engineer before proceeding with work in the vicinity of such encountered services.

3.9 Additional Drawings

.1 The Engineer may furnish additional drawings to the Contractor to assist in the proper execution of the work. These drawings will be issued for clarification only and shall have the same meaning and intent as if they were included with plans referred to in Contract documents.

3.10 Reference Information

.1 Complete reports containing results of soil contamination and groundwater investigations are available for review from the City of Vancouver.

3.11 Relics and Antiquities

.1 Relics and antiquities and items of historical or scientific interest such as cornerstones and contents, commemorative plaques, inscribed tablets, and similar objects found on site shall remain the property of the Owner. Protect such articles and request direction from the Engineer.

.2 Give immediate notice to the Engineer if evidence of archaeological

finds are encountered during construction, and await written instructions before proceeding with work in this area.

3.12 Familiarization with Site

Page 5: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver General Section 01005 Triangle Park Instructions Page PS10074

5

.1 Before submitting tender, visit site and become familiar with all conditions likely to affect the work. Discuss with the Engineer, methods of access and temporary power, water, sanitary facilities and restrictions applicable to the work and provide and pay for all services.

3.13 Temporary Facilities

.1 Remove any temporary services or facilities after completion of the work and make good any damage to conditions previously existing or to match new work as acceptable to the Engineer.

.2 Where it is necessary to remove security fences, perimeter fences, barriers or other structures to gain access to the site, these will be replaced, with the cost borne by the Contractor, to the condition found before removal.

3.14 Signs

.1 No signs will be permitted on site unless approved by the Engineer. All signs regarding safety or site instructions shall be in English or readily recognizable international symbols.

3.15 System of Measurement

.1 The metric system of measurement (SI) will be employed on this contract.

3.16 Inspection

.1 The Contractor shall notify the Engineer of working hours.

.2 The Engineer will inspect all work by the Contractor unless the Engineer notifies the Contractor in writing otherwise. The Contractor shall facilitate inspections by the Engineer.

.3 Where the Engineer’s inspection of the Contractor’s work involves verification of position, line or grade, the Contractor shall provide appropriate survey equipment and supplies as well as an assistant as requested by the Engineer.

.4 Provide adequate lighting for nighttime inspections.

3.17 Site Security

Page 6: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver General Section 01005 Triangle Park Instructions Page PS10074

6

.1 The Contractor shall assume responsibility for construction personnel and vehicles requiring access to the site.

3.18 Monuments

.1 Clearly mark and protect all monuments whether or not shown on the drawings.

3.19 Safety Requirements

.1 Observe and enforce construction safety measures required by National Building Code of Canada, Workers' Compensation Board of BC, and all applicable municipal statutes and authorities having jurisdiction.

.2 In event of conflict between any provisions of above authorities the most stringent provision will apply.

3.20 Permits and Notifications

.1 The Contractor shall, at his own expense, procure all permits, certificates and licenses required for the construction of the work and shall comply with all federal, provincial and local laws, regulations and ordinances affecting the execution of the Work, save insofar as the Contract Documents specifically provide otherwise.

END OF SECTION

Page 7: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Measurement Section 01006 Triangle Park and Payment Page PS10074

1

1 GENERAL 1.1 Scope

.1 This Section describes the methods of measurement and basis of payment that will apply to this contract.

1.2 Measurement for Payment

.1 Section 01005 - General Requirements .1 Measurement for Payment for work of this section will not be made.

.2 Section 02223 – Excavation and Placement of Granular Materials

.1 Measurement for payment for excavation will be made of the volume, in cubic meters, of material removed as determined by survey.

.2 Separate measurement for payment for dewatering of excavated materials prior to transport to an approved off-site landfill will not be made.

.3 Separate measurement for payment for off-site disposal of excavated materials will not be made

.4 Separate measurement for payment for on-site stockpiling of excavated materials, classified by the Engineer as suitable for reuse, will not be made.

.5 Measurement for payment for placement and compaction of excavated materials, classified by the Engineer as suitable for reuse and incorporation into final works will be made of the volume, as determined by survey, or material incorporated into the work and accepted by the Engineer.

.6 Measurement for payment for 19mm minus crushed gravel base, drain rock, and granular pipe bedding will not be made.

.3 Section 02511 – Crushed Granite Granular Paving

.1 Measurement for payment for Crushed Granite Granular Paving will be made of the plan area, in square meters, of Crushed Granite Granular Paving installed and accepted by the Engineer.

.4 Section 02517 - Miscellaneous Stone Work

.1 Measurement for Payment for supply and installation of Granite edgers will be made of the plan area, in square meters, of Granite edgers installed and accepted by the Engineer.

.2 Measurement for payment for supply and installation of Granite Setts Paving will be made of the plan area, in square meters, of Granite Setts Paving installed and accepted by the Engineer.

.3 Measurement for Payment for Granite Curbs will be made of the plan area, in square meters, of Granite Curbs installed and accepted by the Engineer. Only those portions of granite curb installed, accepted and remaining in place as permanent work will be measured.

.5 Section 02720 – Subsurface Drainage Systems

Page 8: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Measurement Section 01006 Triangle Park and Payment Page PS10074

2

.1 Measurement for payment for supply and installation of 100mm Sub-drain will be made of the length of 100mm Sub-drain installed measured in the horizontal plane along the axis of the services.

6. Section 02800 – Design Build Automatic Spray Irrigation System

.1 Measurement for payment for Design Build Automatic Spray Irrigation System will not be made.

7. Section 02870 – Site Furnishings

.1 Measurement for payment for supply and installation of Ipe wood and steel bench assembly will not be made.

8. Section 02920 – Growing Medium Preparation and Placement .1 Measurement for payment for supply and installation of Growing Medium

preparation and placement will be made of the volume, as determined by survey, of growing medium supplied, installed and accepted by the engineer.

9. Section 02938 – Sod Lawns

.1 Measurement for payment for sod lawns will be made of the surface area of sod supplied, installed and accepted by the Engineer.

10. Section 02950 – Planting Trees, Shrubs and Ground Cover

.1 Measurement for payment for supply and planting of trees will be by count of the number of each type of tree supplied and planted and accepted by the Engineer.

.2 Measurement for payment for supply and planting of #1 pot plants will be by count of the number of each type of #1 pot plants supplied and planted and accepted by the Engineer.

.3 Measurement for payment for 3.5” pot plants will be by count of the number of each type of 3.5” pot plants supplied and planted and accepted by the Engineer.

11. Section 02970 – Landscape Maintenance

.1 Measurement for payment for landscape maintenance will not be made.

12. Section 03100 – Concrete Formwork .1 Measurement for payment for concrete formwork will not be made.

13. Section 03200 – Concrete Reinforcement

.1 Measurement for payment for supply and installation of concrete reinforcement will not be made.

14. Section 03300 – Cast-In-Place Concrete

.1 Measurement for payment for Cast-in-place concrete will be made of the volume in cubic metres of concrete incorporated into the work and accepted by the Engineer. Payment volume will be calculated from neat lines indicated on the contract drawings or authorized in writing by the Engineer. Concrete placed beyond dimensions noted on the Contract Drawings will not be measured for payment. Deductions will not be made for volume of concrete displaced by inserts.

Page 9: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Measurement Section 01006 Triangle Park and Payment Page PS10074

3

.2 Measure for payment for the supply and construction of the Cast-in-place concrete retaining wall and its associated Cast-in-place concrete band on West side of park will not be made.

.3 Measure for payment for the supply and construction of the Cast-in-place

concrete curved topped bench bases will not be made.

15. Section 03340 – Sandblast Concrete .1 Independent measurement for payment for sandblast surface treatment of

concrete will not be made.

16. Section 03345 – Concrete Finishes .1 Independent measurement for payment for specified concrete finishes will

not be made.

17. Section 05900 – Metal Finish .1 Measurement for Payment for work associated with the supply,

fabrication, delivery and installation of the Triangle Park Pavillion will not be made.

18. Section 16000 – Electrical

.1 Measurement for Payment for Electrical Conduit in Trench will be made of the Length along centreline of duct through junction boxes, with no deductions for lengths junction boxes, over the surface after work has been completed.

.2 Measurement for Payment for Light fixture will be made by Field count for each light fixture/drivers supplied, installed operational and accepted by the Engineer.

.3 Measurement for Payment for wiring and commissioning will be made by Field inspection including inspection of test results and accepted by the Engineer.

1.3 Payment

.1 Section 01005 – General Instructions .1 Payment for mobilization and demobilization will be made on the basis of

the lump sum price bid for this item within the Schedule of Quantities and Unit Prices.

.2 60% of the lump sum price bid for mobilization and demobilization will be paid to the Contractor at the time that the Contractor has mobilized and commenced with the Work, and the remaining 40% of this amount shall be paid to the Contractor after the Contractor has demobilized after substantial completion of the Work.

.2 Section 02223 – Excavation and Placement of Granular Materials

.1 Payment for excavation undertaken will be made on the basis of the unit rates bid for this item within the Schedule of Quantities and Unit Prices and in accordance with the following paragraphs. The unit rate bid shall apply irrespective of final measured excavation volume:

.2 For those materials classified by the Engineer as suitable for incorporation into final works, the unit rate bid shall be inclusive of:

Page 10: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Measurement Section 01006 Triangle Park and Payment Page PS10074

4

.1 Excavation; .2 Temporary on-site (directly on-site) stockpiling at a location approved by

the Engineer and; .3 Any other items necessary to complete the work.

.3 For those materials classified by the Engineer as being unsuitable for incorporation into final works, the unit rate bid shall be inclusive of:

.1 Excavation;

.2 Dewatering prior to transport off-site; .3 Transportation to and disposal of excavated material;

.4 Any other items necessary to complete the work. .4 Payment for placement and compaction of excavated materials, classified

by the Engineer as suitable for reuse and incorporation into final works, as General fill will be made on the basis of the unit rate bid for this item within the Schedule of Quantities and Unit Prices. The unit rate bid shall apply irrespective of final measured payment volume;

.5 19mm minus crushed gravel base, drain rock, and granular pipe bedding to be considered incidental to work covered by other sections.

.3 Section 02511 Crushed Granite Granular Paving

.1 Payment for Crushed Granite Granular Paving will be made on the basis of the unit rate bid for this item within the Schedule of Quantities and Unit Prices. The unit rate bid shall be inclusive of sub-grade preparation, supply, placement and compaction of 150 mm (compacted thickness) crushed granular base course and supply, placement and compaction of crushed granite granular paving.

.4 Section 02517 – Miscellaneous Stone Work

.1 Payment for supply and installation of Granite edgers will be made in accordance with the unit rate bid for this item within the Schedule of Quantities and Unit Prices. The unit rate bid shall be inclusive of: .1 Sub-grade preparation; .2 Supply and installation of filter medium; .3 Supply, placement and compaction of 150 mm (compacted thickness)

of crushed granular base; .4 Supply and placement of setting bed; .5 Supply and placement and compaction of Granite edgers; .6 Supply and installation of jointing sand/sand-lock mix; .7 Supply and installation of below grade cip concrete edge restraint; .8 Cleanup and; .9 Any other items required to complete the work.

.2 Payment for supply and installation of Granite Setts Paving will be made on the basis of the unit rate bid for this item within the Schedule of Quantities and Unit Prices. The unit rate bid shall be inclusive of: .1 Sub-grade preparation; .2 Supply and installation of filter medium; .3 Supply, placement and compaction of 150 mm (compacted thickness)

of crushed granular base; .4 Supply and placement of setting bed; .5 Supply and placement and compaction of Granite Setts Pavers; .6 Supply and installation of jointing sand/sand-lock mix; .7 Cleanup and;

Page 11: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Measurement Section 01006 Triangle Park and Payment Page PS10074

5

.8 Any other items required to complete the work. .3 Payment for supply and installation of Granite Curbs will be made in

accordance with the unit rate bid for this item within the Schedule of Quantities and Unit Prices. The unit rate bid shall be inclusive of: .1 Sub-grade preparation; .2 Supply and installation of filter medium; .3 Supply, placement and compaction of 150 mm (compacted thickness)

of crushed granular base; .4 Supply and placement of setting bed; .5 Supply and placement and compaction of Granite Curbs; .6 Supply and installation of jointing sand/sand-lock mix; .7 Supply and installation of below grade cip concrete edge restraint; .8 Cleanup and; .9 Any other items required to complete the work.

.5 Section 02720 – Subsurface Drainage System

.1 Payment for the supply and installation of 100mm Sub-drain will be made in accordance with the unit rate bid for this item within the Schedule of Quantities and Prices. The unit rate bid shall represent all compensation due to the Contractor for a fully functional system and shall include, but not be limited to excavation and disposal, backfill, dewatering, permits, drain rock, filter gravel, granular pipe bedding, materials, fittings, miscellaneous hardware, tests, connections to associated drainage structures, connections to existing storm sewer, and any other items necessary for the complete and satisfactory performance of the system.

.6 Section 02800 – Design Build Automatic Spray Irrigation System

.1 Payment for Design Build Automatic Spray Irrigation System will be made on the basis of the lump sum price bid for this item within the Schedule of Quantities and Unit Prices.

.7 Section 02870 – Site Furnishing

.0 Payment for supply and installation of site furnishings will be made in accordance with the lump sum price bid for this item within the Schedule of Quantities and Unit Prices. Price shall include all items required to complete the work in a manner acceptable to the Engineer and shall include mock-ups if and as required.

.8 Section 02920 – Growing Medium Preparation and Placement

.1 Payment for supply, preparation and placement of growing medium will be made on the basis of the unit rate bid for this item within the Schedule of Quantities and Prices.

.9 Section 02938 – Sod Lawns

.1 Payment for sod lawns will be made on the basis of the unit rate bid for this item within the Schedule of Quantities and Unit Prices. The unit rate bid shall be inclusive of sub-grade preparation, fertilizers, sod, application, maintenance and any other items required to complete the work in a manner acceptable to the Engineer.

.10 Section 02950 – Planting Trees, Shrubs and Ground Cover

Page 12: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Measurement Section 01006 Triangle Park and Payment Page PS10074

6

.1 Payment for supply and planting of trees will be made on the basis of the unit rate bid for this item within the Schedule of Quantities and Unit Prices. The unit bid price shall be inclusive of sub-grade prep, mulch, fertilizers, maintenance and any other items required to complete the work in a manner acceptable to the Engineer.

.2 Payment for supply and planting of #1 pot plants will be made on the basis

of the unit rate bid for this item within the Schedule of Quantities and Unit Prices. The unit bid price shall be inclusive of sub-grade prep, mulch, fertilizers, maintenance and any other items required to complete the work in a manner acceptable to the Engineer.

.3 Payment for 3.5” pot plants will be made on the basis of the unit rate bid

for this item within the Schedule of Quantities and Unit Prices. The unit bid price shall be inclusive of sub-grade prep, mulch, fertilizers, maintenance and any other items required to complete the work in a manner acceptable to the Engineer.

.11 Section 02970 – Landscape Maintenance

.1 Payment for landscape maintenance will be made in accordance with the lump sum price bid for this item within the Schedule of Quantities and Unit Prices. Payment shall be made over the course of the one year maintenance period.

.12 Section 03100 – Concrete Formwork

.1 Cost of formwork to be considered incidental to the cost of Cast-In-Place concrete and shall be included in the unit rates bid for Cast-In-Place concrete in the Schedule of Contract Unit Prices.

.13 Section 03200 – Concrete Reinforcement

.1 Cost of Concrete Reinforcement to be considered incidental to the cost of Cast-In-Place concrete and shall be included in the unit rates bid for Cast-In-Place concrete in the Schedule of Contract Unit Prices.

.14 Section 03300 – Cast-In-Place Concrete

.1 Payment for Cast-In-Place concrete will be made on the basis of the unit rate bid for this item in the Schedule of Quantities and Unit Prices. The unit rate bid will include the cost of formwork, anchors, reinforcing, concrete, miscellaneous hardware, excavation, sub-grade preparation, 150mm compacted granular base, certification and any other items required for the successful completion of the work.

.2 Payment for the supply and construction of the Cast-in-place concrete retaining wall and its associated Cast-in-place concrete band on West side of park will be made in accordance with the lump sum price bid for this item within the Schedule of Quantities and Prices. The lump sum price bid shall be inclusive of concrete, formwork, anchors, misc. hardware, reinforcement, excavation, sub-grade preparation, finishes, control joints, expansion joints, 150mm compacted granular base, drain rock, PVC drains and connection of PVC drains to sub-surface drainage system, certification and any other items required for the successful completion of the work.

.3 Payment for the supply and construction of the Cast-in-place concrete curved topped bench bases will be made in accordance with the lump sum price bid for this item within the Schedule of Quantities and Prices. The lump sum price bid shall be inclusive of concrete, formwork, anchors,

Page 13: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Measurement Section 01006 Triangle Park and Payment Page PS10074

7

misc. hardware, excavation, sub-grade preparation, reinforcement, finishes, control joints, 150mm compacted granular base, certification and any other items required for the successful completion of the work.

.15 Section 03340 – Sandblast Concrete

.1 Cost of sandblast surface treatment of cast-in-place concrete to be considered incidental to the cost of Cast-In-Place concrete and shall be included in the unit rates bid for Cast-In-Place concrete in the Schedule of Contract Unit Prices.

.16 Section 03345 – Concrete Finishes

.1 Cost of specified finishes of cast-in-place concrete to be considered incidental to the cost of Cast-In-Place concrete and shall be included in the unit rates bid for Cast-In-Place concrete in the Schedule of Contract Unit Prices.

.17 Section 05500 – Metal Fabrications

.1 Payment for fabrication, delivery and erection of the Triangle Park Pavillion will be made in accordance with the lump sum price bid for this item within the Schedule of Quantities and Unit Prices. The lump sum price bid shall include shop fabrication of structural steel supporting members, mock-ups if and as required, coatings, delivery, erection, installation, field repair of coatings, miscellaneous hardware and any other items necessary for the completion of the work.

.18 Section 16000 – Electrical

1. Payment for Electrical Conduit in Trench will be made in accordance with the unit rate bid for this item in the Schedule of Quantities and Unit Prices. The unit rate bid per metre of trench complete with conduit supplied, installed and accepted by the Engineer shall include the trench excavation, disposal of excess excavated material, supply and installation of all conduit related materials, fusing of joints, placement of conduit, conduit bedding, trench backfilling, warning tape, as specified herein and as shown on the Contract Drawings.

2. Payment for Light fixtures/drivers will be made in accordance with the unit rate bid for each light fixture/driver included in the Schedule of Quantities and Unit Prices. 80% of Unit Price bid per unit supplied, installed and accepted by the Engineer. 20% of Unit Price bid per unit when Light system is commissioned tested and operational and accepted by the Engineer. Light fixture shall include the supply and installation or mounting within columns and benches complete with mounting hardware, ballasts, fuses, grounding and wiring as per drawings. Light drivers (illuminators) shall include the supply and installation and mounting of the dimmers within the benches, complete with mounting hardware, ballasts, fuses, grounding and wiring as per drawings.

3. Payment for wiring will be made in accordance with the unit price lump sum for the complete system included in the schedule of quantities. Wiring shall include supply, installation, commissioning and testing of the system complete with grounding as per drawings.

Page 14: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Measurement Section 01006 Triangle Park and Payment Page PS10074

8

2 PRODUCTS Not applicable to this section

3 EXECUTION Not applicable to this section

END OF SECTION

Page 15: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Shop Drawings, Product Data and Samples Section 01130 Triangle Park Page 1 PS10074

1.00 GENERAL

1.01 DESCRIPTION OF WORK

.1 This section specifies general requirements and procedures for contractors submissions to Engineer for review. Additional specific requirements for submissions are specified in individual sections. .1 Shop Drawings. .2 Product Data. .3 Samples and Mock-Ups.

1.02 SUBMISSION REQUIREMENTS

.1 Coordinate each submission with requirements of work and Contract Documents. Individual submission will not be reviewed until all related information is available.

.2 Allow 10 working days for Engineer’s review of each submission. .3 Accompany submissions with transmittal letter containing:

.1 Date.

.2 Project title and number.

.3 Contractor’s name, address, telephone and facsimile.

.4 Contact person’s name and position.

.5 Identification and quantity of each shop drawing, product data, and sample (if requested or required).

.6 Other pertinent data.

.4 Submissions shall include: .1 Date and revision dates: .2 Project title and number. .3 Name, address telephone, facsimile and contact person of:

.1 Subcontractor.

.2 Supplier.

.3 Manufacturer.

.4 Contractor’s stamp, signed by Contractors authorized representative certifying approval of submissions, verification of field measurements and compliance with Contract Documents. Submittals, which do not contain this information, will be returned without being examined and shall be considered rejected.

.5 Details of appropriate portions of Work as applicable:

.1 Fabrication.

.2 Layout, showing dimensions, including identified field dimensions, and Clearances.

.3 Setting or erection details.

.4 Capacities.

.5 Performance characteristics.

.6 Standards.

Page 16: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Shop Drawings, Product Data and Samples Section 01130 Triangle Park Page 2 PS10074

.7 Operating weight.

.8 Wiring diagrams.

.9 Single line and schematic diagrams.

.10 Relationship to adjacent work.

.11 Materials.

.12 Finishes.

.6 After Engineer’s review and written approval, distribute copies to persons necessary to complete the work. Ensure one copy of reviewed submission is kept on site.

1.03 GENERAL REQUIREMENTS

.1 Work affected by the submittal shall not proceed until review is complete. .3 Present shop drawings, product data, samples and mock-ups in SI Metric Units. .4 Where items or information is not produced in SI Metric units converted values are

accepted. .5 Contractor’s responsibility for errors and omissions in submission is not relieved by

Engineer’s review and/or approval of submissions. .6 Notify Engineer, in writing at time of submission, identifying deviations from

requirements of Contract Documents stating reasons for deviations. .7 Contractor’s responsibility for deviations in submission from requirements of

Contract Documents is not relieved by Engineer’s review of submission, unless Engineer gives written acceptance of specific deviations.

.8 Make any changes in submission which Engineer may require consistent with Contract

Documents and resubmit as directed by Engineer. .9 Notify Engineer, in writing when resubmitting, any revisions other than those

requested by Engineer. 1.04 SHOP DRAWINGS

.1 Shop drawings: are defined as original drawings, or modified standard drawings, catalogue information, illustrations, schedules, performance charts, brochures and other product data provided by Contractor, to illustrate details of portions of Work, which are specific to project requirements.

.2 Adjustments made on shop drawings by the Engineer are not intended to change the

Contract Price. If adjustments affect the value of work, state such in writing to the Engineer prior to proceeding with work.

.3 Submit six (6) opaque diazo prints or Xerox reproductions for each requirement

requested.

Page 17: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Shop Drawings, Product Data and Samples Section 01130 Triangle Park Page 3 PS10074

.4 Cross-reference shop drawing information to applicable portions of Contract

Documents. .5 Faxed shop drawings are not acceptable.

1.05 SAMPLES

.1 Samples: examples of materials, equipment, quality, finishes, workmanship. .2 Deliver samples prepaid to the Engineer’s business address. .3 Where colour, pattern or texture is criterion, submit full range of samples. .4 Adjustments made to samples by the Engineer are not intended to change the

Contract Price. If adjustments affect the value of work, state such in writing to the Engineer prior to proceeding with work.

.5 Reviewed samples will become standard of workmanship and material against which

installed work will be verified. 1.06 MOCK-UPS

.1 Mock-ups: field erected example of work complete with specified materials and workmanship.

.2 Erect mock-ups at locations acceptable to Engineer. .3 Adjustments made to mock-ups by the Engineer are not intended to change the

Contract Price. If adjustments affect the value of work, state such in writing to the Engineer prior to proceeding with work

.4 Reviewed mock-ups will become standards of workmanship and material against

which installed work will be verified. 1.07 SHOP DRAWING, MOCK-UP AND SAMPLE REVIEW

.1 The review of shop drawings, mock-ups and samples by the Engineer is for the sole purpose of ascertaining conformance with the general concept. This review shall not mean that the Engineer approves the detail design inherent in the shop drawings, responsibility for which shall remain with the Contractor submitting same, and such review shall not relieve the Contractor of responsibility for requirements of the construction and contract documents. Without restricting the generality of the foregoing, the Contractor is responsible for dimensions to be confirmed and correlated at the job site, for information that pertains solely to fabrication processes or to techniques of construction and installation and for co-ordination of the work of all subtrades.

Page 18: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Shop Drawings, Product Data and Samples Section 01130 Triangle Park Page 4 PS10074

PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable)

END OF SECTION 01330

Page 19: City of Vancouver General Section 01005 Triangle Park ...

CITY OF VANCOUVER ENVIRONMENTAL Section 01561 Triangle Park PROTECTION Page 1 PS10074

Section 01561

PART 1 GENERAL

1.1 Requirements

.1 This Specification addresses general requirements for environmental protection.

1.2 Compliance

.1 The Contractor and each Subcontractor, while performing the Work, shall comply with relevant statutes, regulations, laws and directives of legislative authorities in all matters relating to the protection of the environment. In addition, if, in the opinion of the Engineer or environmental monitor, the Contractor's construction practices or facilities require immediate modification to reduce the risk of environmental damage, the Contractor shall be required to stop work and make the necessary changes prior to proceeding with the Work. No compensation shall be provided by the Owner for any losses resulting from the shutdown of work.

1.3 Conflicts and Omissions

.1 If the Contractor finds or observes that there appears to be a conflict between the contents of this Section or other Sections of the Specifications and the requirements of legislative authorities, then such conflict shall be brought to the attention of the Engineer for resolution. Similarly, any omissions or apparent omissions from this Section relevant to current legislation shall be referred to the Engineer. Omissions or apparent omissions shall in no way diminish the Contractor's responsibility to comply with the statutes, regulations, bylaws and directives of legislative authorities.

1.4 Environmental Protection Plan

.1 The Contractor shall employ a consultant specializing in environmental protection to complete environmental monitor duties for this project. The environmental monitor shall also prepare and submit to the Engineer for review and approval an Environmental Protection Plan (EPP) specific to the Work. The Contractor shall not commence the Work at the Site until the Engineer has approved the EPP. The EPP shall address at a minimum the following:

(1) Applicable regulations that apply for all jurisdictions, including compliance with Appendix B – Department of Fisheries and Oceans Authorization.

(2) List of all materials and products to be used on the Site. (3) Environmental protection measures to be used for each material and product. (4) List of environmental impacts that will be created in the course of construction. (5) Protection measures to mitigate environmental impacts. (6) Erosion and sediment control details and procedures (7) Emergency spill/emission response plan. (8) Dewatering plan and discharge points including sediment control measures. (9) Water quality monitoring and Site inspection plan. (10) Containment plans for equipment service areas. (11) Liquid storage, fuelling, and equipment operation and maintenance procedures. (12) Site restoration and clean-up plans.

Page 20: City of Vancouver General Section 01005 Triangle Park ...

CITY OF VANCOUVER ENVIRONMENTAL Section 01561 Triangle Park PROTECTION Page 2 PS10074

Section 01561

.2 The Contractor's environmental monitor shall submit to the Engineer, on a weekly basis, comprehensive environmental reports in PDF format demonstrating that the Contractor is complying with the approved Environmental Protection Plan, detailing non-compliances and detailing corrective actions. The report shall include colour photographs of the work in progress.

1.5 Hazardous Substances

.1 The Contractor shall make itself fully aware of all Federal and Provincial legislation and restrictions on the storage and use of certain products or materials considered harmful to the environment or persons and shall comply with all applicable regulations and guidelines.

.2 The Contractor shall promptly provide to the Engineer with copies onsite of all Material Safety Data Sheets (MSDS) relating to all hazardous substances brought to the Site.

1.6 Water Management

.1 The Contractor shall comply with the water-taking requirements of the British Columbia Water Act in connection with its operations.

1.7 Surface Water Quality Protection

.1 The Contractor shall provide and maintain containment works to ensure no material resulting from the construction activity enters any river, creek, stream, watercourse or storm drainage system. All such dewatering works are to be designed and implemented in consultation with the environmental monitor. Detailed drawings and procedures that will be followed to ensure the watercourses' water quality will be protected are to be submitted to the Engineer for review by the environmental monitor at least three (3) days prior to the start of work. Construction work shall not begin until the containment works have been reviewed and accepted by the appropriate governing authority.

.2 All water containing a chlorine residual shall be dechlorinated before discharge into any watercourse.

.3 Accidental chemical or fuel spills, which may enter a water body, shall be cleaned up immediately by the Contractor and reported as required.

1.9 Erosion and Sediment Control

.1 Erosion and sediment control shall be achieved by following the requirements of the Environmental Protection Plan. These requirements include the use of silt fences in drainage areas on land, by the use of specified granular materials for in-water work, by use of settlement ponds, and by the use of in-water silt curtains and check dams, and such other means as are required to satisfy governing standards.

.2 All erosion and sediment control works shall be submitted for review by the environmental monitor. Construction work shall not proceed until the control works have been reviewed and accepted by the Engineer and the appropriate governing authority.

.3 The Contractor shall be responsible for the provision and maintenance of all erosion and sediment control installations at all points and areas of natural drainage.

1.10 Spill Contingency Planning

Page 21: City of Vancouver General Section 01005 Triangle Park ...

CITY OF VANCOUVER ENVIRONMENTAL Section 01561 Triangle Park PROTECTION Page 3 PS10074

Section 01561

.1 As part of the Environmental Protection Plan, the Contractor shall prepare a Spill Contingency Plan no less than three (3) days prior to the start of construction work.

.2 The main objectives of the Spill Contingency Plan shall be to comply with all regulatory requirements and provide the best response to a spill within the shortest possible time. To meet these objectives, the Plan shall include mechanisms for initiating and carrying out the required notifications, spill containment, clean-up and remedial actions.

.3 The Contractor shall be familiar with all regulatory requirements and be adequately prepared to respond to a spill condition within the shortest possible time.

.4 The Contractor shall designate a Spill Response Team formed from suitably qualified members of its workforce at the Site.

.5 The spill contingency procedures must be posted in a visible location within the Contractor's site offices and worker trailers. These plans shall be reviewed by the Contractor's Spill Response Team, on a scheduled basis to ensure a thorough understanding.

.6 The notices and actions detailed in the reviewed Spill Contingency Plan shall be followed by the Contractor.

.7 Any spill greater than 0.5 litres shall be reported to the Engineer.

.8 Drainage control measures shall be put in place as required by Site drainage features to protect open water and watercourses from potential spill substances.

.9 Sorbent material shall be on hand at work areas as a means of containing and soaking up any spill substance before it reaches the groundwater table or open water.

.10 Excess concrete, grout, drilling wastes and other liquid waste products shall be directed to secure containment facilities for subsequent removal and disposal by the Contractor.

.11 Empty drums shall be provided by the Contractor at the Site for pre-disposal storage of spillable substances and for disposal of used sorbents, contaminated soil, and the like.

.12 The Contractor shall supply and maintain an appropriate spill response kit at the Site.

1.11 Waste Management

.1 The Contractor shall comply with all requirements for managing waste through the course of the Work.

.2 Waste types anticipated at the Site may include sanitary sewage, domestic garbage, construction garbage, rock and soil wastes, concrete, grout waste, reinforcing and other steel waste, recovered granular materials, formwork and falsework waste, operating fluid wastes from vehicles and construction equipment, collected sediment, and hazardous wastes.

1.12 Liquid Storage

Page 22: City of Vancouver General Section 01005 Triangle Park ...

CITY OF VANCOUVER ENVIRONMENTAL Section 01561 Triangle Park PROTECTION Page 4 PS10074

Section 01561

.1 Onsite fuel storage tanks and storage for other environmentally hazardous liquids shall be located as far away from open water, watercourses and other drainage courses as is practicable, and shall be contained within dikes or equivalent enclosures on flat ground in the laydown area. Enclosures in liquid storage areas shall be such as to contain the total volume stored plus precipitation. Protection against seepage shall be provided.

.2 The Contractor shall follow the Spill Contingency Plan, which is approved by the Engineer as part of the Environmental Protection Plan. Sorbent materials shall be on hand at liquid storage areas as a means of containing or soaking up errant spills. Empty drums shall be on hand for predisposal storage of spilled substances; sufficient drums shall be available to accommodate stored and in-service volumes of spillable substances.

1.13 Refuelling and Equipment Operation

.1 Refuelling

a) Readily mobile highway vehicles shall be refuelled at the Site as approved by the Engineer.

b) Motorized mobile equipment and machinery shall be refuelled in a refuelling/service area to be developed in the laydown area. Care shall be taken to ensure that petroleum products do not spill during refuelling.

c) Equipment, which is not readily mobile, may be refuelled at the Site location as far as possible from open water or watercourses. Drip trays shall be used and sorbent materials shall be immediately on hand for rapid deployment in the event of a spill.

.2 Equipment Operation

a) Equipment shall be cleaned and serviced as necessary to prevent deposition of soils, oil, grease, coolant, fuel and any other contaminants.

b) Stationary equipment operating near open water or watercourses or in dewatered areas shall be equipped with drip trays to contain any fuel, oil, coolant or grease leakage. Drip trays for grout pumps and grout reservoirs shall be capable of containing all accidental spills/leakage during hose connection and operation.

c) No equipment shall be washed in work areas or near open water or watercourses.

d) All equipment shall be in good operating condition and meet applicable statutory requirements for serviceability and exhaust emissions. Exhaust systems shall function in a manner to control exhaust noise within acceptable levels.

e) An equipment service area, if required by the Contractor, shall be on relatively flat ground in the laydown area. A granular mat overlying an impermeable liner shall be used in this service area and shall be placed so as to contain seepage. The Contractor shall take precautions to ensure that this liner does not become punctured. Drip trays shall be used to control on-ground spillage of fuels, oils,

Page 23: City of Vancouver General Section 01005 Triangle Park ...

CITY OF VANCOUVER ENVIRONMENTAL Section 01561 Triangle Park PROTECTION Page 5 PS10074

Section 01561

coolants and grease. The Contractor shall be responsible for any and all clean up of contamination resulting from its operations. Contaminated granular mat materials and other contaminated soils shall be carefully excavated and shall be disposed of at an appropriate location. These materials may be classified as hazardous waste as disposed of by the Contractor in accordance with provincial and federal regulations.

1.14 Construction Dust Control

.1 Environmentally acceptable dust suppressants or water shall be used as necessary to control dust on access roads, laydown, work and disposal areas. Dust shall be controlled throughout the Work. No oils shall be used for dust control. Preference shall be given to the use of water, bearing in mind water conservation and drainage where appropriate.

.2 Cover or wet down dry materials and rubbish to prevent blowing dust and debris. Provide dust control for temporary and permanent roads.

1.15 Construction Noise Control

.1 Construction safety based on Workers' Compensation Board of British Columbia requirements and local municipal bylaws shall provide the regulatory basis for noise control and hearing protection. Noise bylaws or formal exemption therefore shall be used in setting hours of work limitations.

.2 Construction operations shall be performed to minimize noise.

1.16 Air Pollution and Odour Control

.1 Volatile liquids, including fuels and solvents, shall be stored in closed containers.

.2 Equipment shall be properly maintained to reduce gaseous pollutant emissions.

1.17 No tracking off-site

.1 The contractor shall not track dirt, grease, oil, and other contaminants off-site and shall employ necessary facilities and operations as necessary to minimize tracking of such substances offsite. The contactor shall regularly sweep and clean roadways and adjacent areas to the Site.

.2 Construction at the Site shall not proceed and may be suspended by the Engineer if adequate provisions are not in place.

1.18 Dewatering

.1 Pumps used to maintain dewatered areas on the Site must discharge water in accordance with all applicable regulations. The Contractor is responsible for obtaining necessary disposal or discharge permits.

.2 Work area runoff water contaminated with hazardous substances shall be treated as the product of a spill to the environment.

Page 24: City of Vancouver General Section 01005 Triangle Park ...

CITY OF VANCOUVER ENVIRONMENTAL Section 01561 Triangle Park PROTECTION Page 6 PS10074

Section 01561

.3 Dewatering facilities shall also be constructed and maintained so that all placement of concrete is completed in a dry area.

1.19 Earthwork Activities

.1 The Contractor shall exercise judgment and skill in carrying out all earthwork-related activities due to the suspended solids loading they pose to receiving water quality. All Work shall be within accepted standards of good practice for environmentally sensitive locations.

.2 Temporary slopes shall not be steeper than the permanent slopes and the bench at the foot of the excavation surface shall always slope towards the hillside to prevent direct runoff to tributary drainages.

.3 The Contractor shall conduct its activities under the premise that an intense precipitation event can occur at any time and shall take preventive measures to protect against erosion.

.4 Drainage shall be arranged to avoid concentration to runoff. Preference should be given to longer, less direct, drainage paths to existing waterways utilizing overland flow through undisturbed areas.

.5 The maintenance, work, parking and disposal areas shall be protected by perimeter ditches, if necessary, to prevent drainage through the Work area. Runoff contaminated with sediment shall be collected at a catchment basin, and then dispersed over a wide, vegetated area where it cannot flow overland to the river or streams. Use of other facilities such as silt fences and settling ponds shall also be required. Runoff contaminated with petroleum products or other chemicals shall be disposed of outside of the watershed. Disposal of all runoff shall be in accordance with B.C. Ministry of Environment and Department of Fisheries and Oceans.

.6 Operations shall be frequently reviewed by the environmental monitor to ensure water quality is maintained. No compensation will be provided for equipment or labour, which is on standby or stand-down due to weather conditions.

1.20 Sedimentation and Water Handling

Silts and fine materials introduced into water systems can have adverse effects to the aquatic environment. This construction Site is particularly sensitive due to its vicinity to fish habitat. Therefore, controlling sediment and run-off during construction work will be of high priority during this work. An interim construction water-settling pond or other sediment control measures shall be constructed and maintained by the Contractor during construction activities as deemed necessary by the Engineer.

The Contractor and environmental monitor shall ensure that water exiting the construction Site is free of sediments and other deleterious substances. All runoff leaving the site and entering water bodies, drainage courses, or drainage systems shall meet all applicable criteria and regulations.

Page 25: City of Vancouver General Section 01005 Triangle Park ...

CITY OF VANCOUVER ENVIRONMENTAL Section 01561 Triangle Park PROTECTION Page 7 PS10074

Section 01561

Should these criteria be exceeded, construction will be stopped until the situation is rectified to the satisfaction of the environmental monitor and Engineer. The Contractor and environmental monitor shall control silt-laden runoff from the working and stockpile areas. This will involve utilizing a combination of several techniques on a site-specific basis as described below:

• Installations of upslope drainage interception to remove clean uncontaminated water and reduce amount of water flowing through the Site.

• Install additional erosion control measures such as check dams, hay bales, erosion control fencing in selected areas.

• Installation of cross-slope swales to enhance drainage and to prevent erosion of excavated materials.

PART 2 PRODUCTS

.1 Not Applicable

PART 3 EXECUTION

.1 Not Applicable

END OF SECTION 01561

Page 26: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Excavation and Section 02223 Triangle Park Placement of Page 1 PS10074 Granular Materials

1 GENERAL 1.1 Scope

.1 This section refers to those portions of the work that are unique to excavation and placement of granular materials as base materials for specified surface treatments. This section must be referenced to and interpreted simultaneously with all other sections described within the Contract Documents.

.2 Work covered by this section includes:

.1 Survey of: original ground surfaces in existence prior to the commencement of work; completed excavation surfaces and; completed surfaces of all overlying fill materials.

.2 Excavation of existing fill, native soils to facilitate construction of proposed works;

.3 Dewatering and management/disposal of water derived from dewatering operations;

.4 Off-site disposal, within an approved landfill, of excavated materials that are classified by the Engineer as being unsuitable for reuse in completed works

.5 Temporary stockpiling of excavated materials, classified by the Engineer as being suitable for reuse, and subsequent incorporation of these materials within final works;

.6 Supply, placement and compaction of imported angular granular products;

1.2 Related Work .1 Force Account Section 01008 .2 Aggregates and Granular Materials Section 02226

1.3 Measurement and Payment .1 Measurement and Payment for work of this section shall be undertaken in

accordance with Section 01006 Measurement and Payment.

2 PRODUCTS 2.1 General

.1 For product descriptions refer to Section 02226 - Aggregates and Granular Materials.

Page 27: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Excavation and Section 02223 Triangle Park Placement of Page 2 PS10074 Granular Materials

3 EXECUTION

3.1 Coordination with Other Contractors .1 Protect work provided under other contracts, assume full responsibility

for and repair any damage to the satisfaction of the Engineer.

3.2 Survey .1 Surveys shall be undertaken by the Contractor to verify construction limits

and for payment purposes.

.2 As a minimum, Contractor shall survey cross-sections perpendicular to and at intervals not exceeding 5m along the longitudinal axis of the work. Survey methodology and location of surveyed cross sections subject to prior approval of the Engineer. In addition, contractor shall survey the location of all treatment boundaries including limits of filter cloth, changes in material type / placement and changes in surface treatment.

.3 Cross sections shall be surveyed of existing ground surfaces prior to initiation of construction, of completed excavation surfaces and of the completed surfaces of all specified overlying materials.

.4 Survey data collected shall be of sufficient density to fully characterize the work. At a minimum, survey levels at approximately 2 m intervals along each section with additional spot elevations surveyed at all breaks in slope or changes in construction. Survey data shall be collected to an accuracy of +/-0.01m horizontal and 0.005 m vertical or better and shall be referenced to the project elevation and coordinate grid system.

.5 Survey data shall be provided to the Engineer in digital xyz format as well as in Autocad 3-dimensional drawing format.

.6 Contractor to ensure that surveys are scheduled and completed at regular intervals to enable the estimation of payment volumes by the Engineer.

.7 The Contractor shall provide detailed volume calculations using average end area determination. Details of volume calculations shall be provided to the Engineer for review.

.8 Surveys will be subject to verification by the Engineer. In case of discrepancy, the Engineer's survey will govern.

.9 Contractor shall prepare as-built drawings at the completion of the work in 3-dimensional AutoCAD format. The drawings shall be comprised of plan and cross section views, sufficient in number, to fully characterize the work

3.3 Existing Fill Materials .1 Soil quality investigations have been conducted. Complete geotechnical

report summarizing the results of these investigations are available for review from the Owner.

.2 Where, during excavation, structures that could not be identified through visual inspection at the outset of construction are encountered, these structures shall be demolished and removed under the provisions of Supplementary General Condition 8.0 - Extra Work.

.3 Quantities of high quality fill materials, suitable for reuse in completed works, shall be separated and stockpiled on site for subsequent incorporation into new construction.

Page 28: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Excavation and Section 02223 Triangle Park Placement of Page 3 PS10074 Granular Materials

3.4 Water

.1 Contract work involves construction within inter-tidal and sub-tidal zones of False Creek. All work shall be scheduled in consideration of tide levels. To the maximum extent possible, all inter-tidal work shall be undertaken during daytime periods of low tide and all work at or above Elevation 0.0 m Vancouver City Datum shall be undertaken in the dry.

.2 Construction is subject to water quality criteria specified by authorities having jurisdiction. The contractor shall comply with such criteria and must employ methods to control sediment dispersion into False Creek.

.3 The contractor shall be responsible for management of any water resulting from construction activities.

3.5 Excavation .1 Excavation shall be confined to the limits indicated by the Contract

Drawings.

.2 The Engineer will classify all excavated materials as suitable for reuse in new construction or as unsuitable for reuse. Excavated materials classified as being unsuitable for reuse shall be transported to and disposed of at an appropriate disposal location. Excavated materials classified by the Engineer as suitable for reuse shall be stockpiled on the site for subsequent placement material.

.3 Excavated materials shall be dewatered prior to transport off-site. Dewatering methodology shall be developed by the Contractor and submitted to the Engineer for approval.

.4 Any excavated material that is odorous, contains debris or is otherwise suspected of containing elevated levels of contaminants shall be segregated and temporarily stockpiled on site pending instruction by the Engineer.

.5 Excavation surfaces shall not be covered by specified overlying materials until surfaces are inspected and approval by the Engineer and applicable surveys are completed and approved. Schedule work to minimize the period that excavation surfaces are left exposed and unprotected by overlying materials.

3.6 Boulders

.1 Boulders that are encountered during the course of excavations associated with the scope of work, having a nominal diameter of 300 mm or greater, shall be separated and stockpiled on-site at a location specified by the Engineer for integration into final works.

.2 Boulders shall be pressure washed to remove soil or other deleterious materials. Wash pressure to be a minimum of 2000 psi.

3.7 Placement of Angular Products – General

.1 No material shall be placed unless the applicable surveys on sub-grade surfaces have been carried out, plotted, and accepted by the Engineer, and the sub-grade surface has been inspected and accepted by the Engineer.

Page 29: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Excavation and Section 02223 Triangle Park Placement of Page 4 PS10074 Granular Materials

.2 Place materials on a clean surface, properly shaped and free from debris, to the lines and thickness shown on the Contract Drawings and maintained free of contamination by other materials throughout construction process.

.3 Materials shall be placed - do not drop from a height greater than 1.0 m vertically from final position.

.4 Do not place by dumping into chutes or by end dumping from haul units or by similar methods likely to cause segregation of various sizes and damage to sub grade materials.

.5 The contractor shall select a method of material placement that will not lead to segregation or degradation of aggregate. Method subject to approval by the Engineer.

.6 The Contractor shall ensure that the construction methodology adopted produces a finished surface that comprises the full spectrum of particle sizes continuously throughout its length and breadth.

.7 Objectionable pockets of small or large stones, as determined by the Engineer, shall be redistributed to the satisfaction of the Engineer.

.8 Where placed on a slope, place commencing at the toe and proceeding up the slope. Angular Material shall be densely placed and individual stones shall be worked with placement equipment to form a well keyed surface.

.9 Dress all Angular Material surfaces and fill in voids so that the final surface is well keyed, densely placed and uniform. The Engineer will require that all surface voids be filled into which a stone having a mass equal or greater than 25% of the maximum stone mass can be placed.

3.8 Placement of Angular Products – Lift Thickness and Compaction .1 General fill (as referred to in geotechnical report) shall be placed and

compacted in continuous horizontal lifts not exceeding 300 mm loose depth. Compact each lift to a minimum 95% standard Proctor density, as confirmed through independent testing by the Engineer. Process material as required to achieve moisture content within +/-2% of optimum.

.2 19mm minus crushed gravel base (as referred to in geotechnical report) shall be placed and compacted in continuous horizontal lifts not exceeding 300 mm loose depth. Compact each lift to a minimum 100% standard Proctor density, as confirmed through independent testing by the Engineer. Process material as required to achieve moisture content within +/-2% of optimum.

3.9 Placement of Angular Products - Tolerances

.1 Finished surfaces of General fill and 19mm minus crushed gravel base shall be within the following limits of established grade measured normal to finished grade, but not uniformly high or low:

.1 General fill and 19mm minus crushed gravel base: ± 25 mm

END OF SECTION

Page 30: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Aggregates Section 02226 Triangle Park and Page PS10074 Granular Materials

1

1 GENERAL 1.1 Scope

.1 Section 02226 refers to those portions of the work that are unique to the supply and processing of granular aggregate materials. This section must be referenced to and interpreted simultaneously with all other sections pertinent to the works described herein.

.2 Work covered by this section includes: .1 Supply of all angular granular products: General fill (as referred to in

geotechnical report), 19mm minus crushed gravel base (as referred to in geotechnical report), drain rock, granular pipe bedding.

1.2 Related Work

.1 Section 02226 includes specifications for aggregates and granular materials referred to in the following sections:

.1 Excavation and Placement of Granular Materials Section 02223

1.3 Approvals

.1 Inform the Engineer of proposed source and provide samples or access for sampling at least 2 weeks prior to commencing production.

.2 If, in the opinion of the Engineer, materials from proposed source do not meet, or cannot reasonably be processed to meet specified requirements, locate alternate source or demonstrate that material from source in question can be processed to meet specified requirements.

.3 Should a change of material source be proposed during work, advise the Engineer 2 weeks in advance of proposed change to allow sampling and testing.

.4 Acceptance of material does not preclude future rejection if it is subsequently found to lack uniformity, or if it fails to conform to requirements specified, or if its field performance is found to be unsatisfactory.

1.4 Measurement for Payment

.1 Measurement and Payment for work of this section shall be undertaken in accordance with Section 01006 Measurement and Payment.

2 PRODUCTS 2.1 Materials – General

.1 At least two weeks prior to commencing delivery of granular materials, the contractor must provide the Engineer with documentation specifying the source (i.e., origin) and environmental quality of all proposed granular materials and provide samples for testing by the Engineer.

.2 All proposed materials must meet standards contained in Column II of Contaminated Sites Regulation (CSR) Schedule 7.

Page 31: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Aggregates Section 02226 Triangle Park and Page PS10074 Granular Materials

2

.3 Gravel to be composed of inert, durable material, reasonably uniform in quality and free from soft or disintegrate particles. In absence of satisfactory performance records over a five-year period for particular source of material, soundness to be tested according to ASTM test procedure C-88 or latest revised issue. Maximum average weight losses for course and fine aggregates to be 30% when magnesium sulphate is used.

.4 All crushed gravel when tested according to ASTM C-136, or latest revised issue, to have a generally uniform gradation, shall conform to following gradation limits and 60% of the material passing each sieve must have one or more fractured faces. The Plasticity Index for crushed gravel to not exceed 6.0.

2.2 General Fill .1 General fill as referred to in geotechnical report shall consist of free-draining

sand or sand & gravel (of the portion passing the #10 sieve, no more than 5% should pass the #200 sieve) compacted in lifts to at least 95% standard Proctor density.

2.3 Drain Rock

.2 To consist of clean round stone or crushed rock conforming to following gradation:

Sieve Designation Percent Passing

25.0 mm 100

19.0 mm 0 - 100

12.5 mm 0 - 30

9.5 mm 0-3

.2 Drain rock to be used only where specified on Contract Drawings. Use of drain rock other than as specified requires approval of the Engineer after examination of soils against which drain rock will be placed.

2.4 Granular Pipe Bedding

Page 32: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Aggregates Section 02226 Triangle Park and Page PS10074 Granular Materials

3

.1 Crushed or graded gravels: to conform to following gradations:

Sieve Designation Percent Passing

Type 1* Type 2*

19.0 mm 90 - 100 90 - 100

12.5 mm 65 - 85 70 - 100

9.5 mm 50 - 75

4.75 mm 25 - 50 40 - 70

2.36 mm 10 - 35

0.850 mm 5 - 20 8 - 30

0.425 mm 0 - 15

0.300 mm 3 - 20

0.180 mm 0 - 8

0.075 mm 0 - 5 0 - 8

*Type 1: standard gradation

*Type 2: to be used only in dry trench conditions and with the Engineer's prior approval

.2 Other permissible materials: only where shown on Contract Drawings or directed

by the Engineer shall drain rock, pit run sand or approved native material be used for bedding and pipe surround.

2.5 Granular Base

.1 To be 19 mm crushed gravel conforming to following gradations:

Sieve Designation Percent Passing

19 mm 100

12.5 mm 75 - 100

9.5 mm 60 -90

4.75 mm 40 - 70

2.36 mm 27 - 55

0.850 mm 10 - 35

0.300 mm 5 - 20

0.075 mm 2 - 8

Page 33: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Aggregates Section 02226 Triangle Park and Page PS10074 Granular Materials

4

3 EXECUTION 3.1 Handling

.1 Handle and transport aggregates to avoid segregation, contamination and degradation.

.2 Do not use intermixed or contaminated materials. Remove and dispose of rejected materials as directed by the Engineer within 48 hours of rejection.

END OF SECTION

Page 34: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Crushed Granite Granular Paving Section 02511Triangle Park Page 1PS10074

1.00 GENERAL 1.01 GENERAL REQUIREMENTS .1 Refer to Section 01005, General Instructions.

.2 All contract documents form an integral part of this section. 1.02 RELATED WORK .1 Excavation and Placement of Granular Materials Section 02223

1.03 DESCRIPTION .1 Furnish all labour, materials, equipment, and services necessary to supply and install

and grade crushed granular base course and top course of crushed granite granular paving as shown on the drawings and as specified herein.

.2 The work shall include the supply and installation of granular paving as indicated,

including: .1 Crushed Granular Base Course .2 Crushed Granite Granular Paving

1.04 LAYOUT .1 Before proceeding with construction, stake layout of all crushed granite paving areas

for review. Verify all locations and dimensions and report to Engineer any deviation or conflicts between drawings, specifications and site conditions.

1.05 PROTECTION .1 Protect all work from damage and protect all property from damage arising from this

contract. Take every precaution necessary to avoid damage to drainage and irrigation systems.

1.06 EXISTING UTILITIES AND STRUCTURES

.1 Exact location of all existing utilities and structures, whether or not indicated on the drawings will be determined by the Contractor. Conduct work so as to prevent interruption of service or damage.

.2 Contractor will be responsible for repair of any utilities damaged in the course of his

work.

Page 35: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Crushed Granite Granular Paving Section 02511Triangle Park Page 2PS10074

.3 Coordinate all irrigation, drainage and electrical work with crushed granite paving work.

1.07 SAMPLES

.1 Submit two (2), one (1) litre samples of crushed granite granular material conforming to specifications for review by Engineer prior to start of work in this section. Color to match waterfront crushed granite as closely as possible.

2.00 PRODUCTS 2.01 MATERIALS .1 Crushed Granite Granular Paving: shall consist of sound, durable granite particles.

Granite material is to be free from clay, organic material or other deleterious matter, evenly graded, to meet the following gradation requirements:

Sieve Size (mm) Sieve Size (inches/#) Percent Passing 19 (3/4”) 100 12.5 (1/2”) 98-100 9.5 (3/8”) 50-80 4.75 (#4) 70-90 2.00 (#10) 40-70 0.42 (#40) 15-35 0.177 (#80) 7-15 0.149 (#100) 5-12 0.074 (#200) 3-8

.2 Crushed Granular Base Course: The 19 mm (3/4”) crushed granular base course shall consist of sound, durable particles free from clay, organic material or other deleterious matter, evenly graded, to meet the following gradation requirements. Sieve Size (mm) Sieve Size (inches/#) Percent Passing 19 (3/4”) 100 12.5 (1/2”) 75 – 100 9.5 (3/8”) 60 – 90 4.75 (#4) 40 – 70 2.36 (#8) 27 - 55 1.18 (#16) 16 – 42 0.60 (#30) 8 - 30 0.30 (#50) 5 – 20 0.15 (#100) 5 - 15

0.074 (#200) 2 – 5 .3 Binder: Crushed Granite to be stabalized with EnviroBINDER available from Stream

Organics 888-535-4149 or approved equal

Page 36: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Crushed Granite Granular Paving Section 02511Triangle Park Page 3PS10074

3.00 EXECUTION 3.01 INSPECTION .1 Areas of work to receive crushed granite granular paving and base course shall be

examined and unsatisfactory conditions reported to Engineer. Commencement of work shall imply acceptance of conditions.

3.02 PREPARATION OF SUBGRADE .1 Compact subgrade to 95% Modified Proctor Density. .2 Excavate soft and unstable areas of subgrade that cannot be compacted to standard

noted, fill and compact with approved granular material. .3 Ensure subgrade is true to line and grade and allows for sufficient depth to ensure

finish grade can be established as noted on plans. 3.03 CRUSHED GRANULAR BASE COURSE .1 Place granular base course over sub–grade in maximum 150 mm (6”) lifts compacted

to 95% MPD. 3.04 CRUSHED GRANITE GRANULAR PAVING .1 Engineer shall review crushed granular base course prior to the placement of the

crushed granite granular paving. .2 Place crushed granite to depths as per Landscape Drawings, integrate EnviroBINDER

as per manufacturer specifications and compact to 95% MPD. .3 Mist granite paving surface to activate binder as per manufacturer specifications.

.4 After final compaction, the surface shall be true to elevation and shall not vary by

more than 5 mm (1/4”) tested with a 3m straight edge at any location on the surface. Surfaces shall be crowned at a minimum of 2 % and abut flush with adjacent materials.

3.05 ADJUST AND CLEAN .1 All paved areas or adjacent surface shall be brushed clean and excess materials shall

be removed from the work site and disposed of in an approved dump location.

END OF SECTION

Page 37: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Miscellaneous Stone Work Section 02517Triangle Park Page 1PS10074

1.00 GENERAL 1.01 GENERAL REQUIREMENTS .1 Refer to Division 1, General Requirements.

.2 All contract documents form an integral part of this section. 1.02 RELATED WORK 1.03 DESCRIPTION .1 Furnish all labour, materials, equipment, and services necessary to construct, supply

and install all miscellaneous stone work noted on the drawings and as specified herein. Work includes but is not limited to:

.1 Granite Elements, Supply and Install .1 Granite Sett Paving including tumbled finish as indicated on

drawings. .2 Granite edger and curbs, split faced and sawn as indicated on

drawings. 1.04 PROTECTION

.1 Site and Adjacent Property .1 Protect all work from damage related to weather, other trades, and/or on

site construction activities. .2 Protect adjacent property and construction activities from damage arising

from this contract. .2 Finished Stone

.1 Properly protect all stone against damage in transit or at project site.

.2 Place wood timbers under stone when stored on open ground to prevent contact with grade.

1.05 EXISTING UTILITIES AND STRUCTURES

.1 Exact location of all existing utilities and structures, whether or not indicated on the drawings will be determined by the Contractor. Conduct work so as to prevent interruption of service or damage.

.2 Ensure that all underground utilities including drainage and irrigation systems are

clearly located and protected during construction. Make good all damages.

Page 38: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Miscellaneous Stone Work Section 02517Triangle Park Page 2PS10074

1.06 APPROVED EQUALS

.1 Approved Equal .1 Should the Contractor be seeking permission for use of an approved equal

beyond the suppliers identified in this specification the following process shall be followed for the review and approval of an alternate material.

.2 Within the first ten (5) business days from the date of the Tender call for work of this section the Contractor shall provide in writing either by fax or email a notification to the Engineer of the intention to seek an approved equal.

.3 Following notification and within the first fourteen (10) days from the date of the Tender call supply documentation as noted to the Engineer at no cost to the Owner or the Engineer. Documentation to include; .1 One (1) 300 mm x 300 mm x 40mm sample (in the case of granular a one

(1) litre sample ) of material proposed as ‘Approved Equal’. The sample shall clearly illustrate specified finishes and be labeled with the supplier name, address and phone number, stone name or product name, quarry location, type of stone, size of stone in the case of aggregate, sieve analysis in the case of aggregate, various finishes, project name and date.

.4 Engineer shall review proposal for ‘Approved Equal’ and notify the Contractor in writing either by fax or email that the sample proposed as an ‘Approved Equal’ has been either accepted or rejected within five (5) business days of receipt of sample.

.5 Rejected proposals will not be considered during the Tender evaluation.

1.07 APPROVED MATERIAL SUBMITTALS

.1 Material Samples; Two weeks prior to the start of construction submit to the Engineer three (3) representative samples to the sizes and finishes noted. Clearly label the stone name or product name, quarry location, various finishes, project name and date.

.1 Granite: 300mmx300mmx100mm samples illustrating the following finishes on at least one face of each sample; split face finish, saw cut finish, hand chisel and weathered finish.

.2 Granite Setts: Representative of size, shape colour, texture.

.2 All materials delivered to site will conform to selected samples, subject to normal stone variations. One (1) submitted sample will be retained on site at Site Office as record of approved material.

Page 39: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Miscellaneous Stone Work Section 02517Triangle Park Page 3PS10074

1.08 QUALITY ASSURANCE

.1 Source Supply: All material shall be obtained from quarries having adequate capacity and facilities to meet specified requirements. Cutting and finishing shall be carried out by a firm equipped to process material promptly on order and in strict accord with specifications.

.3 All materials delivered to the site shall be clean, in good condition free of defects,

stains and markings. 1.09 SCHEDULE

.1 Provide the Engineer three (3) copies of a schedule outlining the key milestone dates

related to quantity and sequence as required to properly expedite installation. .1 The completion of quarry extraction and dressing of stone .2 Delivery to the site .3 Installation and completion

1.10 EXAMINATION

.1 Prior to the commencement of work of this section, inspect all surfaces on which work is to be laid and ascertain that surfaces are adequate in relationship to the preparation of work to be performed under this section. Commencement of work will signify acceptance. Report any defects to the Engineer.

2.00 PRODUCTS 2.01 MATERIALS

.1 Granite Elements, Supply and Install .1 Free of cracks, seams or starts that may impair structural integrity or function.

Minor variations in stone characteristic will be acceptable. .2 All granite to be salt and pepper mix of grey, black and white fleck. Acceptable

suppliers and proprietary products include; .1 Huckleberry Mist as supplied by Northwest Landscape and Stone Supply –

Burnaby, BC 604.435.4842 .2 Fox Island Granite as supplied by Quadra Stone - Vancouver, BC

1.888.266.5341 .3 Local Squamish White as supplied by Mahovlich Marble and Granite – Burnaby,

BC 604.293.0093 .4 Hardy Island Granite as supplied by Bedrock Granite Sales – Coquitlam, BC

604.941.7783 .5 Pre approved equal as per Section 1.06 Approved Equals.

.2 Finish .1 Accessory Granite Elements, Supply and Install

Page 40: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Miscellaneous Stone Work Section 02517Triangle Park Page 4PS10074

.1 Granite Setts Paving .1 Roughly square in shape sawn and tumbled as required to sizes

indicated on drawings.

.3 Crushed Granular Base Course: The 19 mm (3/4”) crushed granular base course shall consist of sound, durable particle free from clay, organic material or other deleterious matter, evenly graded, to meet the following gradation requirements. Sieve Size (mm) Sieve Size (inches/#) Percent Passing 19 (3/4”) 100 12.5 (1/2”) 75 – 100 9.5 (3/8”) 60 – 90 4.75 (#4) 40 – 70 2.36 (#8) 27 - 55 1.18 (#16) 16 – 42 0.60 (#30) 8 - 30 0.30 (#50) 5 – 20 0.15 (#100) 5 - 15

0.074 (#200) 2 – 8 .4 Jointing Sand: shall be free of deleterious soluble salts and other contaminants,

which may cause efflorescence and comply with ASTM, C144, CSA A82.56M-1976. Sieve Size Percent Passing 5mm 100 2.5mm 95–100 1.25mm 60-100 .600mm 35-80 .300mm 15-80 .150mm 2-15

.5 Sand Sealer: Joint sand to be stabilized with Sand – Lock by Pave Chem

(800.728.3832). .6 Anchors & Dowels: All anchors or dowels shall be deformed non-ferrous metal of

types and sizes shown on reviewed shop drawings.

3.00 EXECUTION 3.01 LAYOUT .1 Prior to the start of construction, stake layout the following elements for Engineer

review. .1 Granite Curbs and edgers .2 Granite Setts.

Verify all locations and dimensions and report to Engineer any deviation or conflicts between drawings, specifications and site conditions.

Page 41: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Miscellaneous Stone Work Section 02517Triangle Park Page 5PS10074

3.02 SUBGRADE PREPARATION .1 Compact subgrade to 95% Modified Proctor Density. .2 Excavate soft and unstable areas of subgrade that cannot be compacted to standard

noted, fill and compact with approved granular material. .3 Ensure subgrade is true to line and grade and allows for sufficient depth to ensure

finish grade can be established as noted on plans. 3.03 PLACEMENT OF GRANITE ELEMENTS .1 Examine material prior to installation for visible defects or damage. Do not install

cracked, chipped, stained or physically damaged pieces. Report any damages to Engineer immediately.

.2 Place crushed granular base course to lines and levels noted on drawings. .3 Set Granite setts, curbs and edgers to lines and levels noted on drawings.

.1 Ensure elements listed above sit true, do not rock or move under the load of pedestrian or where indicated vehicle traffic.

.4 Granite Setts Paving

.1 The granite setts paving shall be laid to pattern as indicated on the Contract Documents.

.2 The granite setts paving shall be laid in such a manner that the desired

pattern is maintained and the joints between the units do not exceed dimension noted in detail. Full units shall be laid first. Partial pieces shall be fitted subsequently and shall be saw cut.

.3 After placement of granite setts paving, jointing sand sealer mixture shall

be brushed over the surface, fully broomed to fill all joints. Final treatment of sand sealer to activate mixture as per manufacturers instructions.

.4 The finished surface shall be true to elevation and shall not vary by more

than 6mm tested with a 3m straight edge at any location on the surface. Surfaces shall abut flush with adjacent materials.

3.04 ADJUST AND CLEAN .1 Carefully clean all stone removing all dirt and debris from all surfaces.

.2 Remove and dispose of off site all debris as a result of work in this section.

Page 42: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Miscellaneous Stone Work Section 02517Triangle Park Page 6PS10074

END OF SECTION

Page 43: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 1 PS10074

1.00 GENERAL 1.01 GENERAL REQUIREMENTS

.1 Refer to Division 1, General Requirements.

.2 All contract documents form an integral part of this section.

1.02 RELATED WORK .1 Planting, Trees, Shrubs and Ground Covers: Section 02920

1.03 DESCRIPTION

.1 Work Included: Furnish all equipment, materials, trenching, backfilling, labour and services

necessary for the complete design and installation of the entire Permanent Automatic Remote Irrigation. Note: new irrigation system to tie into existing waterfront irrigation system, some sections in this specification will therefore not be applicable, but have been retained for reference only.

System to include: .1 Permanent Automatic Remote Irrigation System, including spray heads and

emitters. .2 Moisture sensor(s), controls and miscellaneous equipment .3 Complete system maintenance and operation for ninety (90) days after Substantial

Performance. 1.04 DEFINITIONS

.1 For the purpose of this specification and project the following terms and definitions shall be used; .1 Engineer – City of Vancouver .2 Permanent Automatic Remote Irrigation System installed underground as per this

specification.

1.05 SITE VERIFICATIONS

.1 The Contractor is to verify site measurements and irrigation coverage, and unless deficiencies are identified by the contractor and an amendment is made to the Contract Document prior to the quotation date, the Contractor accepts full responsibility to deliver the intended performance of the system at no additional cost to the City of Vancouver.

.2 If any conditions are subsequently observed on site that will impair proper and intended uniform irrigation coverage, notify the Engineer as soon as possible, and inform what the impairment is and its resolution.

.3 Do not proceed with any work that would yield unsatisfactory coverage as it will not be accepted.

Page 44: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 2 PS10074

1.06 QUALITY ASSURANCE

.1 All irrigation design and installation work shall be done by an experienced and competent Irrigation Contractor having the capabilities and personnel necessary for all phases of the work specified.

.2 The Irrigation Contractor and irrigation designer shall be a member in good standing

of the Irrigation Industry Association of British Columbia (IIABC) and have met the qualification standards currently applied to contractors by that organization.

.3 The Contractor and designer must provide proof of membership, and shall provide

proof of having worked in the industry for a minimum of five (5) years and provide a list of clients for whom similar sized irrigation projects have been satisfactorily completed.

.4 The acceptance of experience and work history rests solely with the City of

Vancouver.

.5 A standard manufacturer’s warranty is required for all irrigation equipment outlined in this specification. Refer to the General Conditions.

.6 The Contractor is to verify that all pipe, fittings, primers and cements are

compatible for proper installation. .7 Obtain field assistance from pipe manufacturer/supplier as necessary to ensure

correct installation and adhesive techniques are used on joints. .8 Do not cement pipe and fittings under wet or muddy conditions. Follow the

manufacturer’s recommendations for material use.

1.07 CONTRACT DRAWINGS

.1 Irrigation design build drawings prepared by irrigation contractor to accommodate all soft landscaped areas as noted on plans. Drawings must be approved by City of Vancouver before work is started.

1.08 SYSTEM DESIGN

.1 Design Criteria: The irrigation system shall apply a consistent, even, measurable amount of water to the landscape over a prescribed period of time to satisfy the following conditions;

.2 Head to Head Coverage: The maximum spacing of the spray heads shall be equal to

the radius throw with appropriate allowance for wind as required. In the case of drip line head to head coverage indicates emitter to emitter.

.3 Sprinklers:

.1 Selection of pop-up or riser style sprinklers must consider safety, maintenance, risk of vandalism and appearance on the site.

Page 45: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 3 PS10074

.2 Pop-up riser height locations must consider the related plant material, its growth potential and interfering landscape features in design of system.

.3 Sprinklers shall be suitably adjustable and located to ensure water spray is kept within the landscaped area and minimize overthrow.

.4 Pipe:

.1 Velocity of flow in any pipe shall not exceed 1.5 metres per second (5 feet per second).

.2 Review changes in existing and proposed site elevations to ensure system design minimizes low head drainage.

.3 Ensure pipe sizing and routing of system allows for required pressure under all site circumstances. Pressure variations within the lateral lines are to be kept to a minimum.

.5 Zone Designation:

.1 All sprinklers and drip irrigation lines are to be grouped into zones of equal precipitation rates which are matched through the arcs of coverage.

.2 Consideration shall be given to the irrigation type (spray versus drip) type of plant material, location on site, exposure to sun, slope conditions and soil conditions.

.3 Sprinklers and drip irrigation areas shall be zoned separately. Lawn, shrub or tree planting areas shall be zoned separately.

.4 Pressure variation from the first to the last head must not exceed 15%. .6 Controls:

.1 Controllers shall be CSA approved, suitable for their mounting location and sufficiently flexible to allow for optimum operation of the designed system.

.2 Valves shall meet the pressure and flow requirements of the zone controlled.

.3 Moisture sensor system and controls as part of overall automated remote design. .7 Pressure Control:

.1 The design shall include suitable regulation of the water pressure throughout the irrigation system.

.2 The pressure at every head shall be within the range of the manufacturer’s recommended head/nozzle pressure.

.8 Winterization:

.1 All water connections shall be designed to ensure they are safe from winter freeze damage.

.2 Ensure a minimum of two (2) blow out points and blow out tees are included in system design. All blow out locations shall be within 30 metres (98’-0”) of a vehicle access point.

1.09 DESIGN DRAWINGS

.1 Irrigation design build drawings shall meet the standards of the Vancouver Park

Board and indicate the arrangement of system.

.2 Contractor shall provide five (5) sets of irrigation design drawings for Engineer and City of Vancouver review a minimum of fourteen (14) days prior to the start of

Page 46: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 4 PS10074

work. .3 Design Drawings: As a minimum requirement irrigation design drawings shall

contain: .1 Location, type and manufacturer of all sprinkler heads and drip lines. .2 Location and size of main line, all lateral lines and sleeves. .3 Clear graphic indication of sprinkler spray pattern and sprinkler spray

radius. .4 Location and designation of all valves. .5 Location of all quick couplers and blow out tees. .6 Location and manufacturers model number of irrigation controller,

moisture sensor control and moisture meter locations. .7 Shop drawings of weather proof irrigation control cabinet and pedestal

stand. .8 Depth of Pipe

.4 Full and complete head to head irrigation coverage is required for Permanent

Automatic Remote Irrigation. 1.10 SUBMITTAL AND INSTRUCTIONS

.1 Maintenance Data and Operation Instructions/Manual: Prior to and as a condition of Substantial Performance, submit to the Engineer three (3) copies of an operating and maintenance manual containing operational information for all operating components, cleaning and lubrication schedules, overhaul/adjustment schedules and similar maintenance operations. Each manual shall be bound in a three ring binder and marked with the name ‘SEFC Site Servicing & Public Realm Olympic Village’ with the date of Substantial Performance.

.2 As-Built Drawings: As a condition of Substantial Performance, submit with the

operating and maintenance manuals, a suitably scaled reproducible copy of the "as-constructed" installation of the system. The drawings shall be accurately drawn, showing all components of the irrigation system as installed, with clear measurements provided from identifiable reference points (in metric). As-Builts shall include invert depths and off-set measurements.

.3 Maintenance Devices: Submit to the Engineer two (2) sets of all special tools, keys,

and equipment that is required to commission the system or as otherwise specified in the Contract Documents.

.4 Commissioning: Instruct the Engineer in the complete operating and maintenance

procedures for this system. This instruction shall include but not be limited to showing the relative timing differences between zones of different precipitation rates and a schedule of run times suggested for various weather conditions.

1.11 DELIVERY AND STORAGE

Page 47: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 5 PS10074

.1 Deliver and store materials in new condition, in unopened containers and protect until installed.

.2 Deliver, handle and store pipe and fittings so as to avoid gouging, bending or cracking.

1.12 SITE CONDITIONS

.1 Existing Conditions/Underground Services: The Contractor is to verify the existence and location of all on - site utilities and underground services by hand digging or use of an electronic toning device or M-Scope. Mark the location of all buried cables, conduits, pipes etc., prior to any trenching. Cooperate with City of Vancouver and utility companies to keep their respective utilities in operation. Notify Engineer immediately for directions as to the procedure should any piping utilities be affected during excavation.

.2 Site Preparation: Prior to the work of this Section, the Contractor is to carefully

inspect any installed work of other trades or contractors and verify all such work is complete to the extent that this work may properly begin.

.3 Field Measurements: Make all measurements in the field to confirm that the design

meets the on site conditions to ensure the precise fit of items in accordance with the original design and performance criteria.

.4 Discrepancies: In the event of a major discrepancy, errors or conflicts between the

drawings and the actual site conditions, immediately notify Engineer as to procedure before proceeding with work.

.5 Repair to Underground Services: Repair or replace all damage to underground

services caused by the work of this Contract. Damage to services that are shown on the drawings or have been brought to the Contractor’s attention in the field prior to commencement or during construction of the work shall be repaired in its entirety at the Contractor’s expense.

.6 Damage to services that were clearly unforeseen /unknown of existence (provided

that all reasonable measures were undertaken by the Contractor to ascertain the existence of these services) shall be repaired in accordance with the Changes clause of the General Conditions. Notify Engineer of damage immediately.

1.13 PROTECTION

.1 Protect existing buildings, equipment, sidewalks, landscape reference points, monuments, markers and other completed work. Make good any damage resulting from work of this Contract at no expense to the City of Vancouver.

.2 Do not park vehicles on the site in areas where the work will be undertaken without

express written consent of the Engineer. Utilize only such equipment/vehicles essential for construction of the system.

Page 48: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 6 PS10074

.3 Trenching and other excavations for vaults, valve boxes etc. are not to be left open during non work hours of operation unless they are protected to current Worker’s Compensation Board Standards. Cover, mark, and/or protect as necessary all open excavations to ensure worker and public safety.

1.14 GUARANTEE & WARRANTY

.1 Provide one (1) copy of a written Guarantee on corporate letterhead signed by the company owner or signing officer for all workmanship and materials for one year from date of Substantial Performance. Make all corrections, adjustments and maintenance operations required as a result of failure of the irrigation system to perform due to the work of this Section.

.2 Manufactured products, including but not limited to irrigation heads, drip lines,

moisture sensors and controls, quick couplers, controllers, valve boxes and valves, shall be warranted as per the manufacturers’ standard guarantee period or a minimum of one year, whichever is greater.

1.15 EQUALS

.1 All items as specified herein and on the drawings or pre-approved equals. .2 Alternative equipment may be considered for inclusion in this project. These

proposed alternatives shall meet or exceed the specifications in performance, flow, pressure loss and all other important characteristics of the original equipment specified. The alternative equipment shall be of good quality construction, with a proven record of trouble free performance and low maintenance, on projects of similar size and scope. In addition, the alternative equipment must be available from a local distributor with a well stocked inventory of all readily available spare parts. The alternative equipment must have a comparable warranty to the original equipment specified and must not compromise the intent of the original design.

.3 Alternative equipment must be compatible with all other remaining system

components and must be agreed upon by both parties to the contract. In the case where an Engineer represents the City of Vancouver, that Engineer may agree on its behalf.

.4 Submission guidelines for approval of equal products must be strictly adhered to or

no consideration for approval as equals will be considered. 1.16 SEQUENCE

.1 Coordinate and ensure the installation of all sleeving and irrigation piping as required under all paved surfaces and through planter walls as noted on the drawings unless otherwise approved by City of Vancouver.

Page 49: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 7 PS10074

.2 The Contractor is to verify the location of the municipal water supply connection point for the automatic irrigation system. Coordinate as necessary.

.3 The Contractor is to verify the location and have installed the electrical conduit for

the low voltage wire from the controller location to point below grade adjacent to controller only.

1.17 INSPECTION

.1 Prior to commencement of any work related to this irrigation project, the contractor is required to make contact with the designated Engineer authorized to make project decisions.

.2 All work is to remain uncovered for inspection of workmanship and materials. Notify

Engineer a minimum of forty-eight (48) hours prior to required inspections. Failure to provide such notice and closing in of uninspected work is sufficient grounds for withholding any payments due to the Contractor. All buried work that has not been inspected and approved will have to be totally uncovered.

2.00 PRODUCTS

2.1 PIPE AND FITTINGS

.1 Plastic Pipe: Pipe shall be Schedule 40 polyvinyl chloride (PVC) conforming to ASTM D1784-97, D1785-96B and/or CSA B137.3-93 standards.(ASTM F441/441M-97 or CSA B137.6-96 for CPVC). It shall be extruded, virgin, high impact pipe conforming to Cell Class 12454-B, solvent weldable with belled ends, and continually and permanently marked showing manufacturer's name or trademark, type of material, pipe size and pressure rating.

Size and Classes as follows: Size Class 19 - 25 mm. diameter Schedule 40 PVC 31 -100 mm. diameter Schedule 40 PVC Mainlines, any size Schedule 40 PVC

.2 Plastic Pipe Fittings:

.1 GSR Schedule 40 PVC conforming to ASTM D-2466-97 (and F438-97 for CPVC) standards and be of the same material as the pipe. Fittings shall be designed for solvent welding to PVC pipe except where valves, risers, etc. require threaded joints.

.2 Fittings for PVC pipe shall be 1/2 to 2/3 interference fit to ensure a fully sealed joint. Provide a minimum two (2) times depth of insert of fitting clearance between fittings to allow for repair. No exception.

.3 All threaded connections shall be joined with minimum three (3) wraps Teflon Tape: no substitutions accepted.

.4 Threaded nipples shall be Schedule 80 PVC and be manufactured from the same

Page 50: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 8 PS10074

material specified for the pipe. .5 Threaded connections of PVC to metal shall have female threads on the PVC and

male threads on the metal. 2.2 PRIMERS AND PIPE SOLVENTS

.1 CSA approved type as recommended by pipe manufacturer for the temperature and conditions under which the work is being performed. Deliver in sealed containers clearly marked with name of manufacturer and lot number. Use of non CSA approved specialty primers or solvents such as “Wet R Dry” are not acceptable.

2.3 SLEEVES

.1 Sleeves; at locations noted on the drawings. Sized, minimum two (2) nominal pipe sizes larger than any irrigation lateral line to be carried, minimum three (3) minimal pipe sizes larger if carrying a mainline: .1 Shall be cast iron piping under all designated vehicular access routes. .2 Shall be Schedule 40 PVC under all other paved surfaces, through walls, and

through or underneath footing walls and to irrigated island. 2.4 VALVES AND VALVE BOXES

.1 Solenoid Valves: First quality of the types indicated on drawings, and sized the same diameter as the pipe they control. Integrally Regulated solenoid valves are not acceptable unless site topography deems their use necessary and specific approval by Engineer has been given. Integrally Regulated solenoid valves will not be considered as pre-approved equals.

.2 Quick Coupler Valves: Brass, 19 mm. Install quick coupler at location shown on

drawings. Accommodate quick coupler in valve box or separate enclosure, as required, and install in active, non-solenoid valved line. Ensure top of quick coupler valve is installed a maximum of 50 mm. below lid of valve box to allow easy key operation.

.3 In Line Filter: Molded impact resistant nylon body with glass reinforced nylon locking

ring. Pressure range 0.3-9.8 bars (5-142 psi). Stainless steel filter element of 150 mesh. Toro Plastic Y or approved equal.

In Line Filter Sizes 25mm (1”) Valve Toro Plastic Y Filter ALFS 10150-L Max Flow Rate 35 gpm 38mm (11/2”) Valve

Toro Plastic Y Filter ALFS 15150-L Max Flow Rate 80 gpm

.4 Pressure Regulator: Molded impact resistant nylon body. Toro and Netafim as

indicated or approved equal.

Pressure Regulator 25mm (1”) Valve Toro PR25 HF

Page 51: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 9 PS10074

38mm (11/2”) Valve

Netafim 32PRV1.5-35V2K

38mm (11/2”) Valve

Netafim PRV2-435V2K

.3 Isolation Valves: Cast Bronze gate valves with non-rising stems: R&W Model 280 or

pre-approved equal for 13 mm up to 63 mm diameter. .4 Bronze Ball Valves: Jones J1949SG-50 mm, 90E Shut off curb stop type or pre-

approved equal. .5 Valve Boxes: Shall be green plastic irrigation boxes complete with captive lock bolt

cover; sized to suit valves and other components with adequate room for operating and maintenance access:

1 – 2 Valves 3 Valves NDS - 113 BC (14" x 19") 1-2 valves NDS - 117 BC (17" 20") 3 valves Carson 1419 (14" x 19") 1-2 valves Carson 1320 (13" x 20") 3 valves

2.5 SPRINKLER HEADS

.1 First quality of the types indicated on drawings.

.1 Large Open Area/Passive Lawn Heads: The full or part-circle sprinklers shall be gear driven rotary types. Part-circle

models shall be adjustable from 40 degrees to 330 degrees The sprinkler shall be capable of covering designed radius at x pounds per square inch pressure with a discharge rate of designed litres per second. Water distribution shall be via one modular nozzle mounted and locked onto a 35 mm diameter nozzle turret. The dual nozzles shall elevate 60 mm when in operation. Radius reduction shall be adjustable up to 25%, by means of a stainless steel radius adjustment screw accessible from the top of the nozzle when the sprinkler is properly installed. The body and cap of the sprinkler shall be injection molded from ABS, a non-corrosive, impact-resistant, UV-resistant, heavy-duty plastic material. The sprinkler shall have a plastic filter screen sized to prevent entry of foreign material to the nozzle. All components shall be removable from the top of the sprinkler case. The sprinkler shall have a single piece riser/body seal that regulates flushing during pop-up and retraction to clear any debris from around the riser, and a heavy-duty stainless steel spring to ensure positive retraction. The seal shall be a single piece injection molded from Santoprene, a synthetic rubber. The sprinkler shall be capable of accepting any one of 24 nozzles. The nozzles shall be colour-coded and available in three trajectories. Rotation shall be accomplished by a sealed, oil-packed gear-drive assembly isolated from the water supply and driven by a variable stator that maintains a constant speed of rotation with all nozzles. The variable stator shall require no adjustments when changing nozzles. The sprinkler shall employ a modular, interchangeable nozzle technology. Any individual nozzle shall be easily removed, installed and locked if field adjustment

Page 52: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 10PS10074

is required. A standard pop-up model shall be available with a check valve which shall maintain 3000 mm of elevation change. A lavender effluent water use indicator must be available and able to be fitted into the nozzle. A 19 mm NPT plug shall be provided with all side inlet models to plug the unused inlet.

Hi-Pop Version The sprinkler shall be of a pop-up design with an overall height of 413 mm, a body diameter of 60 mm and a pop-up stroke of 263 mm. The sprinkler shall be capable of installation at grade level and shall have a 19 mm NPT female inlet. Lawn Version The sprinkler shall be of a pop-up design with an overall height of 175 mm, a body diameter of 75 mm and a pop-up stroke of 75 mm. The sprinkler shall be capable of installation at grade level and shall have a 19 mm NPT female inlet. Commercial Version The sprinkler shall be of a pop-up design with an overall height of 175 mm, a body diameter of 75mm and a pop-up stroke of 75mm. The sprinkler shall have a standard locking cap to provide vandal resistance. It shall be supplied with a standard check valve which shall hold 3000 mm of elevation change. The riser assembly shall be encased in stainless steel for increased vandal resistance and durability. The sprinkler shall be capable of installation at grade level and shall have a 19 mm NPT female inlet. Shrub Version The sprinkler shall be of shrub design with an overall height of 128 mm and a base diameter of 44 mm. The sprinkler shall be capable of mounting above grade and shall have a 13 mm or 19 mm NPT female threaded inlet.

.3 Small Lawn Areas/Shrub Bed Areas:

The nozzles shall be the fixed spray type designed to provide matched precipitation rates from 1500 mm to 4500 mm radius. The nozzles shall have a colour-coded base that provides easy identification of the radius and/or type of nozzle in use. The nozzle top shall provide an alphanumeric indication of the radius and arc of the nozzle as well as a graphical indication of the arc. The nozzle shall be available with a pressure compensating device capable of maintaining 207 KPa with operating pressures from 207 KPa to 470 KPa. Non-pressure compensating nozzles shall be capable of accepting a compensating device to provide this feature at any time. The nozzle shall be capable of 25% radius reduction and complete shut-off via a stainless steel screw accessible from the top of the nozzle. The nozzle shall have male threads. The nozzles shall be accompanied by a colour-coded screen appropriately sized to prevent entry of foreign materials into the nozzle. A secondary 200-mesh stainless steel screen shall accompany all nozzles with a 207 KPa flow rate less than 1.89 litres per minute. The nozzle shall be injection molded from ABS, a non-corrosive, impact resistant, UV-resistant heavy-duty plastic material. The accompanying primary screen shall be injection molded from polyethylene, a non-corrosive plastic material. The accompanying secondary screen shall be stainless steel.

Page 53: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 11PS10074

2.6 DRIP IRRIGATION

.1 Subsurface Irrigation Drip Line:

.1 Pressure-compensating, self cleaning, polyethylene irrigation drip line.

.2 Drip line shall have a 18mm (0.630 inches) outside diameter, 15.5mm (0.540 inches) inside diameter and wall thickness of 1.5 mm (0.059 inches).

.3 Inline emitter shall be welded to the inner circumference of the polyethylene tubing. The inline emitter shall have dual outlet ports, 180° apart.

.4 All components shall be of the same manufacturer and shall be marked with

the manufacturer's name and identification, in such a position that they can be identified without being removed from the system. Acceptable products inculeAqua-line by Aquarius A18-2 and 4 -12 or Toro RPG 212E coil length to suit with root guard or approved equal.

Subsurface Irrigation Drip Line Emitters at 300 mm (12”) on center spacing 4.5 litres per hour

(1.02 GPH)

.2 Drip System Run Indicator:

.1 100mm (4”) pop up head with swing arm and miscellaneous components. Decommission nozzle, paint head DayGlo Orange. One head per zone.

.3 Air/Vacuum Relief Valve: Size to suit, polypropylene valve, tee and cap, Toro Air

Release Valve or approved equal. .4 In Line Filter: Molded impact resistant nylon body with glass reinforced nylon locking

ring. Pressure range 0.3-9.8 bars (5-142 psi). Stainless steel filter element of 150 mesh. Toro Plastic Y or approved equal. In Line Filter Sizes 25mm (1”) Valve Toro Plastic Y Filter ALFS 10150-L Max Flow Rate 35 gpm 38mm (11/2”) Valve

Toro Plastic Y Filter ALFS 15150-L Max Flow Rate 80 gpm

.5 Pressure Regulator: Molded impact resistant nylon body. Toro and Netafim as

indicated or approved equal. Pressure Regulator 25mm (1”) Valve Toro PR25 HF 38mm (11/2”) Valve

Netafim 32PRV1.5-35V2K

38mm (11/2”) Valve

Netafim PRV2-435V2K

Page 54: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 12PS10074

.6 Moisture Sensor: Self contained unit meeting the following performance criteria;

.1 Shall detect volumetric moisture content temperature and conductivity in various media based on a time-domain transmissometry (TDT) system.

.2 Successive fast transitions are injected into a transmission line immersed into its surrounding growing medium, and a characteristic received waveform is digitized and analyzed by a continuously sampling multiple received waveforms at short time intervals.

.3 The Moisture Sensor shall be capable of detecting propagation delay within a resolution of 25 picoseconds.

.4 The Moisture Sensor shall be constructed with one (1) printed circuit board covered in a waterproof epoxy and encased in ABS plastic case.

.5 Two (2) probes connected to the ABS case shall be rust resistant type 3-16 stainless steel rods.

.6 The Moisture Sensor shall have three #14 or larger direct burial wires, one red, one white and one black for connectivity. All splices to the 3-wire set must use 3M, DBY (direct burial) connector kits with grease caps or equivalent.

.7 The Moisture Sensor shall have built in lighting arrestors.

.8 All metal components of the Moisture Sensor shall be electrically isolated to prevent galvanic corrosion.

.9 Moisture Sensor shall be compatible with Soil Moisture Controller. Acceptable products include L.R. Nelson Irrigation 8701 EX PRO XTRA Moisture Sensor, distributed by Andrew Sheret Limited, Richmond BC 604.278.3766 or pre-approved equal.

.7 Soil Moisture Controller

.1 Soil moisture controller shall perform the following functions; .1 Set, maintain and monitor any desired moisture level. .2 Incorporate a bypass switch that allows a traditional timed controller to

bypass the soil moisture controller and run the system. In bypass mode the soil moisture sensor shall continue to take moisture readings, but will not inhibit the irrigation timer from running the system.

.3 Suspend controller activity when soil moisture levels in growing medium are meets or exceeds the prescribed moisture settings.

.4 Shall interface and operate with a traditional zone/ timer irrigation controller.

.5 Allow for a fully adjustable and programmable soil moisture level threshold.

.8 Soil Moisture controller shall provide the following display functions; .1 Current soil moisture reading displayed as Volumetric Water Content (VWC) 0%

to100%. .2 Soil temperature in degrees Fahrenheit or Celsius. .3 Displays Soil Conductivity in dS/m. .4 Moisture control ON/OFF switch with ‘Watering On Hold’ indicator. .5 Operating and Physical Specifications

.1 25 Volts AC at 12 watts.

.2 Complete with a minimum of 450mm (18”) cable for power and timer

Page 55: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 13PS10074

connection. .3 Operating Temperature Range -20ºC to 70ºC, Survival Temperature Range: -

40ºC to 85ºC. .4 Dimensions: Width: 114 mm (4 1/2"), Height: 60mm (2 3/8") Depth: 2.5mm

(1"). .6 Moisture Controller shall be compatible with Soil Moisture Sensor. Acceptable

products include 8701 EX PRO XTRA Moisture Sensor by L.R. Nelson Irrigation, distributed by Andrew Sheret Limited, Richmond BC 604.278.3766 or pre-approved equal.

.9 Zone Valve Adapter

.1 Heavy duty construction, water proof, sealed communication device capable of being installed within a valve box (maximum run length 15M (45’).

.2 Acceptable products include L.R. Nelson Irrigation 8701 DC 4 zone valve adapter distributed by Andrew Sheret Limited, Richmond BC 604.278.3766 or approved equal.

.10 Lamicoid Tags

.1 3mm (1/8”) thick, uv resistant, three ply modified acrylic, exterior tag.

.2 Provide contrasting colour, red top surface contrasting black core, glossy finish.

.3 Plastic zip strap fastener.

2.7 CONTROL AND COMMON GROUND WIRING .1 14 gauge insulated single strand TWU copper of a type approved by the governing

electrical authority and by CSA for direct underground burial, sized to suit load, and distances. Maximum voltage loss shall be five percent (5%). Insulated cover colour for control/signal wire shall be consistently applied throughout the system, and white conductor shall always be the common wire.

.2 Confirm control wire size with the manufacturer of zone control valves to ensure wire is sized to the length of its run and in compliance with the current Canadian Electrical Code, as amended by the Province of British Columbia and the City of Vancouver.

.3 Wire, breakers, conduits and related materials that comprise the electrical supply to the controller shall be CSA approved, and installation shall be pursuant to the Canadian Electrical Code, as amended by the province of British Columbia and the City of Vancouver.

2.8 MISCELLANEOUS MATERIALS

.1 Electrical Tape: All weather, black plastic 19 mm wide, a minimum 0.1778 mm thick, or use approved equal.

.2 Electrical Wire Splices shall be made watertight with CSA approved watertight connectors. No splicing of wires shall occur unless located in an accessible box and shown on the As-Built Drawings.

.3 Thread Lubricant: Type manufactured for plastic to metal connections such as Teflon tape or Permatex 2.

Page 56: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 14PS10074

2.9 AUTOMATIC CONTROLLERS

.1 Automatic Controllers; CSA Approved capable of providing all necessary features for programming the irrigation system design.

Specific Features:

.1 Capable of manual and automatic operation.

.2 Independent stand-alone operation with 16 programs

.3 Ready for central control via radio communication.

.4 Must be capable of supporting 1 flow meter input to monitor real time flow rates, alarming for:

.1 High flow, shutdown station(s)

.2 Low flow, shutdown station(s)

.3 Unopened, shutdown station(s)

.4 Burst main, shutdown station(s)

.5 Main leak, shutdown station(s) .5 Must be capable of supporting a connection of any digital sensor to force a

“wait response”. .6 Electrical surge protection. .7 Independent and remote station programming. .8 Water adjustment factor by using percentage scale, 0-999% in 1% steps. .9 Selective station operation, sequential station operation, single station

operation. .10 Stop time prevents irrigation past a specific deadline entered. .11 Program by time, volume or time and flow .12 Cycles per program 1-98, 99=infinite. .13 Electrical characteristics:

.1 CSA approved, 120/240 VAC, 50-60 Hz @ 30 VA.

.2 Capable of not less than STATED independent stations; allowing for variation due to size of system, spares and future expansion of the system/or requirements of proposed system as requested by VPB.

.14 Options to include: Rain Sensor Capability. Rain Sensor By-Pass Capability.

.15 Operational key pad(s) shall be supplied with each controller.

.16 Controller to be radio controlled.

.17 Controller must allow minimum allowance: one (1) extra output for activation hydrometer (when specifying number of stations on controller one station must be designated for activation of hydrometer).

2.9 IRRIGATION CONTROL SYSTEMS CABINET

.1 Stainless steel, approved weatherproof lockable metal cabinet to CSA Standards grounded by means of ground rods or plates.

.2 Sized to incorporate all irrigation control components including but not limited radio controller, keyboards, moisture sensor controls, irrigation controls, line voltae duplex receptacles, antenna connections, cable and wiring.

.3 Provide shop drawings for Engineer review prior to fabrication.

Page 57: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 15PS10074

2.10 BACK FLOW PREVENTER AND SERVICE VAULT (See Vault Drawing)

.1 Wilkins Zurn or Watts Series 007M1QT double check Back flow Prevention Assembly, complete with gate valves, or pre-approved equal. All back flow preventers larger than 50 mm should be the approved type or pre-approved equal. All back flow prevention devices to be CSA and BCWWA approved and conform with all current Municipal cross connection control standards as applicable.

.2 All back flow prevention devices to be located in precast concrete vaults complete

with concrete bottom. Size as shown on drawings supplied by AE Precast Concrete Products or equivalent. Vaults to be supplied complete with double hinged, galvanize steel checker plate locking covers, with lock and hasp assembly to be recessed below top of lid. Lids are to extend the full length of the service vault to allow for unimpeded access into the vault. Each lid is to be a maximum weight of 27 kg each. Install service vault flush with finished grade.

.3 The piping and valve assembly within the vault must be adequately supported and

braced (minimum two (2) riser type supports and two (2) side wall supports), with adjustable supports, complete with riser, pipe clamps, galvanized metal and stainless steel bolts.

.4 All piping inside the vault is to be brass or pre-approved equal, and is to extend a

minimum of 300 mm outside the vault on the downstream side and a minimum of 150 mm on the upstream side.

.5 The top of the piping will be 600 mm from the top of the lid. The service vault will

be filled with 25 mm drain rock to within 300 mm of the bottom of the pipe. Contractor to install a 100 mm PVC drain pipe, complete with a backwater valve. The vertical section of the drain pipe is to be perforated and terminating with a grate that is flush with the surface of the drain rock. The drain pipe is to run (minimum of .5% slope) into a catch basin or approved drainage system.

.6 PVC connections to brass outside the vault on the downstream side are to be made

with schedule 80 PVC female adapters. .7 All piping to vault from city service is to be copper or pre-approved equal. Inside

vault piping to be brass including swing joints for blow down quick coupler, or pre-approved equal, see drawing for sequence of mechanical devices.

2.8 PRESSURE REDUCING VALVE

.1 As required, Watts Series 223 sized to system: Range 173 KPa to 470 KPa or pre-approved equal.

Page 58: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 16PS10074

2.9 BLOW OUT TEE .1 Brass, 19 mm: size or pre-approved equal on triple swing joint.

2.10 FLOW METER

.1 Hydrometer: Shall combine a turbine type water meter and a diaphragm actuated, solenoid controlled valve mounted in a single globe style valve body. The meter shall power a gear mechanism that activates a reed switch that transmits a pulse at a pre-determined amount of flow. The unit shall include integral flow guides to eliminate the need for straight pipe allowances before and after the valve. The hydrometer shall be capable of sending electronic flow data to a compatible irrigation controller to enable it to be integrated within an overall computer controlled system and shall be Bermad Model No. 910-P or pre-approved equal. Four wires, 2 coloured and 2 white wires shall be installed to the controller from the Bermad.

2.11 Tie Down Stakes

.1 12 gauge galvanized steel rod pre bent to shape Rainbird TDS-050 with bend or approved equal.

2.12 Warning Tape

.1 Non adhesive polyethylene yellow tape with black letters marking ‘Caution’. Tyco Industries or approved equal.

2.13 Cable Ties

.1 Nylon, self clasping, 200mm (8”) fasteners manufactured by Ideal Industries or approved equal.

3.0 EXECUTION 3.1 IRRIGATION SYSTEM LAYOUT

.1 Establish and coordinate exact locations of lines, valves, spray heads and drip lines, with planting locations to avoid conflicts and damage to plants during installation. Stake locations for approval by Engineer. The Contractor is to verify grades for all components.

.2 Layout the piping, spray heads and drip line locations with flags or short lengths of

pipe, in accordance with the drawings, and obtain the approval of the Engineer before proceeding.

.3 Colour code flag layout to represent ; .1 Drip Irrigation Areas separate any other type of irrigation area. .2 The layout shall be in accordance with the approved design drawing.

Alternative layouts from those indicated on approved design drawings as a result of on site conditions shall be reviewed and approved by the Engineer in the field. The resulting revisions shall be indicated on As Built drawings.

3.2 TRENCHING IRRIGATION AREAS

Page 59: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 17PS10074

.1 Open excavation shall be carried out in a safe and orderly manner and in accordance with the requirements of the Workers' Compensation Act of B.C. Approved shoring shall be used where required for safe working conditions.

.2 All trenches are to be hand or machine excavated. Pulling pipes is not acceptable.

All trenches shall be dug on the alignment and to the depth required as shown on the drawings and as stated herein. In any event, the water main service pipe shall be buried to a depth of at least 750 mm below ground. The irrigation main and zone lines shall be buried to a depth of at least 400 mm below the surface measured to top of pipe. Trenches are to be straight with uniform slopes to the bottom of all trenches.

.3 Where the pipes are to be laid in sub-surface material the trench shall be excavated

to a depth at least 100 mm below the bottom of the pipe elevation. The trench shall be backfilled with at least 100 mm of sand passing a 5 mm sieve and be carefully compacted by hand.

.4 Prior to backfilling, all lines, valves and fittings shall be inspected by Engineer . .5 Trenches shall be at least 300 mm away from paving stones or other hard surfaces to

avoid undermining such surface or its edge retention. .6 Backfilling shall take place in an orderly fashion.

.1 Where the line is within an enclosed plant bed or sod lawn area and beds within the growing medium layer, the growing medium shall be placed over the pipe and be carefully tamped by hand to achieve compaction equivalent to the surrounding area.

.2 Where the lines bed on or within the native soil or sub-surface fill, backfilling to a depth of 100mm over the top of the pipe shall be carried out with sand passing a 5 mm sieve and be carefully compacted by hand. .1 The remainder of the backfill to finish grade shall be with suitable material,

free of any rocks over 25mm in diameter and other similar materials that could damage the pipe or create unusual settling conditions.

.7 Compact the growing medium to the same density as the native material in the

trench sidewalls to prevent differential settlement. .8 Fill piping with water at approx. 0.172 MPa during backfill operations. .9 Contractor is responsible to repair all trenches which have settled below the

adjacent grade for a period of one (1) year from date of Substantial Performance. .10 Material refuse such as pipe pieces, excess wire, rags, fittings or PVC cement

canisters shall not be left as a part of backfill in any trenches. 3.3 INSTALLATION OF PIPING

Page 60: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 18PS10074

.1 Layout the piping system for Permanent Automatic Remote in accordance with drawings. Route piping to take into account site elevation changes and to minimize low head weeping subsequent to shut-down.

.2 Permanent Automatic Remote Irrigation shall be directly over and parallel to another

irrigation line or service line of any other trade. Ensure minimum horizontal and vertical clearance requirements as dictated by Canadian Electrical Code for all piping installations near any electrical conduit/service.

.3 Where possible, main supply lines for Permanent Automatic Remote Irrigation areas

may occupy the same trench as sprinkler lines, provided a minimum horizontal clearance of 150mm is maintained. Multiple lateral lines may occupy the same trench provided that a min. of 50mm horizontal clearance can be maintained and the pipes are all on the same plane.

.4 Install pipes in long ‘S’ curves to allow for expansion and contraction. Ensure

longest mainline straight run is installed and sized to compensate for potential surges in system.

.5 Comply with all the manufacturer’s printed data and recommendations regarding

pipe cutting, cleaning, beveling, deburring, fitting preparation, primer and cement application and correct joining techniques. Ensure that all joints are properly fused and bonded and that all curing times given site climatic conditions are fully observed prior to testing or charging of piping system.

.6 Install yellow warning tape approximately 250mm above all Irrigation mainline runs

with low voltage wiring located below piping. Warning tape on Irrigation lateral lines is not required.

3.4 INSTALLATION OF EQUIPMENT FOR PERMANENT AUTOMATIC REMOTE IRRIGATION SYSTEM

.1 General; Install all equipment as shown on approved design build plans and details, using appropriate connectors, cements, lubricants, solvents for each type of joint.

.2 Automatic Controls;

.1 Ensure controller(s), moisture sensors and miscellaneous control equipment is located to allow for maximum viewing of the system operation.

.2 Install all control equipment at location shown on constructions drawings.

.3 Install Irrigation Control Systems Cabinet as per design build detail at 1500 mm height above surrounding finished grade at location(s) shown indicated on approved design build drawings.

.4 Sequence station valves in a reasonable fashion to allow for proper testing of all system operations in an orderly and sequential manner.

.3 Control Wiring;

.1 Protect control and common wiring by installing beside or beneath irrigation mainline.

Page 61: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 19PS10074

.2 Obtain approval from Engineer or for all wiring to be installed in separate trenching and protect with Yellow Buried Wire Warning Tape at a minimum of 76 mm above the wires.

.3 Leave additional 600 mm of each wire at each valve.

.4 Wrap conductors with electrical tape at 900 mm intervals.

.5 Make wire splices only in accessible valve boxes.

.6 Minimize the number of splices. As much as possible ensure that wire runs are continuous without interruption.

.7 Run control wiring from valves and connect to automatic controller.

.8 Install control wiring in conduit that extends 1000 mm horizontally from the vertical connection point of the controller, with the horizontal portion 600 mm below grade.

.9 Conduit to be a 50 mm diameter galvanized steel pipe with a sweep elbow from below grade to bottom of controller cabinet location.

.10 Ensure conduit clamped to mounting surfaces with conduit pipe clamps at 250 mm o.c. spacing or as detailed.

.4 Irrigation Heads;

.1 Install all irrigation heads on triple swing joint assemblies of the same size as the sprinkler inlet.

.2 All sprinkler heads to be installed a minimum 50 mm away from any hard surface. .3 Adjust all heads to 12 mm below finished grade for sod lawn, flush with finish

grade for all planted areas after approval of sod lawn and shrub beds by Engineer .

.5 Drip Irrigation;

.1 Install dripline AFTER THE INSTALLATION OF ALL PLANT MATERIAL. .2 Drip line to be set at a uniform depth of 75mm (3”) below the final finished grade

400mm – 450mm (16”-18”) on centre at a maximum of 100 mm (4”) from the edge of all planters.

.3 Install drip line supply header as per manufacturer's instructions. Ensure all open

ends are taped or plugged to prevent debris contamination of line. .4 Pin drip line in place with galvanized tie down stake at minimum 1200mm (4’-0”)

on centre. .5 Install drip line laterals to accommodate plant spacing and layout . .6 Interconnect drip line laterals while flushing system. .7 Ensure air/vacuum relief valve is installed at the high point of each zone. .8 Ensure all drip lines are looped to provide water from two directions to facilitate

flushing of drip line in the event of disruption or break in system. .9 Minor changes in drip line layout required as a result of on site conditions shall be

Page 62: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 20PS10074

made by the contractor at no additional cost to the owner. Ensure design coverage is maintained .

.6 Moisture Sensor

.1 Locate moisture sensor(s) as noted on drawings parallel to slope, at uniform depth of 75mm (3”) below the surface as per manufacturers instructions. Utilize care not to disrupt surrounding plant material.

.2 Label by number with lamacoid tag the serial number of moisture sensor. Serial number to be used in system programming.

.3 Moisture sensor within 15M (45’) of nearest valve shall act as the zone valve

adapter for that valve. .4 Sensor wiring to run within appropriately sized PVC conduit to TWB tie in at

main or lateral lines. .5 TWB to Moisture Sensor connection to be made within Carson 610 valve box.

.7 Zone Valve Adapters .1 Two (2) zone valve adapter module to be installed as per manufacturers

instruction at each valve location exceeding 15Metres (45’) from valve to valve. Zone valve adapter to be connected to TWB.

.2 Where valves are within 15Metres of each other the two (2) zone adapter shall

connect both valves to the TWB. .3 Record serial number of zone valve adapter. Serial number to be used in system

programming.

.8 Valve Boxes; .1 Install valves in valve boxes, allowing adequate space within boxes for proper

operation/servicing of each component. Keep the valve box clean and clear of all debris that may fall into it during construction/installation. Ensure a minimum 150 mm of 19 mm drain gravel is placed in the bottom of each valve box.

Additionally, ensure the following: .1 In all Permanent Automatic Remote Irrigation and areas the top of the valve

box is to be level and flush with grade, and located in shrub areas where possible.

.2 Irrigation valve boxes to be blocked (with brick or concrete pavers) so that

neither blocking or valve box rest on lateral or mainlines when supporting the weight of expected forces on the top of the box.

.3 Irrigation quick coupler valves to be installed within valve boxes in active,

non-solenoid valved line.

.9 Quick Coupler Valves: Install in valve box to allow for easy insertion and rotation of quick coupler keys, with the top of the Quick Coupler installed a maximum of 50 mm

Page 63: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 21PS10074

below the lid of the valve box, on swing jointed piping to provide sufficient “give” should a hose or line be pulled.

3.5 TESTING AND INSPECTION

.1 Closing in Uninspected Work: .1 Obtain approval of Engineer before backfilling any sections of the Permanent

Automatic Remote Irrigation and . .2 Any work closed in before inspection will be required to be re-exposed for

inspection at no extra cost to the City of Vancouver. Provide 48 hours minimum notice to Engineer to arrange inspections and review of pressure testing.

.2 Testing: Upon completion of the Permanent Automatic Remote Irrigation and ,

arrange for the Engineer to be present to observe pressure testing. Test all plastic pipe and sprinklers as follows: .1 After the Permanent Automatic Remote Irrigation and pipe is in place in the

bottom of the trench or laid on surface with risers in place, cap the risers where the sprinklers will be attached and all pipe couplings and fittings exposed.

.2 Apply a pressure of 0.551 MPa (80 psi) to each section, using a test pump and

calibrated container. Inspect visually for leaks at couplings and fittings, cut out and replace any that leak. Maintain test pressure for two (2) hours. After replacing any defective sections, pressure test for two (2) hours and note any pressure loss.

.3 After approval by the Engineer, backfill the pipe maintaining pressure in the line,

noting any sudden drop in pressure. If there is any indication of a leak, locate the defective section and replace. Leaks shall not be repaired by patching.

.4 Provide written notice that pressure testing has been completed satisfactorily,

including re-testing (for 2 hours) of all defective sections. Written notice shall state the date, parties present, pressures applied and duration of pressure tests.

.5 Flushing: after testing and prior to attaching sprinkler heads, flush out each section

to remove any dirt accumulated. .6 Adjustment: Adjust Permanent Automatic Remote Irrigation heads, drip lines for

optimum coverage and rate of flow, including minor adjustment in actual head locations. Set the controller operation times as dictated by Engineer. The Contractor is required to balance and adjust the various components of the system to ensure the efficient operation of the system. This includes the adjustment of any pressure regulators, full and part circle radius heads, valves and adjustments to controllers.

.7 Systems that are substantially complete on or after September 15, shall be left in a

winterized state as per specifications. The contractor is responsible to return in the following Spring at a time dictated by the Engineer and start-up the system and perform all maintenance functions necessary to provide a fully operating system.

Page 64: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Design Build Permanent Automatic Remote Irrigation Section 02800Triangle Park Page 22PS10074

.8 Coverage Test: When the irrigation system has been completed, a coverage test of

the Permanent Automatic Remote Irrigation will be undertaken in the presence of the Engineer to determine if coverage of water on planted areas is complete and determine if any adjustments are required.

.9 Controller Test: As part of the above, and prior to Final Acceptance by the Engineer,

the automatic controller(s) shall be set in sequence and thoroughly tested through each zone to determine if any adjustments are required.

.10 Submit Certificate of Double Check Valve Assembly Test and Pass at the time of

Substantial Completion. 3.6 WINTERIZING

.1 Winterize the system for the first time with the Engineer observing. Winterizing shall include all operations necessary to protect the system from freezing temperatures, including manual and solenoid valve operations to isolate vulnerable parts of the system and draining components and pipes and/or blowing water out of all pipes with compressed air.

3.7 SITE MAINTENANCE/CLEAN-UP

.1 The job site shall be kept in a neat, clean and orderly condition at all times during the installation process.

.2 Trenching, laying pipe and backfilling shall be continuous so that the amount of open

trenching at the end of each work day is minimized. Any open trench or other excavations shall be barricaded and marked with high visibility marking tape to current Worker’s Compensation Board requirements.

.3 Any damage to paving, planting or any other structures/elements due to settlement

of improperly compacted trenches shall be immediately repaired at the Contractor’s expense to satisfaction of the Engineer.

.4 Remove and dispose from the site any and all surplus material, excess excavated

materials, trash, debris and waste material arising from the work of this Section.

END OF SECTION

Page 65: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Site Furnishings Section 02870 Triangle Park Page 1 PS10074

1.00 GENERAL 1.01 GENERAL REQUIREMENTS

.1 Refer to Division 1, General Requirements. .2 All contract documents form an integral part of this section.

1.02 RELATED WORK

.1 Concrete formwork Section 03100

.2 Sandblast concrete Section 03340

.3 Concrete finishes Section 03345 1.03 DESCRIPTION

.1 Work of this section includes providing all labor, materials, equipment and services necessary to complete the stainless steel/ IPE seating elements of types and conditions shown on the drawings and specifications.

.2 Seating elements at SEFC Triangle Park include but are not limited to:

a. Stainless steel laser cut face plate b. Stainless steel attachment bracket c. Stainless steel leveling blocks (various sizes) d. Stainless steel board straps e. IPE Seating Boards – standard cross section size f. IPE Seating boards – custom bevel cut g. Corrosion resistant hardware

.3 Provide fabricated items and assemblies of stainless steel with applied finish process of

passivation & electro-polish as specified. .4 Provide fabricated items and assemblies of IPE wood with specifications as specified.

1.04 SUBMITTALS

.1 In accordance with General Conditions and Division 1 Submittal Procedures Section. .2 Qualifications: Submit to confirm for respective work of fabrication, finishing,

packaging & shipping. .3 Product Data: Submit manufacturer’s data for seating element materials, components,

processes, finishes & packaging. .4 Shop Drawings: Submit for review and city approval prior to production fabrication. .5 Certificates of compliance

Page 66: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Site Furnishings Section 02870 Triangle Park Page 2 PS10074

.1 Stainless Steel Materials Composition & Properties: Submit certificates attesting to the quality, grade & material chemical composition. Submit prior to start of fabrication.

.2 Welding Fabrication: Submit certificates of compliance that welders have passed qualification tests in compliance to specified requirements.

.3 Tropical Hardwood Materials: Submit certificates attesting to the sustainable harvest of the tropical hardwood.

.4 Stainless Steel Production & Finishing: Submit samples of surface finish for approval. Must be submitted & approved before start of fabrication.

.5 Welding procedure: Submit qualified welding procedure for all fabricated sub-assemblies to be manufactured.

1.05 MOCK UPS

.1 Install a maximum 2.4M section of bench assembly to top of cip concrete bench wall.

The mock up will be the standard from which the work of the project is judged. .2 Use the section as the standard to judge the remaining work. .3 Subject to acceptance by the owner, mock-up may be retained as part of the finished

work. .4 If mock-up is not retained, remove and dispose of mock-up. Reuse mock-up materials

where materials are consistent with approved products and in equivalent condition.

1.06 QUALITY ASSURANCE

.1 Manufacturer(s) shall be able to demonstrate at least five (5) years of experience in manufacturing site furnishings similar in design, material, extent and quality indicated for this project.

.2 Single-source Responsibility: Obtain each construction component from a source with

resources to provide products and materials of consistent quality, appearance and physical properties without delaying progress of the work.

.3 General: Materials, welding fabrication, finishing & established procedures shall be in

accordance with drawings and specifications, approved shop drawings and shall be of the highest quality possible

.4 Welders and machine operators must be certified. .5 Product must pass ASTM and BIFMA testing standards.

1.07 SUBSTITUTIONS .1 Product Substitutions: No substitutions permitted unless otherwise approved in

writing by Consultant. Submit three (3) copies of substitution requests to the Consultant in writing with supporting technical data to verify conformance with this specifications.

Page 67: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Site Furnishings Section 02870 Triangle Park Page 3 PS10074

1.08 DELIVERY, STORAGE AND HANDLING

.1 General: Comply with Division 1 Product Requirement Section. .2 Comply with manufacturer’s ordering instructions and lead-time requirements to

avoid construction delays. .3 During shipping, care shall be taken to prevent movement of product, crates, or

packages. .4 Receiving address & contact shall be notified 24 hours prior to shipment arrival.

1.09 GUARANTEE .1 The Contractor hereby warrants that the site furnishings and their installation will

remain free of defects in accordance with the General Conditions.

2.00 PRODUCTS

2.01 MATERIALS

Site furnishings include but are not limited to:

.1 Custom IPE wood and stainless steel bench top assembly: See Landscape Drawings. .2 IPE (Iron Wood): shall be procured from growers who harvest under the guidelines and

techniques of sustainable yield forestry management and manufacturer’s who follow the guidelines as set forth by the International Tropical Timber Organization (ITTO) and or Forest Stewardship Council (FSC) certified.

.1 Wood bench components as noted on drawings and details. .3 Miscellaneous Metal Fasteners:

.1 Hot Dip Galvanized Metal – to ASTM A 153 3-10mils (2.3 oz/ft) ensure threaded components are blown off with air wand and thread is fully functional.

.4 Metal Finishes .1 Coloured metal finishes noted on details, drawings and site furnishing elements

to have rust inhibitor and top coat finish of thermosetting polyester powder coat that is U.V. stable chip and flake resistant.

.2 Rust Inhibitor – applied thickness of 0.6 mils to 1.2 mils. Rust inhibitor shall meet or exceed a 3000 hour salt spray test as per ASTM B117-A with less than 4mm creep.

.3 Powder Coat finish - applied thickness of 3.0 mils to 10.0 mils. Rust inhibitor shall meet or exceed a 3000 hour salt spray test as per ASTM B117-A with less than 4mm creep. Colour fade and UV resistance should pass ASTM G155, cycle 7.

.4 Stainless steel to be finished through a process of passivation and bead blast/ matte electropolish.

Page 68: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Site Furnishings Section 02870 Triangle Park Page 4 PS10074

3.00 EXECUTION 3.01 FABRICATION .1 General: Fabrication of stainless steel materials shall be performed in a shop area

dedicated to only producing stainless steel products & material. This shall be done to eliminate the possibility of cross contamination of carbon particles into the stainless steel surfaces.

.2 All surfaces and welded joints shall be free of manufacturing imperfections. .3 Provide fabricated items and assemblies of stainless steel with applied finish process

of passivation & electro-polish as specified. .4 All work shall be of the highest quality industry standard and in accordance with the

best trade practice. 3.02 INSTALLATION

.1 Custom Ipe wood and metal bench top assembly: .1 Assemble and install bench as illustrated in drawings and in accordance with manufacturer's instructions. .2 Touch-up damaged finishes to the acceptance of Engineer.

.2 Touch-up damaged finishes to the acceptance of Engineer.

END OF SECTION

Page 69: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Growing Medium Preparation and Placement Section 02920 Triangle Park Page 1 PS10074

1.00 GENERAL 1.01 GENERAL REQUIREMENTS .1 Refer to Division 1, General Requirements

.2 All contract documents form an integral part of this section. 1.02 RELATED WORK .1 Planting of Trees, Shrubs and Ground Covers Section 02950 1.03 DESCRIPTION .1 Furnish all labour, materials, equipment, and services necessary to supply and place

growing medium and growing medium additives. Work includes but is not limited to: .1 Preparation of growing medium mix. .2 Analysis and recommendation for growing medium additives. .3 Supply growing medium to project site including loading growing medium

onto site and all planting areas. .4 Fine grade growing medium to lines and levels noted on drawings.

1.04 TESTING .1 Submit to the Engineer, a sample of growing medium two weeks prior to the delivery

of any growing medium to the project. The Engineer will have the sample tested for presence of noxious weeds. Growing medium delivery and placement will not begin until written authorization is given to the Contractor by the Engineer.

.2 Submit to the Engineer a copy of a growing medium analysis from a laboratory

approved by the Engineer. The analysis shall be of tests done on the proposed growing medium from samples taken at the supply source within three weeks immediately prior to soil placement. Cost of initial analysis and subsequent tests to ensure compliance with specification shall be borne by the contractor. Results of these tests shall be presented to the Engineer for review BEFORE any growing medium delivery to site.

.3 The analysis shall include break down of the following components: particle size class

and properties, total nitrogen by weight, available levels of phosphorus, potassium, calcium, magnesium, soluble salt content, organic matter by weight, and pH value.

.4 The analysis shall outline the testing laboratory’s recommendations for amendments,

fertilizer and other required modifications to make the proposed growing medium meet the requirements of this specification.

.5 At the discretion of the Engineer submit up to two additional samples at intervals

outlined by the Engineer of growing medium taken from material delivered to site. Samples shall be taken from a minimum of three random locations and mixed to

Page 70: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Growing Medium Preparation and Placement Section 02920 Triangle Park Page 2 PS10074

create a single uniform sample for testing. Results of these tests shall be presented to the Engineer for review.

1.05 SAMPLES .1 Submit to the Engineer samples of the following materials: .1 Dolomite Limestone: .5 kg (11 lb) .2 Organic Material: .5 kg (11 lb) .2 Growing Medium Sample: One composite sample. Sample shall be a composite of at

least three samplings from the proposed source, and shall be at least one (1) litre in volume.

1.06 QUALITY CONTROL .1 Carry out growing medium preparation and placement such that the final product

matches the standard established which has incorporated the recommendations for amendment by the testing laboratory.

1.07 PRODUCT HANDLING .1 DO NOT MOVE OR WORK GROWING MEDIUM OR ADDITIVES WHEN THEY ARE

EXCESSIVELY WET, EXTREMELY DRY, FROZEN OR IN A MANNER WHICH WILL ADVERSELY AFFECT GROWING MEDIUM STRUCTURE. Growing medium whose structure has been destroyed by handling under these conditions will be rejected and shall be replaced by the contractor at no cost to the owner.

.2 Protect growing medium and additives against extreme wetting by rain or other

agents, and against contamination by weeds and insects.

.3 Deliver fertilizer and other chemicals in manufacturer’s original containers. Protect against damage and moisture until incorporated into the work.

.4 All growing medium will be delivered to site premixed from a recognized growing

medium source ensuring consistency throughout the mix. 2.00 PRODUCTS 2.01 MATERIALS .1 Imported Growing Medium: Growing medium shall be imported and stockpiled on

site in an approved location. Stockpiling work shall be such that the soil is not damaged or contaminated.

.2 Growing medium shall be free of subsoil, pests, roots, wood, construction debris,

undesirable grasses including crabgrass or couch grass, noxious or weeds, weed by products, weed seeds or parts thereof, foreign objects and toxic materials.

Page 71: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Growing Medium Preparation and Placement Section 02920 Triangle Park Page 3 PS10074

.3 Fertilizer: .1 Complete commercial synthetic slow release fertilizer meeting the

requirements of the Canada Fertilizer Act, packed in water proof containers, clearly marked with the name of the manufacture, weight and analysis.

.2 Formulation ratio: as per soil test recommendations. .4 Lime: .1 Coarse (unless noted otherwise), ground dolomite limestone containing

minimum 85% of total carbonates. .5 Organic Material: submit sample prior to shipping to site:

.1 Organic Material shall be Soil Amender, black/brown in colour, manufactured by Fraser Richmond Bio-Cycle, Richmond, B.C., or pre-approved equal.

.6 Wood Residuals: Content of wood residuals such as Fir or Hemlock sawdust present in

the growing medium shall not cause the total Carbon to total Nitrogen ratio to exceed 40 to 1. Cedar or redwood sawdust shall not be present in growing medium.

.7 Sand: hard, granular, river pump sand, well washed and free of contaminants,

chemical and organic matter. Particle sizes by weight:

SIEVE SIZE CLASSIFICATION % RETAINED No. 4 (4.76mm) Gravel 0% No. 10 (2.0 mm) Fine gravel 0-5% No.18 (1.0 mm) Very coarse sand 5-10% No.35 (0.50 mm) Coarse sand 15-20% No.60 (0.25 mm) Medium sand 50-75% No.140 (0.105 mm) Fine sand 5-15% No. 270 Very fine sand 0-2% Passing No. 270 Silt, clay 0%

2.02 STANDARD FOR PREPARED GROWING MEDIUM .1 Particle Size Class and Properties Lawn Areas All Other Areas

Sand (> 0.05-< 2 mm round) 85-92% 80-88% Silt (> 0.002 mm -< 0.05mm) 3 max.% 3 max.% Clay (< 0.002mm) 2% max. 2% max. Total Maximum Fines 5% 5% max. Organic Material Content 8- 10% 12 - 15%

.2 Acidity (pH): 6.0 - 6.5 5.0 - 6.0 .3 Salinity: Maximum saturation extract conductivity: 3.0 millihos/cm at 25 degrees C. .4 Cation exchange: 30 - 50 meq. .5 Carbon to nitrogen ratio: maximum 40:1 .6 Hydraulic Conductivity: Minimum saturated hydraulic conductivity 5.0 - 7.0 cm/hour

in place. .7 Fertility:

Page 72: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Growing Medium Preparation and Placement Section 02920 Triangle Park Page 4 PS10074

Total nitrogen: .2 - .6% by weight. Available phosphorus 50 - 150 ppm

Available potassium 50 - 300 ppm C/N ratio max 25:1 3.00 EXECUTION 3.01 MIXING PREPARED GROWING MEDIUM .1 Screen growing medium with mechanical screening equipment. Thoroughly mix

imported growing medium with recommended additives during screening process to produce a growing medium with the particle size class and properties as specified in 2.02. No hand mixing will be accepted unless specifically approved by the Engineer.

.2 Screening and mixing of growing medium will be not be allowed. All growing medium

is to arrive pre - mixed.

3.02 PREPARATION .1 Scarify existing sub grade and compacted gravel areas to a minimum depth of 200

mm (8”).

.2 Ensure proper drainage in all planting beds. .3 Remove all substrates from surface of boulders within intertidal areas and place

within interstices of boulders. Compact all substrates occurring within interstices of intertidal boulders.

3.03 PLACEMENT OF GROWING MEDIUM .1 Do not place growing medium until the Engineer has reviewed subgrade.

.2 Ensure that irrigation lines to be installed have been reviewed by the Engineer prior to the placing of growing medium.

.3 Break up and loosen subgrade and compacted gravel areas to allow for proper

drainage in planting areas and planted islands.

.4 Place prepared growing medium in compacted layers of 100 mm to 150 mm (4” to 6”) in planting.

.5 Ensure proper drainage in all shrub and tree pits. .6 Place growing medium to the required finished grades with adequate moisture, in

uniform layers, during dry weather, over approved, dry, unfrozen sub grade where planting is indicated to the following minimum depths:

Page 73: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Growing Medium Preparation and Placement Section 02920 Triangle Park Page 5 PS10074

Trees pits: 1000 mm (3’-3”) Shrub beds: 450 mm (1’-6”) Lawn areas: 300 mm (1’-0”)

.7 Growing medium to be 25 mm (1”) below paving finished grade and curbs for planted

areas. 3.04 SOIL AMENDMENTS .1 Apply lime, or other soil amendment at rate determined by testing laboratory’s

recommendations.

.2 Mix amendments well into full depth of growing medium by cultivating or rototilling prior to application of fertilizer.

3.05 APPLICATION OF FERTILIZER .1 Apply fertilizer at least two weeks after lime application and at least 6 days before

planting.

.2 Spread fertilizer with mechanical spreaders over entire area of growing medium at rate recommended by the testing laboratory. Mix fertilizer thoroughly into upper 100 mm (4”) of growing medium.

3.06 WEED CONTROL .1 Eliminate all weeds and weed roots from growing medium.

.2 Have method for elimination of weeds reviewed by the Engineer prior to any action

by the Contractor. 3.07 FINISH GRADING .1 Fine grade (manually) growing medium areas to contours and elevations shown on

drawings or as directed by Engineer. Eliminate rough spots and low areas to ensure positive drainage.

.2 Leave surface smooth, uniform, firm against deep foot printing, with a fine loose

texture. 3.08 SURPLUS MATERIAL .1 Dispose of surplus growing medium not required for fine grading and landscaping off

site. END OF SECTION

Page 74: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Sodded Lawn Section 02935 Triangle Park Page 1 PS10074

PART 1: GENERAL 1.1 DOCUMENTS 1.1.1 This section of the specification forms part of the Contract Documents and is to be read,

interpreted and coordinated with other parts, and with the pertinent sections of the B.C. Landscape Standard.

1.2 DESCRIPTION 1.2.1 Work Included: Furnish all labour, equipment, material and services necessary for

complete installation of sod lawn. Including control of noxious weeds within sodded lawn areas until Acceptance.

1.2.2 Related Work in Other Sections:

.1 Growing Medium Preparation & Placement Section 02920 .2 Planting trees, shrubs and groundcover Section 02950 .3 Design build irrigation system Section 02800 .4 Landscape Maintenance Section 02970

1.3 PERTINENT STANDARDS AND LEGISLATION 1.3.1 Conform to the requirements of the latest editions of the following standards and

legislation: .1 BCSLA/BCLNA British Columbia Landscape Standard .2 British Columbia Standard for Turfgrass Sod .3 British Columbia Weed Control Act .4 Canada Seed and Fertilizer Act .5 Canada Pest Control Products Act

1.4 SUBMITTALS 1.4.1 Guaranteed analysis of the grass mixture and purity of sod. Submit sample of sod prior

to installation. Submit soil analysis of sod growing medium with sod sample. 1.5 INSPECTION/APPROVALS 1.5.1 Notify VPB Staff at least forty eight (48) hours before installing sod for inspection of

finished grades and sod. 1.5.2 Obtain approval in writing from the VPB Staff Inspector for application of any chemical

vegetation controls. Comply with applicable federal, provincial and municipal legislation and regulations.

1.6 CONDITIONS FOR ACCEPTANCE 1.6.1 The conditions for acceptance of sodded areas:

.1 Achieving Substantial Completion of the contract. .2 Sod shall be mown as specified no more than two days before inspection for Acceptance. .3 Sod shall be uniformly healthy, dense, in a vigorous growing condition, rooted into the

underlying soil and shall show no signs of yellowing. There shall be no gaps showing between adjacent rolls of sod.

Sod shall have no evidence of noxious weeds.

Page 75: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Sodded Lawn Section 02935 Triangle Park Page 2 PS10074

1.6.2 Inspection and Acceptance by the Board: Notify the VPB Inspector(s) at least 48 hours in advance to schedule inspection of the entire landscape ready for Acceptance.

1.7 PRODUCT HANDLING 1.7.1 During shipping, storage and installation, protect sod against drying, to the

requirements of the B.C. Standard for Turfgrass Sod. 1.8 PROTECTION 1.8.1 Protect all sodded areas against trespassing and from damage at all times until

Acceptance. If any sodded areas are damaged, they shall be repaired as required by the Contractor.

1.8.2 Comply with COV pesticide/herbicide control regulations regarding application of

herbicides to control noxious weeds. Ensure all manufacturer’s recommendations regarding application are strictly adhered to.

1.9 APPROVED EQUALS 1.9.1 All items as specified or pre-approved equals. 1.10 GUARANTEE 1.10.1 All workmanship and materials covered under Work of this Section shall be guaranteed

for a period of ONE (1) full year from the date of Substantial Performance. PART 2: PRODUCTS 2.1 MATERIAL 2.1.1 Fertilizer shall be as recommended for season of application (as per industry

standards). 2.1.2 Dolomite Lime: Shall be finely and uniformly ground containing not less than 90%

calcium carbonate. 2.1.3 Sod:

.1 Suitability: All turfgrass sod shall be suited to the locality, site conditions and intended function of each project or area.

.2 Sod shall be nursery grown turfgrass sod, true to type, conforming to the B.C. Standard

for Turfgrass Sod. "Non-Netted" Sod, only will be accepted by VPB.

.3 The quality grade of sod (based on B.C. Standard for Turfgrass Sod) shall be No. 1 Premium Grade grown on a screened alluvial sand base, cultivated on a sterilized soil base to ensure a weed free product. The maximum fines (silt and clay) in the alluvial sand base to be no more than 1% by weight.

VPB approved turf includes:

Anderson Sod Farms “Pro Sport”

Submit sieve analysis for turf farm sand if requested by VPB Staff.

Page 76: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Sodded Lawn Section 02935 Triangle Park Page 3 PS10074

2.1.4 The grass mixture in sod shall be suited to the location and intended use and shall be as described in the B.C. Standard for Turfgrass Sod unless otherwise specified. Standard grass mixture requirements for general purpose areas shall be in the following approximate proportions:

Kentucky Bluegrass 50% Perennial Turf Type Ryegrass 50%

2.1.5 Weed Control: Manual weed control is the preferred method in COV and may be the

only permitted methodology. Confirm with VPB Staff. If chemical vegetation control is permitted, use herbicides of type and at an application rate as required to achieve the desired control. Use only standard commercial herbicide products registered for sale and use in Canada under the Pest Control Products Act.

PART 3: EXECUTION 3.1 FERTILIZER 3.1.1 Apply fertilizer at manufacturers' recommended rates. Ensure equal distribution. Mix

into top 50 mm. (2") of growing medium by discing, raking or harrowing. Application of fertilizer shall be within 48 hours of laying sod.

3.2 LIMING 3.2.2 Add limestone as required to ensure pH 6.0 to 6.5. Mix into full depth of growing

medium. Coordinate with soils analysis. 3.3 SUBGRADE PREPARATION AND FINISHING 3.3.1 Obtain approval of VPB Staff of subgrade and growing medium prior to laying any

sod. Ensure that growing medium is placed to required depths and tolerances as specified and detailed in the Contract Documents and spread evenly over the approved subgrade. Ensure the growing medium is firm against footprints, loose in texture and free of all stones, roots branches etc as required under Section 02920 Growing Medium Preparation and Placement.

3.3.2 Ensure smooth finish on all surfaces and finished grades as shown on the drawings and as

specified herein. 3.3.3 Grades:

.1 Areas to be sodded shall be at grades as shown at the time of sodding, less an allowance for the thickness of the sod.

.2 Restore all areas to be sodded which are misshapen or eroded to original specified condition, grade and slope as directed just prior to sodding. Minor adjustment and refinement of finish grade to be made as directed by the VPB Inspector.

.3 Crown or slope for surface drainage and eliminate all low spots or depressions.

.4 Obtain approval of finish grading from the VPB Inspector prior to proceeding.

.5 VPB do not allow sod laying on any slopes steeper than 4:1. 3.3.4 If the surface of the growing medium is dry, lightly moisten the growing medium

immediately prior to laying sod.

Page 77: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Sodded Lawn Section 02935 Triangle Park Page 4 PS10074

3.4 SOD LAYING 3.4.1 Use full rolls where possible. No bits or sod remnants are allowed. 3.4.2 Lay sod in rows with ends staggered. Butt all sections closely. Do not overlap or allow

gaps wider than 2mm between sections. Top of sod to be flush with adjacent walking surfaces.

3.4.3 Protect new sod from heavy foot traffic during laying. Place planks or plywood if

necessary to prevent damage. Lay within 24 hours after delivery to prevent deterioration. Any sod laid after the 24 hour period will be rejected.

3.4.4 Lay sections on slopes at right angles to the direction of the slope. Stake sod into place

with wood stakes driven flush with the surface in any locations having slopes steeper than 3:1. Interval spacing on stakes shall not exceed 500mm. Prior to pedestrian traffic being allowed onto the sod, and only after the sod is well rooted into the growing medium, pegs or stakes shall be removed or driven to an elevation 50mm below the finished surface.

3.4.5 Cut sod where necessary only with sharp tools. 3.4.6 Water thoroughly to penetrate the full depth of the growing medium as specified. 3.4.7 When sod has dried sufficiently, roll with 113kg. (250lb.) roller to obtain smooth uniform

surface and ensure a good bond between soil and sod. 3.5 MAINTENANCE 3.5.1 Begin maintenance immediately after installation and continue until Acceptance of

sodded areas. Maintenance shall consist of all measures necessary to keep grass healthy, in a vigorous growing condition and well rooted into the underlying soil. The Contractor is responsible for maintenance for one year from the date of issuance of the Certificate of Substantial Performance. Maintenance shall include, but shall not be limited to the following:

.1 Mowing shall be carried out at regular intervals as required to maintain grass at a maximum height of 60mm. (2-1/2"). Not more than 1/3 of the blade shall be cut at any one mowing. Edges of sodded areas shall be neatly trimmed. Heavy clippings shall be removed immediately after mowing and trimming.

.2 Watering shall be carried out when required and with sufficient quantities to prevent grass and underlying growing medium from drying out.

.3 Rolling shall be carried out when required to remove any minor depressions or irregularities.

.4 Weed control shall be carried out when the density of weeds reaches 10 broadleaf weeds or 50 annual weedy grasses per 37 sq. M. (400 square feet).

.5 Weed control, whether manual or chemical, shall reduce the density of weeds to zero. If chemical apply in strict accordance with the manufacturer’s recommendations and to the standards specified herein.

.6 Any sodded areas showing deterioration or bare spots shall be repaired immediately. All areas showing shrinkage due to lack of watering shall be top dressed and seeded with a seed mix matching the original seed mix.

Page 78: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Sodded Lawn Section 02935 Triangle Park Page 5 PS10074

.7 All sodded areas shall be adequately protected with warning signs and fencing as directed by VPB Staff. Fencing shall be maintained in good condition to provide a continuous barrier until Acceptance. Except as otherwise required by the work of this Contract, the fencing shall be removed from the site upon Acceptance by the VPB.

3.6 SUPPLEMENTARY FERTILIZER APPLICATION

3.6.1 Prior to Acceptance, at a time approved by the VPB Staff Inspector, apply fertilizer formulation as recommended for the season at manufacturer's recommended rates evenly to all sodded areas. Water thoroughly.

3.7 CLEAN UP

3.7.1 All excess materials and other debris resulting from sodding operations shall be removed from the job site.

3.7.2 Sweep and flush all walks and paved areas clean to the satisfaction of the VPB Staff

Inspector.

END OF SECTION

Page 79: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 1 PS10074

1

1.00 GENERAL

1.01 GENERAL REQUIREMENTS

.1 Refer to Division 1, General Requirements.

.2 All contract documents form an integral part of this section. 1.02 RELATED WORK

.1 Growing Medium Preparation and Placement: Section 02920 .2 Landscape Maintenance: Section 02970

1.03 DESCRIPTION .1 Furnish all labour, materials, equipment, and services necessary to source, supply

and install all project plant material. Work includes but is not limited to: .1 Source, supply and installation of all project plant material. .2 Application of fertilizers and required amendments. .3 Maintenance of all planting areas including entire plant beds until

acceptance by Engineer and Owner. 1.04 STANDARDS

.1 Except as modified in this specification, all plant material specified shall conform to

the latest additions of the: .1 Canadian Nursery & Landscape Association (CNLA) Standard for Nursery Stock. .2 The British Columbia Landscape & Nursery Association (BCLNA). .3 The BC Landscape Standard. (Latest Edition)

.2 ANSI A-300 Tree Pruning Guidelines. 1.05 SUBMITTALS

.1 Contractor shall confirm in writing the following related to plant availability; .1 The availability of plant material noted on project Plant List four (4) weeks

prior to the Contractor and Engineer review of plant material at the source which shall be no less than four (4) weeks prior to the scheduled start of plant shipments to the project site.

.2 Proposed substitutions for review four (4) weeks prior to the Contractor and Engineer review of plant material. Plant substitutions shall be of similar genus and species and of equal or greater size as those originally specified. The list shall contain the following information:

.1 Botanical name, common name.

.2 Pot size and plant size in the nursery.

Page 80: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 2 PS10074

2

.2 Plant Material Review at the source: .1 Contractor to provide the Engineer with a minimum of seven (7) days notice

of proposed plant review time and date at supply nursery. .2 Contractor shall accompany Engineers during review. .3 Prior to any delivery of any plant material to site, submit to the Engineer, a copy of

the Phytophthora ramorum, (Sudden Oak Death) Free Certificate for all plant material supply nurseries supplying plants to the Project, as issued by the Canadian Food Inspection Agency. This Certificate certifies that the nursery and its suppliers are free of the Phytophthora ramorum pathogen.

.4 The Contractor is to submit a full planting schedule for review by Engineer two (2)

weeks prior to the start of work of this section. The schedule shall include but is not limited to the following information set up within a minimum of one week intervals for the duration of the work of this section including maintenance operations;

1. Review of Plant material at nursery 2. Delivery of plant material to the site 3. Milestone dates for planting operations coordinated with review and

approval of subgrade and growing medium installation. 4. Substantial Completion milestone date. 5. Acceptance milestone date.

1.06 PLANT MATERIAL SEARCH AREA .1 Search area for availability of plant material shall include all of Western North

America

1.07 SOURCE QUALITY CONTROL .1 All plant material, including substitutions shall be gathered at one location for

review. .2 Engineer shall make two (2) visit to source for review of plant material for entire

project. Reviews by the Engineer required for approval of plant material at the source over and above this shall be paid for by the Contractor.

.3 Shipping of plant material to project site shall not proceed until Engineer review of

plant material has been reviewed and is acceptable to Engineer. .4 Plant Material Review at Project Site: All plant material shall be reviewed at the

project site by the Engineer prior to planting. Plant material that is rejected by the Engineer shall be replaced at the Contractors expense.

.5 Imported Plant Material:

.1 Plant material imported from out of province and out of country shall be accompanied with necessary federal and provincial permits and import licenses.

.2 The contractor shall conform to all federal and provincial laws and regulations

Page 81: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 3 PS10074

3

with regard to horticultural inspection of domestic and imported plant material.

.8 Plant material will be supplied from a Nursery certified Free of Phytophthora

ramorum, (Sudden Oak Death), as determined and certified by the Canadian Food Inspection Agency. Only Nurseries that are certified free of Phytophthora ramorum will be able to supply Plant Material for this project.

.9 Trees grown and or supplied in IN-GROUND FABRIC CONTAINERS will not be used.

1.08 SHIPMENT AND PRE-PLANTING CARE

.1 Coordinate shipping of plant material and excavation of planting pits to ensure minimum time lapse between nursery digging and on site planting.

.2 Ensure branches of trees and shrubs are bound securely into a confined mass during

handling and transport. .3 Do not bind planting stock with rope or wire which would damage bark, break or

damage branches or damage the natural shape of the plant

.4 Protect plant material against abrasion, and exposure to extreme temperature change during transit.

.5 Cover plant foliage and branches with tarpaulin to prevent loss of moisture during

transit. .6 Fully support root ball of large trees during all lifting operations. .7 Do not lift trees or shrub by the trunk or branches. Plant material to be moved by

lifting the rootball or container.

.8 Remove broken and damaged roots with clean cuts using sharp pruning shears.

.9 Temporary Storage of Plant Material on Site: .1 Heel-in all trees, shrubs and miscellaneous plant material which cannot be

planted immediately. .2 Ensure temporary heel-in area is shaded and protected from the wind. .3 Provide sufficient water at regular intervals to ensure health of plant

material.

1.09 WARRANTY

.1 The Contractor hereby warrants that the plant material will remain free of defects in accordance the General Conditions for a period of one (1) year from the date of issuance of the Certificate of Substantial Performance. The contractor shall make all corrections, adjustments and replacements required as a result of failure of all plant

Page 82: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 4 PS10074

4

material in this section. .2 The Engineer accompanied by the Contractor will undertake an End-of-Warranty

inspection to identify plant material that will be replaced by the Contractor.

.3 The Engineer reserves the right to extend Contractor's warranty and responsibilities for an additional year if, at end of the initial warranty period the leaf development and growth of the plant material is not sufficient to ensure future survival.

1.10 CONDITIONS FOR ACCEPTANCE

.1 The conditions for Acceptance of landscape areas and for turning over the landscape areas to the Owner for subsequent maintenance are:

.1 Growing medium quality, fertility levels, depths and surface grading have been completed to the requirements of Section 02920.

.2 Plant quantities, sizes quality and locations are as shown in the Contract Documents or as otherwise approved by the Engineer.

.3 Substantial Performance for the complete project shall have been declared.

.4 All plant material shall be installed at the correct elevation relative to finished grade,.

.5 All plant material shall be healthy, in a vigorous growing condition.

.6 All plant material shall be well established to the satisfaction of the Engineer .

.7 All plant pruning to current ISA standards shall be completed and all debris removed and disposed of off site where required and directed by Engineer.

.8 All deficiencies with regard to landscape work shall have been rectified.

.9 All trees to be staked.

.10 All planted areas shall have been maintained by the Contractor for 1 year from the date of issuance of the Certificate of Substantial Performance.

.11 All planted areas are free of all visible weeds and substantial free from underground weed seeds or parts there of to the requirements of Section 02970 Landscape Maintenance.

.12 Mulch has been placed as required. All areas not to receive mulch are in a cultivated, loose, friable condition where water can freely permeate the surface.

.2 The date of Acceptance shall be as determined by the Engineer based upon a

successful Inspection for Acceptance. The Contractor shall provide a minimum of forty eight (48) hours notice to the Engineer when the scope of work in this section is ready for Inspection for Acceptance.

1.11 PLANT MATERIAL REPLACEMENTS .1 The contractor shall remove from the site any plant material that has been

determined by the Engineer to have died or failed to grow in a satisfactory manner during the warranty or maintenance period.

.2 The Contractor shall replace dead plant material immediately after removal from the

Page 83: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 5 PS10074

5

site.

.3 The Contractor shall extend the warranty on replacement plant material for one (1) year or a period equal to the original warranty.

.4 The Contractor shall continue such replacement and warranty of plant material to

the satisfaction of the Engineer. 2.00 PRODUCTS 2.01 MATERIALS

.1 Water: potable and free of minerals that are detrimental to plant growth.

.2 Mulch: Owner Composted Mulch (soil amender mulch as per park board spec),

comprised of a combination of leaf matter, composted wood chips and miscellaneous composted material. Submit sample for review prior to shipment to site. Contractor to submit a one (1) litre sample to the Engineer for review prior to shipping to the site.

.3 Anti-desiccant: wax-like emulsion that will provide a transpiration reducing film over

the plant surface. Contractor to submit three (3) copies of manufacturer product data and specification for Engineer review prior to application.

.4 Tree trunk Protection: extrusion mold process, polyethylene with UV protectors:

“Arborgard” manufactured by DeepRoot products Canada, Inc., Vancouver, B.C., or pre-approved equal.

.5 Burlap: shall be untreated, free from toxic contaminants and of sufficient strength to

hold the root ball in a compact, stable mass that does not move relative to the main stem(s) of the tree or shrub.

.6 Wire Baskets: non galvanized metal basket designed and manufactured for the

purpose of tree moving. Basket shall be shaped to ensure that the root ball will allow a stable planting condition in accordance with BCNLA/BCSLA Landscape Standard.

.7 Tree Ties: Arbor Tie by Deep Root or approved equal. Flat woven polypropylene

material. 20 mm (3/4”) wide, 544 Kg (1200 lb.). break strength tree tie. .8 Tree guy anchors: Anchors shall be buried, 100 mm (4”) diameter steel disc, screw–in

type. .9 Stakes: No. 2 Grade or better Cedar 50 mm x 50 mm (2” x 2”) square, 2500 mm (8’-

0”) long.

Page 84: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 6 PS10074

6

2.02 PLANT MATERIAL .1 Plant Size:

.1 Overall plant spread to be measured when branches are in their natural position.

.2 Height and spread dimensions refer to main body of plant and not from branch tip to branch tip.

.2 Grade: Trees and shrubs and miscellaneous plant material to be No. 1 grade or

better. .3 Plant material obtained from areas with milder climatic conditions from those of site

are acceptable provided: .1 Plant material is moved to the site prior to the breaking of buds at their

original climatic zone. .2 Plant material is heeled-in at a protected area until the climatic conditions

are suitable for planting. .4 Trees and shrubs shall have structurally sound, strong fibrous root system free of

disease, insects, defects or injuries. .5 Trees shall have straight trunks and a well formed branch system which is

characteristic of the species. .6 Root Pruning at Source:

.1 Plant material shall have been root pruned on a regular basis at the nursery.

.2 Plant material shall be root pruned at least one growing season prior to digging and shipment to the project site.

.3 Large trees shall be half root pruned during each of two successive growing seasons. The second root pruning shall have carried out a minimum of one growing season prior to shipment to the site.

.7 Shade, Ornamental and Evergreen Trees:

.1 Trees shall have vigorous growth .

.2 Trees shall have good twig extension growth, branch spacing and trunk taper.

.3 Tree foliage shall be evenly distributed on upper 2/3 of the tree.

.4 Trees shall not have upright branches other than leaders.

.5 Trees will have spreading branches with a single trunk and a single leader and, unless otherwise noted on plans or plant list.

.6 Tree trunks and branches shall not have any mechanical damage.

.7 Trees shall be in good health with no presence of insects or disease.

.8 Trees shall not be headed back.

.9 Tree root balls shall be solid, kept moist at all times and/or protected from drying.

.10 Trees shall not exhibit symptoms of root circling or girdling

Page 85: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 7 PS10074

7

.4 Container Grown Plant Material : .1 Root ball to container relationship shall be of sufficient ratio to ensure room

for healthy, vigorous root development. .2 Plant material shall have been container grown for a minimum of one growing

season but not longer than two growing seasons. .3 The plant material root systems must have the ability to "hold" growing

medium when removed from the container. .4 Root bound plant material is not acceptable.

.5 Balled and Burlapped Plant Material :

.1 Coniferous and broadleafed evergreens over 2.4 metre (7’-8”) tall shall be dug with firm soil root ball.

.2 Deciduous trees in excess of 3.0 metre (10’-0”) height shall be dug with firm soil root ball.

.3 Root ball diameter shall be a minimum of 230 mm (9”) for each 25 mm (1”) caliper size.

.4 Secure root-balls with burlap, heavy twine and rope.

.5 Large tree root balls shall be double layer burlap wrapped. Burlap to be secured with drum laces made up of 10 mm (3/8”) (minimum) diameter rope.

.6 Tree Spade Dug Plant Material:

.1 Plant material shall be dug with mechanized hydraulic spade or clam-shell type digging equipment .

.2 Root ball diameter shall be a minimum of 230 mm (9”) for each 25 mm (1”) caliper size.

.3 Wire basket shall be lined with burlap. Root ball shall be laced and tied to wire basket with heavy rope.

.4 Ensure trunk of tree is not damaged by wire basket, ties or rope. 3.00 EXECUTION

3.01 PRE PLANTING OPERATIONS

.1 Place stakes on site to identify location trees and plant beds as landscape plans. Engineer to review all tree locations and plant bed layout prior to start of plant bed preparation and planting operation.

.2 Anti-desiccant shall be applied only as directed by the Engineer. Application of anti-

desiccant shall be in accordance with manufacturer's instructions .

.3 Coordinate planting operations with other trades and project schedule.

3.02 PLANTING SCHEDULE .1 Contractor to carry out planting operation and sequencing as per the approved

schedule. Contractor to review deviations in to the schedule with Engineer prior to continuing with work in this section. All planting operations shall be done in a timely

Page 86: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 8 PS10074

8

manner.

.2 Planting operations shall be carried out under conditions that are conducive to healthy, vigorous growth of plant material.

3.03 EXCAVATION

.1 Existing Utilities: The contractor is responsible for confirming the location and extent of existing utilities prior to the start of all planting operations. All attempts should be made to ensure that utility services are maintained to all on and off site parties through out the entire planting operation.

.2 Tree Pits:

.1 Excavation of the depth of the tree pit shall be equal to the height of root ball.

.2 Width of tree pit shall be a minimum of 450 mm to 600 mm (1’-6” to 2’-0”) greater than diameter of the root ball.

.3 Tree pit widths in heavy or compacted soils shall be increased to three (3) to five (5) times the width of the root ball.

.4 Scarify the sides of tree pits created with a tree spade to eliminate glazed surface.

.3 Ensure tree pits dug in heavy or compacted soils exhibit the ability to drain freely.

.1 Free draining tree pits will allow 4 litres of water to completely penetrate the sub grade within thirty (30) minutes of application to excavated tree pit.

.2 Notify Engineer if tree pits in any soil condition do not drain freely or if tree pit fills with ground water.

.4 Protect bottom of tree pit(s) against freezing.

.5 Ensure tree pits and plant beds are kept well drained and free of contaminants and

construction debris. .6 Remove water which may have collected in bottom of tree pit as a result of rain or

site watering activities prior to planting. 3.04 PLANTING

.1 Plant trees, shrubs and miscellaneous plant material vertical, straight and plumb at locations staked in field and or noted on landscape plans.

.2 Ensure orientation of plant material will give best appearance in relation to

structures, roads and walks. .3 Ensure planting depth of root ball is equal to the depth of root ball originally

established in the nursery. The top of root ball shall be level with adjacent growing medium.

Page 87: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 9 PS10074

9

.4 Ball and Burlap Plant Material: After plant has been lowered into plant bed or tree

pit loosen burlap from around trunk and cut away minimum top 1/3 without disturbing root ball.

.1 Burlap and tie surround on plant material that has been tied with star pattern and has been identified by nursery supplier to remain in place until warranty period has expired shall be left in place until after warranty review.

.5 Container Grown Plant Material: Remove entire container (including bio degradable

containers) without disturbing rootball. Score rootball vertically at six (6) locations evenly spaced around entire root ball to minimize girdling of roots.

.6 Tree Spade Dug Rootballs: Cut wire basket around entire perimeter of rootball. Bend

down top 2/3of wire basket without disturbing rootball.

.7 Backfill tree pit in 150 mm (6”) lifts to 2/3 of the depth of the tree pit tamping each lift of growing medium around root system to eliminate air voids. Do not use frozen or saturated growing medium for backfill operation.

.8 Prior to placing remaining growing medium, fill tree pit with water. Complete

backfill operation only after water has completely penetrated into growing medium.

.9 Build 100 mm high by 150 mm wide (4” high by 6” wide) saucer around outer edge of tree pit to assist with maintenance watering.

.10 Guy or stake trees as directed by Engineer. Ensure guy pins and stakes are not placed

through the root ball. Trees that have had root balls penetrated by guy pins and stakes will be rejected

.11 Place Tree Trunk Protector around base of tree trunk as per manufacturers

instructions. .1 Trees 100 mm (4”) caliper or less will have one protector. .2 Trees greater than 100 mm (4”) caliper shall have a minimum of two

interlocked protectors. 3.05 PRUNING

.1 All pruning cuts shall be made with pruning saws or hook and blade pruning tools designed and manufactured for pruning operations. Anvil-type pruning tools shall not be used in any pruning operations.

.2 Prune trees and shrubs after planting operation as directed by Engineer. .3 Employ clean sharp tools and make cuts without damaging the branch collar. .4 Do not damage the leader, lead branches or remove smaller twigs along the main

Page 88: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 10 PS10074

10

structural branches.

3.06 MULCHING .1 Engineer to review all plant beds and tree planting prior to the addition of any mulch

material. .2 Ensure that all fine grading is complete, the growing medium is loose and friable and

all debris and weeds have been removed from plant beds and tree pits prior to the application of mulch material.

.3 Spread mulch to minimum thickness of 50 mm (2”). .4 Ensure mulch is kept 125 mm (5”) away from trunks of trees and 75 mm (3”) away

from stems of shrubs. 3.07 MAINTENANCE

.1 Maintenance of plants shall begin immediately after planting operation and shall continue until;

.1 The expiration of the one year maintenance period which begins from the date of issuance of the Certificate of Substantial Performance; and

.2 All deficiencies noted in the Substantial Performance review have been rectified to the satisfaction of the Engineer; and

.3 Issuance of the Certificate of Total Performance. The Contractor is to notify the Engineer in writing forty eight hours (48) prior to stopping maintenance operations.

.2 Maintenance of plant material includes but is not limited to;

.1 Watering at intervals sufficient to maintain healthy, vigorous growth.

.2 Weeding of plant beds and cultivating of growing medium.

.3 Pruning operations by ISA Certified Arbourist.

.4 Treatment of insects, molds, fungi or disease to the Level 2 “Groomed’ as per the BC Landscape Standard consistent with the policies and regulations of the Owner or as directed by Engineer.

.3 Plant material shall be deep watered at least once per day when temperatures

exceed 25 degrees Celsius (77 degrees F). .4 Contractor to ensure adequate moisture in root zone at prior to winter freeze-up. .5 Ensure that all plants that have settled are reset to level of surrounding finished

grade. 3.08 CLEAN-UP

Page 89: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Planting Trees Shrubs and Groundcover Section 02950 Triangle Park Page 11 PS10074

11

.1 Clean up immediately any growing medium or debris spilled onto pavement. .2 Remove all materials and other debris resulting from work of this section and dispose

of off site.

END OF SECTION

Page 90: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Landscape Maintenance Section 02970 Trianlge Park Page 1 PS10074

1.00 GENERAL

1.01 CONFORMANCE .1 Conform to Division 1, General Requirements. .2 All contract documents form an integral part of this section. 1.02 RELATED WORK

.1 Excavation and Placement of Granular Materials Section 02223 .2 Sod lawn Section 02938 .3 Planting Trees, Shrubs and Groundcover Section 02950

1.03 DESCRIPTION

.1 Soft Landscape Maintenance for a one year (1) year Soft Landscape Maintenance Period to ensure the adaptation and established vigorous growth of plant material in preparation for take over by the Owner. Established maintenance procedures apply to all soft landscape areas, including:

.1 Complete maintenance of Sod Lawn areas.

.2 Complete maintenance of Perennials, Perennial Beds and Groundcovers.

.3 Complete maintenance of Trees, Shrubs, and Shrub Beds.

1.04 PERTINENT STANDARDS AND LEGISLATION .1 Conform to the latest requirements of the latest editions of the following standards and legislation:.

.1 BCSLA / BCNLA British Columbia Landscape Standard, Latest Edition

.2 Weed Control Act

.3 Canada Seed and Fertilizer Act .4 Acceptable Practices of Integrated Pest Management.

1.05 SOFT LANDSCAPE MAINTENANCE PERIODS

.1 Landscape Maintenance Periods are as follows. .1 A one (1) year Soft Landscape Maintenance Period that begins on the date of

issuance of the Certificate of Substantial Performance. 1.06 MAINTENANCE FIELD REVIEWS

.1 Field Reviews: Field reviews during the maintenance period will be conducted at the following intervals.

.1 A minimum of one maintenance field review per month during the one (1) year

Soft Landscape Maintenance Period. These reviews are to be attended by

Page 91: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Landscape Maintenance Section 02970 Trianlge Park Page 2 PS10074

representatives of the Engineer, Vancouver Park Board and the Landscape Contractor.

1.07 REPORTING PROCEDURES .1 A Maintenance Log Book is to be maintained by contractor. Minimum requirements as per

BCSLA/BCNLA Landscape Standard latest edition.

.2 Maintenance Reports prepared by the contractor to be sent weekly to the Engineer and throughout the duration of the maintenance period. Maintenance reports to be completed as per Vancouver Park Board standard format.

1.08 STANDARDS TO BE MET PRIOR TO ACCEPTANCE REVIEWS

.1 Not withstanding the conditions for acceptance as noted in Section 02938 and 02950 the following minimum requirements shall be met prior to the review of the soft landscape by the Engineer before a Soft Landscape Maintenance Period review will be conducted.

.1 All plant material is healthy, well established, exhibits clear signs of active growth and root development.

.2 All plant material is free of disease, fungus, and pests. .3 All lawn areas are healthy, well established and exhibit signs of vigorous growth. .4 Lawn areas shall be kept within accepted height range. .5 All planted areas are weed free. All plant beds are free of debris. All debris from

plant bed maintenance has been removed from the site. .6 All deficiencies with regard to landscape maintenance have been rectified .5 Maintenance and regular monitoring to avoid any deterioration of the soft

landscape shall have been undertaken by the contractor throughout the Soft Landscape Maintenance Period. The Level of maintenance will be ‘Groomed’ as defined by the BCSLA / BCNLA British Columbia Landscape Standard, Latest Edition.

1.09 GROWING MEDIUM AND SOIL TESTING .1 A minimum of one (1) growing medium test shall be conducted by the contractor at the

beginning of the one (1) year Soft Landscape Maintenance Period. A minimum of one (1) growing medium test shall be conducted by the contractor at the end of the Soft Landscape Maintenance Period. Growing medium samples shall be taken as follows:

Page 92: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Landscape Maintenance Section 02970 Trianlge Park Page 3 PS10074

.1 Lawn: Six (6) 1 liter samples at representative locations throughout the site. Combine to form one (1) representative 1 liter testing sample.

.2 Shrub Beds and Tree Pits: Six (6) 1 liter samples at representative locations

throughout the site. Combine to form one (1) representative 1 liter testing sample.

.2 Growing medium analysis shall provide nutrient breakdown and fertilizer recommendations

to ensure growing medium nutrient level is equal to original specification. Provide one copy of test to Engineer/ Owner for review.

1.10 PRODUCT HANDLING .1 Deliver fertilizer, lime and growing medium amendment products in waterproof bags showing

mass, analysis and name of manufacturers. .2 Do not store on site. Deliver to site the quantity to be utilized the day of delivery. 2.00 PRODUCTS 2.01 MATERIALS

.1 Fertilizer: Complete commercial synthetic slow release fertilizer with maximum 35% water

soluble nitrogen. Formulation ratio: As per soil/ growing medium test recommendations.

.2 Lime: .1 Coarse, (unless noted otherwise), ground dolomite limestone containing minimum

85% of total carbonates. .2 Use lime as indicated by acidity analysis of topsoil to bring pH to required level.

.3 Organic Matter/Organic Mulch: Composted Mulch, comprised of a combination of leaf

matter, composted wood chips and miscellaneous composted material. .4 Stakes: 75 mm (3”) dia. x 2500 mm (8’-0”) #2 Grade or better Cedar. Ensure ends are shaped

to allow easy penetration of ground. .5 Tree Ties: Arbor Tie by Deep Root or approved equal. Flat woven polypropylene material. 20

mm (3/4”) wide, 544 Kg (1200 lb) break strength tree tie. .6 Tree guy anchors: Anchors shall be buried, 100 mm (4”) diameter steel disc, screw–in type. .7 Sand: hard, granular, river pump sand, well washed and free of contaminants, chemical and

organic matter. Particle sizes by weight:

SIEVE SIZE CLASSIFICATION % RETAINED

Page 93: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Landscape Maintenance Section 02970 Trianlge Park Page 4 PS10074

No. 4 (4.76mm) Fine gravel 0% No. 10 (2.0 mm) Fine gravel 0-5% No.18 (1.0 mm) Very coarse sand 1-10% No.35 (0.50 mm) Coarse sand 15-20% No.60 (0.25 mm) Medium sand

50-75% No.140 (0.105 mm) Fine sand 5-15% No. 270 Very fine sand 0-2% Passing No. 270 Silt, clay 0%

.7 Prepared Growing Medium: As per Section 02920.

3.00 EXECUTION 3.01 GENERAL WORKMANSHIP

.1 All soft landscape maintenance to meet or exceed the standards of ‘Groomed’ as defined

by the BCSLA / BCNLA British Columbia Landscape Standard, Latest Edition .2 Program timing of operations to growth, weather conditions and use of site. .3 Do each operation continuously and complete within reasonable time period. .4 Collect and dispose of debris or excess material on weekly basis or as required to

maintain a neat appearance. .5 Notify the Engineer and Owner immediately of damage incurred by pest, disease,

mechanical or vandalism. 3.02 GROWING MEDIUM

.1 Prepared as per Section 02920. 3.03 WATERING

.1 Plants shall be watered at minimum of every ten (10) days between April 1 and July 31,

and every twenty (20) days between August 1 and September 15. Watering shall be carried out more frequently if plants are reaching permanent wilting state. Scheduled watering shall be missed only when rainfall has penetrated the growing medium fully.

.2 Newly planted trees are to be deep watered every second day from June 30 and August

31.

.3 Watering shall be such that the water penetrates the full depth of the growing medium.

3.04 MULCH

Page 94: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Landscape Maintenance Section 02970 Trianlge Park Page 5 PS10074

.1 Mulch: To depths and extent as noted in Section 02950.

3.05 WEED CONTROL

.1 All soft landscape areas including lawn areas shall have all weeds removed at least once every two weeks during the (1) year Soft Landscape Maintenance Period by hoeing, hand-pulling or cultivation to a maximum depth of 80 mm (3 1/8”).

3.06 PEST AND DISEASE CONTROL

.1 All soft landscape areas including lawns shall be inspected for pests and diseases at least

once every week during the maintenance period. Treatment for pests or diseases shall be carried out promptly and consistently for maximum effectiveness. The principles of Integrated Pest Management (IPM) should be applied in controlling pests and diseases. Methods used should be in conformance with standards set by Owner.

3.07 TREE SUPPORT .1 All trees to be staked.

.2 Use buried anchors and Arborknot as per manufacturers instructions to achieve a

straight, secure tree. 3.08 PRUNING

.1 Trees and shrubs shall be pruned to remove all dead, weak or diseased wood. Clipping or shaping shall be carried out only if required in the maintenance for specific varieties or conditions as directed by Engineer.

3.09 FERTILIZING

.1 Except as otherwise recommended on the basis of growing medium/soil test results, shrubs and trees shall be fertilized only as required to correct symptoms of nutrient deficiency as noted in growing medium analysis.

3.10 MAINTENANCE AND REPAIR OF LAWN AREAS

.1 Watering: Hoses and sprinklers, irrigation systems or other methods shall be used to apply water to all lawn areas such that the grass is maintained in a turgid condition. The method of application shall be such that compaction or erosion of the growing medium does not occur.

.2 Each application of water shall be of an application rate and duration such that the

water content in the growing medium reaches field capacity to the full depth of the

Page 95: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Landscape Maintenance Section 02970 Trianlge Park Page 6 PS10074

growing medium. The next application shall take place when the water content reaches 25% of field capacity.

.3 Fertilizing:

.1 Except as otherwise recommended on the basis of growing medium/soil test results, lawn areas are to be fertilized as per the recommended intervals, with fertilizer as noted in the BCSLA / BCNLA British Columbia Landscape Standard, Latest Edition ‘Groomed’ maintenance standard.

.3 Mowing and Trimming:

.1 The initial four (4) mowing operations shall be by a sharp rotary type mower. Excess grass clippings shall be removed after each cut.

.2 Subsequent mowing operations shall be carried out with a reel or rotary mower

when the grass reaches a height of 60 mm (2 3/8”). Mow to a height of 40 mm (1 1/2”). Trim with nylon line type power trimmer.

.4 Edging:

.1 Areas shall be edged with a half-moon or power edger as frequently as necessary to accurately establish and maintain the intended edge location as per the original design construction drawings

.2 Radius curves established by string or other marking methods suited to the design layout shall be employed to ensure smooth, continuous curves.

.5 Aeration:

.1 Aeration shall not be carried out in the first growing season. If necessary in the second growing season, aeration shall be done in early May with a suitable mechanical corer. Coring shall be done to a depth of 100 mm (4”), and the cores shall be broken up on the surface by the use of a diamond wire or wood drag.

.6 Repairs

.1 Regrading, or resodding shall be carried out when necessary to restore damaged

or failing grass areas. Where lawn fails due to conditions that cannot be modified (such as deep shade or heavy foot traffic) and would result in subsequent failure of lawn notify the Engineer.

.2 New sod shall match the grass varieties in the surrounding area. Resodding may

be carried out throughout the growing season as needed to ensure that all lawn areas are in a healthy, vigorously growing condition..

3.11 REPLACEMENT OF TREES, SHRUBS, PERENIALS AND GROUNDCOVER

.1 Shrubs, perennials and groundcover that do not meet the standards set out by the BCSLA / BCNLA British Columbia Landscape Standard, Latest Edition ‘Groomed’, are dead,

Page 96: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Landscape Maintenance Section 02970 Trianlge Park Page 7 PS10074

damaged or are in a condition that is of lesser quality at than at the time of initial installation shall be removed and replaced by the contractor.

END OF SECTION

Page 97: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Sandblasting Section 03340 Triangle Park Page 1 PS10074

1.00 GENERAL

1.01 GENERAL REQUIREMENTS .1 Refer to Section 01005, General Instructions.

.2 All Contract Documents form an integral part of this section. 1.02 RELATED WORK .1 Concrete Finishes Section 03345 .2 Concrete formwork Section 031000 1.03 REQUIREMENTS INCLUDED

.1 Furnish labour, material, equipment and services necessary for the

completion of sandblasting work, as indicated in the drawings and as hereinafter specified.

.2 The work shall include but is not limited to sandblasting of exposed exterior

concrete surfaces, as indicated,: .1 Concrete walls. .3 Refer to drawings for locations and extent of sandblasting. 1.04 QUALITY ASSURANCE .1 All work and material shall conform to Chapter 9 of CPCA/MPDA Specification

Manual (latest edition) and as herein specified. .2 This Subcontractor shall have a record of satisfactory performance in the

trade and shall maintain a qualified crew of sandblasters throughout the duration of the work.

.3 Engage only qualified journeyman (and apprentices) in the sandblasting work

and ensure they hold a Provincial Tradesman Qualified Certificate of Proficiency, or are under supervision of a tradesman holding the Provincial Tradesman Qualification Certificate of Proficiency.

1.05 REQUIREMENTS OF REGULATORY AGENCIES .1 Applicable Provincial Regulations and local requirements shall be carefully

observed during sandblasting operations. .2 Safety regulations shall be strictly adhered to as per Workers’ Compensation

Board of B.C. Regulations, latest revision and other authorities having jurisdiction. The permissible noise level in each octave band shall be as lain down by the Workers’ Compensation Board

Page 98: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Sandblasting Section 03340 Triangle Park Page 2 PS10074

1.06 SAMPLE PANELS .1 Prepare 3Mx3M sample panels of sandblasting for review by Engineer a

minimum of four (4) weeks prior to the start of work of this section. .2 Sample panels shall be sandblasted after the specified curing time has

elapsed. Record of cure time and concrete mix design shall be submitted to Engineer in writing. This along with the sample panels shall form the standard for all work related to this section.

1.07 PRODUCT DELIVERY, STORAGE AND HANDLING .1 Store materials and equipment in areas assigned by the Contractor for this

purpose and take necessary precautions to prevent fire or other damage. 1.08 JOB CONDITIONS .1 Equipment used in sandblasting operations shall be properly muffled. All dust

shall be eliminated during the operation. .2 Protect surrounding and adjoining work by adequately covering with

tarpaulins or other necessary protective covering. Make good any damage caused by failure to provide suitable protection.

.3 Protect the work of other trades against damage and soiling. Any damage to

work of others caused by this trade shall be immediately made good, cleaned or replaced at own expense.

2.00 PRODUCTS 2.01 MATERIALS .1 Sand shall be Target Industrial Coarse Sand conforming to CGSB Specification

31-GP-421 or pre-approved equal. .2 Sand gradation will be selected by the Sandblasting Subcontractor to achieve

finishes specified in this section. .3 Abrasives must be free from foreign matter. Fine particles shall be no smaller

than those retained on a #40 mesh. If applying industrial sand, use washed industrial (river sand) only.

3.00 EXECUTION

Page 99: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Sandblasting Section 03340 Triangle Park Page 3 PS10074

3.01 INSPECTION .1 Inspect surfaces and job conditions prepared by other sections before

commencing work. Report defects in writing to the Contractor. Commencement of work indicates acceptance for the above condition.

.2 Engineer to review all surfaces to be sandblasted prior to proceeding with any sandblasting operation.

3.02 APPLICATION .1 All sandblasting required on this project shall be carried out by the air-

blasting method, using proper equipment for this type and method of work. .2 Sandblasting may be carried out at any time between 21 and 30 days, after

concrete has been placed, depending upon construction convenience. Each surface area shall be sandblasted at the same age in order to ensure reasonable colour uniformity. Carry out all sandblasting operation so that the resulting surfaces are uniform in texture and colour.

3.03 FINISH .1 Sandblasting finishes shall be medium finishes as called up on details and

drawings. The exact finish of sandblast will be governed by matching samples reviewed by the Engineer.

.2 Refer to drawing for location, type and extent of sandblasted finishes. 3.04 DUST CONTROL .1 Sandblasting shall be done before painting is commenced.

.2 Erect protective tarping or hoarding as required to protect adjacent surfaces and construction areas.

.3 Sandblasting adjacent to water bodies shall be in accordance with all local,

provincial and federal regulations. The Contractor is responsible for the supply and operation of all equipment necessary to complete work of this section within the government agency requirements noted.

3.05 CLEAN UP .1 On completion of the work, remove all excess materials, water and sand.

During the progress of the work, keep the premises free from any unnecessary accumulation of tools, equipment, surplus materials and debris.

END OF SECTION

Page 100: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Concrete Finishes Section 03345 Triangle Park Page 1 PS10074

1.00 GENERAL 1.01 GENERAL REQUIREMENTS

.1 Refer to Section 01005, General Instructions. .2 All contract documents form an integral part of this section.

1.02 DESCRIPTION .1 This section describes the tolerance and finish requirements for architectural

concrete surfaces and rough formed finish concrete. It is intended to supplement and to be read in conjunction with other sections of the Contract Documents governing concrete work. In the case of conflicts between this section and other sections, the most stringent requirement will govern.

1.03 RELATED WORK

.1 Concrete Formwork Section 031000 .2 Sandblasting Section 03340

1.04 REFERENCE STANDARDS .1 Concrete finishes shall conform to the requirements of the following standards (or

most recent version of the standard) unless otherwise required by this specification: .1 B.C. Building Code 1998. .2 City of Vancouver Building Bylaw No. 6134. .3 ACI 303R-91 Guide to Cast-In Place Architectural Concrete Practice.

1.05 QUALITY ASSURANCE .1 Contractor to ensure that consistency in concrete mix design, placement methods,

form design, and finish techniques are carried out through the duration of the work in this and related sections.

.2 Schedule the delivery of concrete to ensure that a consistency in appearance of

Architectural Concrete is maintained throughout the duration of the project.

2.00 PRODUCTS 2.03 MATERIALS

.1 Concrete Materials: In accordance with CSA CAN3-A23.1.

Page 101: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Concrete Finishes Section 03345 Triangle Park Page 2 PS10074

.2 Premoulded Joint Fillers: .1 Bituminous Impregnated Fibre Board. Board shall conform to ASTM D1751-

73 (1978)) (AASHTO M213-74).

.3 Bonding Agent: Formulated for bonding new concrete to cured concrete; Grace “Daraweld C”, Target “Polymer Bonding Agent”, “Concresive Liquid LPL” Master Builders Technologies or approved equal.

.4 Concrete Joint Sealer: Joint sealer shall be self-leveling two-part polyurethane

type sealer, conforming to CGSB 19-GP-15M Type 1, or Federal Specification TT-A 00227E, type 1. Primers and bond breakers as required to install the control joint sealant system shall be in strict accordance with sealant manufacturer’s recommendations.

.1 Approved Type: Iso-Flex GB (Self-Leveling) Sealant as manufactured by

Harry S. Peterson Co, Inc.; PRC Permapol RC-2SL Sealant; Sternson’s Uraflex 2, or other pre-approved sealant.

.5 Non-shrink Grout for Patching: Master Builder’s “Embeco Mortar”, premixed Target

“Fast- Set Patching Concrete”, or approved equivalent. .6 Sealer: Cementone Clear Sealer by L.M. Scofield, or approved equivalent. .7 Concrete set retarder: Fab-Sol, Type F, manufactured by FabriKem or other pre-

approved equivalent.

3.00 EXECUTION 3.01 SITE MOCK UP - ARCHITECTURAL CONCRETE

.1 Prior to placing any architectural concrete a mock up of the following components

shall be constructed on site (at the Engineer’s discretion a portion of the permanent work may be designated as mock up). The appearance, surface finish, colour, details, tie holes, jointing, assembly and alignment shall be reviewed by the Engineer:

.1 Concrete Walls. 3.02 FINISHING OF CONCRETE SURFACES

.1 Architectural Concrete Finish: Exposed exterior surfaces above grade.

.1 Surface finishing shall conform to CAN 3-A23.1-M94, Section 24, Finishing of Formed Surfaces, Clause 24.3.3, Smooth Form Finish.

.2 Rough Form Finish: All concealed concrete surfaces.

.1 Surface finishing shall conform to CAN 3-A23.1-M94, Section 24, Finishing of Formed Surfaces, Clause 24.3.2, Rough Form Finish. Patching to be done in

Page 102: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Concrete Finishes Section 03345 Triangle Park Page 3 PS10074

accordance with clause 24.2 Patching.

.4 Sandblast Surface Finish: On concrete surfaces noted on drawings as per Section

03340 Sandblasting.

3.03 CURING

.1 Cure and protect the surface finishes in accordance with CAN3 - A23.1-M94, Section 03300 and Section 03341.

3.04 REPAIRS TO DEFECTS

.1 Architectural concrete shall have a pleasing appearance with minimal colour and

texture variation when viewed at a distance of 6 metres (20’-0”). Repairs shall match the surrounding area. Architectural concrete requiring repair deemed to be excessive by the Engineer is subject to rejection and subsequent removal and replacement with new work at no additional cost to the Owner.

.2 Defective concrete includes but is not limited to honeycombing, rock pockets, chips,

cracks, spalls, fins and stains. .3 Prior to commencing any repair work the contractor shall confirm repair procedure

with the Engineer and establish by trial mix the formula required. The contractor shall demonstrate the repair technique and final finish on the mock up. The following are key steps to making a repair to architectural concrete: .1 Remove all loose particles and chip out area deemed unsuitable or defective

to sound concrete to avoid weather edge repairs. .2 Repair mortar mix shall be especially formulated matching coloured mortar.

It shall be non-shrink, and applied according to manufacturer's recommendations. Proportion the repair mix by weight according to the same proportions as used in the concrete mix but substituting a portion of white cement for grey cement. This should be based on tests to determine what is required to match the finished surface.

.3 Soak the area to be repaired with water.

.4 Apply a coat of bonding material to the root of the areas to be repaired being careful to avoid dripping on exposed finished surfaces.

.5 Place colour matching repair mortar mix in void, strike flush with wood float and texture as required to achieve desired finish. Sandblasting to be carried out over entire concrete surface once patch has properly cured.

.6 Allow the repaired area to cure.

.7 Clean the repaired area to remove laitance.

3.05 PROTECTION

.1 Protect architectural concrete from any damage by the elements and defacement

Page 103: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Concrete Finishes Section 03345 Triangle Park Page 4 PS10074

of any nature during construction operation. .2 Keep traffic that would effect and/or otherwise disturb the curing procedures off

the finished surfaces for a period of seven (7) days, minimum. .3 All corners and surfaces subject to possible damage shall be suitably protected with

boards or hoardings.

.4 Make adequate provision to keep all exposed concrete free from laitance caused by spillage, leaking forms or other contaminants. In no event shall laitance be allowed to penetrate, stain or harden on surfaces that have been sandblasted.

.5 Adequate protection shall be given to all exposed reinforcing steel in architectural

concrete to prevent staining of surfaces of concrete due to rust and corrosion. If any rust or corrosion does occur it shall be removed immediately to avoid permanent staining.

3.06 CLEANING

.1 Rubbish and debris resulting from work of this section shall be collected

regularly, and removed from the project site and properly disposed. .2 Repair, remove and clean all drips or smears resulting from the work of this

section on exposed, finished surfaces or surfaces to be subsequently finished.

END OF SECTION

Page 104: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 051000 Triangle Park STRUCTURAL STEEL PS10074 PAGE 1

1.0 GENERAL 1.1 DESCRIPTION

.1 Related Work Specified Elsewhere: .1 Metal Finish Section 05900

.2 All codes and documents referred to in this Section are to be the current adopted edition.

1.2 REFERENCE STANDARDS

.1 CAN3 S16.1, Steel Structures for Buildings.

.2 CISC Code of Standard Practice.

.3 CAN/CSA S136, Cold Formed Steel Structural Members.

.4 CAN/CSA W47.1, Certification of Companies for Fusion Welding of Steel Structures.

.5 CAN/CSA W59, Welded Steel Construction (Metal-Arc Welding)

.6 CAN 3-G40.20, General Requirements for Rolled or Welded Structural Quality Steel.

.7 CAN 3-G40.21, Structural Quality Steels.

.8 City of Vancouver Building By-law 2007.

1.3 QUALIFICATIONS

.1 All Steel Fabricators must have full approval of the Canadian Welding Bureau under CSA W47.1

1.4 EXAMINATION

.1 All dimensions shall be taken from the drawings and checked against the building. Be responsible for the correctness of such measurements and report to the Engineer of Record (“Engineer” henceforth) in writing all discrepancies between measurements at building and those shown on drawings prior to commencing work. Verify location of anchor bolts and embedded steel and ensure that work prepared by other trades is at a proper elevation, on line, level and true.

1.5 SUBMITTALS

.1 Shop Drawings .1 Submit shop drawings prepared under the supervision of a Professional Engineer

registered in British Columbia. Drawings of components designed by the Fabricator shall be signed and sealed by the Registered Professional Engineer.

.2 Submit shop drawings in accordance with General Conditions.

.3 Structural drawings are not prepared to be used in sepia form as Erection drawings. Design drawings include Architectural, Mechanical, and Electrical drawings.

.4 Shop drawings shall complete details necessary for fabrication and erection of the component parts of the structure, including location, type, size and extent of all welds. Splices not shown on the shop drawings will not be accepted.

.5 Review of Shop drawings constitutes review of general methods only and will not include approval of dimensions, figures or quantities. The structural steel supplier is responsible for structural design, correct fabrication and proper fitting of various items.

Page 105: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 051000 Triangle Park STRUCTURAL STEEL PS10074 PAGE 2

1.6 INSPECTION AND TESTING

.1 The Registered Professional Engineer sealing the Steel Fabricators shop drawings is also responsible for all field review of their work and shall provide a letter to the Engineer confirming that the work has been completed in accordance with the final reviewed steel shop drawings and all structural requirements.

.2 The Owner will engage and pay for the services of a Welding Engineer and a Testing

Agency, to submit written reports to the satisfaction of the Engineer. .3 Allow free access to all parts of the works for the purposes of inspection at all times. .4 Prior to commencement of work provide a schedule of shop fabrication. .5 Submit certified results of testing in accordance with CAN 3-G40.20 properly correlated

to the elements being fabricated. .6 High tensile bolts will be tested in accordance with CSA S16.1. .7 Submit certified copy of mill reports covering chemical and physical properties of steel

used in this work, upon request. .8 For the purposes of bidding, assume all welds will be examined by a non-destructive

testing method. .9 Testing of all connections and splices not indicated on the design drawings shall be

undertaken by an independent testing agency approved by the Engineer and will be to the Structural Steel Sub-Contractor's account.

.10 If more than 5% reinspection is required due to faulty workmanship, the Structural

Steel Sub-Contractor will be required to pay for this reinspection. .11 The Engineer may reject at any time during the progress of the work a piece of

material for any member which he may find defective or not in accordance with the detailed drawings. This material may be rejected notwithstanding any previous acceptance and components so rejected shall be replaced at no expense to the Owner. In case of dispute, the decision of the Engineer shall be final.

1.7 STORAGE AND HANDLING

.1 Be responsible for the protection of all steel work during fabrication, shipping, storage and construction. All small bends and damage shall be reported to the Engineer for instructions. Steel work, which is bent, broken or otherwise damage, shall be repaired or replaced by the Structural Steel Sub-Contractor at no cost to the Owner.

.2 Be responsible for proper scheduling of delivery and erection for the structural steel,

all in accordance with the construction schedule.

1.8 CO-ORDINATION WITH OTHER TRADES

.1 Supply all necessary instructions and drawings to other trades for setting bearing plates, anchor bolts, and other members that are built in with the work of other trades. Supply the necessary material in accordance to the construction schedule.

Page 106: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 051000 Triangle Park STRUCTURAL STEEL PS10074 PAGE 3

2.0 PRODUCTS 2.1 MATERIALS

.1 All steel shall be new unless otherwise indicated and be of sizes and shapes listed in the current CISC handbook and as indicated on the drawings.

.2 Rolled shapes and welded wide flange sections shall be to CAN 3-G40.21-350W. .3 Plates and flat bars shall be to CAN3-G40.21-300W. .4 Hollow structural sections shall be to CAN 3-G40.21-350W Class C. .5 High strength bolts shall be to ASTM A325. .6 Bolts and nuts anchored into concrete or wood are to ASTM A307. .7 Primers for exterior exposure shall be zinc chromate Type 1, conforming to CGSB 1-GP-

40d. .8 Primers for interior exposure shall be CISC/CPMA Standard 1-73 Primer or other pre-

approved. .9 Structural steel to contain 75% post consumer recycled content and 90% total recycled

content. Fabricator to provide mill certificate to verify recycled content.

2.2 DESIGN

.1 All trusses and connections not detailed on the drawings shall be designed by the Fabricator to the reference standards unless otherwise noted.

.2 All bolted connections for bracing, trusses, and roof struts shall utilize friction

connections. .3 Connections shall be designed for the forces shown on the drawings and shall allow for

the effects of beam deflections. Provide a minimum of two (2) 19 mm diameter A325 bolts or an equivalent weld for all beam to girder connections.

.4 Column to beam and girder connections shall allow for a horizontal stability force in all

directions equal to 2% of the design column axial load in addition to all other loads.

3.0 EXECUTION 3.1 FABRICATION

.1 All fabrication shall be to CSA S16.1. .2 All Welding shall be to CSA W59, by welders qualified in accordance with CSA W47.1. .3 All fabricated units shall be straight and true and without sharp kinks or bends. .4 All hollow structural sections shall be closed airtight with end plates sealed with welds.

Page 107: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 051000 Triangle Park STRUCTURAL STEEL PS10074 PAGE 4

.5 All plates and shapes shall be inspected visually for laminations. Repair plates or

shapes that contain laminations in a manner to be reviewed by the Engineer. .6 Fabricate structural steel in accordance with final reviewed Shop drawings and

Structural drawings. .7 If sizes of members shown on drawings are unavailable, provide available equivalent

member next size (or thickness) larger.

3.2 CLEANING AND PRIMING

.1 All steel shall be thoroughly cleaned of all loose mill scale, loose rust, oil or dirt. .2 All steel shall be primed except for steel to be encased in concrete, steel to be

fireproofed, steel which will receive shear studs, and faying surfaces of friction connections.

.3 Structural steel to be primed for interior exposure shall be cleaned in accordance with

CISC/CPMA Standard 1-73 (minimum). .4 Structural steel to be primed for exterior exposure or to receive a shop or field paint

finish shall be cleaned in accordance with SSPC-SP6 "Commercial Blast Cleaning". .5 All primers shall be spray-applied strictly in accordance with the Manufacturers

instructions. Apply one (1) coat of primer thoroughly and evenly and work well into the joints and other open spaces.

.6 After erection and after connections are completed, provide a field touch up coat of

primer to all surfaces that had no shop coat, or have been chipped or scraped. .7 Where required, all hot dipped galvanizing shall conform to CSA G164. .8 Apply 2 coats of galvanized paint protection to hot dipped galvanized surfaces damaged

by transportation, erection or site welding.

3.3 ERECTION

.1 Supervise the setting of bases, anchor bolts, and other steel to concrete connections. Cutting of base plates to accommodate anchor bolts shall be cause for rejection of base plates.

.2 Install all temporary bracing that is required to stabilize the work against wind,

earthquake and construction loads. Keep structure true and plumb until completion of the building.

.3 As erection progresses, the work shall be securely bolted up to take care of all dead

loads, wind, earthquake, and erection stresses. Any failure to make proper and adequate provisions for stresses during erection shall be solely the responsibility of the Structural Steel Sub-Contractor.

.4 The Structural Steel Erector shall be responsible for the design of all hooks, erection

connections and handling gear.

Page 108: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 051000 Triangle Park STRUCTURAL STEEL PS10074 PAGE 5

.5 Whenever piles of materials, erection equipment, or other loads are carried during

erection, proper provision shall be made to take care of stresses resulting from same. .6 All structural steel shall be assembled and erected in accordance with the reviewed

erection drawings and specified reference standards. .7 Structural steel work shall be carefully located at the proper elevation and rigidly

secured in place, using steel shims. All spaces under the steel shall then be filled with non-shrink, pre-mix, non-metallic grout, pre-approved by the Engineer.

.8 Plumb, level and align individual members of steel work as specified in CSA S16.1. .9 All exposed steel work shall be finished and assembled to provide the best possible

visual appearance to the satisfaction of the Engineer. .10 Obtain written permission from the Engineer prior to field cutting or altering of

structural members. .11 Clean and touch up shop primer to bolts, rivets, welds and burned or scratched

surfaces at completion of erection.

3.4 WELDING

.1 All welding shall be done by the shielded metal-arc method in accordance with the requirements CSA W59. The welding operators shall have passed within the preceding six (6) months, the qualification test as set forth in CSA W47.1.

.2 Submit welding procedures prepared and sealed by a Professional Engineer registered

in the Province of British Columbia familiar with this discipline to the Engineer for his examination and comments, where requested.

.3 Surfaces to be welded shall be free from loose scale, rust, paint, or other foreign

matter. Where weld material is deposited in two or more layers, each layer shall be cleaned before the next layer is deposited. Care shall be taken to minimize stresses due to heat expansion, contraction and distortion by using proper sequence in welding and by approved methods.

.4 Welding consumables for all processes shall be fully approved by the Canadian Welding

Bureau and certified by the manufacturers as complying with the requirements of this specification. Such certificates shall be no more than two years old.

.5 Electrode strengths to be equal to E70xx or better. .6 All exposed welding shall be finished to provide the best possible visual appearance to

the satisfaction of the Engineer and the Architect. Types of weld are:

'A'- Architectural: Continuous, formed with 'rod' or 'stick' application, with even surface, bead width not to vary by more than + 2mm, but welds to be filled with metal filler and sanded smooth, no weld splatter.

'B' -Standard: Spot or continuous welds formed with 'wire' application. All visible welds, within 3m vertically and horizontally of an accessible viewpoint are to be type 'A'. All other welds are type 'S' unless noted otherwise on the drawings.

Page 109: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 051000 Triangle Park STRUCTURAL STEEL PS10074 PAGE 6

Samples of fillet and butt welds of 'A' and 'S' types on min. 150mm material are required for approval prior to start of fabrication.

3.5 CLEAN-UP

.1 Make good to the satisfaction of the Engineer any damage or injury to the work of other trades. Remove all debris and scrap resulting from the execution of this trade in accordance with the requirements of the Contract Documents.

END OF SECTION

Page 110: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Metal Finish Section 05900 Triangle Park Page 1 PS10074

1.00 GENERAL 1.01 GENERAL REQUIREMENTS .1 Refer to Section 01005, General Instructions .2 All contract documents form an integral part of this section. 1.02 RELATED WORK .1 Structural Steel Section 051000

This Subsection includes requirements regarding the appearance, surface preparation and integration of the Triangle Park Pavilion only. For technical requirements, refer to Section 051000 Structural Steel.

1.03 GUARANTEE

.1 The Contractor hereby warrants that the Site Furnishings and their installation will remain free of defects and in good condition in accordance with the General Conditions.

1.04 SUBMITALS

.1 Shop drawings: submit shop drawings of fabricated items. Completely detail indicating all dimensions and methods of fixing. Prepare shop drawings in imperial units. Show all site measured dimensions.

.2 Indicate any special tolerances and erection requirements.

.3 Allow a minimum of 15 days for the review of steel shop drawings. 1.05 QUALITY ASSURANCE

.1 Manufacturer(s) shall be able to demonstrate at least ten (10) years of experience in manufacturing structures similar in complexity, material, extent and quality indicated for this project.

.2 Welders and machine operators are certified.

.3 Manufacture(s) must have demonstrated examples of work similar in scale and quality to the Triangle Park Pavilion Design.

.4 All work must follow CSI Master Specifications. 1.06 MOCKUP REQUIREMENTS

.1 Manufacture(s) must provide a mock up of connection details 1 and 2, pg A2.3.

.2 Mockups should be fabricated at full scale. .3 Mockups should display the level of surface preparation, surface, and weld

finish described in subsection 2.05. .4 Engineer’s approval of mockups is required before starting fabrication of final units. .5 Mockups should be retained until the project is complete.

Page 111: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Metal Finish Section 05900 Triangle Park Page 2 PS10074

1.07 WARRANTY

.1 The manufacture must warrant its products to be free from defects in material and/or workmanship in accordance with the warranty provisions of the General Conditions.

1.08 DELIVERY, STORAGE, AND HANDLING

.1 Ensure that all items are properly prepared, handled and/or packaged for storage and shipping to prevent damage to product.

.2 Erect finished pieces using softened slings or other methods such that they are not damaged. Provide padding as required to protect while rigging and aligning member’s frames. Weld tabs for temporary bracing and safety cabling only at points concealed from view in the completed structure or where approved by the Engineer.

2.00 PRODUCTS 2.01 MATERIALS

.1 All materials used in the contract shall be of the certifiable (mill certificates) quality, as manufactured by nationally recognized manufacturers, and of the type indicated on the drawings and in the Subsections of Division 5 “Structural Steel”.

.2 All stainless steel material to be pickled and pasivated. 2.02 SPECIAL SURFACE PREPERATION

.1 Primers: Primers must be specified. 2.03 FABRICATION

.1 General Fabrication. The fabricator is to take special care in handling the steel to avoid marking or distorting the steel members.

.1.1 All slings will be nylon type or chains with softeners or wire rope with softeners.

.1.2 Care is also taken to minimized damage to any shop paint or coating.

.1.3 If temporary braces or fixtures are required during fabrication, during shipment, or to facilitate erection, care must be taken to avoid and/or repair any blemishes or unsightly surfaces resulting from the use or removal of such temporary elements.

.1.4 Tack welds are ground smooth. .2 Fabricate and assemble The Triangle Park Pavilion in the shop to the greatest extent

possible. Locate field joints of the Triangle Park Pavilion at concealed locations or as approved by the Engineer.

.3 Fabricate the Triangle Park Pavilion with surface quality consistent with Subsections 2.05 and visual samples.

.4 Tolerances for Rolled Shapes. The permissible tolerances for depth, width, and out of square, camber and sweep of rolled shapes shall be one-half of the standard camber

Page 112: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Metal Finish Section 05900 Triangle Park Page 3 PS10074

and sweep tolerance as specified in CSA G40.20/21 and ASTM A6. The matching of abutting cross-sections shall also be required.

2.04 MEMBER AND SURFACE GENERAL CHARACTERISTICS

.1 Surface preparation to SSPC-SP 6

.2 Sharp edges ground and smooth

.3 Continuous weld appearance

.4 Standard structural bolts

.5 Weld spatters removed

.6 One-half standard fabrication tolerances

.7 Fabrication marks not apparent

.8 Welds uniform and smooth

.9 Mill marks removed

.10 Butt and plug welds ground smooth and filled

.11 Cross sectional abutting surface aligned

.12 Joint gap tolerances minimized

.13 Weld show-through minimized 2.05 FINISHES

.1 Stainless steel finishes on all visible members to be 80 Mesh Media Bead Blast Finish (Starblast XL).

.2 All exposed stainless steel welds (not covered with earth / gravel) to be ground flush to parent material and finished with a 80 Mesh Media Bead Blast Finish (Starblast XL) to match parent member shape.

.3 Galvanized metal primers: cement oil base type, Pittsburg Ironhide, or Retardo rust inhibitive paint. .4 Standard shop priming: shop prime all exposed mild steel surfaces (not imbedded in

concrete) with primer meeting CGSB 1-GP-40. Touch up or field-prime any damage or welds immediately after erection

.5 Touch-up: touch up or field-prime any damages, cuts or welds to galvanized members immediately after erection with Galvicron paint, or special primer as required.

.6 Touch-up: Fix and finish any damages, cut or welds to stainless steel members immediately after erection to match parent member.

2.06 SHOP CONNECTIONS

.1 Bolted Connections: Make in accordance with Section 051000. Provide bolt type and finish as specified and place bolt heads as indicated on the approved shop drawings.

.2 Welded Connections: Comply with CSA W59-03 and Section 051000. Appearance and quality of welds shall be consistent with Subsection 2.05 and visual samples. Assemble and weld built-up sections by methods that will maintain alignment of members to the tolerance of this Subsection.

Page 113: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Metal Finish Section 05900 Triangle Park Page 4 PS10074

2.07 ARCHITECTURAL REVIEW

.1 The Engineer shall review the Triangle Park Pavilion in place and determine acceptability based on Subsection 2.05 and visual samples. The Fabricator/Erector will advise the consultant the schedule of the work.

3.00 EXECUTION 3.01 EXAMINATION

.1 The erector shall check the Triangle Park Pavilion before delivery for twist, kinks, gouges or other imperfections, which might result in rejection of the appearance of the member. Coordinate remedial action prior to delivery.

3.02 PREPERATION

.1 Provide connections for temporary shoring, bracing and supports only where noted on the approved shop erection drawings. Temporary connections shown shall be made at locations not exposed to view in the final structure or as approved by the Engineer. Handle, lift and align pieces using padded slings and / or other protection required to maintain the appearance of the Triangle Park Pavilion through the process of erection.

3.03 ERECTION

.1 Set the Triangle Park Pavilion accurately in locations and to elevations indicated and according to CSA S16-01.

.2 In addition to the special care used to handle and erect the Triangle Park Pavilion, employ the proper erection techniques to ensure the surface quality, and pavilion geometry is maintained:

.2.1 Triangle Park Pavilion Erection tolerances: Erection tolerances shall meet the requirements of standard frame tolerances for structural steel per CSA S16-01;

.2.2 Bolt Head Placement: All bolt heads shall be placed as indicated on the structural design document. Where not noted, the bolt heads in a given connection shall be placed to one side;

.2.3 Removal of field connection aids: Run-out tabs, erection bolts and other steel members added to connections to allow for alignment, fit-up and welding in the field shall be removed from the structure. Welds at run-out tabs shall be removed to match adjacent surfaces specified in subsection 2.05. Holes for erection bolts shall be plug welded and ground smooth to match adjacent surfaces specified in subsection 2.05;

.2.4 Filling of connection access holes: Filling shall be executed with proper procedures to match architectural profile, where specified;

.2.5 Field Welding: Weld profile, quality, and finish shall be consistent with Subsection 2.05 and visual samples.

3.04 FIELD CONNECTIONS

.1 Bolted Connections: Make in accordance with Section 051000. Provide bolt type and finish as specified and place bolt heads as indicated on the approved shop drawings.

Page 114: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver Metal Finish Section 05900 Triangle Park Page 5 PS10074

.2 Welded Connections: Comply with CSA W59-03 and Section 051000. Appearance and quality of welds shall be consistent with the Category and visual samples if applicable. Assemble and weld built-up sections by methods that will maintain alignment of members to the tolerance of this Subsection.

.2.1 Assemble and weld built-up sections by methods that will maintain alignment of axes. Verify that weld sizes, fabrication sequence, and equipment used for The Triangle Park Pavilion will limit distortions to allowable tolerances.

3.05 ARCHITECTURAL REVIEW

.1 The Engineer shall review the Triangle Park Pavilion in place and determine acceptability based on Subsection 2.05 and visual samples. The Fabricator/Erector will advise the consultant the schedule of the work.

END OF SECTION

Page 115: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver ELECTRICAL GENERAL PROVISIONS Section 16010 Triangle Park Page 1 PS10074

1 GENERAL

1.1 CODES AND STANDARDS

.1 Install in accordance with CSA C22.1-2002 except where specified otherwise.

.2 Comply with CSA Electrical Bulletins and local by laws.

.3 Install overhead and underground systems in accordance with CSA C22.3 No.1-M1979 except where specified otherwise.

1.2 PERMITS AND FEES

.1 Submit to Electrical Inspection Department local Fire Authorities and Supply Authority necessary number of drawings and specifications for examination and approval prior to commencement of work.

.2 Pay associated fees.

.3 Contractor to obtain all permits required and after completion of the work, furnish to the Engineer a Certificate of Final Inspection and Approval from electrical inspection authority. Contractor to take out all permits at beginning of the work.

1.3 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES

.1 Submit shop drawings, product data and samples in accordance with the Contract requirements and Section 01330 Shop Drawings and as follows.

.2 Indicate details of construction, dimensions, capacities, weights and electrical performance characteristics of equipment or material.

.3 Where applicable, include wiring, single line and schematic diagrams.

.4 Include wiring drawings or diagrams showing interconnection with work of other Sections.

1.4 NOT APPLICABLE

1.5 NOT APPLICABLE

1.6 CARE, OPERATION AND START-UP

.1 Instruct Engineer and operating personnel in the operation, care and maintenance of equipment.

.2 Arrange and pay for services of manufacturer's factory service Engineer to supervise start-up of installation, check, adjust, balance and calibrate components, where required in these specifications.

.3 Provide these services for such period, and for as many visits as necessary to put equipment in operation, and ensure that operating personnel are conversant with aspects of its care and operation.

1.7 VOLTAGE RATINGS

.1 Operating voltages: to CAN3-C235-83.

.2 All electrical equipment to operate satisfactorily at 60 Hz within normal operating limits established by above standard. Equipment to operate in extreme operating conditions established in above standard without damage to equipment.

Page 116: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver ELECTRICAL GENERAL PROVISIONS Section 16010 Triangle Park Page 2 PS10074

1.8 INSPECTION

.1 Furnish a Certificate of Acceptance from Inspection Department on completion of work.

1.9 MATERIALS AND EQUIPMENT

.1 Equipment and material to be CSA certified and manufactured to standard quoted.

.2 Where there is no alternative to supplying equipment which is not CSA certified, obtain special approval from Inspection Department.

.3 Factory assemble control panels and component assemblies.

.4 Alternate approvals granted before the closing of tenders will be limited to a manufacturer's system and/or series only. This limited approval will not preclude substitute equipment/material from complying with specific features included with equipment/material specified. Alternate approvals will be given by written addendum only. No other substitution will be permitted after closing of tenders. Refer to Instructions to Bidders.

.5 Where alternate equipment/materials are selected, allow for effects on other parts of the work of this Trade and other Trades. Where substantial changes in arrangement are required, submit shop drawings of the proposed changes with Plan and Section views and show effects on work of other Trades. Alternate equipment/materials shall not exceed the available space limitations. No extra will be allowed due to the use of alternate equipment/materials.

.6 Determine that the alternate product meets the specification intent before basing a tender on the Product.

.7 Where two or more manufacturers are listed as acceptable, the first mentioned was used in preparing the design. Tenders may be based on any one of those named, provided that they meet every aspect of the drawings and specifications.

.8 Where other than the first-named manufacturer is selected or accepted, include the cost of any resulting work and redesign of associated services or structure and submit redesign drawings for review with the shop drawings. Redesign drawings shall be to scale and of a standard equal to the Contract Drawings and indicate changes with plan and section views and show effects on work of other Trades. No extra will be allowed due to use of alternate materials.

1.10 FINISHES

.1 Shop finish metal enclosure surfaces by removal of rust and scale, cleaning, application of rust resistant primer inside and outside and at least two coats of finish enamel.

.2 Clean and touch up surfaces of shop-painted equipment scratched or marred during shipment or installation, to match original finish.

.3 Clean and prime paint exposed hangers, racks, fastenings to prevent rusting.

1.11 WIRING IDENTIFICATION

.1 Identify wiring with permanent indelible identifying markings, either numbered or coloured plastic tapes, on both ends of phase conductors of feeders and branch circuit wiring.

.2 Maintain phase sequence and colour coding throughout.

.3 Colour code: to CSA C22.1.

.4 Use colour coded wires in communication cables, matched throughout system.

Page 117: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver ELECTRICAL GENERAL PROVISIONS Section 16010 Triangle Park Page 3 PS10074

1.12 MANUFACTURERS AND CSA LABELS

.1 Manufacturers nameplates and CSA labels to be visible and legible after equipment is installed.

1.13 WARNING SIGNS

.1 Provide warning signs, as specified or to meet requirements of Inspection Department, and the Engineer.

.2 Use decal signs, minimum 175 x 250 mm size.

1.14 TESTS

.1 Conduct and pay for tests and provide written reports for the following: .1 Main ground resistance (at all grounding locations). .2 Power and distribution system including phasing, voltage, grounding and load

balancing. .3 Circuits originating from branch distribution panels. .4 Lighting and its controls. .5 Motors, heaters and associated control equipment including sequenced operation

of systems where applicable. .6 Systems: fire & intruder alarm systems and communications. .7 Metering equipment and interface with DDC.

.2 Furnish manufacturer's certificate or letter conforming that entire installation as it pertains to each system has been installed to manufacturer's instructions.

.3 Carry out tests in presence of the Engineer.

.4 Provide instruments, meters, equipment and personnel required to conduct tests during and at conclusion of project. If applicable during these tests, equipment shall be disconnected to prevent damage to the solid state control components.

.5 Submit tests results in triplicate to the Engineer.

1.15 INSULATION RESISTANCE TESTING

.1 Megger circuit, feeders and equipment up to 350 V with a 500 V instrument.

.2 Megger 350-600 V circuits, feeders and equipment with a 1000 V instrument.

.3 Check resistance to ground before energizing.

1.16 CLEANING

.1 At time of final cleaning, clean lighting reflectors, lenses and other lighting surfaces that have been exposed to construction dust and dirt.

1.17 EXAMINATION

.1 Visit the site before preparing the tender and examine all existing conditions. No extra cost will be considered for any misunderstanding of work to be done resulting from failure to visit the site. Refer to Instructions to Bidders.

.2 Examine the documents for details of work included. Obtain a written clarification in the event of conflict within the specification, between the specification and the drawing, or in the drawing. Obtain written clarification from the Engineer if work affecting the installation is not clear. Where this is not done in advance, allow in the tender sum for providing the more costly alternative. Refer to Instructions to Bidders.

Page 118: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver ELECTRICAL GENERAL PROVISIONS Section 16010 Triangle Park Page 4 PS10074

1.18 RESPONSIBILITY

.1 Protect equipment and material from the weather, moisture, dust and physical damage.

.2 Cover equipment openings and open ends of conduit, piping and pullboxes as work progresses. Failure to do so will result in the Trade being required to adequately clean or replace materials and equipment at no extra cost to the Owner.

.3 Protect all existing services encountered. Obtain instructions from the Engineer when existing services require relocation or modification. Note existing electrical service to existing school shall not be disturbed until new school has been commissioned and occupied.

.4 Refinish damaged or marred factory finish to factory finish.

.5 The specifications and drawings form an integral part of the Contract Documents. Neither the drawings nor the specifications shall be used alone. Work omitted from the drawings but mentioned or reasonably implied in the specifications, vice versa, shall be considered as properly and sufficiently specified and shall be provided. Misinterpretation of any requirement of either plans or specifications shall not relieve this Sub-contractor of the responsibility of properly completing his trade to the approval of the Engineer.

1.19 PROJECT RECORD DRAWINGS

.1 The Contractor shall provide project record drawings.

.2 During the construction period, keep on Site a clean set of drawings marked up to reflect the "As-Built" state, for examination by the Engineer on a regular basis. Include elevations and detailed locations of buried services, empty conduit systems and junction and pull boxes.

.3 At the time of "Substantial Performance" purchase a set of CAD files from the Engineer. Allow a single per project cost of $200.00 plus $20 per drawing. Obtain the services of an approved CAD draftsperson to transfer all changes to amend the CAD files in the latest version of AutoCAD. Include all revisions and change orders. Submit the "Record Drawing" CAD files and one set of plots to the Engineer prior to issue of Final Certificate for Payment. Note: The Electrical Sub-contractor will be required to sign a standard Stantec / Contractor agreement entitled "Authorization to Use CAD drawing files". The agreement restricts the use of the CAD files to the purpose of "as-built" only and determines the editing procedures.’

1.20 CUTTING, PATCHING, TRENCHING, BACKFILLING & CONCRETE WORK

.1 The layout and execution for cutting, patching and openings is the responsibility of the Contractor. If laid out in advance the work will be done by the Contractor under the supervision of electrical sub trade.

.2 Concrete for encasement of ducts and lamp standard supports shall be provided by the Constractor , coordinated and supervised by the electrical sub trade.

.3 Excavation and backfilling refer to civil work specifications. 1.21 WORKMANSHIP

.1 Workmanship shall be in accordance with well-established practice and standards accepted and recognized by Engineers and the Trade.

Page 119: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver ELECTRICAL GENERAL PROVISIONS Section 16010 Triangle Park Page 5 PS10074

.2 The Engineer shall have the right to reject any item of work that does not conform to the Contract Documents and accepted standards of performance, quietness of operation, finish and appearance.

END OF SECTION

Page 120: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver CONDUITS & FITTINGS Section 16011 Triangle Park Page 1 PS10074

1 GENERAL

1.1 LOCATION OF CONDUIT

.1 Drawings do not show all conduits. Those shown are in diagrammatic form only.

.2 Conceal all conduits where possible. Note particular requirements for routing of conduits where detailed.

.3 Typically conduits shall not be installed in slab toppings such as the upper floor.

.4 Conduits may be installed in the lower floor slabs but limited to as detailed.

.5 Note particular details for conduit support below the lower floor slab where the fill is sacrificial.

2 PRODUCTS

2.1 CONDUITS

.1 Rigid metal conduit: to CSA C22.2 No.45-M1981.

.2 Epoxy coated conduit: to CSA C22.2 No.45-M1981 with zinc coating and corrosion resistant epoxy finish.

.3 Rigid PVC conduit: to CSA C22.2 No.136-1966.

.4 Flexible metal conduit and liquid-tight flexible metal conduit: to CSA C22.2 No.56-1977.

2.2 CONDUIT FASTENINGS

.1 One hold steel straps to secure surface conduits 50 mm and smaller. Use two hole steel straps to conduits larger than 50 mm.

.2 Beam clamps to secure conduits to exposed steel work.

.3 Channel type supports for two or more conduits.

.4 10 mm dia threaded rods to support suspended channels.

2.3 CONDUIT FITTINGS

.1 Fittings for raceways: to CSA C22.2 No.18-1972.

.2 Fittings manufactured for use with conduits specified.

.3 Provide factory "ells" where 90 degree bends are required for 32 mm and larger conduits.

2.4 EXPANSION FITTINGS FOR RIGID CONDUIT

.1 Weatherproof expansion fittings with internal bonding assembly suitable linear expansion.

.2 Watertight expansion fittings with integral bonding jumper suitable for linear expansion and 19 mm deflection in all directions.

.3 Weatherproof expansion fittings for linear expansion at entry to panel as required.

3 EXECUTION

3.1 INSTALLATION

.1 Bend conduits cold, so that conduit at any point is not flattened more than 1/10th of its original diameter. Consider conduits bent more than this or kinked as defective and replace.

.2 Field threads on rigid conduit shall be sufficient length to draw conduits up tight.

Page 121: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver CONDUITS & FITTINGS Section 16011 Triangle Park Page 2 PS10074

.3 Provide PVC covered fish cord (#12 AWG wire) in empty conduits to facilitate pulling

wiring in future. .4 Where conduits become blocked, use of corrosive agents is prohibited. Remove and

replace blocked section. .5 Conduit sizes indicated on drawings are minimum only. Increase sizes as required to

comply with Code.

3.2 CONDUITS, PIPES AND SLEEVES EMBEDDED IN CONCRETE

.1 Pipes, conduits, and sleeves embedded in concrete shall be allowed only if installed in accordance with the following guidelines.

.2 Submit layout of conduits at points of congestion and additional reinforcing and / or thicken slab and / or reroute as directed by the consultant, at contractor’s expense.

.3 Coordinate installation of embedded conduits with other divisions.

.4 Slabs and walls (conduits in plane of): .1 Locate between top and bottom reinforcing in slab or each face of wall. .2 Maximum size of conduit in one layer to be not more than one-quarter (1/4)

concrete thickness. .3 Centreline spacing between parallel conduits to be not less than 3 diameters. .4 Maximum total size of conduits crossing shall be not more than one-third (1/3)

concrete thickness. .5 Three or more layers crossing will not be permitted. .6 Sleeves through slabs are not allowed near supports without prior approval of the

consultant. .7 Locate to suit reinforcing steel. .8 Install in centre third of slab. .9 Protect conduits from damage where they stub out of concrete. .10 Where conduits pass through waterproof membrane provide oversized sleeve

before membrane is installed. Use cold mastic between sleeve and conduit. .11 Conduits to be completely encased in concrete.

3.3 EXPANSION JOINT CONDUIT FITTINGS

.1 Provide conduit expansion joint fittings at concrete expansion joints.

END OF SECTION

Page 122: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver POWER WIRING Section 16122 Triangle Park Page 1 PS10074

1 GENERAL NOT APPLICABLE.

2 PRODUCTS

2.1 MATERIALS

.1 Conductors: stranded for 10 AWG and larger.

.2 Copper conductors sized as indicated with 600/1000 volt, moisture resisting insulation of chemically cross-linked thermosetting polyethylene material (XLPE) rated RW90: to CSA C22.1-1990 Section 12. Minimum installation temperature: -40øC Maximum conductor temperature: 90øC

.3 Minimum size #12 AWG.

.4 Provide Teck90 cable. Provide ground wiring for all conduits in or below grade. Upsize conduits as required.

.5 Conductors to be colour-coded. Conductors No.10 gauge and smaller shall have colour impregnated into insulation at time of manufacture. Conductors size No.8 gauge and larger may be colour-coded with adhesive colour coding tape, but only black insulated conductors shall be employed in this case, except for neutrals which shall be white wherever possible. Where colour coding tape is utilized, it shall be applied for a minimum of 50 mm at terminations, junctions and pullboxes and condulet fittings. Conductors not to be painted.

3 EXECUTION

3.1 INSTALLATION

.1 Install all wiring as shown on plans.

.2 Wire up to and including No.6 gauge shall be spliced with nylon-insulated expandable spring-type connectors. Large conductors shall be spliced using split-bolt or other compression type connectors wrapped with cambric tape then PVC tape.

.3 Wires shall be sized for 2% maximum voltage drop to farthest outlet on a loaded circuit. Increase home run cable size to meet these requirements.

END OF SECTION

Page 123: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver GROUNDING Section 16450 Triangle Park Page 1 PS10074

1 GENERAL

1.1 REFERENCE STANDARDS

.1 Do grounding work to CSA C22.1 1998.

1.2 SCOPE OF WORK

.1 Refer to drawings for extent of grounding in addition to code requirements.

2 PRODUCTS

2.1 MATERIALS

.1 Grounding equipment to: CSA C22.2 No.41.

.2 Copper grounding conductors to: ASA G7.1-1964.

2.2 EQUIPMENT

.1 Clamps for grounding of conductor, size as required.

.2 Copper conductor at least 10 m long for each concrete encased electrode, bare, stranded, soft annealed, size as indicated.

.3 Rod electrodes, copper clad steel 20 mm dia by 3 m long as indicated.

.4 System and circuit, equipment, grounding conductors, bare stranded copper, soft annealed, sized as indicated.

.5 Insulated grounding conductors to Section 16122.

.6 Non-corroding accessories necessary for grounding system, type, size material as indicated, including but not necessarily limited to:

.1 Grounding and bonding bushings.

.2 Protective type clamps.

.3 Bolted type conductor connectors.

.4 Thermit welded type conductor connectors.

.5 Bonding jumpers, straps.

.6 Pressure wire connectors. .7 For the alternate bid (providing unit substation and integral primary disconnect) provide

necessary grounding accessories to bond grounding grid around unit substation with unit substation and also with remote secondary main distribution.

2.3 MANUFACTURERS

.1 Acceptable manufacturers: .1 Burndy Corp., Erico Inc. Cadweld Div., Fe deral Pioneer Ltd.

3 EXECUTION

3.1 INSTALLATION GENERAL

.1 Install complete permanent, continuous, system and circuit, equipment, grounding systems including electrodes, conductors, connectors, accessories, as indicated, to conform to requirements of Owner, and local authority having jurisdiction over installation. Coordinate ground rod installation with local soil conditions to assure proper grounding system.

Page 124: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver GROUNDING Section 16450 Triangle Park Page 2 PS10074

.2 Install connectors to manufacturer's instructions. .3 Protect exposed grounding conductors from mechanical injury. .4 Make buried connections, and connections to conductive water main and electrodes,

using copper welding by thermit process or approved equal methods. .5 Use mechanical connectors for grounding connections to equipment provided with lugs. .6 Soldered joints not permitted. .7 Install bonding wire for flexible conduit, connected at both ends of grounding bushing,

solderless lug, clamp or cup washer and screw. Neatly clip bonding wire to exterior of flexible conduit.

.8 Connect building structural steel and metal to ground by welding copper to steel.

.9 Make grounding connections in radial configuration only, with connections terminating at single grounding points. Avoid loop connections.

3.2 TESTS

.1 Perform tests in accordance with Section 16010.

.2 Perform ground continuity and resistance tests using method appropriate to site conditions and to approval of Consultant and local authority having jurisdiction over installation. Confirm test results in writing to the consultant.

.3 Carry out all tests required by the Provincial Electrical Inspection Dept. and provide all required reports. Include all associated costs.

.4 Perform tests before energizing electrical system. Submit test results to consultant to include results of grounding resistance tests, prior to energizing the system.

END OF SECTION

Page 125: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver LIGHTING GENERAL DESCRIPTION Section 16505 Triangle Park Page 1 PS10074

1 GENERAL

1.1 INTENT

.1 Provide lighting fixtures and accessories for as shown on drawings.

.2 Lighting fixtures shall be structurally well designed and constructed, using new parts and materials of the highest commercial grade available.

.3 Ground all lighting equipment to grounding system.

2 PRODUCTS

2.1 LAMPS

.1 Provide and install lamps in all fixtures in the project.

.2 Store the lamps in a safe place and install them in accordance with the requirements of this specification leaving fixtures completely lamped and in operating condition.

.3 Dimensions and electrical characteristics shall meet the requirements of CSA Specification C10-1951. New lamps shall be installed on completion of project.

2.2 FIXTURES

.1 All fixtures shall comply with CSA Standard C22.2 No.9-1968. Accessories and components shall comply with relevant CSA Standards applicable to accessory or components.

.2 The electrical trade shall supply and install all necessary supports, etc., required for complete and proper installation.

.3 Fixtures shall incorporate adequate gasketting, stops and barriers to form light traps and prevent light leaks.

.4 Illuminators shall be designed for adequate dissipation of heat to avoid short ballast/lamp life, nuisance thermal tripping and decreased lamp output. Heat test reports by independent laboratories shall be provided where required by the Consultant.

3 EXECUTION

3.1 INSTALLATION AND SUPPORTS

.1 Provide complete and proper support for all fixtures.

.2 All supports, fastenings or accessory fittings shall be protected against corrosion. Care shall be taken during the installation to assure that insulation and corrosion protection is not damaged.

END OF SECTION

Page 126: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver LUMINAIRES Section 16510 Triangle Park Page 1 PS10074

1 GENERAL

1.1 RELATED WORK

.1 Lighting general description: Section 16505.

1.2 SHOP DRAWINGS & PRODUCTS DATA

.1 Submit shop drawings and product data in accordance with Section 16010.

.2 Submit complete photometric data prepared by independent testing laboratory for luminaires specified.

.3 Submit samples as requested by the Engineer.

1.3 GUARANTEE

.1 Replace illuminators that fail within 12 months of issuance of Certificate of Total Performance.

.2 Replace any lamps that fail within three months of issuance of Certificate of Total Performance.

1.4 LUMINAIRES/ILLUMINATORS NOTES

.1 Illuminators to be supplied complete with bolt anchors, mounting hardware, supports, gaskets as required for a complete and finished installation.

.2 Fixtures shall be completely assembled in factory and shall be delivered in their original cartons.

1.5 SUBSTITUTIONS

.1 Refer to Section 16010.

2 PRODUCTS

2.1 MATERIALS

.1 Incandescent and electric discharge fixtures: to CSA C22.2 No.9-1968.

.2 Socket screw-shell lampholders: to CSA C22.2 No.43-1965.

.3 Electric discharge lampholders: to CSA C22.2 No.74-1969.

.4 Incandescent lamps: to CSA C10-1951 and CSA C22.2 No.84-1974.

.5 Tungsten halogen lamps: to CSA C22.2 No.84-1974.

.6 HID lamps: to ANSI C78 series.

.7 Fluorescent lamps: to ANSI C78 series.

.8 Ballasts: to CSA C22.2 No.74-1969.

2.2 SPARE LAMPS

.1 Provide 2% spare lamps for all types supplied (rounded up to nearest unit).

2.3 FLUORESCENT LUMINAIRES

.1 Fixture alternatives to be equal to the first specified product and as modified by the minimum requirements in the Schedule.

Page 127: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver LUMINAIRES Section 16510 Triangle Park Page 2 PS10074

.2 Refer to Section 16010.1.9 for approved alternative procedure.

3 EXECUTION

3.1 INSTALLATION

.1 Locate luminaires as indicated.

3.2 WIRING

.1 Connect luminaires to lighting circuits as indicated.

3.3 TESTS

.1 Perform tests in accordance with Section 16010.

.2 Check luminaires and replace defective lamps, ballasts and accessories.

END OF SECTION

Page 128: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 031000 Triangle Park CONCRETE FORMWORK PS10074 PAGE 1

1.0 GENERAL 1.1 DESCRIPTION

.1 Related Sections:

.1 Concrete Reinforcement Section 032000 .2 Cast-in-place Concrete Section 033000 .3 Concrete Finishes Section 033500 .4 Structural Steel Section 051000

All codes and documents referred to in this Section are to be the current adopted edition.

1.2 REFERENCE STANDARDS

.1 CAN/CSA A23.1, Concrete Materials and Methods of Concrete Construction.

.2 City of Vancouver Building By-law 2007. 1.3 INSPECTION AND TESTING

.1 Immediately before concrete is placed, all forms shall be carefully inspected to ensure

that they are properly placed, sufficiently rigid and tight, thoroughly clean, properly treated and free from snow, ice or other foreign materials.

.2 Temporary openings shall be provided at the bottom of all deep units, such as columns and

walls, to facilitate cleaning and inspection. In restricted units they shall be located so that water can be used to wash out debris. They shall be closed with patches flush on the inside. Cleanouts shall be located bearing architectural considerations in mind.

.3 Forms shall not have patches, broken edges, or joint widths greater than 1.5 mm, except

for cleanouts as noted above. 2.0 PRODUCTS 2.1 MATERIALS

.1 Forms

.1 Type A Concrete: Concrete form materials for this type of concrete shall be as per “Rough Form Finish”, CSA A23.1-00, Section 24.3.5.

.2 Type B Concrete: Concrete form materials for this type of concrete shall be as per

“Smooth Form Finish”, CSA A23.1-00, Section 24.3.6. Form work shall be high density overlay plywood, 19mm Douglas Fir plywood with phenolic resin impregnated cellulose fibre sheet bonded on face. Back and all edges sealed.

.3 Type C Architectural Concrete: Concrete form materials for this type of concrete

shall be as per “Formwork for Special Architectural Finishes”, CSA A23.1-00, Section 27.4. Form work shall be high density overlay plywood, 19mm Douglas Fir plywood with phenolic resin impregnated cellulose fibre sheet bonded on face. Back and all edges sealed. Seal joints between panels with closed cell PVC foam tape with pressure sensitive adhesive on one side.

Page 129: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 031000 Triangle Park CONCRETE FORMWORK PS10074 PAGE 2

.4 Round Column Forms: Shall be lined with no horizontal joints, no vertical seams

and no diagonal lines apparent on stripped columns. .5 Form Release Agent: Chemically active release agents containing compounds that

react with free lime present in concrete to provide water insoluble soaps, preventing concrete from sticking to forms. Form release agents and curing agents shall be compatible with applied finishes where applicable. Do not use release agents containing wax or oil in contact with concrete to receive applied coatings. a) Vegetable based: 100% biodegradable, zero-VOC, rapeseed or soy-based b) Water based: Biodegradable, maximum VOC content allowed: 55

grams/litre

.6 Form Ties: free of devices leaving holes larger than 25mm dia. in concrete surface; a) Type A and Type B Concrete: Ties shall generally be placed symmetrically

about all sections with plywood sheets and from each wall section. b) Type C Concrete: Ties shall be placed in accordance with reviewed shop

drawings and mock-up. c) Cone-Tie Hole Plugs: Pre-formed concrete tie hole plugs shall be inserted

and sealed into cone tie holes in exposed architectural concrete areas within 10mm recess to plug surface.

.7 All formwork shall conform with CSA A23.1.

2.2 DESIGN

.1 Formwork design and inspection is solely the responsibility of the Contractor. 3.0 EXECUTION 3.1 PLACING

.1 Erect and brace formwork plumb and true.

.2 Forms shall be so constructed that the finished concrete will conform to the shapes, lines,

grade and dimensions indicated on the drawings. Particular care to be taken with all exposed concrete.

.3 Apply form coating in accordance with manufacturer's recommendations prior to placing of reinforcing steel. Remove any excess form coating.

.4 Install all inserts including anchors, ties, bolts, nailers, form for holes and such like as

required by work of this or other trades.

.5 Untreated forms shall be kept wetted down to prevent shrinkage prior to the placing of the concrete and shall be surface wetted at the time of placing.

.6 Where concrete is to be exposed, forms shall be laid so that joints are kept to a minimum

and located in an orderly and symmetrical arrangement where possible.

.7 Strength and rigidity of forms shall be such that they will not deflect or leak mortar.

Page 130: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 031000 Triangle Park CONCRETE FORMWORK PS10074 PAGE 3

.8 Forms for exposed exterior concrete shall not be reused if there is any evidence of surface wear and tear which will impair the quality of the concrete. Forms shall be thoroughly cleaned and re-lubricated with approved form oils before reuse.

.9 Removal of form ties shall be done carefully to avoid marking concrete and to allow for

patching. Grout bottom of form tie hole to prevent rust staining.

.10 At times of placing, all formwork shall have been thoroughly washed and shall be clean and free of all dirt and debris. Formwork shall be wetted down to eliminate suction as far as practicable and wash water shall be drained away.

3.2 CLEAN UP

.1 Remove debris and excess material in accordance with the requirements of the Contract

Documents.

END OF SECTION 031000

Page 131: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 032000 Triangle Park CONCRETE REINFORCEMENT PS10074 PAGE 1

1.0 GENERAL 1.1 DESCRIPTION

.1 Related Work Specified Elsewhere:

.1 Concrete Formwork Section 031000

.2 Caste-in-place Concrete Section 033000

.3 Concrete Finishes Section 033500

.4 Structural Steel Section 051000

All codes and documents referred to in this Section are to be the current adopted edition. . 1.2 REFERENCE STANDARDS

.1 CAN/CSA A23.1, Concrete Materials and Methods of Concrete Construction.

.2 City of Vancouver Building By-law 2007.

.3 CAN/CSA G30.18, Billet-Steel Bars for Concrete Reinforcement.

.4 Provide weldable reinforcement to CAN/CSA G30.18 and perform welding to CSA W186.

.5 CAN/CSA G30.5. 1.3 INSPECTION AND TESTING

.1 Placing and reinforcement shall be reviewed by the Engineer prior to any concrete being

placed in the section to be poured. .2 All steel required for the section shall be placed, before the Engineer shall give permission

will be given to place concrete.

.3 Furnish mill certificates of physical and chemical analysis in accordance with CSA G30.18, if requested.

1.4 SUBMITTALS

.1 Shop Drawings: .1 Prepare and check reinforcing steel and mesh placing drawings and bar bending

and cutting schedules for all steel reinforcing for structural concrete. All drawings and schedules shall be prepared and checked by competent personnel experienced with this type of work.

.2 Structural drawings take precedence over placement drawings and bar schedules

unless otherwise instructed in writing by the Engineer. 1.5 DELIVERY AND STORAGE

.1 Reinforcing steel, welded wire fabric and accessories shall be delivered, handled and stored in a manner which prevents contamination from bond-reducing foreign matter and damage to its fabricated form.

.2 Ship bundles of bar reinforcement, identified clearly in accordance with bar list.

1.6 CLEANING

Page 132: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 032000 Triangle Park CONCRETE REINFORCEMENT PS10074 PAGE 2

.1 Before being placed, all reinforcement shall be clean from loose, scaly rust, dirt, oil, paint

or other coatings that may be detrimental. A slight film of red rust will not be considered objectionable.

2.0 PRODUCTS 2.1 MATERIALS

.1 All reinforcing steel, unless otherwise noted, shall be deformed bars of Grade 400 new billet steel conforming to the current CSA G30.18.

.2 Welded wire fabric shall conform to CSA G30.5, sizes and gauges as shown on the drawings. .3 Provide all accessories such as stirrups, hanger bars, spirals, wire ties, chairs, spacers,

supports and other devices required to install and secure the reinforcing properly, to CSA A23.1.

2.2 FABRICATION

.1 All reinforcing bars shall be bent cold. Reinforcing bars shall not be straightened or re-bent. .2 Location of reinforcement splices not shown on the drawings shall be approved by the

Engineer and shall, for beams and slabs, be away from points of maximum stress in the steel. Splices shall provide sufficient lap to transfer the stress between bars by bond and shear in accordance with CSA A23.3.

.3 All welded wire fabric of 5.9mm diameter and larger bar sizes shall be provided in flat

sheet unless otherwise authorized by the Engineer.

3.0 EXECUTION 3.1 PLACING

.1 Reinforcement of the size and shapes shown on the drawings shall be accurately placed in

accordance with the Placement Drawings, Structural Drawings, requirements of the B.C. Building Code, CSA A23.1 and CSA A23.3.

.2 Clear distance between bars, except for columns, shall be not less than the nominal

diameter of the bar, or 25mm or one and one third (1-1/3) times the maximum size of the coarse aggregate. Bars placed in two or more layers shall have a minimum clear distance between the layers of not less than 25mm and shall be placed directly above and below each other.

.3 Clear distance between bars in columns shall be not less than one and one half the nominal

diameter of the bars or 38mm or one and one half (1-1/2) times the maximum size of the coarse aggregate.

Page 133: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 032000 Triangle Park CONCRETE REINFORCEMENT PS10074 PAGE 3

.4 Reinforcing steel shall, where not otherwise shown on the Structural drawings, be protected by the clear cover of concrete over the reinforcements as follows: .1 Where concrete is deposited against the ground without the use of forms, not less

than 75mm. .2 Where concrete is placed against forms to be exposed to weather, or be in contact

with the ground, not less than 50mm for bars larger than 15M and not less than 38mm for bars 15M and smaller.

.3 In slabs and walls not exposed to the ground or weather, not less than 25mm.

.4 In beams, girders and columns not exposed to the ground or weather, not less than 38mm.

.5 The foregoing clear covers shall be maintained within + 6mm.

.6 Reinforcement shall be adequately supported by metal chairs, spacers or hangers and secured against displacement within the tolerance permitted, and in accordance with CSA A23.1 and CSA A23.3.

.7 For concrete exposed to view, all chairs and items in contact with the exposed surface shall be to the Engineers approval.

3.2 FIELD BENDING

.1 Do not field bend reinforcement except where indicated or authorized by the Engineer. .2 When field bending is authorized, bend without heat, applying slow, steady pressure as

instructed. .3 Replace bars which develop cracks or splits.

3.3 CLEAN UP

.1 Remove debris and excess material in accordance with the requirmenets of the Contract

Documents.

END OF SECTION 032000

Page 134: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 033000 Triangle Park CAST-IN-PLACE CONCRETE PS10074 PAGE 1 1.0 GENERAL 1.1 DESCRIPTION

.1 Related Sections: .5 Concrete Formwork Section 031000 .1 Concrete Reinforcement Section 032000 .3 Concrete Finishes Section 033500 .8 Precast Hollow Core Panels Section 034100

.2 All codes and documents referred to in this Section are to be the current adopted edition. 1.2 REFERENCE STANDARDS

.1 CAN/CSA A23.1, Concrete Materials and Methods of Concrete Construction. .2 City of Vancouver Building By-law 2007.

1.3 SUBMITTALS

.1 Mock Up: .1 Provide slab mock up in an isolated, unexposed slab area for approval of finish

and colour. Accepted mock up may remain part of work. 1.4 INSPECTIONS AND TESTING

.1 All required sampling, preparation of specimens and testing shall be performed by an independent testing agency hired by the Contractor and approved by the Engineer. The Contractor/testing agency shall report immediately to the Engineer when any procedure is contrary to the specifications and good practice.

.2 Testing costs will be paid by the Contractor. .3 Cost of supplying materials for samples shall be borne by the Contractor. Contractor to

inform Testing Agency with sufficient notice prior to concrete pour, and cooperate with same in obtaining required samples.

.4 The testing agency will perform the following:

.1 Review mix designs for conformance with specifications, providing written report to Engineer.

.2 Test cement and aggregates for conformance with the material requirements of the specification.

.3 Supply cylinder moulds, sample the concrete, make and cure test cylinders and perform compressive strength tests in accordance with CSA A23.2.

.4 Make slump tests and air content tests in accordance with CSA A23.2 for each concrete test.

.5 Take three (3) test cylinders for each 50 cu.m. or fraction thereof and for each class of concrete placed in any one day, except that in no case shall a class of concrete be represented by less than three (3) tests.

.6 All cylinders shall be made from concrete taken from the forms.

.7 The Engineer may at his discretion reduce or eliminate the test cylinders to be taken for minor pours or pours not of structural significance.

Page 135: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 033000 Triangle Park CAST-IN-PLACE CONCRETE PS10074 PAGE 2

.8 A compression strength of one cylinder of each set shall be performed at the test specimen age of seven (7) days.

.9 Compression strength test of the remaining two cylinders of each group shall be performed at the test specimen age of twenty-eight (28) days.

.10 One 28-day strength test shall mean the average compressive strength of two (2) companion test specimens.

.11 Test results shall meet "Concrete Test Strength Requirements" of the B.C. Building Code.

.12 Certified copies of the test reports shall be forwarded to the Engineer, Contractor and Concrete Producer.

.5 Should any test indicate concrete below strength, the Engineer shall have the right to

stop work on the suspect area until subsequent tests are made. The Contractor shall bear the cost of such required tests. Should all tests indicate below strength concrete, the Contractor shall remove this portion of the work at the Engineer's request. The removal and replacement of this work will be at the Contractor's expense.

.6 Contractor shall supply proposed mix designs to Testing Agency and obtain approval

from Engineer minimum 14 days prior to first concrete pour.

1.5 PROTECTION

.1 Cold Weather Requirements: Shall be in accordance with CSA A23.1. .2 Hot Weather Requirements: Shall be in accordance with CSA A23.1.

2.0 PRODUCTS 2.1 MATERIALS

.1 Cement: Type 10, Normal Portland, shall conform CSA CAN3-A5. .2 Aggregates: Fine and coarse, shall conform to CSA A23.1. .3 Water: Mixing water for concrete shall be clean and free from injurious amounts of

oils, acids, alkali, organic matter, or other deleterious substances. .4 Air Entraining Admixtures: Shall conform to the requirements of the latest issue of

ASTM C260, such as: .1 "N.V.R." by Sternson Ltd. .2 "DAREX AEA" by Grace Construction Materials. .3 "MB-VR" by Masters Builders.

.5 Curing Compounds: to CSA A23.1 white Type 1 - chlorinated rubber, suitable for interior use and compatible with floor finish adhesives.

.6 Integral Concrete Colour Additive: Colour additives shall contain pure, concentrated

mineral pigments specially processed for mixing into concrete and complying with ASTM C979-82. Colour additives containing carbon black are not acceptable. Approved Product: .1 Davis Colours, colour to be selected by Consultant.

Page 136: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 033000 Triangle Park CAST-IN-PLACE CONCRETE PS10074 PAGE 3

.7 Form Coatings: Non-staining form coatings such as "NOX-CRETE" by Grace Construction Materials or other pre-approved.

.8 Isolation Joint Filler: 12 mm thick asphalt impregnated rigid board of cane fibre such

as: .1 "FLEXCELL" by Sternson Ltd. .2 "GIVENTAKE" by Spicers. .3 "KORK-PAK" by Grace Construction Materials.

.9 Water Stops: .1 Size: 6" x 3/8". .2 Type: DURAJOINT TYPE '5' or other pre-approved. .3 Material: P.V.C. shall be as shown on drawings.

.10 Under slab damp proof membrane/vapour barrier: 6 mil thick polyethylene film. .11 Joint Sealant: Shall be self-levelling two (2) part polyurethane type, conforming to

CGSB 19.24 Type 1, or Federal Specification TT-S-00227E, Type II, Class A. Approved Type: Iso-Flex 880 GB (Self-Levelling) Sealant as manufactured by Harry S. Peterson Co. Inc., Sternson RC2-SL, Vulkem 245, or other pre-approved sealant. Colour as selected by the Architect from standard range. Primers and bond breakers as required to install the perimeter joint sealant system shall be provided in strict accordance with sealant manufacturer's recommendations.

.12 Sonotube Form: Are to be non-spiral, smooth pvc liner with no visible seams.

2.2 MIXES

.1 Proportions: As recommended in CSA A23.1; to be a guide for the water cement ratio to give durable concrete. Minimum cement content for concrete exposed to view to be 300 kg per cubic metre, unless otherwise specified.

.2 Strengths, Slumps, Sizes of Aggregates: See Structural drawings. .3 Admixtures:

.1 Specified air entraining agent shall be added to all concrete exposed to weather. The amount of air entrainment to be 6% + 1%, unless noted otherwise on structural drawings or approved by the Engineer.

.2 Obtain Engineer’s approval before using chemical admixtures other than those specified. Chloride admixtures not permitted without the Engineer's approval.

.4 Consistency: Concrete materials shall be proportioned to provide a workable mix that

can be handled, placed and worked into angles and corners of forms and around reinforcing steel and inserts. The mix proportions shall not be such that the concrete will easily segregate or cause excessive water to collect on the surface.

3.0 EXECUTION 3.1 GENERAL

.1 All concrete shall be "controlled concrete" according to CSA A23.1 and as defined by B.C. Building Code.

Page 137: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 033000 Triangle Park CAST-IN-PLACE CONCRETE PS10074 PAGE 4

3.2 OPENINGS AND INSERTS

.1 Provide and cast-in all sleeves, frameouts, inserts and fastening devices shown on the drawings, except as otherwise specified. This includes but is not limited to OWSJ support, Precast Hollow Core Panel support, sunshade/trellis support and structural stair support. Sleeves, openings, etc., greater than 300 mm x 300 mm not indicated on structural drawings must be approved by the Engineer.

.2 Anchor bolts and other anchoring devices for beams, columns and wall panels shall be

supplied by the respective trade and installed under this section in accordance with the trade-approved shop drawings.

.3 Sleeves, inserts and fastening devices required by other trades, but not shown on the

drawings shall be supplied by the respective trade and installed under this section. The installation shall be checked and verified by the respective trade.

.4 Openings and driven fasteners required in the concrete work after the concrete is

placed shall be approved by the Engineer. .5 Notify other trades sufficiently in advance to ensure that provision is made for

openings, inserts and attachments. .6 Paint exposed threads of anchor bolts with a mixture of molybdenum disulfide in oil

before nuts are installed. .7 Do not eliminate or displace reinforcement to accommodate hardware. If inserts

cannot be located as indicated, obtain approval of all modifications from the Engineer before placing concrete.

.8 Check locations and sizes of sleeves, openings, etc., shown on structural drawings with

architectural, mechanical and electrical drawings.

3.3 CONCRETE SUPPLY

.1 Submit a copy of the proposed concrete mixes, approved by the Testing Agency for review by the Engineer before any concrete is delivered to the site.

.2 Transportation shall be done in such a fashion that no segregation occurs. .3 Concrete which has commenced to stiffen shall not be used nor shall it be re-tempered

with additional water or cement for use.

3.5 MIXING AND DELIVERY

.1 Concrete shall be mixed in a mechanical batch mixer of a type approved by the Engineer and meeting requirements of CSA A23.1.

.2 Mixing time shall conform to CSA A23.1. Mixers shall be rotated at the rate

recommended by the manufacturer of the equipment.

Page 138: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 033000 Triangle Park CAST-IN-PLACE CONCRETE PS10074 PAGE 5

.3 Concrete from the mechanical batch mixer shall be transported to the project site in agitating or non-agitating equipment conforming to CSA A23.1.

.4 Ready-mixed or transit-mixed concrete shall be batched, mixed and transported in

accordance with CSA A23.1. 3.6 CONVEYING

.1 Concrete shall be conveyed from the mixer to the place of final deposit by methods that will prevent separation or loss of materials.

.2 Equipment for chuting, pumping and pneumatically conveying concrete shall be of such

size and design as to ensure a practically continuous flow of concrete at the delivery end without separation of materials.

.3 Conveying of concrete shall be in accordance with CSA A23.1.

3.7 PLACING

.1 Preparation:

.1 Notify the Engineer and the independent testing agency at least 48 hours prior to any concrete operation. No concrete shall be delivered to the project unless permission to pour has been obtained from the Engineer.

.2 All excavations for footings and all forms shall be pumped clear of water

before placing concrete therein. .3 Formwork shall have been completed, reinforcement shall have been secured

in place; expansion joint material, anchors, and other embedded items shall have been positioned; and the entire preparation reviewed by the Engineer, or the Engineers agent prior to placing concrete.

.4 Formwork shall have been thoroughly washed and shall be clean and free of all

dirt and debris. Formwork to be wetted down to eliminate suction as far as practicable and wash water to be drained away.

.5 Under slab dampproof membrane/vapour barrier: Install membrane over

prepared granular base to entire areas of slabs-on-grade. Lap membrane minimum 150 mm at joints and seal using tape or sealant, to produce continuous installation. Seal punctures in membrane before placing concrete. Use patching material at least 150 mm larger than puncture and seal using tape or sealant.

.2 Depositing:

.1 Concrete shall be deposited in the forms as close as is practicable to its final position to avoid segregation due to rehandling of flow and in approximately horizontal lifts to maintain a level surface.

.2 To prevent segregation, the vertical height of free fall of concrete shall not

exceed 1500mm.

Page 139: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 033000 Triangle Park CAST-IN-PLACE CONCRETE PS10074 PAGE 6

.3 When placing has started, it shall be carried on as a continuous operation until placement of the panel or section is completed. The top surface shall be kept level throughout the pour.

.4 While concrete is being placed, it shall be consolidated thoroughly and

uniformly by means of vibrators or finishing machines to secure a dense, homogeneous structure, close bond with reinforcing and smooth formed surfaces.

.5 Vibrator to be the internal type having a minimum frequency of 7,000

revolutions per minutes. A spare vibrator shall be on hand during all concrete placing. Extreme care shall be taken to ensure that internal type vibrators do not disturb the reinforcing steel or the forms.

.6 Ensure reinforcement and inserts are not disturbed during concrete placement.

3.8 FINISHING - UNFORMED SURFACES

.1 Finishing shall conform to CSA A23.1 as specified under Section 03350 - Concrete Finishes.

.2 Unless noted otherwise, floor finishes shall have gaps less than or equal to 8mm under

a 3000 straight edge.

3.9 FINISHES - FORMED SURFACES

.1 All formed surfaces shall be treated in accordance with CSA A23.1 as specified under Section 03350 Concrete Finishes.

.2 All round columns exposed to view to be formed with sonotubes (see Section 2.1.11).

3.10 CURING

.1 Concrete shall be cured in accordance with CSA A23.1. .2 Slabs shall be cured using curing compound as specified. Coverage rate and method of

application shall be in accordance with Manufacturer's printed specifications. .3 Freshly placed concrete shall be protected from the effects of direct sunshine, drying

winds, cold, excessive heat and running water, by the use of adequate tarpaulins or other suitable material to cover completely or enclose all freshly finished surfaces, until the end of the curing period.

3.11 CONSTRUCTION JOINTS

.1 The location and detail of all construction joints not detailed on the Structural drawings shall be approved by the Engineer.

.2 Construction joints shall conform to CSA A23.1. .3 In beams and slabs, construction joint locations shall be approved by the Engineer prior

to their installation. Proper key and dowels or extensions of reinforcing shall be provided at all construction joints.

Page 140: City of Vancouver General Section 01005 Triangle Park ...

City of Vancouver SECTION 033000 Triangle Park CAST-IN-PLACE CONCRETE PS10074 PAGE 7

3.12 JOINT FILLERS AND SEALERS

.1 Provide joint fillers and sealers at interior slabs on grade at junctions with vertical surfaces and at exterior concrete paving at the location and to the details shown on the drawings.

.2 Particular care shall be taken to construct clean joints free from any foreign material

which will impair the proper function of the joint. .3 Joint filler material shall be anchored to the previously poured concrete surface. .4 Unless shown otherwise, joint filler shall extend for the full depth of the joint and shall

terminate 12mm below the top of the joint. The 12mm space shall be filled with joint sealer specified.

3.13 CLEAN UP

.1 Remove debris and excess material in accordance with the requirements of the Contract Documents.

END OF SECTION