CITY OF LAREDO, TEXAS UNITEC WWTP – PHASE I EXPANSION – FY 2020 ADDENDUM NO. 4 May 4, 2020 BID DUE DATE: May 7, 2020 by 4:00 PM BID OPENING: May 8, 2020 at 10:00 AM The following additions, deletions, modifications, or clarifications shall be made to the appropriate sections of the plans and specifications and shall become a part of the Contract Documents. Bidders shall acknowledge receipt of this Addendum in the space provided on the Bid form. I. General Notice A. Reminder: Bids are due on Thursday May 7, 2020 at 4:00 PM. Instruction for Manual Bid Drop-Offs can be found in the following link: https://www.cityoflaredo.com/assets/manual_bid_dropoff_procedures.pdf B. The City will be holding the bid opening via live video stream. Live stream can be accessed via the following link: http://laredotx.swagit.com/live C. A video of the Unitec WWTP project site can be downloaded via the following link: https://share.lnvinc.com/index.php/s/B8BkeKFx4BKZkj2 D. A list of prospective bidders is available for viewing on the City’s website. II. Contract Documents A. Division A 1. Section A-02 Table of Contents Delete: The document in its entirety. ADD: The revised document (see Attachment No. 1), in lieu thereof. 2. Section A-05 Bid Proposal, Affidavit and Bid Schedule; Bid Bond; and Certificate of Interested Parties Delete: The document in its entirety. ADD: The revised document (see Attachment No. 2), in lieu thereof. III. Construction Documents and Technical Specifications A. Specification Section 40 05 59.23 Stainless Steel Slide Gates ADD: The Stainless Steel Slide Gate specification SECTION 40 05 59.23 (see Attachment No. 3), in lieu thereof.

Transcript of CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33...

Page 1: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

CITY OF LAREDO, TEXAS UNITEC WWTP – PHASE I EXPANSION – FY 2020

ADDENDUM NO. 4 May 4, 2020

BID DUE DATE: May 7, 2020 by 4:00 PM BID OPENING: May 8, 2020 at 10:00 AM The following additions, deletions, modifications, or clarifications shall be made to the appropriate sections of the plans and specifications and shall become a part of the Contract Documents. Bidders shall acknowledge receipt of this Addendum in the space provided on the Bid form.

I. General Notice

A. Reminder: Bids are due on Thursday May 7, 2020 at 4:00 PM. Instruction for Manual Bid Drop-Offs can be found in the following link: https://www.cityoflaredo.com/assets/manual_bid_dropoff_procedures.pdf

B. The City will be holding the bid opening via live video stream. Live stream can be accessed via the following link: http://laredotx.swagit.com/live

C. A video of the Unitec WWTP project site can be downloaded via the following link: https://share.lnvinc.com/index.php/s/B8BkeKFx4BKZkj2

D. A list of prospective bidders is available for viewing on the City’s website.

II. Contract Documents

A. Division A

1. Section A-02 Table of Contents

Delete: The document in its entirety.

ADD: The revised document (see Attachment No. 1), in lieu thereof.

2. Section A-05 Bid Proposal, Affidavit and Bid Schedule; Bid Bond; and Certificate of Interested Parties

Delete: The document in its entirety.

ADD: The revised document (see Attachment No. 2), in lieu thereof.

III. Construction Documents and Technical Specifications

A. Specification Section 40 05 59.23 Stainless Steel Slide Gates

ADD: The Stainless Steel Slide Gate specification SECTION 40 05 59.23 (see Attachment No. 3), in lieu thereof.

Page 2: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Unitec WWTP – Phase I Expansion – FY 2020 Addendum No. 4

Page 2 of 4

6010 McPherson, Ste. 110 | Laredo, TX 78041 | 956.462.5511 | www.ardurra.com

B. Specification Section 40 05 71.33 Telescoping Valve

ADD: The Telescoping Valve specification SECTION 40 05 71.33 (see Attachment No. 4), in lieu thereof.

C. Specification Section 46 02 01 Circular Spiral Scraper Clarifier

Delete: The section 1.4 Design Criteria in the specification Section 46 02 01 in its entirety.

ADD: The following Table in the section1.4 Design Criteria in the Section 46 02 01, in lieu thereof.

1.4 DESIGN CRITERIA Average daily Influent flow rates per clarifier 0.18 MGD Peak Influent flow rates per clarifier 0.72 (4Q) MGD Tank diameter (ft.): 35 feet Side water depth (ft.): 12 feet (Total depth 15.9 feet) Freeboard (ft.): 1.0 foot min. Bottom slope (in./ft.): 2:12 Minimum Continuous Torque (ft-lb): 8,000 ft-lb Minimum Momentary Peak Torque (ft-lb): 18,000 ft-lb

D. Specification Section 33 32 16 Wastewater Lift Station

Delete: The section 1.1.B in the specification 33 32 16 in its entirety.

ADD: The following section 1.1.B in the specification 33 32 16, in lieu thereof.

B. The two pumps together shall be designed to pump 2% abrasive slurries of wastewater grit, debris and organics solids without clogging at a minimum flow rate of 150 gpm for 2 two equal sized pumps operating simultaneously @ 45-feet of Total Dynamic Head (TDH).

Note: When future third (3rd) Pump is installed – 225 US gpm 59’ TDH.

All guide rails, brackets, anchors, and supports to be 316 stainless steel (including base elbow and rails for future 3rd pump). The pump(s) shall be manufactured by a company regularly engaged in the manufacture and assembly of similar units for a minimum of twenty-five (25) years.

Page 3: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Unitec WWTP – Phase I Expansion – FY 2020 Addendum No. 4

Page 3 of 4

6010 McPherson, Ste. 110 | Laredo, TX 78041 | 956.462.5511 | www.ardurra.com

E. Specification Section 33 32 17 MLSS Lift Station (ALT#2)

Delete: The 1.1.B in the specification 33 32 17 in its entirety.

ADD: The following section 1.1.B in the specification 33 32 17, in lieu thereof.

B. The two (2) equal sized pumps together shall be designed to pump 2% abrasiveslurries of wastewater grit, debris and organics solids without clogging. Eachpump should be designed for a flow rate of 306 gpm @ 33-feet of total head. Thepump shall be capable of passing 3” solids.

F. Specification Section 33 32 17 MLSS Lift Station (ALT#2)

Delete: The 1.1.B in the specification 33 32 17 in its entirety.

ADD: The following section 1.1.B in the specification 33 32 17, in lieu thereof.

IV. Bidder Questions

Q1 : The spec Section 33 32 16 is asking for submersible grinders but it also reads that the pump shall pass 3” solids. Can you please clarify if you are expecting a true grinder pump or a non-clog pump?

A1: The section 33 32 16 refers to grinder type pumps. Refer to the above revision in section D of this addendum.

Q2: On C16 there is a note on the lifting system to see sect 151620, where is that?

A2: Please disregard the note “see sect 151620” on plan sheet C16.

Q3 : How will the pumps be lowered and raised specified under the spec Section 33 32 16? Will there be an overhead hoist structure? Is there any requirement for any base and guide rails for the 3rd future pump? Is there any upper or lower brackets to be provided for the 3rd future pump?

A3: No hoist structure to be provided for the pumps specified in the section 33 32 16. The pumps will be lowered or raised via city’s mobile hoist(truckmounted equipment). No upper or lower brackets to be provided for the 3rd

future pump specified in the section 33 32 16. Guiderails and base to beprovided for the two pumps, not for the 3rd Future pump.

Page 4: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Unitec WWTP – Phase I Expansion – FY 2020 Addendum No. 4

Page 4 of 4

6010 McPherson, Ste. 110 | Laredo, TX 78041 | 956.462.5511 | www.ardurra.com

Q4: Following are queries on Section 33 32 17 MLSS LS (Alt2). How many pumps to be provided? Do only want the base and guide rails for the 3rd future pump? No

upper or lower brackets? How will the pumps be lowered and raised? Will there be an

overhead hoist structure?

A4: Section 33 32 17 MLSS LS (Alt2) requires two (2) pumps. No 3rd pump to be provided. No guiderail, base, and brackets to be provided for the 3rd future pump. No overhead hoist structures. Guiderails and base to be provided for the two pumps, not for the 3rd Future pump. The pumps will be lowered or raised via city’s mobile hoist (truck mounted equipment).

END OF ADDENDUM NO. 4

Dan S. Leyendecker, PE Managing Principal LNV, LLC

Enclosures: Attachment No. 1 – Contract Documents – Division A Section A02 Table Of

Contents Attachment No. 2 – Contract Documents – Division A Section A-05 Bid

Proposal, Affidavit and Bid Schedule; Bid Bond; and Certificate of Interested Parties

Attachment No. 3 – Technical Specifications – Section 40 05 59.23 Stainless Steel Slide Gates

Attachment No. 4 – Technical Specification – Section 40 05 71.33 Telescoping Valve

Page 5: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Attachment No. 1- Contract Documents -

Division A- Section A-02 Table of Contents

Page 6: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

3/18/2020

Rev: 5/4/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Table of Contents Page 1 of 4

Table of Contents

DIVISION A

Section A-1 Notice to Bidders

Section A-2 Information to Bidders

Section A-2.1 Summary of Work

Section A-3 Advice to Bidders

Section A-4 Information to Contractors

Section A-5 Bid Proposal, Affidavit and Bid Schedule; Bid Bond; and Certificate of Interested

Parties

Section A-6 Checklist for Bidders

Section A-7 Construction Contract

Section A-8 Performance Bond/Payment Bond

Section A-9 Contractors/Subcontractors Certificate of Insurance

Section A-10 Notice of Award

Section A-11 Notice to Proceed

Section A-12 Certificate of Owner's Attorney

Section A-13 Notice from the Texas Ethics Commission

DIVISION B

Section B-1 Contract Time & Liquidated Damages

Section B-2 Equal Opportunity Clause

Section B-3 HUD Wages

Section B-4 Inspection by City

Section B-5 Project Sign

Section B-7 Illegal Dumping

DIVISION C

Section C-l Definition of Terms

Section C-2 Definition of Abbreviations

Section C-3 Instruction to Bidders

Section C-4 Award and Execution of Contract

Section C-5 Scope of Work

Section C-6 Control of Work and Materials

Section C-7 Legal Relations and Responsibilities to the Public

Section C-8 Prosecution and Progress

Section C-9 Measurement and Payment

Section C-10 Warranty Statement Form

Page 7: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

3/18/2020

Rev: 5/4/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Table of Contents Page 2 of 4

DIVISION D - TECHNICAL PROVISIONS

I. WATER Section 102 Excavation and Backfill for Utilities

Section 104 PVC Water Pipe

Section 106 Ductile Iron Pipe

Section 108 Butterfly Valve

Section 110 Water Valves

Section 116 Hydrostatic Tests for Pressure Mains

Section 120 Concrete Encasement, Cradles, Saddles, and Collars

Section 122 Adjusting Valve Boxes to Grade

Section 128 Disposal of Waste Material and Salvageable Material

Section 130 Ductile Iron Fittings

Section 132 Pipe Joint Restraint Systems

Section 134 Flowable Backfill

Section 136 Cement Stabilized backfill

II. WASTEWATER

Section 202 PVC Sewer Pipe

Section 208 Fiberglass Reinforced Plastic Manholes

Section 214 Sanitary Sewer Cleanouts

Section 216 Adjusting Manholes, and Cleanouts

Section 218 Testing Sewer System

III. SITE

Section 402 Clearing and Grubbing

Section 404 General Construction and Preparation of Site Specifications

Section 410 Reinforcing Steel

Section 412 Welded Wire Fabric

Section 416 Expansion Joint Materials

Section 418 Membrane Curing

Section 422 Conduits

Section 430 Concrete Sidewalks

Section 510 Flexible Base Course

IV. ENVIRONMENTAL

Section 602 Silt Fence

Section 604 Erosion Control Blankets

Section 606 NPDES Requirements

V. MISCELLANEOUS

Section 802 Sheeting and Bracing

Section 804 Work Performed on Non-Working Days

Page 8: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

3/18/2020

Rev: 5/4/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Table of Contents Page 3 of 4

VI. TECHNICAL SPECIFICATIONS

CIVIL/MECHANICAL

01 75 60 Commissioning and Facility Start-Up

09 90 20 Painting

11 00 02 Chlorination Equipment

15 10 20 Check Valves

15 10 30 Plug Valves

15 43 00 Emergency Eye Wash and Shower

15 95 60 Piping Systems Testing

22 32 19 Return Activated Sludge Pumps for Bid allowance

33 32 11 Non-Potable Water Pump Station

33 32 16 Wastewater Lift Station

33 32 17 MLSS Lift Station Pumps

40 00 00 Positive Displacement Blower for Bid Allowance

40 05 23.01 Stainless Steel Pipe and Tubing

40 05 59.23 Stainless Steel Slide Gates

40 05 71.33 Stainless Steel Telescoping Valve

40 71 13 Magnetic Flow Meters

46 01 00 Headworks System (Spiral Screen, Compactor/Bagger, Degritter)

46 02 01 Circular Spiral Scraper Clarifier

46 51 46 Fine and Coarse Bubble Aeration System (Alt #1)

46 51 47 Old Package Plant Coarse Bubble Aeration (Alt #2)

STRUCTURAL

03 01 30 Concrete Restoration and Coatings for Repurposed Plant

03 10 00 Concrete Forming and Accessories

03 20 00 Concrete Reinforcing

03 30 00 Cast-In-Place Concrete

05 12 00 Structural Steel Framing

05 50 00 Metal Fabrications

05 72 10 Ornamental Aluminum Railings

07 90 00 Joint Protection

31 23 16 Excavation

31 23 23 Fill

ELECTRICAL

16000 General Electrical Requirements

16030 Electrical Power System Testing and Coordination

16060 Grounding and Bonding

16070 Hangers and Supports

16075 Electrical Identification

16123 600 Volt or Less Wires and Cables

16134 Boxes

16140 Wiring Devices

16272 Dry Type Transformers

16285 Surge Protective Devices

16411 Disconnect Switches

16444 Low Voltage Motor Control Centers

16600 Electrical Acceptance Testing

16610 Chart Recorder

Page 9: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

3/18/2020

Rev: 5/4/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Table of Contents Page 4 of 4

16620 Multi-Functional Level Control System

16630 Dissolved Oxygen Sensor

VII. REFERENCE DOCUMENTS

Geotechnical Report

Page 10: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Attachment No. 2- Contract Documents -

Division A- Section A-05 Bid Proposal,

Affidavit and Bid Schedule; Bid Bond; and Certificate of

Interested Parties

Page 11: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 1

BID PROPOSAL

To: The City of Laredo, Texas

Honorable Pete Saenz, Mayor

From: Contractor

Address:

Phone:

Fax: ________________________

Project: Unitec Wastewater Treatment Plant – Phase I Expansion Project – FY 2020

Pursuant to Notice to Bidders, the undersigned bidder hereby proposes to furnish the labor, materials, and equipment in accordance with the plans and specifications, general conditions of the agreement, special provisions of the Agreement, and Addenda, if any. The bidder binds himself upon acceptance of his proposal to execute a contract and bonds accompanying form of performing and completing the said work within the time stated as required by the detailed specifications at the following unit prices. The quantities shown below are based on the Engineer’s estimate of quantities and it is agreed that the quantities may be increased or diminished, and may be considered necessary in the opinion of the City of Laredo, Texas to complete the work fully as planned and contemplated, and that all quantities of work, either increased or decreased, are to be performed at the unit prices set forth below (except as provided in the General Conditions of the Agreement or the specifications, the contract documents).

Acknowledgment of Addenda: (Please initial and date):

Addendum No. 1:

Addendum No. 2:

Addendum No. 3:

Addendum No. 4:

Addendum No. 5:

Acknowledgment of other documents: (Please initial and date):

Wage Determination:

Labor Provisions:

Affirmative Action Program:

Page 12: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 2

Project: Unitec Wastewater Treatment Plant – Phase I Expansion – FY 2020

Form of Non-Collusive Affidavit A F F I D A V I T

STATE OF TEXAS {}

COUNTY OF WEBB {}

being first duly sworn, deposes and says That he is (a Partner of Officer of the firm of, etc.) the party making the foregoing proposal or bid, that such proposal or bid is genuine and not collusive or sham; that said Bidder has not colluded, conspired, connived or agreed, directly or indirectly, with any Bidder or Person, to put in a sham bid or to refrain from bidding, and has not in any manner, directly or indirectly, sought by agreement or collusion, or communication or conference, with any person, to fix the bid price or affiant or of any other Bidder or to fix any overhead, profit or cost element of said bid price, or of that of any other Bidder, or to secure any advantage against the City of Laredo or any person interested in the proposed Contract; and that all statements in said proposal or bid are true. Signature of Bidder, if the Bidder is an individual Partner, if the Bidder is a Partnership Officer, if the Bidder is a Corporation Subscribed and sworn before me this day of , 20 . Notary Public My Commission expires

Page 13: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 3

STATEMENT OF MATERIALS AND OTHER CHARGES PROJECT: Unitec Wastewater Treatment Plant – Phase I Expansion Project – FY 2020 MATERIALS INCORPORATED INTO THE PROJECT - BASE BID: $ MATERIALS INCORPORATED INTO THE PROJECT - ALT. # 1: $ MATERIALS INCORPORATED INTO THE PROJECT - ALT. # 2: $ ALL OTHER CHARGES: $ *TOTAL: $ *This total must agree with the total figure shown in the Item and Quantity Sheets in the bound contract. For purposes of complying with the Texas Tax Code, the Contractor agrees that the charges for any material incorporated into the project in excess of the estimated quantity provided for herein will be no less than the invoice price for such material to the Contractor. NOTE: ONLY THE COPY OF THIS FORM IN THE BOUND CONTRACTS IS TO BE

FILLED OUT.

Page 14: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 4

INFORMATION FROM BIDDERS MUST BE COMPLETED AND SUBMITTED WITH BID PROPOSAL

Project: Unitec Wastewater Treatment Plant – Phase I Expansion Project – FY 2020

Statement of Qualifications: (Similar Projects Completed by Bidder)

1. Name of Project:

Value of Contract:

Date Completed:

2. Name of Project:

Value of Contract:

Date Completed:

3. Name of Project:

Value of Contract:

Date Completed:

Experience Data: (Include name and experience record of the Superintendent)

Financial Status: A confidential financial statement will be submitted by the apparent successful low Bidder only if the Owner deems it necessary.

NOTE: TO BE SUBMITTED UPON REQUEST

IS NOT AN ACCEPTABLE ANSWER.

Project: Unitec Wastewater Treatment Plant – Phase I Expansion Project – FY 2020

Page 15: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 5

Proposed Progress Schedules:

Data on Equipment to be used on the Work: (Include the number of machines, the type, capacity, age and conditions and location)

Subcontractors: (Submit a list of proposed Subcontractors. List sources, types and manufacturers of proposed materials)

NOTE: TO BE SUBMITTED UPON REQUEST

IS NOT AN ACCEPTABLE ANSWER.

Page 16: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 6

CITY OF LAREDO UTILITIES DEPARTMENT

BID SCHEDULE

PROJECT: Unitec Wastewater Treatment Plant – Phase I Expansion Project – FY 2020

BASE BID

Item No.

Description of item with Lump Sum Price Written in Words

Unit Amount

1

Mobilization, Bonds, Storm Water Pollution Prevention Plan (SWPPP) and

Compliance with National Pollutant Discharge Elimination System (NPDES)

Permit; complete, in place, ready to use for the lump sum of:

______________________________________dollars and

____________________________________cents.

LS $

2

Miscellaneous site civil work including all clearing, grubbing, concrete flatwork,

sidewalks, steps, handrails, access road improvements, trench safety protection,

subsurface utility excavation (SUE), all yard piping; complete, in place, tested,

ready to use for the lump sum of:

______________________________________dollars and

____________________________________cents

LS $

3

Installation of new factory-built Headworks. Structure to be welded 316 (L)

Stainless Steel, 3/8” wall thickness (min.); all required equipment including

concrete foundation, mechanical bar screen with passive bypass system,

compactor-bagger/classifier/de-gritter; concrete or 316 (L) S.S. splitter box, all

piping, fittings, reducers, measuring devices, electrical, controls, metering,

restraints, tie-ins to existing 8” diameter force main (FM) and existing Aeration

basin A; meeting all TCEQ requirements; all work complete, in place, tested,

ready to use for the lump sum of:

_____________________________________dollars and

____________________________________cents.

LS $

Page 17: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 7

BASE BID

Item No.

Description of item with Lump Sum Price Written in Words

Unit Amount

4

Provide and install 3HP RAS pump - Hidrostal Model D3K-S; including all

equipment for a complete Pump Assembly; all work to include all,

appurtenances, fittings, reducers, header, valves, electrical and controls, air relief

valves, VFD, meter, and all other items for a complete installation; all work

complete, in-place, tested; ready to use for lump sum of

_____________________________________ dollars and

_______________________________ cents.

LS BID ALLOWANCE

$22,000.00

5

Provide and install 60 HP Blower - Gardner Denver Model Helifow 616;

including all equipment for a complete Blower Assembly; all work to include all,

appurtenances, fittings, reducers, header, valves, electrical and controls, VFD,

meter, and all other items for a complete installation; all work complete, in-

place, tested; ready to use for lump sum of

_____________________________________ dollars and

_______________________________ cents.

LS BID ALLOWANCE

$60,000.00

6

Construction and installation of New Bridge Supported Concrete Clarifier

including all equipment, access stairs/walkway; spray bar; bridge and structure

assembly; electrical and controls, all piping and tie-ins; all work complete, in-

place, tested, and ready to use per lump sum of:

_____________________________________ dollars and

_______________________________ cents.

LS $

7

Construction and installation of New Lift Station with two (2) pumps; 8’

diameter FRP wetwell; all connections, valves, fittings; controls; Air release

valves, alarms, electrical; all work complete, in place, tested, and ready to use

per lump sum cost of:

_____________________________________ dollars and

_______________________________ cents.

LS $

8

Construction and installation of New Non-Potable Plant Water Supply

(NPW) with two (2) pumps; including concrete foundation, strainers, pneumatic

tank, valves, all piping/connections, reducers, metering, controls, fittings and

appurtenances; complete, in-place, tested, and ready to use per lump sum of:

____________________________________ dollars and

_______________________________ cents.

LS $

Page 18: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 8

BASE BID

Item No.

Description of item with Lump Sum Price Written in Words

Unit Amount

9

Complete upgrade of the existing Gas Chlorine Disinfection System in existing

building; all required demolition and new equipment, improvements, all

piping/connections, all connections to chlorine contact chamber (CCC); meeting

TCEQ and OSHA requirements for disinfection and safety; all work complete

in-place, tested, and ready to use per lump sum of:

__________________________________________ dollars and

__________________________________________cents.

LS $

10

All Electrical items and materials for a complete and working electrical system.

For the installation of, but not limited to, Headworks, Clarifier, Blower, Lift

Station, Non-Potable Water Supply, Control Panels, Dissolved Oxygen Sensors

and Controls, Flow Meters, Chart Recorder and area lighting, required

conduits/piping, and other items detailed in the plans and specifications.

All complete and in place for the lump sum of:

_____________________________________ dollars and

____________________________________ cents.

LS $

11

Utility Allowance. This allowance is to be used at the Owner's discretion

for unanticipated adjustment of a utility or unknown structure, which

warrants the use of the Allowance. Should use of the Allowance become

necessary, the Owner will provide written authorization at a cost to be

negotiated between the Owner and the Contractor and based on the

Contractor’s actual cost. No work is to be performed under this Item

without written approval and authorization from the Owner. Work

performed without written authorization will not be paid. There is no

guarantee that any of these funds will be used. If approved, an authorization

shall be measured by complete and functioning adjustment of the unanticipated

work. Payment shall be made for work complete, in place, tested, and ready to

use.

All complete and in place for the lump sum of:

_____________________________________ dollars and

____________________________________ cents.

LS $ 200,000.00

TOTAL BASE BID AMOUNT (Bid Items No. 1-11) $_____________________________________

TOTAL BASE BID WRITTEN IN WORDS: __________________________________________________________

________________________________________________________________________________________________

Page 19: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 9

ALTERNATE #1 – New Aeration Basin (TRAIN B) Item No.

Description of item with Lump Sum Price Written in Words

Unit Amount

Alt# 1

Construction and installation of New 0.18 MGD Aeration and Digester Concrete

Basin (TRAIN B) including all equipment; access stairs, landings, concrete

walkways and handrails; all RAS/WAS and MLSS piping and tie-ins; all

stainless steel Aeration piping: including all Header/Fine Bubble Aeration and

Digester Coarse Bubble air drops; valves and fittings; all drains and connections

to lift station; NPW piping and connections; telescoping valves; D.O. equipment;

provide yard piping/valves/fittings/connections to splitter box, NPW Station and

Blower/RAS pump; concrete flatwork; work to be complete, in place, tested, and

ready to use for the lump sum of: _____________________________________

dollars and _______________________________ cents.

LS $

TOTAL ALTERNATE #1 AMOUNT $_____________________________________

TOTAL BASE BID WRITTEN IN WORDS: __________________________________________________________

________________________________________________________________________________________________

Page 20: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 10

ALTERNATE #2 – Old Package (Pkg) Plant

Item No.

Description of item with Lump Sum Price Written in Words

Unit Amount

Alt# 2

Upgrade existing 0.11 MGD concrete Package Plant including demolition of all

existing mechanical equipment, access stairs, landings, handrails and air piping;

provide concrete repair and interior coating system; provide New Coarse Bubble

Air Diffuser System to existing Aeration Basins; provide stainless steel headers

with air drops and all tie-ins to Blower; provide yard piping/valves/fittings/

connections to splitter box, NPW Station and Blower/RAS pump; provide new

MLSS Lift Station including two (2) pumps and weir with piping connection to

MLSS Lift Station; new access stairs, handrails, and landings; all work complete,

in place, tested, and ready to use for the lump sum of:

_____________________________________ dollars and

_______________________________ cents.

LS $

TOTAL ALTERNATE #2 AMOUNT $_____________________________________

TOTAL BASE BID WRITTEN IN WORDS: __________________________________________________________

________________________________________________________________________________________________

NOTE: 1) Items of work or requirements not shown nor specifically listed for payment in the Bid

Proposal and for work, scope, requirements in the plans, contract documents or specifications, if not listed, shall be considered necessary and subsidiary to the other items in the Bid Schedule and shall be required under the Contract. Meet All Local, State, Federal, AWWA, TCEQ, and OSHA Codes and Regulations; complete, in-place, tested, and ready to use.

2) All Bid Items listed are approximate and are for reference only. See plans and

specifications.

Page 21: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 11

3) Manufacturer’s Authorized Factory Representative(s) shall be present for equipment,installation, testing, and start-up to successful operation and acceptance by the City.Manufacturer shall supply a written Certification when equipment installation iscomplete meets all manufacturer’s requirements and is ready for operation.

Note: For any conflict for measurement and payment items shown in the plans, standard or technical specifications, or drawings of this project the items shown in the “Bid Proposal/Schedule of Values” will prevail and be the only items to be used for project payment; complete, tested, in place and ready to use.

Contractor

Signature Title

Address City/State Zip Code

Telephone Number:( ) _____

Fax Number:( ) _____

Date:

NOTE: FINAL PAYMENT FOR BID ITEMS SHOWN IN BID PROPOSAL/SCHEDULE WILL BE PAID FOR WHEN COMPLETE IN PLACE, TESTED, AND ACCEPTED BY THE OWNER.

Page 22: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 12

BID BOND Project: Unitec Wastewater Treatment Plant – Phase I Expansion Project – FY 2020 KNOW ALL MEN BY THESE PRESENTS, that we, the undersigned

as Principal, and as

Surety, are hereby held and firmly bound unto

as Owner in the penal sum of 5% of greatest amount bid for payment of which, well and

truly to be made, we hereby jointly an severally bid ourselves, our heirs, executors,

administrations, successors and assigns. Signed, this day of , 20 . The condition of the above obligation is such that whereas the Principal has submitted to a certain Bid, attached hereto and hereby made a part hereof to enter into a Contract in writing for the NOW, THEREFORE, (a) If said Bid shall be rejected, or in the alternate, (b) If said Bid shall be accepted and the Principal shall execute and deliver a

Contract in the Form of Contract attached hereto (properly completed in accordance with said Bid) and shall furnish a bond for his faithful performance of said Contract, and for the payment of all persons performing labor or furnishing materials in connection therewith, and shall in all other respects perform the Agreement created by the acceptance of said Bid,

then this obligation shall be void, otherwise the same shall remain in force and effect; it being expressly understood and agreed that the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal amount of this obligation as herein stated. The Surety, for value received, hereby stipulates and agrees that he obligations of said Surety, and its bonds shall be in no way impaired or affected by any extension of the

Page 23: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Proposal and Bid Schedule A05 - 13

time within which the Owner may accept such Bid; and said Surety does hereby waive notice of any such extension. IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals and such of them as are corporations have caused their corporate seals to be hereto affixed and these presents to be signed by their proper officers, the day and year first set fourth herein. (L.S.) Principal Surety By:

Page 24: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Attachment No. 3- Technical Specifications -

Section 40 05 59.23 Stainless Steel Slide Gates

Page 25: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Wastewater Lift Station 40 05 59.23

Page 1 of 8

SECTION 40 05 59.23

STAINLESS STEEL SLIDE GATES

PART 1 GENERAL

1.01 SCOPE OF WORK

A. The CONTRACTOR shall furnish all labor, materials, equipment and incidentals required to

install, ready for operation and field test stainless steel gates and appurtenances as shown on the

Contract Drawings and as specified herein.

B. The gates and appurtenances shall be supplied in accordance with the latest edition of

AWWA C561 Standard for Fabricated Stainless Steel Slide Gates as modified herein. The

allowable leakage rate for the stainless steel gates in this specification shall be 1/2 the allowable

leakage listed in the latest revision of AWWA C561.

1.02 SUBMITTALS

A. Provide the following information to confirm compliance with the specification:

1. Complete description of all materials including the material thickness of all structural

components of the frame and slide.

2. Installation drawings showing all details of construction, details required for installation,

dimensions and anchor bolt locations.

3. Maximum bending stress and deflection of the slide under the maximum design head.

4. The location of the company headquarters and the location of the principle manufacturing

facility. Provide the name of the company that manufactures the equipment if the supplier

utilizes an outside source.

1.03 QUALITY ASSURANCE

A. Qualifications

1. All of the equipment specified under this Section shall be furnished by a single

manufacturer with a minimum of 20 years experience designing and manufacturing water

control gates. The manufacturer shall have manufactured water control gates for a

minimum of 100 projects.

2. Any gate imported into the United States must be fully shop tested at a test location within

the US and shall be witnessed by a representative of the engineer. The cost of travel for the

Engineer’s representative shall be borne by the gate manufacturer.

1.04 APPROVED MANUFACTURERS

A. Fontaine-Aquanox

Page 26: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Wastewater Lift Station 40 05 59.23

Page 2 of 8

B. -Hydro Gate -

C. -Rodney Hunt

D. -Whipps

E. -Waterman

F. Engineer Approved Equal

PART 2 EQUIPMENT

2.01 GENERAL

A. Gates shall be as specified herein and have the characteristics and dimensions shown on the

Contract Drawings.

B. Leakage shall not exceed 0.05 gpm/ft of wetted seal perimeter in seating head and unseating

head conditions.

C. The gate shall utilize self-adjusting seals. Due to the difficulty of accessing gates when they are

in service, gates that utilize adjustable wedges, wedging devices or pressure pads are not

acceptable.

D. All structural components of the frame and slide shall be fabricated of stainless steel having a

minimum thickness of 1/4-inch and shall have adequate strength to prevent distortion during

normal handling, during installation and while in service.

E. Slide gate frames shall be shipped fully assembled with the invert member welded to the side

frames and the slide installed in the frame unless the overall width of the slide gate exceeds 96

inches or the overall height of the slide gate exceed 25 feet.

F. All welds shall be performed by welders with AWS D1.6 certification.

G. Finish: Mill finish on stainless steel. Welds shall be sandblasted to remove weld burn and scale.

All iron and steel components shall be properly prepared and shop coated with a primer.

H. Materials:

Components Materials

Frame Assembly and Retainers Stainless Steel, Type 316L, ASTM A240

Slide and Stiffeners Stainless Steel, Type 316L, ASTM A240

Stem Stainless Steel, Type 316, ASTM A276

Anchor Studs Stainless Steel, Type 316, ASTM A276

Fasteners and Nuts Stainless Steel, Type 316, ASTM F593/F594

Invert Seal (Upward Opening Gates Only) Neoprene or EPDM ASTM D-2000

Seat/Seals and Facing Ultra-High Molecular Weight Polyethylene ASTM

D4020

Page 27: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Wastewater Lift Station 40 05 59.23

Page 3 of 8

Pedestals and Wall Brackets Stainless Steel, Type 316L, ASTM A240

Operator Housing Cast aluminum

2.02 FRAME

A. The frame assembly, including the guide members, invert member and yoke members, shall be

constructed of formed stainless steel plate with a minimum thickness of 1/4-inch.

1. Frame design shall allow for embedded mounting, mounting directly to a wall with stainless

steel anchor bolts and grout or mounting to a wall thimble with stainless steel mounting studs

and a mastic gasket material. Mounting style shall be as shown on the Contract Drawings.

2. All wall mounted or wall thimble mounted gates shall have a flange frame. Flat frame gates are

not acceptable.

3. The structural portion of the frame that incorporates the seat/seals shall be formed into a one-

piece shape for rigidity. Guide members that consist of two or more bolted structural members

are not acceptable. Guide member designs where water loads are transferred through the

assembly bolts are specifically not acceptable.

4. Gussets shall be provided as necessary to support the guide members in an unseating head

condition. The gussets shall extend to support the outer portion of the guide assembly and shall

be positioned to ensure that the load is transferred to the anchor bolts or the wall thimble studs.

5. The frame shall extend to accommodate the entire height of the slide when the slide is in the

fully opened position on upward opening gates or downward opening weir gates.

6. On self-contained gates, a yoke shall be provided across the top of the frame. The yoke shall

be formed by two structural members affixed to the top of the side frame members to provide

a one-piece rigid assembly. The yoke shall be designed to allow removal of the slide. The

Yoke shall be sized to withstand normal operating loads as well as the maximum hoist output.

The Yoke deflection shall not exceed 1/360 of the gate width or a maximum of ¼” whichever

is less at maximum operating load.

7. A rigid stainless steel invert member shall be provided across the bottom of the opening. The

invert member shall be of the flushbottom type on upward opening gates.

8. A rigid stainless steel top seal member shall be provided across the top of the opening on gates

designed to cover submerged openings.

9. A rigid stainless steel member shall be provided across the invert of the opening on downward

opening weir gates.

2.03 SLIDE

A. The slide and reinforcing stiffeners shall be constructed of stainless steel plate. All structural

components shall have a minimum thickness of 1/4-inch.

1. The slide shall not deflect more than 1/720 of the span or 1/16 inch, whichever is smaller,

under the maximum design head.

2. When the width of the gate opening in feet multiplied by the maximum design head in feet is

greater than 80 square feet the portion of the slide member that engages the guide shall be

1/2” thick. When the width of the gate opening in feet multiplied by the maximum design

head in feet is greater than 120 square feet, the portion of the slide that engages the guide

Page 28: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Wastewater Lift Station 40 05 59.23

Page 4 of 8

members shall be of a “thick edge” design. The thick edge portion of the slide shall have a

minimum thickness of 2.5 inches.

3. Reinforcing stiffeners shall be welded to the slide and mounted horizontally. Vertical

stiffeners shall be welded on the outside of the horizontal stiffeners for additional

reinforcement. When required to maintain proper plate stress and deflection intermediate

vertical gussets shall be provided. Appropriate safety factors shall be applied to the ultimate

tensile and yield strength of the material.

4. The stem connector shall be constructed of two angles or plates. The stem connector shall be

welded to the slide. A minimum of two bolts shall connect the stem to the stem connector.

2.04 SEALS

A. All gates shall be provided with a self-adjusting seal system to restrict leakage in accordance

with the requirements listed in this specification.

1. All gates shall be equipped with UHMW polyethylene seat/seals to restrict leakage and

to prevent metal to metal contact between the frame and slide. Seat contact pressure

shall not exceed 600 psi at the design head.

2. The seat/seals shall extend to accommodate the 1-1/2 x the height of the slide when the

slide is in the fully closed or fully opened position.

3. All upward opening gates shall be provided with a resilient seal to seal the bottom

portion of the gate. The seal shall be attached to the invert member or the bottom of the

slide and it shall be held in place with stainless steel attachment hardware.

4. All downward opening weir gates shall be provided with UHMW polyethylene

seat/seals across the invert member.

5. The seal system shall be durable and shall be designed to accommodate high velocities

and frequent cycling without loosening or suffering damage.

6. All seals must be bolted or otherwise mechanically fastened to the frame or slide.

Arrangement with seals that are force fit or held in place with adhesives are

unacceptable.

7. The seals shall be mounted so as not to obstruct the water way opening.

8. Gates that utilize rubber “J” seals or “P” seals are not acceptable.

9. The seal system shall have been factory tested to confirm negligible wear (less than

0.01”) and proper sealing. The factory testing shall consist of an accelerated wear test

comprised of a minimum of 25,000 open-close cycles using a well-agitated sand/water

mixture to simulate fluidized grit.

2.05 STEM

A. A threaded operating stem shall be utilized to connect the operating mechanism to the slide.

On rising stem gates, the threaded portion shall engage the operating nut in the manual

operator or motor actuator. On non-rising stem gates, the threaded portion shall engage

the nut on the slide.

1. The threaded portion of the stem shall have a minimum outside diameter of 1-1/2

inches.

Page 29: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Wastewater Lift Station 40 05 59.23

Page 5 of 8

2. The stem shall be constructed of solid stainless steel bar for the entire length, the metal

having a tensile strength of not less than 75,000 psi. Stem extension pipes are not

acceptable.

3. The stem shall be threaded to allow full travel of the slide unless the travel distance is

otherwise shown on the Contract Drawings.

4. Maximum L/R ratio for the unsupported part of the stem shall not exceed 200.

5. The operating stem shall be designed to transmit in compression at least 2 times the

rated hoist output with an effort of 40 lb on the crank or handwheel. The Euler column

formula shall be utilized. Where a hydraulic or electric actuator is used, the stem

design load shall not be less than 1.25 times the output thrust of the hydraulic cylinder

with a pressure equal to the maximum working pressure of the fluid supply or 1.25

times the output thrust of the electric actuator at the stalled condition..

6. The stem shall be designed to withstand the tension load caused by the application of

a 40 lb effort on the crank or handwheel without exceeding 1/5 of the ultimate tensile

strength of the stem material.

7. The threaded portion of the stem shall have machine rolled threads of the full Acme

type with a 16 microinch finish or better. Stub threads are not acceptable.

8. Stems of more than one section shall be joined by stainless steel or bronze couplings.

The coupling shall be bolted to the stems.

9. Stems, on manually operated gates, shall be provided with adjustable stop collars to

prevent over closing of the slide.

2.06 STEM GUIDES

A. Stem guide shall be provided when necessary to ensure that the maximum L/R ratio for the

unsupported part of the stem is 200 or less.

1. Stem guide brackets shall be fabricated of stainless steel and shall be outfitted with

UHMW or bronze bushings.

2. Adjustable in two directions.

2.07 WALL THIMBLES

A. Wall thimbles shall be provided when shown on the Contract Drawings.

1. The wall thimble depth shall be equal to the thickness of the concrete wall in which

the thimble is to be mounted.

2. Wall thimbles shall be fabricated stainless steel construction of adequate section to

withstand all operational and reasonable installation stresses.

3. Wall thimbles shall be constructed of 1/4-inch minimum thickness stainless steel and

the front face shall have a minimum thickness of 1/4–inch.

4. The fabrication process shall ensure that the wall thimble is square and plumb and the

front face is sufficiently flat to provide a proper mounting surface for the gate frame.

5. The face of the wall thimble shall only be machined if recommended by the gate

manufacturer. If the wall thimble is to be machined, the front face shall have a

minimum thickness of 1/4-inch after machining.

Page 30: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Wastewater Lift Station 40 05 59.23

Page 6 of 8

6. A water stop shall be welded around the periphery of the thimble. Wall thimbles shall

be designed to allow thorough and uniform concrete placement during installation.

7. Studs and nuts shall be stainless steel. Water stop may be stitch welded.

8. A suitable gasket or mastic shall be provided to seal between the gate frame and the

wall thimble.

2.08 MANUAL OPERATORS

A. Unless otherwise shown on the Drawings, gates shall be operated by a manual handwheel or a

manual crank-operated gearbox. The operator shall be mounted on the yoke of self contained

gates or on the pedestal of non-self contained gates.

1. The gate manufacturer shall select the proper gear ratio to ensure that the gate can be

operated with no more than a 40 lb effort when the gate is in the closed position and

experiencing the maximum operating head.

2. An arrow with the word "OPEN" shall be permanently attached or cast onto the operator to

indicate the direction or rotation to open the gate.

3. Handwheel operators shall be fully enclosed and shall have a cast aluminum housing.

a. Handwheel operators shall be provided with a threaded cast bronze lift nut to engage

the operating stem.

b. Handwheel operators shall be equipped with roller bearings above and below the

operating nut.

c. Positive mechanical seals shall be provided above and below the operating nut to

exclude moisture and dirt and prevent leakage of lubricant out of the hoist.

d. The handwheel shall be removable and shall have a minimum diameter of 15 inches.

4. Crank-operated gearboxes shall be fully enclosed and shall have a cast aluminum or ductile

iron housing.

a. Gearboxes shall have either single or double gear reduction depending upon the lifting

capacity required.

b. Gearboxes shall be provided with a threaded cast bronze lift nut to engage the operating

stem.

c. Bearings shall be provided above and below the flange on the operating nut to support

both opening and closing thrusts.

d. Gears shall be steel with machined cut teeth designed for smooth operation.

e. The pinion shaft shall be stainless steel and shall be supported on ball or tapered roller

bearings.

f. Positive mechanical seals shall be provided on the operating nut and the pinion shafts

to exclude moisture and dirt and prevent leakage of lubricant out of the hoist.

g. The crank shall be cast aluminum or cast iron with a revolving nylon grip.

h. The crank shall be removable.

5. All gates having widths in excess of 72 inches and widths greater than twice their height

shall be provided with two gearboxes connected by an interconnecting shaft for

simultaneous operation.

a. Interconnecting shafting shall be constructed of aluminum or stainless steel.

b. Flexible couplings shall be provided at each end of the interconnecting shaft.

Couplings shall be stainless steel or non-metallic.

Page 31: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Wastewater Lift Station 40 05 59.23

Page 7 of 8

c. One crank shall be provided to mount on the pinion shaft of one of the gearboxes.

d. If the operating assembly is motorized, a stainless steel enclosure shall be provided

over the interconnecting shaft to comply with OSHA regulations.

6. An extended operator system utilizing chain and sprockets shall be furnished by the

manufacturer when the centerline of the crank or handwheel, on a non-geared operator, is

located over 48-in above the operating floor. Chain wheels are not acceptable.

a. A removable stainless steel or aluminum cover shall be provided to enclose chain and

sprockets.

b. The extended operator system shall lower the centerline of the pinion shaft to 36-in

above the operating floor.

c. A handwheel may be utilized in conjunction with a gearbox in lieu of the extended

operator system if the centerline of the pinion shaft is 60-in or less above the operating

floor.

7. Pedestals shall be constructed of stainless steel. Aluminum pedestals are not acceptable.

a. The pedestal height shall be such that the handwheel or pinion shaft on the crank-

operated gearbox is located approximately 36-in above the operating floor.

b. Wall brackets shall be used to support floor stands where shown on the Drawings and

shall be constructed of stainless steel.

c. Wall brackets shall be reinforced to withstand in compression at least two times the

rated output of the operator with a 40 lb effort on the crank or handwheel.

d. The design and detail of the brackets and anchor bolts shall be provided by the gate

manufacturer and shall be approved by the ENGINEER. The gate manufacturer shall

supply the bracket, anchor bolts and accessories as part of the gate assembly.

8. Operators shall be equipped with fracture-resistant clear butyrate or lexan plastic stem

covers.

a. The top of the stem cover shall be closed.

b. The bottom end of the stem cover shall be mounted in a housing or adapter for easy

field mounting.

c. Stem covers shall be complete with indicator markings to indicate gate position.

9. When shown on the Contract Drawings, provide 2 inch square nut, mounted in a floor box,

with a non-rising stem.

a. The square nut shall be constructed of bronze.

b. The floor box shall be constructed of stainless steel or cast iron and shall be set in the

concrete floor above the gate as shown.

c. Provide one aluminum or stainless steel T-handle wrench for operation.

2.10 ANCHOR BOLTS

A. Anchor bolts shall be provided by the gate manufacturer for mounting the gates and

appurtenances.

1. Quantity and location shall be determined by the gate manufacturer.

2. If epoxy type anchor bolts are provided, the gate manufacturer shall provide the studs and

nuts.

3. Anchor bolts shall have a minimum diameter of 1/2-inch.

Page 32: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Wastewater Lift Station 40 05 59.23

Page 8 of 8

PART 3 EXECUTION

3.01 INSTALLATION

A. Installation of the gates and appurtenances shall be done in a workmanlike manner. It shall be

the responsibility of the CONTRACTOR to handle, store and install the equipment specified in

this Section in strict accordance with the manufacturer's recommendations.

B. The CONTRACTOR shall review the installation drawings and installation instruction prior to

installing the gates.

C. The gate assemblies shall be installed in a true vertical plane, square and plumb.

D. The CONTRACTOR shall fill the void in between the gate frame and the wall with non-shrink

grout as shown on the installation drawing and in accordance with the manufacturer’s

recommendations.

E. The CONTRACTOR shall add a mastic gasket between the gate frame and wall thimble (when

applicable) in accordance with the manufacturer’s recommendations.

3.02 FIELD TESTING

A. After installation, all gates shall be field tested in the presence of the ENGINEER and OWNER

to ensure that all items of equipment are in full compliance with this Section. Each gate shall

be cycled to confirm that they operate without binding, scraping, or distorting. The effort to

open and close manual operators shall be measured, and shall not exceed the maximum

operating effort specified above. Electric motor actuators shall function smoothly and without

interruption. Each gate shall be water tested by the CONTRACTOR, at the discretion of the

ENGINEER and OWNER, to confirm that leakage does not exceed the specified allowable

leakage.

3.03 MANUFACTURERS FIELD SERVICE

END OF SECTION

Page 33: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

Attachment No. 4- Technical Specifications:

Section 40 05 71.33 Telescoping Valve

Page 34: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Telescoping Valve 40 05 71.33

Page 1 of 6

SECTION 40 05 71.33

TELESCOPING VALVE

PART 1 GENERAL

1.1 SCOPE OF WORK

A. Furnish all labor, materials, equipment and incidentals required to install and ready for operation

telescoping valves and appurtenances as shown on the Contract Drawings and as specified

herein.

1.2 SUBMITTALS

A. Provide the following information to confirm compliance with the specification.

1. Complete description of all materials including the material thickness.

2. Installation drawings showing all details of construction, details required for

installation, dimensions and anchor bolt locations.

3. The location of the company headquarters and the location of the principle

manufacturing facility. Provide the name of the company that manufactures the equipment

if the supplier utilizes an outside source.

1.3 QUALITY ASSURANCE

A. Qualifications

1. All of the equipment specified under this Section shall be furnished by a single

manufacturer with a minimum of 20 years experience designing and manufacturing

telescoping valves. The manufacturer shall have manufactured telescoping valves for a

minimum of 100 projects.

1.4 OPERATION AND MAINTENANCE MANUALS

A. Furnish operation and maintenance manuals for the equipment in accordance with the Contact

Documents. As a minimum, the following information shall be included:

1. Certified shop and erection drawings showing all important details of construction,

dimensions, and anchor bolts locations.

2. Descriptive literature, bulletins, and/or catalogs of the equipment.

3. The total weight of the valves.

Page 35: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Telescoping Valve 40 05 71.33

Page 2 of 6

4. Materials of construction of all parts.

5. A complete total bill of materials for all equipment.

6. A list of the manufacturer’s recommended spare parts.

1.5 MANUFACTURERS

A. Approved Manufacturers

1. Whipps

2. Waterman

3. JMS Equipment

4. Wawcon

5. Pentroy

6. Approved Equal

PART 2 PRODUCTS

2.1 GENERAL

A. Telescoping valves shall be as specified herein and have the characteristics and dimensions

shown on the Contract Drawings.

B. The valve shall utilize a low friction seal to mount to engage the slip tube and mount to the

flange of the receiving pipe.

C. All welds shall be performed by welders with AWS certification.

D. Finish: Mill finish on stainless steel. Welds shall be sandblasted to remove weld burn and scale.

E. Materials:

Components Materials

Slip Tube and Bail Stainless Steel, Type 304L, ASTM A240

Stem Stainless Steel, Type 304, ASTM A276

Anchor Studs, Fasteners and Nuts Stainless Steel, Type 316, ASTM A276

Page 36: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Telescoping Valve 40 05 71.33

Page 3 of 6

Seal Urethane or Neoprene

Lift Nuts Bronze ASTM B584

Pedestals and Wall Brackets Stainless Steel, Type 304L, ASTM A276

Operator Housing Cast aluminum

2.2 SLIP TUBE AND BAIL

A. The slip tube shall be constructed of Schedule 10 minimum thickness stainless steel pipe. . V-

notched weirs, U-notched weirs, scum baffles and/or funnel tops shall be provided as shown on

the Contract Drawings.

B. The bail shall be constructed of stainless steel and shall be bolted to the stem and welded to the

slip tube.

2.3 SEAL

A. The telescoping valve shall be provided with a self-adjusting seal system to restrict leakage

between the slip tube and the receiving pipe.

1. The seal shall be a one–piece molded urethane seal with an upper lip type seal and an

integral companion flange.

2. If a neoprene seal and separate companion flange is provided, the neoprene seal shall

have a minimum thickness of 1/2-inch and the companion flange shall be stainless steel

and shall have a minimum thickness of 3/8-inch.

3. The companion flange shall be provided with a bolt pattern suitable for attachment to

the flange on the receiving pipe.

2.4 STEM

A. A threaded operating stem shall be utilized to connect the operating mechanism to the bail which

in turn is attached to the slip tube. On rising stem valves, the threaded portion shall engage the

operating nut in the manual operator or motor actuator. On non-rising stem valves, the threaded

portion shall engage the nut attached to the bail.

B. The threaded portion of the stem shall have a minimum outside diameter of 1-1/2 inches. Stem

extension pipes are not acceptable.

C. The stem shall be constructed of solid stainless steel bar for the entire length, the metal having a

tensile strength of not less than 75,000 psi.

D. Maximum L/R ratio for the unsupported part of the stem shall not exceed 200.

Page 37: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Telescoping Valve 40 05 71.33

Page 4 of 6

E. In compression, the stem shall be designed for a critical buckling load caused by a 40 lb effort on

the crank or handwheel with a safety factor of 2, using the Euler column formula.

F. The stem shall be designed to withstand the tension load caused by the application of a 40 lb effort

on the crank or handwheel without exceeding 1/5 of the ultimate tensile strength of the stem

material.

G. The threaded portion of the stem shall have machine rolled double lead threads of the full Acme

type with a 16 microinch finish or better. Stub threads are not acceptable.

H. Stems of more than one section shall be joined by stainless steel or bronze couplings. The coupling

shall be pinned and bolted to the stems.

I. Stems, on manually operated valves, shall be provided with adjustable stop collars to prevent over

travel.

2.5 STEM GUIDES

A. Stem guide shall be provided when necessary to ensure that the maximum L/R ratio for the

unsupported part of the stem is 200 or less.

B. Stem guide brackets shall be fabricated of stainless steel and shall be outfitted with UHMW or

bronze bushings. Adjustable in two directions.

2.6 MANUAL OPERATORS

A. Unless otherwise shown on the Drawings, valves shall be operated by a manual handwheel

or a manual crank-operated gearbox. The operator shall be mounted on a pedestal.

1. The valve manufacturer shall select the proper gear ratio to ensure that the valve can be

operated with no more than a 40 lb effort.

2. An arrow with the word "OPEN" shall be permanently attached or cast onto the operator

to indicate the direction or rotation to open the valve.

3. Handwheel operators shall be fully enclosed and shall have a cast aluminum housing.

B. Handwheel operators shall be provided with a threaded cast bronze lift nut to engage the

operating stem.

1. Handwheel operators shall be equipped with roller bearings above and below the

operating nut.

2. Positive mechanical seals shall be provided above and below the operating nut to exclude

moisture and dirt and prevent leakage of lubricant out of the hoist.

Page 38: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Telescoping Valve 40 05 71.33

Page 5 of 6

3. The handwheel shall be removable and shall have a minimum diameter of 15 inches.

4. Crank-operated gearboxes shall be fully enclosed and shall have a cast aluminum housing.

5. Gearboxes shall have either single or double gear reduction depending upon the lifting

capacity required.

6. Gearboxes shall be provided with a threaded cast bronze lift nut to engage the operating

stem.

7. Bearings shall be provided above and below the flange on the operating nut to support both

opening and closing thrusts.

8. Gears shall be steel with machined cut teeth designed for smooth operation.

9. The pinion shaft shall be stainless steel and shall be supported on ball or tapered roller

bearings.

10. Positive mechanical seals shall be provided on the operating nut and the pinion shafts to

exclude moisture and dirt and prevent leakage of lubricant out of the hoist.

11. The crank shall be cast aluminum with a revolving nylon grip.

12. The crank shall be removable.

13. Pedestals shall be constructed of stainless steel. Aluminum pedestals are not acceptable.

14. The pedestal height shall be such that the handwheel or pinion shaft on the crank-operated

gearbox is located approximately 36 in above the operating floor.

15. Wall brackets shall be used to support floor stands where shown on the Drawings and shall

be constructed of stainless steel.

16. Wall brackets shall be reinforced to withstand the maximum operating loads mentioned

herein.

17. The design and detail of the brackets and anchor bolts shall be provided by the valve

manufacturer and shall be approved by the ENGINEER. The valve manufacturer shall

supply the bracket, anchor bolts and accessories as part of the valve assembly.

18. Operators shall be equipped with fracture resistant clear butyrate or lexan plastic stem

covers.

19. The top of the stem cover shall be closed.

20. The bottom end of the stem cover shall be mounted in a housing or adapter for easy field

mounting.

Page 39: CITY OF LAREDO, TEXAS...2020/04/23  · 40 05 59.23 Stainless Steel Slide Gates 40 05 71.33 Stainless Steel Telescoping Valve 40 71 13 Magnetic Flow Meters 46 01 00 Headworks System

5/04/2020

Unitec WWTP – Phase I Expansion – FY 2020 LNV Project # 150534.024

Laredo, Texas

Telescoping Valve 40 05 71.33

Page 6 of 6

21. Stem covers shall be complete with indicator markings to indicate valve position.

2.7 ANCHOR BOLTS

A. Anchor bolts shall be provided by the valve manufacturer for mounting the pedestal and

appurtenances. Quantity and location shall be determined by the valve manufacturer. If

epoxy type anchor bolts are provided, the valve manufacturer shall provide the studs and

nuts. Anchor bolts shall have a minimum diameter of 1/2-inch.

PART 3 EXECUTION

1.1 INSTALLATION

A. Installation of the valves and appurtenances shall be done in a workmanlike manner. It shall

be the responsibility of the CONTRACTOR to handle, store and install the equipment

specified in this Section in strict accordance with the manufacturer's recommendations.

B. The CONTRACTOR shall review the installation drawings and installation instruction prior

to installing the valves.

C. The valve assemblies shall be installed in a true vertical plane, square and plumb.

1.2 FIELD TESTING

A. After installation, all valves shall be field tested by the CONTRACTOR in the presence of

the ENGINEER and OWNER to ensure that all items of equipment are in full compliance

with this Section. Each valve shall be cycled to confirm that they operate without binding,

scraping, or distorting.

END OF SECTION