checksheet

423
Area: 53A02 Package: 53A - FIREWATER DISTRIBUTION Sub System: 53 - FIXED FIREWATER SYSTEM System: LINES FROM 100-FW-5301-A18 to FIRE WATER RING WELLHEAD AREA Description: 100-FW-5302-SL-A18 ObjectID: Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES OE:1076764070 Operational Medium: Flushing Medium: TestMedium: PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0023 Name and Signature Test Witnessed by (Note2) Name and Signature Tested by Contractor Hours Test Duration Date and Time End Date and Time Degree C Ambient Temperature at end BarG Test Pressure at end Date and Time Start Date and Time Degree C Ambient Temperature at start BarG Test Pressure at start Test Results and Readings System tested in accordance with the approved procedure. (Refer Note 1). System prepared for testing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for flushing in accordance with the approved procedure. Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. Date Verified by Completed by Description of Item to be completed and Checked Notes 1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number. 2. Where Test is not witnessed state NA. 3. All activity required Commissioning & Client Witness points Date: Sign: Name: BDEWC Commission BDEWC QA/QC BDEWC Construction OE:1076764070 Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 1/423

description

Hook up & Commissioning

Transcript of checksheet

Page 1: checksheet

Area:53A02Package:

53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:

LINES FROM 100-FW-5301-A18 to FIRE WATERRING WELLHEAD AREA

Description:100-FW-5302-SL-A18ObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1076764070

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0023

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:1076764070

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 1/423

Page 2: checksheet

Area:53A02Package:

53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:

LINES FROM 100-FW-5301-A18 to FIRE WATERRING WELLHEAD AREA

Description:100-FW-5302-SL-A18ObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1076786854

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1076786854

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 2/423

Page 3: checksheet

Area:53A02Package:

53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:

LINES FROM 100-FW-5301-A18 to FIRE WATERRING WELLHEAD AREA

Description:100-FW-5302-SL-A18ObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1345210023

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1345210023

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 3/423

Page 4: checksheet

Area:65C02Package:

65C - NON-HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM NON-HAZARDOUS OPEN DRAINHEADER to OHD CAISSON (T-6510)

Description:150-DN-6547-SL-A18ObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:208686117

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0016

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:208686117

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 4/423

Page 5: checksheet

Area:65C02Package:

65C - NON-HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM NON-HAZARDOUS OPEN DRAINHEADER to OHD CAISSON (T-6510)

Description:150-DN-6547-SL-A18ObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:208676645

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:208676645

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 5/423

Page 6: checksheet

Area:65C02Package:

65C - NON-HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM NON-HAZARDOUS OPEN DRAINHEADER to OHD CAISSON (T-6510)

Description:150-DN-6547-SL-A18ObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:477108004

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:477108004

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 6/423

Page 7: checksheet

Area:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0111 to 150-PG-0151-GIY

Description:150-PG-0101-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:913119723

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:913119723

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 7/423

Page 8: checksheet

Area:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0111 to 150-PG-0151-GIY

Description:150-PG-0101-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:913142507

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:913142507

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 8/423

Page 9: checksheet

Area:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0111 to 150-PG-0151-GIY

Description:150-PG-0101-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:644694762

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:644694762

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 9/423

Page 10: checksheet

Area:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0121 to 150-PG-0152-GIY

Description:150-PG-0102-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:927799787

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:927799787

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 10/42

Page 11: checksheet

Area:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0121 to 150-PG-0152-GIY

Description:150-PG-0102-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:927822571

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:927822571

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 11/42

Page 12: checksheet

Area:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0121 to 150-PG-0152-GIY

Description:150-PG-0102-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:659374826

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:659374826

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 12/42

Page 13: checksheet

Area:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0131 to 150-PG-0153-GIY

Description:150-PG-0103-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:807213547

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:807213547

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 13/42

Page 14: checksheet

Area:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0131 to 150-PG-0153-GIY

Description:150-PG-0103-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:807236331

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:807236331

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 14/42

Page 15: checksheet

Area:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0131 to 150-PG-0153-GIY

Description:150-PG-0103-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:538788586

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:538788586

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 15/42

Page 16: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0141 to 150-PG-0154-GIY

Description:150-PG-0104-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:838670827

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:838670827

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 16/42

Page 17: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0141 to 150-PG-0154-GIY

Description:150-PG-0104-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:838693611

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:838693611

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 17/42

Page 18: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0141 to 150-PG-0154-GIY

Description:150-PG-0104-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:570245866

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:570245866

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 18/42

Page 19: checksheet

Area:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0151 to 150-PG-0155-GIY

Description:150-PG-0105-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:853350891

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:853350891

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 19/42

Page 20: checksheet

Area:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0151 to 150-PG-0155-GIY

Description:150-PG-0105-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:853373675

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:853373675

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 20/42

Page 21: checksheet

Area:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0151 to 150-PG-0155-GIY

Description:150-PG-0105-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:584925930

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:584925930

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 21/42

Page 22: checksheet

Area:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0161 to 150-PG-0156-GIY

Description:150-PG-0106-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:866982379

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:866982379

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 22/42

Page 23: checksheet

Area:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0161 to 150-PG-0156-GIY

Description:150-PG-0106-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:867005163

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:867005163

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 23/42

Page 24: checksheet

Area:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0161 to 150-PG-0156-GIY

Description:150-PG-0106-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:598557418

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:598557418

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 24/42

Page 25: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0171 to 150-PG-0157-GIY

Description:150-PG-0107-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1031608811

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:1031608811

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 25/42

Page 26: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0171 to 150-PG-0157-GIY

Description:150-PG-0107-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1031631595

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1031631595

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 26/42

Page 27: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0171 to 150-PG-0157-GIY

Description:150-PG-0107-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:763183850

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:763183850

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 27/42

Page 28: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0181 to 150-PG-0158-GIY

Description:150-PG-0108-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1046288875

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:1046288875

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 28/42

Page 29: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0181 to 150-PG-0158-GIY

Description:150-PG-0108-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1046311659

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1046311659

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 29/42

Page 30: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0181 to 150-PG-0158-GIY

Description:150-PG-0108-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:777863914

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:777863914

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 30/42

Page 31: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0191 to 150-PG-0159-GIY

Description:150-PG-0109-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1060968939

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:1060968939

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 31/42

Page 32: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0191 to 150-PG-0159-GIY

Description:150-PG-0109-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1060991723

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1060991723

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 32/42

Page 33: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0191 to 150-PG-0159-GIY

Description:150-PG-0109-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:792543978

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:792543978

Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 33/42

Page 34: checksheet

Area:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0201 to 150-PG-0160-GIY

Description:150-PG-0110-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:877463787

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:877463787

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 34/42

Page 35: checksheet

Area:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0201 to 150-PG-0160-GIY

Description:150-PG-0110-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:877487083

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:877487083

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 35/42

Page 36: checksheet

Area:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0201 to 150-PG-0160-GIY

Description:150-PG-0110-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:609047530

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:609047530

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 36/42

Page 37: checksheet

Area:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0211 to 150-PG-0145-GIY

Description:150-PG-0111-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:913115371

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:913115371

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 37/42

Page 38: checksheet

Area:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0211 to 150-PG-0145-GIY

Description:150-PG-0111-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:913138667

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:913138667

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 38/42

Page 39: checksheet

Area:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0211 to 150-PG-0145-GIY

Description:150-PG-0111-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:644699114

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:644699114

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 39/42

Page 40: checksheet

Area:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0221 to 150-PG-0146-GIY

Description:150-PG-0112-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:927795435

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:927795435

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 40/42

Page 41: checksheet

Area:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0221 to 150-PG-0146-GIY

Description:150-PG-0112-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:927818731

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:927818731

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 41/42

Page 42: checksheet

Area:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

LINES FROM CHOKE VALVE HCV-0221 to 150-PG-0146-GIY

Description:150-PG-0112-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:659379178

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:659379178

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 42/42

Page 43: checksheet

Area:42A03Package:

42A - A-4200 PRODUCED WATERSub System:42 - PRODUCED WATER TREATMENTSystem:

LINES FROM PRODUCED WATER SYSTEM (A-4200) to OHD CAISSON (T-6510)

Description:100-PW-4203-SL-B1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1031108017

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0012

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:1031108017

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 43/42

Page 44: checksheet

Area:42A03Package:

42A - A-4200 PRODUCED WATERSub System:42 - PRODUCED WATER TREATMENTSystem:

LINES FROM PRODUCED WATER SYSTEM (A-4200) to OHD CAISSON (T-6510)

Description:100-PW-4203-SL-B1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1031085745

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1031085745

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 44/42

Page 45: checksheet

Area:42A03Package:

42A - A-4200 PRODUCED WATERSub System:42 - PRODUCED WATER TREATMENTSystem:

LINES FROM PRODUCED WATER SYSTEM (A-4200) to OHD CAISSON (T-6510)

Description:100-PW-4203-SL-B1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:762654384

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:762654384

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 45/42

Page 46: checksheet

Area:65B02Package:

65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM HAZ'DOUS OPEN DRAIN HEADER(MAIN DECK) to OHD CAISSON (T-6510)

Description:150-DH-6503-SL-A18ObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1896898980

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0016

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:1896898980

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 46/42

Page 47: checksheet

Area:65B02Package:

65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM HAZ'DOUS OPEN DRAIN HEADER(MAIN DECK) to OHD CAISSON (T-6510)

Description:150-DH-6503-SL-A18ObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1896876708

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1896876708

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 47/42

Page 48: checksheet

Area:65B02Package:

65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM HAZ'DOUS OPEN DRAIN HEADER(MAIN DECK) to OHD CAISSON (T-6510)

Description:150-DH-6503-SL-A18ObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1628453541

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1628453541

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 48/42

Page 49: checksheet

Area:33A02Package:

33A - CONDENSATE EXPORTSub System:33 - CONDENSATE IMPORT/EXPORTSystem:

LINES FROM COND. PIG RECEIVER (L-3310) toPLEM VIA SUBSEA PIPELINE

Description:200-PL-3306-SL-C8YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1268396634

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0013

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:-1268396634

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 49/42

Page 50: checksheet

Area:33A02Package:

33A - CONDENSATE EXPORTSub System:33 - CONDENSATE IMPORT/EXPORTSystem:

LINES FROM COND. PIG RECEIVER (L-3310) toPLEM VIA SUBSEA PIPELINE

Description:200-PL-3306-SL-C8YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1268406618

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1268406618

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 50/42

Page 51: checksheet

Area:33A02Package:

33A - CONDENSATE EXPORTSub System:33 - CONDENSATE IMPORT/EXPORTSystem:

LINES FROM COND. PIG RECEIVER (L-3310) toPLEM VIA SUBSEA PIPELINE

Description:200-PL-3306-SL-C8YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1536846169

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1536846169

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 51/42

Page 52: checksheet

Area:29A02Package:

29A - GAS EXPORTSub System:29 - GAS IMPORT/EXPORTSystem:

LINES FROM GAS PIG LAUNCHER (L-2920) toMEPA / GORA PIPELINE BOUNDARY

Description:500-PG-2921-SL-C8YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2091123198

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0014

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:2091123198

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 52/42

Page 53: checksheet

Area:29A02Package:

29A - GAS EXPORTSub System:29 - GAS IMPORT/EXPORTSystem:

LINES FROM GAS PIG LAUNCHER (L-2920) toMEPA / GORA PIPELINE BOUNDARY

Description:500-PG-2921-SL-C8YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2091150078

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:2091150078

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 53/42

Page 54: checksheet

Area:29A02Package:

29A - GAS EXPORTSub System:29 - GAS IMPORT/EXPORTSystem:

LINES FROM GAS PIG LAUNCHER (L-2920) toMEPA / GORA PIPELINE BOUNDARY

Description:500-PG-2921-SL-C8YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1822710527

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1822710527

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 54/42

Page 55: checksheet

Area:62D14Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0110 CASING to 50-B-6211-G1Y

Description:50-B-6201-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:609277634

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:609277634

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 55/42

Page 56: checksheet

Area:62D14Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0110 CASING to 50-B-6211-G1Y

Description:50-B-6201-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:609271234

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:609271234

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 56/42

Page 57: checksheet

Area:62D14Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0110 CASING to 50-B-6211-G1Y

Description:50-B-6201-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:877694403

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:877694403

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 57/42

Page 58: checksheet

Area:62D15Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0120 CASING to 50-B-6211-G1Y

Description:50-B-6202-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:628152002

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:628152002

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 58/42

Page 59: checksheet

Area:62D15Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0120 CASING to 50-B-6211-G1Y

Description:50-B-6202-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:628145602

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:628145602

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 59/42

Page 60: checksheet

Area:62D15Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0120 CASING to 50-B-6211-G1Y

Description:50-B-6202-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:896568771

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:896568771

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 60/42

Page 61: checksheet

Area:62D16Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0130 CASING to 50-B-6211-G1Y

Description:50-B-6203-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:572577474

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:572577474

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 61/42

Page 62: checksheet

Area:62D16Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0130 CASING to 50-B-6211-G1Y

Description:50-B-6203-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:572571074

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:572571074

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 62/42

Page 63: checksheet

Area:62D16Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0130 CASING to 50-B-6211-G1Y

Description:50-B-6203-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:840994243

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:840994243

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 63/42

Page 64: checksheet

Area:62D17Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0140 CASING to 50-B-6211-G1Y

Description:50-B-6204-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:599840450

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:599840450

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 64/42

Page 65: checksheet

Area:62D17Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0140 CASING to 50-B-6211-G1Y

Description:50-B-6204-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:599834050

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:599834050

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 65/42

Page 66: checksheet

Area:62D17Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0140 CASING to 50-B-6211-G1Y

Description:50-B-6204-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:868257219

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:868257219

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 66/42

Page 67: checksheet

Area:62D18Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0150 CASING to 50-B-6211-G1Y

Description:50-B-6205-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:551605954

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:551605954

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 67/42

Page 68: checksheet

Area:62D18Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0150 CASING to 50-B-6211-G1Y

Description:50-B-6205-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:551599554

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:551599554

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 68/42

Page 69: checksheet

Area:62D18Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0150 CASING to 50-B-6211-G1Y

Description:50-B-6205-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:820022723

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:820022723

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 69/42

Page 70: checksheet

Area:62D01Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM CASING BLOWDOWN HEADER to 50-B-6213-B1Y

Description:50-B-6212-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:628148162

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0003

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:628148162

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 70/42

Page 71: checksheet

Area:62D01Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM CASING BLOWDOWN HEADER to 50-B-6213-B1Y

Description:50-B-6212-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:628141250

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:628141250

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 71/42

Page 72: checksheet

Area:62D01Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM CASING BLOWDOWN HEADER to 50-B-6213-B1Y

Description:50-B-6212-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:896572611

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:896572611

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 72/42

Page 73: checksheet

Area:62D19Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0160 CASING to 50-B-6211-G1Y

Description:50-B-6206-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:563140290

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:563140290

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 73/42

Page 74: checksheet

Area:62D19Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0160 CASING to 50-B-6211-G1Y

Description:50-B-6206-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:563133890

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:563133890

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 74/42

Page 75: checksheet

Area:62D19Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0160 CASING to 50-B-6211-G1Y

Description:50-B-6206-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:831557059

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:831557059

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 75/42

Page 76: checksheet

Area:62D20Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0170 CASING to 50-B-6211-G1Y

Description:50-B-6207-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:792778434

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:792778434

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 76/42

Page 77: checksheet

Area:62D20Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0170 CASING to 50-B-6211-G1Y

Description:50-B-6207-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:792772034

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:792772034

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 77/42

Page 78: checksheet

Area:62D20Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0170 CASING to 50-B-6211-G1Y

Description:50-B-6207-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1061195203

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1061195203

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 78/42

Page 79: checksheet

Area:62D21Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0180 CASING to 50-B-6211-G1Y

Description:50-B-6208-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:744543938

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:744543938

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 79/42

Page 80: checksheet

Area:62D21Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0180 CASING to 50-B-6211-G1Y

Description:50-B-6208-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:744537538

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:744537538

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 80/42

Page 81: checksheet

Area:62D21Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0180 CASING to 50-B-6211-G1Y

Description:50-B-6208-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1012960707

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1012960707

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 81/42

Page 82: checksheet

Area:62D22Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0190 CASING to 50-B-6211-G1Y

Description:50-B-6209-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:755029698

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:755029698

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 82/42

Page 83: checksheet

Area:62D22Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0190 CASING to 50-B-6211-G1Y

Description:50-B-6209-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:755023298

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:755023298

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 83/42

Page 84: checksheet

Area:62D22Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0190 CASING to 50-B-6211-G1Y

Description:50-B-6209-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1023446467

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1023446467

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 84/42

Page 85: checksheet

Area:62D23Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0200 CASING to 50-B-6211-G1Y

Description:50-B-6210-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:644925378

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:644925378

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 85/42

Page 86: checksheet

Area:62D23Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0200 CASING to 50-B-6211-G1Y

Description:50-B-6210-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:644918466

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:644918466

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 86/42

Page 87: checksheet

Area:62D23Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0200 CASING to 50-B-6211-G1Y

Description:50-B-6210-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:913349827

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:913349827

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 87/42

Page 88: checksheet

Area:62D24Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0210 CASING to 50-B-6211-G1Y

Description:50-B-6263-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:572582338

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:572582338

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 88/42

Page 89: checksheet

Area:62D24Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0210 CASING to 50-B-6211-G1Y

Description:50-B-6263-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:572555970

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:572555970

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 89/42

Page 90: checksheet

Area:62D24Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0210 CASING to 50-B-6211-G1Y

Description:50-B-6263-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:841003715

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:841003715

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 90/42

Page 91: checksheet

Area:62D25Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0220 CASING to 50-B-6211-G1Y

Description:50-B-6264-SL-G1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:599845314

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:599845314

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 91/42

Page 92: checksheet

Area:62D25Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0220 CASING to 50-B-6211-G1Y

Description:50-B-6264-SL-G1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:599818946

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:599818946

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 92/42

Page 93: checksheet

Area:62D25Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

LINES FROM WELLHEAD WH-0220 CASING to 50-B-6211-G1Y

Description:50-B-6264-SL-G1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:868266691

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:868266691

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 93/42

Page 94: checksheet

Area:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

LINES FROM OHD CAISSON (T-6510) to OHDCAISSON PUMP (P-6520)(OFFSHORE)

Description:50-DC-6541-SL-B1YObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-76968732

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0021

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:-76968732

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 94/42

Page 95: checksheet

Area:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

LINES FROM OHD CAISSON (T-6510) to OHDCAISSON PUMP (P-6520)(OFFSHORE)

Description:50-DC-6541-SL-B1YObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:996773118

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:996773118

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 95/42

Page 96: checksheet

Area:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

LINES FROM OHD CAISSON (T-6510) to OHDCAISSON PUMP (P-6520)(OFFSHORE)

Description:50-DC-6541-SL-B1YObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:996216050

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:996216050

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 96/42

Page 97: checksheet

Area:65B02Package:

65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM OHD CAISON PUMP (P-6520) to 150-DH-6503-A18

Description:50-DH-6508-SL-A18ObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1745386267

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0021

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:-1745386267

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 97/42

Page 98: checksheet

Area:65B02Package:

65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM OHD CAISON PUMP (P-6520) to 150-DH-6503-A18

Description:50-DH-6508-SL-A18ObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1475839231

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1475839231

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 98/42

Page 99: checksheet

Area:65B02Package:

65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM OHD CAISON PUMP (P-6520) to 150-DH-6503-A18

Description:50-DH-6508-SL-A18ObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1476330739

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1476330739

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 99/42

Page 100: checksheet

Area:65B02Package:

65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM FLARE K.O. DRUM COAMED AREA to150-DH-6503-A18

Description:50-DH-6528-SL-A18ObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1475839205

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0018

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:1475839205

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 100/4

Page 101: checksheet

Area:65B02Package:

65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM FLARE K.O. DRUM COAMED AREA to150-DH-6503-A18

Description:50-DH-6528-SL-A18ObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1745386241

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1745386241

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 101/4

Page 102: checksheet

Area:65B02Package:

65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:

LINES FROM FLARE K.O. DRUM COAMED AREA to150-DH-6503-A18

Description:50-DH-6528-SL-A18ObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1744894733

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1744894733

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 102/4

Page 103: checksheet

Area:53A02Package:

53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:

LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP

Description:50-FW-5310-SL-A18ObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-8879906

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0023

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:-8879906

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 103/4

Page 104: checksheet

Area:53A02Package:

53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:

LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP

Description:50-FW-5310-SL-A18ObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1064861892

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1064861892

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 104/4

Page 105: checksheet

Area:53A02Package:

53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:

LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP

Description:50-FW-5310-SL-A18ObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1064304840

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1064304840

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 105/4

Page 106: checksheet

Area:53A02Package:

53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:

LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP

Description:50-FW-5309-SL-A18ObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2004507870

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0023

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:2004507870

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 106/4

Page 107: checksheet

Area:53A02Package:

53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:

LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP

Description:50-FW-5309-SL-A18ObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1216717628

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1216717628

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 107/4

Page 108: checksheet

Area:53A02Package:

53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:

LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP

Description:50-FW-5309-SL-A18ObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1217209144

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1217209144

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 108/4

Page 109: checksheet

Area:51B02Package:

51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:

LINES FROM AIR RELEASE VALVE P-5110 to VENTTO SAFE LOCATION (OFFSHORE)

Description:50-VA-9802-SL-A18ObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1211973564

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0022

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:-1211973564

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 109/4

Page 110: checksheet

Area:51B02Package:

51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:

LINES FROM AIR RELEASE VALVE P-5110 to VENTTO SAFE LOCATION (OFFSHORE)

Description:50-VA-9802-SL-A18ObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2009251934

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:2009251934

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 110/4

Page 111: checksheet

Area:51B02Package:

51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:

LINES FROM AIR RELEASE VALVE P-5110 to VENTTO SAFE LOCATION (OFFSHORE)

Description:50-VA-9802-SL-A18ObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2009743442

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:2009743442

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 111/4

Page 112: checksheet

Area:51B02Package:

51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:

LINES FROM SERVICE WATER SUPPLY CAISSON(T-5510) to SERVICE WATER NETWORK

Description:50-WS-5104-SL-A18ObjectID:

Inspection Test ReportP04A Flushing and Testing Certificate

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2000686169

Operational Medium:

Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0022

Name and SignatureTest Witnessed by (Note2)

Name and SignatureTested by Contractor

HoursTest Duration

Date and TimeEnd Date and Time

Degree CAmbient Temperature at end

BarGTest Pressure at end

Date and TimeStart Date and Time

Degree CAmbient Temperature at start

BarGTest Pressure at start

Test Results and Readings

System tested in accordance with the approved procedure. (Refer Note1).

System prepared for testing in accordance with the approved procedure.

Flushing completed in accordance with the approved procedure

System prepared for flushing in accordance with the approvedprocedure.

Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.

DateVerified byCompleted byDescription of Item to be completed and Checked

Notes

1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.

3. All activity required Commissioning & Client Witness points

Date:

Sign:

Name:

BDEWC CommissionBDEWC QA/QCBDEWC Construction

OE:2000686169

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 112/4

Page 113: checksheet

Area:51B02Package:

51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:

LINES FROM SERVICE WATER SUPPLY CAISSON(T-5510) to SERVICE WATER NETWORK

Description:50-WS-5104-SL-A18ObjectID:

Inspection Test ReportP02A Piping Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1220539325

TestPack:Service:

All chain wheels and extended spindles installed.21

Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.

20

Gags on spring supports and expansion joints are in position.19

All pipe supports installed according to drawings and specifications.18

All thermowells are installed.17

Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*

16

Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*

15

All Relief valves, Bursting disks, and specified control valves have been removed. *W*14

All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*

13

Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*

12

All pressure connections as per specification.11

Compound on screwed connections in accordance with specifications.10

Branch reinforcements are correct.09

Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.

08

Rating of all forged steel fittings is correct. *W*07

Piping of correct material, schedule and type. *W*06

All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.

05

Correct bolts and gaskets are installed at all mechanical joints.04

All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.

03

All field weld inspection and NDE, Traceability and History records complete andaccepted.

02

System complies with P and ID's and isometric drawings.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1220539325

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 113/4

Page 114: checksheet

Area:51B02Package:

51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:

LINES FROM SERVICE WATER SUPPLY CAISSON(T-5510) to SERVICE WATER NETWORK

Description:50-WS-5104-SL-A18ObjectID:

Inspection Test ReportP10A Line Walk Verification

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1219982257

Service:

Required DOSH & 3rd Party witnessed16

Flange management complete and tag fitted to every joint (if specified in projectrequirements)

15

All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.

14

The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)

13

Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)

12

All temporary commissioning and start up strainers installed *W*11

Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs

10

Check manual valves are correctly lubricated, assessable and operational09

Line preserved according to project requirements.08

Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07

Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*

06

All Hydrotesting completed. *W*05

Lines dried in accordance with Project requirements *W*04

Lines flushed in accordance with Project requirements. *W*03

All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.

02

Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.

01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1219982257

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 114/4

Page 115: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

JUNCTION BOX 7710-JL05-9RDescription:7710-JL05-9RObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-306091743

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-306091743

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 115/4

Page 116: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

JUNCTION BOX 7710-JL05-9RDescription:7710-JL05-9RObjectID:

Inspection Test ReportE05A Distribution Board, Junction Box & ControlStation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-37645536

SingleLineDwg:

SerialNo:Model/Type:Manufacturer:

Replace all covers and check all bolts are correct none missing.12

Check gaskets and seals are not damaged.11

On completion of all cable glanding confirm spare entries are correctly plugged.10

Confirm all components are operational and lockable where necessary09

Check component ratings are as per drawings08

Check correct circuit identification labels.07

Check earthing conforms to project specifications.06

Check interior for damage, cleanliness and transport packing has been removed.05

Check equipment fixings and mountings are secure.04

Confirm equipment is tagged correctly03

Visually inspect equipment for external damage.02

Installation as per AFC Drawings and cable schedule01

Output /RemarksPLOKNADescriptionItem

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-37645536

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 116/4

Page 117: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

JUNCTION BOX 7710-JL06-9RDescription:7710-JL06-9RObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-306091761

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-306091761

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 117/4

Page 118: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

JUNCTION BOX 7710-JL06-9RDescription:7710-JL06-9RObjectID:

Inspection Test ReportE05A Distribution Board, Junction Box & ControlStation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-37645554

SingleLineDwg:

SerialNo:Model/Type:Manufacturer:

Replace all covers and check all bolts are correct none missing.12

Check gaskets and seals are not damaged.11

On completion of all cable glanding confirm spare entries are correctly plugged.10

Confirm all components are operational and lockable where necessary09

Check component ratings are as per drawings08

Check correct circuit identification labels.07

Check earthing conforms to project specifications.06

Check interior for damage, cleanliness and transport packing has been removed.05

Check equipment fixings and mountings are secure.04

Confirm equipment is tagged correctly03

Visually inspect equipment for external damage.02

Installation as per AFC Drawings and cable schedule01

Output /RemarksPLOKNADescriptionItem

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-37645554

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 118/4

Page 119: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

JUNCTION BOX 7710-JL07-9RDescription:7710-JL07-9RObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-306091819

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-306091819

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 119/4

Page 120: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

JUNCTION BOX 7710-JL07-9RDescription:7710-JL07-9RObjectID:

Inspection Test ReportE05A Distribution Board, Junction Box & ControlStation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-37645612

SingleLineDwg:

SerialNo:Model/Type:Manufacturer:

Replace all covers and check all bolts are correct none missing.12

Check gaskets and seals are not damaged.11

On completion of all cable glanding confirm spare entries are correctly plugged.10

Confirm all components are operational and lockable where necessary09

Check component ratings are as per drawings08

Check correct circuit identification labels.07

Check earthing conforms to project specifications.06

Check interior for damage, cleanliness and transport packing has been removed.05

Check equipment fixings and mountings are secure.04

Confirm equipment is tagged correctly03

Visually inspect equipment for external damage.02

Installation as per AFC Drawings and cable schedule01

Output /RemarksPLOKNADescriptionItem

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-37645612

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 120/4

Page 121: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

JUNCTION BOX 7710-JL08-9RDescription:7710-JL08-9RObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-306091855

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-306091855

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 121/4

Page 122: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

JUNCTION BOX 7710-JL08-9RDescription:7710-JL08-9RObjectID:

Inspection Test ReportE05A Distribution Board, Junction Box & ControlStation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-37645648

SingleLineDwg:

SerialNo:Model/Type:Manufacturer:

Replace all covers and check all bolts are correct none missing.12

Check gaskets and seals are not damaged.11

On completion of all cable glanding confirm spare entries are correctly plugged.10

Confirm all components are operational and lockable where necessary09

Check component ratings are as per drawings08

Check correct circuit identification labels.07

Check earthing conforms to project specifications.06

Check interior for damage, cleanliness and transport packing has been removed.05

Check equipment fixings and mountings are secure.04

Confirm equipment is tagged correctly03

Visually inspect equipment for external damage.02

Installation as per AFC Drawings and cable schedule01

Output /RemarksPLOKNADescriptionItem

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-37645648

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 122/4

Page 123: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

LIGHTING FIXTURE 7710-LE05-9RDescription:7710-LE05-9RObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-367956047

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-367956047

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 123/4

Page 124: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

LIGHTING FIXTURE 7710-LE06-9RDescription:7710-LE06-9RObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-367956065

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-367956065

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 124/4

Page 125: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

LIGHTING FIXTURE 7710-LE07-9RDescription:7710-LE07-9RObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-367956411

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-367956411

Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 125/4

Page 126: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

LIGHTING FIXTURE 7710-LE08-9RDescription:7710-LE08-9RObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-367956447

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-367956447

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 126/4

Page 127: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

Cable From JUNCTION BOX 7710-JL04-9R ToJUNCTION BOX 7710-JL05-9R

Description:7710-LE-09/9RObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-373690140

VoltageRating: 240VToTag: JUNCTION BOX 7710-JL05-9R

Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL04-9RCableType: P2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-373690140

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 127/4

Page 128: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

Cable From JUNCTION BOX 7710-JL05-9R ToLIGHTING FIXTURE 7710-LE05-9R

Description:7710-LE-10/9RObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-122049692

VoltageRating: 240VToTag: LIGHTING FIXTURE 7710-LE05-9R

Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL05-9RCableType: P2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-122049692

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 128/4

Page 129: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

Cable From JUNCTION BOX 7710-JL05-9R ToJUNCTION BOX 7710-JL06-9R

Description:7710-LE-11/9RObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-122045852

VoltageRating: 240VToTag: JUNCTION BOX 7710-JL06-9R

Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL05-9RCableType: P2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-122045852

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 129/4

Page 130: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

Cable From JUNCTION BOX 7710-JL06-9R ToLIGHTING FIXTURE 7710-LE06-9R

Description:7710-LE-12/9RObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-122047644

VoltageRating: 240VToTag: LIGHTING FIXTURE 7710-LE06-9R

Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL06-9RCableType: P2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-122047644

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 130/4

Page 131: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

Cable From JUNCTION BOX 7710-JL06-9R ToJUNCTION BOX 7710-JL07-9R

Description:7710-LE-13/9RObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-122058268

VoltageRating: 240VToTag: JUNCTION BOX 7710-JL07-9R

Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL06-9RCableType: P2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-122058268

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 131/4

Page 132: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

Cable From JUNCTION BOX 7710-JL07-9R ToLIGHTING FIXTURE 7710-LE07-9R

Description:7710-LE-14/9RObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-122059036

VoltageRating: 240VToTag: LIGHTING FIXTURE 7710-LE07-9R

Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL07-9RCableType: P2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-122059036

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 132/4

Page 133: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

Cable From JUNCTION BOX 7710-JL07-9R ToJUNCTION BOX 7710-JL08-9R

Description:7710-LE-15/9RObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-122052636

VoltageRating: 240VToTag: JUNCTION BOX 7710-JL08-9R

Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL07-9RCableType: P2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-122052636

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 133/4

Page 134: checksheet

Area:77D07Package:

77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:

Cable From JUNCTION BOX 7710-JL08-9R ToLIGHTING FIXTURE 7710-LE08-9R

Description:7710-LE-16/9RObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-122055580

VoltageRating: 240VToTag: LIGHTING FIXTURE 7710-LE08-9R

Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL08-9RCableType: P2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-122055580

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 134/4

Page 135: checksheet

Area:92E01Package:

92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:GOPB-ANT-9206ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1349334717

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1349334717

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 135/4

Page 136: checksheet

Area:92E01Package:

92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:GOPB-ANT-9206ObjectID:

Inspection Test ReportT01A Telecoms Field Device Installation Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-275101665

Type:

Service:Serial No:Manufacturer:

Suitable grease applied to flanges (Ex-d enclosures).14

Check earthing conforms to earthing philosophy.13

Gaskets & seals fitted correctly.12

Gaskets & seals undamaged.11

Terminal box flanges undamaged.10

Spare gland entries plugged correctly.09

Paintwork correct.08

Access suitable.07

Fixings correct.06

Supports installed correctly.05

Identification correct.04

Equipment suitable for area classification.03

Item complies with Data sheet.02

Installed according to latest revision of Layout drawing.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-275101665

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 136/4

Page 137: checksheet

Area:92E01Package:

92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:GOPB-ANT-9207ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1370961597

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1370961597

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 137/4

Page 138: checksheet

Area:92E01Package:

92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:GOPB-ANT-9207ObjectID:

Inspection Test ReportT01A Telecoms Field Device Installation Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-297777121

Type:

Service:Serial No:Manufacturer:

Suitable grease applied to flanges (Ex-d enclosures).14

Check earthing conforms to earthing philosophy.13

Gaskets & seals fitted correctly.12

Gaskets & seals undamaged.11

Terminal box flanges undamaged.10

Spare gland entries plugged correctly.09

Paintwork correct.08

Access suitable.07

Fixings correct.06

Supports installed correctly.05

Identification correct.04

Equipment suitable for area classification.03

Item complies with Data sheet.02

Installed according to latest revision of Layout drawing.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-297777121

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 138/4

Page 139: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PRESSURE GAUGEDescription:GORA-PG-2950ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:942423269

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:942423269

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 139/4

Page 140: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PRESSURE GAUGEDescription:GORA-PG-2953ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2016165108

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:2016165108

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 140/4

Page 141: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PRESSURE GAUGEDescription:GORA-PG-2954ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-131318541

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-131318541

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 141/4

Page 142: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

PRESSURE GAUGEDescription:GORA-PG-3390ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:955366657

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:955366657

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 142/4

Page 143: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

PRESSURE GAUGEDescription:GORA-PG-3393ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2029108496

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:2029108496

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 143/4

Page 144: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

PRESSURE GAUGEDescription:GORA-PG-3394ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-118375145

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-118375145

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 144/4

Page 145: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PRESSURE TRANSMITTERDescription:GORA-PIA-2952ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:452355156

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:452355156

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 145/4

Page 146: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PRESSURE TRANSMITTERDescription:GORA-PIA-2952ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-621386675

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-621386675

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 146/4

Page 147: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PRESSURE DIFFERENTIAL TRANSMITTERDescription:GORA-PIA-2955ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:440689748

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:440689748

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 147/4

Page 148: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PRESSURE DIFFERENTIAL TRANSMITTERDescription:GORA-PIA-2955ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-633052083

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-633052083

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 148/4

Page 149: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

PRESSURE TRANSMITTERDescription:GORA-PIA-3392ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:366367540

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:366367540

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 149/4

Page 150: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

PRESSURE TRANSMITTERDescription:GORA-PIA-3392ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-707374291

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-707374291

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 150/4

Page 151: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PRESSURE TRANSMITTERDescription:GORA-PZA-2951ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:449841236

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:449841236

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 151/4

Page 152: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PRESSURE TRANSMITTERDescription:GORA-PZA-2951ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-623900595

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-623900595

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 152/4

Page 153: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

PRESSURE TRANSMITTERDescription:GORA-PZA-3391ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:368066356

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:368066356

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 153/4

Page 154: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

PRESSURE TRANSMITTERDescription:GORA-PZA-3391ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-705675475

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-705675475

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 154/4

Page 155: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

SHUTDOWN VALVEDescription:GORA-SDV-2950ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-157891497

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-157891497

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 155/4

Page 156: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

SHUTDOWN VALVEDescription:GORA-SDV-2950ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-157891492

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-157891492

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 156/4

Page 157: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

SHUTDOWN VALVEDescription:GORA-SDV-2950ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:915850318

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:915850318

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 157/4

Page 158: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

SHUTDOWN VALVEDescription:GORA-SDV-2951ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-153959337

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-153959337

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 158/4

Page 159: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

SHUTDOWN VALVEDescription:GORA-SDV-2951ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-153959332

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-153959332

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 159/4

Page 160: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

SHUTDOWN VALVEDescription:GORA-SDV-2951ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:919782478

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:919782478

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 160/4

Page 161: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

SHUTDOWN VALVEDescription:GORA-SDV-3390ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-105450697

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-105450697

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 161/4

Page 162: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

SHUTDOWN VALVEDescription:GORA-SDV-3390ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-105450692

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-105450692

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 162/4

Page 163: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

SHUTDOWN VALVEDescription:GORA-SDV-3390ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:968291118

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:968291118

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 163/4

Page 164: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PIG SIGNALLER - LOCAL INDICATION -L2950Description:GORA-XI-2952ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1051489945

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1051489945

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 164/4

Page 165: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

PIG SIGNALLER - LOCAL INDICATION -L3390Description:GORA-XI-3392ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1047656317

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1047656317

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 165/4

Page 166: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PIG SIGNALLER - REMOTE INDICATION - L2950Description:GORA-XIA-2951ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2060608599

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:2060608599

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 166/4

Page 167: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

PIG SIGNALLER - REMOTE INDICATION - L2950Description:GORA-XIA-2951ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1160616882

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1160616882

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 167/4

Page 168: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

PIG SIGNALLER - REMOTE INDICATION - L3390Description:GORA-XIA-3391ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1978815287

Service:

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1978815287

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 168/4

Page 169: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

PIG SIGNALLER - REMOTE INDICATION - L3390Description:GORA-XIA-3391ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1242410194

Service:

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1242410194

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 169/4

Page 170: checksheet

Area:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0111Description:HY-0111ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-660729992

VoltageRating: -ToTag: MEPA-HY-0111

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-660729992

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 170/4

Page 171: checksheet

Area:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0121Description:HY-0121ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-660959368

VoltageRating: -ToTag: MEPA-HY-0121

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-660959368

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 171/4

Page 172: checksheet

Area:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0131Description:HY-0131ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-662188168

VoltageRating: -ToTag: MEPA-HY-0131

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-662188168

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 172/4

Page 173: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0141Description:HY-0141ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-662679688

VoltageRating: -ToTag: MEPA-HY-0141

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-662679688

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 173/4

Page 174: checksheet

Area:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0151Description:HY-0151ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-661860488

VoltageRating: -ToTag: MEPA-HY-0151

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-661860488

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 174/4

Page 175: checksheet

Area:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0161Description:HY-0161ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-662106248

VoltageRating: -ToTag: MEPA-HY-0161

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-662106248

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 175/4

Page 176: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0171Description:HY-0171ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-659402888

VoltageRating: -ToTag: MEPA-HY-0171

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-659402888

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 176/4

Page 177: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0181Description:HY-0181ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-658583688

VoltageRating: -ToTag: MEPA-HY-0181

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-658583688

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 177/4

Page 178: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0191Description:HY-0191ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-658813064

VoltageRating: -ToTag: MEPA-HY-0191

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-658813064

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 178/4

Page 179: checksheet

Area:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0201Description:HY-0201ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-661221540

VoltageRating: -ToTag: MEPA-HY-0201

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-661221540

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 179/4

Page 180: checksheet

Area:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0211Description:HY-0211ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-660730020

VoltageRating: -ToTag: MEPA-HY-0211

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-660730020

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 180/4

Page 181: checksheet

Area:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-009 To MEPA-HY-0221Description:HY-0221ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-660959396

VoltageRating: -ToTag: MEPA-HY-0221

Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-660959396

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 181/4

Page 182: checksheet

Area:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

Inst. Cable From MEPA-IJB-015 To MEPA-LT-6510Description:LT-6510ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1579289606

VoltageRating: -ToTag: MEPA-LT-6510

Size: 1PRx1.5mm2FromTag: MEPA-IJB-015CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1579289606

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 182/4

Page 183: checksheet

Area:92A02Package:

92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:MEPA-ANT-9201ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1351177929

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1351177929

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 183/4

Page 184: checksheet

Area:92A02Package:

92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:MEPA-ANT-9201ObjectID:

Inspection Test ReportT01A Telecoms Field Device Installation Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-276944789

Type:

Service:Serial No:Manufacturer:

Suitable grease applied to flanges (Ex-d enclosures).14

Check earthing conforms to earthing philosophy.13

Gaskets & seals fitted correctly.12

Gaskets & seals undamaged.11

Terminal box flanges undamaged.10

Spare gland entries plugged correctly.09

Paintwork correct.08

Access suitable.07

Fixings correct.06

Supports installed correctly.05

Identification correct.04

Equipment suitable for area classification.03

Item complies with Data sheet.02

Installed according to latest revision of Layout drawing.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-276944789

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 184/4

Page 185: checksheet

Area:92A02Package:

92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:MEPA-ANT-9202ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1353537225

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1353537225

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 185/4

Page 186: checksheet

Area:92A02Package:

92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:MEPA-ANT-9202ObjectID:

Inspection Test ReportT01A Telecoms Field Device Installation Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-279304085

Type:

Service:Serial No:Manufacturer:

Suitable grease applied to flanges (Ex-d enclosures).14

Check earthing conforms to earthing philosophy.13

Gaskets & seals fitted correctly.12

Gaskets & seals undamaged.11

Terminal box flanges undamaged.10

Spare gland entries plugged correctly.09

Paintwork correct.08

Access suitable.07

Fixings correct.06

Supports installed correctly.05

Identification correct.04

Equipment suitable for area classification.03

Item complies with Data sheet.02

Installed according to latest revision of Layout drawing.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-279304085

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 186/4

Page 187: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:MEPA-ANT-9203ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1346852553

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1346852553

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 187/4

Page 188: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:MEPA-ANT-9203ObjectID:

Inspection Test ReportT01A Telecoms Field Device Installation Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-273667989

Type:

Service:Serial No:Manufacturer:

Suitable grease applied to flanges (Ex-d enclosures).14

Check earthing conforms to earthing philosophy.13

Gaskets & seals fitted correctly.12

Gaskets & seals undamaged.11

Terminal box flanges undamaged.10

Spare gland entries plugged correctly.09

Paintwork correct.08

Access suitable.07

Fixings correct.06

Supports installed correctly.05

Identification correct.04

Equipment suitable for area classification.03

Item complies with Data sheet.02

Installed according to latest revision of Layout drawing.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-273667989

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 188/4

Page 189: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:MEPA-ANT-9204ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1350260425

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1350260425

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 189/4

Page 190: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:MEPA-ANT-9204ObjectID:

Inspection Test ReportT01A Telecoms Field Device Installation Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-276027285

Type:

Service:Serial No:Manufacturer:

Suitable grease applied to flanges (Ex-d enclosures).14

Check earthing conforms to earthing philosophy.13

Gaskets & seals fitted correctly.12

Gaskets & seals undamaged.11

Terminal box flanges undamaged.10

Spare gland entries plugged correctly.09

Paintwork correct.08

Access suitable.07

Fixings correct.06

Supports installed correctly.05

Identification correct.04

Equipment suitable for area classification.03

Item complies with Data sheet.02

Installed according to latest revision of Layout drawing.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-276027285

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 190/4

Page 191: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:MEPA-ANT-9205ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1344231113

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1344231113

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 191/4

Page 192: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

PARABOLIC ANTENNADescription:MEPA-ANT-9205ObjectID:

Inspection Test ReportT01A Telecoms Field Device Installation Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-269997973

Type:

Service:Serial No:Manufacturer:

Suitable grease applied to flanges (Ex-d enclosures).14

Check earthing conforms to earthing philosophy.13

Gaskets & seals fitted correctly.12

Gaskets & seals undamaged.11

Terminal box flanges undamaged.10

Spare gland entries plugged correctly.09

Paintwork correct.08

Access suitable.07

Fixings correct.06

Supports installed correctly.05

Identification correct.04

Equipment suitable for area classification.03

Item complies with Data sheet.02

Installed according to latest revision of Layout drawing.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-269997973

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 192/4

Page 193: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

UHF DATA RADIO 5.8GHZDescription:MEPA-ANT-9206ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1345410761

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1345410761

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 193/4

Page 194: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

UHF DATA RADIO 5.8GHZDescription:MEPA-ANT-9206ObjectID:

Inspection Test ReportT01A Telecoms Field Device Installation Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-272226197

Type:

Service:Serial No:Manufacturer:

Suitable grease applied to flanges (Ex-d enclosures).14

Check earthing conforms to earthing philosophy.13

Gaskets & seals fitted correctly.12

Gaskets & seals undamaged.11

Terminal box flanges undamaged.10

Spare gland entries plugged correctly.09

Paintwork correct.08

Access suitable.07

Fixings correct.06

Supports installed correctly.05

Identification correct.04

Equipment suitable for area classification.03

Item complies with Data sheet.02

Installed according to latest revision of Layout drawing.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-272226197

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 194/4

Page 195: checksheet

All Fireproofing clean and undamaged86

Fireproofing material finish conforms to agreed sample (where applicable)85

Fireproofing materials applied according to specification84

All paintwork clean and undamaged83

Finish paint colour conforms to specification82

All remedial work completed and accepted81

All specified adhesion tests completed and accepted80

Correct paint system applied according to specification and in accordance with supplierrequirements

79

Painting , Coatings and Fireproofing78

Hose reel rewind satisfactorily.77

Hose nozzle operation and shut-off checked.76

Hose free from damage and kinks.75

Hose reel runs out correctly.74

Main valves checked for ease of operation and shut-off.73

Stop valves checked for ease of operation and shut-off.72

Operation instructions fitted and legible.71

Cabinet doors secure.70

Hose reel correctly installed to manufacturers instructions.69

Hose reels68

Escape route / safety signs not obstructed and legible.67

Escape route / safety signs securely fixed in position.66

Escape route / safety signs, location correct as per Loss Control layout drawings.65

Direction of escape correct and clearly marked.64

Escape routes painted to specification and non-skid surface complete.63

Escape routes not obstructed.62

Escape route in accordance with Loss Control layout drawings.61

Escape Routes and Platform Signs60

Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.

59

Insulation materials do not obstruct operation of access man-ways.58

All data plates and tag numbers are visible.57

All equipment nozzles and instruments are clear of the insulation material and jacketing.56

Jacketing, type, application and condition conforms to latest AFC specifications.55

Insulation, thickness and material in accordance with latest AFC specifications.54

Equipment53

Mastic and water seals correctly installed52

Cable and piping penetrations completed and sealed in accordance with the latest AFCspecifications.

51

Fixing materials, including screws and banding, are of the correct type and installed inaccordance with the latest AFC specification.

50

Jacketing thickness and material in accordance with the latest AFC specifications.49

Insulation, thickness and material in accordance with the latest AFC specifications.48

Snap on boxes fitted at all required locations in accordance with the specifications.47

Access to all instruments, including in-line instruments unobstructed by insulationmaterials.

46

No attachment points on the piping system are covered by insulation material.45

Limits of insulation in accordance with the latest AFC P&ID, drawings and specifications.44

Piping Systems43

System and temporary dust blinds are visible.42

Identification labels and arrows installed.41

Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.

40

Insulation materials do not obstruct operation of access man-ways.39

Data plates and tag numbers are visible.38

Jacketing, type, application and condition conforms to requirements.37

Insulation, thickness and material in accordance with the latest AFC specifications.36

Limits of insulation with the latest AFC D & ID drawings and specifications.35

HVAC Ductwork34

Galvanised steel lining fixed to protect wall and deck-head insulation as specified bylatest AFC shop drawings and Vendor details.

33

All cable penetrations confirm to the requirements of the penetration dossier for firerating.

32

All piping and ducting penetrations in accordance with the requirements of the latest AFCpenetration dossier for fire rating.

31

Mesh of correct type has been installed according to the latest AFC specification.30

Insulating material and thickness in accordance with the latest AFC specification. Vapourbarriers installed where required.

29

Pins installed, where applicable, in accordance with latest AFC specifications.28

Walls and Ceilings27

Confirm all cable ladder are fully covered (if applicable)26

Confirm cable dressing is complete25

Confirm all transits are complete and blocked.24

Confirm all transits are packed in accordance with the transit schedule23

Confirm all transit frames are installed correctly22

Confirm all dissimilar metal insulators are installed.21

Confirm all earth bonding is complete20

Confirm all cables are clipped with permanent fixings19

Confirm all cable racks are identified18

Confirm all supports and fixings are correct and complete17

Confirm all cable trays and racks are installed in accordance with routing and detaildrawings

16

Electrical Cable Racks, ladder, transit and cover15

Area is clean and free of all debris.14

Information signs installed.13

Furniture: All furniture of correct colour and placed in accordance with drawings, alldrawers/locker doors open/shut, all locks function. All spare keys taped securely adjacentto respective locks.

12

All doors and windows free from damage and installed correctly in accordance with latestAFC drawings.

11

Suspended floors correct and un-damaged.10

Water bunds turned up around walls in wet areas.09

Floors lay to drain evenly to outlets, with no puddling or flat spots.08

Floor coating: Floor screed placed according to specification, carpet or tiles of correctcolour, embedding of carpet or tiles is firm without any gaps or damage.

07

Pre-fabricated firewalls/louvers installed to specification with sealed joints, plumb andlined, without damage.

06

Wall and ceiling linings: Insulation and vapour barrier placed and undamaged, liningcolour correct, ceiling and wall panels correctly trimmed and free from damage.

05

All equipment performs its specified function.04

All equipment free from damage installed and correctly secured in accordance with latestAFC drawings.

03

All equipment located and correctly tagged in accordance with latest AFC drawings.02

General01

Output /RemarksPLOKNADescriptionItem

Area:71E01Package:

71E - BOAT LANDINGSub System:71 - STRUCTURALSystem:

BOAT LANDINGDescription:MEPA-BL-7100ObjectID:

Inspection Test ReportM20A Area Completion

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:335707679

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:335707679

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 195/4

Page 196: checksheet

All Fireproofing clean and undamaged86

Fireproofing material finish conforms to agreed sample (where applicable)85

Fireproofing materials applied according to specification84

All paintwork clean and undamaged83

Finish paint colour conforms to specification82

All remedial work completed and accepted81

All specified adhesion tests completed and accepted80

Correct paint system applied according to specification and in accordance with supplierrequirements

79

Painting , Coatings and Fireproofing78

Hose reel rewind satisfactorily.77

Hose nozzle operation and shut-off checked.76

Hose free from damage and kinks.75

Hose reel runs out correctly.74

Main valves checked for ease of operation and shut-off.73

Stop valves checked for ease of operation and shut-off.72

Operation instructions fitted and legible.71

Cabinet doors secure.70

Hose reel correctly installed to manufacturers instructions.69

Hose reels68

Escape route / safety signs not obstructed and legible.67

Escape route / safety signs securely fixed in position.66

Escape route / safety signs, location correct as per Loss Control layout drawings.65

Direction of escape correct and clearly marked.64

Escape routes painted to specification and non-skid surface complete.63

Escape routes not obstructed.62

Escape route in accordance with Loss Control layout drawings.61

Escape Routes and Platform Signs60

Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.

59

Insulation materials do not obstruct operation of access man-ways.58

All data plates and tag numbers are visible.57

All equipment nozzles and instruments are clear of the insulation material and jacketing.56

Jacketing, type, application and condition conforms to latest AFC specifications.55

Insulation, thickness and material in accordance with latest AFC specifications.54

Equipment53

Mastic and water seals correctly installed52

Cable and piping penetrations completed and sealed in accordance with the latest AFCspecifications.

51

Fixing materials, including screws and banding, are of the correct type and installed inaccordance with the latest AFC specification.

50

Jacketing thickness and material in accordance with the latest AFC specifications.49

Insulation, thickness and material in accordance with the latest AFC specifications.48

Snap on boxes fitted at all required locations in accordance with the specifications.47

Access to all instruments, including in-line instruments unobstructed by insulationmaterials.

46

No attachment points on the piping system are covered by insulation material.45

Limits of insulation in accordance with the latest AFC P&ID, drawings and specifications.44

Piping Systems43

System and temporary dust blinds are visible.42

Identification labels and arrows installed.41

Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.

40

Insulation materials do not obstruct operation of access man-ways.39

Data plates and tag numbers are visible.38

Jacketing, type, application and condition conforms to requirements.37

Insulation, thickness and material in accordance with the latest AFC specifications.36

Limits of insulation with the latest AFC D & ID drawings and specifications.35

HVAC Ductwork34

Galvanised steel lining fixed to protect wall and deck-head insulation as specified bylatest AFC shop drawings and Vendor details.

33

All cable penetrations confirm to the requirements of the penetration dossier for firerating.

32

All piping and ducting penetrations in accordance with the requirements of the latest AFCpenetration dossier for fire rating.

31

Mesh of correct type has been installed according to the latest AFC specification.30

Insulating material and thickness in accordance with the latest AFC specification. Vapourbarriers installed where required.

29

Pins installed, where applicable, in accordance with latest AFC specifications.28

Walls and Ceilings27

Confirm all cable ladder are fully covered (if applicable)26

Confirm cable dressing is complete25

Confirm all transits are complete and blocked.24

Confirm all transits are packed in accordance with the transit schedule23

Confirm all transit frames are installed correctly22

Confirm all dissimilar metal insulators are installed.21

Confirm all earth bonding is complete20

Confirm all cables are clipped with permanent fixings19

Confirm all cable racks are identified18

Confirm all supports and fixings are correct and complete17

Confirm all cable trays and racks are installed in accordance with routing and detaildrawings

16

Electrical Cable Racks, ladder, transit and cover15

Area is clean and free of all debris.14

Information signs installed.13

Furniture: All furniture of correct colour and placed in accordance with drawings, alldrawers/locker doors open/shut, all locks function. All spare keys taped securely adjacentto respective locks.

12

All doors and windows free from damage and installed correctly in accordance with latestAFC drawings.

11

Suspended floors correct and un-damaged.10

Water bunds turned up around walls in wet areas.09

Floors lay to drain evenly to outlets, with no puddling or flat spots.08

Floor coating: Floor screed placed according to specification, carpet or tiles of correctcolour, embedding of carpet or tiles is firm without any gaps or damage.

07

Pre-fabricated firewalls/louvers installed to specification with sealed joints, plumb andlined, without damage.

06

Wall and ceiling linings: Insulation and vapour barrier placed and undamaged, liningcolour correct, ceiling and wall panels correctly trimmed and free from damage.

05

All equipment performs its specified function.04

All equipment free from damage installed and correctly secured in accordance with latestAFC drawings.

03

All equipment located and correctly tagged in accordance with latest AFC drawings.02

General01

Output /RemarksPLOKNADescriptionItem

Area:71E01Package:

71E - BOAT LANDINGSub System:71 - STRUCTURALSystem:

BOAT LANDINGDescription:MEPA-BL-7100ObjectID:

Inspection Test ReportM20A Area Completion

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:335707679

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:335707679

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 196/4

Page 197: checksheet

Area:71E01Package:

71E - BOAT LANDINGSub System:71 - STRUCTURALSystem:

BOAT LANDINGDescription:MEPA-BL-7100ObjectID:

Inspection Test ReportM20A Area Completion

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:335707679

All Fireproofing clean and undamaged86

Fireproofing material finish conforms to agreed sample (where applicable)85

Fireproofing materials applied according to specification84

All paintwork clean and undamaged83

Finish paint colour conforms to specification82

All remedial work completed and accepted81

All specified adhesion tests completed and accepted80

Correct paint system applied according to specification and in accordance with supplierrequirements

79

Painting , Coatings and Fireproofing78

Hose reel rewind satisfactorily.77

Hose nozzle operation and shut-off checked.76

Hose free from damage and kinks.75

Hose reel runs out correctly.74

Main valves checked for ease of operation and shut-off.73

Stop valves checked for ease of operation and shut-off.72

Operation instructions fitted and legible.71

Cabinet doors secure.70

Hose reel correctly installed to manufacturers instructions.69

Hose reels68

Escape route / safety signs not obstructed and legible.67

Escape route / safety signs securely fixed in position.66

Escape route / safety signs, location correct as per Loss Control layout drawings.65

Direction of escape correct and clearly marked.64

Escape routes painted to specification and non-skid surface complete.63

Escape routes not obstructed.62

Escape route in accordance with Loss Control layout drawings.61

Escape Routes and Platform Signs60

Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.

59

Insulation materials do not obstruct operation of access man-ways.58

All data plates and tag numbers are visible.57

All equipment nozzles and instruments are clear of the insulation material and jacketing.56

Jacketing, type, application and condition conforms to latest AFC specifications.55

Insulation, thickness and material in accordance with latest AFC specifications.54

Equipment53

Mastic and water seals correctly installed52

Cable and piping penetrations completed and sealed in accordance with the latest AFCspecifications.

51

Fixing materials, including screws and banding, are of the correct type and installed inaccordance with the latest AFC specification.

50

Jacketing thickness and material in accordance with the latest AFC specifications.49

Insulation, thickness and material in accordance with the latest AFC specifications.48

Snap on boxes fitted at all required locations in accordance with the specifications.47

Access to all instruments, including in-line instruments unobstructed by insulationmaterials.

46

No attachment points on the piping system are covered by insulation material.45

Limits of insulation in accordance with the latest AFC P&ID, drawings and specifications.44

Piping Systems43

System and temporary dust blinds are visible.42

Identification labels and arrows installed.41

Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.

40

Insulation materials do not obstruct operation of access man-ways.39

Data plates and tag numbers are visible.38

Jacketing, type, application and condition conforms to requirements.37

Insulation, thickness and material in accordance with the latest AFC specifications.36

Limits of insulation with the latest AFC D & ID drawings and specifications.35

HVAC Ductwork34

Galvanised steel lining fixed to protect wall and deck-head insulation as specified bylatest AFC shop drawings and Vendor details.

33

All cable penetrations confirm to the requirements of the penetration dossier for firerating.

32

All piping and ducting penetrations in accordance with the requirements of the latest AFCpenetration dossier for fire rating.

31

Mesh of correct type has been installed according to the latest AFC specification.30

Insulating material and thickness in accordance with the latest AFC specification. Vapourbarriers installed where required.

29

Pins installed, where applicable, in accordance with latest AFC specifications.28

Walls and Ceilings27

Confirm all cable ladder are fully covered (if applicable)26

Confirm cable dressing is complete25

Confirm all transits are complete and blocked.24

Confirm all transits are packed in accordance with the transit schedule23

Confirm all transit frames are installed correctly22

Confirm all dissimilar metal insulators are installed.21

Confirm all earth bonding is complete20

Confirm all cables are clipped with permanent fixings19

Confirm all cable racks are identified18

Confirm all supports and fixings are correct and complete17

Confirm all cable trays and racks are installed in accordance with routing and detaildrawings

16

Electrical Cable Racks, ladder, transit and cover15

Area is clean and free of all debris.14

Information signs installed.13

Furniture: All furniture of correct colour and placed in accordance with drawings, alldrawers/locker doors open/shut, all locks function. All spare keys taped securely adjacentto respective locks.

12

All doors and windows free from damage and installed correctly in accordance with latestAFC drawings.

11

Suspended floors correct and un-damaged.10

Water bunds turned up around walls in wet areas.09

Floors lay to drain evenly to outlets, with no puddling or flat spots.08

Floor coating: Floor screed placed according to specification, carpet or tiles of correctcolour, embedding of carpet or tiles is firm without any gaps or damage.

07

Pre-fabricated firewalls/louvers installed to specification with sealed joints, plumb andlined, without damage.

06

Wall and ceiling linings: Insulation and vapour barrier placed and undamaged, liningcolour correct, ceiling and wall panels correctly trimmed and free from damage.

05

All equipment performs its specified function.04

All equipment free from damage installed and correctly secured in accordance with latestAFC drawings.

03

All equipment located and correctly tagged in accordance with latest AFC drawings.02

General01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:335707679

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 197/4

Page 198: checksheet

Area:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

-Description:MEPA-GB-5110ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1673674738

Service: Service Water Pump P-5110RUN/STOP STATUS

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1673674738

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 198/4

Page 199: checksheet

Cellar DeckArea:80E02Package:

80E - FIRE ZONE 4Sub System:80 - FIRE & GAS DETECTIONSystem:

IR - POINT TYPE GAS DETECTOR - Cellar DeckDescription:MEPA-GD-8026ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:497631589

Service: Gas Detector at Cellar Deck

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:497631589

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 199/4

Page 200: checksheet

Cellar DeckArea:80E02Package:

80E - FIRE ZONE 4Sub System:80 - FIRE & GAS DETECTIONSystem:

IR - POINT TYPE GAS DETECTOR - Cellar DeckDescription:MEPA-GD-8027ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1571373406

Service: Gas Detector at Cellar Deck

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1571373406

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 200/4

Page 201: checksheet

Area:32A01Package:

32A - A-3200 CONDENSATE ALLOCATIONMETERING

Sub System:32 - CONDENSATE METERINGSystem:

LIMIT SWITCH CLOSE - MEPA-XV-3210 - AllocationCondensate Meter Duty Run

Description:MEPA-GSC-3210ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:985257494

Service: MEPA-XV-3210 - AllocationCondensate Meter Duty Run

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:985257494

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 201/4

Page 202: checksheet

Area:32A01Package:

32A - A-3200 CONDENSATE ALLOCATIONMETERING

Sub System:32 - CONDENSATE METERINGSystem:

LIMIT SWITCH CLOSE - MEPAXV-3211 - AllocationCondensate Meter Duty Run

Description:MEPA-GSC-3211ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:989713942

Service: MEPA-XV-3211 - AllocationCondensate Meter Duty Run

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:989713942

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 202/4

Page 203: checksheet

Area:32A01Package:

32A - A-3200 CONDENSATE ALLOCATIONMETERING

Sub System:32 - CONDENSATE METERINGSystem:

LIMIT SWITCH CLOSE - MEPA-XV-3220-AllocationCondensate Meter Standby Run

Description:MEPA-GSC-3220ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:985257782

Service: MEPA-XV-3220-AllocationCondensate Meter Standby Run

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:985257782

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 203/4

Page 204: checksheet

Area:32A01Package:

32A - A-3200 CONDENSATE ALLOCATIONMETERING

Sub System:32 - CONDENSATE METERINGSystem:

LIMIT SWITCH CLOSE - MEPA-XV-3221-AllocationCondensate Meter Standby Run

Description:MEPA-GSC-3221ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:989714230

Service: MEPA-XV-3221-AllocationCondensate Meter Standby Run

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:989714230

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 204/4

Page 205: checksheet

Area:32A01Package:

32A - A-3200 CONDENSATE ALLOCATIONMETERING

Sub System:32 - CONDENSATE METERINGSystem:

LIMIT SWITCH OPEN - MEPA-XV-3210 - AllocationCondensate Meter Duty Run

Description:MEPA-GSO-3210ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:28956182

Service: MEPA-XV-3210 - AllocationCondensate Meter Duty Run

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:28956182

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 205/4

Page 206: checksheet

Area:32A01Package:

32A - A-3200 CONDENSATE ALLOCATIONMETERING

Sub System:32 - CONDENSATE METERINGSystem:

LIMIT SWITCH OPEN - MEPA-XV-3211 - AllocationCondensate Meter Duty Run

Description:MEPA-GSO-3211ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:33412630

Service: MEPA-XV-3211 - AllocationCondensate Meter Duty Run

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:33412630

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 206/4

Page 207: checksheet

Area:32A01Package:

32A - A-3200 CONDENSATE ALLOCATIONMETERING

Sub System:32 - CONDENSATE METERINGSystem:

LIMIT SWITCH OPEN - MEPA-XV-3220-AllocationCondensate Meter Standby Run

Description:MEPA-GSO-3220ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:28956470

Service: MEPA-XV-3220-AllocationCondensate Meter Standby Run

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:28956470

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 207/4

Page 208: checksheet

Area:32A01Package:

32A - A-3200 CONDENSATE ALLOCATIONMETERING

Sub System:32 - CONDENSATE METERINGSystem:

LIMIT SWITCH OPEN - MEPA-XV-3222-AllocationCondensate Meter Standby Run

Description:MEPA-GSO-3221ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:33412918

Service: MEPA-XV-3222-AllocationCondensate Meter Standby Run

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:33412918

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 208/4

Page 209: checksheet

Area:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0110Gas Flowline

Description:MEPA-HCV-0111ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-874538855

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-874538855

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 209/4

Page 210: checksheet

Area:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0110Gas Flowline

Description:MEPA-HCV-0111ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1948280700

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1948280700

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 210/4

Page 211: checksheet

Area:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0120Gas Flowline

Description:MEPA-HCV-0121ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-874538567

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-874538567

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 211/4

Page 212: checksheet

Area:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0120Gas Flowline

Description:MEPA-HCV-0121ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1948280412

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1948280412

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 212/4

Page 213: checksheet

Area:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0130Gas Flowline

Description:MEPA-HCV-0131ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-874537239

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-874537239

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 213/4

Page 214: checksheet

Area:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0130Gas Flowline

Description:MEPA-HCV-0131ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1948279052

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1948279052

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 214/4

Page 215: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Gas Wellhead MEPA-WH-0140 Gas FlowlineDescription:MEPA-HCV-0141ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-874537207

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-874537207

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 215/4

Page 216: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Gas Wellhead MEPA-WH-0140 Gas FlowlineDescription:MEPA-HCV-0141ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1948279020

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1948279020

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 216/4

Page 217: checksheet

Area:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Gas Wellhead MEPA-WH-0150 Gas FlowlineDescription:MEPA-HCV-0151ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-874537943

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-874537943

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 217/4

Page 218: checksheet

Area:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Gas Wellhead MEPA-WH-0150 Gas FlowlineDescription:MEPA-HCV-0151ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1948279756

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1948279756

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 218/4

Page 219: checksheet

Area:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Gas Wellhead MEPA-WH-0160 Gas FlowlineDescription:MEPA-HCV-0161ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-874537639

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-874537639

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 219/4

Page 220: checksheet

Area:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Gas Wellhead MEPA-WH-0160 Gas FlowlineDescription:MEPA-HCV-0161ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1948279484

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1948279484

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 220/4

Page 221: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0170Gas Flowline

Description:MEPA-HCV-0171ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-874540151

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-874540151

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 221/4

Page 222: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0170Gas Flowline

Description:MEPA-HCV-0171ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1948281964

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1948281964

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 222/4

Page 223: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0180Gas Flowline

Description:MEPA-HCV-0181ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-874540887

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-874540887

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 223/4

Page 224: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0180Gas Flowline

Description:MEPA-HCV-0181ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1948282700

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1948282700

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 224/4

Page 225: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0190Gas Flowline

Description:MEPA-HCV-0191ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-874540599

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-874540599

Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 225/4

Page 226: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0190Gas Flowline

Description:MEPA-HCV-0191ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1948282412

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1948282412

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 226/4

Page 227: checksheet

Area:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0200Gas Flowline

Description:MEPA-HCV-0201ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-889218375

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-889218375

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 227/4

Page 228: checksheet

Area:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0200Gas Flowline

Description:MEPA-HCV-0201ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1962960220

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1962960220

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 228/4

Page 229: checksheet

Area:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0210Gas Flowline

Description:MEPA-HCV-0211ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-889218919

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-889218919

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 229/4

Page 230: checksheet

Area:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0210Gas Flowline

Description:MEPA-HCV-0211ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1962960764

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1962960764

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 230/4

Page 231: checksheet

Area:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0220Gas Flowline

Description:MEPA-HCV-0221ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-889218631

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-889218631

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 231/4

Page 232: checksheet

Area:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

CHOKE VALVE - Gas Wellhead MEPA-WH-0220Gas Flowline

Description:MEPA-HCV-0221ObjectID:

Inspection Test ReportI03A Valve and Ancillaries

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1962960476

02.33 - Correct to Data Sheet

MISCELLANEOUS ACCESSORIES02.32

02.31 - Range

02.30 - Model / type : ______________________

02.29 - Serial No : ______________________

FILTER/REGULATOR02.28

02.27 - Output range

02.26 - Signal range

02.25 - Model / type : ______________________

02.24 - Serial No : ______________________

I/P CONVERTER02.23

02.22 - Output range

02.21 - Signal range

02.20 - Model / type : ______________________

02.19 - Serial No : ______________________

POSITIONER02.18

02.17 - Hand wheel operation correct

02.16 - Failure action

02.15 - Input range

02.14 - Model / type : ______________________

02.13 - Serial No : ______________________

ACTUATOR02.12

02.11 - Leakage class

02.10 - Trim material correct

02.09 - Body material

02.08 - Material certification correct

02.07 - Service

02.06 - Flange type

02.05 - Rating

02.04 - Size

02.03 - Model / type : ______________________

02.02 - Serial No : ______________________

VALVE02.01

All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.

02

All equipment free from damage and installed correctly01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1962960476

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 232/4

Page 233: checksheet

Area:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0111 - GasWellhead MEPA-WH-0110

Description:MEPA-HY-0111ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:478137062

Service: For MEPA-HCV-0111 - Gas WellheadMEPA-WH-0110

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:478137062

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 233/4

Page 234: checksheet

Area:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0111 - GasWellhead MEPA-WH-0110

Description:MEPA-HY-0111ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:125821927

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:125821927

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 234/4

Page 235: checksheet

Area:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0121 - GasWellhead MEPA-WH-0120

Description:MEPA-HY-0121ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:477842150

Service: For MEPA-HCV-0121 - Gas WellheadMEPA-WH-0120

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:477842150

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 235/4

Page 236: checksheet

Area:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0121 - GasWellhead MEPA-WH-0120

Description:MEPA-HY-0121ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:125527015

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:125527015

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 236/4

Page 237: checksheet

Area:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0131 - GasWellhead MEPA-WH-0130

Description:MEPA-HY-0131ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:476449510

Service: For MEPA-HCV-0131 - Gas WellheadMEPA-WH-0130

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:476449510

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 237/4

Page 238: checksheet

Area:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0131 - GasWellhead MEPA-WH-0130

Description:MEPA-HY-0131ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:124134375

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:124134375

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 238/4

Page 239: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0141 - GasWellhead MEPA-WH-0140

Description:MEPA-HY-0141ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:476154598

Service: For MEPA-HCV-0141 - Gas WellheadMEPA-WH-0140

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:476154598

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 239/4

Page 240: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0141 - GasWellhead MEPA-WH-0140

Description:MEPA-HY-0141ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:123839463

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:123839463

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 240/4

Page 241: checksheet

Area:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0151 - GasWellhead MEPA-WH-0150

Description:MEPA-HY-0151ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:476908262

Service: For MEPA-HCV-0151 - Gas WellheadMEPA-WH-0150

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:476908262

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 241/4

Page 242: checksheet

Area:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0151 - GasWellhead MEPA-WH-0150

Description:MEPA-HY-0151ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:124593127

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:124593127

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 242/4

Page 243: checksheet

Area:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0161 - GasWellhead MEPA-WH-0160

Description:MEPA-HY-0161ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:476629734

Service: For MEPA-HCV-0161 - Gas WellheadMEPA-WH-0160

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:476629734

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 243/4

Page 244: checksheet

Area:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0161 - GasWellhead MEPA-WH-0160

Description:MEPA-HY-0161ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:124314599

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:124314599

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 244/4

Page 245: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0171 - GasWellhead MEPA-WH-0170

Description:MEPA-HY-0171ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:475237094

Service: For MEPA-HCV-0171 - Gas WellheadMEPA-WH-0170

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:475237094

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 245/4

Page 246: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0171 - GasWellhead MEPA-WH-0170

Description:MEPA-HY-0171ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:122921959

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:122921959

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 246/4

Page 247: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0181 - GasWellhead MEPA-WH-0180

Description:MEPA-HY-0181ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:475990758

Service: For MEPA-HCV-0181 - Gas WellheadMEPA-WH-0180

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:475990758

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 247/4

Page 248: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0181 - GasWellhead MEPA-WH-0180

Description:MEPA-HY-0181ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:123675623

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:123675623

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 248/4

Page 249: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0191 - GasWellhead MEPA-WH-0190

Description:MEPA-HY-0191ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:475695846

Service: For MEPA-HCV-0191 - Gas WellheadMEPA-WH-0190

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:475695846

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 249/4

Page 250: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0191 - GasWellhead MEPA-WH-0190

Description:MEPA-HY-0191ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:123380711

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:123380711

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 250/4

Page 251: checksheet

Area:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0201 - GasWellhead MEPA-WH-0200

Description:MEPA-HY-0201ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:477579970

Service: For MEPA-HCV-0201 - Gas WellheadMEPA-WH-0200

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:477579970

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 251/4

Page 252: checksheet

Area:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0201 - GasWellhead MEPA-WH-0200

Description:MEPA-HY-0201ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:125264835

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:125264835

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 252/4

Page 253: checksheet

Area:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0211 - GasWellhead MEPA-WH-0210

Description:MEPA-HY-0211ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:478137026

Service: For MEPA-HCV-0211 - Gas WellheadMEPA-WH-0210

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:478137026

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 253/4

Page 254: checksheet

Area:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0211 - GasWellhead MEPA-WH-0210

Description:MEPA-HY-0211ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:125821891

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:125821891

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 254/4

Page 255: checksheet

Area:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0221 - GasWellhead MEPA-WH-0220

Description:MEPA-HY-0221ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:477842114

Service: For MEPA-HCV-0221 - Gas WellheadMEPA-WH-0220

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:477842114

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 255/4

Page 256: checksheet

Area:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

I/P POSITIONER - For MEPA-HCV-0221 - GasWellhead MEPA-WH-0220

Description:MEPA-HY-0221ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:125526979

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:125526979

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 256/4

Page 257: checksheet

Area:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

LEVEL TRANSMITTER - OHD Caisson, A-6510 LevelDescription:MEPA-LT-6510ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1849458024

Service: OHD Caisson, A-6510 Level

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1849458024

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 257/4

Page 258: checksheet

Area:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

LEVEL TRANSMITTER - OHD Caisson, A-6510 LevelDescription:MEPA-LT-6510ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1698444904

Service: OHD Caisson, A-6510 Level

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1698444904

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 258/4

Page 259: checksheet

Area:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

LEVEL TRANSMITTER - OHD Caisson, A-6510 LevelDescription:MEPA-LT-6510ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-2117869415

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-2117869415

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 259/4

Page 260: checksheet

Area:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

LEVEL TRANSMITTER - OHD Caisson, A-6510 LevelDescription:MEPA-LT-6510ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1849439848

Service: OHD Caisson, A-6510 Level

SerialNo:Model/Type:Manufacturer:

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1849439848

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 260/4

Page 261: checksheet

Area:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

LEVEL TRANSMITTER - OHD Caisson, A-6510 LevelDescription:MEPA-LT-6510ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1849435240

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1849435240

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 261/4

Page 262: checksheet

Cellar DeckArea:42A01Package:

42A - A-4200 PRODUCED WATERSub System:42 - PRODUCED WATER TREATMENTSystem:

LEVEL TRANSMITTER - Degassing Vessel, V-4220Level Trip

Description:MEPA-LZT-4222ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-950454217

Service: Degassing Vessel, V-4220 Level Trip

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-950454217

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 262/4

Page 263: checksheet

Sub-Cellar DeckArea:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

SERVICE WATER PUMPDescription:MEPA-P-5110ObjectID:

Inspection Test ReportM05A Submersible Pump

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-991462951

Type: Motor TagSerialNo: 110600613Manufacturer: FLOWSERVE

Confirm external lubrication system installed correctly and filled (if fitted)14

Check motor cable is secure and undamaged.13

Check Hypochlorite dosing pipework is complete (if fitted)12

Check headroom for spool removal is sufficient.11

Check delivery head flange to caisson is secure.10

Check spider restraints are correct to drawing.09

Check riser spool stud bolts are to spec. and all fitted.08

Check riser spool gaskets are to spec. and all fitted.07

Check riser spool faces are undamaged and square.06

Check and record number of riser spools.05

Confirm suction strainer/mesh fitted. *W*04

Motor/pump assembly correct. *W*03

Check equipment is installed to manufacturer's instructions.02

Nameplate details are in accordance with data sheet.01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points______________________________________________________________________________________________________________________Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-991462951

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 263/4

Page 264: checksheet

Sub-Cellar DeckArea:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

SERVICE WATER PUMPDescription:MEPA-P-5110ObjectID:

Function Test ReportM04B Pumps

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1156020702

SerialNo: 110600613Model:Manufacturer: FLOWSERVE

Ensure motor direction is correct and clearly marked, and matches direction of rotation ofpump *W*

13

Cooling system complete.12

Hypochlorite dosing lines complete, (if fitted)11

Pump discharge is protected against over pressure.10

Air release valve fitted correctly09

All guards are fitted and secure.08

Coupling spacer is fitted.07

Check pump discharge is protected against over pressurisation.06

Check Lube/Seal oil systems for leaks.05

Lube/Seal oil systems filled with the correct grade of lubricant to full level. *W*04

Lube/Seal oil systems flushing complete.03

Preservation removed.02

Construction check list completed and no subsequent damage occurred.01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points______________________________________________________________________________________________________________________Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1156020702

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 264/4

Page 265: checksheet

Cellar DeckArea:62D14Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0110 Casing Blowdown

Description:MEPA-PG-6215ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-761019664

Service: Gas Wellhead MEPA-WH-0110 CasingBlowdown

SerialNo:Model/Type: BDT 21/AManufacturer: BADOTHERM

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-761019664

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 265/4

Page 266: checksheet

Cellar DeckArea:62D14Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0110 Casing Blowdown

Description:MEPA-PG-6215ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-761016080

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-761016080

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 266/4

Page 267: checksheet

Area:62D15Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0120 Casing Blowdown

Description:MEPA-PG-6225ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-760804880

Service: Gas Wellhead MEPA-WH-0120 CasingBlowdown

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-760804880

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 267/4

Page 268: checksheet

Area:62D15Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0120 Casing Blowdown

Description:MEPA-PG-6225ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-760790288

Service: Gas Wellhead MEPA-WH-0120 CasingBlowdown

SerialNo:Model/Type:Manufacturer:

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-760790288

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 268/4

Page 269: checksheet

Area:62D15Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0120 Casing Blowdown

Description:MEPA-PG-6225ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-760786704

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-760786704

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 269/4

Page 270: checksheet

Cellar DeckArea:62D16Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0130 Casing Blowdown

Description:MEPA-PG-6235ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-759561488

Service: Gas Wellhead MEPA-WH-0130 CasingBlowdown

SerialNo:Model/Type: ASI 316Manufacturer: BADOTHERM

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-759561488

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 270/4

Page 271: checksheet

Cellar DeckArea:62D16Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0130 Casing Blowdown

Description:MEPA-PG-6235ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-759557904

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-759557904

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 271/4

Page 272: checksheet

Cellar DeckArea:62D17Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0140 Casing Blowdown

Description:MEPA-PG-6245ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-759332112

Service: Gas Wellhead MEPA-WH-0140 CasingBlowdown

SerialNo:Model/Type: ASI 316Manufacturer: BADOTHERM

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-759332112

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 272/4

Page 273: checksheet

Cellar DeckArea:62D17Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0140 Casing Blowdown

Description:MEPA-PG-6245ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-759328528

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-759328528

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 273/4

Page 274: checksheet

Cellar DeckArea:62D18Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0150 Casing Blowdown

Description:MEPA-PG-6255ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-760151312

Service: Gas Wellhead MEPA-WH-0150 CasingBlowdown

SerialNo:Model/Type: BDT21/AManufacturer: BADOTHERM

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-760151312

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 274/4

Page 275: checksheet

Cellar DeckArea:62D18Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0150 Casing Blowdown

Description:MEPA-PG-6255ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-760147728

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-760147728

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 275/4

Page 276: checksheet

Cellar DeckArea:62D19Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0160 Casing Blowdown

Description:MEPA-PG-6265ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-759905552

Service: Gas Wellhead MEPA-WH-0160 CasingBlowdown

SerialNo:Model/Type: ASI 316Manufacturer: BADOTHERM

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-759905552

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 276/4

Page 277: checksheet

Cellar DeckArea:62D19Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0160 Casing Blowdown

Description:MEPA-PG-6265ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-759901968

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-759901968

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 277/4

Page 278: checksheet

Cellar DeckArea:62D20Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0170 Casing Blowdown

Description:MEPA-PG-6275ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-762346768

Service: Gas Wellhead MEPA-WH-0170 CasingBlowdown

SerialNo:Model/Type: BDT21/AManufacturer: BADOTHERM

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-762346768

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 278/4

Page 279: checksheet

Cellar DeckArea:62D20Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0170 Casing Blowdown

Description:MEPA-PG-6275ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-762343184

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-762343184

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 279/4

Page 280: checksheet

Cellar DeckArea:62D22Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0190 Casing Blowdown

Description:MEPA-PG-6295ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-762936592

Service: Gas Wellhead MEPA-WH-0190 CasingBlowdown

SerialNo:Model/Type: BDT21/AManufacturer: BADOTHERM

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-762936592

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 280/4

Page 281: checksheet

Cellar DeckArea:62D22Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0190 Casing Blowdown

Description:MEPA-PG-6295ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-762933008

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-762933008

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 281/4

Page 282: checksheet

Area:62D23Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGEDescription:MEPA-PG-6305ObjectID:

Inspection Test ReportI05A Instrument Calibration Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-760542950

Service: Gas Wellhead MEPA-WH-0200 CasingBlowdown

SerialNo:Model/Type:Manufacturer:

Valve Stroke Time in accordance with data sheet06

Miscellaneous equipment operating correctly05

I/P & Positioner operating correctly04

Solenoid Valve operating correctly03

Position transmitter/switches (open/closed) operating correctly.02

Calibrate Instrument as per Data Sheet (refer to table1)01

Output /RemarksPLOKNADescriptionItem

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-760542950

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 282/4

Page 283: checksheet

Area:62D23Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGEDescription:MEPA-PG-6305ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-760528358

Service: Gas Wellhead MEPA-WH-0200 CasingBlowdown

SerialNo:Model/Type:Manufacturer:

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-760528358

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 283/4

Page 284: checksheet

Area:62D23Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGEDescription:MEPA-PG-6305ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-760524774

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-760524774

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 284/4

Page 285: checksheet

Cellar DeckArea:62D21Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0180 Casing Blowdown

Description:MEPA-PG-6285ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-763165968

Service: Gas Wellhead MEPA-WH-0180 CasingBlowdown

SerialNo:Model/Type: BDT 21/AManufacturer: BADOTHERM

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-763165968

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 285/4

Page 286: checksheet

Cellar DeckArea:62D21Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGE - Gas Wellhead MEPA-WH-0180 Casing Blowdown

Description:MEPA-PG-6285ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-763162384

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-763162384

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 286/4

Page 287: checksheet

Cellar DeckArea:62D24Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGEDescription:MEPA-PG-6315ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-761019878

Service: Gas Wellhead MEPA-WH-0210 CasingBlowdown

SerialNo:Model/Type: BDT21/AManufacturer: BADOTHERM

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-761019878

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 287/4

Page 288: checksheet

Cellar DeckArea:62D24Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGEDescription:MEPA-PG-6315ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-761016294

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-761016294

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 288/4

Page 289: checksheet

Cellar DeckArea:62D25Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGEDescription:MEPA-PG-6325ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-760790502

Service: Gas Wellhead MEPA-WH-0220 CasingBlowdown

SerialNo:Model/Type: BDT21/AManufacturer: BADOTHERM

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-760790502

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 289/4

Page 290: checksheet

Cellar DeckArea:62D25Package:

62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:

PRESSURE GAUGEDescription:MEPA-PG-6325ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-760786918

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-760786918

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 290/4

Page 291: checksheet

Area:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

Motor - Service Water Pump MotorDescription:MEPA-PM-5110ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-2104628081

SerialNo:Model/Type:Manufacturer:

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-2104628081

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 291/4

Page 292: checksheet

Area:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

Motor - Service Water Pump MotorDescription:MEPA-PM-5110ObjectID:

Inspection Test ReportE08A Electric Motor

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1836196210

SerialNo:Model/Type:Manufacturer:

Where applicable visually inspect and confirm no damage to local devices:i.e. Temperature indicators/detectors and Vibration switches

17

Reconnect motor power and heater cables as per connection diagram16

Disconnect heater cable test and record insulation resistance valueHeater voltage Test voltage<=240V 500V

Values: Element to earth:__________ ohm

15

Disconnect motor cables test and record insulation resistance valueMotor voltage Test voltage<=1Kv 500VValues:L1-E:__________ohm L2-E:__________ohm L3-E:__________ohmFor motors >= 1kV See Vendor Recommendations

14

Check paintwork is complete13

Check bolts are of correct type and that no bolts are missing12

Confirm all guards and covers are installed11

Confirm equipment mountings are secure and grouting is complete10

Check unused cable entries have been plugged correctly09

For motors >= 5.5 kW check anti-condensate heater, confirm element voltage rating iscorrect, i.e.240V

08

Verify terminal box gasket and seals are present and have been installed correctly07

Check all cable connections/glands are tight and cables are identified06

Confirm motor shaft rotates freely05

Motor and control station are earthed according to drawings04

Confirm all equipment is tagged in accordance with specification03

Installation conforms to hazardous area classification02

Installation as per AFC Drawing and data sheet01

Output /RemarksPLOKNADescriptionItem

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1836196210

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 292/4

Page 293: checksheet

Notes:

1. All switching and testing of equipment is to be carried out in accordance with the BDEWC / Client electrical safety rules and operating procedures

2. All relevant ITR’s and FTR’s to be complete prior to commissioning3. All test durations and acceptable values to be as per vendor recommendations4. All directly connected motors to be commissioned in conjunction with vendor

Area:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

Motor - Service Water Pump MotorDescription:MEPA-PM-5110ObjectID:

Function Test ReportE08B Electric Motor

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1718755698

Manufacturer:

For motorised valves confirm operation of limit switches and indicators17

In conjunction with mechanical and process run motor "on load" and record line amps(refer to Table 2)L1: ______ A L2: ______ A L3: ______ A

16

Mechanicals to reinstate motor and driven device coupling (M06B item 14)15

Uncoupled Motor RunNoise checks, shall be checked at a height if 1mtr above ground level and at both 3 mtrsand 6 mtrs from the drive, in accordance with relevant standards and codes or practice.

Perform no load run and record line amps (refer to Table 1)L1: ______ A L2: ______ A L3: ______ A

13

"Bump" motor and confirm correct direction of rotation, if a direction change is requiredthis is to be affected where practical within the motor terminal box

12

Confirm functionality of local controls and emergency stop11

Remove isolation from motor feeder10

If applicable test RTD's and vibration switches09

Confirm motor is uncoupled from driven device and reinstate motor guard08

Confirm anti condensate heater is functioning07

Reconnect power and heater cables as per connection diagram, for HV motors ensuretorque settings are as per vendor requirements

06

Disconnect heater cable, test and record insulation resistance value

Heater voltage Test voltage<=240V 500VElement to earth: ___________(ohm)

05

Measure resistance between phasesL1-L2: ______(ohm) L1-L3: ______(ohm) L2-L3: ______(ohm)04

Check cable is at zero potential, disconnect motor cables, test and record motorinsulation resistance value

Motor voltage Test voltage<=1kV 500V

Record values:L1-E: ______(ohm) L2-E: ______(ohm) L3-E: ______(ohm)

For motors > 1kV See Vendor Recommendations

03

Confirm motor feeder cubicle is isolated and locked out02

Erect safety barriers and warning signs in and around test areas01

Output /RemarksPLOKNADescriptionItem

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1718755698

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 293/4

Page 294: checksheet

Area:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

Motor - Service Water Pump MotorDescription:MEPA-PM-5110ObjectID:

Function Test ReportE08B Electric Motor

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1718755698

Table 1 - Uncoupled Motor Run

Table 2 - Coupled Motor Run

______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1718755698

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 294/4

Page 295: checksheet

Cellar DeckArea:01B02Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0111 Open/ClosedStatus

Description:MEPA-PSL-0111ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1994257559

Service: SCSSV-0111 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1994257559

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 295/4

Page 296: checksheet

Cellar DeckArea:01B02Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0112 Open/ClosedStatus

Description:MEPA-PSL-0112ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1996092567

Service: SSV-0112 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1996092567

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 296/4

Page 297: checksheet

Cellar DeckArea:01B02Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0113 Open/ClosedStatus

Description:MEPA-PSL-0113ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1981019287

Service: WV-0113 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1981019287

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 297/4

Page 298: checksheet

Cellar DeckArea:01C02Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0121 Open/ClosedStatus

Description:MEPA-PSL-0121ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1994257847

Service: SCSSV-0121 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1994257847

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 298/4

Page 299: checksheet

Cellar DeckArea:01C02Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0122 Open/ClosedStatus

Description:MEPA-PSL-0122ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1996092855

Service: SSV-0122 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1996092855

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 299/4

Page 300: checksheet

Cellar DeckArea:01C02Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0123 Open/ClosedStatus

Description:MEPA-PSL-0123ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1981019575

Service: WV-0123 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1981019575

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 300/4

Page 301: checksheet

Cellar DeckArea:01D02Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0131 Open/ClosedStatus

Description:MEPA-PSL-0131ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1994257127

Service: SCSSV-0131 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1994257127

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 301/4

Page 302: checksheet

Cellar DeckArea:01D02Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0132 Open/ClosedStatus

Description:MEPA-PSL-0132ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1996092135

Service: SSV-0132 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1996092135

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 302/4

Page 303: checksheet

Cellar DeckArea:01D02Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0133 Open/ClosedStatus

Description:MEPA-PSL-0133ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1981018855

Service: WV-0133 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1981018855

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 303/4

Page 304: checksheet

Cellar DeckArea:01E02Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0141 Open/ClosedStatus

Description:MEPA-PSL-0141ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1994257159

Service: SCSSV-0141 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1994257159

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 304/4

Page 305: checksheet

Cellar DeckArea:01E02Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0142 Open/ClosedStatus

Description:MEPA-PSL-0142ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1996092167

Service: SSV-0142 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1996092167

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 305/4

Page 306: checksheet

Cellar DeckArea:01E02Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0143 Open/ClosedStatus

Description:MEPA-PSL-0143ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1981018887

Service: WV-0143 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1981018887

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 306/4

Page 307: checksheet

Cellar DeckArea:01F02Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0151 Open/ClosedStatus

Description:MEPA-PSL-0151ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1994256423

Service: SCSSV-0151 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1994256423

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 307/4

Page 308: checksheet

Cellar DeckArea:01F02Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0152 Open/ClosedStatus

Description:MEPA-PSL-0152ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1996091431

Service: SSV-0152 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1996091431

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 308/4

Page 309: checksheet

Cellar DeckArea:01F02Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0153 Open/ClosedStatus

Description:MEPA-PSL-0153ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1981018151

Service: WV-0153 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1981018151

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 309/4

Page 310: checksheet

Cellar DeckArea:01G02Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0161 Open/ClosedStatus

Description:MEPA-PSL-0161ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1994256727

Service: SCSSV-0161 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1994256727

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 310/4

Page 311: checksheet

Cellar DeckArea:01G02Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0162 Open/ClosedStatus

Description:MEPA-PSL-0162ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1996091735

Service: SSV-0162 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1996091735

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 311/4

Page 312: checksheet

Cellar DeckArea:01G02Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0163 Open/ClosedStatus

Description:MEPA-PSL-0163ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1981018455

Service: WV-0163 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1981018455

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 312/4

Page 313: checksheet

Cellar DeckArea:01H02Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0171 Open/ClosedStatus

Description:MEPA-PSL-0171ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1994260359

Service: SCSSV-0171 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1994260359

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 313/4

Page 314: checksheet

Cellar DeckArea:01H02Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0172 Open/ClosedStatus

Description:MEPA-PSL-0172ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1996095367

Service: SSV-0172 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1996095367

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 314/4

Page 315: checksheet

Cellar DeckArea:01H02Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0173 Open/ClosedStatus

Description:MEPA-PSL-0173ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1981022087

Service: WV-0173 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1981022087

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 315/4

Page 316: checksheet

Cellar DeckArea:01I02Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0181 Open/ClosedStatus

Description:MEPA-PSL-0181ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1994259623

Service: SCSSV-0181 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1994259623

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 316/4

Page 317: checksheet

Cellar DeckArea:01I02Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0182 Open/ClosedStatus

Description:MEPA-PSL-0182ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1996094631

Service: SSV-0182 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1996094631

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 317/4

Page 318: checksheet

Cellar DeckArea:01I02Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0183 Open/ClosedStatus

Description:MEPA-PSL-0183ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1981021351

Service: WV-0183 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1981021351

Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 318/4

Page 319: checksheet

Cellar DeckArea:01J02Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0191 Open/ClosedStatus

Description:MEPA-PSL-0191ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1994259911

Service: SCSSV-0191 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1994259911

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 319/4

Page 320: checksheet

Cellar DeckArea:01J02Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0192 Open/ClosedStatus

Description:MEPA-PSL-0192ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1996094919

Service: SSV-0192 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1996094919

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 320/4

Page 321: checksheet

Cellar DeckArea:01J02Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0193 Open/ClosedStatus

Description:MEPA-PSL-0193ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1981021639

Service: WV-0193 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1981021639

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 321/4

Page 322: checksheet

Cellar DeckArea:01K02Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0201 Open/ClosedStatus

Description:MEPA-PSL-0201ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2013132471

Service: SCSSV-0201 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:2013132471

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 322/4

Page 323: checksheet

Cellar DeckArea:01K02Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0202 Open/ClosedStatus

Description:MEPA-PSL-0202ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2010773175

Service: SSV-0202 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:2010773175

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 323/4

Page 324: checksheet

Cellar DeckArea:01K02Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0203 Open/ClosedStatus

Description:MEPA-PSL-0203ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1999894199

Service: WV-0203 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1999894199

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 324/4

Page 325: checksheet

Cellar DeckArea:01L02Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0211 Open/ClosedStatus

Description:MEPA-PSL-0211ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2013131927

Service: SCSSV-0211 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:2013131927

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 325/4

Page 326: checksheet

Cellar DeckArea:01L02Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0212 Open/ClosedStatus

Description:MEPA-PSL-0212ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2010772631

Service: SSV-0212 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:2010772631

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 326/4

Page 327: checksheet

Cellar DeckArea:01L02Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0213 Open/ClosedStatus

Description:MEPA-PSL-0213ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1999893655

Service: WV-0213 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1999893655

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 327/4

Page 328: checksheet

Cellar DeckArea:01M02Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SCSSV-0221 Open/ClosedStatus

Description:MEPA-PSL-0221ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2013132215

Service: SCSSV-0221 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:2013132215

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 328/4

Page 329: checksheet

Cellar DeckArea:01M02Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - SSV-0222 status Open/CloseStatus

Description:MEPA-PSL-0222ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2010772919

Service: SSV-0222 status Open/Close Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:2010772919

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 329/4

Page 330: checksheet

Cellar DeckArea:01M02Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE SWITCH - WV-0223 Open/ClosedStatus

Description:MEPA-PSL-0223ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1999893943

Service: WV-0223 Open/Closed Status

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1999893943

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 330/4

Page 331: checksheet

CELLAR DECKArea:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0111)

Description:MEPA-PT-0114ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1499449624

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0111)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1499449624

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 331/4

Page 332: checksheet

CELLAR DECKArea:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0111)

Description:MEPA-PT-0114ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1113579545

SerialNo: 91H913547Model/Type: EJX530AManufacturer: YOKOGAWA

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1113579545

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 332/4

Page 333: checksheet

CELLAR DECKArea:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0111)

Description:MEPA-PT-0114ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1382009112

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0111)

SerialNo: 91H913547Model/Type: EJX530AManufacturer: YOKOGAWA

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1382009112

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 333/4

Page 334: checksheet

CELLAR DECKArea:01B03Package:

01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0111)

Description:MEPA-PT-0114ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1382013720

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1382013720

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 334/4

Page 335: checksheet

CELLAR DECKArea:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0121)

Description:MEPA-PT-0124ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1499154712

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0121)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1499154712

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 335/4

Page 336: checksheet

CELLAR DECKArea:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0121)

Description:MEPA-PT-0124ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1113284633

SerialNo: 11294827Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1113284633

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 336/4

Page 337: checksheet

CELLAR DECKArea:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0121)

Description:MEPA-PT-0124ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1381714200

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0121)

SerialNo: 11294827Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1381714200

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 337/4

Page 338: checksheet

CELLAR DECKArea:01C03Package:

01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0121)

Description:MEPA-PT-0124ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1381718808

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1381718808

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 338/4

Page 339: checksheet

CELLAR DECKArea:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0131)

Description:MEPA-PT-0134ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1497762072

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0131)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1497762072

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 339/4

Page 340: checksheet

CELLAR DECKArea:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0131)

Description:MEPA-PT-0134ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1111891993

SerialNo: 91H913549Model/Type: EJX530AManufacturer: YOKOGAWA

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1111891993

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 340/4

Page 341: checksheet

CELLAR DECKArea:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0131)

Description:MEPA-PT-0134ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1380321560

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0131)

SerialNo: 91H913549Model/Type: EJX530AManufacturer: YOKOGAWA

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1380321560

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 341/4

Page 342: checksheet

CELLAR DECKArea:01D03Package:

01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0131)

Description:MEPA-PT-0134ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1380326168

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1380326168

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 342/4

Page 343: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0141)

Description:MEPA-PT-0144ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1497467160

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0141)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1497467160

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 343/4

Page 344: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0141)

Description:MEPA-PT-0144ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1111597081

SerialNo: 91L 911840-139Model/Type: EJA 530 AManufacturer: YOKOGAWA

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1111597081

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 344/4

Page 345: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0141)

Description:MEPA-PT-0144ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1380026648

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0141)

SerialNo: 91L 911840-139Model/Type: EJA 530 AManufacturer: YOKOGAWA

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1380026648

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 345/4

Page 346: checksheet

Area:01E03Package:

01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0141)

Description:MEPA-PT-0144ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1380031256

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1380031256

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 346/4

Page 347: checksheet

Cellar DeckArea:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0151)

Description:MEPA-PT-0154ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1498220824

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0151)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1498220824

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 347/4

Page 348: checksheet

Cellar DeckArea:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0151)

Description:MEPA-PT-0154ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1112350745

SerialNo:Model/Type: EJA 530 AManufacturer: YKOGAWA

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1112350745

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 348/4

Page 349: checksheet

Cellar DeckArea:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0151)

Description:MEPA-PT-0154ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1380780312

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0151)

SerialNo:Model/Type: EJA 530 AManufacturer: YKOGAWA

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1380780312

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 349/4

Page 350: checksheet

Cellar DeckArea:01F03Package:

01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0151)

Description:MEPA-PT-0154ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1380784920

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1380784920

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 350/4

Page 351: checksheet

Cellar DeckArea:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0161)

Description:MEPA-PT-0164ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1497942296

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0161)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1497942296

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 351/4

Page 352: checksheet

Cellar DeckArea:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0161)

Description:MEPA-PT-0164ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1112072217

SerialNo: 91L911 841-139Model/Type: EJA 530 AManufacturer: YOKOGAWA

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1112072217

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 352/4

Page 353: checksheet

Cellar DeckArea:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0161)

Description:MEPA-PT-0164ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1380501784

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0161)

SerialNo: 91L911 841-139Model/Type: EJA 530 AManufacturer: YOKOGAWA

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1380501784

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 353/4

Page 354: checksheet

Cellar DeckArea:01G03Package:

01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0161)

Description:MEPA-PT-0164ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1380506392

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1380506392

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 354/4

Page 355: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0171)

Description:MEPA-PT-0174ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1500743960

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0171)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1500743960

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 355/4

Page 356: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0171)

Description:MEPA-PT-0174ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1114873881

SerialNo: 91L911838 138Model/Type: EJA 530AManufacturer: YOKOGAWA

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1114873881

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 356/4

Page 357: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0171)

Description:MEPA-PT-0174ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1383303448

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0171)

SerialNo: 91L911838 138Model/Type: EJA 530AManufacturer: YOKOGAWA

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1383303448

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 357/4

Page 358: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0171)

Description:MEPA-PT-0174ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1383308056

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1383308056

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 358/4

Page 359: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0181)

Description:MEPA-PT-0184ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1501497624

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0181)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1501497624

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 359/4

Page 360: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0181)

Description:MEPA-PT-0184ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1115627545

SerialNo:Model/Type: EJA 530 AManufacturer: YOKOGAWA

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1115627545

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 360/4

Page 361: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0181)

Description:MEPA-PT-0184ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1384057112

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0181)

SerialNo:Model/Type: EJA 530 AManufacturer: YOKOGAWA

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1384057112

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 361/4

Page 362: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0181)

Description:MEPA-PT-0184ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1384061720

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1384061720

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 362/4

Page 363: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0191)

Description:MEPA-PT-0194ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1501202712

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0191)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1501202712

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 363/4

Page 364: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0191)

Description:MEPA-PT-0194ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1115332633

SerialNo: 91L911839-138Model/Type: EJA 530AManufacturer: YOKOGAWA

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1115332633

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 364/4

Page 365: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0191)

Description:MEPA-PT-0194ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1383762200

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0191)

SerialNo: 91L911839-138Model/Type: EJA 530AManufacturer: YOKOGAWA

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1383762200

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 365/4

Page 366: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0191)

Description:MEPA-PT-0194ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1383766808

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1383766808

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 366/4

Page 367: checksheet

CELLAR DECKArea:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0201)

Description:MEPA-PT-0204ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1498892604

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0201)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1498892604

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 367/4

Page 368: checksheet

CELLAR DECKArea:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0201)

Description:MEPA-PT-0204ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1113022525

SerialNo: 11294828Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1113022525

Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 368/4

Page 369: checksheet

CELLAR DECKArea:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0201)

Description:MEPA-PT-0204ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1381452092

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0201)

SerialNo: 11294828Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1381452092

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 369/4

Page 370: checksheet

CELLAR DECKArea:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0201)

Description:MEPA-PT-0204ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1381456700

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1381456700

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 370/4

Page 371: checksheet

CELLAR DECKArea:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0211)

Description:MEPA-PT-0214ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1499449660

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0211)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1499449660

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 371/4

Page 372: checksheet

CELLAR DECKArea:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0211)

Description:MEPA-PT-0214ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1113579581

SerialNo: 11294829Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1113579581

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 372/4

Page 373: checksheet

CELLAR DECKArea:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0211)

Description:MEPA-PT-0214ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1382009148

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0211)

SerialNo: 11294829Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1382009148

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 373/4

Page 374: checksheet

CELLAR DECKArea:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0211)

Description:MEPA-PT-0214ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1382013756

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1382013756

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 374/4

Page 375: checksheet

CELLAR DECKArea:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0221)

Description:MEPA-PT-0224ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1499154748

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0221)

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1499154748

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 375/4

Page 376: checksheet

CELLAR DECKArea:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0221)

Description:MEPA-PT-0224ObjectID:

Inspection Test ReportE17A Certified Equipment

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1113284669

SerialNo: 11294830Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO

Equipment Certification No:_____________________________13

Ensure all electrical connections are tight12

Check earthing conforms to design requirement11

Clean all blind holes of dirt and grease prior to assembly.10

Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09

Ensure no build up of dirt or corrosion on flame paths.08

Apparatus is not damaged and has no unauthorised modifications.07

Apparatus is clean and corrosion free.06

Enclosure has manufacturer's data identification label attached.05

Enclosure has Certifying Authority label attached.04

Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification

03

Check equipment is as per data sheet02

Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification

01

Output /RemarksPLOKNADescriptionItem

Notes:

1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________

Remarks:

___________________________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1113284669

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 376/4

Page 377: checksheet

CELLAR DECKArea:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0221)

Description:MEPA-PT-0224ObjectID:

Inspection Test ReportI01A Inst Inspection

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1381714236

Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0221)

SerialNo: 11294830Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO

Equipment Certification No.:____________________________09

Hydraulic connections correct.08

Pneumatic connections correct.07

Electrical connections correct.06

Process connections correct.05

Instrument is not damaged.04

All materials are correct.03

Data plate details correct02

Instrument is checked correct against current revision of data sheet.01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1381714236

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 377/4

Page 378: checksheet

CELLAR DECKArea:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0221)

Description:MEPA-PT-0224ObjectID:

Inspection Test ReportI02A Inst Installation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1381718844

03.05 - Confirm all impulse lines have been drained and cleaned

03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.

03.03 - Confirm the following lines have been blown clear:

Pneumatic Lines Test Gas Lines

03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:

Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines

03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.

Instrument Line Pressure and Leak Test *W*03

02.11 - Labelling correct.

02.10 - Check all Tag No's.

02.09 - EOL resistor fitted and correctly rated where applicable.

02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.

02.07 - Instrument earthed in accordance with project specification.

02.06 - Spare entries plugged correctly.

02.05 - In-Line equipment installed and supported correctly.

02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.

02.03 - Vent lines are directed into a safe area.

02.02 - Instrument is accessible for maintenance and clear of obstructions.

02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.

InspectionThe following checks are to be performed.

02

01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.

Data01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points

____________________________________________________________________________________________________________________________________

Remarks:

____________________________________________________________________________________________________________________________________

Test Equipment

Code Description

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1381718844

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 378/4

Page 379: checksheet

Mezzanine DeckArea:04A01Package:

04A - PRODUCTION HEADERSub System:04 - MANIFOLDSSystem:

PRODUCTION Header Manifold (sand detector)Description:MEPA-QT-0401ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:371673588

Service: Production Header Manifold ToProduction Cooler

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:371673588

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 379/4

Page 380: checksheet

Mezzanine DeckArea:04B01Package:

04B - TEST HEADERSub System:04 - MANIFOLDSSystem:

SAND DETECTOR - Test Header ManifoldDescription:MEPA-QT-0402ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1775810064

Service: Test Header Manifold To TestSeparator

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1775810064

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 380/4

Page 381: checksheet

Area:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

Field Control Unit - Service Water PumpDescription:MEPA-RCU-PM-5110ObjectID:

Function Test ReportE05B Distribution Board, Junction Box & ControlStation

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-167979851

SingleLineDwg:Manufacturer:

Lock out equipment07

For lighting and small power distribution boards check balance of phases is as per singleline diagramRecord full load current readings:Red Ø: AmpsYellow Ø: AmpsBlue Ø: Amps

06

Energise Distribution Board confirm and record voltage:L1 - L2 L1 - L3 L2 - L3L1 - N L2 - N L3 - N

05

Using a 1000V Megger perform IR Test on Distribution BoardL1 - E _________Mohm L2 - E _________Mohm L3 - E _________MohmL1 - L2_________Mohm L1 - L3_________Mohm L2 - L3_________MohmL1 - N _________Mohm L2 - N _________Mohm L3 - N _________Mohm

04

For local control stations confirm switching in conjunction with motor run test03

Check busbars are at zero potential and main isolator and all MCB's are open02

Check ratings of MCB's and main isolator are as per AFC Drawing01

Output /RemarksPLOKNADescriptionItem

Notes.1. All switching and testing of equipment is to be carried out in accordance with the BDEWC / Client electrical safety rules and operating

procedures

All relevant ITR’s and FTR’s to be complete prior to commissioning

______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-167979851

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 381/4

Page 382: checksheet

Area:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

Switchboard Cubicle - Service Water PumpDescription:MEPA-SB-7700-L5BObjectID:

Function Test ReportE22B Motor Starter Contactor

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-964814696

SingleLineDwg:Manufacturer:

Motor to be run and tested in accordance with FTR EO8B08

Equipment is ready for service07

Check voltage and phase rotation is correct06

05.05 - Anti condensate heater

05.04 - Operation of local and field controls, stop start station

05.03 - Manual and automatic closing

05.02 - Indication lights and Ammeter

05.01 - Trips and alarms

Prove auxiliary circuits and function of following: *W*05

Perform injection test on overload relays: *W*

Motor: _______ KW ______ Amps Set range: _______ Amps Test Current: _______ (2xlr Amps) Acceptable Curve: _______ secs Actual: _______ secsStarter Unit Function Checked: _______

04

Confirm control voltage is available and energise controls03

Place equipment in test position02

Confirm switchboard busbars are at zero potential and all switchboard feeders areisolated and locked out

01

Output /RemarksPLOKNADescriptionItem

Notes1. All switching and testing of equipment is to be carried out in accordance with the BDEWC / Client electrical safety rules and operating

procedures

2. All relevant ITR’s and FTR’s to be complete prior to energisation procedure

3. Some of the tests listed below may have been performed at the FAT and not scheduled to be re tested at the SAT, in which case a copy of the FAT tests shall be attached to this check sheet

*W* Commissioning & Client Witness points

______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-964814696

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 382/4

Page 383: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6801ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:391859120

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:391859120

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 383/4

Page 384: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6802ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1755624524

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1755624524

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 384/4

Page 385: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6803ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-681882711

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-681882711

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 385/4

Page 386: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6804ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1465600942

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1465600942

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 386/4

Page 387: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6805ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-681882718

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-681882718

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 387/4

Page 388: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6806ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:391859111

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:391859111

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 388/4

Page 389: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6807ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1465600924

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1465600924

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 389/4

Page 390: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6809ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1465600917

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1465600917

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 390/4

Page 391: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6810ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1756116040

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1756116040

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 391/4

Page 392: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6811ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:391367600

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:391367600

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 392/4

Page 393: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6812ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1756116044

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1756116044

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 393/4

Page 394: checksheet

Mezzanine DeckArea:68A02Package:

68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)

Sub System:68 - CHEMICAL INJECTIONSystem:

SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6808ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-681882736

Service: Corrossion inhibitor -Flowline

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-681882736

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 394/4

Page 395: checksheet

Sub-Cellar DeckArea:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

SERVICE WATER SUPPLY CAISSONDescription:MEPA-T-5110ObjectID:

Inspection Test ReportM01A Tank

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2003270091

SerialNo:

Upon successful completion of all steps above, close manway door with shipping gasketonly and finger tighten all bolts. New gasket must NOT be used. Seal/cover flange toprevent entry of water/dirt. *W*

30

If overflow is fitted, ensure that it is unobstructed and routed to location shown on P&ID.29

Where preservation materials are installed, equipment is marked"PRESERVATION INSIDE".

28

Ensure that preservation is correct.27

Adequate clearance exists for removal of internals.26

Check nozzle loading is not excessive.25

Confirm earth bonding completed.24

Confirm that the manway gasket/s (which must not yet be fitted) are correctly preservedand stored in the warehouse.

23

All gaskets are fitted, with the exception of the manway gasket/s.22

All gaskets are correct to specification.21

Access to valves, gauges and fittings is adequate.20

Access ladders and platforms are correctly installed.19

Manway lifting arrangements are adequate.18

Manway is accessible.17

Check coating is undamaged. *W*16

Tank is clean internally. *W*15

Internals and vessel trims are fitted as per drawing. *W*14

Vent and drain valves are fitted13

If specified on project drawings, confirm that vacuum breaker is installed and itscertification is valid

12

All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipesupports shall not be welded onto adjacent wall which may be common with tank wall.

11

All checks sheets for associated equipment such as pumps that require internal access tothe tank have been completed. e.g. inspection of pump inlet strainers.

10

All flange management tags are still intact on all vessel flanges (if specified)09

All pipes and equipment which interface with the tank have been installed, their flangeshave been torqued/tensioned.

08

All hot oil flushing and chemical cleaning of adjoining pipework has been completed07

Fittings, connections, sacrificial anodes, bird screens, etc, complete as per vendordrawings.

06

Tank is secure. All structural bolting is tight and to spec.05

Sliding feet (if any) are free to move, and are fitted with locknuts.04

Tank is installed level and as per P & IDs.03

Tank has been installed to the manufacturer's instructions.02

Nameplate details are correct in accordance with the data sheet.01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points______________________________________________________________________________________________________________________

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:2003270091

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 395/4

Page 396: checksheet

Sub-Cellar DeckArea:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

SERVICE WATER SUPPLY CAISSONDescription:MEPA-T-5110ObjectID:

Function Test ReportM01B TANK

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2003270080

SerialNo:

Torque manway flanges and confirm that torquing/tightening certification is complete*W*

16

After items 2 to 13 have been completed, close manway(s)/hatch(s) with correct gasketsand bolting. *W*

15

Confirm earth bonding completed.14

If specified on project drawings, confirm that vacuum breaker is installed and itscertification is valid

13

Remove all non soluble preservation, and ensure that soluble preservation coatings areapplied, (if specified in project Preservation Procedure).

12

Vent and drain valves fitted and exercised.11

Vessel internally clean and no internal degradation has occurred since the 'A' checkswere carried out *W*

10

Vessel externally clean and free from obstruction.09

All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipesupports shall not be welded onto adjacent wall which may be common with tank wall.

08

All checks sheets for associated equipment such as pumps that require internal access tothe tank have been completed. e.g. inspection of pump inlet strainers.

07

All hot oil flushing and chemical cleaning of adjoining pipework, (if any), has beencompleted.

06

All fittings, connections, sacrificial anodes, bird screens, spec blinds, etc, still present andin good order.

05

All flange management tags are still intact on all vessel flanges (if specified)04

All flange bolts have been torqued/tensioned/tightened.03

All pipes and equipment which interface with the vessel have been installed.02

Construction check list completed and no subsequent damage has occurred.01

Output /RemarksPLOKNADescriptionItem

Notes & Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:2003270080

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 396/4

Page 397: checksheet

Sub-Cellar DeckArea:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

OHD CAISSONDescription:MEPA-T-6510ObjectID:

Inspection Test ReportM01A Tank

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1943499339

SerialNo:

Upon successful completion of all steps above, close manway door with shipping gasketonly and finger tighten all bolts. New gasket must NOT be used. Seal/cover flange toprevent entry of water/dirt. *W*

30

If overflow is fitted, ensure that it is unobstructed and routed to location shown on P&ID.29

Where preservation materials are installed, equipment is marked"PRESERVATION INSIDE".

28

Ensure that preservation is correct.27

Adequate clearance exists for removal of internals.26

Check nozzle loading is not excessive.25

Confirm earth bonding completed.24

Confirm that the manway gasket/s (which must not yet be fitted) are correctly preservedand stored in the warehouse.

23

All gaskets are fitted, with the exception of the manway gasket/s.22

All gaskets are correct to specification.21

Access to valves, gauges and fittings is adequate.20

Access ladders and platforms are correctly installed.19

Manway lifting arrangements are adequate.18

Manway is accessible.17

Check coating is undamaged. *W*16

Tank is clean internally. *W*15

Internals and vessel trims are fitted as per drawing. *W*14

Vent and drain valves are fitted13

If specified on project drawings, confirm that vacuum breaker is installed and itscertification is valid

12

All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipesupports shall not be welded onto adjacent wall which may be common with tank wall.

11

All checks sheets for associated equipment such as pumps that require internal access tothe tank have been completed. e.g. inspection of pump inlet strainers.

10

All flange management tags are still intact on all vessel flanges (if specified)09

All pipes and equipment which interface with the tank have been installed, their flangeshave been torqued/tensioned.

08

All hot oil flushing and chemical cleaning of adjoining pipework has been completed07

Fittings, connections, sacrificial anodes, bird screens, etc, complete as per vendordrawings.

06

Tank is secure. All structural bolting is tight and to spec.05

Sliding feet (if any) are free to move, and are fitted with locknuts.04

Tank is installed level and as per P & IDs.03

Tank has been installed to the manufacturer's instructions.02

Nameplate details are correct in accordance with the data sheet.01

Output /RemarksPLOKNADescriptionItem

Notes:

*W* Commissioning & Client Witness points______________________________________________________________________________________________________________________

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1943499339

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 397/4

Page 398: checksheet

Sub-Cellar DeckArea:65A02Package:

65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:

OHD CAISSONDescription:MEPA-T-6510ObjectID:

Function Test ReportM01B TANK

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1943499328

SerialNo:

Torque manway flanges and confirm that torquing/tightening certification is complete*W*

16

After items 2 to 13 have been completed, close manway(s)/hatch(s) with correct gasketsand bolting. *W*

15

Confirm earth bonding completed.14

If specified on project drawings, confirm that vacuum breaker is installed and itscertification is valid

13

Remove all non soluble preservation, and ensure that soluble preservation coatings areapplied, (if specified in project Preservation Procedure).

12

Vent and drain valves fitted and exercised.11

Vessel internally clean and no internal degradation has occurred since the 'A' checkswere carried out *W*

10

Vessel externally clean and free from obstruction.09

All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipesupports shall not be welded onto adjacent wall which may be common with tank wall.

08

All checks sheets for associated equipment such as pumps that require internal access tothe tank have been completed. e.g. inspection of pump inlet strainers.

07

All hot oil flushing and chemical cleaning of adjoining pipework, (if any), has beencompleted.

06

All fittings, connections, sacrificial anodes, bird screens, spec blinds, etc, still present andin good order.

05

All flange management tags are still intact on all vessel flanges (if specified)04

All flange bolts have been torqued/tensioned/tightened.03

All pipes and equipment which interface with the vessel have been installed.02

Construction check list completed and no subsequent damage has occurred.01

Output /RemarksPLOKNADescriptionItem

Notes & Remarks:

*W* Commissioning & Client Witness points

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:1943499328

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 398/4

Page 399: checksheet

Main DeckArea:92D01Package:

92D - MISCELLANEOUS EQUIPMENTSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

TELECOM TOWERDescription:MEPA-TEL-TOWERObjectID:

Inspection Test ReportM21A Main Structural Completion

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:200104837

All items covered by this record undamaged and clean.17

All piping & ducting penetrations through bulkheads & decks fitted with gas tightsleeves/seals

16

All welding and NDT work completed and cleared.15

Temporary steel work to be removed at a later date, clearly marked and identified onrelevant drawings.

14

Main and Interface dimensions checked.13

Confirm that all maintenance / scaffolding lugs are installed in accordance with layoutdrawings with the correct orientation.

12

All structural supports installed in accordance with drawings and all temporary aids /brackets removed.

11

Foundations and handrails installed in accordance with specifications, ladder entranceshave safety bar complete with protected landing end and portable hand railings aresecured.

10

All foundations installed and do not create traps for water, ample drainage is available forthe area.

09

All grating installed and no gaps exist that allow the penetration of a ball bearing ofdiameter > 15 mm.

08

All penetrations installed, with sleeves/kick plates of specified size complete with drainholes as required.

07

All gulley gratings to drains installed.06

All platforms and walkways are installed in accordance with drawings, and all temporaryaids/brackets removed.

05

Roof structures are installed in accordance with drawings, and all temporary aids /brackets removed.

04

Deck structures installed in accordance with drawings, and all temporary aids / bracketsremoved.

03

Bulkheads installed in accordance with drawings, and all temporary aids / bracketsremoved.

02

Main structural members installed in accordance with drawings, and all temporary aids /brackets removed.

01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:200104837

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 399/4

Page 400: checksheet

Area:92B02Package:

92B - CCTV/LAN SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

IP TELEPHONEDescription:MEPA-TUO-9201ObjectID:

Inspection Test ReportT01A Telecoms Field Device Installation Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-235039639

Type:

Service:Serial No:Manufacturer:

Suitable grease applied to flanges (Ex-d enclosures).14

Check earthing conforms to earthing philosophy.13

Gaskets & seals fitted correctly.12

Gaskets & seals undamaged.11

Terminal box flanges undamaged.10

Spare gland entries plugged correctly.09

Paintwork correct.08

Access suitable.07

Fixings correct.06

Supports installed correctly.05

Identification correct.04

Equipment suitable for area classification.03

Item complies with Data sheet.02

Installed according to latest revision of Layout drawing.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-235039639

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 400/4

Page 401: checksheet

E&I ROOMArea:92B02Package:

92B - CCTV/LAN SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

IP TELEPHONEDescription:MEPA-TUO-9202ObjectID:

Inspection Test ReportT01A Telecoms Field Device Installation Check

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-237398935

Type:

Service:Serial No:Manufacturer:

Suitable grease applied to flanges (Ex-d enclosures).14

Check earthing conforms to earthing philosophy.13

Gaskets & seals fitted correctly.12

Gaskets & seals undamaged.11

Terminal box flanges undamaged.10

Spare gland entries plugged correctly.09

Paintwork correct.08

Access suitable.07

Fixings correct.06

Supports installed correctly.05

Identification correct.04

Equipment suitable for area classification.03

Item complies with Data sheet.02

Installed according to latest revision of Layout drawing.01

Output /RemarksPLOKNADescriptionItem

Notes and Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-237398935

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 401/4

Page 402: checksheet

Area:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

-Description:MEPA-UA-5110ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1751269186

Service: Service Water Pump P-5110 FAULTALARM

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1751269186

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 402/4

Page 403: checksheet

Area:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

-Description:MEPA-UZ-5110ObjectID:

Function Test ReportI01B Loop Test

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1751266802

Service: Trip Service Water Pump MEPA-P-5110 Fan Motor

LoopNo:LoopDwg:C&E No:

Relevant as-built mark-ups complete10

Cause & Effect Yellow Lined09

Graphic points displayed correctly08

Face Plates displayed correctly07

Function test of loop and all components in accordance with loop & data sheet(s)06

Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05

Confirm valve action correct04

Confirm valve stroke time(s) is as per data sheet03

All relevant installation checklists complete02

All relevant inspection & calibration checklists complete01

Output /RemarksPLOKNADescriptionItem

Remarks :

Valve Action = dir/rev

Alarm Point = inc/dec

Trip Point = inc/dec

Stroke Time = secs

Range(s) =

_____________________________________________________________________________________________________________________

Test Equipment :

Code Description Calibration Date

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1751266802

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 403/4

Page 404: checksheet

Area:89A03Package:

89A - MEPA NAVAIDSSub System:89 - NAVAIDSSystem:

Cable From MEPA-NCCP-8900 NAV-AIDS CENTRALCONTROL PANEL To TELECOM MAST AIRCRAFTWA

Description:PL-8900-4ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:2036215469

VoltageRating: 240VToTag: TELECOM MAST AIRCRAFTWARNING LIGHT

Size: 2Cx4mm2FromTag: MEPA-NCCP-8900 NAV-AIDSCENTRAL CONTROL PANEL

CableType: P5

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:2036215469

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 404/4

Page 405: checksheet

Area:51A01Package:

51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:

Cable From 415V SWITCHBOARD/MCC MEPA-SB-7700 To MEPA-PM-5110 SERVICE WATER PUMP

Description:PN-PM5110ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1062693670

VoltageRating: 415VToTag: MEPA-PM-5110 SERVICE WATERPUMP

Size: 3Cx4mm2FromTag: 415V SWITCHBOARD/MCC MEPA-SB-7700

CableType: P2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1062693670

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 405/4

Page 406: checksheet

Area:01H03Package:

01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-010 To MEPA-PT-0174Description:PT-0174ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1651356538

VoltageRating: -ToTag: MEPA-PT-0174

Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1651356538

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 406/4

Page 407: checksheet

Area:01I03Package:

01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-010 To MEPA-PT-0184Description:PT-0184ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1650537338

VoltageRating: -ToTag: MEPA-PT-0184

Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1650537338

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 407/4

Page 408: checksheet

Area:01J03Package:

01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-010 To MEPA-PT-0194Description:PT-0194ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1650766714

VoltageRating: -ToTag: MEPA-PT-0194

Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1650766714

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 408/4

Page 409: checksheet

Area:01K03Package:

01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-010 To MEPA-PT-0204Description:PT-0204ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1648980830

VoltageRating: -ToTag: MEPA-PT-0204

Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1648980830

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 409/4

Page 410: checksheet

Area:01L03Package:

01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-010 To MEPA-PT-0214Description:PT-0214ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1648489310

VoltageRating: -ToTag: MEPA-PT-0214

Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1648489310

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 410/4

Page 411: checksheet

Area:01M03Package:

01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE

Sub System:01 - WELLHEADS & FLOWLINESSystem:

Inst. Cable From MEPA-IJB-010 To MEPA-PT-0224Description:PT-0224ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1648718686

VoltageRating: -ToTag: MEPA-PT-0224

Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1648718686

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 411/4

Page 412: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

GORA Reinstatement Test Pack - 29Description:RTP-GORA-1ObjectID:

Function Test ReportP05B Witnessed Joint

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:898532292

Joint desciption ::Flange description/ID::PIDNo:

Attach supporting documentation for post reisnstement test to this sheet15

Post reinstatement test described in line 10 completed satisfactorily14

Circle one item from list below: - N2 Helium leak test / Service test / Nil / Soapy bubble leak test / - check with hand held gas detector after introduction of gas / - other (providedetails)………………………………………………………………………………...……..

13

Post reinstatement, the following checks will be made:12

Torquing/ tension certificate complete and flange management tag fitted (if specified inproject requirements)

11

No excessive length of stud bolt protruding through each nut.10

Minimum of one thread proud of all nuts.09

No visible damage to gasket when joint completed.08

All nuts pulled up to required tightness.07

Joint pulled up evenly on opposing stud bolts.06

Flange faces parallel.05

Nuts and stud bolts examined and seen to be undamaged and correct size and type.04

Gaskets examined and seen to be clean, damage free and the correct type and size.03

Flange faces examined and seen to be clean and damage free.02

Prior to reinstatement, the following checks will be made:01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:898532292

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 412/4

Page 413: checksheet

Area:29C01Package:

29C - MEPA GAS RECEIVING FACILITIES ATGORA

Sub System:29 - GAS IMPORT/EXPORTSystem:

GORA Reinstatement Test Pack - 29Description:RTP-GORA-1TestPack No:

Function Test ReportP04B N2 LEAK TEST

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:898544068

Recorder Serial No.:Chart Reference:

TestMedium:Design temperature:Design Pressure (MAWP):

Gauge Serial No.:Operational Flow Medium:Test temperature:

TestPressure:TestDuration:PIDNo:

CommentP&IDDescriptionLineNo

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM HV-29408 TO HV-29409100-PG-2928-C8Y-2

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM 100-PG-2928-C8Y-2 TO HV-29411100-PG-2928-C8Y-4

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM SBT-2903 TO HV-29403400-PG-2945-C8Y-1

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM 400-PG-2945-C8Y-1 TO HV-29402400-PG-2945-C8Y-2

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM SDV-2950 TO T05.EL.17000500-PG-2925-C8Y-5

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM TO T05.EL.17000500-PG-2925-C8Y-6

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM T05.EL.17000 TO HV-29404500-PG-2925-C8Y-7

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM HV-29413 TO HV-2941550-PG-2927-C1Y-1

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM 50-PG-2927-C1Y-1 TO HV-2941650-PG-2927-C1Y-2

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM 400-PG-2945-C8Y TO HV-2940050-PG-2943-C1Y-1

06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM TP-314A TO SDV-295150-PG-2954-C1Y-1

All witness joints entered into Witness Joint Register and copy attached to this sheet.02

Leak test completed and certificate attached to this sheet01

Output /RemarksPLOKNADescriptionItem

Remarks:

Type of Test: Service TestReinstatement Leak Test (N2He)(Delete as appropriate)1. Line valves confirmed half open for test (to test stem packing) . 2. Isolation valve integrity test to be conducted.

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:898544068

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28946). 413/4

Page 414: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

GORA Reinstatement Test Pack - 33Description:RTP-GORA-2ObjectID:

Function Test ReportP05B Witnessed Joint

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1248951360

Joint desciption ::Flange description/ID::PIDNo:

Attach supporting documentation for post reisnstement test to this sheet15

Post reinstatement test described in line 10 completed satisfactorily14

Circle one item from list below: - N2 Helium leak test / Service test / Nil / Soapy bubble leak test / - check with hand held gas detector after introduction of gas / - other (providedetails)………………………………………………………………………………...……..

13

Post reinstatement, the following checks will be made:12

Torquing/ tension certificate complete and flange management tag fitted (if specified inproject requirements)

11

No excessive length of stud bolt protruding through each nut.10

Minimum of one thread proud of all nuts.09

No visible damage to gasket when joint completed.08

All nuts pulled up to required tightness.07

Joint pulled up evenly on opposing stud bolts.06

Flange faces parallel.05

Nuts and stud bolts examined and seen to be undamaged and correct size and type.04

Gaskets examined and seen to be clean, damage free and the correct type and size.03

Flange faces examined and seen to be clean and damage free.02

Prior to reinstatement, the following checks will be made:01

Output /RemarksPLOKNADescriptionItem

Remarks:

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1248951360

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 414/4

Page 415: checksheet

Area:33C01Package:

33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA

Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:

GORA Reinstatement Test Pack - 33Description:RTP-GORA-2TestPack No:

Function Test ReportP04B N2 LEAK TEST

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1248939584

Recorder Serial No.:Chart Reference:

TestMedium:Design temperature:Design Pressure (MAWP):

Gauge Serial No.:Operational Flow Medium:Test temperature:

TestPressure:TestDuration:PIDNo:

CommentP&IDDescriptionLineNo

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33311 TO HV-33313100-PL-3323-C1Y-1

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33311 TO HV-33313100-PL-3323-C1Y-2

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SBT-3302 TO HV-33300150-PL-3308-C8Y-1

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM 150-PL-3308-C8Y-1 TO HV-33301150-PL-3308-C8Y-2

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM 150-PL-3308-C8Y-2 TO SOC-3304150-PL-3308-C8Y-3

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-1

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-2

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-3

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-4

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-5

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-6

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33302 TO HV-33304200-PL-3315-C8Y-7

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-3330750-PL-3322-C8Y-1

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-3330750-PL-3322-C8Y-2

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-3330750-PL-3322-C8Y-3

06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-3330750-PL-3322-C8Y-4

All witness joints entered into Witness Joint Register and copy attached to this sheet.02

Leak test completed and certificate attached to this sheet01

Output /RemarksPLOKNADescriptionItem

Remarks:

Type of Test: Service TestReinstatement Leak Test (N2He)(Delete as appropriate)1. Line valves confirmed half open for test (to test stem packing) . 2. Isolation valve integrity test to be conducted.

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QC

OE:-1248939584

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28946). 415/4

Page 416: checksheet

Area:92A02Package:

92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

Telecom CablesDescription:YAFC-0001ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:690104358

VoltageRating:ToTag: x

Size:FromTag:CableType:

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:690104358

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 416/4

Page 417: checksheet

Area:92A02Package:

92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

Telecom CablesDescription:YAFC-0002ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1457379294

VoltageRating:ToTag: x

Size:FromTag:CableType:

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1457379294

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 417/4

Page 418: checksheet

Area:92E01Package:

92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

Telecom CablesDescription:YAFC-0006ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:690104369

VoltageRating:ToTag: x

Size:FromTag:CableType:

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:690104369

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 418/4

Page 419: checksheet

Area:92E01Package:

92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

Telecom CablesDescription:YAFC-0007ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1763846154

VoltageRating:ToTag: x

Size:FromTag:CableType:

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1763846154

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 419/4

Page 420: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

Telecom CablesDescription:YDEE-0007ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:1761748666

VoltageRating:ToTag: x

Size:FromTag:CableType:

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:1761748666

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 420/4

Page 421: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

Telecom CablesDescription:YUHF-0002ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-1445829582

VoltageRating:ToTag: x

Size:FromTag:CableType:

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-1445829582

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 421/4

Page 422: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

Telecom CablesDescription:YUHF-0003ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:-372087761

VoltageRating:ToTag: x

Size:FromTag:CableType:

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:-372087761

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 422/4

Page 423: checksheet

Area:92C02Package:

92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:

Telecom CablesDescription:YVHF-0001ObjectID:

Inspection Test ReportE02A Cable < 1000 Volts

MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES

OE:701659830

VoltageRating:ToTag: x

Size:FromTag:CableType:

Replace all equipment covers, check bolts washers etc. are reinstated correctly10

Discharge all cores to ground09

Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values

08

Destination of cable and phasing confirmed by continuity test07

Cable neatly laid and strapped to rack06

Cable racks adequately supported, bonded and visibly earthed05

Cable correctly numbered, tagged at both ends and at specified intervals04

Cable glands suited to hazardous are classification03

Cable properly glanded and terminated02

Installation as per AFC Drawings and data sheets01

Output /RemarksPLOKNADescriptionItem

Notes:

Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________

Test Equipment :

Date:

Signature:

Name:

BDEWC CommissioningBDEWC QA/QCBDEWC Construction

OE:701659830

Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 423/4