checksheet
-
Upload
abdul-hakam-mohamed-yusof -
Category
Documents
-
view
47 -
download
1
description
Transcript of checksheet
Area:53A02Package:
53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:
LINES FROM 100-FW-5301-A18 to FIRE WATERRING WELLHEAD AREA
Description:100-FW-5302-SL-A18ObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1076764070
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0023
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:1076764070
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 1/423
Area:53A02Package:
53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:
LINES FROM 100-FW-5301-A18 to FIRE WATERRING WELLHEAD AREA
Description:100-FW-5302-SL-A18ObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1076786854
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1076786854
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 2/423
Area:53A02Package:
53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:
LINES FROM 100-FW-5301-A18 to FIRE WATERRING WELLHEAD AREA
Description:100-FW-5302-SL-A18ObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1345210023
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1345210023
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 3/423
Area:65C02Package:
65C - NON-HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM NON-HAZARDOUS OPEN DRAINHEADER to OHD CAISSON (T-6510)
Description:150-DN-6547-SL-A18ObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:208686117
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0016
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:208686117
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 4/423
Area:65C02Package:
65C - NON-HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM NON-HAZARDOUS OPEN DRAINHEADER to OHD CAISSON (T-6510)
Description:150-DN-6547-SL-A18ObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:208676645
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:208676645
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 5/423
Area:65C02Package:
65C - NON-HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM NON-HAZARDOUS OPEN DRAINHEADER to OHD CAISSON (T-6510)
Description:150-DN-6547-SL-A18ObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:477108004
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:477108004
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 6/423
Area:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0111 to 150-PG-0151-GIY
Description:150-PG-0101-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:913119723
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:913119723
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 7/423
Area:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0111 to 150-PG-0151-GIY
Description:150-PG-0101-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:913142507
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:913142507
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 8/423
Area:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0111 to 150-PG-0151-GIY
Description:150-PG-0101-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:644694762
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:644694762
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 9/423
Area:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0121 to 150-PG-0152-GIY
Description:150-PG-0102-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:927799787
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:927799787
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 10/42
Area:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0121 to 150-PG-0152-GIY
Description:150-PG-0102-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:927822571
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:927822571
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 11/42
Area:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0121 to 150-PG-0152-GIY
Description:150-PG-0102-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:659374826
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:659374826
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 12/42
Area:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0131 to 150-PG-0153-GIY
Description:150-PG-0103-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:807213547
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:807213547
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 13/42
Area:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0131 to 150-PG-0153-GIY
Description:150-PG-0103-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:807236331
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:807236331
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 14/42
Area:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0131 to 150-PG-0153-GIY
Description:150-PG-0103-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:538788586
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:538788586
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 15/42
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0141 to 150-PG-0154-GIY
Description:150-PG-0104-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:838670827
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:838670827
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 16/42
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0141 to 150-PG-0154-GIY
Description:150-PG-0104-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:838693611
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:838693611
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 17/42
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0141 to 150-PG-0154-GIY
Description:150-PG-0104-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:570245866
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:570245866
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 18/42
Area:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0151 to 150-PG-0155-GIY
Description:150-PG-0105-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:853350891
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:853350891
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 19/42
Area:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0151 to 150-PG-0155-GIY
Description:150-PG-0105-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:853373675
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:853373675
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 20/42
Area:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0151 to 150-PG-0155-GIY
Description:150-PG-0105-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:584925930
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:584925930
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 21/42
Area:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0161 to 150-PG-0156-GIY
Description:150-PG-0106-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:866982379
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:866982379
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 22/42
Area:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0161 to 150-PG-0156-GIY
Description:150-PG-0106-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:867005163
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:867005163
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 23/42
Area:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0161 to 150-PG-0156-GIY
Description:150-PG-0106-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:598557418
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:598557418
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 24/42
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0171 to 150-PG-0157-GIY
Description:150-PG-0107-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1031608811
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:1031608811
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 25/42
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0171 to 150-PG-0157-GIY
Description:150-PG-0107-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1031631595
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1031631595
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 26/42
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0171 to 150-PG-0157-GIY
Description:150-PG-0107-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:763183850
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:763183850
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 27/42
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0181 to 150-PG-0158-GIY
Description:150-PG-0108-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1046288875
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:1046288875
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 28/42
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0181 to 150-PG-0158-GIY
Description:150-PG-0108-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1046311659
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1046311659
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 29/42
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0181 to 150-PG-0158-GIY
Description:150-PG-0108-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:777863914
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:777863914
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 30/42
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0191 to 150-PG-0159-GIY
Description:150-PG-0109-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1060968939
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:1060968939
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924). 31/42
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0191 to 150-PG-0159-GIY
Description:150-PG-0109-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1060991723
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1060991723
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 32/42
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0191 to 150-PG-0159-GIY
Description:150-PG-0109-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:792543978
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:792543978
Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922). 33/42
Area:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0201 to 150-PG-0160-GIY
Description:150-PG-0110-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:877463787
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:877463787
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 34/42
Area:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0201 to 150-PG-0160-GIY
Description:150-PG-0110-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:877487083
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:877487083
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 35/42
Area:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0201 to 150-PG-0160-GIY
Description:150-PG-0110-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:609047530
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:609047530
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 36/42
Area:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0211 to 150-PG-0145-GIY
Description:150-PG-0111-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:913115371
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:913115371
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 37/42
Area:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0211 to 150-PG-0145-GIY
Description:150-PG-0111-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:913138667
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:913138667
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 38/42
Area:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0211 to 150-PG-0145-GIY
Description:150-PG-0111-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:644699114
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:644699114
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 39/42
Area:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0221 to 150-PG-0146-GIY
Description:150-PG-0112-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:927795435
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:927795435
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 40/42
Area:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0221 to 150-PG-0146-GIY
Description:150-PG-0112-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:927818731
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:927818731
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 41/42
Area:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
LINES FROM CHOKE VALVE HCV-0221 to 150-PG-0146-GIY
Description:150-PG-0112-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:659379178
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:659379178
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 42/42
Area:42A03Package:
42A - A-4200 PRODUCED WATERSub System:42 - PRODUCED WATER TREATMENTSystem:
LINES FROM PRODUCED WATER SYSTEM (A-4200) to OHD CAISSON (T-6510)
Description:100-PW-4203-SL-B1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1031108017
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0012
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:1031108017
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 43/42
Area:42A03Package:
42A - A-4200 PRODUCED WATERSub System:42 - PRODUCED WATER TREATMENTSystem:
LINES FROM PRODUCED WATER SYSTEM (A-4200) to OHD CAISSON (T-6510)
Description:100-PW-4203-SL-B1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1031085745
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1031085745
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 44/42
Area:42A03Package:
42A - A-4200 PRODUCED WATERSub System:42 - PRODUCED WATER TREATMENTSystem:
LINES FROM PRODUCED WATER SYSTEM (A-4200) to OHD CAISSON (T-6510)
Description:100-PW-4203-SL-B1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:762654384
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:762654384
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 45/42
Area:65B02Package:
65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM HAZ'DOUS OPEN DRAIN HEADER(MAIN DECK) to OHD CAISSON (T-6510)
Description:150-DH-6503-SL-A18ObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1896898980
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0016
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:1896898980
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 46/42
Area:65B02Package:
65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM HAZ'DOUS OPEN DRAIN HEADER(MAIN DECK) to OHD CAISSON (T-6510)
Description:150-DH-6503-SL-A18ObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1896876708
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1896876708
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 47/42
Area:65B02Package:
65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM HAZ'DOUS OPEN DRAIN HEADER(MAIN DECK) to OHD CAISSON (T-6510)
Description:150-DH-6503-SL-A18ObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1628453541
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1628453541
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 48/42
Area:33A02Package:
33A - CONDENSATE EXPORTSub System:33 - CONDENSATE IMPORT/EXPORTSystem:
LINES FROM COND. PIG RECEIVER (L-3310) toPLEM VIA SUBSEA PIPELINE
Description:200-PL-3306-SL-C8YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1268396634
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0013
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:-1268396634
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 49/42
Area:33A02Package:
33A - CONDENSATE EXPORTSub System:33 - CONDENSATE IMPORT/EXPORTSystem:
LINES FROM COND. PIG RECEIVER (L-3310) toPLEM VIA SUBSEA PIPELINE
Description:200-PL-3306-SL-C8YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1268406618
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1268406618
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 50/42
Area:33A02Package:
33A - CONDENSATE EXPORTSub System:33 - CONDENSATE IMPORT/EXPORTSystem:
LINES FROM COND. PIG RECEIVER (L-3310) toPLEM VIA SUBSEA PIPELINE
Description:200-PL-3306-SL-C8YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1536846169
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1536846169
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 51/42
Area:29A02Package:
29A - GAS EXPORTSub System:29 - GAS IMPORT/EXPORTSystem:
LINES FROM GAS PIG LAUNCHER (L-2920) toMEPA / GORA PIPELINE BOUNDARY
Description:500-PG-2921-SL-C8YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2091123198
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0014
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:2091123198
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 52/42
Area:29A02Package:
29A - GAS EXPORTSub System:29 - GAS IMPORT/EXPORTSystem:
LINES FROM GAS PIG LAUNCHER (L-2920) toMEPA / GORA PIPELINE BOUNDARY
Description:500-PG-2921-SL-C8YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2091150078
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:2091150078
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 53/42
Area:29A02Package:
29A - GAS EXPORTSub System:29 - GAS IMPORT/EXPORTSystem:
LINES FROM GAS PIG LAUNCHER (L-2920) toMEPA / GORA PIPELINE BOUNDARY
Description:500-PG-2921-SL-C8YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1822710527
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1822710527
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 54/42
Area:62D14Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0110 CASING to 50-B-6211-G1Y
Description:50-B-6201-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:609277634
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:609277634
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 55/42
Area:62D14Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0110 CASING to 50-B-6211-G1Y
Description:50-B-6201-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:609271234
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:609271234
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 56/42
Area:62D14Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0110 CASING to 50-B-6211-G1Y
Description:50-B-6201-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:877694403
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:877694403
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 57/42
Area:62D15Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0120 CASING to 50-B-6211-G1Y
Description:50-B-6202-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:628152002
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:628152002
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 58/42
Area:62D15Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0120 CASING to 50-B-6211-G1Y
Description:50-B-6202-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:628145602
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:628145602
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 59/42
Area:62D15Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0120 CASING to 50-B-6211-G1Y
Description:50-B-6202-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:896568771
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:896568771
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 60/42
Area:62D16Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0130 CASING to 50-B-6211-G1Y
Description:50-B-6203-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:572577474
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:572577474
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 61/42
Area:62D16Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0130 CASING to 50-B-6211-G1Y
Description:50-B-6203-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:572571074
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:572571074
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 62/42
Area:62D16Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0130 CASING to 50-B-6211-G1Y
Description:50-B-6203-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:840994243
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:840994243
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 63/42
Area:62D17Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0140 CASING to 50-B-6211-G1Y
Description:50-B-6204-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:599840450
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:599840450
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 64/42
Area:62D17Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0140 CASING to 50-B-6211-G1Y
Description:50-B-6204-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:599834050
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:599834050
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 65/42
Area:62D17Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0140 CASING to 50-B-6211-G1Y
Description:50-B-6204-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:868257219
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:868257219
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 66/42
Area:62D18Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0150 CASING to 50-B-6211-G1Y
Description:50-B-6205-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:551605954
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:551605954
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 67/42
Area:62D18Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0150 CASING to 50-B-6211-G1Y
Description:50-B-6205-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:551599554
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:551599554
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 68/42
Area:62D18Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0150 CASING to 50-B-6211-G1Y
Description:50-B-6205-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:820022723
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:820022723
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 69/42
Area:62D01Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM CASING BLOWDOWN HEADER to 50-B-6213-B1Y
Description:50-B-6212-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:628148162
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0003
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:628148162
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 70/42
Area:62D01Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM CASING BLOWDOWN HEADER to 50-B-6213-B1Y
Description:50-B-6212-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:628141250
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:628141250
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 71/42
Area:62D01Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM CASING BLOWDOWN HEADER to 50-B-6213-B1Y
Description:50-B-6212-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:896572611
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:896572611
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 72/42
Area:62D19Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0160 CASING to 50-B-6211-G1Y
Description:50-B-6206-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:563140290
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:563140290
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 73/42
Area:62D19Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0160 CASING to 50-B-6211-G1Y
Description:50-B-6206-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:563133890
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:563133890
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 74/42
Area:62D19Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0160 CASING to 50-B-6211-G1Y
Description:50-B-6206-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:831557059
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:831557059
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 75/42
Area:62D20Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0170 CASING to 50-B-6211-G1Y
Description:50-B-6207-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:792778434
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:792778434
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 76/42
Area:62D20Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0170 CASING to 50-B-6211-G1Y
Description:50-B-6207-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:792772034
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:792772034
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 77/42
Area:62D20Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0170 CASING to 50-B-6211-G1Y
Description:50-B-6207-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1061195203
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1061195203
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 78/42
Area:62D21Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0180 CASING to 50-B-6211-G1Y
Description:50-B-6208-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:744543938
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:744543938
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 79/42
Area:62D21Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0180 CASING to 50-B-6211-G1Y
Description:50-B-6208-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:744537538
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:744537538
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 80/42
Area:62D21Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0180 CASING to 50-B-6211-G1Y
Description:50-B-6208-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1012960707
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1012960707
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 81/42
Area:62D22Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0190 CASING to 50-B-6211-G1Y
Description:50-B-6209-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:755029698
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:755029698
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 82/42
Area:62D22Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0190 CASING to 50-B-6211-G1Y
Description:50-B-6209-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:755023298
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:755023298
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 83/42
Area:62D22Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0190 CASING to 50-B-6211-G1Y
Description:50-B-6209-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1023446467
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1023446467
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 84/42
Area:62D23Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0200 CASING to 50-B-6211-G1Y
Description:50-B-6210-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:644925378
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:644925378
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 85/42
Area:62D23Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0200 CASING to 50-B-6211-G1Y
Description:50-B-6210-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:644918466
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:644918466
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 86/42
Area:62D23Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0200 CASING to 50-B-6211-G1Y
Description:50-B-6210-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:913349827
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:913349827
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 87/42
Area:62D24Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0210 CASING to 50-B-6211-G1Y
Description:50-B-6263-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:572582338
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:572582338
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 88/42
Area:62D24Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0210 CASING to 50-B-6211-G1Y
Description:50-B-6263-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:572555970
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:572555970
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 89/42
Area:62D24Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0210 CASING to 50-B-6211-G1Y
Description:50-B-6263-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:841003715
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:841003715
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 90/42
Area:62D25Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0220 CASING to 50-B-6211-G1Y
Description:50-B-6264-SL-G1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:599845314
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001-1
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:599845314
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 91/42
Area:62D25Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0220 CASING to 50-B-6211-G1Y
Description:50-B-6264-SL-G1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:599818946
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:599818946
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 92/42
Area:62D25Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
LINES FROM WELLHEAD WH-0220 CASING to 50-B-6211-G1Y
Description:50-B-6264-SL-G1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:868266691
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:868266691
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 93/42
Area:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
LINES FROM OHD CAISSON (T-6510) to OHDCAISSON PUMP (P-6520)(OFFSHORE)
Description:50-DC-6541-SL-B1YObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-76968732
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0021
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:-76968732
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 94/42
Area:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
LINES FROM OHD CAISSON (T-6510) to OHDCAISSON PUMP (P-6520)(OFFSHORE)
Description:50-DC-6541-SL-B1YObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:996773118
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:996773118
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 95/42
Area:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
LINES FROM OHD CAISSON (T-6510) to OHDCAISSON PUMP (P-6520)(OFFSHORE)
Description:50-DC-6541-SL-B1YObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:996216050
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:996216050
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 96/42
Area:65B02Package:
65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM OHD CAISON PUMP (P-6520) to 150-DH-6503-A18
Description:50-DH-6508-SL-A18ObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1745386267
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0021
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:-1745386267
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 97/42
Area:65B02Package:
65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM OHD CAISON PUMP (P-6520) to 150-DH-6503-A18
Description:50-DH-6508-SL-A18ObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1475839231
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1475839231
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 98/42
Area:65B02Package:
65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM OHD CAISON PUMP (P-6520) to 150-DH-6503-A18
Description:50-DH-6508-SL-A18ObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1476330739
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1476330739
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 99/42
Area:65B02Package:
65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM FLARE K.O. DRUM COAMED AREA to150-DH-6503-A18
Description:50-DH-6528-SL-A18ObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1475839205
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0018
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:1475839205
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 100/4
Area:65B02Package:
65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM FLARE K.O. DRUM COAMED AREA to150-DH-6503-A18
Description:50-DH-6528-SL-A18ObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1745386241
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1745386241
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 101/4
Area:65B02Package:
65B - HAZARDOUS OPEN DRAINS HEADERSub System:65 - OPEN DRAINSystem:
LINES FROM FLARE K.O. DRUM COAMED AREA to150-DH-6503-A18
Description:50-DH-6528-SL-A18ObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1744894733
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1744894733
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 102/4
Area:53A02Package:
53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:
LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP
Description:50-FW-5310-SL-A18ObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-8879906
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0023
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:-8879906
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 103/4
Area:53A02Package:
53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:
LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP
Description:50-FW-5310-SL-A18ObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1064861892
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1064861892
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 104/4
Area:53A02Package:
53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:
LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP
Description:50-FW-5310-SL-A18ObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1064304840
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1064304840
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 105/4
Area:53A02Package:
53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:
LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP
Description:50-FW-5309-SL-A18ObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2004507870
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0023
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:2004507870
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 106/4
Area:53A02Package:
53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:
LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP
Description:50-FW-5309-SL-A18ObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1216717628
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1216717628
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 107/4
Area:53A02Package:
53A - FIREWATER DISTRIBUTIONSub System:53 - FIXED FIREWATER SYSTEMSystem:
LINES FROM 100-FW-5302-A18 to OVERBOARDDUMP
Description:50-FW-5309-SL-A18ObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1217209144
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1217209144
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 108/4
Area:51B02Package:
51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:
LINES FROM AIR RELEASE VALVE P-5110 to VENTTO SAFE LOCATION (OFFSHORE)
Description:50-VA-9802-SL-A18ObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1211973564
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0022
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:-1211973564
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 109/4
Area:51B02Package:
51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:
LINES FROM AIR RELEASE VALVE P-5110 to VENTTO SAFE LOCATION (OFFSHORE)
Description:50-VA-9802-SL-A18ObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2009251934
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:2009251934
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 110/4
Area:51B02Package:
51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:
LINES FROM AIR RELEASE VALVE P-5110 to VENTTO SAFE LOCATION (OFFSHORE)
Description:50-VA-9802-SL-A18ObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2009743442
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:2009743442
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 111/4
Area:51B02Package:
51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:
LINES FROM SERVICE WATER SUPPLY CAISSON(T-5510) to SERVICE WATER NETWORK
Description:50-WS-5104-SL-A18ObjectID:
Inspection Test ReportP04A Flushing and Testing Certificate
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2000686169
Operational Medium:
Flushing Medium:TestMedium:PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0022
Name and SignatureTest Witnessed by (Note2)
Name and SignatureTested by Contractor
HoursTest Duration
Date and TimeEnd Date and Time
Degree CAmbient Temperature at end
BarGTest Pressure at end
Date and TimeStart Date and Time
Degree CAmbient Temperature at start
BarGTest Pressure at start
Test Results and Readings
System tested in accordance with the approved procedure. (Refer Note1).
System prepared for testing in accordance with the approved procedure.
Flushing completed in accordance with the approved procedure
System prepared for flushing in accordance with the approvedprocedure.
Limits of Test in accordance with the scope listed on attached TestIndex P-01A and marked up P&ID's.
DateVerified byCompleted byDescription of Item to be completed and Checked
Notes
1. All test and Calibration charts to be Signed, Verified and Identified with the Test Number.2. Where Test is not witnessed state NA.
3. All activity required Commissioning & Client Witness points
Date:
Sign:
Name:
BDEWC CommissionBDEWC QA/QCBDEWC Construction
OE:2000686169
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924). 112/4
Area:51B02Package:
51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:
LINES FROM SERVICE WATER SUPPLY CAISSON(T-5510) to SERVICE WATER NETWORK
Description:50-WS-5104-SL-A18ObjectID:
Inspection Test ReportP02A Piping Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1220539325
TestPack:Service:
All chain wheels and extended spindles installed.21
Check that system is adequately supported such that no spring in pipework causes stresson pumps or vessel nozzles.
20
Gags on spring supports and expansion joints are in position.19
All pipe supports installed according to drawings and specifications.18
All thermowells are installed.17
Check Orifice flanges have required upstream and downstream clearances, which boreshave been ground and orifice plates have been removed. *W*
16
Check Orifice valve tap orientation correct, taps and plugs have been seal welded andunused. Tapped holes are plugged and welded. *W*
15
All Relief valves, Bursting disks, and specified control valves have been removed. *W*14
All instrument connections installed and any delicate instruments are isolated / removedfrom test. *W*
13
Correct direction of flow through filters and strainers traps, check valves, globe valvesand control valves. *W*
12
All pressure connections as per specification.11
Compound on screwed connections in accordance with specifications.10
Branch reinforcements are correct.09
Check Valve Materials - (Use spec ref. in piping material specification, tags andnameplates.
08
Rating of all forged steel fittings is correct. *W*07
Piping of correct material, schedule and type. *W*06
All vents and drains are installed, including vents and drains for testing and are of correctpressure rating.
05
Correct bolts and gaskets are installed at all mechanical joints.04
All NDT/Stress relieving requirements performed in accordance with requirements anddocumented.
03
All field weld inspection and NDE, Traceability and History records complete andaccepted.
02
System complies with P and ID's and isometric drawings.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1220539325
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 113/4
Area:51B02Package:
51B - SERVICE WATER DISTRIBUTIONSub System:51 - SERVICE WATER SYSTEMSystem:
LINES FROM SERVICE WATER SUPPLY CAISSON(T-5510) to SERVICE WATER NETWORK
Description:50-WS-5104-SL-A18ObjectID:
Inspection Test ReportP10A Line Walk Verification
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1219982257
Service:
Required DOSH & 3rd Party witnessed16
Flange management complete and tag fitted to every joint (if specified in projectrequirements)
15
All certification documentation, including test charts and test equipment calibrationcertificates signed and approved.
14
The ITRs have been completed for all in-line items that require dismantling of flanges tocarry out ITR, e.g. M-09A inspection of inline filters. (mandatory)
13
Coupling alignment completed in accordance with ITR M06A on all pipe spoolsconnected to rotating equipment. (mandatory)
12
All temporary commissioning and start up strainers installed *W*11
Line reinstated according to requirements and latest revision of the P&ID's, and allspectacle blinds in position shown on P&IDs
10
Check manual valves are correctly lubricated, assessable and operational09
Line preserved according to project requirements.08
Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W*07
Lines Chemically cleaned / Pickled according to Project / Vendor requirements, wherespecified. *W*
06
All Hydrotesting completed. *W*05
Lines dried in accordance with Project requirements *W*04
Lines flushed in accordance with Project requirements. *W*03
All pipe supports installed in accordance with the drawings and Project spec's and alllines adequately supported.
02
Line walk sub-system and verify it reflects the latest revision of the P & ID's, and allpipework, valves, auxiliaries, etc are undamaged.
01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1219982257
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 114/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
JUNCTION BOX 7710-JL05-9RDescription:7710-JL05-9RObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-306091743
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-306091743
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 115/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
JUNCTION BOX 7710-JL05-9RDescription:7710-JL05-9RObjectID:
Inspection Test ReportE05A Distribution Board, Junction Box & ControlStation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-37645536
SingleLineDwg:
SerialNo:Model/Type:Manufacturer:
Replace all covers and check all bolts are correct none missing.12
Check gaskets and seals are not damaged.11
On completion of all cable glanding confirm spare entries are correctly plugged.10
Confirm all components are operational and lockable where necessary09
Check component ratings are as per drawings08
Check correct circuit identification labels.07
Check earthing conforms to project specifications.06
Check interior for damage, cleanliness and transport packing has been removed.05
Check equipment fixings and mountings are secure.04
Confirm equipment is tagged correctly03
Visually inspect equipment for external damage.02
Installation as per AFC Drawings and cable schedule01
Output /RemarksPLOKNADescriptionItem
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-37645536
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 116/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
JUNCTION BOX 7710-JL06-9RDescription:7710-JL06-9RObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-306091761
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-306091761
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 117/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
JUNCTION BOX 7710-JL06-9RDescription:7710-JL06-9RObjectID:
Inspection Test ReportE05A Distribution Board, Junction Box & ControlStation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-37645554
SingleLineDwg:
SerialNo:Model/Type:Manufacturer:
Replace all covers and check all bolts are correct none missing.12
Check gaskets and seals are not damaged.11
On completion of all cable glanding confirm spare entries are correctly plugged.10
Confirm all components are operational and lockable where necessary09
Check component ratings are as per drawings08
Check correct circuit identification labels.07
Check earthing conforms to project specifications.06
Check interior for damage, cleanliness and transport packing has been removed.05
Check equipment fixings and mountings are secure.04
Confirm equipment is tagged correctly03
Visually inspect equipment for external damage.02
Installation as per AFC Drawings and cable schedule01
Output /RemarksPLOKNADescriptionItem
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-37645554
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 118/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
JUNCTION BOX 7710-JL07-9RDescription:7710-JL07-9RObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-306091819
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-306091819
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 119/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
JUNCTION BOX 7710-JL07-9RDescription:7710-JL07-9RObjectID:
Inspection Test ReportE05A Distribution Board, Junction Box & ControlStation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-37645612
SingleLineDwg:
SerialNo:Model/Type:Manufacturer:
Replace all covers and check all bolts are correct none missing.12
Check gaskets and seals are not damaged.11
On completion of all cable glanding confirm spare entries are correctly plugged.10
Confirm all components are operational and lockable where necessary09
Check component ratings are as per drawings08
Check correct circuit identification labels.07
Check earthing conforms to project specifications.06
Check interior for damage, cleanliness and transport packing has been removed.05
Check equipment fixings and mountings are secure.04
Confirm equipment is tagged correctly03
Visually inspect equipment for external damage.02
Installation as per AFC Drawings and cable schedule01
Output /RemarksPLOKNADescriptionItem
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-37645612
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 120/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
JUNCTION BOX 7710-JL08-9RDescription:7710-JL08-9RObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-306091855
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-306091855
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 121/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
JUNCTION BOX 7710-JL08-9RDescription:7710-JL08-9RObjectID:
Inspection Test ReportE05A Distribution Board, Junction Box & ControlStation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-37645648
SingleLineDwg:
SerialNo:Model/Type:Manufacturer:
Replace all covers and check all bolts are correct none missing.12
Check gaskets and seals are not damaged.11
On completion of all cable glanding confirm spare entries are correctly plugged.10
Confirm all components are operational and lockable where necessary09
Check component ratings are as per drawings08
Check correct circuit identification labels.07
Check earthing conforms to project specifications.06
Check interior for damage, cleanliness and transport packing has been removed.05
Check equipment fixings and mountings are secure.04
Confirm equipment is tagged correctly03
Visually inspect equipment for external damage.02
Installation as per AFC Drawings and cable schedule01
Output /RemarksPLOKNADescriptionItem
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-37645648
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 122/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
LIGHTING FIXTURE 7710-LE05-9RDescription:7710-LE05-9RObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-367956047
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-367956047
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 123/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
LIGHTING FIXTURE 7710-LE06-9RDescription:7710-LE06-9RObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-367956065
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-367956065
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 124/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
LIGHTING FIXTURE 7710-LE07-9RDescription:7710-LE07-9RObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-367956411
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-367956411
Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922). 125/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
LIGHTING FIXTURE 7710-LE08-9RDescription:7710-LE08-9RObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-367956447
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-367956447
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 126/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
Cable From JUNCTION BOX 7710-JL04-9R ToJUNCTION BOX 7710-JL05-9R
Description:7710-LE-09/9RObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-373690140
VoltageRating: 240VToTag: JUNCTION BOX 7710-JL05-9R
Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL04-9RCableType: P2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-373690140
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 127/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
Cable From JUNCTION BOX 7710-JL05-9R ToLIGHTING FIXTURE 7710-LE05-9R
Description:7710-LE-10/9RObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-122049692
VoltageRating: 240VToTag: LIGHTING FIXTURE 7710-LE05-9R
Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL05-9RCableType: P2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-122049692
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 128/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
Cable From JUNCTION BOX 7710-JL05-9R ToJUNCTION BOX 7710-JL06-9R
Description:7710-LE-11/9RObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-122045852
VoltageRating: 240VToTag: JUNCTION BOX 7710-JL06-9R
Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL05-9RCableType: P2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-122045852
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 129/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
Cable From JUNCTION BOX 7710-JL06-9R ToLIGHTING FIXTURE 7710-LE06-9R
Description:7710-LE-12/9RObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-122047644
VoltageRating: 240VToTag: LIGHTING FIXTURE 7710-LE06-9R
Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL06-9RCableType: P2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-122047644
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 130/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
Cable From JUNCTION BOX 7710-JL06-9R ToJUNCTION BOX 7710-JL07-9R
Description:7710-LE-13/9RObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-122058268
VoltageRating: 240VToTag: JUNCTION BOX 7710-JL07-9R
Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL06-9RCableType: P2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-122058268
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 131/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
Cable From JUNCTION BOX 7710-JL07-9R ToLIGHTING FIXTURE 7710-LE07-9R
Description:7710-LE-14/9RObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-122059036
VoltageRating: 240VToTag: LIGHTING FIXTURE 7710-LE07-9R
Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL07-9RCableType: P2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-122059036
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 132/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
Cable From JUNCTION BOX 7710-JL07-9R ToJUNCTION BOX 7710-JL08-9R
Description:7710-LE-15/9RObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-122052636
VoltageRating: 240VToTag: JUNCTION BOX 7710-JL08-9R
Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL07-9RCableType: P2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-122052636
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 133/4
Area:77D07Package:
77D - LV EMERGENCY DISTRIBUTIONSub System:77 - POWER GENERATION DISTRIBUTION LVSystem:
Cable From JUNCTION BOX 7710-JL08-9R ToLIGHTING FIXTURE 7710-LE08-9R
Description:7710-LE-16/9RObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-122055580
VoltageRating: 240VToTag: LIGHTING FIXTURE 7710-LE08-9R
Size: 2Cx4mm2FromTag: JUNCTION BOX 7710-JL08-9RCableType: P2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-122055580
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 134/4
Area:92E01Package:
92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:GOPB-ANT-9206ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1349334717
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1349334717
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 135/4
Area:92E01Package:
92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:GOPB-ANT-9206ObjectID:
Inspection Test ReportT01A Telecoms Field Device Installation Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-275101665
Type:
Service:Serial No:Manufacturer:
Suitable grease applied to flanges (Ex-d enclosures).14
Check earthing conforms to earthing philosophy.13
Gaskets & seals fitted correctly.12
Gaskets & seals undamaged.11
Terminal box flanges undamaged.10
Spare gland entries plugged correctly.09
Paintwork correct.08
Access suitable.07
Fixings correct.06
Supports installed correctly.05
Identification correct.04
Equipment suitable for area classification.03
Item complies with Data sheet.02
Installed according to latest revision of Layout drawing.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-275101665
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 136/4
Area:92E01Package:
92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:GOPB-ANT-9207ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1370961597
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1370961597
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 137/4
Area:92E01Package:
92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:GOPB-ANT-9207ObjectID:
Inspection Test ReportT01A Telecoms Field Device Installation Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-297777121
Type:
Service:Serial No:Manufacturer:
Suitable grease applied to flanges (Ex-d enclosures).14
Check earthing conforms to earthing philosophy.13
Gaskets & seals fitted correctly.12
Gaskets & seals undamaged.11
Terminal box flanges undamaged.10
Spare gland entries plugged correctly.09
Paintwork correct.08
Access suitable.07
Fixings correct.06
Supports installed correctly.05
Identification correct.04
Equipment suitable for area classification.03
Item complies with Data sheet.02
Installed according to latest revision of Layout drawing.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-297777121
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 138/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PRESSURE GAUGEDescription:GORA-PG-2950ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:942423269
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:942423269
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 139/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PRESSURE GAUGEDescription:GORA-PG-2953ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2016165108
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:2016165108
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 140/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PRESSURE GAUGEDescription:GORA-PG-2954ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-131318541
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-131318541
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 141/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
PRESSURE GAUGEDescription:GORA-PG-3390ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:955366657
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:955366657
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 142/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
PRESSURE GAUGEDescription:GORA-PG-3393ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2029108496
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:2029108496
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 143/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
PRESSURE GAUGEDescription:GORA-PG-3394ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-118375145
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-118375145
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 144/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PRESSURE TRANSMITTERDescription:GORA-PIA-2952ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:452355156
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:452355156
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 145/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PRESSURE TRANSMITTERDescription:GORA-PIA-2952ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-621386675
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-621386675
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 146/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PRESSURE DIFFERENTIAL TRANSMITTERDescription:GORA-PIA-2955ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:440689748
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:440689748
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 147/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PRESSURE DIFFERENTIAL TRANSMITTERDescription:GORA-PIA-2955ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-633052083
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-633052083
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 148/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
PRESSURE TRANSMITTERDescription:GORA-PIA-3392ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:366367540
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:366367540
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 149/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
PRESSURE TRANSMITTERDescription:GORA-PIA-3392ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-707374291
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-707374291
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 150/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PRESSURE TRANSMITTERDescription:GORA-PZA-2951ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:449841236
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:449841236
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 151/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PRESSURE TRANSMITTERDescription:GORA-PZA-2951ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-623900595
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-623900595
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 152/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
PRESSURE TRANSMITTERDescription:GORA-PZA-3391ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:368066356
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:368066356
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 153/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
PRESSURE TRANSMITTERDescription:GORA-PZA-3391ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-705675475
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-705675475
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 154/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
SHUTDOWN VALVEDescription:GORA-SDV-2950ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-157891497
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-157891497
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 155/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
SHUTDOWN VALVEDescription:GORA-SDV-2950ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-157891492
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-157891492
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 156/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
SHUTDOWN VALVEDescription:GORA-SDV-2950ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:915850318
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:915850318
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 157/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
SHUTDOWN VALVEDescription:GORA-SDV-2951ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-153959337
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-153959337
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 158/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
SHUTDOWN VALVEDescription:GORA-SDV-2951ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-153959332
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-153959332
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 159/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
SHUTDOWN VALVEDescription:GORA-SDV-2951ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:919782478
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:919782478
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 160/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
SHUTDOWN VALVEDescription:GORA-SDV-3390ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-105450697
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-105450697
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 161/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
SHUTDOWN VALVEDescription:GORA-SDV-3390ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-105450692
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-105450692
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 162/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
SHUTDOWN VALVEDescription:GORA-SDV-3390ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:968291118
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:968291118
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 163/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PIG SIGNALLER - LOCAL INDICATION -L2950Description:GORA-XI-2952ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1051489945
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1051489945
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 164/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
PIG SIGNALLER - LOCAL INDICATION -L3390Description:GORA-XI-3392ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1047656317
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1047656317
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 165/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PIG SIGNALLER - REMOTE INDICATION - L2950Description:GORA-XIA-2951ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2060608599
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:2060608599
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 166/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
PIG SIGNALLER - REMOTE INDICATION - L2950Description:GORA-XIA-2951ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1160616882
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1160616882
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 167/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
PIG SIGNALLER - REMOTE INDICATION - L3390Description:GORA-XIA-3391ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1978815287
Service:
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1978815287
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 168/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
PIG SIGNALLER - REMOTE INDICATION - L3390Description:GORA-XIA-3391ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1242410194
Service:
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1242410194
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 169/4
Area:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0111Description:HY-0111ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-660729992
VoltageRating: -ToTag: MEPA-HY-0111
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-660729992
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 170/4
Area:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0121Description:HY-0121ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-660959368
VoltageRating: -ToTag: MEPA-HY-0121
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-660959368
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 171/4
Area:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0131Description:HY-0131ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-662188168
VoltageRating: -ToTag: MEPA-HY-0131
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-662188168
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 172/4
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0141Description:HY-0141ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-662679688
VoltageRating: -ToTag: MEPA-HY-0141
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-662679688
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 173/4
Area:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0151Description:HY-0151ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-661860488
VoltageRating: -ToTag: MEPA-HY-0151
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-661860488
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 174/4
Area:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0161Description:HY-0161ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-662106248
VoltageRating: -ToTag: MEPA-HY-0161
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-662106248
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 175/4
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0171Description:HY-0171ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-659402888
VoltageRating: -ToTag: MEPA-HY-0171
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-659402888
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 176/4
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0181Description:HY-0181ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-658583688
VoltageRating: -ToTag: MEPA-HY-0181
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-658583688
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 177/4
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0191Description:HY-0191ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-658813064
VoltageRating: -ToTag: MEPA-HY-0191
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-658813064
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 178/4
Area:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0201Description:HY-0201ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-661221540
VoltageRating: -ToTag: MEPA-HY-0201
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-661221540
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 179/4
Area:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0211Description:HY-0211ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-660730020
VoltageRating: -ToTag: MEPA-HY-0211
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-660730020
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 180/4
Area:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-009 To MEPA-HY-0221Description:HY-0221ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-660959396
VoltageRating: -ToTag: MEPA-HY-0221
Size: 1PRx1.5mm2FromTag: MEPA-IJB-009CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-660959396
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 181/4
Area:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
Inst. Cable From MEPA-IJB-015 To MEPA-LT-6510Description:LT-6510ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1579289606
VoltageRating: -ToTag: MEPA-LT-6510
Size: 1PRx1.5mm2FromTag: MEPA-IJB-015CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1579289606
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 182/4
Area:92A02Package:
92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:MEPA-ANT-9201ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1351177929
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1351177929
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 183/4
Area:92A02Package:
92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:MEPA-ANT-9201ObjectID:
Inspection Test ReportT01A Telecoms Field Device Installation Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-276944789
Type:
Service:Serial No:Manufacturer:
Suitable grease applied to flanges (Ex-d enclosures).14
Check earthing conforms to earthing philosophy.13
Gaskets & seals fitted correctly.12
Gaskets & seals undamaged.11
Terminal box flanges undamaged.10
Spare gland entries plugged correctly.09
Paintwork correct.08
Access suitable.07
Fixings correct.06
Supports installed correctly.05
Identification correct.04
Equipment suitable for area classification.03
Item complies with Data sheet.02
Installed according to latest revision of Layout drawing.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-276944789
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 184/4
Area:92A02Package:
92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:MEPA-ANT-9202ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1353537225
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1353537225
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 185/4
Area:92A02Package:
92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:MEPA-ANT-9202ObjectID:
Inspection Test ReportT01A Telecoms Field Device Installation Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-279304085
Type:
Service:Serial No:Manufacturer:
Suitable grease applied to flanges (Ex-d enclosures).14
Check earthing conforms to earthing philosophy.13
Gaskets & seals fitted correctly.12
Gaskets & seals undamaged.11
Terminal box flanges undamaged.10
Spare gland entries plugged correctly.09
Paintwork correct.08
Access suitable.07
Fixings correct.06
Supports installed correctly.05
Identification correct.04
Equipment suitable for area classification.03
Item complies with Data sheet.02
Installed according to latest revision of Layout drawing.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-279304085
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 186/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:MEPA-ANT-9203ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1346852553
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1346852553
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 187/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:MEPA-ANT-9203ObjectID:
Inspection Test ReportT01A Telecoms Field Device Installation Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-273667989
Type:
Service:Serial No:Manufacturer:
Suitable grease applied to flanges (Ex-d enclosures).14
Check earthing conforms to earthing philosophy.13
Gaskets & seals fitted correctly.12
Gaskets & seals undamaged.11
Terminal box flanges undamaged.10
Spare gland entries plugged correctly.09
Paintwork correct.08
Access suitable.07
Fixings correct.06
Supports installed correctly.05
Identification correct.04
Equipment suitable for area classification.03
Item complies with Data sheet.02
Installed according to latest revision of Layout drawing.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-273667989
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 188/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:MEPA-ANT-9204ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1350260425
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1350260425
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 189/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:MEPA-ANT-9204ObjectID:
Inspection Test ReportT01A Telecoms Field Device Installation Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-276027285
Type:
Service:Serial No:Manufacturer:
Suitable grease applied to flanges (Ex-d enclosures).14
Check earthing conforms to earthing philosophy.13
Gaskets & seals fitted correctly.12
Gaskets & seals undamaged.11
Terminal box flanges undamaged.10
Spare gland entries plugged correctly.09
Paintwork correct.08
Access suitable.07
Fixings correct.06
Supports installed correctly.05
Identification correct.04
Equipment suitable for area classification.03
Item complies with Data sheet.02
Installed according to latest revision of Layout drawing.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-276027285
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 190/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:MEPA-ANT-9205ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1344231113
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1344231113
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 191/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
PARABOLIC ANTENNADescription:MEPA-ANT-9205ObjectID:
Inspection Test ReportT01A Telecoms Field Device Installation Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-269997973
Type:
Service:Serial No:Manufacturer:
Suitable grease applied to flanges (Ex-d enclosures).14
Check earthing conforms to earthing philosophy.13
Gaskets & seals fitted correctly.12
Gaskets & seals undamaged.11
Terminal box flanges undamaged.10
Spare gland entries plugged correctly.09
Paintwork correct.08
Access suitable.07
Fixings correct.06
Supports installed correctly.05
Identification correct.04
Equipment suitable for area classification.03
Item complies with Data sheet.02
Installed according to latest revision of Layout drawing.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-269997973
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 192/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
UHF DATA RADIO 5.8GHZDescription:MEPA-ANT-9206ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1345410761
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1345410761
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 193/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
UHF DATA RADIO 5.8GHZDescription:MEPA-ANT-9206ObjectID:
Inspection Test ReportT01A Telecoms Field Device Installation Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-272226197
Type:
Service:Serial No:Manufacturer:
Suitable grease applied to flanges (Ex-d enclosures).14
Check earthing conforms to earthing philosophy.13
Gaskets & seals fitted correctly.12
Gaskets & seals undamaged.11
Terminal box flanges undamaged.10
Spare gland entries plugged correctly.09
Paintwork correct.08
Access suitable.07
Fixings correct.06
Supports installed correctly.05
Identification correct.04
Equipment suitable for area classification.03
Item complies with Data sheet.02
Installed according to latest revision of Layout drawing.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-272226197
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 194/4
All Fireproofing clean and undamaged86
Fireproofing material finish conforms to agreed sample (where applicable)85
Fireproofing materials applied according to specification84
All paintwork clean and undamaged83
Finish paint colour conforms to specification82
All remedial work completed and accepted81
All specified adhesion tests completed and accepted80
Correct paint system applied according to specification and in accordance with supplierrequirements
79
Painting , Coatings and Fireproofing78
Hose reel rewind satisfactorily.77
Hose nozzle operation and shut-off checked.76
Hose free from damage and kinks.75
Hose reel runs out correctly.74
Main valves checked for ease of operation and shut-off.73
Stop valves checked for ease of operation and shut-off.72
Operation instructions fitted and legible.71
Cabinet doors secure.70
Hose reel correctly installed to manufacturers instructions.69
Hose reels68
Escape route / safety signs not obstructed and legible.67
Escape route / safety signs securely fixed in position.66
Escape route / safety signs, location correct as per Loss Control layout drawings.65
Direction of escape correct and clearly marked.64
Escape routes painted to specification and non-skid surface complete.63
Escape routes not obstructed.62
Escape route in accordance with Loss Control layout drawings.61
Escape Routes and Platform Signs60
Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.
59
Insulation materials do not obstruct operation of access man-ways.58
All data plates and tag numbers are visible.57
All equipment nozzles and instruments are clear of the insulation material and jacketing.56
Jacketing, type, application and condition conforms to latest AFC specifications.55
Insulation, thickness and material in accordance with latest AFC specifications.54
Equipment53
Mastic and water seals correctly installed52
Cable and piping penetrations completed and sealed in accordance with the latest AFCspecifications.
51
Fixing materials, including screws and banding, are of the correct type and installed inaccordance with the latest AFC specification.
50
Jacketing thickness and material in accordance with the latest AFC specifications.49
Insulation, thickness and material in accordance with the latest AFC specifications.48
Snap on boxes fitted at all required locations in accordance with the specifications.47
Access to all instruments, including in-line instruments unobstructed by insulationmaterials.
46
No attachment points on the piping system are covered by insulation material.45
Limits of insulation in accordance with the latest AFC P&ID, drawings and specifications.44
Piping Systems43
System and temporary dust blinds are visible.42
Identification labels and arrows installed.41
Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.
40
Insulation materials do not obstruct operation of access man-ways.39
Data plates and tag numbers are visible.38
Jacketing, type, application and condition conforms to requirements.37
Insulation, thickness and material in accordance with the latest AFC specifications.36
Limits of insulation with the latest AFC D & ID drawings and specifications.35
HVAC Ductwork34
Galvanised steel lining fixed to protect wall and deck-head insulation as specified bylatest AFC shop drawings and Vendor details.
33
All cable penetrations confirm to the requirements of the penetration dossier for firerating.
32
All piping and ducting penetrations in accordance with the requirements of the latest AFCpenetration dossier for fire rating.
31
Mesh of correct type has been installed according to the latest AFC specification.30
Insulating material and thickness in accordance with the latest AFC specification. Vapourbarriers installed where required.
29
Pins installed, where applicable, in accordance with latest AFC specifications.28
Walls and Ceilings27
Confirm all cable ladder are fully covered (if applicable)26
Confirm cable dressing is complete25
Confirm all transits are complete and blocked.24
Confirm all transits are packed in accordance with the transit schedule23
Confirm all transit frames are installed correctly22
Confirm all dissimilar metal insulators are installed.21
Confirm all earth bonding is complete20
Confirm all cables are clipped with permanent fixings19
Confirm all cable racks are identified18
Confirm all supports and fixings are correct and complete17
Confirm all cable trays and racks are installed in accordance with routing and detaildrawings
16
Electrical Cable Racks, ladder, transit and cover15
Area is clean and free of all debris.14
Information signs installed.13
Furniture: All furniture of correct colour and placed in accordance with drawings, alldrawers/locker doors open/shut, all locks function. All spare keys taped securely adjacentto respective locks.
12
All doors and windows free from damage and installed correctly in accordance with latestAFC drawings.
11
Suspended floors correct and un-damaged.10
Water bunds turned up around walls in wet areas.09
Floors lay to drain evenly to outlets, with no puddling or flat spots.08
Floor coating: Floor screed placed according to specification, carpet or tiles of correctcolour, embedding of carpet or tiles is firm without any gaps or damage.
07
Pre-fabricated firewalls/louvers installed to specification with sealed joints, plumb andlined, without damage.
06
Wall and ceiling linings: Insulation and vapour barrier placed and undamaged, liningcolour correct, ceiling and wall panels correctly trimmed and free from damage.
05
All equipment performs its specified function.04
All equipment free from damage installed and correctly secured in accordance with latestAFC drawings.
03
All equipment located and correctly tagged in accordance with latest AFC drawings.02
General01
Output /RemarksPLOKNADescriptionItem
Area:71E01Package:
71E - BOAT LANDINGSub System:71 - STRUCTURALSystem:
BOAT LANDINGDescription:MEPA-BL-7100ObjectID:
Inspection Test ReportM20A Area Completion
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:335707679
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:335707679
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 195/4
All Fireproofing clean and undamaged86
Fireproofing material finish conforms to agreed sample (where applicable)85
Fireproofing materials applied according to specification84
All paintwork clean and undamaged83
Finish paint colour conforms to specification82
All remedial work completed and accepted81
All specified adhesion tests completed and accepted80
Correct paint system applied according to specification and in accordance with supplierrequirements
79
Painting , Coatings and Fireproofing78
Hose reel rewind satisfactorily.77
Hose nozzle operation and shut-off checked.76
Hose free from damage and kinks.75
Hose reel runs out correctly.74
Main valves checked for ease of operation and shut-off.73
Stop valves checked for ease of operation and shut-off.72
Operation instructions fitted and legible.71
Cabinet doors secure.70
Hose reel correctly installed to manufacturers instructions.69
Hose reels68
Escape route / safety signs not obstructed and legible.67
Escape route / safety signs securely fixed in position.66
Escape route / safety signs, location correct as per Loss Control layout drawings.65
Direction of escape correct and clearly marked.64
Escape routes painted to specification and non-skid surface complete.63
Escape routes not obstructed.62
Escape route in accordance with Loss Control layout drawings.61
Escape Routes and Platform Signs60
Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.
59
Insulation materials do not obstruct operation of access man-ways.58
All data plates and tag numbers are visible.57
All equipment nozzles and instruments are clear of the insulation material and jacketing.56
Jacketing, type, application and condition conforms to latest AFC specifications.55
Insulation, thickness and material in accordance with latest AFC specifications.54
Equipment53
Mastic and water seals correctly installed52
Cable and piping penetrations completed and sealed in accordance with the latest AFCspecifications.
51
Fixing materials, including screws and banding, are of the correct type and installed inaccordance with the latest AFC specification.
50
Jacketing thickness and material in accordance with the latest AFC specifications.49
Insulation, thickness and material in accordance with the latest AFC specifications.48
Snap on boxes fitted at all required locations in accordance with the specifications.47
Access to all instruments, including in-line instruments unobstructed by insulationmaterials.
46
No attachment points on the piping system are covered by insulation material.45
Limits of insulation in accordance with the latest AFC P&ID, drawings and specifications.44
Piping Systems43
System and temporary dust blinds are visible.42
Identification labels and arrows installed.41
Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.
40
Insulation materials do not obstruct operation of access man-ways.39
Data plates and tag numbers are visible.38
Jacketing, type, application and condition conforms to requirements.37
Insulation, thickness and material in accordance with the latest AFC specifications.36
Limits of insulation with the latest AFC D & ID drawings and specifications.35
HVAC Ductwork34
Galvanised steel lining fixed to protect wall and deck-head insulation as specified bylatest AFC shop drawings and Vendor details.
33
All cable penetrations confirm to the requirements of the penetration dossier for firerating.
32
All piping and ducting penetrations in accordance with the requirements of the latest AFCpenetration dossier for fire rating.
31
Mesh of correct type has been installed according to the latest AFC specification.30
Insulating material and thickness in accordance with the latest AFC specification. Vapourbarriers installed where required.
29
Pins installed, where applicable, in accordance with latest AFC specifications.28
Walls and Ceilings27
Confirm all cable ladder are fully covered (if applicable)26
Confirm cable dressing is complete25
Confirm all transits are complete and blocked.24
Confirm all transits are packed in accordance with the transit schedule23
Confirm all transit frames are installed correctly22
Confirm all dissimilar metal insulators are installed.21
Confirm all earth bonding is complete20
Confirm all cables are clipped with permanent fixings19
Confirm all cable racks are identified18
Confirm all supports and fixings are correct and complete17
Confirm all cable trays and racks are installed in accordance with routing and detaildrawings
16
Electrical Cable Racks, ladder, transit and cover15
Area is clean and free of all debris.14
Information signs installed.13
Furniture: All furniture of correct colour and placed in accordance with drawings, alldrawers/locker doors open/shut, all locks function. All spare keys taped securely adjacentto respective locks.
12
All doors and windows free from damage and installed correctly in accordance with latestAFC drawings.
11
Suspended floors correct and un-damaged.10
Water bunds turned up around walls in wet areas.09
Floors lay to drain evenly to outlets, with no puddling or flat spots.08
Floor coating: Floor screed placed according to specification, carpet or tiles of correctcolour, embedding of carpet or tiles is firm without any gaps or damage.
07
Pre-fabricated firewalls/louvers installed to specification with sealed joints, plumb andlined, without damage.
06
Wall and ceiling linings: Insulation and vapour barrier placed and undamaged, liningcolour correct, ceiling and wall panels correctly trimmed and free from damage.
05
All equipment performs its specified function.04
All equipment free from damage installed and correctly secured in accordance with latestAFC drawings.
03
All equipment located and correctly tagged in accordance with latest AFC drawings.02
General01
Output /RemarksPLOKNADescriptionItem
Area:71E01Package:
71E - BOAT LANDINGSub System:71 - STRUCTURALSystem:
BOAT LANDINGDescription:MEPA-BL-7100ObjectID:
Inspection Test ReportM20A Area Completion
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:335707679
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:335707679
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 196/4
Area:71E01Package:
71E - BOAT LANDINGSub System:71 - STRUCTURALSystem:
BOAT LANDINGDescription:MEPA-BL-7100ObjectID:
Inspection Test ReportM20A Area Completion
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:335707679
All Fireproofing clean and undamaged86
Fireproofing material finish conforms to agreed sample (where applicable)85
Fireproofing materials applied according to specification84
All paintwork clean and undamaged83
Finish paint colour conforms to specification82
All remedial work completed and accepted81
All specified adhesion tests completed and accepted80
Correct paint system applied according to specification and in accordance with supplierrequirements
79
Painting , Coatings and Fireproofing78
Hose reel rewind satisfactorily.77
Hose nozzle operation and shut-off checked.76
Hose free from damage and kinks.75
Hose reel runs out correctly.74
Main valves checked for ease of operation and shut-off.73
Stop valves checked for ease of operation and shut-off.72
Operation instructions fitted and legible.71
Cabinet doors secure.70
Hose reel correctly installed to manufacturers instructions.69
Hose reels68
Escape route / safety signs not obstructed and legible.67
Escape route / safety signs securely fixed in position.66
Escape route / safety signs, location correct as per Loss Control layout drawings.65
Direction of escape correct and clearly marked.64
Escape routes painted to specification and non-skid surface complete.63
Escape routes not obstructed.62
Escape route in accordance with Loss Control layout drawings.61
Escape Routes and Platform Signs60
Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.
59
Insulation materials do not obstruct operation of access man-ways.58
All data plates and tag numbers are visible.57
All equipment nozzles and instruments are clear of the insulation material and jacketing.56
Jacketing, type, application and condition conforms to latest AFC specifications.55
Insulation, thickness and material in accordance with latest AFC specifications.54
Equipment53
Mastic and water seals correctly installed52
Cable and piping penetrations completed and sealed in accordance with the latest AFCspecifications.
51
Fixing materials, including screws and banding, are of the correct type and installed inaccordance with the latest AFC specification.
50
Jacketing thickness and material in accordance with the latest AFC specifications.49
Insulation, thickness and material in accordance with the latest AFC specifications.48
Snap on boxes fitted at all required locations in accordance with the specifications.47
Access to all instruments, including in-line instruments unobstructed by insulationmaterials.
46
No attachment points on the piping system are covered by insulation material.45
Limits of insulation in accordance with the latest AFC P&ID, drawings and specifications.44
Piping Systems43
System and temporary dust blinds are visible.42
Identification labels and arrows installed.41
Check that where required 'snap on' boxes are fitted in accordance with the latest AFCspecification.
40
Insulation materials do not obstruct operation of access man-ways.39
Data plates and tag numbers are visible.38
Jacketing, type, application and condition conforms to requirements.37
Insulation, thickness and material in accordance with the latest AFC specifications.36
Limits of insulation with the latest AFC D & ID drawings and specifications.35
HVAC Ductwork34
Galvanised steel lining fixed to protect wall and deck-head insulation as specified bylatest AFC shop drawings and Vendor details.
33
All cable penetrations confirm to the requirements of the penetration dossier for firerating.
32
All piping and ducting penetrations in accordance with the requirements of the latest AFCpenetration dossier for fire rating.
31
Mesh of correct type has been installed according to the latest AFC specification.30
Insulating material and thickness in accordance with the latest AFC specification. Vapourbarriers installed where required.
29
Pins installed, where applicable, in accordance with latest AFC specifications.28
Walls and Ceilings27
Confirm all cable ladder are fully covered (if applicable)26
Confirm cable dressing is complete25
Confirm all transits are complete and blocked.24
Confirm all transits are packed in accordance with the transit schedule23
Confirm all transit frames are installed correctly22
Confirm all dissimilar metal insulators are installed.21
Confirm all earth bonding is complete20
Confirm all cables are clipped with permanent fixings19
Confirm all cable racks are identified18
Confirm all supports and fixings are correct and complete17
Confirm all cable trays and racks are installed in accordance with routing and detaildrawings
16
Electrical Cable Racks, ladder, transit and cover15
Area is clean and free of all debris.14
Information signs installed.13
Furniture: All furniture of correct colour and placed in accordance with drawings, alldrawers/locker doors open/shut, all locks function. All spare keys taped securely adjacentto respective locks.
12
All doors and windows free from damage and installed correctly in accordance with latestAFC drawings.
11
Suspended floors correct and un-damaged.10
Water bunds turned up around walls in wet areas.09
Floors lay to drain evenly to outlets, with no puddling or flat spots.08
Floor coating: Floor screed placed according to specification, carpet or tiles of correctcolour, embedding of carpet or tiles is firm without any gaps or damage.
07
Pre-fabricated firewalls/louvers installed to specification with sealed joints, plumb andlined, without damage.
06
Wall and ceiling linings: Insulation and vapour barrier placed and undamaged, liningcolour correct, ceiling and wall panels correctly trimmed and free from damage.
05
All equipment performs its specified function.04
All equipment free from damage installed and correctly secured in accordance with latestAFC drawings.
03
All equipment located and correctly tagged in accordance with latest AFC drawings.02
General01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:335707679
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 197/4
Area:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
-Description:MEPA-GB-5110ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1673674738
Service: Service Water Pump P-5110RUN/STOP STATUS
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1673674738
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 198/4
Cellar DeckArea:80E02Package:
80E - FIRE ZONE 4Sub System:80 - FIRE & GAS DETECTIONSystem:
IR - POINT TYPE GAS DETECTOR - Cellar DeckDescription:MEPA-GD-8026ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:497631589
Service: Gas Detector at Cellar Deck
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:497631589
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 199/4
Cellar DeckArea:80E02Package:
80E - FIRE ZONE 4Sub System:80 - FIRE & GAS DETECTIONSystem:
IR - POINT TYPE GAS DETECTOR - Cellar DeckDescription:MEPA-GD-8027ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1571373406
Service: Gas Detector at Cellar Deck
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1571373406
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 200/4
Area:32A01Package:
32A - A-3200 CONDENSATE ALLOCATIONMETERING
Sub System:32 - CONDENSATE METERINGSystem:
LIMIT SWITCH CLOSE - MEPA-XV-3210 - AllocationCondensate Meter Duty Run
Description:MEPA-GSC-3210ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:985257494
Service: MEPA-XV-3210 - AllocationCondensate Meter Duty Run
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:985257494
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 201/4
Area:32A01Package:
32A - A-3200 CONDENSATE ALLOCATIONMETERING
Sub System:32 - CONDENSATE METERINGSystem:
LIMIT SWITCH CLOSE - MEPAXV-3211 - AllocationCondensate Meter Duty Run
Description:MEPA-GSC-3211ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:989713942
Service: MEPA-XV-3211 - AllocationCondensate Meter Duty Run
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:989713942
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 202/4
Area:32A01Package:
32A - A-3200 CONDENSATE ALLOCATIONMETERING
Sub System:32 - CONDENSATE METERINGSystem:
LIMIT SWITCH CLOSE - MEPA-XV-3220-AllocationCondensate Meter Standby Run
Description:MEPA-GSC-3220ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:985257782
Service: MEPA-XV-3220-AllocationCondensate Meter Standby Run
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:985257782
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 203/4
Area:32A01Package:
32A - A-3200 CONDENSATE ALLOCATIONMETERING
Sub System:32 - CONDENSATE METERINGSystem:
LIMIT SWITCH CLOSE - MEPA-XV-3221-AllocationCondensate Meter Standby Run
Description:MEPA-GSC-3221ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:989714230
Service: MEPA-XV-3221-AllocationCondensate Meter Standby Run
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:989714230
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 204/4
Area:32A01Package:
32A - A-3200 CONDENSATE ALLOCATIONMETERING
Sub System:32 - CONDENSATE METERINGSystem:
LIMIT SWITCH OPEN - MEPA-XV-3210 - AllocationCondensate Meter Duty Run
Description:MEPA-GSO-3210ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:28956182
Service: MEPA-XV-3210 - AllocationCondensate Meter Duty Run
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:28956182
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 205/4
Area:32A01Package:
32A - A-3200 CONDENSATE ALLOCATIONMETERING
Sub System:32 - CONDENSATE METERINGSystem:
LIMIT SWITCH OPEN - MEPA-XV-3211 - AllocationCondensate Meter Duty Run
Description:MEPA-GSO-3211ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:33412630
Service: MEPA-XV-3211 - AllocationCondensate Meter Duty Run
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:33412630
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 206/4
Area:32A01Package:
32A - A-3200 CONDENSATE ALLOCATIONMETERING
Sub System:32 - CONDENSATE METERINGSystem:
LIMIT SWITCH OPEN - MEPA-XV-3220-AllocationCondensate Meter Standby Run
Description:MEPA-GSO-3220ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:28956470
Service: MEPA-XV-3220-AllocationCondensate Meter Standby Run
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:28956470
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 207/4
Area:32A01Package:
32A - A-3200 CONDENSATE ALLOCATIONMETERING
Sub System:32 - CONDENSATE METERINGSystem:
LIMIT SWITCH OPEN - MEPA-XV-3222-AllocationCondensate Meter Standby Run
Description:MEPA-GSO-3221ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:33412918
Service: MEPA-XV-3222-AllocationCondensate Meter Standby Run
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:33412918
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 208/4
Area:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0110Gas Flowline
Description:MEPA-HCV-0111ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-874538855
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-874538855
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 209/4
Area:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0110Gas Flowline
Description:MEPA-HCV-0111ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1948280700
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1948280700
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 210/4
Area:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0120Gas Flowline
Description:MEPA-HCV-0121ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-874538567
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-874538567
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 211/4
Area:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0120Gas Flowline
Description:MEPA-HCV-0121ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1948280412
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1948280412
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 212/4
Area:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0130Gas Flowline
Description:MEPA-HCV-0131ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-874537239
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-874537239
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 213/4
Area:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0130Gas Flowline
Description:MEPA-HCV-0131ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1948279052
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1948279052
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 214/4
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Gas Wellhead MEPA-WH-0140 Gas FlowlineDescription:MEPA-HCV-0141ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-874537207
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-874537207
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 215/4
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Gas Wellhead MEPA-WH-0140 Gas FlowlineDescription:MEPA-HCV-0141ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1948279020
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1948279020
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 216/4
Area:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Gas Wellhead MEPA-WH-0150 Gas FlowlineDescription:MEPA-HCV-0151ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-874537943
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-874537943
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 217/4
Area:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Gas Wellhead MEPA-WH-0150 Gas FlowlineDescription:MEPA-HCV-0151ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1948279756
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1948279756
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 218/4
Area:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Gas Wellhead MEPA-WH-0160 Gas FlowlineDescription:MEPA-HCV-0161ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-874537639
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-874537639
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 219/4
Area:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Gas Wellhead MEPA-WH-0160 Gas FlowlineDescription:MEPA-HCV-0161ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1948279484
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1948279484
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 220/4
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0170Gas Flowline
Description:MEPA-HCV-0171ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-874540151
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-874540151
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 221/4
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0170Gas Flowline
Description:MEPA-HCV-0171ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1948281964
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1948281964
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 222/4
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0180Gas Flowline
Description:MEPA-HCV-0181ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-874540887
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-874540887
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 223/4
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0180Gas Flowline
Description:MEPA-HCV-0181ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1948282700
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1948282700
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 224/4
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0190Gas Flowline
Description:MEPA-HCV-0191ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-874540599
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-874540599
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922). 225/4
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0190Gas Flowline
Description:MEPA-HCV-0191ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1948282412
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1948282412
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 226/4
Area:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0200Gas Flowline
Description:MEPA-HCV-0201ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-889218375
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-889218375
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 227/4
Area:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0200Gas Flowline
Description:MEPA-HCV-0201ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1962960220
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1962960220
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 228/4
Area:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0210Gas Flowline
Description:MEPA-HCV-0211ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-889218919
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-889218919
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 229/4
Area:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0210Gas Flowline
Description:MEPA-HCV-0211ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1962960764
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1962960764
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 230/4
Area:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0220Gas Flowline
Description:MEPA-HCV-0221ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-889218631
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-889218631
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 231/4
Area:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
CHOKE VALVE - Gas Wellhead MEPA-WH-0220Gas Flowline
Description:MEPA-HCV-0221ObjectID:
Inspection Test ReportI03A Valve and Ancillaries
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1962960476
02.33 - Correct to Data Sheet
MISCELLANEOUS ACCESSORIES02.32
02.31 - Range
02.30 - Model / type : ______________________
02.29 - Serial No : ______________________
FILTER/REGULATOR02.28
02.27 - Output range
02.26 - Signal range
02.25 - Model / type : ______________________
02.24 - Serial No : ______________________
I/P CONVERTER02.23
02.22 - Output range
02.21 - Signal range
02.20 - Model / type : ______________________
02.19 - Serial No : ______________________
POSITIONER02.18
02.17 - Hand wheel operation correct
02.16 - Failure action
02.15 - Input range
02.14 - Model / type : ______________________
02.13 - Serial No : ______________________
ACTUATOR02.12
02.11 - Leakage class
02.10 - Trim material correct
02.09 - Body material
02.08 - Material certification correct
02.07 - Service
02.06 - Flange type
02.05 - Rating
02.04 - Size
02.03 - Model / type : ______________________
02.02 - Serial No : ______________________
VALVE02.01
All equipment to be checked for correctness against current revision of data sheet for:Manufacturer, Type, Model No. and Serial No.
02
All equipment free from damage and installed correctly01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1962960476
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 232/4
Area:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0111 - GasWellhead MEPA-WH-0110
Description:MEPA-HY-0111ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:478137062
Service: For MEPA-HCV-0111 - Gas WellheadMEPA-WH-0110
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:478137062
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 233/4
Area:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0111 - GasWellhead MEPA-WH-0110
Description:MEPA-HY-0111ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:125821927
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:125821927
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 234/4
Area:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0121 - GasWellhead MEPA-WH-0120
Description:MEPA-HY-0121ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:477842150
Service: For MEPA-HCV-0121 - Gas WellheadMEPA-WH-0120
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:477842150
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 235/4
Area:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0121 - GasWellhead MEPA-WH-0120
Description:MEPA-HY-0121ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:125527015
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:125527015
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 236/4
Area:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0131 - GasWellhead MEPA-WH-0130
Description:MEPA-HY-0131ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:476449510
Service: For MEPA-HCV-0131 - Gas WellheadMEPA-WH-0130
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:476449510
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 237/4
Area:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0131 - GasWellhead MEPA-WH-0130
Description:MEPA-HY-0131ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:124134375
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:124134375
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 238/4
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0141 - GasWellhead MEPA-WH-0140
Description:MEPA-HY-0141ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:476154598
Service: For MEPA-HCV-0141 - Gas WellheadMEPA-WH-0140
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:476154598
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 239/4
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0141 - GasWellhead MEPA-WH-0140
Description:MEPA-HY-0141ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:123839463
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:123839463
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 240/4
Area:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0151 - GasWellhead MEPA-WH-0150
Description:MEPA-HY-0151ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:476908262
Service: For MEPA-HCV-0151 - Gas WellheadMEPA-WH-0150
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:476908262
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 241/4
Area:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0151 - GasWellhead MEPA-WH-0150
Description:MEPA-HY-0151ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:124593127
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:124593127
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 242/4
Area:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0161 - GasWellhead MEPA-WH-0160
Description:MEPA-HY-0161ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:476629734
Service: For MEPA-HCV-0161 - Gas WellheadMEPA-WH-0160
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:476629734
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 243/4
Area:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0161 - GasWellhead MEPA-WH-0160
Description:MEPA-HY-0161ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:124314599
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:124314599
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 244/4
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0171 - GasWellhead MEPA-WH-0170
Description:MEPA-HY-0171ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:475237094
Service: For MEPA-HCV-0171 - Gas WellheadMEPA-WH-0170
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:475237094
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 245/4
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0171 - GasWellhead MEPA-WH-0170
Description:MEPA-HY-0171ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:122921959
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:122921959
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 246/4
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0181 - GasWellhead MEPA-WH-0180
Description:MEPA-HY-0181ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:475990758
Service: For MEPA-HCV-0181 - Gas WellheadMEPA-WH-0180
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:475990758
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 247/4
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0181 - GasWellhead MEPA-WH-0180
Description:MEPA-HY-0181ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:123675623
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:123675623
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 248/4
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0191 - GasWellhead MEPA-WH-0190
Description:MEPA-HY-0191ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:475695846
Service: For MEPA-HCV-0191 - Gas WellheadMEPA-WH-0190
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:475695846
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 249/4
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0191 - GasWellhead MEPA-WH-0190
Description:MEPA-HY-0191ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:123380711
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:123380711
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 250/4
Area:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0201 - GasWellhead MEPA-WH-0200
Description:MEPA-HY-0201ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:477579970
Service: For MEPA-HCV-0201 - Gas WellheadMEPA-WH-0200
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:477579970
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 251/4
Area:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0201 - GasWellhead MEPA-WH-0200
Description:MEPA-HY-0201ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:125264835
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:125264835
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 252/4
Area:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0211 - GasWellhead MEPA-WH-0210
Description:MEPA-HY-0211ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:478137026
Service: For MEPA-HCV-0211 - Gas WellheadMEPA-WH-0210
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:478137026
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 253/4
Area:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0211 - GasWellhead MEPA-WH-0210
Description:MEPA-HY-0211ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:125821891
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:125821891
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 254/4
Area:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0221 - GasWellhead MEPA-WH-0220
Description:MEPA-HY-0221ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:477842114
Service: For MEPA-HCV-0221 - Gas WellheadMEPA-WH-0220
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:477842114
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 255/4
Area:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
I/P POSITIONER - For MEPA-HCV-0221 - GasWellhead MEPA-WH-0220
Description:MEPA-HY-0221ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:125526979
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:125526979
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 256/4
Area:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
LEVEL TRANSMITTER - OHD Caisson, A-6510 LevelDescription:MEPA-LT-6510ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1849458024
Service: OHD Caisson, A-6510 Level
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1849458024
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 257/4
Area:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
LEVEL TRANSMITTER - OHD Caisson, A-6510 LevelDescription:MEPA-LT-6510ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1698444904
Service: OHD Caisson, A-6510 Level
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1698444904
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 258/4
Area:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
LEVEL TRANSMITTER - OHD Caisson, A-6510 LevelDescription:MEPA-LT-6510ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-2117869415
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-2117869415
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 259/4
Area:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
LEVEL TRANSMITTER - OHD Caisson, A-6510 LevelDescription:MEPA-LT-6510ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1849439848
Service: OHD Caisson, A-6510 Level
SerialNo:Model/Type:Manufacturer:
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1849439848
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 260/4
Area:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
LEVEL TRANSMITTER - OHD Caisson, A-6510 LevelDescription:MEPA-LT-6510ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1849435240
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1849435240
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 261/4
Cellar DeckArea:42A01Package:
42A - A-4200 PRODUCED WATERSub System:42 - PRODUCED WATER TREATMENTSystem:
LEVEL TRANSMITTER - Degassing Vessel, V-4220Level Trip
Description:MEPA-LZT-4222ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-950454217
Service: Degassing Vessel, V-4220 Level Trip
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-950454217
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 262/4
Sub-Cellar DeckArea:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
SERVICE WATER PUMPDescription:MEPA-P-5110ObjectID:
Inspection Test ReportM05A Submersible Pump
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-991462951
Type: Motor TagSerialNo: 110600613Manufacturer: FLOWSERVE
Confirm external lubrication system installed correctly and filled (if fitted)14
Check motor cable is secure and undamaged.13
Check Hypochlorite dosing pipework is complete (if fitted)12
Check headroom for spool removal is sufficient.11
Check delivery head flange to caisson is secure.10
Check spider restraints are correct to drawing.09
Check riser spool stud bolts are to spec. and all fitted.08
Check riser spool gaskets are to spec. and all fitted.07
Check riser spool faces are undamaged and square.06
Check and record number of riser spools.05
Confirm suction strainer/mesh fitted. *W*04
Motor/pump assembly correct. *W*03
Check equipment is installed to manufacturer's instructions.02
Nameplate details are in accordance with data sheet.01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points______________________________________________________________________________________________________________________Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-991462951
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 263/4
Sub-Cellar DeckArea:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
SERVICE WATER PUMPDescription:MEPA-P-5110ObjectID:
Function Test ReportM04B Pumps
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1156020702
SerialNo: 110600613Model:Manufacturer: FLOWSERVE
Ensure motor direction is correct and clearly marked, and matches direction of rotation ofpump *W*
13
Cooling system complete.12
Hypochlorite dosing lines complete, (if fitted)11
Pump discharge is protected against over pressure.10
Air release valve fitted correctly09
All guards are fitted and secure.08
Coupling spacer is fitted.07
Check pump discharge is protected against over pressurisation.06
Check Lube/Seal oil systems for leaks.05
Lube/Seal oil systems filled with the correct grade of lubricant to full level. *W*04
Lube/Seal oil systems flushing complete.03
Preservation removed.02
Construction check list completed and no subsequent damage occurred.01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points______________________________________________________________________________________________________________________Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1156020702
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 264/4
Cellar DeckArea:62D14Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0110 Casing Blowdown
Description:MEPA-PG-6215ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-761019664
Service: Gas Wellhead MEPA-WH-0110 CasingBlowdown
SerialNo:Model/Type: BDT 21/AManufacturer: BADOTHERM
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-761019664
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 265/4
Cellar DeckArea:62D14Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0110 Casing Blowdown
Description:MEPA-PG-6215ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-761016080
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-761016080
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 266/4
Area:62D15Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0120 Casing Blowdown
Description:MEPA-PG-6225ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-760804880
Service: Gas Wellhead MEPA-WH-0120 CasingBlowdown
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-760804880
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 267/4
Area:62D15Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0120 Casing Blowdown
Description:MEPA-PG-6225ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-760790288
Service: Gas Wellhead MEPA-WH-0120 CasingBlowdown
SerialNo:Model/Type:Manufacturer:
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-760790288
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 268/4
Area:62D15Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0120 Casing Blowdown
Description:MEPA-PG-6225ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-760786704
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-760786704
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 269/4
Cellar DeckArea:62D16Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0130 Casing Blowdown
Description:MEPA-PG-6235ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-759561488
Service: Gas Wellhead MEPA-WH-0130 CasingBlowdown
SerialNo:Model/Type: ASI 316Manufacturer: BADOTHERM
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-759561488
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 270/4
Cellar DeckArea:62D16Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0130 Casing Blowdown
Description:MEPA-PG-6235ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-759557904
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-759557904
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 271/4
Cellar DeckArea:62D17Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0140 Casing Blowdown
Description:MEPA-PG-6245ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-759332112
Service: Gas Wellhead MEPA-WH-0140 CasingBlowdown
SerialNo:Model/Type: ASI 316Manufacturer: BADOTHERM
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-759332112
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 272/4
Cellar DeckArea:62D17Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0140 Casing Blowdown
Description:MEPA-PG-6245ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-759328528
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-759328528
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 273/4
Cellar DeckArea:62D18Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0150 Casing Blowdown
Description:MEPA-PG-6255ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-760151312
Service: Gas Wellhead MEPA-WH-0150 CasingBlowdown
SerialNo:Model/Type: BDT21/AManufacturer: BADOTHERM
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-760151312
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 274/4
Cellar DeckArea:62D18Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0150 Casing Blowdown
Description:MEPA-PG-6255ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-760147728
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-760147728
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 275/4
Cellar DeckArea:62D19Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0160 Casing Blowdown
Description:MEPA-PG-6265ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-759905552
Service: Gas Wellhead MEPA-WH-0160 CasingBlowdown
SerialNo:Model/Type: ASI 316Manufacturer: BADOTHERM
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-759905552
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 276/4
Cellar DeckArea:62D19Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0160 Casing Blowdown
Description:MEPA-PG-6265ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-759901968
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-759901968
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 277/4
Cellar DeckArea:62D20Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0170 Casing Blowdown
Description:MEPA-PG-6275ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-762346768
Service: Gas Wellhead MEPA-WH-0170 CasingBlowdown
SerialNo:Model/Type: BDT21/AManufacturer: BADOTHERM
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-762346768
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 278/4
Cellar DeckArea:62D20Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0170 Casing Blowdown
Description:MEPA-PG-6275ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-762343184
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-762343184
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 279/4
Cellar DeckArea:62D22Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0190 Casing Blowdown
Description:MEPA-PG-6295ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-762936592
Service: Gas Wellhead MEPA-WH-0190 CasingBlowdown
SerialNo:Model/Type: BDT21/AManufacturer: BADOTHERM
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-762936592
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 280/4
Cellar DeckArea:62D22Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0190 Casing Blowdown
Description:MEPA-PG-6295ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-762933008
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-762933008
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 281/4
Area:62D23Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGEDescription:MEPA-PG-6305ObjectID:
Inspection Test ReportI05A Instrument Calibration Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-760542950
Service: Gas Wellhead MEPA-WH-0200 CasingBlowdown
SerialNo:Model/Type:Manufacturer:
Valve Stroke Time in accordance with data sheet06
Miscellaneous equipment operating correctly05
I/P & Positioner operating correctly04
Solenoid Valve operating correctly03
Position transmitter/switches (open/closed) operating correctly.02
Calibrate Instrument as per Data Sheet (refer to table1)01
Output /RemarksPLOKNADescriptionItem
Table 1
_____________________________________________________________________________________________________________________
Record Valve Stroke Time:
Remarks:
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-760542950
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 282/4
Area:62D23Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGEDescription:MEPA-PG-6305ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-760528358
Service: Gas Wellhead MEPA-WH-0200 CasingBlowdown
SerialNo:Model/Type:Manufacturer:
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-760528358
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 283/4
Area:62D23Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGEDescription:MEPA-PG-6305ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-760524774
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-760524774
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 284/4
Cellar DeckArea:62D21Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0180 Casing Blowdown
Description:MEPA-PG-6285ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-763165968
Service: Gas Wellhead MEPA-WH-0180 CasingBlowdown
SerialNo:Model/Type: BDT 21/AManufacturer: BADOTHERM
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-763165968
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 285/4
Cellar DeckArea:62D21Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGE - Gas Wellhead MEPA-WH-0180 Casing Blowdown
Description:MEPA-PG-6285ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-763162384
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-763162384
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 286/4
Cellar DeckArea:62D24Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGEDescription:MEPA-PG-6315ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-761019878
Service: Gas Wellhead MEPA-WH-0210 CasingBlowdown
SerialNo:Model/Type: BDT21/AManufacturer: BADOTHERM
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-761019878
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 287/4
Cellar DeckArea:62D24Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGEDescription:MEPA-PG-6315ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-761016294
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-761016294
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 288/4
Cellar DeckArea:62D25Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGEDescription:MEPA-PG-6325ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-760790502
Service: Gas Wellhead MEPA-WH-0220 CasingBlowdown
SerialNo:Model/Type: BDT21/AManufacturer: BADOTHERM
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-760790502
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 289/4
Cellar DeckArea:62D25Package:
62D - CASING BLOWDOWNSub System:62 - HP FLARE SYSTEMSystem:
PRESSURE GAUGEDescription:MEPA-PG-6325ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-760786918
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-760786918
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 290/4
Area:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
Motor - Service Water Pump MotorDescription:MEPA-PM-5110ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-2104628081
SerialNo:Model/Type:Manufacturer:
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-2104628081
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 291/4
Area:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
Motor - Service Water Pump MotorDescription:MEPA-PM-5110ObjectID:
Inspection Test ReportE08A Electric Motor
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1836196210
SerialNo:Model/Type:Manufacturer:
Where applicable visually inspect and confirm no damage to local devices:i.e. Temperature indicators/detectors and Vibration switches
17
Reconnect motor power and heater cables as per connection diagram16
Disconnect heater cable test and record insulation resistance valueHeater voltage Test voltage<=240V 500V
Values: Element to earth:__________ ohm
15
Disconnect motor cables test and record insulation resistance valueMotor voltage Test voltage<=1Kv 500VValues:L1-E:__________ohm L2-E:__________ohm L3-E:__________ohmFor motors >= 1kV See Vendor Recommendations
14
Check paintwork is complete13
Check bolts are of correct type and that no bolts are missing12
Confirm all guards and covers are installed11
Confirm equipment mountings are secure and grouting is complete10
Check unused cable entries have been plugged correctly09
For motors >= 5.5 kW check anti-condensate heater, confirm element voltage rating iscorrect, i.e.240V
08
Verify terminal box gasket and seals are present and have been installed correctly07
Check all cable connections/glands are tight and cables are identified06
Confirm motor shaft rotates freely05
Motor and control station are earthed according to drawings04
Confirm all equipment is tagged in accordance with specification03
Installation conforms to hazardous area classification02
Installation as per AFC Drawing and data sheet01
Output /RemarksPLOKNADescriptionItem
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1836196210
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 292/4
Notes:
1. All switching and testing of equipment is to be carried out in accordance with the BDEWC / Client electrical safety rules and operating procedures
2. All relevant ITR’s and FTR’s to be complete prior to commissioning3. All test durations and acceptable values to be as per vendor recommendations4. All directly connected motors to be commissioned in conjunction with vendor
Area:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
Motor - Service Water Pump MotorDescription:MEPA-PM-5110ObjectID:
Function Test ReportE08B Electric Motor
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1718755698
Manufacturer:
For motorised valves confirm operation of limit switches and indicators17
In conjunction with mechanical and process run motor "on load" and record line amps(refer to Table 2)L1: ______ A L2: ______ A L3: ______ A
16
Mechanicals to reinstate motor and driven device coupling (M06B item 14)15
Uncoupled Motor RunNoise checks, shall be checked at a height if 1mtr above ground level and at both 3 mtrsand 6 mtrs from the drive, in accordance with relevant standards and codes or practice.
Perform no load run and record line amps (refer to Table 1)L1: ______ A L2: ______ A L3: ______ A
13
"Bump" motor and confirm correct direction of rotation, if a direction change is requiredthis is to be affected where practical within the motor terminal box
12
Confirm functionality of local controls and emergency stop11
Remove isolation from motor feeder10
If applicable test RTD's and vibration switches09
Confirm motor is uncoupled from driven device and reinstate motor guard08
Confirm anti condensate heater is functioning07
Reconnect power and heater cables as per connection diagram, for HV motors ensuretorque settings are as per vendor requirements
06
Disconnect heater cable, test and record insulation resistance value
Heater voltage Test voltage<=240V 500VElement to earth: ___________(ohm)
05
Measure resistance between phasesL1-L2: ______(ohm) L1-L3: ______(ohm) L2-L3: ______(ohm)04
Check cable is at zero potential, disconnect motor cables, test and record motorinsulation resistance value
Motor voltage Test voltage<=1kV 500V
Record values:L1-E: ______(ohm) L2-E: ______(ohm) L3-E: ______(ohm)
For motors > 1kV See Vendor Recommendations
03
Confirm motor feeder cubicle is isolated and locked out02
Erect safety barriers and warning signs in and around test areas01
Output /RemarksPLOKNADescriptionItem
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1718755698
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 293/4
Area:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
Motor - Service Water Pump MotorDescription:MEPA-PM-5110ObjectID:
Function Test ReportE08B Electric Motor
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1718755698
Table 1 - Uncoupled Motor Run
Table 2 - Coupled Motor Run
______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1718755698
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 294/4
Cellar DeckArea:01B02Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0111 Open/ClosedStatus
Description:MEPA-PSL-0111ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1994257559
Service: SCSSV-0111 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1994257559
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 295/4
Cellar DeckArea:01B02Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0112 Open/ClosedStatus
Description:MEPA-PSL-0112ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1996092567
Service: SSV-0112 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1996092567
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 296/4
Cellar DeckArea:01B02Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0113 Open/ClosedStatus
Description:MEPA-PSL-0113ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1981019287
Service: WV-0113 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1981019287
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 297/4
Cellar DeckArea:01C02Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0121 Open/ClosedStatus
Description:MEPA-PSL-0121ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1994257847
Service: SCSSV-0121 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1994257847
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 298/4
Cellar DeckArea:01C02Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0122 Open/ClosedStatus
Description:MEPA-PSL-0122ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1996092855
Service: SSV-0122 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1996092855
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 299/4
Cellar DeckArea:01C02Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0123 Open/ClosedStatus
Description:MEPA-PSL-0123ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1981019575
Service: WV-0123 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1981019575
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 300/4
Cellar DeckArea:01D02Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0131 Open/ClosedStatus
Description:MEPA-PSL-0131ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1994257127
Service: SCSSV-0131 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1994257127
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 301/4
Cellar DeckArea:01D02Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0132 Open/ClosedStatus
Description:MEPA-PSL-0132ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1996092135
Service: SSV-0132 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1996092135
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 302/4
Cellar DeckArea:01D02Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0133 Open/ClosedStatus
Description:MEPA-PSL-0133ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1981018855
Service: WV-0133 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1981018855
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 303/4
Cellar DeckArea:01E02Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0141 Open/ClosedStatus
Description:MEPA-PSL-0141ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1994257159
Service: SCSSV-0141 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1994257159
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 304/4
Cellar DeckArea:01E02Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0142 Open/ClosedStatus
Description:MEPA-PSL-0142ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1996092167
Service: SSV-0142 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1996092167
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 305/4
Cellar DeckArea:01E02Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0143 Open/ClosedStatus
Description:MEPA-PSL-0143ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1981018887
Service: WV-0143 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1981018887
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 306/4
Cellar DeckArea:01F02Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0151 Open/ClosedStatus
Description:MEPA-PSL-0151ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1994256423
Service: SCSSV-0151 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1994256423
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 307/4
Cellar DeckArea:01F02Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0152 Open/ClosedStatus
Description:MEPA-PSL-0152ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1996091431
Service: SSV-0152 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1996091431
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 308/4
Cellar DeckArea:01F02Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0153 Open/ClosedStatus
Description:MEPA-PSL-0153ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1981018151
Service: WV-0153 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1981018151
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 309/4
Cellar DeckArea:01G02Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0161 Open/ClosedStatus
Description:MEPA-PSL-0161ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1994256727
Service: SCSSV-0161 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1994256727
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 310/4
Cellar DeckArea:01G02Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0162 Open/ClosedStatus
Description:MEPA-PSL-0162ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1996091735
Service: SSV-0162 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1996091735
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 311/4
Cellar DeckArea:01G02Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0163 Open/ClosedStatus
Description:MEPA-PSL-0163ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1981018455
Service: WV-0163 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1981018455
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 312/4
Cellar DeckArea:01H02Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0171 Open/ClosedStatus
Description:MEPA-PSL-0171ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1994260359
Service: SCSSV-0171 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1994260359
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 313/4
Cellar DeckArea:01H02Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0172 Open/ClosedStatus
Description:MEPA-PSL-0172ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1996095367
Service: SSV-0172 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1996095367
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 314/4
Cellar DeckArea:01H02Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0173 Open/ClosedStatus
Description:MEPA-PSL-0173ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1981022087
Service: WV-0173 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1981022087
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 315/4
Cellar DeckArea:01I02Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0181 Open/ClosedStatus
Description:MEPA-PSL-0181ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1994259623
Service: SCSSV-0181 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1994259623
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 316/4
Cellar DeckArea:01I02Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0182 Open/ClosedStatus
Description:MEPA-PSL-0182ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1996094631
Service: SSV-0182 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1996094631
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 317/4
Cellar DeckArea:01I02Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0183 Open/ClosedStatus
Description:MEPA-PSL-0183ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1981021351
Service: WV-0183 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1981021351
Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922). 318/4
Cellar DeckArea:01J02Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0191 Open/ClosedStatus
Description:MEPA-PSL-0191ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1994259911
Service: SCSSV-0191 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1994259911
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 319/4
Cellar DeckArea:01J02Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0192 Open/ClosedStatus
Description:MEPA-PSL-0192ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1996094919
Service: SSV-0192 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1996094919
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 320/4
Cellar DeckArea:01J02Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0193 Open/ClosedStatus
Description:MEPA-PSL-0193ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1981021639
Service: WV-0193 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1981021639
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 321/4
Cellar DeckArea:01K02Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0201 Open/ClosedStatus
Description:MEPA-PSL-0201ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2013132471
Service: SCSSV-0201 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:2013132471
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 322/4
Cellar DeckArea:01K02Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0202 Open/ClosedStatus
Description:MEPA-PSL-0202ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2010773175
Service: SSV-0202 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:2010773175
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 323/4
Cellar DeckArea:01K02Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0203 Open/ClosedStatus
Description:MEPA-PSL-0203ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1999894199
Service: WV-0203 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1999894199
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 324/4
Cellar DeckArea:01L02Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0211 Open/ClosedStatus
Description:MEPA-PSL-0211ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2013131927
Service: SCSSV-0211 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:2013131927
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 325/4
Cellar DeckArea:01L02Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0212 Open/ClosedStatus
Description:MEPA-PSL-0212ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2010772631
Service: SSV-0212 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:2010772631
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 326/4
Cellar DeckArea:01L02Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0213 Open/ClosedStatus
Description:MEPA-PSL-0213ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1999893655
Service: WV-0213 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1999893655
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 327/4
Cellar DeckArea:01M02Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SCSSV-0221 Open/ClosedStatus
Description:MEPA-PSL-0221ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2013132215
Service: SCSSV-0221 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:2013132215
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 328/4
Cellar DeckArea:01M02Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - SSV-0222 status Open/CloseStatus
Description:MEPA-PSL-0222ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2010772919
Service: SSV-0222 status Open/Close Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:2010772919
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 329/4
Cellar DeckArea:01M02Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE SWITCH - WV-0223 Open/ClosedStatus
Description:MEPA-PSL-0223ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1999893943
Service: WV-0223 Open/Closed Status
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1999893943
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 330/4
CELLAR DECKArea:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0111)
Description:MEPA-PT-0114ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1499449624
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0111)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1499449624
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 331/4
CELLAR DECKArea:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0111)
Description:MEPA-PT-0114ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1113579545
SerialNo: 91H913547Model/Type: EJX530AManufacturer: YOKOGAWA
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1113579545
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 332/4
CELLAR DECKArea:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0111)
Description:MEPA-PT-0114ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1382009112
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0111)
SerialNo: 91H913547Model/Type: EJX530AManufacturer: YOKOGAWA
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1382009112
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 333/4
CELLAR DECKArea:01B03Package:
01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0111)
Description:MEPA-PT-0114ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1382013720
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1382013720
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 334/4
CELLAR DECKArea:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0121)
Description:MEPA-PT-0124ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1499154712
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0121)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1499154712
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 335/4
CELLAR DECKArea:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0121)
Description:MEPA-PT-0124ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1113284633
SerialNo: 11294827Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1113284633
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 336/4
CELLAR DECKArea:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0121)
Description:MEPA-PT-0124ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1381714200
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0121)
SerialNo: 11294827Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1381714200
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 337/4
CELLAR DECKArea:01C03Package:
01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0121)
Description:MEPA-PT-0124ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1381718808
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1381718808
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 338/4
CELLAR DECKArea:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0131)
Description:MEPA-PT-0134ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1497762072
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0131)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1497762072
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 339/4
CELLAR DECKArea:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0131)
Description:MEPA-PT-0134ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1111891993
SerialNo: 91H913549Model/Type: EJX530AManufacturer: YOKOGAWA
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1111891993
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 340/4
CELLAR DECKArea:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0131)
Description:MEPA-PT-0134ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1380321560
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0131)
SerialNo: 91H913549Model/Type: EJX530AManufacturer: YOKOGAWA
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1380321560
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 341/4
CELLAR DECKArea:01D03Package:
01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0131)
Description:MEPA-PT-0134ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1380326168
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1380326168
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 342/4
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0141)
Description:MEPA-PT-0144ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1497467160
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0141)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1497467160
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 343/4
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0141)
Description:MEPA-PT-0144ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1111597081
SerialNo: 91L 911840-139Model/Type: EJA 530 AManufacturer: YOKOGAWA
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1111597081
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 344/4
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0141)
Description:MEPA-PT-0144ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1380026648
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0141)
SerialNo: 91L 911840-139Model/Type: EJA 530 AManufacturer: YOKOGAWA
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1380026648
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 345/4
Area:01E03Package:
01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0141)
Description:MEPA-PT-0144ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1380031256
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1380031256
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 346/4
Cellar DeckArea:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0151)
Description:MEPA-PT-0154ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1498220824
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0151)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1498220824
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 347/4
Cellar DeckArea:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0151)
Description:MEPA-PT-0154ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1112350745
SerialNo:Model/Type: EJA 530 AManufacturer: YKOGAWA
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1112350745
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 348/4
Cellar DeckArea:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0151)
Description:MEPA-PT-0154ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1380780312
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0151)
SerialNo:Model/Type: EJA 530 AManufacturer: YKOGAWA
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1380780312
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 349/4
Cellar DeckArea:01F03Package:
01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0151)
Description:MEPA-PT-0154ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1380784920
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1380784920
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 350/4
Cellar DeckArea:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0161)
Description:MEPA-PT-0164ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1497942296
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0161)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1497942296
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 351/4
Cellar DeckArea:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0161)
Description:MEPA-PT-0164ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1112072217
SerialNo: 91L911 841-139Model/Type: EJA 530 AManufacturer: YOKOGAWA
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1112072217
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 352/4
Cellar DeckArea:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0161)
Description:MEPA-PT-0164ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1380501784
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0161)
SerialNo: 91L911 841-139Model/Type: EJA 530 AManufacturer: YOKOGAWA
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1380501784
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 353/4
Cellar DeckArea:01G03Package:
01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0161)
Description:MEPA-PT-0164ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1380506392
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1380506392
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 354/4
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0171)
Description:MEPA-PT-0174ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1500743960
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0171)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1500743960
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 355/4
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0171)
Description:MEPA-PT-0174ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1114873881
SerialNo: 91L911838 138Model/Type: EJA 530AManufacturer: YOKOGAWA
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1114873881
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 356/4
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0171)
Description:MEPA-PT-0174ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1383303448
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0171)
SerialNo: 91L911838 138Model/Type: EJA 530AManufacturer: YOKOGAWA
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1383303448
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 357/4
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0171)
Description:MEPA-PT-0174ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1383308056
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1383308056
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 358/4
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0181)
Description:MEPA-PT-0184ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1501497624
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0181)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1501497624
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 359/4
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0181)
Description:MEPA-PT-0184ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1115627545
SerialNo:Model/Type: EJA 530 AManufacturer: YOKOGAWA
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1115627545
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 360/4
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0181)
Description:MEPA-PT-0184ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1384057112
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0181)
SerialNo:Model/Type: EJA 530 AManufacturer: YOKOGAWA
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1384057112
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 361/4
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0181)
Description:MEPA-PT-0184ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1384061720
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1384061720
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 362/4
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0191)
Description:MEPA-PT-0194ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1501202712
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0191)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1501202712
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 363/4
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0191)
Description:MEPA-PT-0194ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1115332633
SerialNo: 91L911839-138Model/Type: EJA 530AManufacturer: YOKOGAWA
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1115332633
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 364/4
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0191)
Description:MEPA-PT-0194ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1383762200
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0191)
SerialNo: 91L911839-138Model/Type: EJA 530AManufacturer: YOKOGAWA
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1383762200
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 365/4
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0191)
Description:MEPA-PT-0194ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1383766808
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1383766808
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 366/4
CELLAR DECKArea:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0201)
Description:MEPA-PT-0204ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1498892604
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0201)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1498892604
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 367/4
CELLAR DECKArea:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0201)
Description:MEPA-PT-0204ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1113022525
SerialNo: 11294828Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1113022525
Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922). 368/4
CELLAR DECKArea:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0201)
Description:MEPA-PT-0204ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1381452092
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0201)
SerialNo: 11294828Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1381452092
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 369/4
CELLAR DECKArea:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0201)
Description:MEPA-PT-0204ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1381456700
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1381456700
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 370/4
CELLAR DECKArea:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0211)
Description:MEPA-PT-0214ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1499449660
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0211)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1499449660
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 371/4
CELLAR DECKArea:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0211)
Description:MEPA-PT-0214ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1113579581
SerialNo: 11294829Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1113579581
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 372/4
CELLAR DECKArea:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0211)
Description:MEPA-PT-0214ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1382009148
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0211)
SerialNo: 11294829Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1382009148
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 373/4
CELLAR DECKArea:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0211)
Description:MEPA-PT-0214ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1382013756
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1382013756
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 374/4
CELLAR DECKArea:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0221)
Description:MEPA-PT-0224ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1499154748
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0221)
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1499154748
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 375/4
CELLAR DECKArea:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0221)
Description:MEPA-PT-0224ObjectID:
Inspection Test ReportE17A Certified Equipment
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1113284669
SerialNo: 11294830Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO
Equipment Certification No:_____________________________13
Ensure all electrical connections are tight12
Check earthing conforms to design requirement11
Clean all blind holes of dirt and grease prior to assembly.10
Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly.09
Ensure no build up of dirt or corrosion on flame paths.08
Apparatus is not damaged and has no unauthorised modifications.07
Apparatus is clean and corrosion free.06
Enclosure has manufacturer's data identification label attached.05
Enclosure has Certifying Authority label attached.04
Check glands have IP sealing washer fitted and are installed in accordance with vendorspecification
03
Check equipment is as per data sheet02
Equipment is installed as per AFC Drawings and conforms to hazardous areaclassification
01
Output /RemarksPLOKNADescriptionItem
Notes:
1. All checks to be in accordance with IEC60079-0______________________________________________________________________________________________________________________
Remarks:
___________________________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1113284669
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 376/4
CELLAR DECKArea:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0221)
Description:MEPA-PT-0224ObjectID:
Inspection Test ReportI01A Inst Inspection
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1381714236
Service: At Chem. Inj. Ring Upstream of Chokevlv (HCV-0221)
SerialNo: 11294830Model/Type: IGP10-T52E5D-L1TManufacturer: FOXBORO
Equipment Certification No.:____________________________09
Hydraulic connections correct.08
Pneumatic connections correct.07
Electrical connections correct.06
Process connections correct.05
Instrument is not damaged.04
All materials are correct.03
Data plate details correct02
Instrument is checked correct against current revision of data sheet.01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1381714236
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 377/4
CELLAR DECKArea:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
PRESSURE TRANSMITTER - At Chem. Inj. RingUpstream of Choke vlv (HCV-0221)
Description:MEPA-PT-0224ObjectID:
Inspection Test ReportI02A Inst Installation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1381718844
03.05 - Confirm all impulse lines have been drained and cleaned
03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications.
03.03 - Confirm the following lines have been blown clear:
Pneumatic Lines Test Gas Lines
03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable:
Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines
03.01 - Prior to any testing taking place, confirm test equipment is within calibration period.
Instrument Line Pressure and Leak Test *W*03
02.11 - Labelling correct.
02.10 - Check all Tag No's.
02.09 - EOL resistor fitted and correctly rated where applicable.
02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly.
02.07 - Instrument earthed in accordance with project specification.
02.06 - Spare entries plugged correctly.
02.05 - In-Line equipment installed and supported correctly.
02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported.
02.03 - Vent lines are directed into a safe area.
02.02 - Instrument is accessible for maintenance and clear of obstructions.
02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration.
InspectionThe following checks are to be performed.
02
01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings.
Data01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points
____________________________________________________________________________________________________________________________________
Remarks:
____________________________________________________________________________________________________________________________________
Test Equipment
Code Description
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1381718844
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 378/4
Mezzanine DeckArea:04A01Package:
04A - PRODUCTION HEADERSub System:04 - MANIFOLDSSystem:
PRODUCTION Header Manifold (sand detector)Description:MEPA-QT-0401ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:371673588
Service: Production Header Manifold ToProduction Cooler
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:371673588
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 379/4
Mezzanine DeckArea:04B01Package:
04B - TEST HEADERSub System:04 - MANIFOLDSSystem:
SAND DETECTOR - Test Header ManifoldDescription:MEPA-QT-0402ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1775810064
Service: Test Header Manifold To TestSeparator
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1775810064
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 380/4
Area:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
Field Control Unit - Service Water PumpDescription:MEPA-RCU-PM-5110ObjectID:
Function Test ReportE05B Distribution Board, Junction Box & ControlStation
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-167979851
SingleLineDwg:Manufacturer:
Lock out equipment07
For lighting and small power distribution boards check balance of phases is as per singleline diagramRecord full load current readings:Red Ø: AmpsYellow Ø: AmpsBlue Ø: Amps
06
Energise Distribution Board confirm and record voltage:L1 - L2 L1 - L3 L2 - L3L1 - N L2 - N L3 - N
05
Using a 1000V Megger perform IR Test on Distribution BoardL1 - E _________Mohm L2 - E _________Mohm L3 - E _________MohmL1 - L2_________Mohm L1 - L3_________Mohm L2 - L3_________MohmL1 - N _________Mohm L2 - N _________Mohm L3 - N _________Mohm
04
For local control stations confirm switching in conjunction with motor run test03
Check busbars are at zero potential and main isolator and all MCB's are open02
Check ratings of MCB's and main isolator are as per AFC Drawing01
Output /RemarksPLOKNADescriptionItem
Notes.1. All switching and testing of equipment is to be carried out in accordance with the BDEWC / Client electrical safety rules and operating
procedures
All relevant ITR’s and FTR’s to be complete prior to commissioning
______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-167979851
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 381/4
Area:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
Switchboard Cubicle - Service Water PumpDescription:MEPA-SB-7700-L5BObjectID:
Function Test ReportE22B Motor Starter Contactor
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-964814696
SingleLineDwg:Manufacturer:
Motor to be run and tested in accordance with FTR EO8B08
Equipment is ready for service07
Check voltage and phase rotation is correct06
05.05 - Anti condensate heater
05.04 - Operation of local and field controls, stop start station
05.03 - Manual and automatic closing
05.02 - Indication lights and Ammeter
05.01 - Trips and alarms
Prove auxiliary circuits and function of following: *W*05
Perform injection test on overload relays: *W*
Motor: _______ KW ______ Amps Set range: _______ Amps Test Current: _______ (2xlr Amps) Acceptable Curve: _______ secs Actual: _______ secsStarter Unit Function Checked: _______
04
Confirm control voltage is available and energise controls03
Place equipment in test position02
Confirm switchboard busbars are at zero potential and all switchboard feeders areisolated and locked out
01
Output /RemarksPLOKNADescriptionItem
Notes1. All switching and testing of equipment is to be carried out in accordance with the BDEWC / Client electrical safety rules and operating
procedures
2. All relevant ITR’s and FTR’s to be complete prior to energisation procedure
3. Some of the tests listed below may have been performed at the FAT and not scheduled to be re tested at the SAT, in which case a copy of the FAT tests shall be attached to this check sheet
*W* Commissioning & Client Witness points
______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-964814696
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 382/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6801ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:391859120
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:391859120
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 383/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6802ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1755624524
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1755624524
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 384/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6803ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-681882711
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-681882711
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 385/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6804ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1465600942
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1465600942
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 386/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6805ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-681882718
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-681882718
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 387/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6806ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:391859111
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:391859111
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 388/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6807ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1465600924
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1465600924
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 389/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6809ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1465600917
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1465600917
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 390/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6810ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1756116040
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1756116040
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 391/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6811ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:391367600
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:391367600
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 392/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6812ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1756116044
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1756116044
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 393/4
Mezzanine DeckArea:68A02Package:
68A - A-6800 CHEMICAL INJECTION SKIDPACKAGE (CORROSION INHIBITOR - FLOWLINE)
Sub System:68 - CHEMICAL INJECTIONSystem:
SOLENOID VALVE - A6800 Chemical Injection SkidDescription:MEPA-SV-6808ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-681882736
Service: Corrossion inhibitor -Flowline
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-681882736
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 394/4
Sub-Cellar DeckArea:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
SERVICE WATER SUPPLY CAISSONDescription:MEPA-T-5110ObjectID:
Inspection Test ReportM01A Tank
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2003270091
SerialNo:
Upon successful completion of all steps above, close manway door with shipping gasketonly and finger tighten all bolts. New gasket must NOT be used. Seal/cover flange toprevent entry of water/dirt. *W*
30
If overflow is fitted, ensure that it is unobstructed and routed to location shown on P&ID.29
Where preservation materials are installed, equipment is marked"PRESERVATION INSIDE".
28
Ensure that preservation is correct.27
Adequate clearance exists for removal of internals.26
Check nozzle loading is not excessive.25
Confirm earth bonding completed.24
Confirm that the manway gasket/s (which must not yet be fitted) are correctly preservedand stored in the warehouse.
23
All gaskets are fitted, with the exception of the manway gasket/s.22
All gaskets are correct to specification.21
Access to valves, gauges and fittings is adequate.20
Access ladders and platforms are correctly installed.19
Manway lifting arrangements are adequate.18
Manway is accessible.17
Check coating is undamaged. *W*16
Tank is clean internally. *W*15
Internals and vessel trims are fitted as per drawing. *W*14
Vent and drain valves are fitted13
If specified on project drawings, confirm that vacuum breaker is installed and itscertification is valid
12
All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipesupports shall not be welded onto adjacent wall which may be common with tank wall.
11
All checks sheets for associated equipment such as pumps that require internal access tothe tank have been completed. e.g. inspection of pump inlet strainers.
10
All flange management tags are still intact on all vessel flanges (if specified)09
All pipes and equipment which interface with the tank have been installed, their flangeshave been torqued/tensioned.
08
All hot oil flushing and chemical cleaning of adjoining pipework has been completed07
Fittings, connections, sacrificial anodes, bird screens, etc, complete as per vendordrawings.
06
Tank is secure. All structural bolting is tight and to spec.05
Sliding feet (if any) are free to move, and are fitted with locknuts.04
Tank is installed level and as per P & IDs.03
Tank has been installed to the manufacturer's instructions.02
Nameplate details are correct in accordance with the data sheet.01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points______________________________________________________________________________________________________________________
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:2003270091
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 395/4
Sub-Cellar DeckArea:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
SERVICE WATER SUPPLY CAISSONDescription:MEPA-T-5110ObjectID:
Function Test ReportM01B TANK
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2003270080
SerialNo:
Torque manway flanges and confirm that torquing/tightening certification is complete*W*
16
After items 2 to 13 have been completed, close manway(s)/hatch(s) with correct gasketsand bolting. *W*
15
Confirm earth bonding completed.14
If specified on project drawings, confirm that vacuum breaker is installed and itscertification is valid
13
Remove all non soluble preservation, and ensure that soluble preservation coatings areapplied, (if specified in project Preservation Procedure).
12
Vent and drain valves fitted and exercised.11
Vessel internally clean and no internal degradation has occurred since the 'A' checkswere carried out *W*
10
Vessel externally clean and free from obstruction.09
All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipesupports shall not be welded onto adjacent wall which may be common with tank wall.
08
All checks sheets for associated equipment such as pumps that require internal access tothe tank have been completed. e.g. inspection of pump inlet strainers.
07
All hot oil flushing and chemical cleaning of adjoining pipework, (if any), has beencompleted.
06
All fittings, connections, sacrificial anodes, bird screens, spec blinds, etc, still present andin good order.
05
All flange management tags are still intact on all vessel flanges (if specified)04
All flange bolts have been torqued/tensioned/tightened.03
All pipes and equipment which interface with the vessel have been installed.02
Construction check list completed and no subsequent damage has occurred.01
Output /RemarksPLOKNADescriptionItem
Notes & Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:2003270080
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 396/4
Sub-Cellar DeckArea:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
OHD CAISSONDescription:MEPA-T-6510ObjectID:
Inspection Test ReportM01A Tank
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1943499339
SerialNo:
Upon successful completion of all steps above, close manway door with shipping gasketonly and finger tighten all bolts. New gasket must NOT be used. Seal/cover flange toprevent entry of water/dirt. *W*
30
If overflow is fitted, ensure that it is unobstructed and routed to location shown on P&ID.29
Where preservation materials are installed, equipment is marked"PRESERVATION INSIDE".
28
Ensure that preservation is correct.27
Adequate clearance exists for removal of internals.26
Check nozzle loading is not excessive.25
Confirm earth bonding completed.24
Confirm that the manway gasket/s (which must not yet be fitted) are correctly preservedand stored in the warehouse.
23
All gaskets are fitted, with the exception of the manway gasket/s.22
All gaskets are correct to specification.21
Access to valves, gauges and fittings is adequate.20
Access ladders and platforms are correctly installed.19
Manway lifting arrangements are adequate.18
Manway is accessible.17
Check coating is undamaged. *W*16
Tank is clean internally. *W*15
Internals and vessel trims are fitted as per drawing. *W*14
Vent and drain valves are fitted13
If specified on project drawings, confirm that vacuum breaker is installed and itscertification is valid
12
All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipesupports shall not be welded onto adjacent wall which may be common with tank wall.
11
All checks sheets for associated equipment such as pumps that require internal access tothe tank have been completed. e.g. inspection of pump inlet strainers.
10
All flange management tags are still intact on all vessel flanges (if specified)09
All pipes and equipment which interface with the tank have been installed, their flangeshave been torqued/tensioned.
08
All hot oil flushing and chemical cleaning of adjoining pipework has been completed07
Fittings, connections, sacrificial anodes, bird screens, etc, complete as per vendordrawings.
06
Tank is secure. All structural bolting is tight and to spec.05
Sliding feet (if any) are free to move, and are fitted with locknuts.04
Tank is installed level and as per P & IDs.03
Tank has been installed to the manufacturer's instructions.02
Nameplate details are correct in accordance with the data sheet.01
Output /RemarksPLOKNADescriptionItem
Notes:
*W* Commissioning & Client Witness points______________________________________________________________________________________________________________________
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1943499339
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 397/4
Sub-Cellar DeckArea:65A02Package:
65A - T-6510 OPEN DRAINS CAISSON & PUMPSub System:65 - OPEN DRAINSystem:
OHD CAISSONDescription:MEPA-T-6510ObjectID:
Function Test ReportM01B TANK
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1943499328
SerialNo:
Torque manway flanges and confirm that torquing/tightening certification is complete*W*
16
After items 2 to 13 have been completed, close manway(s)/hatch(s) with correct gasketsand bolting. *W*
15
Confirm earth bonding completed.14
If specified on project drawings, confirm that vacuum breaker is installed and itscertification is valid
13
Remove all non soluble preservation, and ensure that soluble preservation coatings areapplied, (if specified in project Preservation Procedure).
12
Vent and drain valves fitted and exercised.11
Vessel internally clean and no internal degradation has occurred since the 'A' checkswere carried out *W*
10
Vessel externally clean and free from obstruction.09
All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipesupports shall not be welded onto adjacent wall which may be common with tank wall.
08
All checks sheets for associated equipment such as pumps that require internal access tothe tank have been completed. e.g. inspection of pump inlet strainers.
07
All hot oil flushing and chemical cleaning of adjoining pipework, (if any), has beencompleted.
06
All fittings, connections, sacrificial anodes, bird screens, spec blinds, etc, still present andin good order.
05
All flange management tags are still intact on all vessel flanges (if specified)04
All flange bolts have been torqued/tensioned/tightened.03
All pipes and equipment which interface with the vessel have been installed.02
Construction check list completed and no subsequent damage has occurred.01
Output /RemarksPLOKNADescriptionItem
Notes & Remarks:
*W* Commissioning & Client Witness points
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:1943499328
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 398/4
Main DeckArea:92D01Package:
92D - MISCELLANEOUS EQUIPMENTSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
TELECOM TOWERDescription:MEPA-TEL-TOWERObjectID:
Inspection Test ReportM21A Main Structural Completion
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:200104837
All items covered by this record undamaged and clean.17
All piping & ducting penetrations through bulkheads & decks fitted with gas tightsleeves/seals
16
All welding and NDT work completed and cleared.15
Temporary steel work to be removed at a later date, clearly marked and identified onrelevant drawings.
14
Main and Interface dimensions checked.13
Confirm that all maintenance / scaffolding lugs are installed in accordance with layoutdrawings with the correct orientation.
12
All structural supports installed in accordance with drawings and all temporary aids /brackets removed.
11
Foundations and handrails installed in accordance with specifications, ladder entranceshave safety bar complete with protected landing end and portable hand railings aresecured.
10
All foundations installed and do not create traps for water, ample drainage is available forthe area.
09
All grating installed and no gaps exist that allow the penetration of a ball bearing ofdiameter > 15 mm.
08
All penetrations installed, with sleeves/kick plates of specified size complete with drainholes as required.
07
All gulley gratings to drains installed.06
All platforms and walkways are installed in accordance with drawings, and all temporaryaids/brackets removed.
05
Roof structures are installed in accordance with drawings, and all temporary aids /brackets removed.
04
Deck structures installed in accordance with drawings, and all temporary aids / bracketsremoved.
03
Bulkheads installed in accordance with drawings, and all temporary aids / bracketsremoved.
02
Main structural members installed in accordance with drawings, and all temporary aids /brackets removed.
01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:200104837
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 399/4
Area:92B02Package:
92B - CCTV/LAN SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
IP TELEPHONEDescription:MEPA-TUO-9201ObjectID:
Inspection Test ReportT01A Telecoms Field Device Installation Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-235039639
Type:
Service:Serial No:Manufacturer:
Suitable grease applied to flanges (Ex-d enclosures).14
Check earthing conforms to earthing philosophy.13
Gaskets & seals fitted correctly.12
Gaskets & seals undamaged.11
Terminal box flanges undamaged.10
Spare gland entries plugged correctly.09
Paintwork correct.08
Access suitable.07
Fixings correct.06
Supports installed correctly.05
Identification correct.04
Equipment suitable for area classification.03
Item complies with Data sheet.02
Installed according to latest revision of Layout drawing.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-235039639
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 400/4
E&I ROOMArea:92B02Package:
92B - CCTV/LAN SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
IP TELEPHONEDescription:MEPA-TUO-9202ObjectID:
Inspection Test ReportT01A Telecoms Field Device Installation Check
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-237398935
Type:
Service:Serial No:Manufacturer:
Suitable grease applied to flanges (Ex-d enclosures).14
Check earthing conforms to earthing philosophy.13
Gaskets & seals fitted correctly.12
Gaskets & seals undamaged.11
Terminal box flanges undamaged.10
Spare gland entries plugged correctly.09
Paintwork correct.08
Access suitable.07
Fixings correct.06
Supports installed correctly.05
Identification correct.04
Equipment suitable for area classification.03
Item complies with Data sheet.02
Installed according to latest revision of Layout drawing.01
Output /RemarksPLOKNADescriptionItem
Notes and Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-237398935
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 401/4
Area:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
-Description:MEPA-UA-5110ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1751269186
Service: Service Water Pump P-5110 FAULTALARM
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1751269186
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 402/4
Area:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
-Description:MEPA-UZ-5110ObjectID:
Function Test ReportI01B Loop Test
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1751266802
Service: Trip Service Water Pump MEPA-P-5110 Fan Motor
LoopNo:LoopDwg:C&E No:
Relevant as-built mark-ups complete10
Cause & Effect Yellow Lined09
Graphic points displayed correctly08
Face Plates displayed correctly07
Function test of loop and all components in accordance with loop & data sheet(s)06
Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule.05
Confirm valve action correct04
Confirm valve stroke time(s) is as per data sheet03
All relevant installation checklists complete02
All relevant inspection & calibration checklists complete01
Output /RemarksPLOKNADescriptionItem
Remarks :
Valve Action = dir/rev
Alarm Point = inc/dec
Trip Point = inc/dec
Stroke Time = secs
Range(s) =
_____________________________________________________________________________________________________________________
Test Equipment :
Code Description Calibration Date
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1751266802
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 403/4
Area:89A03Package:
89A - MEPA NAVAIDSSub System:89 - NAVAIDSSystem:
Cable From MEPA-NCCP-8900 NAV-AIDS CENTRALCONTROL PANEL To TELECOM MAST AIRCRAFTWA
Description:PL-8900-4ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:2036215469
VoltageRating: 240VToTag: TELECOM MAST AIRCRAFTWARNING LIGHT
Size: 2Cx4mm2FromTag: MEPA-NCCP-8900 NAV-AIDSCENTRAL CONTROL PANEL
CableType: P5
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:2036215469
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 404/4
Area:51A01Package:
51A - T-5110 SERVICE WATER CAISSON/PUMPSub System:51 - SERVICE WATER SYSTEMSystem:
Cable From 415V SWITCHBOARD/MCC MEPA-SB-7700 To MEPA-PM-5110 SERVICE WATER PUMP
Description:PN-PM5110ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1062693670
VoltageRating: 415VToTag: MEPA-PM-5110 SERVICE WATERPUMP
Size: 3Cx4mm2FromTag: 415V SWITCHBOARD/MCC MEPA-SB-7700
CableType: P2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1062693670
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 405/4
Area:01H03Package:
01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-010 To MEPA-PT-0174Description:PT-0174ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1651356538
VoltageRating: -ToTag: MEPA-PT-0174
Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1651356538
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 406/4
Area:01I03Package:
01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-010 To MEPA-PT-0184Description:PT-0184ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1650537338
VoltageRating: -ToTag: MEPA-PT-0184
Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1650537338
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 407/4
Area:01J03Package:
01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-010 To MEPA-PT-0194Description:PT-0194ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1650766714
VoltageRating: -ToTag: MEPA-PT-0194
Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1650766714
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 408/4
Area:01K03Package:
01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-010 To MEPA-PT-0204Description:PT-0204ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1648980830
VoltageRating: -ToTag: MEPA-PT-0204
Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1648980830
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 409/4
Area:01L03Package:
01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINESub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-010 To MEPA-PT-0214Description:PT-0214ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1648489310
VoltageRating: -ToTag: MEPA-PT-0214
Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1648489310
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 410/4
Area:01M03Package:
01M - WELLHEAD WH-0220 (SLOT 12) &FLOWLINE
Sub System:01 - WELLHEADS & FLOWLINESSystem:
Inst. Cable From MEPA-IJB-010 To MEPA-PT-0224Description:PT-0224ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1648718686
VoltageRating: -ToTag: MEPA-PT-0224
Size: 1PRx1.5mm2FromTag: MEPA-IJB-010CableType: I2
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1648718686
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 411/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
GORA Reinstatement Test Pack - 29Description:RTP-GORA-1ObjectID:
Function Test ReportP05B Witnessed Joint
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:898532292
Joint desciption ::Flange description/ID::PIDNo:
Attach supporting documentation for post reisnstement test to this sheet15
Post reinstatement test described in line 10 completed satisfactorily14
Circle one item from list below: - N2 Helium leak test / Service test / Nil / Soapy bubble leak test / - check with hand held gas detector after introduction of gas / - other (providedetails)………………………………………………………………………………...……..
13
Post reinstatement, the following checks will be made:12
Torquing/ tension certificate complete and flange management tag fitted (if specified inproject requirements)
11
No excessive length of stud bolt protruding through each nut.10
Minimum of one thread proud of all nuts.09
No visible damage to gasket when joint completed.08
All nuts pulled up to required tightness.07
Joint pulled up evenly on opposing stud bolts.06
Flange faces parallel.05
Nuts and stud bolts examined and seen to be undamaged and correct size and type.04
Gaskets examined and seen to be clean, damage free and the correct type and size.03
Flange faces examined and seen to be clean and damage free.02
Prior to reinstatement, the following checks will be made:01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:898532292
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 412/4
Area:29C01Package:
29C - MEPA GAS RECEIVING FACILITIES ATGORA
Sub System:29 - GAS IMPORT/EXPORTSystem:
GORA Reinstatement Test Pack - 29Description:RTP-GORA-1TestPack No:
Function Test ReportP04B N2 LEAK TEST
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:898544068
Recorder Serial No.:Chart Reference:
TestMedium:Design temperature:Design Pressure (MAWP):
Gauge Serial No.:Operational Flow Medium:Test temperature:
TestPressure:TestDuration:PIDNo:
CommentP&IDDescriptionLineNo
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM HV-29408 TO HV-29409100-PG-2928-C8Y-2
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM 100-PG-2928-C8Y-2 TO HV-29411100-PG-2928-C8Y-4
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM SBT-2903 TO HV-29403400-PG-2945-C8Y-1
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM 400-PG-2945-C8Y-1 TO HV-29402400-PG-2945-C8Y-2
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM SDV-2950 TO T05.EL.17000500-PG-2925-C8Y-5
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM TO T05.EL.17000500-PG-2925-C8Y-6
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM T05.EL.17000 TO HV-29404500-PG-2925-C8Y-7
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM HV-29413 TO HV-2941550-PG-2927-C1Y-1
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM 50-PG-2927-C1Y-1 TO HV-2941650-PG-2927-C1Y-2
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM 400-PG-2945-C8Y TO HV-2940050-PG-2943-C1Y-1
06001-GORA-EG-PR-DWG-PNID-0004GORA - PIG RECEIVER R-2950 LINE FROM TP-314A TO SDV-295150-PG-2954-C1Y-1
All witness joints entered into Witness Joint Register and copy attached to this sheet.02
Leak test completed and certificate attached to this sheet01
Output /RemarksPLOKNADescriptionItem
Remarks:
Type of Test: Service TestReinstatement Leak Test (N2He)(Delete as appropriate)1. Line valves confirmed half open for test (to test stem packing) . 2. Isolation valve integrity test to be conducted.
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:898544068
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28946). 413/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
GORA Reinstatement Test Pack - 33Description:RTP-GORA-2ObjectID:
Function Test ReportP05B Witnessed Joint
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1248951360
Joint desciption ::Flange description/ID::PIDNo:
Attach supporting documentation for post reisnstement test to this sheet15
Post reinstatement test described in line 10 completed satisfactorily14
Circle one item from list below: - N2 Helium leak test / Service test / Nil / Soapy bubble leak test / - check with hand held gas detector after introduction of gas / - other (providedetails)………………………………………………………………………………...……..
13
Post reinstatement, the following checks will be made:12
Torquing/ tension certificate complete and flange management tag fitted (if specified inproject requirements)
11
No excessive length of stud bolt protruding through each nut.10
Minimum of one thread proud of all nuts.09
No visible damage to gasket when joint completed.08
All nuts pulled up to required tightness.07
Joint pulled up evenly on opposing stud bolts.06
Flange faces parallel.05
Nuts and stud bolts examined and seen to be undamaged and correct size and type.04
Gaskets examined and seen to be clean, damage free and the correct type and size.03
Flange faces examined and seen to be clean and damage free.02
Prior to reinstatement, the following checks will be made:01
Output /RemarksPLOKNADescriptionItem
Remarks:
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1248951360
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 414/4
Area:33C01Package:
33C - MEPA CONDENSATE RECEIVINGFACILITIES AT GORA
Sub System:33 - CONDENSATE IMPORT/EXPORTSystem:
GORA Reinstatement Test Pack - 33Description:RTP-GORA-2TestPack No:
Function Test ReportP04B N2 LEAK TEST
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1248939584
Recorder Serial No.:Chart Reference:
TestMedium:Design temperature:Design Pressure (MAWP):
Gauge Serial No.:Operational Flow Medium:Test temperature:
TestPressure:TestDuration:PIDNo:
CommentP&IDDescriptionLineNo
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33311 TO HV-33313100-PL-3323-C1Y-1
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33311 TO HV-33313100-PL-3323-C1Y-2
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SBT-3302 TO HV-33300150-PL-3308-C8Y-1
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM 150-PL-3308-C8Y-1 TO HV-33301150-PL-3308-C8Y-2
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM 150-PL-3308-C8Y-2 TO SOC-3304150-PL-3308-C8Y-3
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-1
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-2
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-3
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-4
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-5
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302200-PL-3315-C8Y-6
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33302 TO HV-33304200-PL-3315-C8Y-7
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-3330750-PL-3322-C8Y-1
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-3330750-PL-3322-C8Y-2
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-3330750-PL-3322-C8Y-3
06001-GORA-EG-PR-DWG-PNID-0010GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-3330750-PL-3322-C8Y-4
All witness joints entered into Witness Joint Register and copy attached to this sheet.02
Leak test completed and certificate attached to this sheet01
Output /RemarksPLOKNADescriptionItem
Remarks:
Type of Test: Service TestReinstatement Leak Test (N2He)(Delete as appropriate)1. Line valves confirmed half open for test (to test stem packing) . 2. Isolation valve integrity test to be conducted.
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QC
OE:-1248939584
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28946). 415/4
Area:92A02Package:
92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
Telecom CablesDescription:YAFC-0001ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:690104358
VoltageRating:ToTag: x
Size:FromTag:CableType:
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:690104358
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 416/4
Area:92A02Package:
92A - DMR SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
Telecom CablesDescription:YAFC-0002ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1457379294
VoltageRating:ToTag: x
Size:FromTag:CableType:
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1457379294
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 417/4
Area:92E01Package:
92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
Telecom CablesDescription:YAFC-0006ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:690104369
VoltageRating:ToTag: x
Size:FromTag:CableType:
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:690104369
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 418/4
Area:92E01Package:
92E - GOPB TELECOMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
Telecom CablesDescription:YAFC-0007ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1763846154
VoltageRating:ToTag: x
Size:FromTag:CableType:
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1763846154
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 419/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
Telecom CablesDescription:YDEE-0007ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:1761748666
VoltageRating:ToTag: x
Size:FromTag:CableType:
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:1761748666
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 420/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
Telecom CablesDescription:YUHF-0002ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-1445829582
VoltageRating:ToTag: x
Size:FromTag:CableType:
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-1445829582
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 421/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
Telecom CablesDescription:YUHF-0003ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:-372087761
VoltageRating:ToTag: x
Size:FromTag:CableType:
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:-372087761
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 422/4
Area:92C02Package:
92C - UHF/VHF SYSTEMSub System:92 - TELECOMMUNICATIONS SYSTEMSystem:
Telecom CablesDescription:YVHF-0001ObjectID:
Inspection Test ReportE02A Cable < 1000 Volts
MERAPUH-A (MEPA) PRODUCTION TOPSIDEFACILITIES
OE:701659830
VoltageRating:ToTag: x
Size:FromTag:CableType:
Replace all equipment covers, check bolts washers etc. are reinstated correctly10
Discharge all cores to ground09
Perform insulation resistance test, indicate number of cores and identification method,colour or numbered coresTest voltage <=1000VRecord values
08
Destination of cable and phasing confirmed by continuity test07
Cable neatly laid and strapped to rack06
Cable racks adequately supported, bonded and visibly earthed05
Cable correctly numbered, tagged at both ends and at specified intervals04
Cable glands suited to hazardous are classification03
Cable properly glanded and terminated02
Installation as per AFC Drawings and data sheets01
Output /RemarksPLOKNADescriptionItem
Notes:
Cable bending radii to be as per vendor recommendations______________________________________________________________________________________________________________________
Remarks:
______________________________________________________________________________________________________________________
Test Equipment :
Date:
Signature:
Name:
BDEWC CommissioningBDEWC QA/QCBDEWC Construction
OE:701659830
Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922). 423/4