Cheakamus River October 2003 Flood Restoration...

18
NVOS Hatchery in flood October 2003 Cheakamus River October 2003 Flood Restoration Project (04.Ch.03) Government of Canada Fisheries and Oceans Canada North Vancouver Outdoor School

Transcript of Cheakamus River October 2003 Flood Restoration...

NVOS Hatchery in flood October 2003

Cheakamus River October 2003Flood Restoration Project (04.Ch.03)

Government of CanadaFisheries and Oceans

CanadaNorth VancouverOutdoor School

Cheakamus River October 2003Flood Restoration

Final Report

Submitted by: NorthVancouver Outdoor SchoolSchool District #44

Prepared by: Carl Halvorsonwith financial support of the

BC Hydro Bridge Coastal Fish and Wildlife Restoration Program

Table of Contents

Executive Summary

1. Introduction

2. Study Area

3. Methods

4. Results

5. Acknowledgements

Appendices

A. Financial Statements

B. Restoration Details (maps / photos / drawings)1. Site Location Map2. NVOS Site Map3. Photo Pages 1 - 54. Far Point intake site map5. Bighouse channel layout6. Eagle Point Connector channel layout

C. Additional Information

Executive Summary

This project involved restoration and reconstruction of channel habitats and support structures forsalmonid habitat located at North Vancouver Outdoor School (NVOS) that were impacted by theOctober 2003 flood of record on the Cheakamus River.

Several sites on property were damaged. Works included required upgrades to the dike at the Far Pointintake, repair of the dike and valve intake at the Gorbuscha intake valve (previous BCRP project 02.Ch.6),reconstruction of a protective berm washed away on Moodie’s Channel, restoration of two sections ofMoodie’s Channel, replacement of LWDs in the Moodie’s Sidechannel pond complex, replacement ofLWDs in the Canoe Pond and “Hydro Pond”. Other restoration works after the 2003 flood includedthe reconstruction of Kisutch Channel and restoration of the protective berm that prevent flood flowsthat outflank NVOS dikes to flow down through the NVOS hatchery and downstream spawningchannels and replacement of a roadbridge crossing Lower Paradise Channel.

This project involved restoration of 350 meters of sidechannel, repairing 2800 square meters (m2) ofhabitat and 1600 m2 of new habitat. More than 130 pieces of “Large Woody Debris” (LWDs) androotwads were replaced in various pond complexes.

This project was link to other ongoing initiatives funded by various partnership groups including theSchool Protection Program, the Provincial Emergency Program, District of Squamish, School District#44 and the concurrent BCRP project 04.Ch.1 (Mykiss Channel Construction).

Introduction

The North Vancouver Outdoor School (NVOS) has worked with the Department of Fisheries andOceans Canada (DFO) and various funding partners to develop salmon habitat restoration projects onschool property over the last two decades. These projects have been directed at improving spawningand rearing habitats for coho, chum, chinook and pink salmon. NVOS has operated a teaching hatcherythat has produced chum, chinook and coho fry for over two decades.

This project was directed at restoring important spawning and rearing habitats and support structuresdamaged in the October 2003 flood of record.

Study Area

The restoration sites are located off the west bank of the Cheakamus River on property owned by theNorth Vancouver Outdoor School, School District 44 (North Vancouver).

Map reference is Natural Resources Canada NTS map Cheakamus 92G/14.between (Far Point intake structure): N 49°˚ 49. 844' W123°˚ 09. 396'

and (the Moodie’s Channel exit): N 49˚° 48. 687' W123°˚ 08. 983'

Methods

Materials excavated during the linked BCRP project 04.Ch.1 were utilized to restore and upgradeprotective dike and berm infrastructures. Approx. 2080 m3 of rock was excavated from the Farpointintake site and placed on the reconstructed dike nearby. Appox, 2200 m3 of engineered fill supplied bythe District of Squamish was placed and compacted during reconstruction of this dike. (This materialsupplied by the District of Squamish replaced aluvial gravels borrowed from NVOS to make emergencyrepairs to Paradise Valley Road - immediately following the October 2003 flood)

Approx. 50 m3 of excavated fill was used to fill and repair flood damage at the Gorbuscha intake valvesite.

Approx. 100 m3 of excavated rock was transported to repair the Gorbuscha Intake site.

Approx. 1275 m3 of excavated fill was transported to the Moodie’s Channel protective berm. Thismaterial was placed and compacted with funding from the Provincial Emergency Program.

Approx. 500 m3 of excavate fill was transported, placed and compacted to repair the protective bermjust north of the NVOS hatchery.

Excavation was done with Cat 225, 235 and 320 excavators and Cat 966 loaders. Material was movedaround site by a variety of standard dump trucks and a D250 Cat truck.

LWDs were replaced using a Cat 320 excavator for placement and transported with standard dumptrucks and a D250 Cat truck. LWDs were supplied by NVOS.

NVOS partnered with Fisheries and Oceans Canada during all phases of the design and developmentof these restoration works.

Results

Repair work after the 2003 flood has resulted in restoration of a total of almost 2800 square metres(m2) of enhanced off channel spawning and rearing habitat for pink, chinook, coho, and chum salmonand steelhead trout.

Reconstruction work at the NVOS Bighouse / Canoe Pond outfall has resulted in the creation of 90m of new side channel habitat totalling approx. 400 m2 in area. Approx. 70+ LWDs were replaced invarious habitats.

The Farpoint intake dike was upgraded to Ministry standards with the addition of 2000 m3 of rocksupplied during excavation of the new intake outflow channel and pond.

The berm protecting the NVOS hatchery and downstream salmonid habitats was repaired with theaddition of 500 m3 of compacted materials.

Repairs to the Moodie’s Channel re-established approx. 1600 m2 of prime chum spawning habitat.

Reconstruction work of the NVOS Canoe Pond / Eagle Point Intake connector channel has resultedin the re-creation of 200 m of side channel habitat, totalling approx. 1200 m2 in area, that was destroyedor damaged during the October 2003 flood event. Approx. 60+ LWDs were placed during this phaseof construction, creating several refuge areas and “log jamb” features.

5: Acknowledgements

This project would not have been possible without the financial support of BC Hydro Bridge CoastalFish and Wildlife Restoration Program and the technical and supervisory support of Fisheries andOceans Canada Pacific Region Habitat and Enhancement Branch, particularly Matt Foy, HaroldBeardmore, and Sam Gidora.

Excavation contraction was provided by John Hunter Ltd.

Engineered gravel for dike reconstruction was supplied by the District of Squamish (replacing materialsborrowed from North Vancouver Outdoor School to make emergency road repairs following theOctober 2003 flood event).

Additional funding to complete repairs detailed in this report were supplied by the School ProtectionPlan, the Provincial Emergency Program and School District #44.

Rock, additional gravels and LWDs were supplied on site by North Vancouver Outdoor School.

Letters of support were furnished for the initial funding application by:Randall Lewis Squamish Nation; Harold Beardmore P.Eng. Fisheries and Oceans; Edith Tobe, for theSquamish River Watershed; Steve Rochetta BC WLAP Habitat Officer for Squamish; Jesse Neri, forDFO confirming contribution; Diane Schartner, for the Pacific Foundation for Understanding Nature.

Appendix A: Financial Statement - Expenditures

Cost Item Description Unit cost

Construction - equipment Cat 235,325 excavator 49,243.49Invoice #255 966 loader, dump trucks

Blasting Site prep / blasting rock 1033.64

Blasting Site prep / blasting rock 3098.24

Freight Bridge deck delivery 856.00

Freight Bridge deck delivery 529.65

NVOS Invoice # 3800 October, 25,2004 54,761.02

Construction - equipment Cat 325 excavator 3964.35Invoice #362 D250 Cat truckNVOS Invoice # 3805 3964.35

Invoice Totals $58,725.37

Grant Amount: 59,000.00 (274.63) surplus

Appendix A: Financial Statement - Contributions

In-Kind Contributions Supplied by: Unit Value: Total:

Senior Biologist DFO 5days @ $700 3,500.00

Senior Engineer DFO 5 days @ $700 3,500.00

Design / Supervision NVOS 10 days @ $500 5,000.00

Construction / engineering support DFO 20 days @ $450 9,000.00

Labour: Landscaping / seeding DFO 10 days @ $200 2,000.00

Labour: Building trails NVOS 10 days @ $300 3,000.00

Labour: Replacing bridges NVOS 2 days @ $300 600.00

Monitoring DFO 10 days @ $500 5,000.00

Gravel NVOS 30,000.00

Rip rap rock NVOS 20,000.00

Large Woody Debris NVOS 5,000.00

Labour: Accounting, copies, reports etc. NVOS 2,300.00

Concrete Bridge Decks DFO 5,000.00

Digital imaging DFO/NVOS 200.00

Groundcover seed (inc. freight) DFO 200.00

Footbridge materials NVOS 800.00

Total In-Kind Contributions $95,100.00

Appendix B: Recognition of

BC Hydro Bridge Coastal Fish and Wildlife Restoration Program

• All publicity activities will be made in the name of the "BC Hydro Bridge Coastal Fish and WildlifeRestoration Program.

• Information regarding the project will be communicated to members of the Squamish River WatershedSociety which include most of the groups in the area that are interested in fish and wildlife issues.

• The North Vancouver Outdoor School produces a school newsletter, which goes out to a wide audienceof staff, students, alumni and partners. This project has been included in that newsletter.

Appendix C: Construction Details / Images

(see attached files)

• Site location map• NVOS site plan• Photo pages (5)• Far Point intake site plan• Bighouse Channel reconstruction site plan• Eagle Point Connector Channel site plan

Appendix D: Additional Information

• Far Point dike approval letter from Diking Authority

Cheakamus River 2003 Flood Restoration / 04.Ch.3 / Final Report / Site Locator

WSC GAUGE08GA043

Squamish

Howe Sound

M

onm

outh

Cre

ek

Sto

ney

Cre

ek

Mam

quam

Riv

er

MashiterC

reek

Cheekye River

Cullito

nC

reek

Pilchuk Creek

Cheakamus River

Squamish River

Map Key:Squamish Watershed

BM 77HA915EL55.411

N 49˚49.596'W123˚09.121'10U 0489065UTM 5519143

Paradise Valley Road

Tenderfoot Creek Hatchery

Midnight Way

Squamish Valley Road

North VancouverOutdoor School

CN Railway

Cheekye River

CHEAKAMUS RIVER:Cheekye River confluence - Swift Creek confluence

Water Elev. Gauge:WSG 08GA043

Cheakamus Flood Restoration: 2004(04.Ch.3)

Cheakamus River Habitats

Off - channel Habitats

River Bars (from flood plain mapping)

BC Hydro transmission corridor

BC Hydro transmission tower

Cheakamus River 2003 Flood Restoration / 04.Ch.3 / Final Report / Site Map

N

S

EW

duck po

nd

Hatchery

• Fish Camp

• Moody's Spawning Channel

Em

erald

Forest

Cre

ek

Main

Building

BC H

ydro

Shelt

er

Wountie E

ast

Upper

Para

dis

eChannel

Kis

utch

Refuge

Channel

Bob's

Berm

Dave's

Ponds

BCR

Spawning

Channel

Kiw

iNort

hHabitat

Channel

Evans

Lake

Road

Em

erald

Forest

“culturally

modified”

cedars

Tenderfoot

Hatchery

Lillooet G

old R

ush Tra

il

chee-Y

AK-m

ush

“fis

hw

eir

pla

ce”

CN

Railw

ay

BCR

Mi l e

49

Channel

• 6 km to Highway #99

• 16 km to Squamish

CN

Rail w

ay

Far Point

Intake

Paradis

eValle

yRoad

Paradis

eVal le

yRoad

Cheak

amus

River

Kis

utch

Refug

eCha

nnel

Gorb

uscha

East

Chann

el

Gorb

uscha

West

Channel

Woun

tie

West

To: Evans Lake

Levette Lake

Hutt Lake

Private Property

Fa

rPoint

Habitat Channels

Mykis

sHabit

at

Chann

el s

Repaired Trail

Repaired Trail

Repaired Trails

Replaced Bridge

N 49˚49.844'W123˚09.396'

Site A

N 49˚49.687'W123˚09.238'

N 49˚49.617'W123˚09.136'

Site E

N 49˚48.810'W123˚09.022'

Site B

Site F

Site D

Site H

Site G

N 49˚48.687'W123˚08.983'

Site C

Site I

North VancouverOutdoor School

School District #44

Bighouse

Replaced Bridges Repaired Trails

Eagle Point

Site J

Cheakamus River 2003 Flood Restoration / 04.Ch.3 / Final Report / Photo page 1

Far Point Dike / Outlet Pond Reconstruction (site A on locator map)

Far Point Intake Site: Dike Completion (looking southeast from D on site plan)

Far Point Intake Site: Preconstruction (panorama looking from south - west - north from A on site plan)

Far Point Intake Site: Pond / Dike Reconstruction (looking northeast from B on site plan)

Far Point Intake Site: Pond / Dike Completion (looking northeast from C on site plan)

Cheakamus River 2003 Flood Restoration / 04.Ch.3 / Final Report / Photo page 2

Far Point Dike Reconstruction

Preparing to blast in Far Point “quarry” site

Excavating Far Point intake headpond

Far Point intake pipe scour protection completed

Laying rock toe protecting Far Point intake pipe

Quarry Cleanup / Rock Recovery (site A)The least expensive supply of rock to rebuild theFar Point dike was available in the abandonedNVOS quarry, adjacent to the intake site. Thisrock source had been mined for several previousenhancement projects - leaving many large bouldersthat required blasting.

Crews blasted the rocks into appropriate sizes forriprap. Additional charges were set to remove arock sill that intruded into the intake outfall site.This provided additional required rock and allowedthe intake to be situated tight to the rocks on thewest side, saving a large cottonwood roosting treethat would have otherwise required removal.

Additional materials excavated from the old quarrysite and new intake headpond were used for non-structural portions of the reconstructed dike andto fill the breach in the south berm that protectsMoodie’s and Lower Paradise Channels approx. 1km downstream.

Far Point Dike ReconstructionThe impacts of the 2003 flood captured theattention of mainstream government agencies.Dikes that were once considered “bank protection”were now being reassessed and the Far Point areaattracted this review. Staff from the office of theInspector of Dikes and engineers representing theDistrict of Squamish reviewed the proposed worksin this area and we were obligated to include their“recommendations” into new design criteria.

Additional rock was installed along the intake pipeto protect it from scour and the dike core wasconstructed with compacted “structural fill”. Thesiting of the dike was also pulled farther back,maximizing the floodplain. Primary dike elevationwas raised by 1 meter in the reconstructed area.

Site Repairs

Cheakamus River 2003 Flood Restoration / 04.Ch.3 / Final Report / Photo page 3

Constructing Bighouse connector channel

Completed Bighouse connector channel prior to rewatering Repairs to Moodie’s Channel

Completed repair of South Berm

Removing flood debris prior to South Berm reconstruction

Moodie's Channel / Bighouse Connector (site B)Approx. 90 metres of channel was reconstructedwhere flood waters destroyed the Canoe Pondoutfall culverts / control structures and connectingchannel to Moodie’s Spawning Channel.

South Berm / Moodie's Channel (site C)Approx. 50 metres of berm protecting Moodie’sChannel was reconstructed using 1250 m3 ofmaterial excavated from the Far Point intake pondextension.

Flood debris blocking Moodie’s Channel wasremoved and 50 meters of the channel and streamside trail rebuilt, restoring access to upstreamspawning and rearing habitats.

Cheakamus River 2003 Flood Restoration / 04.Ch.3 / Final Report / Photo page 4

Site Repairs (cont . . . )

Eagle Point Channel / Moodie's Channel (site J)Approx. 185 metres of dike along the NVOS“Canoe Pond” was washed out by the October2003 flood event. This dike protected the inflowchannel and ponds connected to the “Eagle PointIntake” that supplied significant flows to theMoodie’s and Lower Paradise channel systems.

The Eagle Point connector channel that existedbehind this dike prior to the flood was also in-filled with flood debris, rendering the intakeinoperable.

The Provincial Diking Authority approvedreconstruction of the dike only if the new structurewas placed farther to the west on the existing floodplain - requiring that the existing fisheries channelinfrastructure destroyed in the flood be relocated.

A relic river swale was identified in the forestapprox. 50 metres from the old channel site. Cleanalluvial gravels excavated during construction ofthis replacement channel were mixed with other“structural gravels” crushed on site to form thedike’s core. Organic soils were used to top dressthe pond side slopes of the new dike.

Channel Profiling:The initial construction phase was completed withfunding from the Provincial Emergency Program(PEP) and School District #44 (North Vancouver).Channel engineering was provided by Fisheries andOceans Canada.

BCRP funding was utilized to complete channelprofiling, to bring the finished channel to gradeand to complete LWD complexing.

In total, 200 metres of channel was constructedfor a combined area of 1200 m2. Over 60 piecesof large woody debris was used to create refugeand “log jam” features.

Canoe Pond Dike November 2003

Profiling new Eagle Point Connector channel

Completed channel

Aerial view of completed dike along Canoe Pond and Eagle Point Connector channel

Site Repairs (cont . . . )

Cheakamus River 2003 Flood Restoration / 04.Ch.3 / Final Report / Photo page 5

Replacing LWDs Gorbuscha Channel (site d )

Gorbuscha intake (site e )

LWDs installed in Moodie's Side Channel ponds (site i ) Hatchery Berm under repair (site h )

LWDs installed in “Hydro Pond” (site g ) Reinstalling footbridge on Gorbuscha channel (site f )

Replacing Wood ComplexingThe October 2003 flood washed out much of thewood complexing installed in channel habitats.More than 70 root wads and logs were replaced.

Gorbuscha Intake RepairsThe October 2003 flood scoured rock infill aroundthe Gorbuscha intake site. Rock was provided foruse during the District of Squamish reconstructionof the dike infrastructure in this area. The accesstrail to the Gorbuscha intake valve was badlyscoured and was repaired with the addition ofseveral truck loads of fill.

Hatchery BermThe berm protecting the NVOS Hatchery wasreinforced with 500 cm of compacted fill.

Cheakamus River 2003 Flood Restoration / 04.Ch.3 / Final Report / Intake Site Final Sketch

Exis

ting F

ar P

oin

t In

take

• cr

est

of

new

dik

e 2

004

Pho

to R

efer

ence

Arr

ows

Che

aka

04.C

h.1

/ Fin

al R

epor

t / P

hoto

pag

e 1

• top o

f old d

ike cr

est

• lo

cati

on o

f o

ld c

oncr

ete

bo

x

new

inta

ke p

ipe •

(2004)

• head

wal

l•

3' v

alve

ass

em

bly

new

po

nd (2004)

• dik

e r

eal

ignm

ent

2004

• 5 m

cre

st•

61.0

m e

leva

tio

n +

/-

line o

f ro

ck t

oe •

SCA

LE:

DA

TE:

May

2004

SEPT

2004

DRA

WIN

G N

UM

BER

:CH

-04-0

3

CH

EA

KA

MU

S R

IVER

FAR

PO

INT

IN

TA

KE S

ITE P

LAN

SIT

E P

LAN

SH

EET

1

DES

IGN

ED

DRA

WN

: CH

CH

ECK

ED

APP

RO

VED

REC

OM

MEN

DED

1M

AY

21

2004

SITE

SKET

CH

- (PR

ECO

NST

RU

CTIO

N)

ALL

DIM

ENSI

ON

S REP

RES

ENTA

TIV

E.

2REV

ISIO

NA

PPRO

VED

REV

ISIO

ND

ATE:

NO

.N

OTES

REF

EREN

CE

DRA

WIN

GS

DW

G.N

O.

• 15 m

• 9 m

• 4 m

• 19 m

• 21 m

• 24 m

• 25 m

• 7 m

• 6 m

• 5.5 m

• 4 m

• 3 m

• 6 m 0+00 •

0-10 •

0-20 •

• 0+10

• 0+15

• 0+20

0+30 •

• 0+40

• 0+50

• 0+60

• 0+67

• 0+54

• 0+70

0+80 •

• nai

l - U

nderh

ill a

nd U

nderh

illm

onum

ent

#296 -

2004 (dest

roye

d)

336˚ºo

mag

neti

c

larg

eco

tto

nw

oo

d

larg

eco

tto

nw

oo

ds

C

• 3 m

larg

e r

ock

• 0-36

0-30 •

17.5

m18.5

m

bas

e o

f m

ounta

in •

• ed

ge

of

clea

ring

• ed

ge

of

rive

r / ch

annel

2SE

PT 2

92004

SKET

CH

- A

S BU

ILT N

EW D

OW

NST

REA

M IN

TA

KE

PIPE

/ V

ALV

E /

PON

DA

LL D

IMEN

SIO

NS

REP

RES

ENTA

TIV

E.

B

C

A

D

Cheakamus River 2003 Flood Restoration / 04.Ch.3 / Final Report / Bighouse Site Final Sketch

North VancouverOutdoor School

School District #44

Government of CanadaFisheries and Oceans

Canada

Cheakamus October 2003

Flood Damage Restoration

BCRP project: 04.Ch.03

chalvorson. 9.4.2004

scale: one unit = 10 m

Moodie's Channel: Site B

Bighouse Repair

Reach Specifications:

90 metres in length

400 m2 channel total

200 m2 "refuge" pockets

9 LWDs

Average reach gradient - riffle/pool drops

N

S

E W

Skw'une-was

Bighouse

Skw

'une-w

as

Activ

ity S

hed

Cook

Shelter

SmokeHouse

BCR Railcar Bridge

20.0

0.0

10.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

flow

Moodie

's/L

ow

er P

aradis

espaw

nin

g c

hannels

NVOS Canoe Pond

control weir

control weir

control

weir

control

weir

Cheakamus River 2003 Flood Restoration / 04.Ch.3 / Final Report / Eagle Point Site Final Sketch

North VancouverOutdoor School

School District #44

Government of CanadaFisheries and Oceans

Canada

Cheakamus October 2003

Flood Damage Restoration

BCRP project: 04.Ch.03

chalvorson. 3.14.2005

scale: one unit = 10 m

Moodie's Channel: Site J

Eagle Point Reconstruction

Reach Specifications:

200 metres in length

1200 m2 channel total

270 m2 "refuge" pockets

60+ LWDs

Average reach gradient 0.1%

N

S

E W

location of roadway and dike prior to flood •

Cheak

amus

Riv

er

(flo

w)

• location of channel andpond prior to flood

Water Survey of Canada“Brackendale” gauge

• line of floodplain atrailway right of way

line of washed out toe •

• wood debris used to createlog jam and other refugehabitat features

• existing intake structure

• new trail infrastructure to replace“Fuzzy’s Forest Foray” destroyedduring dike reconstruction

• funded by public donations

• new salmonid channel infrastructure• pre-existing channel was “under”

the new dike realignment

new dike crest alignment •

line of new rock toe •

• Cheakamus River left bank

Canoe Pondto B

igho

use

to NVOS cabins

• reconstructed pond sidetrail to Bighouse

• wood debris used to createlog jam and other refugehabitat features

40

50

30

20

10

0

top

of b

ank

80

70

60

0+50

140

130

120

110

100

90

150

160

170

180

190

200

210

220

230

240

250

0+150

0+130

cottonwoodoff roadway

0+0

0-5

0+160

0+170

telephonepole

0+180

0+190

0+200

“RST”anchorpoint

0+210

0+220

0+230

0+240

0+250

0+260

0+270

0+280

0+290

0+295

0+300

0+310

0+320

0+340

0+330

end of works

0+50

0+60

0+70

0+80

0+90

0+10

0+20

0+30

0+40

0+100

0+110

0+120

0+140

cottonwoodoff roadway