Chapter 17 Project Management 1Saba Bahouth – UCO.
-
Upload
rachael-eager -
Category
Documents
-
view
221 -
download
3
Transcript of Chapter 17 Project Management 1Saba Bahouth – UCO.
![Page 1: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/1.jpg)
1
Chapter 17
Project Management
Saba Bahouth – UCO
![Page 2: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/2.jpg)
Saba Bahouth – UCO 2
Single unitMany related activitiesDifficult production planning controlGeneral purpose equipment; high labor skills
Project Characteristics
Project organization works best when:Work can be defined with a specific goal and deadlineThe job is unique or somewhat unfamiliar to the existing organizationThe work contains complex interrelated tasks requiring specialized skillsThe project is temporary but critical to the organization
TimeCostPerformance/Quality
![Page 3: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/3.jpg)
Saba Bahouth – UCO 3
Examples of ProjectsA project is a temporary customized initiative consisting of smaller activities that must be coordinated to finish the entire project on time, within budget, while meeting requirements.
Project management: 1. Cost2. Time3. Performance/Quality
Projects fail due to schedule overruns, use of unproven technology, poor estimates, weak definitions of objectives, and supplier problems.
![Page 4: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/4.jpg)
Saba Bahouth – UCO 4
Project Stages
1. Define: clearly understand the goal of the project, responsibilities, deliverables, and what must be accomplished.
2. Plan: determine the steps needed to execute the project, delegate tasks, and identify start and completion dates.
3. Organize: coordinating the resources to execute the plan cost-effectively.
4. Control: collecting and assessing status reports and managing changes to baselines.
5. Close: compiling statistics, reassigning people, and preparing “lessons learned”.
![Page 5: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/5.jpg)
Saba Bahouth – UCO 5
Management of Large Projects
PlanningGoal setting, project definition, team organization
Scheduling Relating activities to each otherRelating people, money, and supplies to specific activities
ControllingMonitoring resources, schedule, costs, quality, and budgetsRevising plans and shifting resources to meet time and cost
demands
![Page 6: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/6.jpg)
Saba Bahouth – UCO 6
Project Planning, Scheduling, and ControlWork Breakdown Structure1. Project2. Major tasks in the project3. Subtasks in the major
tasks4. Activities to be
completed
![Page 7: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/7.jpg)
Saba Bahouth – UCO 7
Project Manager Requirements
Four key skills:1. Bias towards task completion,2. Technical and administrative credibility,3. Interpersonal and political sensitivity,4. Leadership ability.
• manage people as a team• reinforce excitement of the team• keep everyone informed - Communication • build agreements and consensus• empower the project team• encourage risk-taking and creativity• Have a Project Champion
![Page 8: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/8.jpg)
Saba Bahouth – UCO 8
© 1984-1994 T/Maker Co.
Project Management Techniques
1. Gantt Charts
2. Network techniques: developed in 1950’s Consider precedence relationships and interdependencies
CPM by DuPont for chemical plants (1957)PERT by Booz, Allen & Hamilton with the U.S. Navy, for Polaris missile (1958)
CPM and PERT are essentially the same (we will see the difference later)
![Page 9: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/9.jpg)
Saba Bahouth – UCO 9
Project Management SoftwareMicrosoft “Project”
![Page 10: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/10.jpg)
Saba Bahouth – UCO 10
Activity Network, AON & AOA Format
Important: AOA Needs
dummy activities to
show all relationship
s
![Page 11: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/11.jpg)
Saba Bahouth – UCO 11
When Activity c is Not Required for e
Important: AOA Needs dummy activities to show all
relationships
Wrong! Right!
![Page 12: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/12.jpg)
Saba Bahouth – UCO 12
When activity f does not need activity a to be completed first
![Page 13: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/13.jpg)
Saba Bahouth – UCO 13
A Comparison of AON and AOA
![Page 14: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/14.jpg)
Saba Bahouth – UCO 14
Relocating an Office – Gantt Chart
![Page 15: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/15.jpg)
Saba Bahouth – UCO 15
Relocating an Office: Network
9w
1w
3w
6w
11w8w
4w
Locate Facilities - 8w
Interview Staff – 4w
Hire and Train – 9w
Order Furniture – 6w
Remodel/phones - 11w
Furniture set up – 3w
Move in – 1w
![Page 16: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/16.jpg)
Saba Bahouth – UCO 16
AON -> AOA -> !
G
B
F
A
D H
C
E
Page 1 of 3
St
![Page 17: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/17.jpg)
Saba Bahouth – UCO 17
TRAIN Design AOA - Example
Activity ImmediateActivity Predecessor
Duration• a - Design TRAIN - 20• b - Build Prototype a 10• c - Perform Tests on Prototype b 8• d - Estimate Material Costs a 11• e - Refine TRAIN Design c,d 7• f - Demonstrate to Customers e 6• g - Estimate Labor Cost d 12
• h - Prepare Technical Proposal e 13• i - Deliver Proposal to Customer g,h 5
![Page 18: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/18.jpg)
1. PERTProgram Evaluation and Review TechniqueBooz-Allen Hamilton/Lockheed/NavyProbabilisticR & DLess popular with timeFocus on time analysis (later also cost)
PMI (2005)ADM / PERT: Arrow Diagram Method
2. CPMCritical Path MethodDuPont/RandDeterministicConstructionMore popular with timeFocus on time and cost analysis
PDM / CPM: Precedence Diagram Method
Methods of Network Graphical Representation1. AOA (ADM)2. AON (PDM)
Methods of Network Analysis
![Page 19: Chapter 17 Project Management 1Saba Bahouth – UCO.](https://reader036.fdocuments.in/reader036/viewer/2022062421/56649cbf5503460f9498480b/html5/thumbnails/19.jpg)
Saba Bahouth – UCO 19
ExampleActivity Duration Preceded by
a 12 ---
b 13 ---c 10 ---d 16 ce 4 af 14 b , dg 7 b , dh 8 ci 22 e , fj 16 e , fk 25 gl 8 b , d , hm 12 in 14 j , ko 10 lp 8 m , n , o