CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV...

41
CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles

Transcript of CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV...

Page 1: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

CHAPTER 10Capital Budgeting

Ch. 9 in the 4th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles

Page 2: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.
Page 3: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Characteristics of Business Projects

Project Types and Risk Capital projects have increasing risk according to

whether they are replacements, expansions or new ventures

Stand-Alone and Mutually Exclusive Projects A stand-alone project has no competing alternatives

The project is judged on its own viability Mutually exclusive projects are involved when selecting

one project excludes selecting the other

Page 4: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Characteristics of Business Projects

Project Cash Flows The first and usually most difficult step in capital

budgeting is reducing projects to a series of cash flows Business projects involve early cash outflows and later

inflows The initial outlay is required to get started

The Cost of Capital A firm’s cost of capital is the average rate it pays its

investors for the use of their money In general a firm can raise money from two sources: debt and

equity If a potential project is expected to generate a return greater

than the cost of the money to finance it, it is a good investment

Page 5: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Capital Budgeting Techniques

There are four basic techniques for determining a project’s financial viability: Payback (determines how many years it takes

to recover a project’s initial cost) Net Present Value (determines by how much

the present value of the project’s inflows exceeds the present value of its outflows)

Internal Rate of Return (determines the rate of return the project earns [internally])

Equivalent annual annuity (EAA)

Page 6: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Capital Budgeting Techniques—Payback

The payback period is the time it takes to recover early cash outflows Shorter paybacks are better

Payback Decision Rules Stand-alone projects

If the payback period < (>) policy maximum accept (reject)

Mutually Exclusive Projects If PaybackA < PaybackB choose Project A

Weaknesses of the Payback Method Ignores the time value of money Ignores the cash flows after the payback period

Page 7: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Relevant Cash Flows

Cash Flow (vs. Accounting Income)

Incremental Cash Flows Partial budget concept

Page 8: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

year Project L $

Project S $

0 1

(100) 10

(100) 70

2 3

60 80

50 20

Example Projects

Page 9: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Payback for Project L(Long: Most CFs in out years)

10 8060

0 1 2 3

-100

=

CFt

Cumul -100 -90 -30 50

PaybackL 2 + 30/80 = 2.375 years

0

2.4

Page 10: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Project S (Short: CFs come quickly)

70 2050

0 1 2 3

-100CFt

Cumul -100 -30 20 40

PaybackL 1 + 30/50 = 1.6 years

0

1.6

=

Page 11: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

10 8060

0 1 2 3

CFt

Cumul(PV) -100 -90.91 -41.32 18.79

Disc.payback

2 + 41.32/60.11 = 2.7 yrs

Discounted Payback: Uses discountedrather than raw CFs.

PVCFt -100

-100

10%

9.09 49.59 60.11

=

Recover invest + cap costs in 2.7 yrs.

Project L

Page 12: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Capital Budgeting Techniques—Payback: another example Consider the following cash flows

Year

0 1 2 3 4

Cash flow (Ci) ($200,000) $60,000 $60,000 $60,000 $60,000

Cumulative cash flows

($200,000) ($140,000) ($80,000) ($20,000) $40,000

Payback period occurs at 3.33 years.

Year

0 1 2 3 4

Cash flow (Ci) ($200,000) $60,000 $60,000 $60,000 $60,000

Payback period is easily visualized by the cumulative cash flows

Page 13: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Capital Budgeting Techniques—Payback— yet another example

Q: Use the payback period technique to choose between mutually exclusive projects A and B.

Exa

mpl

e

800200C5

800200C4

350400C3

400400C2

400400C1

($1,200)($1,200)C0

Project BProject A

A: Project A’s payback is 3 years as its initial outlay is fully recovered in that time. Project B doesn’t fully recover until sometime in the 4th year. Thus, according to the payback method, Project A is better than B.

Page 14: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Capital Budgeting Techniques—Payback Why Use the Payback Method?

It’s quick and easy to apply Serves as a rough screening device Indicates how long to resolve uncertainty

The Present Value Payback Method Involves finding the present value of the

project’s cash flows then calculating the project’s payback

Page 15: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Capital Budgeting Techniques—Net Present Value (NPV)

NPV is the sum of the present values of a project’s cash flows at the cost of capital

outflows

inflows

1 2 n0 1 2 n

C C C C NPV

1+k 1+k 1+kPV

PV

If PVinflows > PVoutflows, NPV > 0

Page 16: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Capital Budgeting Techniques—Net Present Value (NPV)

NPV and Shareholder Wealth A project’s NPV is the net effect that

undertaking a project is expected to have on the firm’s value

A project with an NPV > (<) 0 should increase (decrease) firm value

Since the firm desires to maximize shareholder wealth, it should select the capital spending program with the highest NPV

NPV is the PV of economic profit

Page 17: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Capital Budgeting Techniques—Net Present Value (NPV)

Decision Rules Stand-alone Projects

NPV > 0 accept NPV < 0 reject

Mutually Exclusive Projects NPVA > NPVB choose Project A over B

Page 18: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Capital Budgeting Techniques—Net Present Value (NPV) Example

Q: Project Alpha has the following cash flows. If the firm considering Alpha has a cost of capital of 12%, should the project be undertaken?

Exa

mpl

e $3,000C3

$2,000C2

$1,000C1

($5,000)C0

A: The NPV is found by summing the present value of the cash flows when discounted at the firm’s cost of capital.

Alpha 1 2 3

1,000 2,000 3,000 -5,000 NPV

1.12 1.12 1.12

-5,000 892.90 1,594.40 2,135.40

-5,000 4,622.70

($377.30)

Since Alpha’s NPV<0, it

should not be undertaken.

Page 19: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Use CFj on the cash flow

Show on the board

Page 20: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Techniques—Internal Rate of Return (IRR)

A project’s IRR is the return it generates on the investment of its cash outflows For example, if a project has the following cash flows

0 1 2 3

-5,000 1,000 2,000 3,000

Literally the IRR is the interest rate at which the present value of the three inflows just equals the $5,000 outflow

If you lend yourself the money to make the investment, the IRR is the highest interest rate you could charge and the investment pay off the loan

The “price” of receiving the inflows

Page 21: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

outflows

inflows

1 2 n0 1 2 n

C C C: C IRR

1 IRR 1 IRR 1 IRRPV

PV

Techniques—Internal Rate of Return (IRR)

Defining IRR Through the NPV Equation The IRR is the interest rate that makes a project’s NPV

zero

Solve for IRR one equation, one unknown, but usually impossible to

solve with algebra

Projectcost

Page 22: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Techniques—Internal Rate of Return (IRR) Decision Rules

Stand-alone Projects If IRR > cost of capital (or k) accept If IRR < cost of capital (or k) reject

Mutually Exclusive Projects IRRA > IRRB choose Project A over Project B

(but don’t use IRR to rank mutually exclusive projects)

Page 23: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Techniques—Internal Rate of Return (IRR) Calculating IRRs

Finding IRRs usually requires an iterative, trial-and-error technique

Guess at the project’s IRR Calculate the project’s NPV using this interest rate

If NPV is zero, the guessed interest rate is the project’s IRR

If NPV > (<) 0, try a new, higher (lower) interest rate

Page 24: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Techniques—Internal Rate of Return (IRR)—Example

Q: Find the IRR for the following series of cash flows:

If the firm’s cost of capital is 8%, is the project a good idea? What if the cost of capital is 10%?

Exa

mpl

e

$1,000

C1

($5,000)

C0

$2,000

C2

$3,000

C3

A: We’ll start by guessing an IRR of 12%. We’ll calculate the project’s NPV at this interest rate.

1 2 3

1,000 2,000 3,000 -5,000 NPV

1.12 1.12 1.12

-5,000 892.90 1,594.40 2,135.40

-5,000 4,622.70

($377.30)

Since NPV<0, the project’s

IRR must be < 12%.

Page 25: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Techniques—Internal Rate of Return (IRR)—Example

We’ll try a different, lower interest rate, say 10%. At 10%, the project’s NPV is ($184). Since the NPV is still less than zero, we need to try a still lower interest rate, say 9%. The following table lists the project’s NPV at different interest rates.

Exa

mpl

e

Since NPV becomes positive somewhere

between 8% and 9%, the project’s IRR must be

between 8% and 9%. If the firm’s cost of capital is 8%, the project is marginal. If the firm’s cost of capital is 10%, the project is not a

good idea.$1307

$228

($83)9

($184)10

($377)12%

Calculated NPV

Interest Rate Guess

The exact IRR can be calculated using a financial calculator. The financial calculator uses the iterative process just demonstrated; however it is capable of guessing and recalculating much more quickly.

Page 26: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Okay, if you haven’t already pointed it out by now, there is really no reason to do the trial and error yourself!

Use the CFj calculator function (IRR key)

Cash flows -5000 1000 2000 3000

Page 27: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Techniques—Internal Rate of Return (IRR)

Technical Problems with IRR Multiple Solutions

Unusual projects can have more than one IRR Rarely presents practical difficulties

The number of positive IRRs to a project depends on the number of sign reversals to the project’s cash flows

Normal pattern involves only one sign change

The Reinvestment Assumption IRR method implicitly assumes cash inflows will be reinvested

at the project’s IRR For projects with extremely high IRRs, this is unlikely

Page 28: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

When NPV and IRR disagree

Only when comparisons must be made Not stand alone analysis Use the NPV rankings, not the IRR

rankings

Page 29: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

NPV Profile

A project’s NPV profile is a graph of its NPV vs. the cost of capital

It crosses the horizontal axis at the IRR

Page 30: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Construct NPV Profiles

Enter CFs in CFLO and find NPVL andNPVS at several discount rates:

k

0

5

10

15

20

NPVL

50

33

19

7

(4)

NPVS

40

29

20

12

5

Page 31: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

-10

0

10

20

30

40

50

60

0 5 10 15 20 23.6

NPV ($)

Discount Rate (%)

IRRL = 18.1%

IRRS = 23.6%

Crossover Point = 8.7%

k

0

5

10

15

20

NPVL

50

33

19

7

(4)

NPVS

40

29

20

12

5

S

L

Page 32: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Mutually Exclusive Projects

k 8.7 k

NPV

%

IRRs

IRRL

L

S

k< 8.7: NPVL> NPVS , IRRS > IRRL

CONFLICT k> 8.7: NPVS> NPVL , IRRS > IRRL

NO CONFLICT

Crossover rate = 8.7%

Rankings of S and L were consistent because K was 10%

Page 33: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

To find the crossover rate:1. Find cash flow differences between

the projects. Project L minus Project S

CashL

(100)

10

60

80

CashS

(100)

70

50

20

Difference0

-601060

Page 34: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

2. Enter these differences in CFLOregister, then press IRR. Crossoverrate = 8.68, rounded to 8.7%.

3. Can subtract S from L or vice versa,but better to have first CF negative.

4. If profiles don’t cross, one projectdominates the other.

Page 35: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Two reasons NPV profiles cross:

1) Size (scale) differences. Smallerproject frees up funds at t = 0 forinvestment. The higher the discountrate, the more valuable these funds,so high k favors small projects.

2) Timing differences. Project with faster payback provides more CF inearly years for reinvestment. If k ishigh, early CF especially good, NPVS

> NPVL.

Page 36: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Reinvestment Rate Assumptions

NPV assumes reinvest at k. IRR assumes reinvest at a rate

greater than the crossover rate. Reinvest at opp. cost, k, is more

realistic, so NPV method is best. NPV should be used to choose between mutually exclusive projects.

Page 37: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Comparing Projects with Unequal Lives If a significant difference exists between

mutually exclusive projects’ lives, a direct comparison of the projects can be in error

The problem arises using the NPV method Longer lived projects often have higher NPVs Or shorter projects lower net present cost

Must consider if the investments are really a sequence

If not a sequence then NPV is correct.

Page 38: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Comparing Projects with Unequal Lives Two solutions exist

Replacement Chain Method Extends projects until a common time horizon is reached

For example, if mutually exclusive Projects A (with a life of 3 years) and B (with a life of 5 years) are being compared, both projects will be replicated so that they each last 15 years

Equivalent Annual Annuity (EAA) Method Replaces each project with an equivalent annuity (PMT)

that equates to the project’s original NPV That is, annualize the NPV (or net present cost)

Both methods give the same conclusion so I only use EAA

Page 39: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Comparing Projects with Unequal Lives—Example

Q: Which of the two following mutually exclusive projects should a firm purchase?

Exa

mpl

e

Short-Lived Project (NPV = $432.82 at an 8% discount rate; IRR = 23.4%)

$750$750$750$750$750$750($2,600)

-

C5

-

C4

$750

C3

Long-Lived Project (NPV = $867.16 at an 8% discount rate; IRR = 18.3%)

$750

C1

($1,500)

C0

$750

C2

-

C6

A: The IRR method argues for undertaking the Short-Lived Project while the NPV method argues for the Long-Lived Project. We’ll correct for the unequal life problem by using the EAA Method. Both the EAA and Replacement Chain methods will lead to the same decision.

Page 40: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Comparing Projects with Unequal Lives—Example

The EAA Method equates each project’s original NPV to an equivalent annual annuity. For the Short-Lived Project the EAA is $167.95 (the equivalent of receiving $432.82 spread out over 3 years at 8%); while the Long-Lived Project has an EAA of $187.58 (the equivalent of receiving $867.16 spread out over 6 years at 8%). Since the Long-Lived Project has the higher EAA, it should be chosen. This is the same decision reached by the Replacement Chain Method.

Exa

mpl

e

Page 41: CHAPTER 10 Capital Budgeting Ch. 9 in the 4 th edition PV of Cash Flows Payback NPV IRR EAA NPV profiles.

Review Steps:

1. Create ideas for capital investment

2. Estimate CFs (inflows & outflows).

3. Assess riskiness of CFs.

4. Determine k = WACC (adj. for risk).

5. Find NPV and/or IRR.

6. Accept if NPV > 0 and/or IRR > WACC.

7. If mutually exclusive, take the highest NPV

8. If mutu. excl. & lives differ take highest EAA